1 Abstract TIMBER HARVEST AREA PLANNING IN MALAYSIA USING A NETWORK ALGORITHM Norizah Kamarudin 1, Woodam Chung 2 In Peninsular Malaysia, the most common logging systems are cable skidder and log fisher. A log fisher is an excavator based hydraulic timber harvest system that can winch logs up to 300 meters. While cable skidders can be used only on gentle slopes, log fishers can be applied regardless of slope conditions. Since both harvesting methods are applicable for gentle ground, a decision on harvesting system has to be made depending on existing and proposed forest road network, landing locations, and harvesting costs. Usually, harvesting cost of log fisher is higher than cable skidder, but does not require skid trail construction, which is mandated for cable skidder operations in Malaysia. We developed conceptual network models to represent this complex forest operations planning problem where decisions need to be made simultaneously on harvest system, landing location, and forest road location. We applied the models to a 102 ha timber harvest area in Malaysia and solved the problem using a heuristic network algorithm to obtain the least cost harvesting option while considering both fixed (i.e., road and trail construction costs) and variable costs (i.e., harvesting costs). In this paper, the problem formulation approach and case study solutions are presented. Keywords: Timber harvesting, road planning, Peninsular Malaysia, extraction system, cost efficiency INTRODUCTION Determining the optimal logging systems for a timber harvest area is a difficult task because many considerations need to be taken into account including timber volume and distribution, terrain and environmental conditions, costs and productivity, and the existing road infrastructures. The most common logging systems in Peninsular Malaysia include 1) groundbased system using a cable skidder and 2) cable winching system called log fisher. Log fisher is an excavator based hydraulic cable winching system that can winch logs up to 300 meters. While cable skidders are normally used only on gentle ground, log fishers can be applied regardless of slope conditions. Saharudin et al. (2004) and Norizah et al. (2012) found that log fishers have a higher productivity than cable skidders where ground slope exceeds 20 degrees. However, log fishers have higher machine and operating costs than cable skidders. Another unique difference between the two logging systems in Malaysia is that skid trail construction is mandated by the government for skidding operations, whereas log fishers do not rely on skid trails. In addition, according to the forest regulations in Malaysia, the total length of skid trails from any log landing should not exceed 300m. Because of these differences in costs, productivity, and regulations, Norizah et al. (2012) suggested that the two logging systems could be complementary to each other, and applying a combination of the systems might reduce the overall costs of timber harvesting in a given harvest unit. In this study, we have attempted to 1 Dr, Universiti Putra Malaysia, UPM, Serdang, Selangor, Malaysia. norizah_k@upm.edu.my. 2 Associate Professor, University of Montana, Missoula, MT 59812, USA, woodam.chung@umontana.edu. 37th Council on Forest Engineering Annual Meeting Moline, Illinois 1
2 model and solve this harvest area planning problem to minimize total costs of timber extraction while considering the two aforementioned logging systems and designing required skid trails and forest roads. Although there were several past studies that attempted to solve different harvest area and road network layout problems (Chung et al. 2003, Anderson and Nelson 2004, Epstein et al. 2006, Najafi et al. 2008, Chung et al. 2008), those studies did not simultaneously consider logging systems, skid trails, and road constructions. Also, the two logging systems, as well as skid trail construction requirement and its limitation on maximum length, make the harvest area planning problem in Malaysia unique, which has not been modeled and solved mathematically. Our attempt to model and solve this unique problem is still in progress. In this paper, we present different modeling approaches to tackle such unique and challenging problems based on graph theory and compare preliminary solutions of the approaches. METHODS Network representation of timber harvesting operations Once a harvest area is rasterized, timber flows from individual tree locations to landing and then to the final destination through road network can be represented by series of links developed between grid cells (i.e., nodes). In our approach, some grid cells represent timber volume and location (i.e., timber nodes), others may represent locations of skid trails, landings, or forest roads. Links between grid cells may represent skidding activities, log fisher operations, or truck transportation. Each link is attributed with variable or fixed costs or both depending on the activity that the link represents. In the case of skidding activities, links are attributed with both variable and fixed costs representing skidding and skid trail construction costs, respectively. For log fisher operations, only variable cost will be assigned to the link. For timber transportation, both variable and fixed costs are assigned to the links representing new roads, while only variable costs (i.e., haul cost) exist on the links representing the existing roads. The same physical links between grid cells may often represent multiple activities. For example, a link between two adjacent grid cells can represent skidding activity, log fisher operation, or timber transportation. Since no duplicate links are allowed in network formulation, we used different labels of from- and to-nodes along with different cost attributes to differentiate activities that occur in the same physical locations. Costs associated with each activity are estimated based on a productivity study conducted by Norizah (2013). However, there has not been any productivity study on timber transportation so far in Peninsular Malaysia. Thus, hauling cost was estimated for this study according to expenses allotted for log transportation by forest concessionaire. Road construction cost was estimated using the past study by Mohd Hasmadi et al. (2008). All the cost data used in this study are summarized in Table 1. 37th Council on Forest Engineering Annual Meeting Moline, Illinois 2
3 Table 1. Cost data used in this study for timber harvesting activities. (i) Stump-to-landing Skidding cost with cable skidder MYR 0.06/m 3 /m Skid trail preparation MYR 0.5/m Winching cost with log fisher MYR 0.13/m 3 /m (ii) Timber transportation Hauling cost MYR 0.096/m 3 /km Road construction cost MYR 18/m * MYR 1.0 is approximately equivalent to USD 0.31 Log fisher operations Links representing potential log fisher operations were built from each timber node to multiple neighboring nodes that are within 300m proximity of the timber node (Figure 1). Links are attributed with variable cost only because no skid trail is required. If one of the links is selected, to-node of the link becomes a log landing, and then is connected to the forest road system for truck transportation. Figure 1. A link pattern representing log fisher operation from a timber entry node to neighboring nodes within a 300m distance. Cable skidder operations Timber node Neighbor node Possible link with costs assigned Due to the unique regulations on skidding operations in Malaysia (i.e., skid-trail construction requirement and maximum skidding distance limit of 300m), formulating the harvest area planning problems becomes challenging. We have not yet identified a precise approach to formulate and solve the unique problem mathematically, but our attempt is still in progress. In this paper, we present three different proxy models we developed to represent the unique problem while relaxing one or more regulations. In the first model (i.e., Model A), we assumed that skidding operation can be done in a similar way to log fisher operations (Figure 1) where the log can directly skidded to a log landing within a 300 m from the stump location. However, unlike log fisher operations, skid trails need to be built for skidding operations. Therefore, each link representing skidding operation includes both fixed and variable costs. On the contrary, the second model (i.e. Model B) does not assign fixed cost to each link, but instead skid trail construction cost of the maximum distance (i.e., 300m) is added at the log landing, assuming that skid trail construction cost does not vary with skidding distance. In Model B, the links (i.e., skid trails) that can be used by each timber node are labeled uniquely using a combination of grid cell location and relative direction from timber node (Figures 2a through 2e). This labeling method allows tracking the total length of skid trails from 37th Council on Forest Engineering Annual Meeting Moline, Illinois 3
4 individual timber nodes and thus limiting the maximum skidding distance. The same skid trail may be labeled differently when it gets used by multiple timber nodes. In this case, an imaginary link with no cost is built between the two different labels representing the same grid cell so that the same skid trail can be shared by multiple timber nodes. When a skid trail ends at a landing location, the pre-determined skid trail construction cost is added to the total costs (Figure 2f). Figure 2. Node labels representing skidding activities from a timber entry node to multiple neighboring nodes based on grid cell locations and relative directions from timber nodes (Figures 2a through 2e). Model C assumes there is no maximum skidding distance limit. Therefore, each node is linked to its eight adjacent nodes through skidding activities. Both fixed and variable costs are assigned to each link for skid trail construction and skidding operations (Figure 3). Figure 3. Links representing skidding activities from a timber entry node to its eight adjacent nodes. Each link was attributed with both variable and fixed costs. Road construction and timber transportation Timber node Neighbor node Possible link with costs assigned Because every to-node of the links representing skidding or log fisher operations can potentially serve as a log landing, the to-nodes need to be connected to the existing roads through another set of network representation of road building and truck hauling operations. In order to do this, an imaginary link is developed to connect each grid cell used as to-nodes of timber harvesting operation to itself that represents forest road (e.g., S13 -> R13 in Figure 4). The node is then further connected to its eight neighbors by links that represent forest roads. These links are attributed with both fixed costs (road construction costs) and variable costs (truck hauling costs). Any grid cells representing the existing forest roads serve as the final destination of timber. 37th Council on Forest Engineering Annual Meeting Moline, Illinois 4
5 S1 L1 S3 L3 S5 L5 S11 S15 S21 S13 Imaginary link L13 L11 L15 L21 S23 L23 S25 R13 L25 (a) (b) Figure 4. Grid cells that represent three different activities in the same physical location with three different labels (a), and an example of link created for a timber entry node 13 representing skidding activities (labeled with S), log fisher operation (labeled with L), and road activities (labeled with R) (b). Solution method NETWORK 2000 equipped with a heuristic network algorithm (Chung and Session, 2003) was applied to find the least cost routes from each timber node to the final destination. With the ability to solve fixed and variable cost network problems, the tool provides near-optimal solutions that determine the least-cost extraction methods (i.e., skidder vs. log fisher), skid-trail locations, landing locations, new forest road locations, and transportation routes for timber harvesting operations in a given harvest unit. APPLICATION R1 R3 R5 R11 R15 R21 R23 R25 We applied the methods developed in this study to a 102 ha harvest unit located in Ulu Jelai Forest Reserve, Pahang of Peninsular Malaysia (Figure 5). The study area was rasterized with a 30m resolution, and a total of 550 grid cells were attributed with timber volumes of 6,632m 3 in total, which serve as entry nodes in the network problem. There are 50 grid cells representing the existing roads. Any of these road grid cells serve as the final destination in our network problem. Figure 5. Study area located in Ulu Jelai Forest Reserve, Pahang of Peninsular Malaysia, showing distribution of timber nodes on gentle slopes (<20 degrees) and slopes of 20 degrees and more. 37th Council on Forest Engineering Annual Meeting Moline, Illinois 5
6 PRELIMINARY RESULTS The least cost solutions found by NETWORK 2000 for the three problem formulation models indicate that cable skidder is a preferred harvesting system in most gentle areas regardless of the models (Figures 6a, 6b and 6c, for Models A, B, and C, respectively). Skid trail locations from Models A and B are not shown in Figure 6 because no specific skid trail routes can be identified with Model A and skid trails need to be manually tracked down for displaying the Model B results. For comparison, we also presented a timber harvest area plan manually developed by the Malaysian Forestry Department (Figure 6d). Table 2 compares the three solutions and the manual plan in terms of total forest road length, number of landings, and selected logging systems. The Model B result shows more log fishing operations selected compared to the other two Models. This is because Model B overestimates skid trail construction costs by considering construction of the maximum skid trail distance (i.e., 300m) regardless of skidding distance, which made log fisher more competitive in some areas. In addition, it appears that fewer number of log landings were selected (Table 2) because skid trail construction costs are added at the landing in Model B, and thus the more landings would cause the higher overall costs. This fewer number of log landings further reduced the total length of forest roads required. Forest roads proposed by the Forestry Department are located throughout the entire harvest unit. The Model A shows the similar pattern of road locations, whereas the results from Models B and C show different road patterns. Figure 6. Forest road locations resulted from Models A, B and C (a, b, and c), and road locations proposed by the Malaysian Forestry Department (d). 37th Council on Forest Engineering Annual Meeting Moline, Illinois 6
7 Table 2. Summary of harvest area plans resulted from Models A, B and C, and the Malaysian Forestry Department. Model A B C Forestry Department Road length (m) Skid trail length (m) (max: m) (max: 312m) Total No of Cable skidder landing Log fisher No of timbers with cable skidder No of timbers with log fisher CONCLUDING REMARKS Timber harvest area planning problems in Malaysia are unique because of the government regulations on skid trail construction and maximum skidding distance limit. Our attempt to exactly formulate and analyze the unique problem using a network algorithm is still in progress. Here we presented three problem formulation models that simplified the problem by relaxing one or more regulations. Each model has its own limitations and advantages that will be further investigated in our on-going research. Developing a precise problem formulation and solution method would benefit forest practitioners in Malaysia in finding the least-cost options for their timber harvesting operations. References Anderson, A.E. and Nelson, J Projecting vector-based road networks with shortest path algorithm. Canadian Journal Forestry Research, 34 (2004): Chung, W., Stuckelberger, J., Aruga, K. and Cundy, T.W Forest road network design using a trdeoff analysis between skidding and road construction costs. Canadian Journal Forestry Research, 38(2008): Chung, W. and Sessions, J NETWORK 2000: a program for optimizing large fixed and variable cost transportation problems. In Proceedings of the 8th Symposium on Systems Analysis in Forest Resources, Snowmass Village, September 2000, Colorado. Edited by G.J. Arthaud and T.M. Barrett. Kluwer Academic Publishers, Dordrecht, the Netherlands. Pp Epstein R., Weintraub A., Sessions J.B., Sessions J., Sapunar P., Neto E., A combinatorial heuristic approach for solving real size machinery location and road design problems in forestry planning. Operations Research, 54: Mohd. Hasmadi, I, Kamaruzaman, J and Muhamad Azizon, J Forest road assessment in Ulu Muda Forest Reserve of Peninsular Malaysia. Journal of Modern Applied Science 2(3): Najafi, A., Sobhani, H., Saeed, A., Makhdom, M. and Mohajer, M.M Planning and assessment of alternative forest road and skidding networks. Croatian Journal of Forest Engineering 29 (1): Norizah, K Advanced forest harvest operation and road location planning to reduce negative environmental impacts in Peninsular Malaysia. Ph.D Thesis, Universiti Putra Malaysia, Malaysia. Norizah, K., Mohd Hasmadi, I., Kamaruzaman, J. and Alias, M.S Operational Efficiency of Rimbaka Timber Harvester in Hilly Tropical Forest. Journal of Tropical Forest Science, 24(3): Saharudin, A., Azmi, H. and Mohd-Zamri, R Kajian mengenai kos dan produktiviti sistem pengusahasilan hutan bukit di Semenanjung Malaysia, Jabatan Perhutanan Semenanjung Malaysia: Kuala Lumpur. 37th Council on Forest Engineering Annual Meeting Moline, Illinois 7
Assessing Timber Extraction by Using the RIMBAKA R2020- A Timber Harvester on a Steep Terrain in Ulu Jelai Forest Reserve, Peninsular Malaysia
Pertanika J. Trop. Agric. Sci. 36 (S): 101-108 (2013) TROPICAL AGRICULTURAL SCIENCE Journal homepage: http://www.pertanika.upm.edu.my/ Assessing Timber Extraction by Using the RIMBAKA R2020- A Timber Harvester
More informationSensitivity Analysis of an Optimal Access Road Location in HillyForest Area: A GIS Approach
American Journal of Applied Sciences 5 (12): 1686-1692, 2008 ISSN 1546-9239 2008 Science Publications Sensitivity Analysis of an Optimal Access Road Location in HillyForest Area: A GIS Approach 1 Mohd
More informationDesigning a Forest Road Network using Heuristic Optimization Techniques
Designing a Forest Road Network using Heuristic Optimization Techniques Woodam Chung and John Sessions Graduate Research Assistant and Professor, respectively, Department of Forest Engineering, Oregon
More informationA COMPUTERIZED METHOD FOR DETERMINING CABLE LOGGING FEASIBILITY USING A DEM.
A COMPUTERIZED METHOD FOR DETERMINING CABLE LOGGING FEASIBILITY USING A DEM Woodam Chung 1 and John Sessions 2 1 Assistant Professor, School of Forestry, University of Montana, Missoula, MT 59812 email:
More informationFactors that Affect Fuel Consumption in Logging Systems
Factors that Affect Fuel Consumption in Logging Systems Jonathan Kenney 1, Thomas Gallagher 2, Mathew Smidt 3, Dana Mitchell 4, Timothy McDonald 5 Abstract: Fuel consumption is an important aspect of the
More informationOPTIMAL PLOT SIZE FOR SAMPLING BIOMASS IN NATURAL AND LOGGED TROPICAL FORESTS
OPTIMAL PLOT SIZE FOR SAMPLING BIOMASS IN NATURAL AND LOGGED TROPICAL FORESTS Hamdan Omar 1 Mohd Hasmadi Ismail 2 and Mohd Hakimi Abu Hassan 3 1 Forest Research Institute Malaysia, 52109 FRIM, Kepong,
More information. HSM904 Timberjack 450C. Archive of SID HSM904. Timber jack- 450C HSM
Timber jack C - 450 HSM-904 ( ) (// : // : ) Timber jack- 450C HSM-904. Timber jack 450C.. HSM904. HSM904 Timber jack 450C / HSM904 Timber jack ( ).. /. HSM904 Timberjack 450C * - - - : E-mail: rnaghdi@guilan.ac.ir
More informationThe Scheduling of Forest Harvesting with Adjacency Constraints
The Scheduling of Forest Harvesting with Adjacency Constraints Alastair McNaughton, M. Ronnqvist and D.M. Ryan University of Auckland and Linkoping University, Sweden a.mcnaughton@auckland.ac.nz, miron@mai.liu.se,d.ryan@auckland.ac.nz
More informationNZQA unit standard version 3 Page 1 of 5
Page 1 of 5 Title Extract stems or logs using a ground based machine Level 4 Credits 20 Purpose This unit standard is intended for the operators of forestry machines used to extract stems or logs from
More informationUSING GIS AND AHP FOR PLANNING PRIMER TRANSPORTATION OF FOREST PRODUCTS
USING GIS AND AHP FOR PLANNING PRIMER TRANSPORTATION OF FOREST PRODUCTS A. E. Akay 1,*, B. Yılmaz 1 1 Forest Engineering Department, Faculty of Forestry, Bursa Technical University - 16310 Yıldırım Bursa,
More informationFocus on Forest Engineering 2011
Focus on Forest Engineering 2011 The application of Full-tree and Treelength Systems on Difficult Terrain: Increasing our knowledge base to better select and operate FT and TL equipment Gary Olsen International
More informationDepth-Bound Heuristics and Iterative-Deepening Search Algorithms in Classical Planning
Depth-Bound Heuristics and Iterative-Deepening Search Algorithms in Classical Planning Bachelor s Thesis Presentation Florian Spiess, 13 June 2017 Departement of Mathematics and Computer Science Artificial
More informationAppropriate technologies for small scale forest harvesting operations in Tasmania
Appropriate technologies for small scale forest harvesting operations in Tasmania Rob Smith Private Forests Tasmania Private Forests Tasmania 1 Background: New person to Australia identifies: Perceived
More informationArgumentation of Optimum Road Density in the Forests of Ukraine
Argumentation of Optimum Road Density in the Forests of Ukraine Oleg Styranivsky Ukrainian National Forestry University str. General Chuprynca,103, 79057 Lviv, Ukraine styranivsky@ukr.net Yuriy Hromyak
More informationComparing Productivity and Costs of Two Beetle-killed Stand Harvesting Methods in Northern Colorado
Comparing Productivity and Costs of Two Beetle-killed Stand Harvesting Methods in Northern Colorado Hee Han1, Woodam Chung2, Nathaniel Anderson 3 Abstract There has been increasing interest in utilizing
More informationFinancial and Economic Analyses of Conventional and Reduced Impact Harvesting Systems
Financial and Economic Analyses of Conventional and Reduced Impact Harvesting Systems Abdul Rahim Abdul Samad Department of Economics, Faculty of Economics & Management Universiti Putra Malaysia, 43400
More informationSkidder with single-drum or double-drum winch in mountainous areas A case study from selective forests of Croatia
Skidder with single-drum or double-drum winch in mountainous areas A case study from selective forests of Croatia 1 Zečić, Ž., *1 Vusić, D., 2 Milković, D., 1 Zorić, M. 1 Department of Forest Engineering,
More informationManaging Low-Volume Road Systems for Intermittent Use
224 TRANSPORTATION RESEARCH RECORD 1291 Managing Low-Volume Road Systems for Intermittent Use JERRY ANDERSON AND JOHN SESSIONS In some areas of the United States, particularly in gentle topography, closely
More informationEvaluation Of Existing Forest Road Network Based On Single Tree Selection Cutting Silvicultural Method
Australian Journal of Basic and Applied Sciences, 6(2): 170-174, 2012 ISSN 1991-8178 Evaluation Of Existing Forest Road Network Based On Single Tree Selection Cutting Silvicultural Method 1 Majid Lotfalian,
More informationOverview. LANTw46. Attach and detach timber onto a skidder
Overview This standard is about attaching and detaching timber onto a skidder. Skidders can include grapple skidder or line skidder and are used to extract trees and timber to an accumulation point and
More informationWATER CROSSINGS VERSUS TRANSPORT COST: A NETWORK ANALYSIS CASE STUDY
WATER CROSSINGS VERSUS TRANSPORT COST: A NETWORK ANALYSIS CASE STUDY ABSTRACT Reino Pulkki Faculty of Forestry Lakehead University Thunder Bay, Ontario This study determines the impact of fewer water crossings
More informationSAMPLING SPECIES DIVERSITY IN A MALAYSIAN RAIN FOREST: THE CASE OF A LOGGED-OVER FOREST
Pak. J. Bot., 40(4): 1729-1733, 2008. SAMPLING SPECIES DIVERSITY IN A MALAYSIAN RAIN FOREST: THE CASE OF A LOGGED-OVER FOREST I. FARIDAH-HANUM *, L. PHILIP AND A.G. AWANG NOOR Faculty of Forestry, Universiti
More informationCOMPLETION REPORT COMPLETION REPORT
COMPLETION REPORT COMPLETION REPORT Capacity Building of Forestry Department Peninsular Malaysia s Staff in Identifying Aquilaria to Species Level and in the Grading of Agarwood MALAYSIA S WORK PROGRAM
More informationHarvesting Systems and Equipment in British Columbia
Harvesting Systems and Equipment in British Columbia Ministry of Forests Forest Practices Branch Harvesting Systems and Equipment Part One EQUIPMENT SELECTION Chart 1 to 13 The handbook does not attempt
More information6 th International Forest Engineering Conference Quenching our thirst for new Knowledge Rotorua, New Zealand, April 16 th - 19 th, 2018
6 th International Forest Engineering Conference Quenching our thirst for new Knowledge Rotorua, New Zealand, April 16 th - 19 th, 2018 SUPPLY CHAIN OPERATIONS IN TEAK PLANTATION Laddawan Rianthakool,
More informationForest Engineering in Iran; Background, Education and Looking Forward Ten Years
Forest Engineering in Iran; Background, Education and Looking Forward Ten Years Majid Lotfalian 1, Mohammad Hejazian 1*, Elham Fazeli Shahroudi 1, Kambiz Barari 2 1 Faculty of Natural Resource, Sari Agricultural
More informationPresentation Program /7/4
Abstract Theme Presenter Key Note 24-Jul 11:00-12:00 O-01 0014-001 A Trajectiory of Final Harvests in The Pacific Northwest, USA Over 50 Years: Loggers, Safety, Technology, and The Future John J. Garland
More informationDetermining and Mapping Soil Nutrient Content Using Geostatistical Technique in a Durian Orchard in Malaysia
Vol. 1, No. 1 Journal of Agricultural Science Determining and Mapping Soil Nutrient Content Using Geostatistical Technique in a Durian Orchard in Malaysia Mohd Hasmadi Ismail (Corresponding author) Surveying
More informationCE 191: Civil and Environmental Engineering Systems Analysis. LEC 06 : Integer Programming
CE 191: Civil and Environmental Engineering Systems Analysis LEC 06 : Integer Programming Professor Scott Moura Civil & Environmental Engineering University of California, Berkeley Fall 2014 Prof. Moura
More informationForest Machinery Crane Compound Scheme Synthesis: Skeleton Part
Journal of Forest Engineering 5 Forest Machinery Crane Compound Scheme Synthesis: Skeleton Part Y.Y. Gerasimov and V.S. Siounev Petrozavodsk State University Petrozavodsk, Russia ABSTRACT The optimal model
More informationMicroclimate of Ayer Hitam Forest, Selangor
Pertanika J. Trop. Agric. Sci. 22(2): 125-129(1999) ISSN: 1511-3701 Universiti Putra Malaysia Press Microclimate of Ayer Hitam Forest, Selangor AHMAD AINUDDIN NURUDDIN and SALLEH AWALUDDIN 1 Faculty of
More informationYield Frontier Analysis of Forest Inventory
Yield Frontier Analysis of Forest Inventory S.A. Mitchell & K. Kim Department of Engineering Science University of Auckland New Zealand s.mitchell@auckland.ac.nz Abstract Standing inventory analysis allows
More informationDECISION-SUPPORT SYSTEM FOR WOOD HARVESTING PLANNING IN RUSSIA
FORMEC 2010 Forest Engineering: Meeting the Needs of the Society and the Environment July 11 14, 2010, Padova Italy DECISION-SUPPORT SYSTEM FOR WOOD HARVESTING PLANNING IN RUSSIA Yuri Gerasimov 1, Anton
More informationALTERNATIVES REDUCED IMPACT LOGGING TECHNIQUES IN PENINSULAR MALAYSIA
ALTERNATIVES REDUCED IMPACT LOGGING TECHNIQUES IN PENINSULAR MALAYSIA WAN MOHD SHUKRI WAN AHMAD Forest Research Institute Malaysia (FRIM) Kepong, 52109 Kuala Lumpur, Malaysia Tel: 603-62797174/Fax:603-62797857/E-mail:shukri@frim.gov.my
More informationMODELING GROUND-BASED TIMBER HARVESTING SYSTEMS USING COMPUTER SIMULATION
MODELING GROUND-BASED TIMBER HARVESTING SYSTEMS USING COMPUTER SIMULATION Jingxin Wang Assistant Professor, Division of Forestry, West Virginia University, Morgantown, WV 20 USA Chris B. LeDoux Project
More informationProductivity and cost of farm tractor skidding
JOURNAL OF FOREST SCIENCE, 58, 2012 (1): 21 26 Productivity and cost of farm tractor skidding N. Gilanipoor, A. Najafi, S.M. Heshmat Alvaezin Tarbiat Modares University, Tehran, Iran ABSTRACT: In this
More informationAnt Colony Optimization for Road Modifications
Ant Colony Optimization for Road Modifications Storm Beck 1 and John Sessions 2 Abstract Non-conventional products provide opportunities for the forest industry to increase economic value from forests;
More informationSupply Chain Operations in Teak Plantation
Laddawan Rianthakool, Nopparat Kaakkurivaara, Piyawat Diloksumpun, and Wanchai Arunpraparut Supply Chain Operations in Teak Plantation Department of Forest Engineering Faculty of Forestry, Kasetsart University
More informationArtificial Intelligence Breadth-First Search and Heuristic
Artificial Intelligence Breadth-First Search and Heuristic Chung-Ang University, Jaesung Lee The original version of this content is came from MIT OCW of MIT Electrical Engineering and Computer Science
More informationDate of Public Summary: 24 April 2012
Date of Public Summary: 24 April 2012 PUBLIC SUMMARY OF SECOND SURVEILLANCE AUDIT OF KEDAH STATE FOREST MANAGEMENT UNIT FOR FOREST MANAGEMENT CERTIFICATION Certificate No : FMC 003 Date of Certification
More informationHarvesting Systems and Equipment in British Columbia
Harvesting Systems and Equipment in British Columbia Ministry of Forests Forest Practices Branch Harvesting Systems and Equipment in British Columbia REFERENCE Operating Techniques Page 127 134 The handbook
More informationUnit C: Forest Management. Lesson 5: Harvesting Forest Trees
Unit C: Forest Management Lesson 5: Harvesting Forest Trees 1 Terms Bucking Clear cutting Establishment cutting Felling Group selection method Limbing Logging Non-point source pollution Removal cuttings
More informationN.A. Chappell and H.C. Thang
17 Practical hydrological protection for tropical forests: the Malaysian experience N.A. Chappell and H.C. Thang in the humid tropics give rise to water protection standards that are also partially applicable
More informationPICK PATH OPTIMIZATION. An enhanced algorithmic approach
PICK PATH OPTIMIZATION An enhanced algorithmic approach Abstract Simulated annealing, enhanced with certain heuristic modifications, provides an optimized algorithm for picking parts from a warehouse or
More informationTimber Harvesting Options for Woodland Owners
LOGGING EC 1582 August 2006 $2.50 Timber Harvesting Options for Woodland Owners R. Parker and S. Bowers Contents Choosing the best harvest system... 2 Table 1. General performance of various timber yarding
More informationSustainable Forest Management and Water Resources Conservation: A Malaysian Case 1
Forests & Water/REF/04 Sustainable Forest Management and Water Resources Conservation: A Malaysian Case 1 Introduction Forestry sector plays a significant role in the economy of the country. Malaysia is
More informationLOG SKIDDING WITH FARM TRACTORS
FORMEC 2010 Forest Engineering: Meeting the Needs of the Society and the Environment July 11 14, 2010, Padova Italy LOG SKIDDING WITH FARM TRACTORS Yilmaz Turk *, Selcuk Gumus ** * Ress. Assist., Faculty
More informationJournal of Tropical Resources and Sustainable Science
Journal of Tropical Resources and Sustainable Science j o urnal hom e p age: w w w. jtrss.com.my An Overview of Illegal Logging Situation in Peninsular Malaysia Iqtie Qamar Laila Mohd Gani 1, *, Razak
More informationEVALUATION OF FOREST MACHINERY GROUND MOBILITY USING ALS DATA
EVALUATION OF FOREST MACHINERY GROUND MOBILITY USING ALS DATA Marco Pellegrini, Stefano Grigolato, Raffaele Cavalli marco.pellegrini@unipd.it TESAF Departement University of Padova IUFRO 3.06 Conference
More informationMileage savings from optimization of coordinated trucking 1
Mileage savings from optimization of coordinated trucking 1 T.P. McDonald Associate Professor Biosystems Engineering Auburn University, Auburn, AL K. Haridass Former Graduate Research Assistant Industrial
More informationFOREST HARVESTING PRACTICES TOWARDS ACHIEVING SUSTAINABLE FOREST MANAGEMENT IN PENINSULAR MALAYSIA *
FOREST HARVESTING PRACTICES TOWARDS ACHIEVING SUSTAINABLE FOREST MANAGEMENT IN PENINSULAR MALAYSIA * Mohd Paiz bin Kamaruzaman + & Wan Mohd Shukri Wan Ahmad# Abstract Peninsular Malaysia has long recognized
More informationDeveloping a hybrid algorithm for distribution network design problem
Proceedings of the 2011 International Conference on Industrial Engineering and Operations Management Kuala Lumpur, Malaysia, January 22 24, 2011 Developing a hybrid algorithm for distribution network design
More informationCode of Practice For Timber Management Operations In Riparian Areas
Code of Practice For Timber Management Operations In Riparian Areas Original document produced in 1991 Queen s Printer for Ontario Document amended in April 1998 consistent with Term and Condition 76 in
More informationExcavator-Based Cable Logging and Processing System: A Norwegian Case Study
International Journal of Forest Engineering 11 Excavator-Based Cable Logging and Processing System: A Norwegian Case Study Halvor Torgersen Torstein Lisland Norwegian Forest Research Institute (Skogforsk)
More informationRoad Network Planning, Timber Harvesting and Forest Road Construction in Austria
Faculty of Forestry March 2016, Zagreb Road Network Planning, Timber Harvesting and Forest Road Construction in Austria Univ. Prof. Dipl.-Ing. Dr. Karl Stampfer Institute of Forest Engineering, Department
More informationRoad Network Planning, Timber Harvesting and Forest Road Construction in Austria
Faculty of Forestry March 26 th 2013, Zagreb Road Network Planning, Timber Harvesting and Forest Road Construction in Austria Univ. Prof. Dipl.-Ing. Dr. Karl Stampfer Institute of Forest Engineering, Department
More informationWOOD SCIENCE AND TECHNOLOGY: CURRICULUM DEVELOPED FOR FUTURE CHALLENGES IN WOOD- BASED INDUSTRY
WOOD SCIENCE AND TECHNOLOGY: CURRICULUM DEVELOPED FOR FUTURE CHALLENGES IN WOOD- BASED INDUSTRY Mohd Hamami S., Zaidon A., Awang Noor A.G., Paridah, M.T. and Khamuruddin, M.N. Faculty of Forestry University
More informationSURINAME. MINISTRY OF NATURAL RESOURCES with FOOD AND AGRICULTURE ORGANIZATION
SURINAME MINISTRY OF NATURAL RESOURCES with FOOD AND AGRICULTURE ORGANIZATION Project GCP/SUR/001/NET Forestry Advisory Assistance to the Ministry of Natural Resources in Suriname A ROUNDWOOD PRODUCTION
More informationWe are IntechOpen, the world s leading publisher of Open Access books Built by scientists, for scientists. International authors and editors
We are IntechOpen, the world s leading publisher of Open Access books Built by scientists, for scientists 3,700 108,500 1.7 M Open access books availle International authors and editors Downloads Our authors
More informationECONOMIC BENEFITS OF LONG TERM FORESTRY MACHINE DATA CAPTURE: AUSTRIAN FEDERAL FOREST CASE STUDY
FORMEC 2010 Forest Engineering: Meeting the Needs of the Society and the Environment July 11 14, 2010, Padova Italy ECONOMIC BENEFITS OF LONG TERM FORESTRY MACHINE DATA CAPTURE: AUSTRIAN FEDERAL FOREST
More informationPD 722/13 Rev.1 (I) CAPACITY BUILDING ON REDUCED IMPACT LOGGING (RIL) IN DRY INLAND FOREST IN THE PERMANENT FOREST RESERVE OF PENINSULAR MALAYSIA
COMPLETION REPORT PD 722/13 Rev.1 (I) CAPACITY BUILDING ON REDUCED IMPACT LOGGING (RIL) IN DRY INLAND FOREST IN THE PERMANENT FOREST RESERVE OF PENINSULAR MALAYSIA Implementing Agency: Forestry Department
More informationReduced Impact Logging in Sabah
Reduced Impact Logging in Sabah Asia- Pacific Workshop Reduced Impact Logging : Challenges, opportunities and strategies in the emerging forest carbon economy Kota Kinabalu, Sabah 3-4 May 2012 Global Forestry
More informationUtilization and Cost for Animal Logging Operations
Utilization and Cost for Animal Logging Operations Suraj P. Shrestha and Dr. Bobby L. Lanford School of Forestry and Wildlife Sciences, Auburn University, AL 36849 ABSTRACT - Forest harvesting animals
More informationOptimizing Biomass Feedstock Logistics for Forest Residue Processing and Transportation on a Tree-Shaped Road Network
Article Optimizing Biomass Feedstock Logistics for Forest Residue Processing and Transportation on a Tree-Shaped Road Network Hee Han 1,2 ID, Woodam Chung 1, * ID, Lucas Wells 1 and Nathaniel Anderson
More informationMalaysian Timber Certification Scheme : MC&I(2002) (Associated Documents) MALAYSIAN TIMBER CERTIFICATION SCHEME
Malaysian Timber Certification Scheme : MC&I(2002) (Associated Documents) Doc. Number: AD 34-01 Version Date: 15 September 2009 Page: 1 of 10 MALAYSIAN TIMBER CERTIFICATION SCHEME PUBLIC SUMMARY OF STAGE
More informationOptimization Problems and Algorithms in Supply-Chain Management
Optimization Problems and Algorithms in Supply-Chain Management 1 Botond Bertok, 1 Robert Adonyi, 2 Sandor Bodrogi, and 1 Zoltan Kovacs 1 University of Pannonia, Faculty of Information Technology Department
More informationTimber Legality Assurance System
Timber Legality Assurance System Assessment Standard Ref # G100-188 Auditing Legality of Forest Management Sabah, Malaysia MTC Activity # 5.0 Page 1 Background Malaysia has taken steps to engage the European
More informationEVALUATION OF WINCH PERFORMANCE IN ROUND WOOD HARVESTING
Bulletin of the Transilvania University of Braşov Series II: Forestry Wood Industry Agricultural Food Engineering Vol. 6 (55) No.2-2013 EVALUATION OF WINCH PERFORMANCE IN ROUND WOOD HARVESTING Marcian
More informationOPTIMIZATION MODEL OF SELECTIVE CUTTING FOR TIMBER HARVEST PLANNING BASED ON A SIMULATED ANNEALING APPROACH
Journal of Computer Science 10 (1): 54-65, 2014 ISSN: 1549-3636 2014 doi:10.3844/jcssp.2014.54.65 Published Online 10 (1) 2014 (http://www.thescipub.com/jcs.toc) OPTIMIZATION MODEL OF SELECTIVE CUTTING
More informationDeveloping Policy for Suitable Harvest Zone using Multi Criteria Evaluation and GIS-Based Decision Support System
Developing Policy for Suitable Harvest Zone using Multi Criteria Evaluation and GIS-Based Decision Support System Mohd Hasmadi Ismail Surveying and Engineering Laboratory, Department of Forest Production
More informationAppendix 6. Western felling and timber-carrying machinery
Appendix 6. Western felling and timber-carrying machinery. Page 1 Appendix 6. Western felling and timber-carrying machinery Chainsaw Husqvarna -257 The saw is well known in Russia and is widely used in
More informationuse only equipment which is in good order and has been tested for the purpose.
5. Harvesting operations - 35-5.2.1 Operational equipment Principles use only equipment which is in good order and has been tested for the purpose. Operational equipment Felling and Logging Machines: Implements
More informationMathematical formulation and exact solution for landing location problem in tropical forest selective logging, a case study in Southeast Cameroon
THE UNIVERSITY OF TEXAS AT SAN ANTONIO, COLLEGE OF BUSINESS Working Paper SERIES Date March 20, 2012 WP # 0009MSS-061-2012 Mathematical formulation and exact solution for landing location problem in tropical
More informationA New Approach in Individual Tree Counting of Nyatoh (Palaquium spp.) Using an Airborne Spectroradiometer
American Journal of Applied Sciences 7 (4): 486-492, 2010 ISSN 1546-9239 2010Science Publications A New Approach in Individual Tree Counting of Nyatoh (Palaquium spp.) Using an Airborne Spectroradiometer
More informationAn evaluation of forest road network by α- and β-indices *
An evaluation of forest road network by α- and β-indices * Hideo Sakai Professor, Graduate School of Agricultural and Life Sciences, The University of Tokyo Email: sakaih@fr.a.u-tokyo.ac.jp Abstract The
More informationROADSIDE RESIDUAL HANDLING GUIDELINE VERSION 3.0. Prepared by FPInnovations and Forest Tenures Branch
ROADSIDE RESIDUAL HANDLING GUIDELINE VERSION 3.0 Prepared by FPInnovations and Forest Tenures Branch May 9, 2018 1 Disclaimer This document contains material to inform forest tenure holders on best practices
More informationTopics in Forest Transportation Network Design
Topics in Forest Transportation Network Design Professor Frank Greulich College of Forest Resources University of Washington Seattle, Washington Nihon University September, 2002 Balancing Transportation
More informationINTRODUCTION
Malaysian Criteria and Forest, Including Certification: Its 1. INTRODUCTION Total Forested Land 19.54 million ha (59.5%) MALAYSIAN CRITERIA AND INDICATORS FOR SUSTAINABLE FOREST MANAGEMENT, INCLUDING CERTIFICATION:
More informationRegister Allocation via Graph Coloring
Register Allocation via Graph Coloring The basic idea behind register allocation via graph coloring is to reduce register spillage by globally assigning variables to registers across an entire program
More informationOverview. LANTw44 - HY Choker timber for extraction
Overview This standard is about chokering timber for extraction with a cable crane or winch. An important aspect of this work is the communication between the choker man and the winch or cable crane operator.
More informationMalaysian Timber Certification Scheme : MC&I(2002) (Associated Documents) MALAYSIAN TIMBER CERTIFICATION SCHEME
Malaysian Timber Certification Scheme : MC&I(2002) (Associated Documents) Doc. Number: AD 34-01 Version Date: 15 September 2009 Page: 1 of 6 MALAYSIAN TIMBER CERTIFICATION SCHEME PUBLIC SUMMARY OF SURVEILLANCE
More informationCOMPARISON OF OPERATOR-DESIGNED AND COMPUTER- GENERATED SKID-TRAIL NETWOKS
COMPARISON OF OPERATOR-DESIGNED AND COMPUTER- GENERATED SKID-TRAIL NETWOKS ABSTRACT David Parrott 1 and Marco A. Contreras 2 For ground-based timber harvests, it is essential that skid-trail networks connect
More informationHarvesting Forest Trees
Lesson B3 5 Harvesting Forest Trees Unit B. Plant Wildlife Management Problem Area 3. Forest Management Lesson 5. Harvesting Forest Trees New Mexico Content Standard: Pathway Strand: Natural Resources
More informationMetaheuristics. Approximate. Metaheuristics used for. Math programming LP, IP, NLP, DP. Heuristics
Metaheuristics Meta Greek word for upper level methods Heuristics Greek word heuriskein art of discovering new strategies to solve problems. Exact and Approximate methods Exact Math programming LP, IP,
More informationTitle: A Column Generation Algorithm for the Log Truck Scheduling Problem.
Title: A Column Generation Algorithm for the Log Truck Scheduling Problem. Authors: Myrna Palmgren Department of Optimization Linkoping University S-58183 Linkoping, Sweden e-mail: mypal@mai.liu.se Mikael
More informationSolving a Log-Truck Scheduling Problem with Constraint Programming
Solving a Log-Truck Scheduling Problem with Constraint Programming Nizar El Hachemi, Michel Gendreau, Louis-Martin Rousseau Interuniversity Research Centre on Enterprise Networks, Logistics and Transportation
More informationIMPACT OF FOREST CERTIFICATION: FROM THE PERSPECTIVE OF FOREST CONCESSIONAIRES STAFFS
Abstract IMPACT OF FOREST CERTIFICATION: FROM THE PERSPECTIVE OF FOREST CONCESSIONAIRES STAFFS Syahaneem Mohamad Zainalabidin 1 and Shukri Mohamed 2 Concerned by the increased in tropical deforestation,
More informationAgricultural mechaniza0on: present meets future!
27 th Members Mee2ng of the Club of Bologna Agricultural mechaniza0on: present meets future! 12-13 November 2017 Hannover, Germany A case study: ground yarding opera2ons in mountainous terrain Raffaele
More informationDiscussion on economy and energy balances of forest residues. for Bio-energy at Sano city, Tochigi prefecture in Japan
Discussion on economy and energy balances of forest residues for Bio-energy at Sano city, Tochigi prefecture in Japan Kazuhiro Aruga; Associate Professor, Fac. of Agric., Utsunomiya Univ., Tochigi 321-8505
More informationASIA-PACIFIC WORKSHOP REDUCED IMPACT LOGGING: CHALLENGES, OPPORTUNITIES AND STRATEGIES IN THE EMERGING FOREST CARBON ECONOMY
ASIA-PACIFIC WORKSHOP REDUCED IMPACT LOGGING: CHALLENGES, OPPORTUNITIES AND STRATEGIES IN THE EMERGING FOREST CARBON ECONOMY ROLE OF FOREST CERTIFICATION IN PROMOTING GREATER UPTAKE OF REDUCED IMPACT LOGGING
More informationBig Sky, Big Wind. Wind Power Development in Montana. Marty Schnure GG320: GIS December 7, 2009 Word count: 908
Big Sky, Big Wind Wind Power Development in Montana Marty Schnure GG320: GIS December 7, 2009 Word count: 908 Introduction Historically, Montana's energy has come primarily from coal and hydroelectric
More informationIn-woods Chipping. Popular in the early 1970 s Big demand for pulp fiber and wood for industrial fuel. WDSC 422 Chipping and Wetland Systems 1
In-woods Chipping Popular in the early 1970 s Big demand for pulp fiber and wood for industrial fuel WDSC 422 Chipping and Wetland Systems 1 In-woods Chipping Chippers: Produce whole-tree chips Grind/chip
More informationCHARLES SOIL CONSERVATION DISTRICT COMPLIANCE AGREEMENT FOR THE STANDARD EROSION AND SEDIMENT CONTROL PLAN FOR FOREST HARVEST OPERATIONS
CHARLES SOIL CONSERVATION DISTRICT COMPLIANCE AGREEMENT FOR THE STANDARD EROSION AND SEDIMENT CONTROL PLAN FOR FOREST HARVEST OPERATIONS I. Site Information A. Location (Include site map of harvest area)
More informationFILE COPY. How To Reduce Injuries. Stand Management Activities. to Residual Trees During EDITOR'S. Paul E. Aho, Gary Fiddler, Gregory M.
United States Department of Agricu It ure Forest Service Pacific Northwest Forest and Range Experiment Stat ion General Technical Report, PNW-156 June 1983 EDITOR'S FILE COPY How To Reduce Injuries to
More informationApplication of optimized models through direct block scheduling in traditional mine planning
http://dx.doi.org/10.17159/2411-9717/2018/v118n4a8 Application of optimized models through direct block scheduling in traditional mine planning by P.H.A. Campos*, C.E.Arroyo, and N. Morales Many papers
More informationLOGGING METHODS for WISCONSIN WOODLANDS. A landowner s guide to timber harvesting in Wisconsin s forests
LOGGING METHODS for WISCONSIN WOODLANDS A landowner s guide to timber harvesting in Wisconsin s forests 1 Equipment descriptions & Illustrations Timber harvesting is an integral part of sound forest management.
More informationNelson / Marlborough Forest Industry Working Group Fire Prevention Guidelines for Forestry Operations
Nelson / Marlborough Forest Industry Working Group Fire Prevention Guidelines for Forestry Operations Operative from 1 st Nov 2016 Updated 13/6/2017 When a BUI of over 40 exists, the colour code for each
More informationTHE SHORTEST NOT NECESSARILY THE BEST OTHER PATH ON THE BASIS OF THE OPTIMAL PATH
THE SHORTEST NOT NECESSARILY THE BEST OTHER PATH ON THE BASIS OF THE OPTIMAL PATH Tomasz Neumann 1 1 Gdynia Maritime University, Gdynia, Poland Abstract This paper presents a different perspective on the
More informationTHINNING OF RADIATA PINE BY CRAWLER TRACTOR ON STEEP SLOPES IN NORTH-EASTERN VICTORIA: A PRELIMINARY STUDY
213 THINNING OF RADIATA PINE BY CRAWLER TRACTOR ON STEEP SLOPES IN NORTH-EASTERN VICTORIA: A PRELIMINARY STUDY C. J. LEITCH Forests Commission Victoria, Box 164, Myrtleford 3737, Australia and G. B. MOORE
More informationLANTw42 - SQA Unit Code H2SR 04 Use mechanically powered winches in timber work
Overview This standard is about using mechanically powered wire winches to pull felled trees or timber to a position for further processing or extraction This standard also covers use of winches for single
More information