BACKGROUND: SUBSURFACE CONDITIONS:

Size: px
Start display at page:

Download "BACKGROUND: SUBSURFACE CONDITIONS:"

Transcription

1

2 2 BACKGROUND: The planned project consists of a prefabricated modular apartment building with underground parking, located on the site bounded by Dexter Avenue N. to the east, multi-story residential/commercial structures to the north and south, and an alley to the west. The site slopes to the east, with the alley at elevation feet and Dexter Avenue ranging from elevation 13 feet in the north to 99 feet in the south. The buildings to the north and the south, as well as the structure presently located on the northern portion of the site, are benched into the steep slope that is adjacent the alley. The parking lot within the south portion of the site is separated from the steep slope to the west by a 1-foot-high cast in-place concrete retaining wall. The excavation will cover essentially the entire site with setbacks of 2 feet from the north and south property lines to accommodate shoring. In addition, the basement excavation will be set back from the east property line such that the building footprint will be 146 feet long by just over 1 feet wide (east-west). The excavation will extend to elevation 88 to 96 feet, with maximum depths of excavation along the west (alley) side of 37 feet. This design addendum addresses the re-design of the central section of the west wall, replacing anchored soldier pile shoring with internally-braced soldier piles, as a result of a lack of a temporary construction easement for the associated property to the immediate west of the alley. SUBSURFACE CONDITIONS: The geotechnical information indicates that the subsurface materials consist of fill/colluvium and landslide deposits overlying very stiff to hard glacially over-ridden silt and clay. The groundwater table is located below the planned base of excavation but perched groundwater seepage can be anticipated during construction. SHORING SYSTEM: The replacement shoring will consist of soldier piles supported by rakers and associated walers. The rakers will in turn be supported by toe piles and the rakers will be pre-loaded to control displacements of the alley. A single row of rakers will be employed. After installing the soldier piles, the construction sequence will consist of sequential excavation of the face and placement of the wood lagging. A berm will be left in place, starting at just below the planned elevation of the raker supports. Following excavation to the planned base of the excavation and installation of the toe piles, the rakers will be installed and pre-loaded. The berm will then be removed from beneath and between the installed rakers. In addition to the above, small bar anchors will be installed and attached to each of the internally braced soldier piles. These anchors will not contribute to overall stability, which will be provided by the raker supports, but will simply reduce the flexural demand on the soldier piles until the rakers can be installed. DESIGN PARAMETERS: Design earth pressures corresponding to the soil self-weight are recommended in the geotechnical report. For the raker supported soldier piles, the soil self-weight was modeled using an equivalent fluid density of 45 psf/ft, per the recommendations of the geotechnical report. Live load lateral surcharge pressures were taken as 1 psf. Ground Support PLLC

3 3 The following design values were used to evaluate the depth of embedment of the soldier piles below the base of the excavation: Passive Equivalent Fluid Density Active Equivalent Fluid Density Allowable Pile Skin Friction 3 pcf over 2 pile diameters 15 pcf over 2 pile diameters for berm 3 pcf over 3 pile diameters for toe pile 45 pcf over 1 pile diameter.75 ksf Raker Loads: Individual raker loads are developed from the design earth pressure diagrams presented on the Plans, using a tributary area method to assign loads to the rakers and to the toe shear in the piles. The results are presented in Appendix A (Table A1). Loads indicated are per pile, with the raker loads being twice these loads as each raker supports two adjacent soldier piles. Design calculations for the raker and associated walers are shown in Table 1. Soldier Piles: Soldier pile loadings were determined from the design earth pressure diagrams and the locations and inclinations of the raker supports. The spreadsheet output presented in Appendix A (Table A2) summarizes the following design aspects for the final condition following completion of the excavation: Calculation of soldier pile loads and bending moments, consistent with the design apparent earth pressure diagrams provided on the Plans. For each soldier pile, the calculated shear force, axial load and bending moment are provided. Representative earth pressure diagrams, together with calculated shear force and bending moment diagrams, are also shown for a number of piles, in Appendix A. Calculation of pile toe embedment requirements (for lateral support and uplift resistance) using the criteria indicated on the Plans. Pile structural steel sizing in accordance with the AISC 36-5 Specification for Structural Steel Buildings. Combined flexure and axial load, shear, and compact section steel design checks are performed for the critically loaded section of each pile along the length of the wall. The spreadsheet output summarizes the minimum steel section required for each pile. Also shown in Appendix A are the corresponding design calculations for the toe piles that support the rakers (Table A3 and Figure A4). Table A4 and Figure A5 show design calculations for the intermediate condition where the soldier piles act in a cantilevered condition, prior to the installation of the rakers, and where small bar anchors provide nominal support. Lagging: Timber lagging will be used to support the soil between adjacent soldier piles. The average design earth pressures for the lagging are indicated in Appendix A, and these design earth pressures are derived directly from the design earth pressure diagrams. Hem-Fir No. 2 lagging (4-inch) or equivalent will provide adequate support for the soil between the soldier piles, per the recommendations of the FHWA Engineering Circular No. 4. Ground Support PLLC

4 4 TABLES Ground Support PLLC

5 Available Available Flexure Available Axial Bending Maximum Axial Flexural & Flexure Shear Load Shear Moment Span Steel Strength Axial Strength Axial & Strength Shear P V M L Steel Grade Pa Design Ma Design Axial Va Design Shear Case Analysis Case (k) (k) (ft-k) (ft) Section (ksi) (k) Ratio (ft-k) Ratio Status (k) Ratio Status 1 Waler W14x , OK OK 2 Waler Stubout HSS12x6x3/ OK OK 3 Raker Type Pipe18x5/ OK OK 4 Raker Type Pipe18x5/ OK OK TABLE 1 STRUCTURAL ELEMENT DESIGN

6 5 APPENDIX A DESIGN CALCULATIONS Ground Support PLLC

7 Anchor 1 Design Pile Top Pile Toe Pile Toe Pile Lagging L=NH 2 Unif. Press. Elevation Angle Anchor Load No. of Total Length Bond Length Beam Elevation Embed Elevation Length Pressure Pile ID Station (ft) Height (ft) Spacing (ft) No. Anchors N (psf/ft) P (psf) (feet) (degrees) (kips) Strands (feet) (feet) (feet) (feet) (feet) (feet) (psf) W W21x W8A W21x W W21x W9A W21x W W21x W1A W21x W W21x W W18x TABLE A1 RAKER DESIGN LOADS

8 Pile Vertical Load Analysis Toe Dist. 2 Soldier Beam Loads-Below Anchor 1 Axial Free Pile Pile Pile Pile Pile End Skin Axial Embed Design Load Moment Length Steel Flex/Ax Diameter End Area Skin Area End Bear Skin Frict Bearing Friction Load Length Pile ID Beam (kips) (ft-kips) (feet) Section Ratio (ft) (ft^2) (ft^2/ft) (ksf) (ksf) (kips) (klf) (kips) (ft) W8 W21x W21x W8A W21x W21x W9 W21x W21x W9A W21x W21x W1 W21x W21x W1A W21x W21x W11 W21x W21x W12 W18x W18x TABLE A2 SOLDIER PILE DESIGN

9 Soldier Beam Loads-Below Anchor 1 Axial Free Design Load Moment Length Steel Flex/Ax Pile ID Beam (kips) (ft-kips) (feet) Section Ratio TP W3x W3x TABLE A3 TOE PILE DESIGN

10 Soldier Beam Loads-Below Anchor 1 Axial Free Axial Load Shear Force Steel Shear Design Load Moment Length Steel Flex/Ax Pile ID (kips) (kips) Section Ratio Beam (kips) (ft-kips) (feet) Section Ratio C 9 31 W14x34.38 W18x W18x86.95 TABLE A4 SOLDIER PILE DESIGN LOADS STAGE 1 PRIOR TO RAKER INSTALLATION

11 Earth Pressure (psf) Shear Force (kips) Bend. Moment (ft-kips) Wall Height (ft) 36.4 Pile Spacing (ft) 6.25 FIGURE A1 SOLDIER BEAM - W9

12 Pressure (psf) Point Depth Pressure Width Force Depth(CG) Moment A 6.25 F AB B F BC. C F CD. D F AD E F EF F G F GH. H F HI I F IJ. J F JK. K F GK F LM F AD L F LM M N 6.25 F NO. O F EF P 6.25 F PQ. Q 6.25 R 6.25 F RS. S 6.25 T F TU. U F UV. V F VW. W F TW Anchor Amchor 2. Anchor 3. Anchor A 1 F NO F F RSTW PQ -4.L 1 A 23 4 F GK Load 1. S Forces S Moments -5. FIGURE A1 (cont'd) SOLDIER BEAM - W9

13 Earth Pressure (psf) Shear Force (kips) Bend. Moment (ft-kips) Wall Height (ft) 39. Pile Spacing (ft) 4.25 FIGURE A2 SOLDIER BEAM - W1

14 Pressure (psf) Point Depth Pressure Width Force Depth(CG) Moment A 4.25 F AB B F BC. C F CD. D F AD E F EF F F LM F AD G F GH. H F HI I F IJ. J F JK. K F GK L F LM M F EF N 4.25 F NO. O 4.25 P 4.25 F PQ. Q 4.25 R 4.25 F RS. S T F TU. U F UV. V F VW. W F TW Anchor Amchor 2. Anchor 3. Anchor 4. A 1 F NO F -4. F RSTW PQ L 1 A 23 4 F GK Load 1. S Forces S Moments -6. FIGURE A2 (cont'd) SOLDIER BEAM - W1

15 Earth Pressure (psf) Shear Force (kips) Bend. Moment (ft-kips) Wall Height (ft) 36.7 Pile Spacing (ft) 4.5 FIGURE A3 SOLDIER BEAM - W11

16 P4 P3 W2a W3 A4 A3 A2 W1 P2 Pressure (psf) A1 A9 A5 A6 A7 A8 Resisting Driving Resisting Driving P1 A1 Wall Height (ft).5 Depth of Embed (ft) Depth to Top of Passive (ft) 2.5 moment moment Force p (psf) Kg (psf) h (ft) w (ft) phw (lbf) Kg h 2 w/2 (lbf) depth (ft) arm (ft) (ft-lbf) A A A A P P P P Moments about pile toe Sum of resisting moments (ft-lbf) Sum of driving moments (ft-lbf) FS 1.2 Depth to Zero Shear (ft) at "M" moment moment Force p (psf) Kg (psf) h (ft) w (ft) phw (lbf) Kg h 2 w/2 (lbf) depth (ft) arm (ft) (ft-lbf) a a a a p p p p Moments at Zero Shear Point Sum of shear forces (lbf) at "M" Sum of moments (ft-lbf) at "M" Earth Pressure M W2W FIGURE A4 SOLDIER BEAM - TP

17 P4 P3 W2a W3 P2 P1 Resisting Driving Resisting Driving W1 A1 A9 A6 A7 A8 Pressure (psf) A5 A1 A2 A3 A4 Wall Height (ft) 16.5 Depth of Embed (ft) 25.9 Depth to Top of Passive (ft) 18.5 moment moment moment moment Force p (psf) Kg (psf) h (ft) w (ft) phw (lbf) Kg h 2 w/2 (lbf) depth (ft) arm (ft) (ft-lbf) Force p (psf) Kg (psf) h (ft) w (ft) phw (lbf) Kg h 2 w/2 (lbf) depth (ft) arm (ft) (ft-lbf) A A A A A A A A P A P A P P Moments about pile toe Moments about pile toe Sum of resisting moments (ft-lbf) Sum of driving moments (ft-lbf) moment moment Force p (psf) Kg (psf) h (ft) w (ft) phw (lbf) Kg h 2 w/2 (lbf) depth (ft) arm (ft) (ft-lbf) FS 1.2 a Depth to Zero Shear (ft) at "M" a moment moment a Force p (psf) Kg (psf) h (ft) w (ft) phw (lbf) Kg h 2 w/2 (lbf) depth (ft) arm (ft) (ft-lbf) a a a a a a a p Moments at Zero Shear Point p p p moment moment Force p (psf) Kg (psf) h (ft) w (ft) phw (lbf) Kg h 2 w/2 (lbf) depth (ft) arm (ft) (ft-lbf) W Moments at Zero Shear Point Sum of shear forces (lbf) at "M" W Sum of moments (ft-lbf) at "M" W W W2a Earth Pressure Moments about pile toe moment moment Force p (psf) Kg (psf) h (ft) w (ft) phw (lbf) Kg h 2 w/2 (lbf) depth (ft) arm (ft) (ft-lbf) w w w w w2a M Moments at Zero Shear Point W2W FIGURE A5 SOLDIER BEAM - C

Client Project Job # Wall Loc. SBWall Report deg 120 pcf 950 psf deg 0.0 ft. 6.0 ft 6.0 ft 2.0 ft. W16x50.

Client Project Job # Wall Loc. SBWall Report deg 120 pcf 950 psf deg 0.0 ft. 6.0 ft 6.0 ft 2.0 ft. W16x50. SBWall Report Soils Data Soil Friction Angle, phi Soil Unit Weight, gamma Soil Surcharge (uniform), qs Passive Resistance, FSp Passive Wedge Width, PW*B Backfill Slope Angle, beta Ignore Passive Resistance,

More information

Upon speaking with the representatives with Technical Foundations as well as Walder Foundations, it was determined that:

Upon speaking with the representatives with Technical Foundations as well as Walder Foundations, it was determined that: As part of our analyses, we have considered the design and construction of the cantilever retaining wall that will be located along the north side of Lucks Lane, between Falling Creek and Gladstone Glen

More information

Diaphragm wall with tieback supports (English units)

Diaphragm wall with tieback supports (English units) Diaphragm wall with tieback supports (English units) Deep Excavation LLC Software program: DeepEX 2015 Document version: 1.0 December 16, 2014 www.deepexcavation.com Deep Excavation LLC 1 A. Project description

More information

1.364 ADVANCED GEOTECHNICAL ENGINEERING HOMEWORK No. 5

1.364 ADVANCED GEOTECHNICAL ENGINEERING HOMEWORK No. 5 .364 ADVANCED GEOTECHNICAL ENGINEERING HOMEWORK No. Due: Friday December 2. This question concerns the stability of an open slope cutting that will be used to provide construction access for a 3.2m deep

More information

Cantilever or Restrained Retaining Wall Calculations

Cantilever or Restrained Retaining Wall Calculations Cantilever or Restrained Retaining Wall Calculations Organization: F.E.C. Project Name: Example Report Design by: LAA Job #: 9876 Date: 10/21/2013 Codes used: 2010 & 2013 CBC, 2009 & 2012 IBC, ACI 318-08

More information

Cantilever Sheet Pile Wall (English units)

Cantilever Sheet Pile Wall (English units) Cantilever Sheet Pile Wall (English units) Deep Excavation LLC Software program: DeepEX 2018 Document version: 1.0 August 14, 2018 www.deepexcavation.com www.deepex.com DEEP EXCAVATION 1 A. Project description

More information

Sheetpile Wall Report

Sheetpile Wall Report 16 ft cut Sheetpile Wall Report Project Information Designed By: LAA Organization: 16 ft cut Date: 05/09/2012 Project: Job #: 4952-6 Client: Support condition = Cantilever Unit system = English (ft, lb,

More information

Pump Station Excavation

Pump Station Excavation Pump Station Excavation SPONSORED BY THE KIEWIT CORPORATION A capstone project for the The Department of Civil & Environmental Engineering in The Ira A. Fulton College of Engineering and Technology Brigham

More information

Cantilever or Restrained Retaining Wall Design Calculations

Cantilever or Restrained Retaining Wall Design Calculations Cantilever or Restrained Retaining Wall Design Calculations Organization: F.E.C. Project Name: Ex 3 Driveway Short Wall Design by: LAA Job #: Date: 7/5/2016 Codes used: 2012 + 2015 IBC, ACI 318-14, ACI

More information

Third Avenue New York, NY. Structural Concepts/ Structural Existing Conditions Report September 30, Michelle L.

Third Avenue New York, NY. Structural Concepts/ Structural Existing Conditions Report September 30, Michelle L. Executive Summary The structural design of 554-556 Third Avenue is composed of two way concrete slabs supported by a system of columns spanning an average of twenty feet. Lateral loads are resisted by

More information

Case Study in Steel adapted from Structural Design Guide, Hoffman, Gouwens, Gustafson & Rice., 2 nd ed.

Case Study in Steel adapted from Structural Design Guide, Hoffman, Gouwens, Gustafson & Rice., 2 nd ed. Case Study in Steel adapted from Structural Design Guide, Hoffman, Gouwens, Gustafson & Rice., 2 nd ed. Building description The building is a one-story steel structure, typical of an office building.

More information

OVERALL STRUCTURAL SYSTEM

OVERALL STRUCTURAL SYSTEM EXECUTIVE SUMMARY The at the Pittsburgh International Airport, PA, is a 275,000 square foot multi-use building located directly adjacent to the airport s landside terminal. The building consists of an

More information

David A. Walenga Technical Assignment #1

David A. Walenga Technical Assignment #1 Executive Summary Contained in this report is design information related to the structural system of the Residence Inn by Marriot located in Stamford, Connecticut. Specifically, this report covers: code

More information

Cantilever diaphragm wall (English units)

Cantilever diaphragm wall (English units) Cantilever diaphragm wall (English units) Deep Excavation LLC Software program: DeepEX 2015 Document version: 1.0 December 12, 2014 www.deepexcavation.com Deep Excavation LLC 1 A. Project description In

More information

Structural Technical Report 1 Structural Concepts / Existing Conditions

Structural Technical Report 1 Structural Concepts / Existing Conditions Chris Shelow Structural Advisor: M. Kevin Parfitt Koshland Integrated Natural Science Center 10/05/05 AE 481W Structural Technical Report 1 Structural Concepts / Existing Conditions Executive Summary The

More information

Earth Retention Systems

Earth Retention Systems haywardbaker.com Earth Retention Systems Mark W. Goodsell, P.E., D.GE Senior Engineer 2 Earth Retention Systems Focus of Presentation Different Types and Purposes of Earth Retention Systems Design Considerations/Geotechnical

More information

(c) Presentation of Information. Information is presented in several forms as follows:

(c) Presentation of Information. Information is presented in several forms as follows: CONSTRUCTION SEQUENCE FOR TIMBER SHORING FOR TRENCHES (a) Scope. This appendix contains information that can be used when timber shoring is provided as a method of protection from cave-ins in trenches

More information

Structural Technical Report 1 Structural Concepts / Structural Existing Conditions Report

Structural Technical Report 1 Structural Concepts / Structural Existing Conditions Report Michael A. Troxell Structural Option Advisor: Professor Parfitt College of Business Administration Oct. 5, 2005 Structural Technical Report 1 Structural Concepts / Structural Existing Conditions Report

More information

Foundation Design. π = pi ( radians or 180 ) ρ = reinforcement ratio in concrete beam design = A s /bd µ = coefficient of static friction

Foundation Design. π = pi ( radians or 180 ) ρ = reinforcement ratio in concrete beam design = A s /bd µ = coefficient of static friction Foundation Design Notation: a = name for width dimension A = name for area b = width of retaining wall stem at base = width resisting shear stress b o = perimeter length for two-way shear in concrete footing

More information

UNDERPINNING A CRANE FOUNDATION

UNDERPINNING A CRANE FOUNDATION UNDERPINNING A CRANE FOUNDATION Donald R. McMahon, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New York, USA Andrew J. Nichols, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New

More information

See the IRC for additional information. See CPD-DS Information Bulletin 100 for Requirements for 1 & 2 Family Dwelling plan submittals.

See the IRC for additional information. See CPD-DS Information Bulletin 100 for Requirements for 1 & 2 Family Dwelling plan submittals. As a customer service initiative, the Kansas City, Missouri, City Planning and Development Department/Development Services, in cooperation with the Greater Kansas City Home Builders Association, has developed

More information

Dead man sheet pile wall (SI units)

Dead man sheet pile wall (SI units) Dead man sheet pile wall (SI units) Deep Excavation LLC Software program: DeepEX 2015 Document version: 1.0 January 16, 2015 www.deepexcavation.com Deep Excavation LLC 1 A. Project description In this

More information

Temporary Structures. Excavations and Excavation Supports

Temporary Structures. Excavations and Excavation Supports UNIVERSITY OF WASHINGTON DEPARTMENT OF CONSTRUCTION MANAGEMENT CM 420 TEMPORARY STRUCTURES Winter Quarter 2007 Professor Kamran M. Nemati Temporary Structures Excavations and Excavation Supports CM 420

More information

VOLUNTARY - EARTHQUAKE HAZARD REDUCTION IN EXISTING HILLSIDE BUILDINGS (Division 94 Added by Ord. No. 171,258, Eff. 8/30/96.)

VOLUNTARY - EARTHQUAKE HAZARD REDUCTION IN EXISTING HILLSIDE BUILDINGS (Division 94 Added by Ord. No. 171,258, Eff. 8/30/96.) DIVISION 94 VOLUNTARY - EARTHQUAKE HAZARD REDUCTION IN EXISTING HILLSIDE BUILDINGS (Division 94 Added by Ord. No. 171,258, Eff. 8/30/96.) SEC. 91.9401. PURPOSE. (Amended by Ord. No. 172,592, Eff. 6/28/99,

More information

Traci Peterson Option: Structural Faculty Consultant: Memari. Executive Summary

Traci Peterson Option: Structural Faculty Consultant: Memari. Executive Summary 1 Traci Peterson Option: Structural Faculty Consultant: Memari The Del Monte Center at The North Shore Pittsburgh, PA Structural Technical Report 3 Lateral System Analysis and Confirmation Design Date

More information

Cantilever or Restrained Retaining Wall Design Calculations

Cantilever or Restrained Retaining Wall Design Calculations Cantilever or Restrained Retaining Wall Design Calculations Organization: F.E.C. Project Name: Ex 4 Fence Wall Design by: LAA Job #: Date: 7/5/2016 Codes used: 2012 + 2015 IBC, ACI 318-14, ACI 530-11 NOTES:

More information

20 th STATEWIDE CONFERENCE ON LOCAL BRIDGES. Excavation Protection System Planning & Design

20 th STATEWIDE CONFERENCE ON LOCAL BRIDGES. Excavation Protection System Planning & Design 20 th STATEWIDE CONFERENCE ON LOCAL BRIDGES Excavation Protection System Planning & Design Syracuse, New York 5 November 2014 Training Manual Excavation Protection System Planning & Design Syracuse, New

More information

Alexis Pacella Structural Option Dr. Schneider Lexington II, Washington D.C. Technical Report #3 November 21,

Alexis Pacella Structural Option Dr. Schneider Lexington II, Washington D.C. Technical Report #3 November 21, 1 Executive Summary: Lateral System Analysis and Confirmation Design is an depth look at the lateral system of Lexington II and the loads of which it must carry. The structural system of Lexington II is

More information

TECHNICAL REPORT 1. Structural Concepts / Structural Existing Conditions. Penn State Hershey Medical Center Children s Hospital. Hershey, Pennsylvania

TECHNICAL REPORT 1. Structural Concepts / Structural Existing Conditions. Penn State Hershey Medical Center Children s Hospital. Hershey, Pennsylvania TECHNICAL REPORT 1 Structural Concepts / Structural Existing Conditions Penn State Hershey Medical Center Children s Hospital Matthew V Vandersall The Pennsylvania State University Architectural Engineering

More information

geopier Lateral resistance

geopier Lateral resistance technical bulletin No. 4 geopier Lateral resistance This Technical Bulletin discusses the behavior of Geopier supported shallow foundation systems when subjected to lateral loads. Lateral loads are applied

More information

UNIT-1 RETAINING WALLS

UNIT-1 RETAINING WALLS UNIT-1 RETAINING WALLS PART-A 1. Describe about Retaining wall. 2. Define gravity retaining walls. BT-1 3. Classify the types of retaining walls. 4. Explain cantilever retaining wall? 5. Describe about

More information

CHAPTER 11: WALLS.

CHAPTER 11: WALLS. CHAPTER 11: WALLS MODULAR BLOCK WALL (DRY CAST) Rather than being pre-approved as systems, the components of Modular block walls (dry cast) are pre-approved separately. The approved MBW components are

More information

twenty six concrete construction: foundation design ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SPRING 2013

twenty six concrete construction: foundation design ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SPRING 2013 ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SPRING 2013 lecture twenty six concrete construction: www.tamu.edu foundation design Foundations 1 Foundation the engineered

More information

Michael R. Lockwood Construction Management National Museum of the Marine Corps Quantico, VA

Michael R. Lockwood Construction Management National Museum of the Marine Corps Quantico, VA Soil Retention System Design and Analysis Executive Summary The National Museum of the Marine Corps has a unique design element that portrays an image that the building is built underground. In order to

More information

Date: December 7, 2017 Project No.:

Date: December 7, 2017 Project No.: Date: December 7, 2017 Project No.: 608-5-2 Prepared For: Mr. Alberto Vasquez SAN FRANCISCO UNIFIED SCHOOL DISTRICT 135 Van Ness Avenue - Room 207a San Francisco, California 94102 Re: Geotechnical Consultation

More information

GEOTECHNICAL REPORT PROPOSED DEVELOPMENT 1701 DEXTER AVENUE NORTH SEATTLE, WASHINGTON H-HABIT DEXTER LLC

GEOTECHNICAL REPORT PROPOSED DEVELOPMENT 1701 DEXTER AVENUE NORTH SEATTLE, WASHINGTON H-HABIT DEXTER LLC GEOTECHNICAL REPORT PROPOSED DEVELOPMENT 1701 DEXTER AVENUE NORTH SEATTLE, WASHINGTON Project No. 13-24 February 2014 Image Credit: Bushnaq Studio, LLC Prepared for: H-HABIT DEXTER LLC 2021A Minor Avenue

More information

FOUNDATIONS. Foundations Copyright G G Schierle, 2006 Press Esc to end, for next, for previous slide 1

FOUNDATIONS. Foundations Copyright G G Schierle, 2006 Press Esc to end, for next, for previous slide 1 FOUNDATIONS Foundations Copyright G G Schierle, 2006 Press Esc to end, for next, for previous slide 1 Liquefaction reduced the soil strength under these apartment buildings in Niigata (Japan) 1964. Liquefaction

More information

CE2401-DESIGN OF REINFORCED CONCRETE AND BRICK MASONRY QUESTION BANK

CE2401-DESIGN OF REINFORCED CONCRETE AND BRICK MASONRY QUESTION BANK CE2401-DESIGN OF REINFORCED CONCRETE AND BRICK MASONRY QUESTION BANK UNIT-1 PART-A 1. What is a Retaining wall? 2. What are the disadvantages of gravity retaining walls? 3. What are the types of retaining

More information

Part 28. Temporary Structures for Construction TABLE OF CONTENTS

Part 28. Temporary Structures for Construction TABLE OF CONTENTS Section/Article Part 28 Temporary Structures for Construction 2015 TABLE OF CONTENTS Description 28.1 General............................................................................... 8-28-2 28.1.1

More information

twenty seven concrete construction: foundation design Foundation Structural vs. Foundation Design Structural vs. Foundation Design

twenty seven concrete construction: foundation design Foundation Structural vs. Foundation Design Structural vs. Foundation Design ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SRING 2017 lecture twenty seven Foundation the engineered interface between the earth and the structure it supports that transmits

More information

FACSIMILE/ MAIL TRANSMISSION. Date: December 2, 2011 File:

FACSIMILE/ MAIL TRANSMISSION. Date: December 2, 2011 File: PUAR Engineering Consultants Inc #200-100 Park Royal South W.Vancouver, BC, Canada V7T 1A2 Fax: 604-922-5054; Tel: 604-913-7827 FACSIMILE/ MAIL TRANSMISSION Date: December 2, 2011 File: 07-2-256 To: BRIAN

More information

ENTRY FORM. DVASE 2014 Excellence in Structural Engineering Awards Program

ENTRY FORM. DVASE 2014 Excellence in Structural Engineering Awards Program ENTRY FORM DVASE 2014 Excellence in Structural Engineering Awards Program PROJECT CATEGORY (check one): Buildings under $2M Buildings Over $100M Buildings $2M-$10M Other Structures Under $5M Buildings

More information

SCOPE OF WORK: for new structure for exterior elevator according to manufacturer requirement, with a 36ft tower to install new elevator for 2 floors

SCOPE OF WORK: for new structure for exterior elevator according to manufacturer requirement, with a 36ft tower to install new elevator for 2 floors 5190 Indian Mound St Sarasota Fl. 34232 T 941 330-5095 F 941 866-2695 E-mail: jc generalcontractors@mac.com Web: http://jcontractor.com http://www.sarasotageneralcontractor.net Friday, June 24, 2016 The

More information

M-222 Slope Stabilization Case History Geotechnical Lessons Learned from Michigan Department of Transportation Design Build Project

M-222 Slope Stabilization Case History Geotechnical Lessons Learned from Michigan Department of Transportation Design Build Project Missouri University of Science and Technology Scholars' Mine International Conference on Case Histories in Geotechnical Engineering (2013) - Seventh International Conference on Case Histories in Geotechnical

More information

The following are details of the code requirements of the 2015 International Residential Code for single-story decks.

The following are details of the code requirements of the 2015 International Residential Code for single-story decks. The following are details of the code requirements of the 2015 International Residential Code for single-story decks. The 2015 International Residential Code Section R507 contains additional information

More information

twenty four foundations and retaining walls Foundation Structural vs. Foundation Design Structural vs. Foundation Design

twenty four foundations and retaining walls Foundation Structural vs. Foundation Design Structural vs. Foundation Design ALIED ARCHITECTURAL STRUCTURES: STRUCTURAL ANALYSIS AND SYSTEMS DR. ANNE NICHOLS SRING 2018 lecture twenty four Foundation the engineered interface between the earth and the structure it supports that

More information

Soldier Pile Walls Soil Nail Systems Secant Piling Soil Mix Walls Underpinning Slope Stabilization

Soldier Pile Walls Soil Nail Systems Secant Piling Soil Mix Walls Underpinning Slope Stabilization Soldier Pile Walls Soil Nail Systems Secant Piling Soil Mix Walls Underpinning Slope Stabilization www.malcolmdrilling.com Soldier Pile Walls Soil Nail Systems Secant Piling Soil Mix Walls Underpinning

More information

Perma-Column Deck Post Design Manual

Perma-Column Deck Post Design Manual Perma-Column Deck Post Design Manual DP4430, DP4440, DP4640, DP6630, DP6640, DP6430, and DP6440 models Project Number S007-12 by Brent Leatherman, P.E. Timber Tech Engineering, Inc E-Mail: bl@timbertecheng.com

More information

5-20 FOUNDATION REPORT/GEOTECHNICAL DESIGN

5-20 FOUNDATION REPORT/GEOTECHNICAL DESIGN 5-20 FOUNDATION REPORT/GEOTECHNICAL DESIGN REPORT CHECKLIST FOR EARTH RETAINING SYSTEMS Introduction This checklist was developed to assist the geotechnical project professionals in preparing the Foundation

More information

Analysis and Design of One-way Slab System (Part-I)

Analysis and Design of One-way Slab System (Part-I) Lecture-02 Analysis and Design of One-way Slab System (Part-I) By: Prof Dr. Qaisar Ali Civil Engineering Department UET Peshawar www.drqaisarali.com 1 Topics Addressed Concrete Floor Systems Analysis and

More information

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO. 1140198001 Reported to: SIRRUS ENGINEERS, INC. Houston, Texas Submitted by: GEOTEST

More information

Perma-Column Deck Post Design Manual DP4430, DP4440, DP4640, DP6630, DP6640, DP6430, and DP6440 models

Perma-Column Deck Post Design Manual DP4430, DP4440, DP4640, DP6630, DP6640, DP6430, and DP6440 models Perma-Column Deck Post Design Manual DP4430, DP4440, DP4640, DP6630, DP6640, DP6430, and DP6440 models Project Number S007-12 by Brent Leatherman, P.E. Timber Tech Engineering, Inc E-Mail: bl@timbertecheng.com

More information

UNIT V RETAINING WALLS RETAINING WALL 2.5. Retaining walls are structures used to retain earth or water or other materials such as coal, ore, etc; where conditions do not permit the mass to assume its

More information

CITY OF BATAVIA DECK CONSTRUCTION REQUIREMENTS

CITY OF BATAVIA DECK CONSTRUCTION REQUIREMENTS CITY OF BATAVIA DECK CONSTRUCTION REQUIREMENTS City of Batavia Building Division Community Development Department 100 North Island Avenue Batavia, Illinois 60510 Tel: (630) 454-2700 Fax: (630) 454-2775

More information

Design Specifications- Micropile Foundation System. Geopier Calculations

Design Specifications- Micropile Foundation System. Geopier Calculations Design Specifications- Micropile Foundation System Zone Total Piles Average Length (ft) Total Length 1- Primary Area 233 65 15145 2-Radiotherapy Area (Linac Valuts) 70 65 4550 3-Shell Space & ED Canopy

More information

Geotechnical Investigation Long Timber Brewing Building Highway 99 and Kelly Street Monroe, Oregon TABLE OF CONTENTS

Geotechnical Investigation Long Timber Brewing Building Highway 99 and Kelly Street Monroe, Oregon TABLE OF CONTENTS Highway 99 and Kelly Street TABLE OF CONTENTS PROJECT INFORMATION... 1 FIELD EXPLORATION... 1 SITE CONDITIONS... 2 Surface Conditions:... 2 Subsurface Conditions:... 2 FILL.... 2 Topsoil.... 2 Clay Alluvium....

More information

Case Study: Cement-Bentonite Pre-Trenching and Cutter Soil Mixing (CSM) for Temporary Shoring and Groundwater Cutoff

Case Study: Cement-Bentonite Pre-Trenching and Cutter Soil Mixing (CSM) for Temporary Shoring and Groundwater Cutoff Case Study: Cement-Bentonite Pre-Trenching and Cutter Soil Mixing (CSM) for Temporary Shoring and Groundwater Cutoff Dominic M. Parmantier 1, M. ASCE, P.E; Rowland F P Stow 2, P.Eng.; R. John Byrne 3,

More information

Footings GENERAL CONSIDERATIONS 15.2 LOADS AND REACTIONS 15.4 MOMENT IN FOOTINGS

Footings GENERAL CONSIDERATIONS 15.2 LOADS AND REACTIONS 15.4 MOMENT IN FOOTINGS 4 Footings GENERAL CONSIDERATIONS Provisions of Chapter 15 apply primarily for design of footings supporting a single column (isolated footings) and do not provide specific design provisions for footings

More information

Lecture Retaining Wall Week 12

Lecture Retaining Wall Week 12 Lecture Retaining Wall Week 12 Retaining walls which provide lateral support to earth fill embankment or any other form of material which they retain them in vertical position. These walls are also usually

More information

GEOTECHNICAL DESIGN AND CONSTRUCTION METHODOLOGY OF A DEEP BASEMENT CUT NEXT TO SENSITIVE BUILDINGS

GEOTECHNICAL DESIGN AND CONSTRUCTION METHODOLOGY OF A DEEP BASEMENT CUT NEXT TO SENSITIVE BUILDINGS GEOTECHNICAL DESIGN AND CONSTRUCTION METHODOLOGY OF A DEEP BASEMENT CUT NEXT TO SENSITIVE BUILDINGS James Livingston 1 Ching Dai 2 1 Geotechnical engineer at Coffey Services (NZ) 2 Chartered Senior Principal

More information

Third Avenue New York, NY. Lateral System Analysis and Confirmation Design November 13, Michelle L. Mentzer.

Third Avenue New York, NY. Lateral System Analysis and Confirmation Design November 13, Michelle L. Mentzer. Executive Summary The lateral system for 554-556 Third Avenue is primarily a shear wall core surrounding the elevator shaft and stairwells. There are six slightly different configurations of shear walls

More information

How Loads Are Distributed

How Loads Are Distributed LOAD DISTRIBUTION 1 LOAD DISTRIBUTION This section illustrate how load will transmit from the deck to the stringers. Determining the fraction of load carried by a loaded member and the remainder distributed

More information

Misan University - College of Engineering Civil Engineering Department

Misan University - College of Engineering Civil Engineering Department CHAPTER 2 Soil and Excavations Soil investigation including two phases: surface investigation and subsurface investigation Surface investigation involves making a preliminary judgment about the site s

More information

SCG INTERNATIONAL TRINIDAD AND TOBAGO LIMITED COUVA CHILDREN S HOSPITAL

SCG INTERNATIONAL TRINIDAD AND TOBAGO LIMITED COUVA CHILDREN S HOSPITAL SCG INTERNATIONAL TRINIDAD AND TOBAGO LIMITED COUVA CHILDREN S HOSPITAL GEOTECHNICAL CONSULTANT Prepared by Checked by Approved by Mr. C Allen Dr. Derek Gay Dr. Derek Gay Signature Date Signature Date

More information

Design of Semi gravity Retaining Walls

Design of Semi gravity Retaining Walls Design of Semi gravity Retaining Walls Example 13.1 A semi gravity retaining wall consisting of plain concrete (weight = 145 lb/ft³) is shown in Figure 13.9. The bank of supported earth is assumed to weigh

More information

GEO-SLOPE International Ltd, Calgary, Alberta, Canada Tie-back Wall

GEO-SLOPE International Ltd, Calgary, Alberta, Canada   Tie-back Wall 1 Introduction Tie-back Wall This example simulates the sequential construction of a sheet-pile shoring wall tied back with pre-stressed anchors. The purpose is to demonstrate the steps involved in modeling

More information

Check the strength of each type of member in the one story steel frame building below.

Check the strength of each type of member in the one story steel frame building below. CE 331, Summer 2015 nalysis of Steel Braced Frame Bldg 1 / 9 Check the strength of each type of member in the one story steel frame building below. 4 @ 8 ft B 20 f 1 2 3 @ 25 ft Side Elevation 3 4 Plan

More information

STRUCTURAL ENGINEERING CALCULATIONS NEW WINDOW OPENING IN EXISTING PERIMETER LOAD BEARING WOOD FRAMED WALL Project Address: Job #: 80167

STRUCTURAL ENGINEERING CALCULATIONS NEW WINDOW OPENING IN EXISTING PERIMETER LOAD BEARING WOOD FRAMED WALL Project Address: Job #: 80167 4533 MacArthur Blvd., Ste A-2003 Newport Beach, CA 92660 949-478-4026 cell www.ocstructurecheck.com jeremy@ocstructurecheck.com STRUCTURAL ENGINEERING CALCULATIONS NEW WINDOW OPENING IN EXISTING PERIMETER

More information

DECK PERMIT APPLICATION

DECK PERMIT APPLICATION DECK PERMIT APPLICATION APPLICANT S INFORMATION Name: Company Name: Current address: City: State: ZIP Code: Phone: Email: PROPERTY OWNER S INFORMATION Name: Property Address: Phone: E-mail: City: State:

More information

Earth and Engineering Sciences Building

Earth and Engineering Sciences Building Executive Summary The purpose of this report is to provide an analysis of the existing floor system of the Earth and Engineering Sciences Building at University Park, Pennsylvania, as well as investigating

More information

Typical Deck. CONSTRUCTION TIP SHEET 5 Basic Decks w/ 60 psf Live Loading

Typical Deck. CONSTRUCTION TIP SHEET 5 Basic Decks w/ 60 psf Live Loading CONSTRUCTION TIP SHEET 5 Basic Decks w/ 60 psf Live Loading April 1, 2017 This Tip Sheet reflects code requirements of the 2015 International Residential Code (IRC) with Washington State Amendments which

More information

ICC-ES Evaluation Report Issued February 1, 2011 This report is subject to re-examination in one year.

ICC-ES Evaluation Report Issued February 1, 2011 This report is subject to re-examination in one year. ICC-ES Evaluation Report www.icc-es.org (800) 423-6587 (562) 699-0543 ESR-1854 Issued February 1, 2011 This report is subject to re-examination in one year. A Subsidiary of the International Code Council

More information

Typical Deck. CONSTRUCTION TIP SHEET 5 Basic Decks w/ 60 lb Live Loading

Typical Deck. CONSTRUCTION TIP SHEET 5 Basic Decks w/ 60 lb Live Loading CONSTRUCTION TIP SHEET 5 w/ 60 lb Live Loading April 1, 2017 This Tip Sheet reflects code requirements of the 2015 International Residential Code (IRC) with Washington State Amendments which update the

More information

Analysis for Failure Mechanism of Temporary Shoring Structure

Analysis for Failure Mechanism of Temporary Shoring Structure IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-issn: 2278-1684,p-ISSN: 2320-334X, Volume 15, Issue 2 Ver. I (Mar. - Apr. 2018), PP 31-37 www.iosrjournals.org Analysis for Failure Mechanism

More information

ETTAMAR, INC. Engineers and Consultants TBPE # Joe DiMaggio Blvd. Suite 28, Bldg. 300 Round Rock, TX (512) (512) FAX

ETTAMAR, INC. Engineers and Consultants TBPE # Joe DiMaggio Blvd. Suite 28, Bldg. 300 Round Rock, TX (512) (512) FAX RETAINING WALL CROSS-SECTION WALLS A & F ONLY N.T.S MAX HEIGHT 4"x4"x48" FULL BENCH ADJUST THE BOTTOM (OR TOP) OF WALL LOCATION TO ACCOUNT FOR WALL BATTER. OWNER SHOULD REVIEW AND APPROVE BOTTOM OF WALL

More information

(b) Calculate the required nominal axial compression strength, Pn of the column.

(b) Calculate the required nominal axial compression strength, Pn of the column. 9 Problem 2-3 (a) Determine the factored axial load or the required axial strength, Pu of a column in an office building with a regular roof configuration. The service axial loads on the column are as

More information

Northport Berth 3 design and construction monitoring

Northport Berth 3 design and construction monitoring Proc. 18 th NZGS Geotechnical Symposium on Soil-Structure Interaction. Ed. CY Chin, Auckland Lucy Coe, Nicola Ridgley, Do Van Toan Beca Infrastructure Limited, Auckland, NZ Keywords: retaining wall, deflections,

More information

Soldier pile and tremied concrete walls with strut supports (SI units)

Soldier pile and tremied concrete walls with strut supports (SI units) Soldier pile and tremied concrete walls with strut supports (SI units) Deep Excavation LLC Software program: DeepEX 2015 Document version: 1.0 January 15, 2015 www.deepexcavation.com Deep Excavation LLC

More information

Date: September 27, 2018 Project No.:

Date: September 27, 2018 Project No.: Date: September 27, 2018 Project No.: 307-23-2 Prepared For: Mr. Jonathan Stone PROMETHEUS REAL ESTATE GROUP 1900 S. Norfolk Street, Suite 150 San Mateo, California 94403 Re: Preliminary Shoring and Foundation

More information

Chapter A-15. CID-MO Structural Analysis

Chapter A-15. CID-MO Structural Analysis Kansas Citys, Missouri and Kansas Flood Risk Management Feasibility Study Engineering Appendix to the Final Feasibility Study Chapter A-15 CID-MO Structural Analysis Chapter A-15 CID-MO Structural Analysis

More information

APPENDIX A GEOTECHNICAL INVESTIGATION MEMORANDUM

APPENDIX A GEOTECHNICAL INVESTIGATION MEMORANDUM The City of Winnipeg Bid Opportunity No. 789-2016 Appendices Template Version: C020130321- Main C APPENDIX A GEOTECHNICAL INVESTIGATION MEMORANDUM GEOTECHNICAL INVESTIGATION RUBY AND AUBREY STREET OUTFALL

More information

North Shore at Canton Baltimore, MD Beau Menard Technical Report 1

North Shore at Canton Baltimore, MD Beau Menard Technical Report 1 North Shore at Canton Baltimore, MD Beau Menard Technical Report 1 Structural Schneider 10/05/05 Structural Concepts Executive Summary North Shore at Canton is a 4 story town home and parking garage structure

More information

Steel Design Guide Series. Steel and Composite Beams with. Web Openings

Steel Design Guide Series. Steel and Composite Beams with. Web Openings Steel Design Guide Series Steel and Composite Beams with Web Openings Steel Design Guide Series Steel and Composite Beams with Web Openings Design of Steel and Composite Beams with Web Openings David Darwin

More information

COMPARISON OF STRUCTURAL STEEL LATERAL FORCE RESISTING SYSTEMS FOR A THEORETICAL HOSPITAL GRID SYSTEM GRANT BUELL. B.S., Kansas State University, 2009

COMPARISON OF STRUCTURAL STEEL LATERAL FORCE RESISTING SYSTEMS FOR A THEORETICAL HOSPITAL GRID SYSTEM GRANT BUELL. B.S., Kansas State University, 2009 COMPARISON OF STRUCTURAL STEEL LATERAL FORCE RESISTING SYSTEMS FOR A THEORETICAL HOSPITAL GRID SYSTEM by GRANT BUELL B.S., Kansas State University, 2009 A REPORT submitted in partial fulfillment of the

More information

DIVISION: EARTHWORK SECTION: BORED PILES REPORT HOLDER: HELICAL ANCHORS, INC BOONE AVENUE, NORTH MINNEAPOLIS, MINNESOTA 55428

DIVISION: EARTHWORK SECTION: BORED PILES REPORT HOLDER: HELICAL ANCHORS, INC BOONE AVENUE, NORTH MINNEAPOLIS, MINNESOTA 55428 0 Most Widely Accepted and Trusted ICC-ES Evaluation Report ICC-ES 000 (800) 423-6587 (562) 699-0543 www.icc-es.org ESR-3982 Reissued 09/2017 This report is subject to renewal 09/2019. DIVISION: 31 00

More information

NPTEL Course GROUND IMPROVEMENT USING MICROPILES

NPTEL Course GROUND IMPROVEMENT USING MICROPILES Lecture 22 NPTEL Course GROUND IMPROVEMENT USING MICROPILES Prof. G L Sivakumar Babu Department of Civil Engineering Indian Institute of Science Bangalore 560012 Email: gls@civil.iisc.ernet.in Contents

More information

DIVISION: EARTHWORK SECTION: BORED PILES REPORT HOLDER: GEOTECH ENTERPRISES, INC.

DIVISION: EARTHWORK SECTION: BORED PILES REPORT HOLDER: GEOTECH ENTERPRISES, INC. 0 Most Widely Accepted and Trusted ICC ES Report ICC ES 000 (800) 423 6587 (562) 699 0543 www.icc es.org ESR 3623 Reissued 04/2017 This report is subject to renewal 04/2018. DIVISION: 31 00 00 EARTHWORK

More information

May 2, Mr. Tim Kurmaskie, AIA ARCHITECT KURMASKIE ASSOCIATES, INC Washington Street Raleigh, NC

May 2, Mr. Tim Kurmaskie, AIA ARCHITECT KURMASKIE ASSOCIATES, INC Washington Street Raleigh, NC Mr. Tim Kurmaskie, AIA ARCHITECT KURMASKIE ASSOCIATES, INC. 1030 Washington Street Raleigh, NC 27605-1258 May 2, 2017 Re: Report of Subsurface Investigation Westfield Rehabilitation & Health Care Additions

More information

Underpinning. Underpinning

Underpinning. Underpinning is the installation of temporary or permanent support to an existing foundation to provide either additional depth or an increase in bearing capacity. There are several existing conditions which may lead

More information

Lateral System Analysis and Confirmation Design November 15, 2004

Lateral System Analysis and Confirmation Design November 15, 2004 Jonathan Hill Structural AE Faculty Consultant Dr. Hanagan Lynde and Harry Bradley School of Technology & Trade Milwaukee, Wisconsin Lateral System Analysis and Confirmation Design November 15, 2004 Executive

More information

Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle

Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle Overall Information Location: Singapore Date of Completion: 2010 Cost: $5.7 billion Architect: Moshe Safdie Executive Architect: Aedas, Pte

More information

Technical Assignment 1 10/8/03

Technical Assignment 1 10/8/03 Executive Summary Technical Assignment 1 10/8/03 The is 55 story high-rise condominium being built off the northern Miami coast. The structural design presented in this building is a direct result of its

More information

Advance Design of RC Structure Retaining Wall

Advance Design of RC Structure Retaining Wall 1 Retaining Wall Retaining Walls What are retaining walls Retaining walls are soil-structure systems intended to support earth backfills. Type of retaining walls Gravity retaining wall gravity walls rely

More information

Kevin Wigton Structural Option. Technical Report III. Simmons College School of Management, Boston, Ma

Kevin Wigton Structural Option. Technical Report III. Simmons College School of Management, Boston, Ma Kevin Wigton Structural Option Technical Report III Simmons College School of Management, Boston, Ma Advisor: Professor Parfitt 12/1/2009 Table of Contents Executive Summary: Technical Report III... 3

More information

GEOTECHNICAL ENGINEERING REPORT PROPOSED RESIDENCE & DRIVEWAY IMPROVEMENTS 3835 WEST MERCER WAY MERCER ISLAND, WASHINGTON

GEOTECHNICAL ENGINEERING REPORT PROPOSED RESIDENCE & DRIVEWAY IMPROVEMENTS 3835 WEST MERCER WAY MERCER ISLAND, WASHINGTON GEOTECHNICAL ENGINEERING REPORT PROPOSED RESIDENCE & DRIVEWAY IMPROVEMENTS 3835 WEST MERCER WAY MERCER ISLAND, WASHINGTON Project No. 13-032 Credit: Google Earth Prepared for: Bradford & Jill Jackson 3213

More information

Substructure systems, specifically retaining walls

Substructure systems, specifically retaining walls Design principles of totally prefabricated counterfort retaining wall system compared with existing cast-in-place concrete structures Maen Farhat and Mohsen Issa An alternative to cast-in-place concrete

More information

15.2 Approximate Analysis of a Continuous Beam for Gravity Load

15.2 Approximate Analysis of a Continuous Beam for Gravity Load 15.2 Approximate Analysis of a Continuous Beam for Gravity Load Figure 15.1 Location of points of inflection and shear and moment curves for beams with various idealized end conditions 1 15.2 Approximate

More information

MASONRY WALL DATA: Wall Height = ft. Nominal Wall Thickness = 8.00 in. Depth to c.g. Steel, Wall = 3.81 in.

MASONRY WALL DATA: Wall Height = ft. Nominal Wall Thickness = 8.00 in. Depth to c.g. Steel, Wall = 3.81 in. TIME: 10:49 AM Page: 1 DESIGN METHOD : ACI 530-99: Working Stress Design MASONRY MATERIAL : Hollow Core Concrete Masonry Units MORTAR TYPE : Type S MORTAR MATERIAL : Portland Cement Lime Mortar BLOCK PLACEMENT

More information

VARIOUS TYPES OF SLABS

VARIOUS TYPES OF SLABS VARIOUS TYPES OF SLABS 1 CHOICE OF TYPE OF SLAB FLOOR The choice of type of slab for a particular floor depends on many factors. Economy of construction is obviously an important consideration, but this

More information

Page 1 of 46 Exam 1. Exam 1 Past Exam Problems without Solutions NAME: Given Formulae: Law of Cosines: C. Law of Sines:

Page 1 of 46 Exam 1. Exam 1 Past Exam Problems without Solutions NAME: Given Formulae: Law of Cosines: C. Law of Sines: NAME: EXAM 1 PAST PROBLEMS WITHOUT SOLUTIONS 100 points Tuesday, September 26, 2017, 7pm to 9:30 You are allowed to use a calculator and drawing equipment, only. Formulae provided 2.5 hour time limit This

More information