SECTION TREE & PLANTING PROTECTION

Size: px
Start display at page:

Download "SECTION TREE & PLANTING PROTECTION"

Transcription

1 SECTION PART 1 - GENERAL 4.1 SUMMARY A. The work includes labor, equipment, and materials necessary for existing tree & plant protection, tree trimming and protection of the Critical Root Zone (CRZ). B. Contractor shall contact the zoo's arborist to perform any pruning tree or repair work recommended. If damage occurs due to construction operations, the arborist shall make repairs promptly to prevent progressive deterioration of damaged trees. Any pruning, cabling, root treatment and tying back of limbs will be per recommendation and approval by the arborist. C. Trees, shrubs, and other understory plants within the critical root zone that are not designated for removal shall be protected during clearing, tree removal and construction operations. Protect the root system, trunk, limbs and crown from breakage, scarring and prevent soil compaction or chemical contamination. Contractor shall prevent any contamination of the soil within the Critical Root Zone by construction materials, debris, silt, fuel, oils, concrete or any other chemical substance. Contractor shall notify the Architect of any such spills, compaction or other disturbance within the critical root zone and take immediate corrective action using methods approved by the Zoo. D. The contractor shall provide tree protection signage that must remain posted at designated trees inside the construction zone for the duration of the project. E. Related Work Specified Elsewhere: 1. Section Demolition 2. Section Clearing and Grubbing 3. Section Earthwork 4. Section Plants 4.2 QUALITY ASSURANCE A. The applicable provisions of the following standard publications shall apply throughout this section: 1. American National Standard for Tree Care Operations - Tree, shrub, and other woody plant maintenance - standard practices, - ANSI , published by American National Standards Institute, American National Standard for Tree Care Operations - Tree and shrub transplant standard practices 3. American National Standard for Tree Care Operations - Pruning, trimming, repairing, maintaining, and removing trees, and cutting brush - safety requirements ANSI Z , - published by American National Standards Institute, Pg 1 of 7

2 4. Arrange a pre-construction meeting to review schedule, specifications, and tree protection operations. 4.3 SUBMITTALS A. Name of certified arborist for the project including certificate number and stamp. B. Product Data: Submit product literature with name of product manufacturer's name and compliance with specifications. 1. Pesticides (herbicides, insecticides and fungicides, etc.) 2. Anti-desiccant C. 1 lb. resealable plastic container of proposed mulch. D. Schedule and Work Plan: Submit detailed schedule and work plan for each part of the work. E. A plan of the site showing the location of protection fencing, trees to be removed. 4.4 REGULATORY REQUIREMENTS A. Comply with rules, regulations, laws and ordinances of local, state and federal authorities having jurisdiction. 4.5 PROJECT CONDITIONS A. Existing Conditions 1. Carefully examine the site before submitting a bid. Be informed of the site conditions including adjacent properties, utilities and soil conditions. 2. Should the Contractor find any discrepancies between Drawings and physical conditions inform the Owner's representative immediately for clarification. 4.6 ENVIRONMENTAL CONDITIONS A. Do not perform root pruning, tree removal or tree protection work within the Critical Root Zone area at times when the soil is wet or muddy. 4.7 PRE-CONSTRUCTION COORDINATION A. Prior to the start of construction, the Contractor and Architect shall meet at the site and review the locations of the following: 1. Existing trees to be protected and transplanted, trees to be removed from the site and trees to be removed and stockpiled for use in the project. The procedures and methods to be used to execute the work shall be reviewed during this meeting. 2. Areas for stockpiling trees for permanent removal, stockpiling of trees to be removed and used as snags in animal yards, stockpiling mulch, stockpiling topsoil, concrete wash-out, stockpiling of demolition debris, storage of construction materials, construction trailers, and other incidental contractor needs. Failure to comply with these reserved areas can result in immediate work stoppage and delays due to correction of non-compliance shall be at the contractor's expense. 4.8 TREE AND PLANT PROTECTION A. Operation of equipment, storage of materials, disposition of excavated material, and construction in general shall be conducted so as not to encroach into tree preservation areas. Injuries to tree trunks, branches or roots shall be the sole responsibility of the Pg 2 of 7

3 contractor. Trees and/or groups of trees and plants designated to remain shall be protected by tree protection fencing. B. The Contractor shall be responsible for providing any additional temporary fencing during the work as necessary to protect vegetation. Provide 6' chain link fencing or plywood boxes as required to protect trees, which are to remain free from any damage above and below grade throughout the construction period. Fencing shall extend to tree CRZ minimum. Erect and have approved by the Certified Arborist prior to commencement of demolition work C. Construction, when necessary and approved by the Architect, within the critical root zone shall be performed in a manner that avoids injury to the trees and their roots. 1. In general, construction as designated within the critical root zone shall proceed with extreme care either by the use of hand tools or equipment that will not cause damage to the trees. 2. Need for trimming of tree branches that interfere with construction shall be coordinated with the zoo' arborist. Trimming of branches and the cutting of roots shall be in accordance with accepted arboricultural practices and be performed by the Certified Arborist as designated in section PART 2 - PRODUCTS 5.1 TREE PROTECTION FENCING A. Minimum specifications - Construction style chain link fencing with concrete supports. Panel widths to be a maximum of 8 feet. 5.2 TREE PROTECTION SIGNS A. Heavy-duty cardboard or metal signs 12 by 12 inches attached to 3/4 inch thick exterior grade MDO plywood (or other substrate as recommended by the sign supplier). Sign shall have a blaze orange background with black block letters, 1 inch high, with the inscription "No Construction Activity - Tree Protection Zone". B. Signs shall be attached to the tree protection fence at intervals not to exceed 25 feet on center. 5.3 TREATMENT MATERIALS A. Pesticides: Approved before use for type and rate of application by and local, state, and federal agencies with jurisdiction. B. Anti-desiccant: 'Wiltpruf as manufactured by Wiltproof Products, Inc., P.O. Box 4280, Greenwich, CT 06830, (203) , or approved substitute. C. Chip mulch 1. Hardwood chips shall be produced by a disc style chipper, aged a minimum of six months and shall be free of non-wood material, including plastic, glass or leaves. Chips stockpiled from the tree removal operation may be used. D. Construction Mat 1. Construction matting will consist of 3/4 inch plywood or heavy gauge steel plates with an underlayment of a minimum of six inches of wood chip mulch. The Pg 3 of 7

4 plywood or steel top layer shall only be applied where vehicle movement is anticipated and shall not be kept in place for extended periods of time. PART 3 - EXECUTION 6.1 PREPARATION A. Prior to construction activity at the site, install tree protection fencing, tree protection signs and wood chip mulch as indicated in the project drawings and in accordance with the marked Critical Root Zone. 1. Signs and fencing shall not be attached to trees to be preserved. 2. Tree protection fencing and signs shall remain intact for the length of the project, damaged fencing or missing signs shall be repaired or replaced promptly. 3. Fencing shall not be taken down to store equipment or materials. B. Do not park vehicles or equipment, store materials or stockpiled soil, dispose of building materials, chemicals, petroleum products or other detrimental substances within CRZ of protected trees. Protect plant material from flame, smoke and heat. Construction access to site shall not occur beneath drip line of plant material. C. Tree flagging: 1. Trees flagged for complete removal and disposal: Mark trees scheduled for complete removal and disposal with orange paint in a band completely encircling the trunk of the tree. 2. Tree snags for animal yards: Mark trees to be saved for snags with a different color paint approved by Architect. In coordination with Architect, mark places on trees where cuts are to be made. Coordinate with Owner as to location for stockpiling of snags. D. Identify equipment ingress and egress pathways in the pre-construction walkthrough for inspection and approval by the Architect: 1. Equipment pathways shall avoid critical root zones, except as approved by the Architect Any approved access within the critical root zone shall use an approved construction mat. 2. Additional vertical clearance required for equipment access shall be reviewed and approved at the pre-construction walk-through. 3. Equipment shall not be parked within the critical root zone. 6.2 EXISTING TREES TO REMAIN A. General: 1. Provide 6' high chain link or 4'x4'x8' high plywood fence at tree CRZ. 2. Thoroughly water disturbed areas prior to placement of wood chip mulch. 3. Root zones shall also be protected with 12" of wood chip mulch to prevent compaction. Keep wood chip mulch 12" clear of tree trunk. Remove wood chips prior to placement of finished grades. 4. Where fencing is not possible due to obstructions, walkways, or other conflicting elements notify Architect for alternative fencing locations. 5. Restrict foot and vehicular traffic over root systems to prevent excessive compaction of soil Pg 4 of 7

5 6. Under no circumstances shall the Contractor remove or alter existing trees designated to remain for the convenience or ease of construction. 7. An effective silt fence of geotextile fabric supported by wood or metal fenceposts shall be maintained between sources of silt and the critical root zones. B. Excavation Around Trees: 1. Excavate within CRZ of trees only where shown. 2. Where excavation or construction is required within CRZ, water tree thoroughly a few days before work is to begin 3. Where trenching for utilities is required within CRZ, tunnel under or around roots by hand digging. Do not cut main lateral roots or tap roots. The Contractor shall notify the Architect prior to cutting roots over 3/4" in diameter. Certified arborist shall cut roots larger than 3/4". Contractor may be allowed to prune roots with approval and direction from certified arborist. Make clean cuts. 4. Do not leave roots exposed to sun or other drying. Protect exposed roots with damp burlap or wood shavings within 1 hour of initial exposure. 5. Where excavating for new construction is required within drip line of tree, excavate by hand to minimize damage to roots and perform as follows: a. Comb soil in direction of root growth to expose roots. b. If main lateral roots are immediately adjacent to location of new construction cut roots three (3) inches from new construction. c. Do not allow exposed roots to dry out before permanent backfill is placed. d. Provide temporary cover with damp burlap or wood shavings. e. Water and maintain in moist condition until covered with backfill. 6. Open trench inspections for hand dug areas a. areas designated for hand digging shall require an inspection by the Architect prior to backfilling, to assess the extent of possible root loss or damage. The Architect may also require inspection in certain areas approved for excavation with mechanical equipment. b. Should the contractor backfill any of these locations prior to the Architect's inspection, the Architect may require the contractor to remove the backfill material, at the contractor's expense, as necessary to complete the required inspection. c. The contractor shall provide the Architect with a minimum of 24 hours notice on planned excavations requiring an open trench forestry inspection. C. Grading and filling around trees 1. Maintain existing grades within CRZ of trees unless otherwise indicated or approved by Owner. The Certified Arborist will evaluate the extent of backfilling within the tree root zone of a protected tree and make recommendations if necessary. Fill material to be per Earthwork, Planting and Soil Preparation sections. D. Repair and Replacement of Trees: 1. Plant material protected within fencing that becomes damaged or dies shall be replaced with plant material of the same species and equal or approved size Pg 5 of 7

6 2. Contractor to engage and pay for a certified and licensed arborist to perform tree repair work damaged by construction operations. Make repairs promptly after damage occurs to prevent progressive deterioration of damaged trees. 3. Damaged and destroyed trees which cannot be replaced shall be paid for at the rate of $50.00 per square inch of cross sectional area measured three (3) feet above existing grade for trees up to and including six (6) inch caliper, and at the rate of $ per square inch of cross sectional areas measured three (3) feet above existing grade for trees greater than six (6) inches caliper. This amount shall be credited to the Owner. 4. Remove any damaged and destroyed trees from the site as determined by the arborist to be incapable of restoration to a normal growth pattern. Deliver to Owner. Repair the ground surface. Costs shall be borne by the Contractor. 5. Replacement plants shall be in good health and approved by Owner before installation. E. Irrigation of Trees During Construction 1. Ensure trees are irrigated during construction to maintain health of the tree. 2. Water trees deeply at regular intervals and a minimum of once every two weeks during the growing season. The water should penetrate the soil to a depth of at least six inches 3. Take necessary precautions to prevent over watering, excessive run-off, and erosion from occurring. 4. Do not irrigate if specified irrigation requirements occur naturally through rainfall. 6.3 TREE REMOVAL A. Trees indicated for complete removal and disposal shall be removed in a manner that will not damage adjacent trees or cause injury to people or property. B. An ISA Certified Arborist shall supervise all tree removals. 1. Tree removal service provider shall be experienced with tree removals in areas of limited access. 2. No trees to be removed shall be pushed over or uprooted within 50 feet of a remaining tree's critical root zone. C. Coordinate placement and stockpiling of removed trees with Owner. 6.4 TREE SNAGS/DEADFALLS A. All trees tagged for preservation as snags for future use in animal yards shall be cut as directed by Architectand stockpiled in a location directed by Owner. Trees shall be cut in a manner that will not damage adjacent trees or property or cause injury to people. 1. An ISA Certified Arborist shall supervise all tree removals. 2. Tree removal service provider shall be experienced with tree removals in areas of limited access. 3. No trees to be removed shall be pushed over or uprooted within 50 feet of the critical root zone. 4. Snags shall be cut according to Architect's direction. 5. Stockpile snags in location approved by Architect Pg 6 of 7

7 6.5 TREE TRANSPLANTS A. The Owner is responsible for all tree tranplants prior to construction. The Contractor shall verify with the Owner 6.6 STUMP REMOVAL A. Location of existing and proposed underground utilities shall be identified prior to any stump removal. B. Stumps 12 inch diameter or greater shall be ground to a depth of 12 inches below existing grade in areas where site excavation does not occur. C. Wood chips, shavings, and debris from this operation shall be removed and properly disposed of or used as mulch on site if accepted by architect. D. Contractor shall backfill the stump holes with an approved backfill material.. 1. Compact to 85% of the maximum dry density in areas outside of the CRZ. 2. Compact to 80% of the maximum dry density in areas within CRZ E. Trees less than 12" in diameter shall be removed flush with existing grade. F. No stumps shall be dug or pulled within the CRZ. 6.7 TRIMMING OF EXISTING TREES A. Engage a qualified arborist to selectively remove branches from trees. Do not prune unless approved and directed by the Owner's representative. B. Cut branches with sharp pruning instruments and do no break or chop. Prune to outside edge of branch collar per ANSI pruning standards. END OF SECTION Pg 7 of 7

1993 Specifications CSJ'S & SPECIAL SPECIFICATION ITEM Tree Preservation and Treatment

1993 Specifications CSJ'S & SPECIAL SPECIFICATION ITEM Tree Preservation and Treatment 1993 Specifications CSJ'S 0912-71-554 & 0912-71-555 SPECIAL SPECIFICATION ITEM 1016 Tree Preservation and Treatment 1. Description. This section specifies the requirements for protecting trees and related

More information

CHAPTER 7: TREE PROTECTION DURING CONSTRUCTION 7.1 TREE PROTECTION AREAS

CHAPTER 7: TREE PROTECTION DURING CONSTRUCTION 7.1 TREE PROTECTION AREAS CHAPTER 7: TREE PROTECTION DURING CONSTRUCTION Urban trees need to be protected from damage to maximize their health, safety, benefits and functionality. Mature, young and newly transplanted trees need

More information

B. The purpose of the meeting shall be to establish the conditions of all existing trees upon receipt of the Project site by the Contractor. Failure t

B. The purpose of the meeting shall be to establish the conditions of all existing trees upon receipt of the Project site by the Contractor. Failure t Standard Specification SECTION 01 56 39 TREE AND PLANT PROTECTION PART 1 - GENERAL 1.1 WORK INCLUDED A. Perform all Work necessary and required to protect and maintain all trees, shrubs, groundcover and

More information

Tree Protection & Preservation

Tree Protection & Preservation IV. Tree Protection & Preservation A. Participation at the Construction Planning Stage 1. All Contracted Design Services shall receive a copy Tree Care Plan Sections appropriate to the given project as

More information

Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000

Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000 Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000 610S.1 This item shall govern the proper care and treatment of all trees and other vegetation

More information

TREE PRESERVATION AND PROTECTION SPECIFICATION FOR CONSTRUCTION NEAR TREES

TREE PRESERVATION AND PROTECTION SPECIFICATION FOR CONSTRUCTION NEAR TREES TREE PRESERVATION AND PROTECTION SPECIFICATION FOR CONSTRUCTION NEAR TREES PART I GENERAL 1.02 The objective of this section is to reduce the negative impacts of construction on trees. Tree protection

More information

UNIVERSITY OF CENTRAL FLORIDA SECTION TEMPORARY TREE AND PLANT PROTECTION

UNIVERSITY OF CENTRAL FLORIDA SECTION TEMPORARY TREE AND PLANT PROTECTION PART 1 - GENERAL 1.1 RELATED SECTIONS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Divisions 01 Specification Sections, apply to this Section.

More information

Tree Protection Policy

Tree Protection Policy Appendix F Tree Protection Policy The following is according to the City of Hamilton s special provision SP-97. General Tree Protection shall be in accordance with OPSS 801 as amended by this special provision.

More information

7. A saucer of soil shall be formed so that water is directed down through the roots or root ball rather than around the root ball.

7. A saucer of soil shall be formed so that water is directed down through the roots or root ball rather than around the root ball. Adopted 12/5/00; revised 3/5/02 Marietta Tree Commission Rules and Regulations I. Tree Planting A. Planting Specifications These specifications are Adapted from recommendations of the OSU Extension Service.

More information

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 PART FIVE DOCUMENTS FOR SITE AND INFRASTRUCTURE 31 00 00. EARTHWORK 31 10 00. SITE CLEARING.1 STRUCTURE REMOVAL: Include

More information

Section SITE CLEARING. B. Description of Work: 1. The extent of site clearing is shown on the drawings.

Section SITE CLEARING. B. Description of Work: 1. The extent of site clearing is shown on the drawings. Section 02110 SITE CLEARING 1.00 General: A. Related Documents: The general provisions of the Contract including General and Supplementary Conditions and General Requirements, apply to the work specified

More information

TOWN OF ATHERTON. Tree Preservation Guidelines. Standards and Specifications

TOWN OF ATHERTON. Tree Preservation Guidelines. Standards and Specifications TOWN OF ATHERTON Tree Preservation Guidelines Standards and Specifications February 2004 TOWN OF ATHERTON TREE PRESERVATION GUIDELINES STANDARDS AND SPECIFICATIONS SECTION 1.00 DEFINITIONS For the purpose

More information

DUKE UNIVERSITY DESIGN GUIDELINES

DUKE UNIVERSITY DESIGN GUIDELINES 1 Tree Protection Zones (TPZs) 1. Introduction A. Tree Protection Zones shall be established around all trees not slated for removal which are located within the construction envelope, or located within

More information

Main Campus Urban Forest and Landscape Management Policy

Main Campus Urban Forest and Landscape Management Policy Main Campus Urban Forest and Landscape Management Policy Policy Statement: Clemson University is committed to providing a safe, attractive, educational and sustainable campus urban forest that faculty,

More information

ISA Certified Arborist PN-6545A PO Box ISA Tree Risk Assessment Qualified Lake Forest Park, WA WA. Business #

ISA Certified Arborist PN-6545A PO Box ISA Tree Risk Assessment Qualified Lake Forest Park, WA WA. Business # Michael A. Woodbury Consulting Arborist 206-659-4288 pnrc@comcast.net ISA Certified Arborist PN-6545A PO Box 55162 ISA Tree Risk Assessment Qualified Lake Forest Park, WA 98155 WA. Business #602218294

More information

TREE PROTECTION/PRESERVATION POLICY

TREE PROTECTION/PRESERVATION POLICY TREE PROTECTION/PRESERVATION POLICY THE CORPORATION OF THE TOWN OF AURORA PARKS AND RECREATION SERVICES 100 John West Way, Aurora, Ontario, L4G-6J1 T.905-727-3123 F.905-727-3903 www.aurora.ca JUNE 2015

More information

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 311000 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

Village of Glen Ellyn TREE PRESERVATION GUIDELINES

Village of Glen Ellyn TREE PRESERVATION GUIDELINES Village of Glen Ellyn TREE PRESERVATION GUIDELINES TREE PRESERVATION PLAN APPLICATION REQUIREMENTS It is important that you become familiar with the requirements in Village Code Title 8, Chapter 4, and

More information

Muhlenberg College Tree Plan

Muhlenberg College Tree Plan Muhlenberg College Tree Plan 2014 1) Purpose: The purpose of the Muhlenberg College Tree Care Plan is to identify the policies, procedures, and practices that are to be used in establishing, protecting,

More information

#2 Report replaces report #1 Revised plans received March 25, 2009 Report completed April 15, 2009

#2 Report replaces report #1 Revised plans received March 25, 2009 Report completed April 15, 2009 Community Development Department City of Saratoga 13777 Fruitvale Avenue Saratoga, California 95070 ARBORIST REPORT It is the responsibility of the owner, architect and contractor to be familiar with the

More information

DESIGNING FOR MANDATORY TREE PROTECTION DURING CONSTRUC TION

DESIGNING FOR MANDATORY TREE PROTECTION DURING CONSTRUC TION DESIGNING FOR MANDATORY TREE PROTECTION DURING CONSTRUC TION City of Santa Monica Community Maintenance Department Public Landscape Division 2600 Ocean Park Blvd. Santa Moni ca, CA 90405 (310) 458-8974

More information

SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS

SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS Section Page 13-1 GENERAL... 13.1 13-1.01 Preservation of Property... 13.1 13-1.02 Overloading, Pavement Protection & Repair... 13.1 13-2 REMOVING EXISTING

More information

SECTION UNCLASSIFIED EXCAVATION AND GRADING

SECTION UNCLASSIFIED EXCAVATION AND GRADING SECTION 02210 UNCLASSIFIED EXCAVATION AND GRADING PART 1 GENERAL 1.1 DESCRIPTION Work in this section includes the excavation, undercut excavating, grading, earthwork and compaction required as shown on

More information

CONSTRUCTION SPECIFICATION

CONSTRUCTION SPECIFICATION CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES C212 CONSTRUCTION SPECIFICATION CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES C212 ISSUE: NO:3 July 2018 TABLE OF CONTENTS CLAUSE CONTENTS PAGE GENERAL... 2 C212.01

More information

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 300 EARTHWORK, GRADING, AND GRAVELING

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 300 EARTHWORK, GRADING, AND GRAVELING STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 300 EARTHWORK, GRADING, AND GRAVELING Section Number Title 301 GENERAL 302 MATERIALS SPECIFICATIONS 303 CLEARING

More information

SECTION PROTECTION AND RESTORATION OF EXISTING FACILITIES

SECTION PROTECTION AND RESTORATION OF EXISTING FACILITIES PART 1 - GENERAL 1.1 GENERAL A. The CONTRACTOR shall protect all existing utilities and improvements not designated for removal and shall restore damaged or temporarily relocated utilities and improvements

More information

SECTION EARTHWORK; EXCAVATION, FILLING AND GRADING. A. Excavating soil and other material for surface improvements.

SECTION EARTHWORK; EXCAVATION, FILLING AND GRADING. A. Excavating soil and other material for surface improvements. SECTION 31 20 00 PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating soil and other material for surface improvements. B. Excavating soil and other material for drainage basins. C. Placing fill. D. Compaction

More information

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum Page 1 of 6 DESIGN STANDARDS FOR: MEASUREMENT AND PAYMENT Where bids are utilities for construction, repair or alteration for Public Work park projects, the following bid item descriptions and units of

More information

SECTION 10 - ENVIRONMENTAL CONTROLS AT WORK SITE TABLE OF CONTENTS

SECTION 10 - ENVIRONMENTAL CONTROLS AT WORK SITE TABLE OF CONTENTS SECTION 10 - ENVIRONMENTAL CONTROLS AT WORK SITE TABLE OF CONTENTS Section Page 10-1 DUST CONTROL...10.1 10-2 AIR POLLUTION CONTROL...10.1 10-3 BURNING...10.1 10-4 EROSION, SEDIMENT, AND WATER POLLUTION

More information

SECTION MAINTENANCE OF EXISTING CONDITIONS

SECTION MAINTENANCE OF EXISTING CONDITIONS SECTION 02 01 00 MAINTENANCE OF EXISTING CONDITIONS PART 1 GENERAL 1.1 GENERAL A. The CONTRACTOR shall protect all existing utilities and improvements not designated for removal and shall restore damaged

More information

B. Base Course: Aggregate layer placed between the subbase course and hot-mix asphalt paving.

B. Base Course: Aggregate layer placed between the subbase course and hot-mix asphalt paving. SECTION 312000 - EARTH MOVING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Excavating and filling for rough grading the Site. 2. Preparing subgrades for walks, curbs, pavements, and turf and grasses.

More information

EXCAVATION WORK IN PUBLIC RIGHT-OF-WAY GENERAL NOTES

EXCAVATION WORK IN PUBLIC RIGHT-OF-WAY GENERAL NOTES CITY OF SANTA MONICA Department of Public Works Civil Engineering Division 1685 Main, Room 116 Santa Monica, CA 90401 Tel: (310) 458-2240 or (310) 458-8737 EXCAVATION WORK IN PUBLIC RIGHT-OF-WAY GENERAL

More information

SECTION 1 GENERAL NOTES

SECTION 1 GENERAL NOTES ISSUE DATE NOVEMBER 1st, 2011 SECTION 1 Page List Page Number Page Title COVER COVER GN-01 PAGE 1 GN-02 PAGE 2 GN-03 PAGE 3 GN-04 PAGE 4 GN-05 PAGE 5 GN-06 PAGE 6 GN-07 PAGE 7 : 1. (CCU) STANDARD SPECIFICATIONS

More information

SECTION EXCAVATION AND FILL

SECTION EXCAVATION AND FILL SECTION 02315 EXCAVATION AND FILL PART 1 GENERAL 1.01 SUMMARY A. Furnish labor, materials, equipment, and incidentals necessary to perform excavation, backfill, grading, and slope protection required to

More information

City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV (775) (775) FAX

City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV (775) (775) FAX City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV 89505 (775) 334-3304 (775) 334-1226 FAX SPECIAL CONDITIONS OF APPROVAL FOR Permit # EAE14-00XXX Applicant: Job Description:

More information

SECTION 10 - ENVIRONMENTAL CONTROLS AT WORK SITE TABLE OF CONTENTS

SECTION 10 - ENVIRONMENTAL CONTROLS AT WORK SITE TABLE OF CONTENTS SECTION 10 - ENVIRONMENTAL CONTROLS AT WORK SITE TABLE OF CONTENTS Section Page 10-1 DUST CONTROL... 10.1 10-2 AIR POLLUTION CONTROL... 10.1 10-3 BURNING... 10.1 10-4 EROSION, SEDIMENT, AND WATER POLLUTION

More information

Maintaining a Walkable Sacramento: SIDEWALK MAINTENANCE PROGRAM HANDBOOK

Maintaining a Walkable Sacramento: SIDEWALK MAINTENANCE PROGRAM HANDBOOK Maintaining a Walkable Sacramento: SIDEWALK MAINTENANCE PROGRAM HANDBOOK Well-maintained sidewalks and curb ramps provide safe and desirable paths for pedestrians and others to enjoy neighborhoods, commercial

More information

Top 10 Recommendations for Preserving Trees - a Public Works View

Top 10 Recommendations for Preserving Trees - a Public Works View Hold the Chainsaw: Preserving Existing Trees in Urban Corridors and Sites Peg Staeheli, ASLA, LEED AP 2008 APWA International Public Works Congress and Exposition - August 18, 2008 Top 10 Recommendations

More information

EXCAVATION, TRENCHING & BACKFILLING..1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto.

EXCAVATION, TRENCHING & BACKFILLING..1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto. CITY OF BRAMPTON LANDSCAPE SPECIFICATIONS SECTION 02315-1 PART 1 GENERAL 1.1 Description of Work.1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto. 1.2 Related

More information

SECTION EROSION CONTROL DEVICES

SECTION EROSION CONTROL DEVICES SECTION 02374 PART 1 GENERAL EROSION CONTROL DEVICES 1.1 SUMMARY A. Section Includes: 1. Diversion Channels. 2. Rock Energy Dissipator. 3. Paved Energy Dissipator. 4. Rock Basin. 5. Rock Barriers. 6. Sediment

More information

University of Maryland - College Park Tree Management Plan 2017

University of Maryland - College Park Tree Management Plan 2017 University of Maryland - College Park Tree Management Plan 2017 1 Page I. Purpose and Objective The University of Maryland College Park has over 15,000 plants currently recorded in its GIS based inventory.

More information

Landscape Services QA/QC Manual Sample Selected pages (not a complete plan)

Landscape Services QA/QC Manual Sample Selected pages (not a complete plan) Landscape Services QA/QC Manual Sample Selected pages (not a complete plan) Reporting Forms Inspection Forms Contact: Ed Caldeira 410-451-8006 Pat [Pick the date] [CompanyName] Landscape Services Operating

More information

SPECIAL SPECIFICATION 3504 Septic Tank System

SPECIAL SPECIFICATION 3504 Septic Tank System 1993 Specifications CSJ s 3136-01-126, etc. & 0683-01-070, etc. SPECIAL SPECIFICATION 3504 Septic Tank System 1. Description. This Item shall govern for all materials, equipment and labor necessary for

More information

Standing Permit for Repair by Utility Providers

Standing Permit for Repair by Utility Providers City of Stevens Point Department of Parks, Recreation, and Forestry 2442 Sims Ave., Stevens Point, WI 54481, Phone (715) 346-1532 Fax (715) 346-1582 Standing Permit for Repair by Utility Providers Any

More information

St. Monica Food Pantry Construction Waste Management and Disposal SBA-13105

St. Monica Food Pantry Construction Waste Management and Disposal SBA-13105 St. Monica Food Pantry 01 7419-1 SECTION 01 7419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL PART 1 - GENERAL 1.1 SUMMARY: A. Work of this section includes administrative and procedural requirements for

More information

DOCUMENT CONSTRUCTION WASTE MANAGEMENT

DOCUMENT CONSTRUCTION WASTE MANAGEMENT DOCUMENT 01 50 13 PART 1 - GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS: All Contract Documents should be reviewed for applicable provisions related to the provisions in this document, including without

More information

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING PART 1 GENERAL SECTION 02221 TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING 1.01 SECTION INCLUDES A. Excavation, dewatering and backfilling with compaction of trenches for pipes, conduits, channels

More information

ITEM 706 PIPE SLOPE DRAIN

ITEM 706 PIPE SLOPE DRAIN AFTER NOVEMBER 1, 2008 ITEM 706 PIPE SLOPE DRAIN 706.1 Description. This work shall consist of the installation of temporary erosion protection and sediment control pipe slope drains, utilized during construction

More information

Base Course Design and Construction

Base Course Design and Construction Part I General A. This information is to be used as a guideline in construction a dynamic aggregate base and drainage system. Project conditions may vary based on overall scope of work and location. Any

More information

Copyright 2014 Urban Tree Foundation

Copyright 2014 Urban Tree Foundation 015639 DISCLAIMER AND RESPONSIBILITY OF THE USER Use of this document: The following specification has been prepared by the Urban Tree Foundation and is copyrighted 2014. Permission is granted for use

More information

EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY

EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY 31 25 00 EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY A. Erosion and sedimentation control shall be provided by the Contractor for all areas of the site denuded or otherwise disturbed

More information

SECTION CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL. A. This Section includes administrative and procedural requirements for the following:

SECTION CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL. A. This Section includes administrative and procedural requirements for the following: SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

Tree Protection Standards

Tree Protection Standards Tree Protection Standards 010000S02 Tree Protection Standards Article 56 is in addition to, and takes precedence over the provisions of the Special Conditions for the Project. ARTICLE 56 PART 1 GENERAL

More information

SECTION EROSION AND SEDIMENTATION CONTROLS

SECTION EROSION AND SEDIMENTATION CONTROLS SECTION 312500 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 01 - GENERAL REQUIREMENTS which are hereby made

More information

SECTION CONSTRUCTION WASTE MANAGEMENT. 1. Section Sustainable Project Requirements. 2. Section Temporary Facilities and Controls.

SECTION CONSTRUCTION WASTE MANAGEMENT. 1. Section Sustainable Project Requirements. 2. Section Temporary Facilities and Controls. Buchtel/Perldns Community Learning Center GPD 2007271.15 OSFC Project # 55-7110-9029425 Phase 3 CLC Package Bidding Documents July 1, 2010 PART 1- GENERAL 1.1 SUMMARY SECTION 01524 CONSTRUCTION WASTE MANAGEMENT

More information

DEPARTMENT OF TRANSPORTION ENVIRONMENTAL PROTECTION AGENCY OCCUPATIONAL SAFETY AND HEALTH ACT

DEPARTMENT OF TRANSPORTION ENVIRONMENTAL PROTECTION AGENCY OCCUPATIONAL SAFETY AND HEALTH ACT Page 6 of 15 1.0 GENERAL REQUIREMENTS: 1.1 SCOPE OF WORK: Work includes, but is not limited to, providing all labor, materials, equipment, tools, and services required to provide full professional landscape

More information

Tree Preservation and Protection (Effective May 1, 2003)

Tree Preservation and Protection (Effective May 1, 2003) Tree Preservation and Protection (Effective May 1, 2003) Village of Northfield 361 Happ Road Northfield, IL 60093 Phone: (847) 446-9200 Fax: (847) 446-4670 Section 10-13. Tree Preservation and Protection.

More information

TITLE 2 BOARDS AND COMMISSIONS, ETC. CHAPTER 1 TREE BOARD

TITLE 2 BOARDS AND COMMISSIONS, ETC. CHAPTER 1 TREE BOARD 2-1 CHAPTER 1. TREE BOARD. TITLE 2 BOARDS AND COMMISSIONS, ETC. CHAPTER 1 TREE BOARD SECTION 2-101. Purpose. 2-102. Definitions. 2-103. Creation of a tree board. 2-104. Operation. 2-105. Duties and responsibilities.

More information

DEPARTMENT OF TRANSPORTION ENVIRONMENTAL PROTECTION AGENCY OCCUPATIONAL SAFETY AND HEALTH ACT

DEPARTMENT OF TRANSPORTION ENVIRONMENTAL PROTECTION AGENCY OCCUPATIONAL SAFETY AND HEALTH ACT GENERAL REQUIREMENTS: SCOPE OF WORK: Work includes, but is not limited to, providing all labor, materials, equipment, tools, and services required to provide full professional landscape maintenance, on

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

1. Division 01 Section General Requirements Temporary Facilities and Controls.

1. Division 01 Section General Requirements Temporary Facilities and Controls. PAGE 024210-1 SECTION 024210 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification sections,

More information

SECTION B PART 5 TREE PLANTING AND PROTECTION GUIDELINES (TPP)

SECTION B PART 5 TREE PLANTING AND PROTECTION GUIDELINES (TPP) SECTION B PART 5 TREE PLANTING AND PROTECTION STANDARD CONTRACT DOCUMENTS FOR MUNICIPAL CONSTRUCTION PROJECTS 2018 EDITION 220 1.0 CONSTRUCTION SPECIFICATION AND DESCRIPTION FOR STRUCTURAL SOIL 1.1 GENERAL

More information

CITY OF TACOMA ENVIRONMENTAL SERVICES DEPARTMENT

CITY OF TACOMA ENVIRONMENTAL SERVICES DEPARTMENT Form No. SPEC-220A Revised: 07/30/2015 CITY OF TACOMA ENVIRONMENTAL SERVICES DEPARTMENT ADDENDUM NO.1 DATE: 12/11/17 REVISIONS TO: Request for Bids Specification No. ES17-0237F TREE REMOVAL, PRUNING, AND

More information

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 01 GENERAL REQUIREMENTS SECTION CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 01 GENERAL REQUIREMENTS SECTION CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL PART 1 - GENERAL 1.1 SUMMARY A. This Section includes administrative and procedural requirements for the following: 1. Salvaging non-hazardous

More information

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS SECTION 01 00 00 GENERAL REQUIREMENTS PART 1 - GENERAL 1.1 SECTION INCLUDES A. Summary of Work: 1. General 2. Contract. B. Contract Considerations: 1. Schedule of values. 2. Applications for payment. 3.

More information

SECTION BORING AND/OR JACKING PIPE

SECTION BORING AND/OR JACKING PIPE 02910-1 of 6 SECTION 02910 BORING AND/OR JACKING PIPE 02910.01 GENERAL A. Description Boring and/or jacking pipe shall include, but not necessarily be limited to, furnishing and installing carrier pipe

More information

City of Reno Public Works

City of Reno Public Works City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV 89505 (775) 334-3304 (775) 334-1226 FAX SPECIAL CONDITIONS OF APPROVAL FOR Permit # EAE11-00XXX Applicant: Job Description:

More information

SECTION GENERAL EXCAVATION

SECTION GENERAL EXCAVATION 02210-1 of 11 SECTION 02210 GENERAL EXCAVATION 02210.01 GENERAL A. Description 1. General excavation shall include but not necessarily be limited to, excavation and grading for general site work, roadways,

More information

TREE RETENTION AND PROTECTION SPECIFICATIONS

TREE RETENTION AND PROTECTION SPECIFICATIONS DENVER PARKS AND RECREATION OFFICE OF THE CITY FORESTER UPDATED JULY 2015 SECTION 01 56 39 SPECIFICATIONS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Contract Drawings and general provisions of the Contract,

More information

EBAY SOUTH CAMPUS MAIN STREET MULTI-PURPOSE BUILDING PROJECT

EBAY SOUTH CAMPUS MAIN STREET MULTI-PURPOSE BUILDING PROJECT MITIGATION MONITORING AND REPORTING PROGRAM EBAY SOUTH CAMPUS MAIN STREET MULTI-PURPOSE BUILDING PROJECT File Nos. PDC15-030, PD15-026 September 2015 PREFACE Section 21081.6 of the California Environmental

More information

SANBORN COUNTY

SANBORN COUNTY Sheet 1 of 12 SPECIFICATIONS ESTIMATE OF QUANTITIES BID ITEM NUMBER ITEM QUANTITY UNIT 009E0010 Mobilization Lump Sum LS 110E0500 Remove Pipe Culvert 134 Ft 110E1010 Remove Asphalt Concrete Pavement 178

More information

DOCUMENT ADDENDA AND MODIFICATIONS

DOCUMENT ADDENDA AND MODIFICATIONS DOCUMENT ADDENDA AND MODIFICATIONS PART 1 1.1 PROCEDURE GENERAL A. For filing purposes, add Addenda and Modifications to the Contract Documents following this page. Modified June 20, 2017 Addenda and Modifications

More information

DIVISION 2- EXISTING CONDITIONS

DIVISION 2- EXISTING CONDITIONS DIVISION 2- EXISTING CONDITIONS 024100- SELECTIVE DEMOLITION PART 1 - GENERAL: 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

B. Borrow: Satisfactory soil imported from off-site for use as fill or backfill.

B. Borrow: Satisfactory soil imported from off-site for use as fill or backfill. SECTION 312000- EARTHWORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Special Conditions, apply to this Section. 1.2 SUMMARY This Section

More information

TREE PROTECTION (no.) CODE 990

TREE PROTECTION (no.) CODE 990 NATURAL RESOURCES CONSERVATION SERVICE ILLINOIS URBAN MANUAL PRACTICE STANDARD TREE PROTECTION (no.) CODE 990 (Source: IN Drainage Handbook) DEFINITION The protection of individual trees from damage during

More information

1. Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1. Section Temporary Facilities and Controls for limitations and procedures governing temporary use of Owner's facilities. SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

City of Provo Forestry Division Arboricultural Standards and Specifications Appendix to Provo City Ordinance, Chapter 9.20

City of Provo Forestry Division Arboricultural Standards and Specifications Appendix to Provo City Ordinance, Chapter 9.20 City of Provo Forestry Division Arboricultural Standards and Specifications Appendix to Provo City Ordinance, Chapter 9.20 1 TABLE OF CONTENTS Foreword 3 Section 1. Areas of Responsibility.. 4 Purpose

More information

PAVING SLABS ON AGGREGATE BED FOR ROOF PLAZA DECKS

PAVING SLABS ON AGGREGATE BED FOR ROOF PLAZA DECKS SECTION 32 14 13.16 PAVING SLABS ON AGGREGATE BED FOR ROOF PLAZA DECKS (1995 MasterFormat Section 02784) Note: This guide specification for the U.S. is for paving slabs used as ballast and/or paving on

More information

DSC BUILDING 1200 ALTERATIONS OCTOBER 2011 SECTION CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

DSC BUILDING 1200 ALTERATIONS OCTOBER 2011 SECTION CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements for the following: 1. Salvaging nonhazardous demolition

More information

Gainesville Technical Center 5399 Wellington Branch Drive Gainesville VA Phone (703)

Gainesville Technical Center 5399 Wellington Branch Drive Gainesville VA Phone (703) Gainesville Technical Center 5399 Wellington Branch Drive Gainesville VA 20155 Phone (703) 754-6750 Work Request # UNDERGROUND DISTRIBUTION FACILITIES AGREEMENT (FOR COMMERCIAL CUSTOMER) Developer/Builder/Owner

More information

Table of Contents 3-6-A AGGREGATES A-1 SOURCES OF MATERIALS 3-6-A-2 TESTING 3-6-A-3 APPROVAL AND INSPECTION 3-6-A-4 STORAGE

Table of Contents 3-6-A AGGREGATES A-1 SOURCES OF MATERIALS 3-6-A-2 TESTING 3-6-A-3 APPROVAL AND INSPECTION 3-6-A-4 STORAGE Table of Contents Page 3-1-A EARTHWORK (GENERAL). ERROR! BOOKMARK NOT DEFINED. 3-1-A-1 DESCRIPTION 3-1-A-2 GENERAL REQUIREMENTS... II... II 3-1-A-2-1 Clearing & Grubbing... iii 3-1-A-2-1-1 Description...

More information

Arborist Report & Tree Preservation Plan. 231 Cobourg Street Ottawa, ON K1N 8J2

Arborist Report & Tree Preservation Plan. 231 Cobourg Street Ottawa, ON K1N 8J2 Arborist Report & Tree Preservation Plan 231 Cobourg Street Ottawa, ON K1N 8J2 Prepared for: Mr. Judah Mulalu Ten 2 Four Architecture Inc. 55 Eglinton Avenue East, Suite 606C Toronto, ON. M4P 1G8 Judah@ten24architecture.com

More information

SECTION TRENCHING

SECTION TRENCHING SECTION 31 23 17 TRENCHING PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Excavating trenches for utilities and utility structures. 2. Bedding. 3. Backfilling and compacting to subgrade elevations.

More information

PRESERVING + PROTECTING VEGETATION DURING CONSTRUCTION

PRESERVING + PROTECTING VEGETATION DURING CONSTRUCTION PRESERVING + PROTECTING VEGETATION DURING CONSTRUCTION Preserving native vegetation on your property during construction is a smart and cost-effective alternative to completely clearing your land and having

More information

CITY OF AUBURN STANDARD SPECIFICATIONS SECTION 13 EXCAVATION AND BACKFILL

CITY OF AUBURN STANDARD SPECIFICATIONS SECTION 13 EXCAVATION AND BACKFILL CITY OF AUBURN STANDARD SPECIFICATIONS SECTION 13 EXCAVATION AND BACKFILL 13.01 GENERAL The work included in this section shall consist of furnishing all materials and equipment and performing all labor

More information

MITIGATION MONITORING AND REPORTING PROGRAM

MITIGATION MONITORING AND REPORTING PROGRAM SACRAMENTO COUNTY DEPARTMENT OF ENVIRONMENTAL REVIEW AND ASSESSMENT MITIGATION MONITORING AND REPORTING PROGRAM CONTROL NUMBER: 07-70313 NAME: Clairidge Way Storm Drain Improvement Project LOCATION: The

More information

DECLARATION OF COVENANTS, CONDITIONS AND RESTRICTIONS RADIANT LAKE ESTATES SUPPLEMENTAL ARCHITECTURAL GUIDELINES ARTICLE I INTRODUCTION AND POLICY

DECLARATION OF COVENANTS, CONDITIONS AND RESTRICTIONS RADIANT LAKE ESTATES SUPPLEMENTAL ARCHITECTURAL GUIDELINES ARTICLE I INTRODUCTION AND POLICY DECLARATION OF COVENANTS, CONDITIONS AND RESTRICTIONS RADIANT LAKE ESTATES SUPPLEMENTAL ARCHITECTURAL GUIDELINES ARTICLE I INTRODUCTION AND POLICY SECTION 1.1. Pursuant to the Declaration of Covenants,

More information

DESIGN & CONSTRUCTION GUIDELINES

DESIGN & CONSTRUCTION GUIDELINES FACILITIES MANAGEMENT DESIGN & CONSTRUCTION EDITION: SEPTEMBER 17, 2018 4202 E. FOWLER AVENUE, OPM 100 TAMPA, FLORIDA 33620-7550 PHONE: (813) 974-2845 WEBSITE: usf.edu/fm-dc DESIGN & CONSTRUCTION GUIDELINES

More information

MODEL SPECIFICATIONS: Hydraulically Driven Steel Underpinning Pile Specifications

MODEL SPECIFICATIONS: Hydraulically Driven Steel Underpinning Pile Specifications MODEL SPECIFICATIONS: Hydraulically Driven Steel Underpinning Pile Specifications Mar/2008 v1.0 SECTION 02255 HYDRAULICLY DRIVEN STEEL UNDERPINNING PILES PART 1 GENERAL 1.01 SCOPE OF WORK The work shall

More information

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

STANDARD SPECIFICATIONS SECTION PAVEMENT REQUIREMENTS

STANDARD SPECIFICATIONS SECTION PAVEMENT REQUIREMENTS STANDARD SPECIFICATIONS SECTION 02950 PAVEMENT REQUIREMENTS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for removing, replacing and providing new paving for roads, driveways, parking

More information

SECTION EROSION AND SEDIMENTATION CONTROL

SECTION EROSION AND SEDIMENTATION CONTROL SECTION 02160 EROSION AND SEDIMENTATION CONTROL PART 1 GENERAL 1.1 RELATED DOCUMENTS A. The Contractor shall be held to have read all Bidding Requirements; all of the General Conditions and Supplementary

More information

CITY OF NAPERVILLE, ILLINOIS TREE REMOVAL PERMIT APPLICATION LOCATION: PROJECT CONTACT: VARIETY NUMBER SIZE CONDITION

CITY OF NAPERVILLE, ILLINOIS TREE REMOVAL PERMIT APPLICATION LOCATION: PROJECT CONTACT: VARIETY NUMBER SIZE CONDITION CITY OF NAPERVILLE, ILLINOIS TREE REMOVAL PERMIT APPLICATION NAME ADDRESS _ CITY ZIP PHONE Residence Business Fax Please indicate all trees to be removed: DATE PROJECT: LOCATION: PROJECT CONTACT: VARIETY

More information

CITY OF TROY CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587

CITY OF TROY CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587 CITY OF TROY DESIGN STANDARDS AND CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587 JANUARY 2010 TABLE OF CONTENTS SECTION 1 SECTION 2 SECTION 3 SECTION 4 SECTION 5 SECTION 6 APPENDIX ROADWAY DESIGN DRAINAGE

More information

SECTION CHEMICAL TERMITE CONTROL 11/14

SECTION CHEMICAL TERMITE CONTROL 11/14 SECTION 31 31 16.13 CHEMICAL TERMITE CONTROL 11/14 PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred

More information

C. Foundation stabilization for pipe and utility structures.

C. Foundation stabilization for pipe and utility structures. PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization

More information

SECTION 12 - CONSTRUCTION AREA TRAFFIC CONTROL TABLE OF CONTENTS

SECTION 12 - CONSTRUCTION AREA TRAFFIC CONTROL TABLE OF CONTENTS SECTION 12 - CONSTRUCTION AREA TRAFFIC CONTROL TABLE OF CONTENTS Section Page 12-1 GENERAL... 12.1 12-2 FLAGGING... 12.1 12-2.01 Flaggers... 12.1 12-2.02 Flagging Costs... 12.1 12-3 TRAFFIC-HANDLING EQUIPMENT

More information

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL Section 300 General Summary All projects constructed within the Town of Essex shall be constructed in strict accordance with

More information