1 Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited smi.investment.limited@gmail.com Date : January, 2017

2 Executive Summary The Monthly Progress Report is prepared for providing information about the progress of Sano Milti Khola Hydropower Project, Ramechhap (3 MW). It will contain the information about the project activities and achievement of the preceding month along with the work plan for the particular month. This report will be issued in the first week of every month. Major project activities will be highlighted.

3 1.0 Background The Sano Milti Khola Small Hydroelectric Project (3 MW) is run-off-river type hydropower project proposed along the Sano Milti Khola in Ramechhap and Dolkha District of Janakpur Zone. The project area lies within Fulasi VDC of Ramechhap district and Melung VDC of Dolkha District. Sano Milti Khola Hydropower Ltd. holds the survey license for this project. The boundary co-ordinates of the project are E to E and N to N. Sano Milti Khola Hydroelectric Project has been promoted by SM Investment Ltd (SMI). SMI is basically a collective effort of Nepalese in South Korea to invest in Sano Milti Khola Small Hydroelectric Project. 2.0 Project Development Milestones S No Date Milestone /04/28 BS Survey License Issued in the name of Mr Ram Bdr Tamang /03/07 BS DoED extended the Date of Survey License of 3000 kw in the name of Sano Milti Khola Hydropower Pvt. Ltd upto 2071/02/25 BS /01/05 BS Ministry of Energy approved the ToR of Sano Milti Khola Hydropower Project /05/05 BS DoED extended the date of Survey License up to 2072/02/25 BS /02/24 BS Ministry of Energy approved the IEE Report and at the same day the approved IEE Report was submitted in DoED /02/24 BS Registered application to obtain Generation License /03/10 BS Grid Connection Agreement with NEA /01/13 BS Power Purchase Agreement with Power Trade Department/NEA /02/09 Agreement with Thodung/Waiba & Lama JV for Civil Construction Works /07/01 Generation License Issued by Department of Electricity Development

4 3.0 Project Description 3.1 Location & Access The project site is about 175 km away from Kathmandu, the capital city of Nepal. Manthali, the nearest trade center or town is about 22 km away towards south from the project site. Another nearest town is Charikot which is about 37 km away towards north. The powerhouse site of the project is 3 km far from the Milti Dobhan accessible by the graveled road Charikot Kirnetar Manthali Road. The proposed intake site is located on Milti Khola at about 6 km upstream from the confluence of Milti Khola and Tamakoshi River at the boundary of Melun and Phulasi VDC. The forebay location at Aimantar Village can be reached by constructing about 4.5 km road section from Milti Dobhan. Similarly, the headworks site can be made accessible by excavating about 3 km long track along the Milti Khola from the Milti Dobhan.

5 3.2 Project Layout Map Project Layout Plan

6 3.3 General Features of the Project Name of River : Sano Milti Khola Nearest Town : Manthali of Scheme : Run-of-River Gross Head : 216m Net Rated Head : Installed Capacity : 3.0 MW Average Annual Energy after Outage : GWh 1. Hydrology Catchment Area Mean Annual Discharge Design Discharge (at Q40 PoE) Riparian Release Design Flood Discharge Average Annual Precipitation 2. Diversion Weir of Weir Length of Weir Crest Elevation : 55 km2 : 2.17 m3/s : 1.7 m3/s : 0.09m3/sec : 277m3/sec (100 yr. flood) : 1650mm : Concrete Weir : 26 m : El m 3. Intake Structure : Side intake Size : (1.50 m x 0.80 m) Nos : 2 (Two) 4. Gravel Flushing structure Length Size (Depth) Width Nos : Surface, rectangular type : 11 m : 1.3 m to 2.50 m : 1.60 m : 2 (Two) 5. Desanding Basin : Surface, rectangular type, Concrete No. of Bays : Double Length : 29 m Wide : 3.50 m Total Depth (Including Hopper) : 2.21 to 3.15 Particle size to be settled : 0.20 mm :

7 6. Headrace Canal Length Wide Height : Concrete (Rectangular) : 2191 m : 1.50 m : 1.0 m 7. Forebay Surface Area : 153 m 2 (Length 17 m x Width 4 m) Volume : m 3 Bed Level : m Gate : Sluice Gate 8. Penstock Pipe : Steel Total Length : m Diameter : 0.90 m Material/Thickness : Structural Steel, 10 mm to 18 mm Bifurcation Length : 9.0 m m Bifurcation Diameter : 0.70m 9. Powerhouse Size (L x W) Height Turbine Axis Level 10. Tailrace Section Total length Size Tail Water Level : Surface : 32 m x 14 m : m : m : RCC Structure (Buried) : Rectangular : m : 0.85 m x 2.0 m : m 11. Turbine : Horizontal Axis Pelton No of unit : 2 (Two) Rated Output Capacity Per unit : 1500 kw Rotational Speed : 750 rpm Efficiency : 88.15% 12. Governor : Electric-electronic Adjustment for Speed Drop : Between 0 to 10%

8 13. Generator : Synchronous, 3 Phase No. of Units : 2 (Two) Rated Output Capacity per Unit : 1700 kva Power Factor : 0.85 Voltage : 6600 V Frequency : 50 Hz. Efficiency : 95% 14. Transformer : Three Phase, Oil Immersed Nos of Units : 2 (Two) Rated Capacity per unit : 1700 kva Voltage Ratio : 11/33 kv Efficiency : 99% 15. Transmission Line Voltage Level Length From To : 33 kv : 5 km : Powerhouse : NEA Kirnetar Substation

9 4.0 Construction Schedule:

10 5. Project Progress 5.1 Coordination with Department of Forest and Ministry of Energy Documents for tree cutting and land leasing have been forwarded to the cabinet which will be approved and forwarded for final agreement with the Department of Forest. 5.2 Meeting with the Banks The Due Diligence Audit of the project has been requested by the bank. Thereby we are collecting proposals from the prequalified consultants for finalization of the DDA. 5.3 Meeting with the Electromechanical Suppliers The proposals of the suppliers are under evaluation for necessary amendment with close coordination with our Technical Consultants. 5.4 Joint Survey/Investigation of Headrace Section Based on the detail joint survey/investigation of the headrace section, analysis and necessary medication of the detail design are being finalized by our consultants. 5.5 Work Progress at the Site: 1. The maintenance of kulo at chainage has been completed but the kulo maintenance at chainage is still remaining. The maintenance of kulo was hand over to the local people on contract. The contract was made and agreed to complete the work at 20,000 rupees. Out of 20,000, 15,000 have already been given to the responsible person named Bikram of bagarbese.

11 Figure 1: the gabion at chainage 0+310, and filliing area for grade maintenance Figure 2: gabion wall for filling, flood protection at chainage (Guhey Khola)

12 Figure 3: filling done at guhey khola, causeway construction is going on Figure 4: soling at chainage (Shere Kholsi)

13 Figure 5: gabion construction at chainage (Shere Kholsi) Figure 6: gabion construction at chainage

14 Figure 7: gabion wall construction at chainage (Bagar Bese) Figure 8: gabion wall at chainage (Bagar Bese)

15 Figure 9: gabion construction at chainage Figure 10: clearance of kulo at chainage 2+900

16 Figure 11: the gabion construction at chainage The construction of gabion is nearly in a stage of completion. The remaining chainage for gabion construction is at chainage At it is also in stage of completion. Previously we have decided to construct the gabion at chainage but we have postponed the construction of gabion at this chainage for next year(if necessary). 3. The survey of penstock alignment and power house is going to be started from 2073/10/18. And it will be completed approximately after 3-4 days. Figure 12: powerhouse site survey

17 January, 2017

18 Monthly Work Plan February S No Description Feb Remarks Week 1 Week 2 Week 3 Week 4 1 Follow up Tree Cutting Approval Cabinet and Ministry 2 Access Road Works (Support Strucutures) Site Visit 3 Document Revision for Loan Processing (Bank) Assessment/Meeting with Electromechanical Suppliers at Office 4 5 Headrace Section Final Design (Technical Consultant) 6 Audit Report & AGM Date Finalization