Public Private Partnership in Infrastructure projects in India: Lessons learnt and the way forward

Size: px
Start display at page:

Download "Public Private Partnership in Infrastructure projects in India: Lessons learnt and the way forward"

Transcription

1 Public Private Partnership in Infrastructure projects in India: Lessons learnt and the way forward July 2013 Submitted by: Charu Wadhwa Delhi School of Economics Mentored by: Shri Alok Shekhar Private Secretary to Minister of State, External Affairs, Ministry External Affairs Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 1

2 Preface I am Charu Wadhwa, pursuing Masters in Economics from Delhi School of Economics. I am a very passionate, ambitious and a hardworking. Rakshak Foundation is a non-profit organization that researches different public policy issues and creates awareness about them. Rakshak Foundation s initiative to help strengthen the foundations of our society and bolster the confidence of a common man in the system by creating awareness about the issues affecting him is worth appreciating. I chose to participate in this internship program because this Internship is the best platform for me to make my dream come true to work for a better society. I have always been very passionate about contributing towards the society's welfare. My goals and objective matches with Rakshak Foundation's work. This internship is not only a unique research program which will give me and exposure into the real world of policy, society and governance but also an opportunity to know more about social issues and work for long term improvement and try my best to make a positive impact on society. The structure of the Internship is really good as one gets to learn from their peers as well. This internship is helping me grow as an Individual and has given me a golden opportunity to help change the lives of millions of people. This program will give me a chance to work for a better tomorrow It has been a wonderful experience working with Rakshak Foundation so far. I don t think I ever would have got a chance to meet such eminent people personally and discuss with them about the issues affecting the society today. I feel that India today suffers a huge communication gap between the government and the citizens, and this is one of the most fundamental problems of the society. I hope that through this project I would do my bit in reducing this gap. Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 2

3 Acknowledgements I take this opportunity to express my special gratitude and deep regards to my Mentor Shri Alok Shekharji for his guidance and constant encouragement throughout the course of this project. The help and guidance given by him time to time shall carry me a long way in the journey of life on which I am about to embark. I also take this opportunity to express a deep sense of gratitude to Ms. Anna Roy, Director, Department of Financial Services, Ministry of Finance, Government of India, recently nominated as the Director of Corporation Bank representing the Central Government for her cordial support. Shri Praveen Mahto, Director Infrastructure, Planning Commission, for his valuable information and guidance, which helped me in getting a clear picture regarding the present scenario of PPP in India and documentation and rules which are handled by Planning Commission. Mr. Sidharth Kapur, CFO, GMR who helped me a lot in getting a point of view of a private partner in PPP projects in India. I am obliged to my internship coordinators of Rakshak Foundation as well all the fellow interns for the valuable information provided by them. I am grateful to each one of them for their cooperation during the period of my assignment. Lastly, I would like to thank Rakshak foundation for giving me this opportunity without which this assignment wouldn t have been possible. Besides I would also like to thank Mr. Sachin Bansal, Founder and President, Rakshak Foundation, for giving me this opportunity to work on this project and do my bit for the society. Charu Wadhwa Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 3

4 Table of Contents LIST OF FIGURES... III LIST OF TABLES... III LIST OF ABBREVIATIONS... IV EXECUTIVE SUMMARY... V 1. INTRODUCTION BACKGROUND INFORMATION MAIN PROBLEMS, THEIR SCOPE AND IMPACT ON THE SOCIETY GOALS AND OBJECTIVES METHODOLOGY LITERATURE SEARCH MENTOR MEETINGS MEETINGS AND INTERVIEWS CURRENT NGO AND GOVERNMENT EFFORTS PPP CELLS PPPAC UNION CABINET AND COMMITTEES STANDARDIZATION OF BIDDING AND CONCESSION DOCUMENTS THE MODEL CONCESSION AGREEMENT (MCA) INDIA INFRASTRUCTURE FINANCE COMPANY LIMITED (IIFCL) INDIA INFRASTRUCTURE PROJECT DEVELOPMENT FUND (IIPDF) SEVERAL FISCAL AND OTHER INCENTIVES TO ATTRACT PRIVATE INVESTORS TO ROAD PROJECTS NATIONAL PPP CAPACITY BUILDING PROGRAMME Copyright 2013 Rakshak Foundation. All Rights Reserved. Page i

5 3.10 PUBLIC PRIVATE PARTNERSHIP (PREPARATION, PROCUREMENT AND MANAGEMENT) RULES THE DRAFT PUBLIC PRIVATE PARTNERSHIP RULES THE SECRETARIAT FOR INFRASTRUCTURE THE CABINET COMMITTEE ON INFRASTRUCTURE (CCI) THE INITIATIVES IN AIRPORT SECTOR RESULTS AND DISCUSSIONS FINDINGS FROM THEORETICAL READINGS AND LITERATURE SURVEYS FINDING FROM THE MEETINGS AND IMPACT ON THE THEORETICAL FOCUS GAP ANALYSIS RECOMMENDATIONS, SCOPE AND STRATEGY FOR IMPLEMENTATION FUTURE WORK: REFERENCES APPENDIX A Copyright 2013 Rakshak Foundation. All Rights Reserved. Page ii

6 List of Figures Figure 1: Planned year wise Infrastructure spending... 1 Figure 2: The spectrum of PPP agreements... 3 Figure 3: Evolution of PPP in India... 3 Figure 4: PPP projects in India by sector and by value Figure 5: The steps in the public private partnership processs Figure 6: Equity and revenue share of DIAL in JV Figure 7: DIAL s financing of the Project Figure 8: Modernization and restructuring of IGI Airport at Delhi Figure 9: Climb in number and value of PPP projects in India Figure 10: Recommendation Figure 11: Recommendation Figure 12: Recommendation Figure 13: Recommendation Figure 14: Recommendation Figure 15: Recommendation Figure 16: Recommendation Figure 17: Recommendation Figure 18: Recommendation List of Tables Table 1: Sector wise figures of PPP projects... 6 Table 2: The components adopted by DIAL to finance the project cost Table 3: PPP projects Process Management Table 4: Some issues and Recommendations Copyright 2013 Rakshak Foundation. All Rights Reserved. Page iii

7 List of Abbreviations AAI -Airports Authority of India ADF -Airport Development Fee AERA -Airport Economic Regulatory Authority of India ATC -Air Traffic Control DIAL -Delhi International Airport Limited DGCA -Director General of Civil Aviation DPR -Detailed Project Report EGoM -Empowered Group of Ministers GOI -Government of India IGIA -Indira Gandhi International Airport Delhi IIPDF -India Infrastructure Project Development Fund IIFCL -India Infrastructure Finance Company Limited JV -Joint Venture MoCA -Ministry of Civil Aviation MCA -Model Concession Agreement NTBC - The Noida Toll Bridge Company Ltd OMDA -Operation Management and Development Agreement PPP -Public Private Partnership RFP -Request for Proposal RFQ -Request for qualification SOP -Standard Operating Procedure SPV -Special Purpose Vehicle VGF -Viability gap funding Copyright 2013 Rakshak Foundation. All Rights Reserved. Page iv

8 Executive Summary This report deals with the current scenario of PPP projects in India, development till now and the way forward. Infrastructure is one of the most important sectors of the economy right now where huge investment is required so as to increase the growth rate. Private funding of infrastructure has become a mainstay of the government s policy towards infrastructural development. Economic analysis of the PPP contracts and the relevant laws is undertaken to determine their efficiency properties. I have argued that while the governing laws have several desirable and efficiency enhancing features, the enforcement of these laws has been far from satisfactory. Government has taken policy initiatives to address issues relating to regulatory environment. Now more sectors have been opened to private and foreign investment, regulatory institutions are being set up and strengthened, levy of user charges is promoted, fiscal incentives are provided to infrastructure projects, standardized contractual documents including the Model Concession Agreement are introduced and the mechanism for PPPs in the Central sector had been streamlined through setting up of PPPAC and a website exclusively devoted to PPPs has been launched to serve as a virtual market place for PPP projects. To address financing needs of these projects, India Infrastructure Finance Company had been set up and a new Scheme to meet Viability Gap Funding (VGF) of PPP was launched. Government of India now permits FDI in most infrastructure sectors to the extent of 100 per cent. The question was whether the policy incentives have had the intended effect on investors or not. Two main case studies are considered in the report one from the highway sector DND flyway and the second one is from aviation sector Delhi Airport. Reports, Copyright 2013 Rakshak Foundation. All Rights Reserved. Page v

9 documents and studies available are analyzed. It also makes use of information obtained from public authorities involved in the process of privatization and other officials who are aware of ground realities. DND flyway is taken as a benchmark PPP project and analysis of the issues with the project and comparison with the current situation is carried out. Positive experiences in this sector, both from users as well as private investors, provides us the models which could be extended to other sectors as well, including the social sectors and irrigation. The original compulsion to adopt PPPs was resource scarcity. While additional resources were needed to meet India s infrastructure needs, the experience so far had proven that the efficiencies introduced by welldesigned PPPs, rather than resource scarcity, should be the main reason to pursue them. As second case study evaluation of Delhi Airport Project as one of the initial PPP in Airport sector is done by reading the bidding process, various case studies, OMDA (the agreement signed), GMR s website, reports and articles on this project and meeting CFO of GMR, Airport. In a report titled "Implementation of Public Private Partnership, Indira Gandhi International Airport, Delhi" the Comptroller and Auditor General of India (CAG) has found faults in almost every step of implementation of the Public Private Partnership (PPP) model in the brownfield privatization of New Delhi's Indira Gandhi International Airport (IGIA) so analyze was done to find out how true these allegations are. There are a lot of loopholes found and recommendations given to increase efficiency, some of them are as follows: The most important recommendation is that all the projects should be awarded on the basis of Competitive bidding only. DPR should be properly made Copyright 2013 Rakshak Foundation. All Rights Reserved. Page vi

10 Issues related to land acquisition and environment clearances and all should be taken into consideration Broadening of the sources of financing is required for growth of PPP, so policy reforms in capital market are required Concessions should be made tradable by allowing the project developers to exit after delivering on the construction specifications, when the operations are stabilized. To attract global investment funds for infrastructure, India s PPPs need to offer returns comparable to those in other markets, hence there should be active promotion of private participation Use of Model Agreements in airport sector like highways was thought of one solution before this interview but it was found that Model agreements cannot be used as each airport is very different project like Delhi airport is a brownfield project some are Greenfield also the place. Investment everything is different we cannot generalize. The major finding was that Private Players think that keeping PPP project out of purview of RTI act will result in increasing the efficiency as there is more pressure on concessionaire while working because of this clause they need their freedom to work as a private party. So According to Mr. Sidharath Kapur RTI should not apply It was found that the major issue with PPP in India is that it is treated more like a public project so to make it more efficient private players need autonomy. They want government to design proper contract and all clauses and after that just leave it to private player and let them work accordingly. PPP should be kept away from imposition of bureaucratic hurdles So the main essence is mostly policies in place are efficient we need to work on implementation issues and issues relating to environment clearances, land acquisition, fair and competitive bidding process, bureaucratic hurdles. A stable and efficient regulatory frameworks needs to be established. Copyright 2013 Rakshak Foundation. All Rights Reserved. Page vii

11 Copyright 2013 Rakshak Foundation. All Rights Reserved. Page viii

12 1. Introduction 1.1 Background Information Adequate investment in the development of infrastructure is a prerequisite for higher growth, this was also realized in twelfth five year plan. Accordingly projected investment for the Twelfth Plan is Rs. 55,74,663 crore more than twice the investment of Rs. 24,24,277 crore anticipated during the Eleventh Plan. The Twelfth Plan also projected a share of 48 per cent of private investment against per cent anticipated in the Eleventh Plan. But the target is too ambitious for investment in infrastructure due to the limited budgetary allocations, especially in view of the renewed emphasis on social sectors. Source: Twelfth five year plan Figure 1: Planned year wise Infrastructure spending Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 1

13 As a result, the role of private investment in funding infrastructure projects assumes greater significance in meeting the Twelfth Plan targets. The investment strategy of the Government primarily relies on promoting investment through a combination of public and private participation through Public Private Partnerships (PPPs). The Government of India defines a PPP as a partnership between a public sector entity and a private sector entity for the creation and/or management of infrastructure for public purpose for a specified period of time called concession period on commercial terms and in which the private partner has been procured through a transparent and open procurement system. PPPs presented an opportunity to meet India s investment needs that can be translated into a win-win situation for all. PPPs are thus being seen as an important tool for accelerating infrastructure investments, and deal with the infrastructure deficit in the country. Public-private partnerships can take a wide range of forms varying in the degree of involvement of the private player in traditionally public infrastructure. A publicprivate partnership is through a contract or agreement to outline the responsibilities of each party and clearly allocate risk. Below is the graph that depicts the spectrum of PPP agreements. Source: Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 2

14 Figure 2: The spectrum of PPP agreements PPP has evolved over a period of time as can be seen from the following flowchart Phase III Phase I Few notable PPPs could be found as early as 19th century: 1853: The Great Indian Peninsular Railway Company 1874: The Bombay Tramway company's tramway services in Mumbai Early 20th century: PPP models were there in power generation and distribution in Mumbai and Kolkata Phase II Till 2004: Only 86 PPP projects worth INR340 billion were awarded Most of the projects were in bridges and road sector Large scale private financing has been limited to Vishakapatnam and tirupur Increasing acceptance of PPP reforms and innovative PPP structures July 2011: Growth in PPP from 450 projects costing INR 2,242 billion in November, 2009 to 758 PPP projects costing INR3,833 billion in 2011 Figure 3: Evolution of PPP in India Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 3

15 It is recognized that bottlenecks in Infrastructure has been a matter of concern in India as it acts as a barrier in its way of robust pace of economic growth. The level of investments in infrastructure has to be increased to achieve the targeted economic growth. While many advanced economies and fiscal constrained developing countries have developed their physical infrastructure successfully, in India, private participation in the process of infrastructure development has received lackluster response. There was a pressure to change the standard model of public procurement due to high level of public debt, which rapidly increased during the macroeconomic crisis of the 1970s and 1980s. The country initiated the process of partnering with the private sector in 1991, beginning with the power sector, and since then achieved notable successes in telecom, roads, ports and airports sectors. Infrastructure development in India has largely been in the Government domain. However, recently Government of India and State Government(s) have started focusing in involving the private sector in infrastructure creation under the public private partnership (PPP) framework due to the scarce resources, to fund the infrastructure deficit and fulfill the large investment required for infrastructure development in India. And also because private sector participation add value in the various aspects like innovation, managerial efficiency in the project management process, adoption of better technology in key areas etc. 1 In tenth plan the union government has estimated an investment of $320 billion in the infrastructure. The major infrastructure projects in the Indian state of Maharashtra (more than 50%) are based on the PPP model. In the 2000s, other states such Gujarat, Karnataka, 1 Wikipedia and Infrastructure-Development-Indian html Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 4

16 MP, Tamil Nadu also adopted this model. Sector-wise, the road projects account for about 60% of the total projects in numbers, and 45% in terms of value. Ports come in the second place and account for 10% of the total projects (30% of the total value). Other sectors including power, irrigation, telecommunication, water supply, and airports have gained momentum through the PPPP model. The potential use of PPPs in health and education sectors and e-governance remains largely untapped across India as a whole, though recently there have been some activities in these sectors $225 billion was invested by the private sector in infrastructure between 2007 and 2012, which equivalent to 12% of 2012 GDP, much of it through PPPs. Official figures suggest 758 PPP projects are under way or complete, worth $70 billion. A lot of improvement has taken place, with perhaps only 40% of projects using the standard contract framework that the central government recommends. 2 There are two major data bases that capture the development of PPP projects in India in addition to respective Ministry sources one by the Planning Commission on PPP projects and the other by the World Bank on PPI database. The database lists information on all PPP projects. Development and use of PPPs for delivering infrastructure services has now at least 11 years of presence in India, with the majority of projects coming in the last 5 to 7 years. Policies in favour of attracting private participation as well as innovation with different structures have seen varying degrees of success. Some sectors like road, ports, telecommunications and power, have done very good progress compared to limited success in other sectors. Some specific states and sectors have undertaken far more PPPs than others Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 5

17 Table 1: Sector wise figures of PPP projects Source: Database, PPP in India There are principles that should be kept in mind while developing PPP: 3 A fair and transparent framework needs to be provided to facilitate and encourage PPP mode Ensure that the projects are planned and managed to benefit the users and maximize economic returns of the stakeholders as well. Adopt an efficient, transparent, equitable, consistent and competitive process for selection of private partners Protect the interests of end users, private and public sector entities and other stakeholders. 3 Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 6

18 Encourage efficient delivery of public services by engaging proficient and innovative practices with the utilization of best available skills, knowledge & resources in the private sector. Achieve increased efficiency in the deployment of investments by setting out enabling frameworks for greater private sector participation in building future public assets and ensuring their long-term maintenance. Provide requisite provision in budgets for contingent liabilities for the sponsoring government, in various forms such as, liabilities towards lenders in case of contract termination or minimum revenue guarantees 1.2 Main Problems, their scope and impact on the society India faced a lot challenges like other countries have faced. The initial policy initiatives by the Government however, did not yield the desired results. The failure of PPP initiatives was not surprising. Several constraints hampered the prospects of PPPs, some of them are as follows: Absence of an integrated institutional policy framework for project identification, development and implementation. Coordination failure between various Government agencies involved. Long term finance not easily available Capacity in the public sector and private sector to prepare and implement PPP contracts not adequate and to meet technical and financial requirements of PPPs not adequate Difficult to fulfill both the aims together i.e. Private sector s motivation for profit and public sector s concern for public service Apportion risk in a fair, rational and sustainable way is difficult. Management of the partnership through a tightly framed concession agreement over a period in a rapidly changing environment is not easy Till now there was lack of consensus regarding MCAs (Model Concession Agreement) Absence of standardization of transactional practices and documents Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 7

19 Contractor led bids with little or no Innovation and small ideas sites Delays due to red tape and problems acquiring land are the most endemic issues. Only a quarter of all the projects are on or ahead of schedule One major Concern is the efficiency properties of the contracts and governing PPP projects are long term projects & face several risks such as political, construction, maintenance, commercial and financial risks While the governing laws have several desirable & efficiency enhancing features the, the enforcement of these laws has been not satisfactory Wide and growing gap between the demand and supply of infrastructure The government allows not only gaming with contractual clauses, it is open to renegotiating the contract itself. So, investors can bargain for fiscal and other benefits before and also well after the signing of PPP contracts. The government is ready to bend over backwards to ensure success of ongoing projects, many PPP contracts have been renegotiated in favour of private investors. There is a lot of government pressure and bureaucratic hurdles which hampers the growth in efficiency levels of Private partner. Due to infrastructure bottlenecks society suffers a lot. Many of the times due to the above mentioned issues common man end up paying for the cost overruns. Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 8

20 1.3 Goals and Objectives The objective of this project is to focus on identifying the factors that are critical for Public Private Partnership in Infrastructure projects in India by looking deep into the lessons learnt and also suggesting the way forward. So specific sectors and case studies are considered, like DND flyover as a benchmark in highway sector and the second case study is from aviation sector, Delhi airport from is taken, with the aim of analyzing the issues and how over the period of time things have evolved, do policy changes over the decade have made PPP more efficient, Are these policies successful enough in overcoming the problems that use to exist in PPP initially and then look into existing issues and scope for improvement. Also efforts were made to find out the view point of private partner. This study will further help in improving the overall efficiency of infrastructure industries in India and reach their potential. The main goal of the project is to understand the current scenario of PPP in India and their primary sectors and conduct research on the existing and proposed government policies in encouraging PPP opportunities in India especially in Infrastructure. Also to see how policies in place are taking care of efficiency of PPP projects and how can we further improve so that the full potential is realized. Meeting officials from Planning Commission and Infrastructure companies getting a clear picture was one objective. Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 9

21 2. Methodology 2.1 Literature Search Ministry of finance, Government of India has an entire website called Public Private Partnership in India which provides all the information regarding each step of PPP process, advisory committees, requirement and forms and also case studies. Planning commission deals with the policy issues. Analysis of the website, the policy framework, databases and case studies is done. There are lot policy reports and papers written on PPP as well which helped in getting the insight regarding the present situation of PPP as well the issues it was facing and existing problems as well and also the evolution of new policies and the steps taken by the government Analyzed the website main findings were the framework, case studies, financing, developers, PPP toolkit, mainstreaming of PPP projects, approval committees, regulations and forms, Reports and policy documents, the Draft National Policy Studied Professor Ram Singh s paper PPP: A means or an end? and various articles written by him in economic times and EPW which talks the various issues PPP is facing like PPP is attracted only in urban and mega cities. Findings from the report are various policy initiatives by the government like Standardization of Bidding and Concession Document, India Infrastructure Finance Company Limited (IIFCL), Provision of viability gap funding, India Infrastructure Project Development Fund (IIPDF), Public Private Partnership Appraisal Committee (PPPAC). The government is ready to bend backwards to ensure success of ongoing projects. Several PPP contracts for roads and airports have been renegotiated in favour of investors Studied NTBL s website ( which mentions all the information of DND. The Noida Toll Bridge Company Ltd. (NTBCL) is basically Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 10

22 promoted as a special purpose vehicle (SPV) by Infrastructure Leasing and Financial Services Ltd. (IL&FS) to develop construct, operate and maintain the DND Flyway on a Build Own Operate Transfer (BOOT) basis Government for the Independent regulator to promote PPP projects report talks about how an independent regulator can make PPP projects more efficient The Key finding from the website on Infrastructure (infrastructure.govt.in) is that the Secretariat of Infrastructure, Planning Commission initiates policies that ensures creation of world class infrastructure on time delivering international standard services, developing structures that maximize public-private partnership s (PPPs) role in India and monitoring progress of key infrastructure projects to ensure that established targets are realized The analyses of the whole website of DND flyway was undertaken which highlighted all the information regarding basic information regarding DND, tariffs, schemes, all other facilities available like Golden and silver cards and answering distress calls solutions The paper Distribution of Highways PPP in India: Key legal and economic determinants highlights various issues concerning the efficiency properties of the contracts and governing law and my agenda was to undertake the economic analysis of the PPP contracts and the relevant laws to determine their efficiency properties DND flyaway concession agreement, case study of Delhi Noida bridge by Planning Commission illustrated the need to follow good practice in both contract design and the process of awarding contracts, and the potential pitfalls of not doing so An article from Central Right India s website Delhi-Noida Toll Bridge-Loot in the name of Public-Private Partnerships mentions about the increase in toll rates Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 11

23 for the 22-km Delhi-Noida Direct (DND) flyway by the Noida Toll Bridge Company Limited (NTBCL). Two wheelers toll rates have been increased from Rs 11 to Rs 12, for cars from Rs 22 to Rs 25, LCVs from Rs 45 to Rs 55, bus and truck will now shell out Rs 70 from earlier Rs 55. Large vehicles will pay Rs 100 from existing Rs 75 and extra-large vehicles from Rs 95 to Rs 135. This is not the first hike. DND flyover is a classic case of how Public Private Partnerships (PPP) can be used by the corporate-bureaucratic- politician nexus to loot the nation Analyzed the Model Concession Agreement for PPP in National Highways available at infrastuctue.govt.in In Case Study by Planning Commission- Commercial use of land at Delhi and Mumbai Airports- An analysis of the questions of law and public policy it was found that in June 2003, the Airports Authority of India (the AAI ) had approved a proposal for the modernization of the Delhi and Mumbai airports through Public Private Partnership (PPP) As per the case study by IIM A, the concession agreement for the modernization and operation of Indira Gandhi International airport in Delhi and Chhatrapati Shivaji International airport at Mumbai respectively is referred to as Operation Management and Development Agreement (OMDA). The OMDA was a part of a set of transaction documents along with the request for proposal provided to potential bidders Report by CAG Implementation of Public Private Partnership, Indira Gandhi International Airport, Delhi This Report of the Comptroller and Auditor General of India contains the results of the Performance Audit of implementation of Public Private Partnership Project by Airports Authority of India at Indira Gandhi International Airport Delhi. The Audit covered the period from 2006 to The Report emanates from the scrutiny of files and documents pertaining to the Ministry of Civil Aviation, Airports Authority of India, Airport Economic Regulatory Authority of India, Operation, Management and Development Agreement of 2006, Passenger Service Fee (Security Component) Escrow Account, Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 12

24 etc. The Report has been prepared for submission to the President of India under Article 151 of the Constitution A case study GMR s Terminal 3 for Delhi Airport: A Successful Project Execution Model for Public-Private Partnership Initiatives? This case study discusses the infrastructure deficit in India and how the country was trying to overcome this problem with the help of the Public Private Partnership (PPP) model A case study by Planning Commission Bidding Process for the Delhi and Mumbai Airports elaborates and discusses the bidding process of Delhi and Mumbai Airports in detail and stated that the bidding process for the selection of concessionaires for the Delhi and Mumbai airports was a controversial one GMR s Website mainly focused on the basic information of the PPP project of Delhi Airport. GMR is the main concessionaire in Delhi Airport project, so it deals with all the operations and management. 2.2 Mentor Meetings Apart from Literature reviews and field visits, discussions with mentors regarding the challenges faced by the PPP and issues in policy framework has also proved to be useful in compilation of this report. Meeting Shri Alok Shekhar and discussing the situation of PPP projects in India contributed a great deal to the project and helped in streamlining the research by focusing on case studies like DND and Delhi airport. The structure of the paper was decided, in which It was asked to take the major projects from different sectors. One being DND flyover and the second one is Delhi Airport and taking these two as benchmarks compare the current situation of highway and airport sectors. Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 13

25 Focus was to study the success and failure of the concerned projects, also to find out the main aim of PPP projects and conduct a study to see if the aim is met or not. Further some data regarding PPP projects in India can be collected from experts. The main purpose of the meetings was to evaluate the merits and demerits of bidding process used and toll based highways and various the policy initiatives taken by the government in last decade to increase the efficiency of PPP projects in India. Projects have shown a lot of Improvement. In order to ensure transparency in the process the government has introduced model documents. Discussed two-stage competitive bidding for award of concession contracts in place, two stage process in which private party need to submit Request for Qualification (RfQ) and Request for Proposal (RfP) documents either it s a small or large projects. In the first stage technical evaluation is done and top 5 companies are selected and in the second stage they are asked to submit financial bids. DND is taken as a benchmark and with the help of Mr. Praveen Mahto, current situation of highway projects was found and then comparison is made. Now we have come long way from projects like DND Delhi airport case study was also briefly discussed and the focus was to find out the issues and the loopholes in the policy framework. Meeting such reputed officials won t have been possible without the mentor. The constant guidance helped a lot in moving in right direction Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 14

26 2.3 Meetings and Interviews Date Name Designation Institution Topic of Discussion June 6, 2013 Ms. Anna Roy Director Department of The actual Financial scenario of PPP Services, projects in India Ministry of and correct Finance policies are in place June 10, 2013 Mr. Praveen Director Infra, Planning The Model Mahto Commission Concession agreement available for different sectors on the website of Planning Commission. June 25, 2013 Mr. Sidharth CFO GMR Airport Point of view of Kapur Private Partners on PPP policies available and support required Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 15

27 3. Current Government Efforts The government is committed to continue to create an enabling environment for PPP, by taking initiatives related to funds, schemes, processes, institutional structures as well as guidelines. To overcome the constraints the government has taken the following initiatives: 3.1 PPP Cells The Government has supported PPP Cells at a State or sector level. The functions envisaged of a nodal agency, like PPP Cell is to are as follows: 4 Identify, conceptualize and create a shelf of projects Recommend approval of suitable projects for implementation With the help of consultants assist in preparation of the pre-feasibility reports Appoint consultants to develop the projects Ensure rigorous adherence to managing effective and transparent tendering processes Create efficient machinery for PPPs Develop internal evaluation guidelines to evaluate and assess the projects, Ensuring dissemination to consumers, investors and other government entities on the benefits and procedures for PPP Monitor and review PPP projects under implementation also do inspection visits 3.2 PPPAC 5 The Cabinet Committee on Economic Affairs of the Government has created the PPP Appraisal Committee (PPPAC), which consists of the following: a. Secretary, Department of Economic Affair b. Secretary, Planning Commission c. Secretary, Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 16

28 Department of Expenditure; d. Secretary, Department of Legal Affairs; e. Secretary of the Department sponsoring a project. Every PPP project is expected to obtain clearance from the PPPAC at the central level, it helps in safe guarding user and public interests and cap the contingent liabilities of the Government. The PPPAC also encourages the use of standardized contracts, which lay down the standard terms about allocation of risks, liabilities and guarantees as well as service quality and performance standards, and standardised documents for bidding such as Model Request for Qualifications and Model Request for Proposals that have been notified. 3.3 Union Cabinet and Committees Establishing parameters and targets for the performance of the sectors, as well as decisions to enhance investments are taken by the Union Cabinet and its Committees. 3.4 Standardization of Bidding and Concession Documents The government has introduced model documents in order to ensure transparency in the process, Request for Qualification (RfQ) and Request for Proposal (RfP) documents have been prepared. There is a two-stage competitive bidding process for award of concession contracts. At the RfQ stage, bidders are shortlisted on the basis of their technical and financial capabilities. That is, the bidders who have the necessary technical skills and financial resources to implement the project are short-listed. The admissibility or otherwise of a bid is decided on the basis of the previous experience and the financial capabilities of the bidder. Doubtful and unsuitable bids are screened at this stage itself and some Bidders are selected and issued RfP documents for financial bidding. The objective of this stage is to select the best among the qualified bidders. An attempt is made to select the bidder who offers the best value for money to the public sector. Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 17

29 3.5 The Model Concession Agreement (MCA) In addition, the introduction of the Model Concession Agreement (MCA) documents has gone a long way in streamlining and clarifying the PPP policy. MCAs have been prepared for BOT Annuity, BOT Toll, and BOT operation and maintenance (O&M) contracts. MCAs along with RfQ and RfP documents have provided an integrated institutional policy framework for implementation and identification of the project. All contracts are awarded on the basis of the MCA Since January 1, India Infrastructure Finance Company Limited(IIFCL) In the Indian financial market, debts are generally available for duration of 7 to 8 years whereas infrastructure projects require much longer payback timeframe. Hence, inadequate availability of long term finance, both debt and equity, is a serious problem facing investors. This is partly due to the underdeveloped markets for long term debt. To mitigate this problem the government set up the IIFCL in January IIFCL is allowed to refinance infrastructure loans by banks and FIs as well as lend directly, subject to a limit of 20 percent of the project cost. IIFCL funding schemes gives priority to PPP projects 3.7India Infrastructure Project Development Fund (IIPDF) 6 A major reason behind lacklustre performance of PPPs has been the nonavailability of credible and bankable projects. Detailed Project Reports (DPRs) and Project Feasibility Reports (PFRs) are of poor quality and cannot be relied upon, because the public sector in India has little capacity to prepare quality project reports. It also lacks capacity to implement PPP contracts. At the same time, the bidders cannot be expected to prepare their own reports as the cost of transaction advisors for PPP projects is huge. Therefore, the government has decided to develop capacity in the public sector as to line up credible and bankable projects 6 Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 18

30 that can be offered through competitive bidding. IIPDF has been set up with an initial contribution of Rs 100 crore.16 It is meant to help meet project development costs of public sponsoring agencies of infrastructure projects. It can assist to meet up to 75 percent of the project development costs. The costs are recovered from the successful bidder. 3.8 Several fiscal and other incentives to attract private investors to road projects. 7 The following are the additional initiatives of the new PPP policy: Declaration of road sector as an industry, for easy borrowing Longer concession periods (up to 30 years). Easier external commercial borrowing norms. FDI including foreign equity participation up to 100 percent in the highways is allowed for BOT projects. Provision of encumbrance free site for work, i.e. government bears expenses for land and pre-construction activities. MRTP provisions have been relaxed to enable large firms to enter the highway sector. Duty free import of modern high capacity construction equipments has been allowed. For the purpose of tax concession, Treating housing and other development Activities which are integral part of highway project, as a part of infrastructur100 percent tax holiday for any 10 consecutive years out of 20 years after commissioning of the project. 3.9 National PPP Capacity Building Programme The National PPP Capacity Building Programme was launched by the Union Finance Minister (FM) at the India PPP Conclave held in December The programme found special mention in the FM's Budget speech in February in%20India%20-%20FINAL%28Secured%29.pdf Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 19

31 Over the period of next 3 years, the programme expects to train 10,000 senior and middle-level government officials to improve capacities among government officials in preparing and managing PPP projects across various infrastructure sectors. The training material has been organized into five distinct course offerings in an easy to use structure, with extensive guidance as well as explanatory notes and tips, cross-referencing and additional material which can also be used by the trainees for subsequent revisions and reference 3.10 Public Private Partnership (Preparation, Procurement and Management) Rules 2011 Pursuant to the decision on the recommendations of the Committee on Public Procurement, a Committee has been constituted in Department of Economic Affair to formulate the Rules for PPP projects, including rules for regulating expenditure, appropriation of revenues, contingent liabilities, etc. in PPP projects and proposed delegation of powers in this regard The draft Public Private Partnership Rules Department of Economic Affairs, Ministry of Finance has prepared the draft Public Private Partnership Rules For sustaining investor interest in up gradation and maintenance of highways on DBFOT basis, a precise policy and regulatory framework is being spelt out in this are typically important for limited recourse financing of infrastructure projects, such as mitigation and unbundling of risks; allocation of risks and rewards; symmetry of obligations between the principal parties; precision and predictability of costs and obligations; reduction of transaction costs; force majeure; and termination. It also addresses other important concerns such as user protection, independent monitoring, dispute resolution and financial support from the Government. The MCA also elaborates on the basis for commercializing highways in a planned and phased manner through optimal utilization of resources on the one hand and adoption of International best practices on the other hand. The objective is to secure value for public money and 8 Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 20

32 provide efficient and cost effective services to the users Model Concession Agreement (MCA) The Secretariat for Infrastructure The Secretariat for Infrastructure in the Planning Commission is involved in initiating policies that would ensure time-bound creation of world class infrastructure delivering services matching international standards, developing structures that maximize the role of public-private partnerships (PPPs) and monitoring progress of key infrastructure projects to ensure that established targets are realized The Cabinet Committee on Infrastructure (CCI) The Cabinet Committee on Infrastructure (CCI), under the Chairmanship of the Prime Minister, was constituted on July 6, It substituted the Committee on Infrastructure which was set up on 31st August, 2004 under the chairmanship of Prime Minister. The CCI approves and reviews policies and monitors implementation of programmes and projects across infrastructure sectors The Initiatives in Airport Sector The Committee on Infrastructure has initiated several policy measures that would ensure time-bound creation of world-class airports in India. A comprehensive civil aviation policy is on the anvil. An independent Airports Economic Regulatory Authority Bill for economic regulation is also under consideration. The policy of open skies introduced some time ago has already provided a powerful spurt in traffic growth that has exceeded 20% per annum during the past two years. Major airports such as Chennai and Kolkata are also proposed to be taken up for modernization through the PPP route. To ensure balanced airport development around the country, a comprehensive plan for the development of other 35 non-metro airports is also under Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 21

33 preparation. These measures are expected to bring a total investment of Rs. 40,000 crore (USD billion) for modernization of the airport infrastructure. A Model Concession Agreement is also being developed for standardizing and simplifying the PPP transactions for airports, on the analogy of the highways sector. This would include upgrading of the ATC services at the airports. Issues relating to customs, immigration and security are also being resolved in a manner that enhances the efficiency of airport usage. A Greenfield airport is already operational at Bangalore and the one at Hyderabad, built by private consortia at a total investment of over USD 800 million, will be operational soon. A second Greenfield airport being planned at Navi Mumbai is planned to be developed using public-private partnership (PPP) mode at an estimated cost of USD 2.5 billion. 35 other city airports are proposed to be upgraded through PPP mode where an investment of USD 357 million is being considered over the next three years. Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 22

34 4. Results and Discussions 4.1 Findings from theoretical readings and literature surveys 4.1,1 The website of PPP, India elaborates the framework, case studies, financing, developers, PPP toolkit, mainstreaming of PPP projects, approval committees, regulations and forms, Reports and policy documents, PPP headlines and the Draft National Policy This contains all the policy initiatives discussed above that are followed in India presently. The sector wise share of PPP was found: Source: PPP India Database Figure 4: PPP projects in India by sector and by value Dr. Ram Singh s paper PPP: A means or an end? The key finding was that provision of a public good or service through PPP is not indisputably superior. Its cost and benefits vary from project to project.there have been lot of steps taken by government in favour of private players which are not socially desirable like to make projects attractive for private investment, the PPP Appraisal Committee has Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 23

35 been allowed to increase viability gap funding (VGF)/grants for Phase V projects of NHDP. The government is ready to bend over backwards to ensure success of ongoing projects. Several PPP contracts for roads and airports have been renegotiated in favour of investors Main findings were the basic information regarding DND. Infrastructure Leasing and Financial Services Ltd. (IL&FS) promotes the Noida Toll Bridge Company Ltd. (NTBCL) as a special purpose vehicle (SPV) to develop construct, operate and maintain the DND Flyway on a Build Own Operate Transfer (BOOT) basis. The Flyway has been built with due care for environmental concerns. The project was commissioned almost 4 months ahead of schedule on February 7, 2001 and broadly within the budget As mentioned in the report Government for the Independent regulator to promote PPP projects an independent regulator can make PPP projects more efficient and thought of it as one of the recommendations As per the website of Indian Infrastructure contains all the information about PPP projects in India, It was found out that Secretariat of Infrastructure, Planning Commission is the one who initiates policies that ensures creation of world class infrastructure on time delivering international standard services, developing structures that maximize public-private partnership s (PPPs) role in India and monitoring progress of key infrastructure projects to ensure that established targets are realized. It includes information about all the regulations, two stage bidding process, modal concession agreements documents followed now, Infrastructure finance, reports, tenders, recent events, Database of PPP projects, library of bid documents and website also contains case studies of almost all major PPP projects in India. All this information helped me compare my benchmark project DND with the present scenario where standardized contracts and modal concession agreements are followed. Comparison is made on these grounds only and then analyses if all the problems that DND was facing has been overcome or not like the contract was not well defined, it was a lot in favour of private players, Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 24

36 bidding process was not transparent, cost over runs were huge but now because of the policy initiatives by the government India has been successful in overcoming the loopholes that PPP was facing initially. It has become more efficient now As per DND s website the first Toll Plaza in India to be certified ISO: 9001: 2008 compliant for excellence in the field of Operations and Maintenance and Customer Services. The users have 3 convenient options for payment of toll, namely gold, silver and cash Distribution of Highways PPP in India: Key legal and economic determinants deals with the performance of the Public Private Partnerships (PPPs) programme of Government of India, for development of highways and expressways. The focus of the study was to see why have some projects attracted private investment while others have not? Why only a few states have attracted PPPs, while some others have completely failed to do so?. It also deals with some other issues related to the PPP policy and its limited success. A set of legal and economic variables explained the skewed distribution of PPPs across the states as well as across projects. The key finding was that the richer states have attracted more PPPs than the poorer ones. Also, the probability of PPP is higher for projects located closer to mega cities and those located on national highways connecting richer states. Main learning was that the quality of governance, in terms of the level of property rights protection, in a state is a significant explanatory variable As per DND flyaway concession agreement, case study of Delhi Noida bridge by Planning Commission. The Delhi Noida toll bridge project was awarded in The case study illustrated the need to follow good practice in both contract design and the process of awarding contracts, and the potential pitfalls of not doing so. The contract does not give any role to the Authority to assessing the reasonableness of capital and operational costs reported by the concessionaire. It also guaranteed annual returns of 20% on the total project costs, and not on equity alone. Shortfalls in returns for previous years result in a corresponding increase in project cost, on which further returns are payable. As a result, the initial capital Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 25

37 cost of Rs. 408 crore, as determined by the concessionaire, had risen to Rs. 953 crore as on March 31, Also, since the contract provides for the term of the concession to be extended until the concessionaire recovers the total cost of the project and returns thereon, the concessionaire has noted that it is now entitled to hold the concession for a period of 70 years as against the 30 years initially contemplated in the agreement. In addition, the concessionaire has received in principle approval for development rights over 30.5 acres of prime urban land in Noida, as a supplementary source of returns. In view of these outcomes, the paper concludes that if concessions are to serve the public interest, it is vital to ensure a robust contract design that relies on open competitive bidding and elimination of conflicts of interest An article from Central Right India s website Delhi-Noida Toll Bridge-Loot in the name of Public-Private Partnerships mentions the toll rates for the 22-km Delhi-Noida Direct (DND) flyway were increased from 1st April, 2013 by the Noida Toll Bridge Company Limited (NTBCL). Two wheelers toll rates have been increased from Rs 11 to Rs 12, for cars from Rs 22 to Rs 25, LCVs from Rs 45 to Rs 55, bus and truck will now shell out Rs 70 from earlier Rs 55. Large vehicles will pay Rs 100 from existing Rs 75 and extra-large vehicles from Rs 95 to Rs 135. This is not the first hike. DND flyover is a classic case of how Public Private Partnerships (PPP) can be used by the corporate-bureaucratic-politician nexus to loot the nation Analyzed the Model Concession Agreement for PPP in National Highways available at infrastuctue.govt.in. A precise policy and regulatory framework is mentioned in this Model Concession Agreement (MCA). The MCA also elaborates on the basis for commercializing highways in a planned and phased manner by utilizing the resources optimally on the one hand and adopting international best practices on the other hand. Together with the Schedules, the proposed contractual framework deals with the issues those are likely to arise in financing of highway projects on DBFOT basis. The proposed regulatory and policy framework Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 26

38 contained in the MCA is a pre-requisite for attracting private investment with improved efficiencies and reduced costs, necessary for accelerating grow In Case Study by Planning Commission- Commercial use of land at Delhi and Mumbai Airports- An analysis of the questions of law and public policy it was found that in June 2003, the Airports Authority of India (the AAI ) had approved a proposal for the modernization of the Delhi and Mumbai airports through Public Private Partnership (PPP). The bidding process began in May 2004, it was full of controversies. One major issue that was with respect to the legality of permitting the proposed Concessionaire to develop the airport for commercial uses unrelated to the airport, especially with reference to the provisions of the Airports Authority of India Act, This issue had significant financial and policy implications for the bidding process. Further, it would also determine the pattern of airport development during the proposed concession period spanning 60 years. Since there was a difference of opinion on the issue between the constituents of the Inter-Ministerial Group that was finalizing the transaction documents, it was decided to seek the opinion of the Solicitor General of India (the SGI ), and thereafter, of the Attorney General of India (the AGI ). The final decision was taken by the Empowered Group of Ministers As per the case study by IIM A, the concession agreement for the modernization and operation of Indira Gandhi International airport in Delhi referred to as Operation Management and Development Agreement (OMDA). The OMDA was a part of a set of transaction documents along with the request for proposal provided to bidders. The OMDA laid out the contractual terms for structuring the project through PPP. The paper discusses the evolution of the draft OMDA from when it was first released in April 2005 to the bidders till it was released as a final OMDA in August 2005 before an extended bidding date. During this period, there were critical issues. Some of them which got addressed were: limits to commercial development of airport land, nature of tariff regulatory regime, contingent liabilities including performance bonds and termination payments, and potential contractual and strategic conflicts. It brings out the intra- Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 27

39 governmental issues and processes, and the significant learning that formed part of these PPP concessions, which could well be among the largest in the world The CAG report on the Delhi airport said that the decision by the Civil Aviation Ministry to award the contract for the Delhi airport to GMR caused huge losses to the tax payers and passengers. It claims that land was given to the company at much lower rates than even to government organizations like the DGCA and the BCA. The CAG has pegged the losses at about Rs 3750 crore. DIAL entered in to Operations, Management and Development Agreement (OMDA) on April 4, 2006 with the AAI. Table 2: The components adopted by DIAL to finance the project cost Source: Implementation of Public Private Partnership Indira Gandhi International Airport, Delhi, CAG From the above it is clear that as per the original estimates the entire funding was to be through equity, debt, security deposits and internal accruals. However, as is seen above, this was reduced to per cent of the total fund requirements of the actual project cost. This financial gap was mainly filled by levy of DF which constituted per cent of the total capital outlay. OMDA did not envisage the funding of project cost through levy of DF from passengers since the entire funding Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 28

40 was to be through debt and equity only. Thus the inability of the shareholders of DIAL to bring in additional funds to the project through additional debt from financial institutions led to levy of DF on passengers. This report also deals with the steps in PPP process. Figure 5: The steps in the public private partnership processs Source: Implementation of Public Private Partnership Indira Gandhi International Airport, Delhi, CAG Further It was found from CAG report that according to Article (d) every such Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 29

41 contract entered into by the JVC shall be on an arms length basis. An arms length transaction is defined by Institute of Chartered Accountants of India (ICAI) as transaction between parties that do not have a particular or special relationship that makes prices of transactions uncharacteristic of market conditions. The transaction is presumed to be between unrelated parties each acting independently. Equity participation of DIAL in these JVs makes these contracts not on arms length. Since neither the Government nor the AAI has exercised any access to the books of accounts of these JVs, it can never be ascertained whether the revenue passed on as share of DIAL is indeed correct. 9 9 Implementation of Public Private Partnership Indira Gandhi International Airport, Delhi, CAG Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 30

42 Source: Planning Commissions Website Figure 6: Equity and revenue share of DIAL in JV Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 31

43 Source: Implementation of Public Private Partnership Indira Gandhi International Airport, Delhi, CAG Figure 7: DIAL s financing of the Project Out of the total capital expenditure of ` crore claimed by DIAL, AERA has admitted ` crore as the total project cost. The funding gap to the tune of ` crore was permitted by AERA to be collected from the passengers through levy of DF which was not envisaged in OMDA and SSA. As would be seen from the above, out of the total capital expenditure of ` crore, the promoter s equity has been ` 2450 crore out of which 26 per cent is contributed by AAI. 74 per cent of the equity capital of ` 2450 crore is ` 1813 crore. Out of the capital expenditure of ` crore, only 19 per cent of the capital expenditure has been promoters contribution. ` 5266 crore have come from loans and ` 1471 crore has come from Security Deposits. While only ` 50 crore has come from internal accruals, ` crore have come from Airport Development Fees. It was also noted in audit that in case of Indira Gandhi International Airport, the contribution of internal accruals has been the barest minimum. It was only ` 50 crore. In case of Mumbai airport, internal accrual was ` 1999 crore The case details the Terminal 3 for Delhi Airport project to explain the role and importance of PPP in overcoming infrastructure deficit. It also explains the 10 Implementation of Public Private Partnership Indira Gandhi International Airport, Delhi, CAG Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 32

44 different features of Terminal 3 (T3) which go to make it a world class airport terminal. In the end, the case study covers the limitations of the PPP model. The case study helps to understand the role of PPP and provides scope for discussions on how to overcome the limitations of PPP. It also provides ample scope for discussing how T3 was completed in just 37 months and what the upcoming infrastructure projects can learn from this project. This case is meant for MBA/MS students as part of a project management curriculum. The main aim of this case : 1) Understand the importance of Public-Private Partnership initiatives, especially in emerging markets, to bridge the infrastructure deficit 2) Understand the salient features of Delhi Airport s Terminal 3 (T3) project and analyze all the features that have contributed to the completion of T3 project in a record 37 months 3) Discuss and debate what T3 s record completion in 37 months means for PPP initiatives and what best practices this project execution offers for future PPP initiatives in the infrastructure sector A case study by Planning Commission Bidding Process for the Delhi and Mumbai Airports elaborates and discusses the bidding process of Delhi and Mumbai Airports in detail and stated that the bidding process for the selection of concessionaires for the Delhi and Mumbai airports was a controversial one. It involved much discussions and arguments in different government fora including the Empowered Group of Ministers at the helm. Amid rumours of criticism, the bid process was steadily moving towards the award of the Delhi airport in favour of a particular bidder, thanks to the flawed evaluation by the international consultants of the Airport Authority of India. Close to the conclusion of this process, one of the constituents of the inter-ministerial fora laid bare the infirmities of the evaluation scores. This led to much debate within the government and extensive coverage by the media. Once in the public domain, the entire process became open and transparent. It led to a fair outcome that not only withstood the scrutiny of the Supreme Court but was also free of any criticism in the media or Parliament. This reflected a complete swing of the pendulum, from a process that was regarded as manipulated to one Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 33

45 that was entirely fair and transparent. This case study demonstrates the fragility as well as the strengths of the system in dealing with these two mega projects GMR s website explains that in January 2006, the consortium was awarded the concession to operate, manage and develop the IGI Airport following an international competitive bidding process. DIAL entered in to Operations, Management and Development Agreement (OMDA) on April 4, 2006 with the AAI. The initial term of the concession is 30 years extendable by a further 30 years Besides upgrading the existing terminals, DIAL has already commissioned a new runway at IGI Airport on September 25, It has also inaugurated the new domestic departure terminal 1D (T1D) on 26th February, T1D will increase the capacity of domestic departures to 10 million passengers per annum. In March 2010, DIAL has completed the construction of integrated passenger terminal (Terminal 3). The first phase of the airport is designed and capable to handle 60 million passengers per annum (mppa). This development was the first phase of the airport expansion. In subsequent stages, the airport will be further developed with the increase in passenger demand and more terminals and runways would be added in a modular manner to form a U shaped complex with an ultimate design capacity of 100 million passengers per annum. 11 Bidding Process for the Delhi and Mumbai Airports, Planning Commission Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 34

46 4.2 Finding from the meetings and impact on the theoretical focus The meetings with Ms. Anna Roy, Director, Department of Financial Services, Ministry of Finance, Government of India and the Director of Corporation Bank and Mr. Praveen Mahto, Director Infra, Planning Commission played a very important role in the research. As per these officials the current policy framework is not the problem instead the implementation issues are the problem. Ms. Anna Roy was the part of appraisal committee for quite a long time so she knew the ground realities of PPP in India. The actual scenario was portrayed and also the correct policies that are in place. As per her suggestions, comparison between DND and some recent highway project is conducted, because DND is a very initial project when proper mechanism was not in place so evaluating the effect of new policy with the help of DND is a good idea. Mr. Praveen elaborated on the Model Concession agreements available for different sectors on the website of Planning Commission. It was advised to find out the issues from case studies and information available about DND flyway and see has the new policies able to address the issues The key finding was that Hyderabad Metro is one of the most efficient example of PPP in India. Also Government has taken many policy initiatives in last decade to increase the efficiency of PPP projects in India. Projects have shown a lot of Improvements as well. In order to ensure transparency in the process the government has introduced model documents. The main contribution of these meetings is that DND is taken as a benchmark and compared with the present scenario where Model Concession Agreements are set in place. Now we have come long way from projects like DND. Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 35

47 It was realized that the most improvement point is selection criteria, there is be no opaqueness, it should be highly transparent. At the time of awarding contract itself each and every point should be covered and all uncertainty should be addressed. So the important recommendation is, every PPP project should be awarded by the way of fair competitive bidding only. Earlier because every company has to come up with their own contract there was a lot of transaction cost involved but now there are standard contracts used. Model agreements are developed in metro, highway, port, airport etc. Final selection evaluation should be objective not subjective like in the case of Delhi and Mumbai International Airports like in that case they were asked to submit their plan of action and management and proposals if the concession period if 60 years and given various situations but the outcome of this was far from satisfactory. After this it was realized that everything can go wrong if final evaluation is that much subjective. The process was not transparent and was not even accountable. Hence selection is most crucial, right partner needs to be selected. Also as a private player you should not leave or get any approval after getting selected. Government should give everything upfront. By this the uncertainty decreases as well. Earlier Item rate contract was followed and was source of corruption. When it was changed there was lot of opposition but things changed and are highly transparent now. Now it s more about output specification instead of input specification. The main problem that still exists is DPR (detailed project report) is poorly made. People bid really high than required. People prefer BOT (annuity), so one solution is we can have a regulatory on the rack to look after. And there are still some implementation issues. There is a need to convince big investors and promote PPP. The main important issues are in land acquisition, environment clearances, and statutory clearances etc but because of these we can t blame PPP as a policy. So to see the success of the project we can judge the performance on parameters like was the project timely completed, if cost overruns are there and compare it with government funded projects. Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 36

48 Regarding the case study of Delhi airport, with a aim of knowing the ground realities and the point of view of Private partners on the policy framework available a meeting with Mr. Sidharth Kapur, CFO, GMR Airport was fixed. 26 percent equity by AAI 74 percent equity by a strategic JV partner 45.99% Gross Revenue Share by AAI The airport being managed by Delhi International airport Pvt. Ltd. Figure 8: Modernization and restructuring of IGI Airport at Delhi When asked how supportive and helpful the Government is it was identified that government has been really supportive in terms of all the approvals, agreements, Financial aid etc In a report titled "Implementation of Public Private Partnership, Indira Gandhi International Airport, Delhi" the Comptroller and Auditor General of India (CAG) has found faults in almost every step of implementation of the Public Private Partnership (PPP) model in the brown field privatization of New Delhi's Indira Gandhi International Airport (IGIA). Regarding the controversial report by CAG on Delhi airport project. The report accuses the Ministry of Civil Aviation, headed by Mr. Patel, of violating laws, and providing post contractual benefits to DIAL, to the detriment of the government as well as the travelling public. But it was identified that there were no post contractual changes or renegotiations. Bidding was fair. Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 37

49 It was found that the major issue with PPP in India is that it is treated more like a public project so to make it more efficient private players need autonomy. They want government to design proper contract and all clauses and after that just leave it to private player and let them work accordingly. PPP should be kept away from imposition of bureaucratic hurdles. Private Players think that keeping PPP project out of purview of RTI act will result in increasing the efficiency as there is more pressure on concessionaire while working because of this clause they need their freedom to work as a private party. So According to Mr. Sidharth Kapur RTI should not apply. Use of Model Agreements in airport sector like highways was thought of one solution before this interview but it was found that Model agreements cannot be used as each airport is very different project like Delhi airport is a brownfield project. There should be a proper mechanism for renegotiation in between if required but should be avoided. And this should be mutual and rational. Hence main thing is that agreement should be clearly drafted like GMR says it was efficiently designed in case of Delhi airport. SSA covers all the performance standard agreement which need to be strictly followed by the concessionaire, and these are strictly followed in case of Delhi airport. But one problem is there are no performance standards for other stakeholders, which need to be in place. Government over regulation instead of increasing efficiency end up decreasing it, in case of Delhi airport project GMR appointed KPMG and Engineer India as regulators to look into matters like is cost increase fair or not and if infrastructure in build in time or not. Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 38

50 Delhi Airport Terminal 3 was built in just 37 months because of Common wealth Games held in Delhi in 2010 so it was examined if time pressure was a problem. It was found that yes because of time bounds GMR had to face a lo t issues like many contractors were not ready to take the risk and it also led to cost over runs in some sense. In contrast to CAG report, Mr. Sidharth Kapur says that there were no post bidding changes and passenger fees is lowest if compared to other airports all over the world. The main focus of the case studies is to see have changes in policies made PPP really efficient, find out the issues and challenges, recommend changes and how we can handle implementation issue and improve efficacy. Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 39

51 4.3 Gap analysis In the past five to six years, India s PPP program has grown rapidly. In more than 150 PPP deals were there, compared with 66 in the previous seven years. Source: Price Water Cooper 2007 Figure 9: Climb in number and value of PPP projects in India This growth was mainly in the transport and urban infrastructure sectors, with road projects accounting for a large share of the increase, particularly in the number of projects. India s government had been concerned that local financial markets would be unable to support continued large growth in investment in PPPs. The World Bank, with financial support from PPIAF, undertook a detailed review of financing patterns and trends and the constraints to expanding PPP financing as perceived by market participants. In senior debt accounted for 68 percent of project financing on average, the rest took the form of equity (25 percent), subordinated debt (3 percent), and government grants (4 percent), typically viability gap grants Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 40

52 provided during construction to PPPs deemed economically desirable but not financially viable. Of the senior debt, about 70 percent was provided by commercial banks, four-fifths of this by public sector banks. The rest of the total debt financing came from institutional lenders (around 23 percent), with 5 percent provided by the International Finance Corporation. Bond markets were used sparingly. The use of subordinated debt also remains limited. Its use has become more common, however, particularly in the road sector, which has the largest number of projects and the greatest acceptance by financial markets. But most of the subordinated debt has been provided by the senior lenders themselves. On the equity side, more than 80 percent came from project developers, with the next largest contributor being the public sector. Strategic investors made direct equity investments in the special-purpose vehicles established to implement the PPPs for only nine projects in the sample. These investments totaled almost $167 million (6 percent of the total equity), most of it in the airport sector. Equity investments by financial institutions provided the rest. 12 Talking about PPP in general, from initial period if we see the schemes, policies, efforts in PPP, there were no proper framework and rules defined, there was lot of corruption. Earlier item rate contracts were used where changes of corruption are even higher. There was so defined contract or agreement, disputes redressal mechanism was not in place. The criteria of awarding contracts was not transparent, The contract does not give the Authority a role in assessing the reasonableness of capital and operational costs reported by the concessionaire. One set of issues concern the efficiency properties of these contracts and the governing laws. There was no clear separation between the roles of the public authority and the private sector. There exists lot of issues in PPP. Most sectors face a lot of hindrance 12 and Department of Economic, Affairs PPP Cell Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 41

53 in enabling a regulatory framework as well as a consolidated policy. So it s important to convert such policies into PPP friendly. 13 To achieve the desired results, active participation of various state projects are essential. Lack of ability of private sectors to fit into the risk of investing in diversified projects also needs to be overcome. Prominent issues are weakness in enabling policy and regulatory framework. Substantial work need to be done in making sector policies and regulations PPP friendly. A large number of these projects are in the States and without the active participation of the States it would not be possible to achieve satisfactory results. The market presently does not have adequate instruments and capacity to meet the long-term equity and debt financing needed by infrastructure projects. There is also a lack of shelf of credible, bankable infrastructure projects. This could be offered for financing to the private sector. Public institutions are not able to manage the PPP process.lack of credibility of bankable infrastructure projects used for financing the private sector needs to be overcome. Several initiatives have been undertaken by Indian Government to enable a greater PPP framework in order to eradicate the constraints like encouraging foreign as well as private investments by waving off charges. Standardized contractual documents have been devised which lays down the terminologies related to risks, liabilities and performance standards have streamlined Approval schemes for PPPs. For the purpose of virtual PPP market a website has been launched which serves as an online database for PPP projects Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 42

54 Table 3: PPP projects Process Management Source: and Department of Economic, Affairs PPP Cell Talking about problems specifically with Delhi Noida Bridge: The concession for the Delhi Noida bridge project was not awarded competitively The terms of the concession agreement for the Delhi Noida bridge project were highly in favour of the private partner It was mentioned in the contract that concessionaire will get 20 percent return over total costs, but it was not clear as the contract does not put a cap on project cost and total cost of the project, costs were basically open ended and if not covered concession period would be expanded like it has been expanded from 30 years to 70 years now Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 43

55 The shortfalls in recovery of returns were included in the total cost, this substantially removes traffic risk from the concessionaire, and also increases the total amount due to the concessionaire There is no incentive to minimize cost because the costs were completely passed on to consumers The concessionaire does not bear any significant commercial risk The construction completion risk, which should more appropriately fall to the concessionaire, was shifted to NOIDA. The power to determine, demand, collect, retain and appropriate the fee for use of the Noida bridge was given to private player instead of the government The concession agreement does mention the penalty payments or sanctions for not adhering to performance specifications/standards. Under the agreement NOIDA undertakes not to build a competing facility for a period of 10 years or till the NOIDA bridge reaches its Full Rated Capacity Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 44

56 5. Recommendations, Scope and Strategy for Implementation Reasons: In most of the projects the main issue is bidding on is not fair because of which sometimes we end up choosing less deserving candidate. Private Partners selection is the most important step which has to be done carefully and a fair way because rest of the project, its implementation, efficiency depends on the private party itself. Recommendation 1: The most important recommendation is that all the projects should be awarded on the basis of Competitive bidding only. To get best technical and financial offer, the authorities should start interacting with private sector from the project development activities only and all the concerns of the bidders should be taken into account. And there should not be excessive focus on highest financial bids because speculative bids hamper the project in the long run Scope: This will lead to selection of the most deserving private party and hence increases the efficiency of the projects. Strategy: The two stage process already in place should be followed with more transparency and after each stage name and basis of selection of private partners should be declared and provided in written. Figure 10: Recommendation 1 Private Partner should submit Request for Qualifications Transparent process: selection of best parties on the basis on technical and financial capabilities & it should be declared on what basis are they selected in written Request of Proposals should be submitted by the selected companies Candidate offering highest share to the government should be selected but other factors should be considered as well Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 45

57 Recommendation 2: An independent Institution structure for handling PPP program Reasons: There is no independent PPP regulator which is required to attract more domestic and international private funding of the infrastructure Scope: With the objective of meeting the PPP targets, an independent institute should be set up to act as nodal agency with the responsibility of creation of PPP database. Best practices, model documents for all sectors and coordination with all departments. This will have a positive impact on efficiency level Strategy: Government should set up a nodal agency at central level Figure 11: Recommendation 2 Recommendation 3: Issues related to land acquisition and environment clearances should be taken into consideration Reason: The project development activities such as land acquisition, environment or forest clearances etc. are not given adequate importance by the concessioning authorities, this is because of the absence of adequate project development by authorities. It leads to poor bid response, delays in time of execution, sometimes leads to disputes and mispricing Scope:This will lead to timely completion of projects and also will help in reducing the cost over runs Strategy: The authorities should try to get all approvals and latest feasibility reports with technical scope of work before awarding concessions Figure 12: Recommendation 3 Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 46

58 Recommendation 4: Broadening of the sources of financing is required for growth of PPP, so policy reforms in capital market are required. And also there is a need to develop corporate bond market Reason: There is huge investment required for PPP projects so to raise debt private sector is dependent upon commercial banks. But banks alone cannot fund all projects due to sectoral limits Scope: If financial constraints are removed more and more private parties will bid, also it will be easy to comlete projects timely and efficiently Strategy: Set up infrastructure Debt Funds. Also commercial banks while funding the project can compulsorily fund some part of debt by subscribing bonds Figure 13: Recommendation 4 Recommendation 5: Decentalization-Policies should be different for differnt sectors and even different states Reason:Use of Model Agreements in airport sector like highways was thought of one solution before this report but it was found that Model agreements cannot be used as each airport is very different project like Delhi airport is a brownfield project some are Greenfield also the place. Investment everything is different we cannot generalize Scope: This will give enough flexibility to private partners as well government and hence will take into account the specific issues Figure 14: Recommendation 5 Strategy: There should be authorities at state level as well as sectoral level which deals with all the policy recommendations in the specific sectors and also take care of the designs of the agreements and contracts Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 47

59 Recommendation 6: Keep PPP projects out of purview of RTI act and should be kept away from imposition of bureaucratic hurdles Reason: Private Players think that keeping PPP project out of purview of RTI act will result in increasing the efficiency as there is more pressure on concessionaire while working because of this clause they need their freedom to work as a private party. It was found that the major issue with PPP in India is that it is treated more like a public project so to make it more efficient private players need autonomy. They want government to design proper contract and all clauses and after that just leave it to private player and should be kept away from imposition of bureaucratic hurdles Scope: This will give enough flexibility to private partners as well government and hence will increase the efficiency of private players Strategy: RTI act has to be amended by the government to keep PPP out of its purview Figure 15: Recommendation 6 Recommendation 7: Performance standard Agreements for other stakeholders than the concessioare needs to be in place Reason: SSA covers all the performance standard agreement which need to be strictly followed by the concessionaire. But one problem is there are no performance standards for other stakeholders, which need to be in place Scope: This obliges other stakeholders to perform better and hence will lead to efficiency overall Strategy: SSA should define Performance standard agreements to all the stakeholders of the PPP project and should inform them while initiating its work only Figure 16: Recommendation 7 Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 48

60 Recommendation 8: The Government should also take necessary steps to implement the PPP project in other states where PPP are not attracted as of now Reason: There are only few states which have attracted PPP even after so many policies in place becuse over property right issues and weak regulatory mechanism Scope: This will help in overall development and inclusive growth of the economy. There are huge infrastructural bottlenecks in poorer states rather than metropolitan cities Figure 17: Recommendation 8 Strategy: This can be done by giving to private players to invest in PPP projects in poorer states by giving incentives like higher returns, cheaper inputs and also by improving the policies in poorer states because the main issue is with the policies and property rights Recommendation 9: In the contracts, clauses which restricts other projects to be carried out in the nearby area should not not be allowed Reason: Day by day population is demand for infrastructure incrasing and so is the Scope: This will help in removing the restriction on supply of projects and also protect customers from monolopist's exploitaions Strategy: Governmment or Nodal agencires can include this inthe draft rules, 2011 and modal agreements Figure 18: Recommendation 9 Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 49

61 Some other issues and recommendations are as follows: Table 4: Some issues and Recommendations Some other steps need to be taken to increase the efficiency of PPP projects and address the problems in current system. The strategy would be to just include all these clauses in the contracts signed initially. The steps to be taken are as follows: The tax regime applicable to dividends paid out by SPVs needs to be rationalized; currently dividends are being taxed twice, first at the level of project-specific SPVs and then at the holding company level in cases where a holding company is implementing multiple projects through SPVs Large size PPP projects may be awarded through an SPV route, wherein a project SPV first acquires land, permissions for shifting of utilities and environmental as well as other statutory clearances and approvals necessary Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 50

62 for undertaking the project. The SPV along with the project is then bid out through a transparent process Concessions should be made tradable by allowing the project developers to exit after delivering on the specifications, when the operations stabilized. To attract global investment funds for infrastructure, India s PPPs need to offer returns comparable to those in other markets Credible mechanisms for dispute resolution needs to be set in place Continued government role and support is required to ensure provision of infrastructure services to poor people. Project capital and operational costs should be capped. The party bearing these costs should be able to check that they are reasonable. To avoid bias, crucial appointments such as those of the Independent Engineer, Independent Auditor and Project Oversight Board should be based upon transparent selection criteria. Selection should be made from a mutually acceptable shortlist and should not involve third parties. There should be a proper mechanism for renegotiation in between if required but should be avoided. And this should be mutual and rational. Hence main thing is that agreement should be clearly drafted like GMR says it was efficiently designed in case of Delhi airport A proper survey through a Government Approved Surveyor/ valuer should be conducted to find the exact area of airport land, hospitality area, demised premises, carved out area including the land available with the AAI. AAI should obtain clear title deeds in respect of total area handed over to private airport operators to avoid future dispute In case of PPPs, it is recommended that all pre bid conditions are declared upfront and monetized value of all concessions including assets transferred is arrived at before bids are invited. Any post bid concessions, which are not contemplated earlier, amount to undue favour to the concessionaire. Government should investigate all cases of such post bid actions and fix responsibility. It is necessary to review the various provisions of OMDA and verify to the extent provisions could not be adhered to. DPR should be properly made Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 51

63 6. Future Work: India has witnessed high growth rate in last few years. However, recently it is facing downturn. India is still in its development phase and huge amount of investment is required in almost all sectors but due to financial constraints government alone cannot meet all the investment requirements. Here comes the Private player in picture. PPP is the best way to develop India as it solves two main problem one being the finance and second it avoids inefficiency. There is much scope to work in new sectors like education, skill trainings, Renewable energy etc. Also State comparisons needs to be done and it should be found why some states are progressing well and some are not when it comes to PPP As part of the future work one can keep a track of the implementation of various policies and check whether it is able to achieve its goals. Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 52

64 7. References 1. International Conference on Meeting India s Infrastructure Needs with Public Private Partnerships 2. The International Experience and Perspective February 5 6, 2007, Shangri- La Hotel, New Delhi, iv Conference Report 3. M.Sathanapriya and P.Jesintha, Public Private Partnership in India, Journal of Management and Science, Vol. 1, No.1, Sep 2011, pp "DND flyway toll hike: Noida residents to file PIL " Indian Express, Noida, (Sun Nov ) 5. India s love affair with public-private partnerships faces a stern test, The Economists, (Dec 15th 2012, Chennai) 6. Public Private Partnership: A means or an end?, The Economic Times, Dr.RamSingh, (May 7, 2009) 7. Govt for independent regulators to promote PPP projects, Indian tollways, an e- magazine, (29 Apr, 2013) ia.pdf Report by CAG Implementation of Public Private Partnership, Indira Gandhi International Airport, Delhi 13. A case study GMR s Terminal 3 for Delhi Airport: A Successful Project Execution Model for Public-Private Partnership Initiatives? Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 53

65 14. A case study by Planning Commission Bidding Process for the Delhi and Mumbai Airports 15. GMR s Website 16. Case Study by Planning Commission- Commercial use of land at Delhi and Mumbai Airports- An analysis of the questions of law and public policy Structuring PPPs in Aviation Sector: Case of Delhi and Mumbai Airport Privatization by IIM Ahmadabad Accelerating PPP in India by FICCI and Ersnt & Young Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 54

66 Appendix A Mentor Meeting minutes Date: May 22, 2013 Person: Shri Alok Shekhar Designation: Private Secretary, Minister of State, Ministry of external Affairs Discussion Decided the structure of the paper I was asked to take four major projects from four different sectors One being DND flyover and the second one is Delhi Airport and rest two will be decided within few days Study the success and failure of the concerned projects What is the main aim behind PPP projects and conduct a study to see if that aim is met or not Further some data regarding PPP projects in India can be collected from experts Action Items before Next Discussion Need to mail my mentor a proper structure of the paper first Research about four major PPP Projects in India Find out the reasons behind the success and failure of the projects Research about the problems concerned and how can we overcome them and Provide Recommendations or ways to improve Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 55

67 Date: June 7, 2013 Person: Shri Alok Shekhar Designation: Private Secretary, Minister of State, Ministry of external Affairs Discussion Discussed the rough questionnaire that is to be used in further field visits Issues with DND and recommendations Delhi airport case study briefly discussed and got an appointment fixed with the CFO of GMR Discussed the pros and con of Bidding criteria and toll based highway Discussed the policy initiatives taken by the government in last decade to Increase the efficiency of PPP projects in India. Projects have shown a lot of Improvement. In order to ensure transparency in the process the Government has introduced model documents. Discussed two-stage competitive bidding for award of concession contracts inplace, two stage process in which private party need to submit Request for Qualification (RfQ) and Request for Proposal (RfP) documents either it s a small or large projects. In the first stage technical evaluation is done and say top 5 companies are selected and in the second stage they are asked to submit financial bids Thought of taking DND as a benchmark and with the help of Mr. Praveen choose one recent highway project and compare. Now we have come long way from projects like DND Action Items before Next Discussion Need to complete all the field visits Analyze the success of the project by judging the performance on parameters like was the project timely completed, if cost overruns are there and compare it with government funded projects Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 56

68 The main of the case studies is to see have change in policies made PPP really efficient, find out the issues and challenges, recommend changes and how we can handle implementation issue and improve efficacy After discussing with Mr. Praveen from planning commission have to decide on which highway project should I take Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 57

69 Meetings and Interviews Date: June 8, 2013 Person: Ms. Anna Roy Designation: Director, Department of Financial Services, Ministry of Finance, Govt. of India, New Delhi, and the Director of Corporation Bank representing the Central Government as Government Nominee Director Discussion: Meeting Ms. Anna Roy helped in this report as she gave the true picture of PPP in India. It was found that the Government has taken many policy initiatives in last decade to increase the efficiency of PPP projects in India. Projects have shown a lot of Improvements as well. In order to ensure transparency in the process the government has introduced model documents. Like now there is two-stage competitive bidding for award of concession contracts in place, two stage process in which private party need to submit Request for Qualification (RfQ) and Request for Proposal (RfP) documents either it s a small or large projects. In the first stage technical evaluation is done and top few companies are selected and in the second stage they are asked to submit financial bids. The most improvement point is selection criteria, there is be no opaqueness, it should be highly transparent. At the time of awarding contract itself each and every point should be covered and all uncertainty should be addressed. So the best recommendation is every PPP project should be awarded by the way of Fair competitive bidding only. Earlier because every company has to come up with their own contract there was a lot of transaction cost involved but now there are standard contracts used. Model agreements are developed in metro, highway, port, airport etc. Final selection evaluation should be objective not subjective like in the case of Delhi and Mumbai International Airports like in that case they were asked to submit their plan of action and management and proposals if the concession period if 60 years and Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 58

70 given various situations but the outcome of this was far from satisfactory. After this it was realized that everything can go wrong if final evaluation is that much subjective. The process was not transparent and was not even accountable. Hence selection is most crucial, right partner needs to be selected. Also as a private player you should not leave or get any approval after getting selected. Government should give everything upfront. By this uncertainty decreases as well Earlier Item rate contract was followed and was source of corruption. When it was changed there was lot of opposition but things changed and are highly transparent now. Now it s more about output specification instead of input specification. The main problem that still exists is DPR (detailed project report) is poorly made. People bid really high than required. People prefer BOT (annuity), so one solution is we can have a regulatory on the rack to look after. And there are still some implementation issues. There is a need to convince big investors and promote PPP. The main important issues are in land acquisition, environment clearances, and statutory clearances but because of these we can t blame PPP as a policy. So to see the success of the project we can judge the performance on parameters like was the project timely completed, if cost overruns are there and compare it with government funded projects The main aim of the case studies is to see have change in policies made PPP really efficient, find out the issues and challenges, recommend changes and how we can handle implementation issue and improve efficacy Date: June 10, 2013 Person: Mr. Praveen Mahto Designation: Director, Infrastructure, Planning Commision Discussion: Mr. Praveen elaborated on the Model Concession agreements available for different sectors on the website of Planning Commission. It was advised to find out Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 59

71 the issues from case studies and information available about DND flyway and see has the new policies able to address the issues The key finding was that Hyderabad Metro is one of the most efficient example of PPP in India. Date: June 25, 2013 Person: Mr.Sidharath Kapur Designation: President and Chief Financial Officer- Airports, GMR Discussion: The main aim of the meeting was to find out the point of view of private partners on the current scenario of PPP and the policy framework. When asked how supportive and helpful the Government is It was identified that government have been really supportive in terms of all the approvals, agreements, Financial aid etc In a report titled "Implementation of Public Private Partnership, Indira Gandhi International Airport, Delhi" the Comptroller and Auditor General of India (CAG) has found faults in almost every step of implementation of the Public Private Partnership (PPP) model in the brown field privatization of New Delhi's Indira Gandhi International Airport (IGIA). Regarding the controversial report by CAG on Delhi airport project, it accuses the Ministry of Civil Aviation, headed by Mr. Patel, of violating laws, and providing post contractual benefits to DIAL, to the detriment of the government as well as the travelling public. But it was identified that there were no post contractual changes or renegotiations. Bidding was fair. It was found that the major issue with PPP in India is that it is treated more like a public project so to make it more efficient private players need autonomy. They want government to design proper contract Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 60

72 and all clauses and after that just leave it to private player and let them work accordingly. PPP should be kept away from imposition of bureaucratic hurdles. Private Players think that keeping PPP project out of purview of RTI act will result in increasing the efficiency as there is more pressure on concessionaire while working because of this clause they need their freedom to work as a private party. So According to Mr. Sidharath Kapur RTI should not apply. When asked about the issue of levy and removal of ADF (Airport Development fees) frequently, it was found that it s more like capital grant which helps in decreasing the charges on the permanent basis. It is advantageous to both customers as well as the concessionaire because private partner gets additional capital stream and customers will end up paying less in long term as ADF is for limited period normally three years. Use of Model Agreements in airport sector like highways was thought of one solution before this interview but it was found that Model agreements cannot be used as each airport is very different project like Delhi airport is a brownfield project. There should be a proper mechanism for renegotiation in between if required but should be avoided. And this should be mutual and rational. Hence main thing is that agreement should be clearly drafted like GMR says it was efficiently designed in case of Delhi airport. When Asked if 60 year concession period is good enough to cover the costs, it was realized that yes it is fair. Also GMR is grateful to government for the support and is in favour of PPP as a policy. SSA covers all the performance standard agreement which need to be strictly followed by the concessionaire, and these are strictly followed in case of Delhi airport. But one problem is there are no performance standards for other stakeholders, which need to be in place. Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 61

73 On cost overruns, GMR CFO said that as a private partner you quote revenue share and the regulator, AERA in this case decides the cost its not like EPC where you decide all the costs. But actual costs are almost always different from estimated one s because of the uncertain increase in prices of inputs Government over regulation instead of increasing efficiency end up decreasing it, in case of Delhi airport project GMR appointed KPMG and Engineer India as regulators to look into matters like is cost increase fair or not and if infrastructure in build in time or not. Delhi Airport Terminal 3 was built in just 37 months because of Common wealth Games held in Delhi in 2010 so it was examined if time pressure was a problem. It was found that yes because of time bounds GMR had to face a lot issues like many contractors were not ready to take the risk and it also led to cost over runs in some sense. In contrast to CAG report, Mr. Sidharath Kapur says that there were no post bidding changes and passenger fees is lowest if compared to other airports all over the world. The airport has been adjudged as the second best in the world in the category of million passengers per annum by Airports Council International. accusing the Ministry of giving DIAL land worth more than Rs. 24,000 Crore for a sum of Rs. 31 lakhs, and an annual payment of Rs. 100 only. In contrast to allegations put on GMR by CAG on The report alleges the virtual give-away of land to DIAL, it was said that here comes the role of economics. While bidding and submitting the revenue share all these are considered so had it been the case that land was costly simply the revenue share bid by GMR would have been less. Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 62

74 The highest measure of democracy is neither the extent of freedom nor the extent of equality but rather the highest measure of participation. - A.D. Benoist Rakshak Foundation creates awareness domestically and internationally about the rights and responsibilities of citizens towards the society and state. Rakshak engages in and supports social and scientific research on public policy and social issues. GET INSPIRED IDENTIFY YOUR PASSION GET INVOLVED Contact: secretary@rakshakfoundation.org Website: Disclaimer: This report is an outcome of a student project and the content of this report represents the views of its author. Neither the report nor any of its parts represent the views of Rakshak Foundation and/or any of its affiliates and officials in any capacity whatsoever. The figures and facts used in the report are only suggestive and cannot be used to initiate any legal proceedings against any person or organization. However, the author shall be extremely grateful to acknowledge any inaccuracies in the report brought to author s notice. Please your suggestions or concerns to: hr@rakshakfoundation.org] Copyright 2013 Rakshak Foundation. All Rights Reserved. Page 63

Resume of GAJENDRA HALDEA

Resume of GAJENDRA HALDEA Resume of GAJENDRA HALDEA Gajendra Haldea graduated in Economics and Law at the University of Rajasthan and joined the Indian Administrative Service in 1973. He later went for a Fellowship at the London

More information

Public-Private Partnership

Public-Private Partnership Public-Private Partnership Abstract Public-private partnerships are often touted as a best-of-both-worlds alternative to public provision and privatization. But in practice, they have been dogged by contract

More information

EAST COAST ROAD, TAMIL NADU, INDIA. Case Study (Transportation) Project Summary:

EAST COAST ROAD, TAMIL NADU, INDIA. Case Study (Transportation) Project Summary: EAST COAST ROAD, TAMIL NADU, INDIA Case Study (Transportation) Project Summary: The southern India state of Tamil Nadu has been a leader in the area of urban sector reforms and has established an efficient

More information

Public Private Partnership Projects in India

Public Private Partnership Projects in India Public Private Partnership Projects in India PPP Workshop July 19-21, 2010 Islamic Republic of Iran Ministry of Economic Affairs & Finance, OIETA of Iran Prof. Sharad Pradhan Associate Professor Department

More information

Public Private Partnership. PPP Policy Overview. Policy and Planning Division Ministry of Economic Affairs

Public Private Partnership. PPP Policy Overview. Policy and Planning Division Ministry of Economic Affairs Public Private Partnership PPP Policy Overview Policy and Planning Division Ministry of Economic Affairs Delivery of Public Services Outsourcing: short-term contracts and parts of public service PPPs:

More information

ANNEX A THE IMPLEMENTATION ROADMAP TO DEVELOP SUCCESSFUL INFRASTRUCTURE PUBLIC-PRIVATE PARTNERSHIP (PPP) PROJECTS IN THE APEC REGION

ANNEX A THE IMPLEMENTATION ROADMAP TO DEVELOP SUCCESSFUL INFRASTRUCTURE PUBLIC-PRIVATE PARTNERSHIP (PPP) PROJECTS IN THE APEC REGION Beijing, the People s Republic of China, 22 October 2014 2014 APEC Finance Ministers Meeting Joint Ministerial Statement ANNEX A THE IMPLEMENTATION ROADMAP TO DEVELOP SUCCESSFUL INFRASTRUCTURE PUBLIC-PRIVATE

More information

Government of Grenada PPP Policy July 2014

Government of Grenada PPP Policy July 2014 Government of Grenada PPP Policy July 2014 1 Contents 1 Introduction 3 2 PPP Definition 4 3 Objectives and Scope 6 3.1 Objectives and Scope of Grenada s PPP Programme 6 3.2 Objectives of Grenada s National

More information

Policy Resolution for Promotion of. Petroleum, Chemicals and Petrochemical Investment Regions (PCPIRs)

Policy Resolution for Promotion of. Petroleum, Chemicals and Petrochemical Investment Regions (PCPIRs) Policy Resolution for Promotion of Petroleum, Chemicals and Petrochemical Investment Regions (PCPIRs) POLICY OBJECTIVES 1. The Petroleum, Chemicals and Petrochemical industry in India is well established

More information

LAW ON PUBLIC-PRIVATE PARTNERSHIP IN THE REPUBLIC OF SRPSKA

LAW ON PUBLIC-PRIVATE PARTNERSHIP IN THE REPUBLIC OF SRPSKA LAW ON PUBLIC-PRIVATE PARTNERSHIP IN THE REPUBLIC OF SRPSKA Article 1 This Law regulates the scope, principles, manner, and forms of public-private partnership, requirements for the establishment of a

More information

Public Private Partnership PPP & The Egyptian Experience

Public Private Partnership PPP & The Egyptian Experience Public Private Partnership PPP & The Egyptian Experience Bassel Shoirah Project Manager / Utilities Sector - Egypt Good Governance for Development In Arab Countries initiatives of the OECD July 8, 2009

More information

Public-Private Partnerships in the Airport Sector Structured Guidelines for PPP Implementation

Public-Private Partnerships in the Airport Sector Structured Guidelines for PPP Implementation Public-Private Partnerships in the Airport Sector André Franco Pena Seminar AIRDEV Business Models for Airport Development Lisbon, 20 October 2011 1 OUTLINE Introduction Public-Private Partnerships in

More information

Principal Barriers/ Constraints to Successful Public-Private Partnerships

Principal Barriers/ Constraints to Successful Public-Private Partnerships High-level Expert Group Meeting on Infrastructure Public-Private Partnerships for Sustainable Development 11-13 November 2012 Tehran, Islamic Republic of Iran Principal Barriers/ Constraints to Successful

More information

BENCHMARKING PPP PROCUREMENT 2017 IN MALAYSIA

BENCHMARKING PPP PROCUREMENT 2017 IN MALAYSIA BENCHMARKING PPP PROCUREMENT 2017 IN MALAYSIA Regulatory and Institutional Framework for PPPs Does the regulatory framework in your country allow procuring PPPs?. specify the relevant regulatory framework

More information

INTRODUCTION TO DECREE 15 ON PPP

INTRODUCTION TO DECREE 15 ON PPP INTRODUCTION TO DECREE 15 ON PPP After nearly two years of drafting and stakeholder consultation, the Vietnamese Government has promulgated a unified legislation (Decree No. 15/2015/ND-CP) governing private

More information

Bridging the gaps Implementation challenges for transport PPPs in OIC member states

Bridging the gaps Implementation challenges for transport PPPs in OIC member states Bridging the gaps Implementation challenges for transport PPPs in OIC member states March 28, 2013 Vanesa Sanchez, Senior Analyst Economist Intelligence Unit What are PPPs? Introduction PPPs are public-private

More information

BENCHMARKING PPP PROCUREMENT 2017 IN NEPAL

BENCHMARKING PPP PROCUREMENT 2017 IN NEPAL BENCHMARKING PPP PROCUREMENT 2017 IN NEPAL Regulatory and Institutional Framework for PPPs Does the regulatory framework in your country allow procuring PPPs?. specify the relevant regulatory framework

More information

PER13 PPP. Terms of Reference for consultancy on Public Private Partnerships in the Transport sector

PER13 PPP. Terms of Reference for consultancy on Public Private Partnerships in the Transport sector PER13 PPP Terms of Reference for consultancy on Public Private Partnerships in the Transport sector I. Background Public Private Partnership (PPP) is an important instrument for the Government to attract

More information

The Draft National Public Private Partnership Policy

The Draft National Public Private Partnership Policy The Draft National Public Private Partnership Policy Preliminary Comments Submitted by Ms. Maja Daruwala & Venkatesh Nayak Commonwealth Human Rights Initiative (CHRI) B 117, First Floor, Sarvodaya Enclave,

More information

Queen Alia International Airport Expansion

Queen Alia International Airport Expansion JORDAN Queen Alia International Airport Expansion Image: Aerial view of the terminal after completion by KRISTIN HOOVER, courtesy of Foster and Partners- Photographer Nigel Young / CC BY-NC-ND 3.0 OVERVIEW

More information

Terms of References Recruitment of Consultant for PPP Legal and Institutional Framework Review Republic of Cote d Ivoire

Terms of References Recruitment of Consultant for PPP Legal and Institutional Framework Review Republic of Cote d Ivoire Terms of References Recruitment of Consultant for PPP Legal and Institutional Framework Review Republic of Cote d Ivoire I. The Context After years of political instability, Cote D Ivoire has entered into

More information

PPP IN HEALTH SECTOR: POLICY FRAMEWORK & INSTITUTIONAL CAPACITY

PPP IN HEALTH SECTOR: POLICY FRAMEWORK & INSTITUTIONAL CAPACITY PPP IN HEALTH SECTOR: POLICY FRAMEWORK & INSTITUTIONAL CAPACITY 14th Arab Conference 7th Dec, 2015, Amman A.VENKAT RAMAN FACULTY OF MANAGEMENT STUDIES UNIVERSITY OF DELHI avr@fms.edu A.VENKAT RAMAN FMS-DU

More information

TANZANIA PETROLEUM DEVELOPMENT CORPORATION TENDER NO. PA/031/ /C/10 FOR

TANZANIA PETROLEUM DEVELOPMENT CORPORATION TENDER NO. PA/031/ /C/10 FOR TANZANIA PETROLEUM DEVELOPMENT CORPORATION TENDER NO. PA/031/2018-2019/C/10 FOR CONSULTANCY SERVICES FOR FEASIBILITY STUDY FOR IMPLEMENTATION OF REGIONAL NATURAL GAS DISTRIBUTION PROJECT UNDER PPP MODEL

More information

NIMZ Guidelines :- From : CA Ratan Moondra. Presentation on National Investment & Manufacturing Zone

NIMZ Guidelines :- From : CA Ratan Moondra. Presentation on National Investment & Manufacturing Zone NIMZ Guidelines :- From : CA Ratan Moondra Presentation on National Investment & Manufacturing Zone GUIDELINES FOR ESTABLISHMENT OF NATIONAL INVESTMENT & MANUFACTURING ZONES (NIMZS) o Background o Application

More information

Session 2: Infrastructure finance and public-private partnerships. Presentation. Infrastructure Finance and Public- Private Partnerships

Session 2: Infrastructure finance and public-private partnerships. Presentation. Infrastructure Finance and Public- Private Partnerships MINISTRY OF FINANCE REPUBLIC OF INDONESIA Asia-Pacific Outreach Meeting on Sustainable Development Financing 10-11 June 2014 Djuanda Hall, Ministry of Finance Complex, Jakarta Session 2: Infrastructure

More information

This document is being disclosed to the public in accordance with ADB s Public Communications Policy 2011.

This document is being disclosed to the public in accordance with ADB s Public Communications Policy 2011. Technical Assistance Report Project Number: 48230-001 Capacity Development Technical Assistance (CDTA) December 2014 India: Supporting Public Private Partnerships for Infrastructure Development This document

More information

WHY PPPs INFRASTRUCTURE DEVELOPMENT AND FINANCING

WHY PPPs INFRASTRUCTURE DEVELOPMENT AND FINANCING WHY PPPs INFRASTRUCTURE DEVELOPMENT AND FINANCING G Raghuram Indian Institute of Management Ahmedabad IDF GR/IIMA Outline What is Infrastructure Characteristics of Infrastructure Drivers for Commercial

More information

BRIEFING TO THE PORTFOLIO COMMITEE ON CORRECTIONAL SERVICES OUTSOURCING SERVICES 09 SEPTEMBER 2009

BRIEFING TO THE PORTFOLIO COMMITEE ON CORRECTIONAL SERVICES OUTSOURCING SERVICES 09 SEPTEMBER 2009 BRIEFING TO THE PORTFOLIO COMMITEE ON CORRECTIONAL SERVICES ON OUTSOURCING SERVICES 09 SEPTEMBER 2009 REPUTATION PROMISE / MISSION The Auditor-General has a constitutional mandate and, as the Supreme Audit

More information

Competitive Selection of Concessionaires

Competitive Selection of Concessionaires World Bank & Brazilian Ministry of Transport Workshop on the Toolkit for PPP in Roads and Highways Competitive Selection of Concessionaires Cesar Queiroz World Bank Brasilia, Brazil, June 8-9, 2010 Procurement

More information

Policy,Legal and Regulatory Frameworks

Policy,Legal and Regulatory Frameworks Policy,Legal and Regulatory Frameworks Anthony Smith Chairman PPP Experts Head of Legal Dept. Altra Capital Member United Nations PPP Team of Specialists Former Head of United Nations PPP Readiness Task

More information

INSTITUTIONAL CAPACITY ASSESSMENT

INSTITUTIONAL CAPACITY ASSESSMENT Demand-Side Energy Efficiency Sector Project (RRP IND 48224) INSTITUTIONAL CAPACITY ASSESSMENT A. Overview 1. Introduction. Energy Efficiency Services Limited (EESL) has been set up under the Indian Companies

More information

INSEAD PPPs as Policy Instruments. Abraham Akkawi November 29, 2010

INSEAD PPPs as Policy Instruments. Abraham Akkawi November 29, 2010 INSEAD PPPs as Policy Instruments Abraham Akkawi November 29, 2010 Content PPP Defined PPP Advantages PPP Types Public Sectors Readiness Sample PPP example in the MENA region Case Study: Mafraq-Gweifat

More information

HIGHLIGHTS OF THE ECONOMIC POLICY OF THE LEBANESE GOVERNMENT EXTRACTED FROM THE MINISTERIAL POLICY STATEMENT - NOVEMBER

HIGHLIGHTS OF THE ECONOMIC POLICY OF THE LEBANESE GOVERNMENT EXTRACTED FROM THE MINISTERIAL POLICY STATEMENT - NOVEMBER Republic of Lebanon Ministry of Finance HIGHLIGHTS OF THE ECONOMIC POLICY OF THE LEBANESE GOVERNMENT EXTRACTED FROM THE MINISTERIAL POLICY STATEMENT - NOVEMBER 2000 - The Ministerial policy statement outlines

More information

PPP Model: Success Stories & Lessons from Failure Indo Italian Chamber of Commerce & Industries

PPP Model: Success Stories & Lessons from Failure Indo Italian Chamber of Commerce & Industries PPP Model: Success Stories & Lessons from Failure Indo Italian Chamber of Commerce & Industries 1 July 2010 PPP is everywhere 2 Yet PPP is hardly understood and much misused 3 Presentation Structure PPP

More information

Scheme and Guidelines for Financial Support to. Public Private Partnerships in Infrastructure

Scheme and Guidelines for Financial Support to. Public Private Partnerships in Infrastructure Scheme and Guidelines for Financial Support to Public Private Partnerships in Infrastructure Government of India Ministry of Finance Department of Economic Affairs Scheme and Guidelines for Financial

More information

CONTRIBUTION TO PFPPP DEFINITION

CONTRIBUTION TO PFPPP DEFINITION CONTRIBUTION TO PFPPP DEFINITION 1. What form of PPP should be championed for People First PPP meeting the SDGs? (Transmitted to UNECE in August 2016) I. GENERAL A most critical question for which you

More information

FAIR COMPETITION, TRANSPARENCY AND PROCUREMENT: ATTRACTING EU INVESTMENT TO THE PHILIPPINES

FAIR COMPETITION, TRANSPARENCY AND PROCUREMENT: ATTRACTING EU INVESTMENT TO THE PHILIPPINES FAIR COMPETITION, TRANSPARENCY AND PROCUREMENT: ATTRACTING EU INVESTMENT TO THE PHILIPPINES Tuesday 17 February The Mind Museum, Bonifacio Global City Remarks by Ambassador Guy Ledoux, Delegation of the

More information

Fact Track-Power Distribution Sector in India

Fact Track-Power Distribution Sector in India June 2013 Fact Factor Report Series Copyright 2013, All rights reserved Fact Track-Power Distribution Sector in India 2 Power Distribution Sector in India- An Overview Research Base AT&C Losses Over the

More information

Overview on the Development of the Egyptian PPP Program

Overview on the Development of the Egyptian PPP Program Overview on the Development of the Egyptian PPP Program Rania G. Zayed Advisor to Minister Director, Ministry of Finance USAID Infrastructure Workshop December 19, 2008 1 Agenda PPP Drivers Egypt - PPP

More information

AIRPORT CAPACITY AND THE MODERN INFRASTRUCTURE CHANGES. The developments in India have been quite remarkable. Privatisation has changed the face

AIRPORT CAPACITY AND THE MODERN INFRASTRUCTURE CHANGES. The developments in India have been quite remarkable. Privatisation has changed the face AIRPORT CAPACITY AND THE MODERN INFRASTRUCTURE CHANGES By Sumeet Kachwaha Talk on 2.10.2012 at Dublin IBA Conference Introduction: The developments in India have been quite remarkable. Privatisation has

More information

TRANSMISSION OPPORTUNITIES, CHALLENGES & WAY FORWARD. Confederation of Indian Industry NEW DELHI November 2, 2012

TRANSMISSION OPPORTUNITIES, CHALLENGES & WAY FORWARD. Confederation of Indian Industry NEW DELHI November 2, 2012 TRANSMISSION OPPORTUNITIES, CHALLENGES & WAY FORWARD Confederation of Indian Industry NEW DELHI RAJEEV DALELA CII - Conference on Transmission and Distribution 1 Power Sector : Demand Drivers Demand far

More information

Public Procurement Reforms to enhance value for money

Public Procurement Reforms to enhance value for money Public Procurement Reforms to enhance value for money 1. It is my pleasure to be here in the inaugural function of the Seminar on Public Procurement Reforms to enhance value for money being organized by

More information

International Seminar on Strengthening Public Investment and Managing Fiscal Risks from Public-Private Partnerships

International Seminar on Strengthening Public Investment and Managing Fiscal Risks from Public-Private Partnerships International Seminar on Strengthening Public Investment and Managing Fiscal Risks from Public-Private Partnerships Budapest, Hungary March 7 8, 2007 The views expressed in this paper are those of the

More information

Main steps of a national PPP program

Main steps of a national PPP program Main steps of a national PPP program The launch of a national PPP program is a major policy initiative, whether it is for a single stand-alone project or a pipeline of potential PPP projects. The main

More information

International Airport Expansion Project. Terms of Reference for Legal Advisor

International Airport Expansion Project. Terms of Reference for Legal Advisor A. Background International Airport Expansion Project Terms of Reference for Legal Advisor 1. [ ] International Airport (IA) is a medium size airport with a total passenger per year volume of [ ]. IA has

More information

Case Study UNDERGROUND SEWERAGE SYSTEM ALANDUR. Sewerage

Case Study UNDERGROUND SEWERAGE SYSTEM ALANDUR. Sewerage Case Study UNDERGROUND SEWERAGE SYSTEM ALANDUR Sewerage 1 CASE OVERVIEW Country: India ULB: Alandur, Chennai Metropolitan Area in Tamil Nadu Sector: Urban Basic Services Sub-Sector: Sewerage Award Date:

More information

Report of the. Inter-Ministerial Task Force. Draft Port Regulatory Authority Bill

Report of the. Inter-Ministerial Task Force. Draft Port Regulatory Authority Bill Report of the Inter-Ministerial Task Force on Draft Port Regulatory Authority Bill Planning Commission (Secretariat for PPP & Infrastructure) July 2012 PLANNING COMMISSION (Secretariat for PPP & Infrastructure)

More information

Minutes of the Pre-Bid Meeting for the PPP projects of Delhi Police held on 07 th June 2010 (11.30 A.M.) at Delhi Police Headquarters

Minutes of the Pre-Bid Meeting for the PPP projects of Delhi Police held on 07 th June 2010 (11.30 A.M.) at Delhi Police Headquarters Minutes of the Pre-Bid Meeting for the PPP projects of Delhi Police held on 07 th June 2010 (11.30 A.M.) at Delhi Police Headquarters The meeting was chaired by Special Commissioner of Police (Administration).

More information

Policy for Public Private Partnership in Kerala

Policy for Public Private Partnership in Kerala Policy for Public Private Partnership in Kerala 1. Preamble 1.1 Provision of public services and infrastructure has traditionally been the exclusive domain of the government (Government will continue to

More information

Government of India. Frequently Asked Questions on Model RFQ Document

Government of India. Frequently Asked Questions on Model RFQ Document Government of India Frequently Asked Questions on Model RFQ Document Published by The Secretariat for the Committee on Infrastructure Planning Commission, Government of India Yojana Bhawan, Parliament

More information

Financing Energy and Climate PPP based Infrastructures: Experiences and Emerging Trends. Venice, May 9th,2014

Financing Energy and Climate PPP based Infrastructures: Experiences and Emerging Trends. Venice, May 9th,2014 Financing Energy and Climate PPP based Infrastructures: Experiences and Emerging Trends Venice, May 9th,2014 PPPs are no silver bullet solution... Potential challenges Misaligned incentives Imperfect regulation,

More information

Template for ToR for Transaction Advisory Services

Template for ToR for Transaction Advisory Services Template for ToR for Transaction Advisory Services Addendum 1 Prepared by Genesis Analytics 4 December 2013 PPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR:PHI 30546 TECHNICAL ASSISTANCE (Financed by the Japan Special Fund) TO THE REPUBLIC OF THE PHILIPPINES FOR INSTITUTIONAL STRENGTHENING FOR THE DEVELOPMENT OF THE NATURAL GAS

More information

Corporate Governance Policies

Corporate Governance Policies Corporate Governance Policies 1/4/2018 Partial Revision and enforcement 1/10/2015 Establishment Kurita Water Industries Ltd. Table of contents 1.Basic Concept...2 2.Basic Policies...2 (1) Ensuring the

More information

Preparing for Urban Challenges of 21 st Century (Focus: Issues in Urban Water) February 17 th, 2014

Preparing for Urban Challenges of 21 st Century (Focus: Issues in Urban Water) February 17 th, 2014 Preparing for Urban Challenges of 21 st Century (Focus: Issues in Urban Water) February 17 th, 2014 J B Ravinder Deputy Advisor(PHE) Central Public Health & Env. Engg.Orgn(CPHEEO) Government of India Ministry

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY (RENEWABLE ENERGY GENERATION SOLAR)

SECTOR ASSESSMENT (SUMMARY): ENERGY (RENEWABLE ENERGY GENERATION SOLAR) Installed capacity (GW) Solar Rooftop Investment Program (RRP IND 49419) Sector Road Map SECTOR ASSESSMENT (SUMMARY): ENERGY (RENEWABLE ENERGY GENERATION SOLAR) 1. Sector Performance, Problems, and Opportunities

More information

Policy, legal and regulatory frameworks for successful PPPs

Policy, legal and regulatory frameworks for successful PPPs Policy, legal and regulatory frameworks for successful PPPs Anthony Smith Member UN PPP Team of Specialists Former Head of United Nations PPP Readiness Task Force Associate Expert, UNDP Farne Project Consultancy

More information

Public-Private Partnerships in the Airport Sector Structured Guidelines for PPP Implementation

Public-Private Partnerships in the Airport Sector Structured Guidelines for PPP Implementation Public-Private Partnerships in the Airport Sector André Franco Pena AIRDEV 2012 Business Models for Airport Development Lisbon, 19 April 2012 1 OUTLINE 1 2 3 4 5 Introduction Public-Private Partnerships

More information

Application for the PPP Experts. 1. Advertisement published in newspapers 2. Remuneration and Qualification 3. CV Format for Applicants

Application for the PPP Experts. 1. Advertisement published in newspapers 2. Remuneration and Qualification 3. CV Format for Applicants Application for the PPP Experts 1. Advertisement published in newspapers 2. Remuneration and Qualification 3. CV Format for Applicants DEPARTMENT OF FINANCE (PPP CELL), GOVERNMENT OF WEST BENGAL No. 244/JS(PY)/FD(PPP)

More information

Improving public investment efficiency for infrastructure development

Improving public investment efficiency for infrastructure development Policy Dialogue on Infrastructure Financing Strategies for Sustainable Development in South-East Asia Manila, 29-30 August 2017 Improving public investment efficiency for infrastructure development Mr

More information

(To be published in the Gazette of India, Part I, Section 1) RESOLUTION. Tariff based Competitive-bidding Guidelines for Transmission Service

(To be published in the Gazette of India, Part I, Section 1) RESOLUTION. Tariff based Competitive-bidding Guidelines for Transmission Service (To be published in the Gazette of India, Part I, Section 1) No. 11/5/2005-PG(i) GOVERNMENT OF INDIA Ministry of Power. RESOLUTION New Delhi, Date: 17th April, 2006 Tariff based Competitive-bidding Guidelines

More information

Finalized Scope of Work for Preparation of Report on Setting up of Water Supply & Sewerage Board or Company in the State of Madhya Pradesh

Finalized Scope of Work for Preparation of Report on Setting up of Water Supply & Sewerage Board or Company in the State of Madhya Pradesh Finalized Scope of Work for Preparation of Report on Setting up of Water Supply & Sewerage Board or Company in the State of Madhya Pradesh 1. Background The Government of Madhya Pradesh through the Urban

More information

UNITED KINGDOM Intercity Express Programme SUMMARY

UNITED KINGDOM Intercity Express Programme SUMMARY INTERCITY EXPRESS PROGRAMME UNITED KINGDOM Intercity Express Programme Image: Class 800 Trains with Train Operating Company (TOC) Liveries Courtesy of the UK Department for Transport OVERVIEW Location

More information

RWE Thames Water. GREEN PAPER ON PUBLIC-PRIVATE PARTNERSHIPS AND COMMUNITY LAW ON PUBLIC CONTRACTS AND CONCESSIONS COM(2004) 327 final

RWE Thames Water. GREEN PAPER ON PUBLIC-PRIVATE PARTNERSHIPS AND COMMUNITY LAW ON PUBLIC CONTRACTS AND CONCESSIONS COM(2004) 327 final GREEN PAPER ON PUBLIC-PRIVATE PARTNERSHIPS AND COMMUNITY LAW ON PUBLIC CONTRACTS AND CONCESSIONS COM(2004) 327 final Position RWE Thames Water Introduction: RWE Thames Water welcomes the Commission s Green

More information

Our s : /

Our  s : / Introduction This handbook is an attempt to produce a working guide for PPP practitioners in the various departments of Government of Uttarakhand. Uttarakhand PPP Cell (UPPPC) has collected information

More information

PUBLIC PRIVATE PARTNERSHIP IN CONSTRUCTION INDUSTRY

PUBLIC PRIVATE PARTNERSHIP IN CONSTRUCTION INDUSTRY PUBLIC PRIVATE PARTNERSHIP IN CONSTRUCTION INDUSTRY Pintu Badatiya 1, Bhavin Kashiyani 2 Student, M.E (C.E.M), SNIPT & RC, Umrakh), Bardoli, Gujarat, India 1 Asst. Proff., M.E (CEM), SNPIT & RC, Umrakh),

More information

PRESIDENTIAL REGULATION OF THE REPUBLIC OF INDONESIA NUMBER 13 OF 2010 REGARDING

PRESIDENTIAL REGULATION OF THE REPUBLIC OF INDONESIA NUMBER 13 OF 2010 REGARDING PRESIDENTIAL REGULATION OF THE REPUBLIC OF INDONESIA NUMBER 13 OF 2010 REGARDING AMENDMENT UPON PRESIDENTIAL REGULATION NUMBER 67 OF 2005 REGARDING THE COOPERATION BETWEEN THE GOVERNMENT AND THE BUSINESS

More information

Kosovo s PPP Policy, Legal, & Institutional Framework

Kosovo s PPP Policy, Legal, & Institutional Framework MODULI 1 Kosovo s PPP Policy, Legal, & Institutional Framework Case study PIA concesssion 02, November 2016 Arton Ahmeti Central Public-Private Partnership Department Ministry of Finance 2 Overview Investment

More information

that these standards can only be delivered effectively by devolution of responsibility to the frontline;

that these standards can only be delivered effectively by devolution of responsibility to the frontline; UK GOVERNMENT RESPONSE TO THE EUROPEAN COMMISSION S GREEN PAPER ON PUBLIC-PRIVATE PARTNERSHIPS AND COMMUNITY LAW ON PUBLIC CONTRACTS AND CONCESSIONS, MAY 2004 The UK Government welcomes the debate on the

More information

Managing PPP in Korea through A Think Tank Institution

Managing PPP in Korea through A Think Tank Institution Managing PPP in Korea through A Think Tank Institution Jay-Hyung Kim (jaykim@kdi.re.kr) Public and Private Infrastructure Investment Management Center (PIMAC) Korea Development Institute (KDI) OECD Second

More information

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Project Delivery Methods January 30, 2012 Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Terms Capital Project Capital Program Prioritized Capital Plan

More information

Guidelines for the Development of a Policy for Managing Unsolicited Proposals in Infrastructure Projects

Guidelines for the Development of a Policy for Managing Unsolicited Proposals in Infrastructure Projects Draft Document Shared for Consultation Purposes Only Not for Redistribution Guidelines for the Development of a Policy for Managing Unsolicited Proposals in Infrastructure Projects March 2017 Draft Document

More information

PROCUREMENT - FOLLOW-UP

PROCUREMENT - FOLLOW-UP PROCUREMENT - FOLLOW-UP 25. PROCUREMENT - FOLLOW-UP BACKGROUND.1 The Government Purchases Act controls the acquisition of goods in government. The Act assigns responsibility for acquisition of goods to

More information

The path to successful PPP projects

The path to successful PPP projects Policy Dialogue on Infrastructure Financing Strategies for Sustainable Development in North and Central Asia Tbilisi, 7-8 June 2017 The path to successful PPP projects Mr Mathieu Verougstraete Economic

More information

Development, Operation and Maintenance of Greenfield International Airport at Bhogapuram, Vizianagaram District, Andhra Pradesh

Development, Operation and Maintenance of Greenfield International Airport at Bhogapuram, Vizianagaram District, Andhra Pradesh Andhra Pradesh Airports Development Corporation Limited (APADCL) Development, Operation and Maintenance of Greenfield International Airport at Bhogapuram, Vizianagaram District, Andhra Pradesh Amendment

More information

Application of King III Corporate Governance Principles

Application of King III Corporate Governance Principles Application of Corporate Governance Principles / 1 This table is a useful reference to each of the principles and how, in broad terms, they have been applied by the Group. The information should be read

More information

PUBLIC-PRIVATE PARTNERSHIP

PUBLIC-PRIVATE PARTNERSHIP PUBLIC-PRIVATE PARTNERSHIP Law firm Sajic GP Banja Luka Bulevar vojvode Zivojina Misica 49B, Banja Luka Bosnia and Herzegovina Tel: +387 51 227 620 Fax: +387 51 227 623 e-mail: info@afsajic.com www.advokatskafirmasajic.com

More information

COMPACT TO PROMOTE TRANSPARENCY AND COMBAT CORRUPTION: A NEW PARTNERSHIP BETWEEN THE G8 AND NICARAGUA

COMPACT TO PROMOTE TRANSPARENCY AND COMBAT CORRUPTION: A NEW PARTNERSHIP BETWEEN THE G8 AND NICARAGUA COMPACT TO PROMOTE TRANSPARENCY AND COMBAT CORRUPTION: A NEW PARTNERSHIP BETWEEN THE G8 AND NICARAGUA Nicaragua and the members of the G8 announce today their intention to cooperate in a Compact to Promote

More information

Infrastructure and Capital Projects

Infrastructure and Capital Projects Infrastructure and Capital Projects Contents Deloitte s Capabilities in Infrastructure and Capital Projects 1 Strategy and Planning 3 Financing and Procurement 4 Project Organisation, Execution and Construction

More information

NEW SOLUTIONS FOR ADMINISTRATION, PRODUCTION AND FUNDING OF THE TRANSPORT SYSTEM IN FINLAND

NEW SOLUTIONS FOR ADMINISTRATION, PRODUCTION AND FUNDING OF THE TRANSPORT SYSTEM IN FINLAND NEW SOLUTIONS FOR ADMINISTRATION, PRODUCTION AND FUNDING OF THE TRANSPORT SYSTEM IN FINLAND Tiina Korte Ministry of Transport and Communications, Finland 1. FOREWORD Finnish Ministry of Transport and Communications

More information

Global Infrastructure Facility

Global Infrastructure Facility Global Infrastructure Facility ------------------------------------------------------------------------------------------------------------------- Partnership Framework As Adopted by the Governing Council

More information

Public Private Partnerships in Fiji

Public Private Partnerships in Fiji Public Private Partnerships in Fiji Presentation to the Asia-Pacific Ministerial Conference on Public - Private Partnerships [PPPs] for Infrastructure Development Seoul, Korea, 5 th October 2007 Hon. Poseci

More information

KANPUR MUNCIPAL CORPORATION (PERSONNEL DEPARTMENT) PH , , FAX

KANPUR MUNCIPAL CORPORATION (PERSONNEL DEPARTMENT) PH , , FAX KANPUR MUNCIPAL CORPORATION (PERSONNEL DEPARTMENT) PH-0512-2531215, 2551416, FAX-0512-2531662 E-mail-kanpur_nagar.nigam@yahoo.co.in Letter No.: Date: HIRING OF PROFESSIONALS FOR PROGRAME IMPLEMENTATION

More information

Completion report and next steps. Yemen - Petroleum governance Petroleum Governance Initiative funded Technical Assistance P TAS-TF057534

Completion report and next steps. Yemen - Petroleum governance Petroleum Governance Initiative funded Technical Assistance P TAS-TF057534 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Completion report and next steps Yemen - Petroleum governance Petroleum Governance Initiative

More information

Trade Union Checklist. Partnerships (PPPs)

Trade Union Checklist. Partnerships (PPPs) trade union advisory coittee to the organisation for economic cooperation and development Coission syndicale consultative auprès de l organisation de coopération et de développement économiques Trade Union

More information

SECTOR ASSESSMENT (SUMMARY): TRANSPORT

SECTOR ASSESSMENT (SUMMARY): TRANSPORT Country Partnership Strategy: Pakistan, 2015 2019 SECTOR ASSESSMENT (SUMMARY): TRANSPORT Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Sector performance and problems. The transport

More information

PROJECTS (FINANCE AND INFRASTRUCTURE) VIETNAM APRIL 2015

PROJECTS (FINANCE AND INFRASTRUCTURE) VIETNAM APRIL 2015 client alert PROJECTS (FINANCE AND INFRASTRUCTURE) VIETNAM APRIL 2015 NEW PPP LEGAL FRAMEWORK ISSUED On 14 February 2015, the Government of Vietnam (the "Government") issued the longawaited Decree No.

More information

Introduction. Public services in transport in EU and Central Europe

Introduction. Public services in transport in EU and Central Europe Introducing market forces in public services in transport in an enlarged Europe by Arthur Gleijm, NEA Transport research and training in the Netherlands Introduction Lack of market initiatives and entrepreneurship

More information

Contracting for Goods and Services

Contracting for Goods and Services Contracting for Goods and Services Northwest Territories Office of the Auditor General of Canada Bureau du vérificateur général du Canada Ce document est également publié en français. This document is

More information

Pillar II. Institutional Framework and Management Capacity

Pillar II. Institutional Framework and Management Capacity PILLAR II. INSTITUTIONAL FRAMEWORK AND MANAGEMENT CAPACITY Pillar II. Institutional Framework and Management Capacity Pillar II assesses how the procurement system defined by the legal and regulatory framework

More information

Act on the Government Offices of Iceland 1)

Act on the Government Offices of Iceland 1) Official translation Act on the Government Offices of Iceland 1) Entered into force on 28 September 2011. Amended by Act no. 173/2011 (entered into force on 30 December 2011), Act no. 115/2012 (entered

More information

Make the complex manageable

Make the complex manageable Make the complex manageable Deal Advisory / Global We help create clear Solvency Strategies. Realizing value through insolvency. / 1 Your vision. Our proven capabilities. Insolvencies can test the limits

More information

Session 6: Financing South Asia s Urban Future: Good Practices in PPP for Urban Development

Session 6: Financing South Asia s Urban Future: Good Practices in PPP for Urban Development Session 6: Financing South Asia s Urban Future: Good Practices in PPP for Urban Development Regional Policy Dialogue, UNESCAP MOUD NIUA, December 18, 2014 Chandrima Sinha Director, IDFC Foundation PPPs

More information

Notice Inviting Expression of Interest

Notice Inviting Expression of Interest Notice Inviting Expression of Interest EOI Notice SURAT SITILINK LIMITED(SSL) Room No.95, SMC Main Office, Muglisara, Surat - 395 001. Notice Inviting EOI for "Hiring Service of Statutory Auditors, Internal

More information

Policy Dialogue on PPP Infrastructure Development in South Asia

Policy Dialogue on PPP Infrastructure Development in South Asia Policy Dialogue on PPP Infrastructure Development in South Asia 22-23 Sept, 2015 in Kathmandu SRI LANKA EXPERIENCE WITH PPP PROJECTS THE NATIONAL PPP (POLICY) provides a consistent framework that enables

More information

Social Services Investment Framework

Social Services Investment Framework Social Services Investment Framework Queensland Treasury and Trade Great state. Great opportunity. Foreword The Queensland Government invests in social services to support all Queenslanders, particularly

More information

Code of Corporate Governance

Code of Corporate Governance Code of Corporate Governance 1 FOREWORD From the Chairman of the General Purposes Committee I am pleased to endorse this Code of Corporate Governance, which sets out the commitment of Cambridgeshire County

More information

Action Fiche for Lebanon. Support to Reform Environmental Governance. EU contribution : EUR 8 million

Action Fiche for Lebanon. Support to Reform Environmental Governance. EU contribution : EUR 8 million Action Fiche for Lebanon 1. IDENTIFICATION Title/Number Total cost Method of implementation Support to Reform Environmental Governance EU contribution : EUR 8 million Decentralised management with the

More information

Corporate Governance Guidelines

Corporate Governance Guidelines Corporate Governance Guidelines Chapter 1. General Provisions Article 1. Purpose These guidelines set out the basic policy, framework and operating policy of the corporate governance of Fuji Heavy Industries

More information

PHASE TWO FOLLOW-UP REPORT ON THE AUDIT OF CONTRACTS (2008)

PHASE TWO FOLLOW-UP REPORT ON THE AUDIT OF CONTRACTS (2008) PHASE TWO FOLLOW-UP REPORT ON THE AUDIT OF CONTRACTS (2008) PREPARED BY: Government Audit Services Branch Government of Yukon APPROVED BY: Audit Committee Table of Contents Page PREFACE 3 EXECUTIVE SUMMARY

More information

NATIONAL PUBLIC PRIVATE PARTNERSHIP (PPP) POLICY

NATIONAL PUBLIC PRIVATE PARTNERSHIP (PPP) POLICY THE UNITED REPUBLIC OF TANZANIA NATIONAL PUBLIC PRIVATE PARTNERSHIP (PPP) POLICY PRIME MINISTER S OFFICE ` NOVEMBER, 2009 TABLE OF CONTENTS Page LIST OF ABBREVIATIONS AND ACRONYMS... vi PPP KEY CONCEPTS...

More information