1 PRE-RFQ MEETING CTTS PLANNING Austin District

2 Housekeeping Thanks for coming! Be sure to provide your information on the sign-in sheet Bathrooms and drinking fountain by the visitor entrance Please turn off or silence your cell phones Any answers provided to questions in this meeting shall be considered preliminary and are subject to change Official answers to questions will be posted on the website ( 2

3 CTTS Pre-RFQ Meeting- October 31, 2017 at 1:30 pm Pre-RFQ meeting agenda Timing Topic Presenters 1:30-1:35 Introduction / Ground Rules 1:35-1:45 Solicitation Process 1:45-2:00 RFQ - requirements Precertified work categories, DBE/HUB goal Proposed timeline of procurement 2:00-2:30 CTTS Planning Discuss the project needs 2:30-3:00 Wrap up & discuss next steps Q & A Austin District Heather Ashley-Nguyen Austin District Charles Davidson 3:00-3:30 Consultant Meet and Greet 3

4 CTTS Pre-RFQ Meeting- October 31, 2017 at 1:30 pm Pre-RFQ meeting agenda Timing Topic Presenters 1:30-1:35 Introduction / Ground Rules 1:35-1:45 Solicitation Process 1:45-2:00 RFQ - requirements Precertified work categories and DBE goal Proposed timeline of procurement 2:00-2:30 CTTS Planning Discuss the project needs 2:30-3:00 Wrap up & discuss next steps Q & A Austin District Heather Ashley-Nguyen Austin District Charles Davidson 3:00-3:30 Consultant Meet and Greet 4

5 Introduction / Ground Rules Lorena Echeverria De Misi, P.E. Director, Transportation Planning and Development, TxDOT Austin District Heather Ashley-Nguyen, P.E. Advance Project Development Director, TxDOT Austin District Marcy Saenz, P.E. Transportation Engineering Supervisor, TxDOT Toll Operations Division Hector Tamez, P.E. Transportation Engineer, TxDOT Austin District Steve Linhart Project Development Manager, TxDOT TPP Corridor Planning Charles Davidson, P.E., CTCM PEPS Austin PEPS Service Center Manager Harry Pan, P.E. PEPS Procurement Engineer Shemia Valentine - PEPS Contract Specialist Consultant Meet and Greet after presentation Networking and teaming opportunity TxDOT will not be present 5

6 CTTS Pre-RFQ Meeting- October 31, 2017 at 1:30 pm Pre-RFQ meeting agenda Timing Topic Presenters 1:30-1:35 Introduction / Ground Rules 1:35-1:45 Solicitation Process 1:45-2:00 RFQ - requirements Precertified work categories and DBE goal Proposed timeline of procurement 2:00-2:30 CTTS Planning Discuss the project needs 2:30-3:00 Wrap up & discuss next steps Q & A Austin District Heather Ashley-Nguyen Austin District Charles Davidson 3:00-3:30 Consultant Meet and Greet 6

7 Solicitation Process CTTS Planning Contract - State Process 130 working days from RFQ kick-off to contract execution Two-Step process Statement of Qualifications (SOQs) Evaluation Short listed providers move to Interview phase Interview Selected firms move to Negotiation phase RFQ Screening Make sure to follow the RFQ and submit all applicable documents required Interview and Contract Guide (ICG) If your team is selected for an interview this document will outline the process, presentation topics, and scoring criteria Negotiations 7

8 Solicitation Process (Cont.) Preclusion The preclusion is not determined at this time. If there is preclusion, the preclusion statement will be posted in RFQ. 8

9 RFQ Process RFQ questions RFQ questions were developed to guide your response to focus on the needs for this contract Attachment 2: Question and Response Template for SOQ must use the pre-formatted template. Past-performance will be captured at the interview phase What we are looking for in your response (SOQ) We are interested in meeting the contract goals and consultant characteristics Target SOQ responses to answer each question. Tell us about your experience Provide detailed examples and include challenges/lessons learned and innovation Quality over quantity One or two great examples are better than several good/average ones Thoughtful relevant responses No keyword search; this is about your capabilities, experience, knowledge, and thought process 9

10 Interview Process Interview and Contract Guide (ICG) Outlines the interview date, time, and location Interview evaluation criteria Will include past performance Interview structure Presentation topics Standard TxDOT contract template Attachment B Services to be Provided by the State Attachment C Services to be Provided by the Engineer Typical Interview process Introductions / Instructions Consultants begin with presentation based on topics provided in ICG Topics & questions expand on responses to questions in solicitation CST Break Follow-up question and answer session Concluding Remarks After each interview, the CST individually scores based on presentation topics and Q & A session 10

11 CTTS Pre-RFQ Meeting- October 31, 2017 at 1:30 pm Pre-RFQ meeting agenda Timing Topic Presenters 1:30-1:35 Introduction / Ground Rules 1:35-1:45 Solicitation Process 1:45-2:00 RFQ - requirements Precertified work categories and DBE goal Proposed timeline of procurement 2:00-2:30 CTTS Planning Discuss the project needs 2:30-3:00 Wrap up & discuss next steps Q & A Austin District Heather Ashley-Nguyen Austin District Charles Davidson 3:00-3:30 Consultant Meet and Greet 11

12 RFQ Requirements All firms must be pre-certified before RFQ closes Project Team Composition (PTC) Form (Parts 1, 2, and 3) must include the standard work categories, NLCs, HUB firms, and percentages of work identified in the RFQ Organization Chart not needed for SOQ Examples of Work Categories Systems Planning Feasibility Studies Archaeological Surveys Socio-Economic & Environmental Justice Analysis NLC Travel Demand Modeling NLC Public Involvement Prime provider shall perform at least 30% of the work for the solicitation HUB goal is tentatively set at 23.7% 12

13 Key Dates Procurement schedule (Tentative) Pre-RFQ meeting RFQ posts on website 10/31/17 Week of 11/27/17 or 12/4/17 SOQ due date Week of 12/18/17 or 1/2/18 Interviews Negotiations complete Week of 1/29/18 or 2/5/18 March 2018 Finalize & execute contracts May

14 Key Dates Procurement schedule (Tentative) Individual Debriefs may occur: After SOQ Screenings and notifications: o If a team is disqualified by SOQ screening After the Short List is announced: o If a team was not shortlisted (process with interviews) After the Selection Table is posted: o If a team was shortlisted but was not selected (process with interviews) Up to 4 months after contract execution 14

15 CTTS Pre-RFQ Meeting- October 31, 2017 at 1:30 pm Pre-RFQ meeting agenda Timing Topic Presenters 1:30-1:35 Introduction / Ground Rules 1:35-1:45 Solicitation Process 1:45-2:00 RFQ - requirements Precertified work categories and DBE goal Proposed timeline of procurement 2:00-2:30 CTTS Planning Discuss the project needs 2:30-3:00 Wrap up & discuss next steps Q & A Austin District Heather Ashley-Nguyen Austin District Charles Davidson 3:00-3:30 Consultant Meet and Greet 15

16 CTTS Planning Overview The corridors on the Central Texas Turnpike System (CTTS) include Loop 1, SH 45N, and SH 130 segments 1-4 and SH 45SE. A Capital Improvement Plan (CIP) will identify project needs for the CTTS and provide TxDOT decision makers a tool for financial planning and policy setting. The CIP will prioritize a list of recommended projects and improvements in three categories: short (1-4 years) mid (5-10 years) long range (10+) 16

17 CTTS Planning Overview CTTS Capital Improvement Plan The CIP will include the following items of work: Traffic Studies Operational Improvements Coordination with local government partners Preliminary Cost Estimates for Capital Improvements 17

18 CTTS Planning Overview Update of the Ultimate Schematic An update of the ultimate schematic for the CTTS is needed in conjunction with the CIP and includes the following items of work: Data collection Identification of potential ROW needs Identification of environmental constraints 18

19 Project Overview Purpose and Need TxDOT has a clearly defined planning process through the Unified Transportation Program (UTP), but improvements to the CTTS fall outside of traditional statewide planning and UTP funding. Ultimate schematics for CTTS warrant updates End Result Development of a CIP that identifies a priority list of projects to facilitate CTTS short, mid, and long term system planning improvements Preparation of an updated ultimate schematic for the CTTS corridor 19

20 CTTS Pre-RFQ Meeting- October 31, 2017 at 1:30 pm Pre-RFQ meeting agenda Timing Topic Presenters 1:30-1:35 Introduction / Ground Rules 1:35-1:45 Solicitation Process 1:45-2:00 RFQ - requirements Precertified work categories and DBE goal Proposed timeline of procurement 2:00-2:30 CTTS Planning Discuss the project needs 2:30-3:00 Wrap up & discuss next steps Q & A Austin District Heather Ashley-Nguyen Austin District Charles Davidson 3:00-3:30 Consultant Meet and Greet 20

21 Wrap Up and Next Steps Thank you all for attending the Pre-RFQ meeting Please submit your questions in writing via to: by 11:00 AM, November 3, 2017 Official answers to meeting questions and questions submitted in writing will be posted on the website ( on November 9,

22 CTTS Pre-RFQ Meeting- October 31, 2017 at 1:30 pm Pre-RFQ meeting agenda Timing Topic Presenters 1:30-1:35 Introduction / Ground Rules 1:35-1:45 Solicitation Process 1:45-2:00 RFQ - requirements Precertified work categories and DBE goal Proposed timeline of procurement 2:00-2:30 CTTS Planning Discuss the project needs 2:30-3:00 Wrap up & discuss next steps Q & A Austin District Heather Ashley-Nguyen Austin District Charles Davidson 3:00-3:30 Consultant Meet and Greet 22

23 Consultant Meet and Greet Enjoy the opportunity to discuss the upcoming solicitation Networking and teaming opportunities Please submit your questions in writing via to: by 11:00 AM, November 3,

PRE-RFQ MEETING I-345 FEASIBILITY STUDY SCHEMATICS & ENVIRONMENTAL (SD)

PRE-RFQ MEETING I-345 FEASIBILITY STUDY SCHEMATICS & ENVIRONMENTAL (SD) PRE-RFQ MEETING I-345 FEASIBILITY STUDY SCHEMATICS & ENVIRONMENTAL (SD) Solicitation 18-8SDP5001 Footer Text Housekeeping Thanks for coming! Be sure to provide your information on the sign-in sheet Bathrooms

More information

PEPS Pre-RFQ Meeting. IH 10 and US 59 Freeway Expansion from 4 to 6 Lanes CEI Beaumont District. March 5, Date. Footer Text

PEPS Pre-RFQ Meeting. IH 10 and US 59 Freeway Expansion from 4 to 6 Lanes CEI Beaumont District. March 5, Date. Footer Text PEPS Pre-RFQ Meeting IH 10 and US 59 Freeway Expansion from 4 to 6 Lanes CEI Beaumont District March 5, 2018 Footer Text Housekeeping Thanks for coming! Be sure to provide your information on the sign-in

More information

PRE-RFQ MEETING SAN ANTONIO DISTRICT PLANS, SPECIFICATIONS, & ESTIMATE (PS&E) DECEMBER 3, 4:00PM

PRE-RFQ MEETING SAN ANTONIO DISTRICT PLANS, SPECIFICATIONS, & ESTIMATE (PS&E) DECEMBER 3, 4:00PM PRE-RFQ MEETING SAN ANTONIO DISTRICT PLANS, SPECIFICATIONS, & ESTIMATE (PS&E) DECEMBER 3, 2018 @ 4:00PM Procurement for: LP 1604 (from SH 16 to IH 35 North) PEPS Professional Engineering Procurement Services

More information

PRE-RFQ MEETING FORT WORTH DISTRICT PS&E I30: COOPER ST. TO SH 161 (02-8SDP5003) S/E US 377: SH 167 TO SH 144 (02-8SDP5004)

PRE-RFQ MEETING FORT WORTH DISTRICT PS&E I30: COOPER ST. TO SH 161 (02-8SDP5003) S/E US 377: SH 167 TO SH 144 (02-8SDP5004) PRE-RFQ MEETING FORT WORTH DISTRICT PS&E I30: COOPER ST. TO SH 161 (02-8SDP5003) S/E US 377: SH 167 TO SH 144 (02-8SDP5004) Thursday, May 10, 2018 (10:00 am 11:00 am) Housekeeping Thanks for coming! Be

More information

PEPS QUARTERLY CONSULTANT WEBCAST. Martin L. Rodin, P.E. PEPS Division Director March 22, 2016

PEPS QUARTERLY CONSULTANT WEBCAST. Martin L. Rodin, P.E. PEPS Division Director March 22, 2016 PEPS QUARTERLY CONSULTANT WEBCAST Martin L. Rodin, P.E. PEPS Division Director March 22, 2016 Agenda 1 PEPS Organizational Update 2 3 4 5 6 FY16 Wave 1 Results FY16 Procurement Plan Continuous Improvement

More information

PEPS DIVISION PEPS Conference Martin Rodin, P.E.

PEPS DIVISION PEPS Conference Martin Rodin, P.E. PEPS DIVISION 2017 PEPS Conference Martin Rodin, P.E. November 3, 2017 Texas Department of Transportation, Right of Way Division May 2, 2016 Mission Mission Work with our TxDOT customers and external partners

More information

Procurement and Contract Administration Challenges

Procurement and Contract Administration Challenges Procurement and Contract Administration Challenges Gail Eileen Morea, P.E. PEPS Houston Service Center Manager June 16, 2016 1 Striving for Zero Incidents; Zero Fatalities & Zero Lost-Production Days!

More information

PEPS QUARTERLY CONSULTANT WEBCAST. Martin L. Rodin, P.E. PEPS Division Director October 27, 2015

PEPS QUARTERLY CONSULTANT WEBCAST. Martin L. Rodin, P.E. PEPS Division Director October 27, 2015 PEPS QUARTERLY CONSULTANT WEBCAST Martin L. Rodin, P.E. PEPS Division Director October 27, 2015 Objectives 1 2 3 4 5 6 PEPS Organizational Update FY15 Accomplishments FY16 Procurement Plan Continuous Improvement

More information

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report Internal Audit Follow-Up Report Professional Engineering Procurement Services (PEPS) Consultant Procurement Process TxDOT Internal Audit Division Objective To assess the status of corrective actions for

More information

PRE-REQUEST FOR PROPOSAL (RFP) MEETING GENERAL ENGINEERING CONSULTANT (GEC) FOR I-2/I-69C INTERCHANGE PHARR DISTRICT

PRE-REQUEST FOR PROPOSAL (RFP) MEETING GENERAL ENGINEERING CONSULTANT (GEC) FOR I-2/I-69C INTERCHANGE PHARR DISTRICT PRE-REQUEST FOR PROPOSAL (RFP) MEETING GENERAL ENGINEERING CONSULTANT (GEC) FOR I-2/I-69C INTERCHANGE PHARR DISTRICT RFQ No. 21-9SDP5001 601CT0000003698 November 19, 2018 Safety Minute Purpose of Meeting

More information

CONSULTANT SELECTION TEAM (CST) SCORING & HOW CSTS ARE FORMED

CONSULTANT SELECTION TEAM (CST) SCORING & HOW CSTS ARE FORMED CONSULTANT SELECTION TEAM (CST) SCORING & HOW CSTS ARE FORMED 2018 PEPS Conference Raul Ortega, P.E. November 27, 2018 Presentation Topics 1 2 How CST members are formed How the scoring process works a

More information

TRANSPARENCY IN STRATEGIC PROJECTS DIVISION

TRANSPARENCY IN STRATEGIC PROJECTS DIVISION TRANSPARENCY IN STRATEGIC PROJECTS DIVISION Scott Spradlin, P.E. Strategic Projects Division, TxDOT Footer Text October 13, 2015 Date INNOVATIVE PROJECT DELIVERY INNOVATIVE PROJECT DELIVERY AUTHORITY AND

More information

PEPS DIVISION SEPTEMBER 2018

PEPS DIVISION SEPTEMBER 2018 PEPS DIVISION SEPTEMBER 2018 Texas Department of Transportation, Right of Way Division May 2, 2016 Mission Mission Work with our TxDOT customers and external partners to procure the most qualified consultants

More information

PEPS DIVISION. October 2018 Where are we now where are we headed

PEPS DIVISION. October 2018 Where are we now where are we headed PEPS DIVISION October 2018 Where are we now where are we headed Texas Department of Transportation, Right of Way Division May 2, 2016 Mission Mission Work with our TxDOT customers and external partners

More information

PRE- SUBMITTAL CONFERENCE REQUEST FOR QUALIFICATIONS (RFQ)

PRE- SUBMITTAL CONFERENCE REQUEST FOR QUALIFICATIONS (RFQ) PRE- SUBMITTAL CONFERENCE REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION # H27-VMFDB-2019-006 Al Oracion Sr. Procurement Specialist Houston Airport System

More information

PEPS PRECERTIFICATION PROGRAM UPDATE. February 2018

PEPS PRECERTIFICATION PROGRAM UPDATE. February 2018 PEPS PRECERTIFICATION PROGRAM UPDATE February 2018 Discussion Topics A B C D E F G H What is the precertification program? What has been done on this project? What is the ideal outcome? How will this benefit

More information

TABLE OF CONTENTS FABENS AIRPORT TXDOT CSJ# 1824FABEN

TABLE OF CONTENTS FABENS AIRPORT TXDOT CSJ# 1824FABEN TABLE OF CONTENTS FABENS AIRPORT TXDOT CSJ# 1824FABEN 1. REQUEST FOR QUALIFICATIONS ANNOUNCEMENT 2. EVALUATION CRITERIA 3. FORM AVN-551 (PLEASE BE SURE TO DOWNLOAD THE MOST RECENT REVISED FORM DATED 8/2016)

More information

TABLE OF CONTENTS NEW BRAUNFELS REGIONAL AIRPORT TXDOT CSJ# 17MPNEWBR

TABLE OF CONTENTS NEW BRAUNFELS REGIONAL AIRPORT TXDOT CSJ# 17MPNEWBR TABLE OF CONTENTS NEW BRAUNFELS REGIONAL AIRPORT TXDOT CSJ# 17MPNEWBR 1. REQUEST FOR QUALIFICATIONS ANNOUNCEMENT 2. EVALUATION CRITERIA 3. FORM AVN-551 (PLEASE BE SURE TO DOWNLOAD THE MOST RECENT REVISED

More information

DBE PARTICIPATION ON THE US181 HARBOR BRIDGE PROJECT

DBE PARTICIPATION ON THE US181 HARBOR BRIDGE PROJECT DBE PARTICIPATION ON THE US181 HARBOR BRIDGE PROJECT TxDOT Strategic Projects Division August 1, 2014 1 2 3 4 5 Overview of TxDOT and the Funding Challenge Innovative Project Delivery HUB and DBE Roles

More information

TABLE OF CONTENTS SOUTH TEXAS INTERNATIONAL AT EDINBURG TXDOT CSJ# 19MPEDINB

TABLE OF CONTENTS SOUTH TEXAS INTERNATIONAL AT EDINBURG TXDOT CSJ# 19MPEDINB TABLE OF CONTENTS SOUTH TEXAS INTERNATIONAL AT EDINBURG TXDOT CSJ# 19MPEDINB 1. REQUEST FOR QUALIFICATIONS ANNOUNCEMENT 2. EVALUATION CRITERIA 3. FORM AVN-551 (PLEASE BE SURE TO DOWNLOAD THE MOST RECENT

More information

TEXAS MEXICO TRANSPORTATION BORDER MASTER PLAN UPDATE

TEXAS MEXICO TRANSPORTATION BORDER MASTER PLAN UPDATE TEXAS MEXICO TRANSPORTATION BORDER MASTER PLAN UPDATE Border Trade Advisory Committee Footer Text Date Background Information: May 31, 2017 Previous border master plans (2013 / 2014) Primarily focused

More information

LOOP 9 SOUTHEAST WELCOME TO THE LOOP 9 CORRIDOR/FEASIBILITY STUDY. Presentation 6:30 p.m. to 7:00 p.m.

LOOP 9 SOUTHEAST WELCOME TO THE LOOP 9 CORRIDOR/FEASIBILITY STUDY. Presentation 6:30 p.m. to 7:00 p.m. 1 WELCOME TO THE LOOP 9 CORRIDOR/FEASIBILITY STUDY PUBLIC MEETINGS Open House 5:30 p.m. to 6:30 p.m. Presentation 6:30 p.m. to 7:00 p.m. Open House 7:00 p.m. to 8:00 p.m. Tuesday, September 24, 2013 Thursday,

More information

The Port of New Orleans - As-Needed Consultant Selection Process for Professional Services

The Port of New Orleans - As-Needed Consultant Selection Process for Professional Services The Port of New Orleans - As-Needed Consultant Selection Process for Professional Services September 22, 2015 Catherine C. C. Dunn, P.E., D.NE, N.PE, D.PE P.PE Director, Deputy Port Director Development

More information

HISTORICALLY UNDERUTILIZED BUSINESS (HUB) SUBCONTRACTING PLAN (HSP) COMPLETION

HISTORICALLY UNDERUTILIZED BUSINESS (HUB) SUBCONTRACTING PLAN (HSP) COMPLETION HISTORICALLY UNDERUTILIZED BUSINESS (HUB) SUBCONTRACTING PLAN (HSP) COMPLETION TxDOT HUB Program Footer Text Revised August 2018 Date HUB Subcontracting Plan (HSP) Make sure to use the most current HSP!!

More information

DISADVANTAGED BUSINESS ENTERPRISE (DBE) COMMERCIALLY USEFUL FUNCTION (CUF) COMPLIANCE OVERVIEW FOR PRIME PROVIDER PROJECT MANAGERS DECEMBER 12, 2018

DISADVANTAGED BUSINESS ENTERPRISE (DBE) COMMERCIALLY USEFUL FUNCTION (CUF) COMPLIANCE OVERVIEW FOR PRIME PROVIDER PROJECT MANAGERS DECEMBER 12, 2018 DISADVANTAGED BUSINESS ENTERPRISE (DBE) COMMERCIALLY USEFUL FUNCTION (CUF) COMPLIANCE OVERVIEW FOR PRIME PROVIDER PROJECT MANAGERS DECEMBER 12, 2018 Agenda Topic Welcome - Housekeeping DBE Program Authority

More information

Internal Audit Report. Professional Engineering Procurement Services (PEPS) Consultant Procurement Process TxDOT Internal Audit Division

Internal Audit Report. Professional Engineering Procurement Services (PEPS) Consultant Procurement Process TxDOT Internal Audit Division Internal Audit Report Professional Engineering Procurement Services (PEPS) Consultant Procurement Process TxDOT Internal Audit Division Objective To evaluate the effectiveness and efficiency of the PEPS

More information

PROFESSIONAL SERVICES CONTRACT NEGOTIATION

PROFESSIONAL SERVICES CONTRACT NEGOTIATION PROFESSIONAL SERVICES CONTRACT NEGOTIATION 2018 PEPS Conference Shirin Helmi, P.E. & Philip Howlett, P.E. November 27, 2018 Presentation Topics 1 2 3 4 5 6 Introductions & Welcome Big Picture/Goals Rate

More information

Gloucester Parkway Extension RFQ Information Meeting

Gloucester Parkway Extension RFQ Information Meeting Gloucester Parkway Extension RFQ Information Meeting May 24, 2013 Tim Hartzell, PE District Project Manager Kevin Reichert, PE APD Project Manager and POC Topics Project Location & Overview RFQ Information

More information

TxDOT Public-Private Partnerships Lessons Learned. OMW: Market, Communication, and Policy Trends in Tolling

TxDOT Public-Private Partnerships Lessons Learned. OMW: Market, Communication, and Policy Trends in Tolling OMW: Market, Communication, and Policy Trends in Tolling International Bridge, Tunnel and Turnpike Association Monday, June 18, 2012 Edward P. Pensock, Jr., P.E. Director, Strategic Projects Division Texas

More information

Page 1 of 2 AMENDMENT - REQUEST FOR QUALIFICATIONS (RFQ)

Page 1 of 2 AMENDMENT - REQUEST FOR QUALIFICATIONS (RFQ) Page 1 of 2 Page 1 of 2 AMENDMENT - REQUEST FOR QUALIFICATIONS (RFQ) Amendment No. 2 RFQ No. 4018000166 COMPANY NAME AND ADDRESS (To be completed by Bidder) Project Name Construction Management Services

More information

WORK AUTHORIZATION ASSIGNMENT PROCESS

WORK AUTHORIZATION ASSIGNMENT PROCESS WORK AUTHORIZATION ASSIGNMENT PROCESS Lynn Daniel, P.E. Chris Henry, P.E. November 3, 2017 Table of Contents 1 2 3 4 5 6 Welcome Address & Opening Remarks PEPS Central Service Center Consultant Contract

More information

HOW WE PROCURE SERVICES. Upcoming Projects for Houston District Sargon Youhannazad, P.E.

HOW WE PROCURE SERVICES. Upcoming Projects for Houston District Sargon Youhannazad, P.E. HOW WE PROCURE SERVICES Upcoming Projects for Houston District Sargon Youhannazad, P.E. April 19, 2018 Become Precertified The program is defined under Title 43 TAC, Rule 9.33 A vital part of the TxDOT

More information

CITY OF PORTLAND, TEXAS

CITY OF PORTLAND, TEXAS CITY OF PORTLAND, TEXAS REQUEST FOR QUALIFICATIONS FOR PLANNING SERVICES OLDE TOWN MIXED USE DISTRICT REDEVELOPMENT PLAN CITY OF PORTLAND, TEXAS 1900 Billy G. Webb Drive Due Date: Portland, Texas 78374

More information

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report Internal Audit Follow-Up Report Professional Engineering Procurement Services Contract and Work Authorizations TxDOT Internal Audit Division Objective Assess the status of corrective actions for high-risk

More information

August 31, To Whom It May Concern:

August 31, To Whom It May Concern: August 31, 2017 To Whom It May Concern: The Aerotropolis Atlanta Community Improvement Districts (AACIDs) is soliciting Statements of Qualifications (RFQ) from qualified firm(s) or organization(s) to develop

More information

Odd Fellows Road Interchange at US Route 29/460 and Road Improvements UPC # RFQ Information Meeting

Odd Fellows Road Interchange at US Route 29/460 and Road Improvements UPC # RFQ Information Meeting Odd Fellows Road Interchange at US Route 29/460 and Road Improvements UPC #105515 RFQ Information Meeting Raina Rosado, PE District Project Manager Kevin Reichert, PE APD Project Manager and POC July 11,

More information

REQUEST FOR QUALIFICATIONS

REQUEST FOR QUALIFICATIONS REQUEST FOR QUALIFICATIONS PROJECT: ISSUE DATE: October 22, 2018 ISSUED BY: INQUIRIES: SUBMISSION DEADLINE: SUBMIT TO: City of Delaware, Ohio Public Works Department, Traffic & Engineering Services 440

More information

Proposals will be received at 101 East 11 th Street, Suite G13, Chattanooga, TN until 4:00 P M, EST. End of Day on February 3, 2012 End of Day

Proposals will be received at 101 East 11 th Street, Suite G13, Chattanooga, TN until 4:00 P M, EST. End of Day on February 3, 2012 End of Day Date: 01/17/2012 Ref. No.: PURCHASING DEPARTMENT 101 EAST 11 TH STREET CITY HALL SUITE G13 CHATTANOOGA, TENNESSEE 37402 Request for Qualification (RFQ) for the City of Chattanooga, Tennessee Proposals

More information

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report Internal Audit Follow-Up Report Construction Inspection Program TxDOT Internal Audit Division Objective To assess the status of corrective actions for high-risk Management Action Plans (MAPs) previously

More information

PRIME PROVIDER EVALUATIONS DALLAS DISTRICT - TRAVIS CAMPBELL, P.E. PEPS DAN M. NEAL II, P.E., P.G.

PRIME PROVIDER EVALUATIONS DALLAS DISTRICT - TRAVIS CAMPBELL, P.E. PEPS DAN M. NEAL II, P.E., P.G. PRIME PROVIDER EVALUATIONS DALLAS DISTRICT - TRAVIS CAMPBELL, P.E. PEPS DAN M. NEAL II, P.E., P.G. 2018 PEPS Conference November 28, 2018 Travis Campbell, P.E. 2 Presentation Topics - Travis Campbell 1

More information

Trinity Well Field and Production Facilities Project Management Using CMAR

Trinity Well Field and Production Facilities Project Management Using CMAR Trinity Well Field and Production Facilities Project Management Using CMAR Ian Taylor, P.E., PMP New Braunfels Utilities David Bennett, P.E. Freese and Nichols Kirby Anderson MGC Contractors February 27,

More information

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report Internal Audit Follow-Up Report Professional Engineering Procurement Services Contract and Work Authorizations TxDOT Internal Audit Division Objective To assess the status of corrective actions for high-risk

More information

Internal Audit Report

Internal Audit Report Internal Audit Report Construction Inspection Program TxDOT Internal Audit Division Objective To determine if an adequate process exists to ensure sufficient coverage and qualifications to inspect construction

More information

LEVEL OF EFFORT & NEGOTIATIONS

LEVEL OF EFFORT & NEGOTIATIONS LEVEL OF EFFORT & NEGOTIATIONS Phil Howlett, P.E. Richard De La Cruz, P.E. November 3, 2017 Table of contents 1 2 3 4 5 6 7 Welcome Pre-Level of Effort (LOE) Level of Effort (LOE): Scopes Level of Effort

More information

Request for Qualifications. For. Engineering Services. Industrial Pretreatment Facilities Feasibility Study

Request for Qualifications. For. Engineering Services. Industrial Pretreatment Facilities Feasibility Study Request for Qualifications For Engineering Services Industrial Pretreatment Facilities Feasibility Study Issue Date: March 14, 2018 Response Deadline: April 30, 2018, 3:00 p.m. General In accordance with

More information

Selection of the Regional Consultant List

Selection of the Regional Consultant List LOCAL DESIGN SERVICES AGREEMENT (LDSA) CONSULTANT SELECTION PROCEDURE A Request For Qualifications (RFQ) pursuant to the ad in the New York State Contract Reporter was made available to any architecture/engineering

More information

Route 7 Truck Climbing Lane. RFQ Information Meeting

Route 7 Truck Climbing Lane. RFQ Information Meeting Route 7 Truck Climbing Lane From West Market Street to Route 9 RFQ Information Meeting November 9, 2012 Mark Gibney, PE District Project Manager Ian Millikan, PE APD Project Manager and POC Introduction

More information

TABLE OF CONTENTS FOR THE REQUEST FOR STATEMENTS OF QUALIFICATION FOR RIGHT OF WAY SURVEYING SERVICES INTERNATIONAL BRIDE TRADE CORRIDOR

TABLE OF CONTENTS FOR THE REQUEST FOR STATEMENTS OF QUALIFICATION FOR RIGHT OF WAY SURVEYING SERVICES INTERNATIONAL BRIDE TRADE CORRIDOR TABLE OF CONTENTS FOR THE REQUEST FOR STATEMENTS OF QUALIFICATION FOR RIGHT OF WAY SURVEYING SERVICES INTERNATIONAL BRIDE TRADE CORRIDOR 2013 Page 1 Request for SOQ s Page 2-4 SOQ ROW Surveying Service

More information

PRIME PROVIDER EVALUATION

PRIME PROVIDER EVALUATION PRIME PROVIDER EVALUATION Thuy Luong, P.E. November 3, 2017 Table of Contents 1 2 3 4 5 6 Purpose of Prime Provider Evaluations Scoring System Converting ESA score to Past Performance Score ESA Score for

More information

I-95 Southbound CD Lanes Rappahannock River Crossing Stafford County/ City of Fredericksburg, Virginia. RFQ Information Meeting - November 9, 2016

I-95 Southbound CD Lanes Rappahannock River Crossing Stafford County/ City of Fredericksburg, Virginia. RFQ Information Meeting - November 9, 2016 I-95 Southbound CD Lanes Rappahannock River Crossing Stafford County/ City of Fredericksburg, Virginia RFQ Information Meeting - November 9, 2016 Krishna Potturi, PE Project Manager Suril Shah APD Project

More information

Texas Transportation Institute The Texas A&M University System College Station, Texas

Texas Transportation Institute The Texas A&M University System College Station, Texas 1. Report No. FHWA/TX-06/5-4055-01-3 2. Government Accession No. 3. Recipient's Catalog No. 4. Title and Subtitle CASE STUDY ANALYSIS OF MID-SIZE URBAN/RURAL AREA TOLL ROAD OPTIONS YEAR 2 REPORT 5. Report

More information

I-64/ Route 15 (Zion Crossroads) RFQ Information Meeting

I-64/ Route 15 (Zion Crossroads) RFQ Information Meeting I-64/ Route 15 (Zion Crossroads) Diverging Diamond Interchange RFQ Information Meeting December 13, 2011 Brian Arnold District Project Manager Ian Millikan, PE APD Project Manager and POC Introduction

More information

As a state agency, the College administration is required to develop procedures for Construction Manager selection.

As a state agency, the College administration is required to develop procedures for Construction Manager selection. COLLEGE of CENTRAL FLORIDA ADMINISTRATIVE PROCEDURE Title: Construction Management Selection Process Page 1 of 2 Implementing Procedure For F.S. 1013.45 Date Approved: 09/11/02 Division: Administration

More information

Executive Summary ORGANIZATION CHANGES MANAGEMENT, DECISION- MAKING, AND DAY-TO-DAY OPERATION STRUCTURE

Executive Summary ORGANIZATION CHANGES MANAGEMENT, DECISION- MAKING, AND DAY-TO-DAY OPERATION STRUCTURE Executive Summary The Lane Construction Corporation and HDR have once again assembled a strong team (Lane-HDR) that provides the best value to TxDOT and the CTRMA. Our success in delivering design-build

More information

Atlanta BeltLine West Environmental Assessment and Design Engineering Procurements

Atlanta BeltLine West Environmental Assessment and Design Engineering Procurements Atlanta BeltLine West Environmental Assessment and Design Engineering Procurements January 8, 2014 // Pre-Proposal Meeting 1/9/2014 Atlanta BeltLine // 2014 Page 1 // Agenda Welcome Meeting Logistics Context

More information

Contracting for Architectural and Engineering (A/E) Services Webinar. August 30, AM to 11:30 AM

Contracting for Architectural and Engineering (A/E) Services Webinar. August 30, AM to 11:30 AM Contracting for Architectural and Engineering (A/E) Services Webinar August 30, 2011 10 AM to 11:30 AM 1 Where We're Going Today Webinar Operation - Fred Ward 5 minutes (+/-) Topic Introduction - John

More information

Strategic Intermodal System (SIS) and Shared Use Non Motorized (SUN) Trail Program Update

Strategic Intermodal System (SIS) and Shared Use Non Motorized (SUN) Trail Program Update Strategic Intermodal System (SIS) and Shared Use Non Motorized (SUN) Trail Program Update presented to MPOAC presented by Huiwei Shen Systems Implementation Office, FDOT October 12, 2017 SIS Structure

More information

Please note the following policy concerning communication between Consultants and the City of Dublin during the announcement and selection process:

Please note the following policy concerning communication between Consultants and the City of Dublin during the announcement and selection process: 01-08-19 Posting Date FRA-33-3.70 Smart Technology Connected Vehicle Roundabout Application Project PID No. 109356 City of Dublin Response Due Date: 01-24-19 Communications Restrictions Please note the

More information

Request for Letter of Interest (Electronic Submittal Required)

Request for Letter of Interest (Electronic Submittal Required) Request for Letter of Interest (Electronic Submittal Required) Skyline Drive Engineering Design and Right-of-Way Acquisition October 2017 Page 1 of 10 Overview: Consultant selection is a Qualification-Based

More information

Outdoor School Program. Roles & Responsibilities

Outdoor School Program. Roles & Responsibilities Authority & Role: Outdoor School Program WORK GROUP VOLUNTEER POSITION DESCRIPTION Roles & Responsibilities The role of the Outdoor School (ODS) Work Groups (WG) is to identify needs and interests of stakeholders,

More information

TEXAS DEPARTMENT OF TRANSPORTATION GENERAL SERVICES DIVISION

TEXAS DEPARTMENT OF TRANSPORTATION GENERAL SERVICES DIVISION TEXAS DEPARTMENT OF TRANSPORTATION GENERAL SERVICES DIVISION PREPARED BY: KAREN LEWIS, CPPO, C.P.M., CTPM SPECIFICATION FAX NO.: (512) 374-5480 NO: 958-77-20 E-MAIL: klewis@dot.state.tx.us DATE: FEBRUARY

More information

SH 249 EXTENSION. Industry Workshop. May 29, 2015

SH 249 EXTENSION. Industry Workshop. May 29, 2015 SH 249 EXTENSION Industry Workshop May 29, 2015 Table of Contents 1 2 3 4 5 6 7 Safety Minute Project Layout Project Overview & Status QS Evaluations Procurement Schedule QS Submittals DBE Opportunity

More information

PIEDMONT TRIAD AIRPORT AUTHORITY

PIEDMONT TRIAD AIRPORT AUTHORITY PIEDMONT TRIAD AIRPORT AUTHORITY REQUEST FOR QUALIFICATIONS (RFQ) for ON-CALL ENVIRONMENTAL CONSULTANT SERVICES at the PIEDMONT TRIAD INTERNATIONAL AIRPORT (GSO) The Piedmont Triad Airport Authority (PTAA)

More information

RFQ CM16-01 Page 1 of 5

RFQ CM16-01 Page 1 of 5 REQUEST FOR QUALIFICATIONS (RFQ) RFQ CM16-01 CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES FOR PAVING AND DRAINGE CONSTRUCTION PROJECTS SELECTION CM01 The City of Houston intends to enter into a contract

More information

Civil Rights Division

Civil Rights Division Civil Rights Division Agenda 2 Host Partners Thank you to the following host partners: Regional Hispanic Contractors Association (RHCA) John Martinez President John@regionalhca.org Ruben Landa Vice Chairman

More information

Memorandum. Date: October 17, 2017 To: From: Subject:

Memorandum. Date: October 17, 2017 To: From: Subject: Memorandum Date: October 17, 2017 To: From: Subject: Transportation Authority Board Joe Castiglione Deputy Director for Technology, Data and Analysis 11/14/17 Board Meeting: Award Three-Year Professional

More information

PROFESSIONAL CONSULTANT SERVICES REQUEST FOR QUALIFICATIONS (RFQ)

PROFESSIONAL CONSULTANT SERVICES REQUEST FOR QUALIFICATIONS (RFQ) PROFESSIONAL CONSULTANT SERVICES REQUEST FOR QUALIFICATIONS (RFQ) MARCH 2018 INTRODUCTION AND BACKGROUND The City of Keller is in search of the most qualified firms to provide professional expertise and

More information

US 69 RELIEF ROUTE STUDY

US 69 RELIEF ROUTE STUDY US 69 RELIEF ROUTE STUDY Jacksonville, Texas PUBLIC MEETING #3 August28 th 2018 1 Welcome to the final public meeting for the US 69 Relief Route Study in Jacksonville. This presentation will give a recap

More information

Selection of Contractor Step 5. June 2013

Selection of Contractor Step 5. June 2013 Selection of Contractor Step 5 June 2013 Project Management Concept Step 1: Needs Development Step 2: Scope Development Step 3: Procurement of Design Team Step 4: Design Step 5: Bid/Procurement of Contractor

More information

Vista Ridge Integration Project Progressive Design-Build Services

Vista Ridge Integration Project Progressive Design-Build Services Vista Ridge Integration Project Progressive Design-Build Services Linda Bevis, P.E. Manager Water Resources/Vista Ridge Integration Diana L. Woltersdorf Manager Contract Administration Marisol Robles SMWVB

More information

REACHING YOUR DECISION DESTINATION. Janie Temple, Branch Manager

REACHING YOUR DECISION DESTINATION. Janie Temple, Branch Manager REACHING YOUR DECISION DESTINATION Janie Temple, Branch Manager Model Data Provides Foundation Data for TxDOT s Project Development Process Provides Customers Ability to Make Data Driven Decisions Optimizes

More information

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER SERVICES AT RISK WITH GUARANTEED MAXIMUM PRICE

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER SERVICES AT RISK WITH GUARANTEED MAXIMUM PRICE REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER SERVICES AT RISK WITH GUARANTEED MAXIMUM PRICE Memphis Cook Convention Center Renovation City of Memphis, Department of Housing and Community Development

More information

IH 635 (LBJ Freeway) Corridor Study Implementation Approach. Initial meeting held in June Updated August 2002.

IH 635 (LBJ Freeway) Corridor Study Implementation Approach. Initial meeting held in June Updated August 2002. DNT IH 635 (LBJ Freeway) Corridor Study Initial meeting held in June 2001 Updated August 2002 How to move from three planning sections LBJ Corridor Study Study Sections I.H. 35E President George Bush Turnpike

More information

West Central Texas Council of Governments

West Central Texas Council of Governments West Central Texas Council of Governments 3702 Loop 322 Abilene, TX 79602 (325) 672-8544 Dear Applicant for Employment: Thank you for submitting an application for the current job opening. It is WCTCOG's

More information

MONTGOMERY STREET. Construction Manager at Risk (CMAR) Services

MONTGOMERY STREET. Construction Manager at Risk (CMAR) Services 2 nd PRE-PROPOSAL CONFERENCE March 6, 2015 MONTGOMERY STREET (City Project #02432) Construction Manager at Risk (CMAR) Services PROCUREMENT MARCH 19, 2015 1 Michael Weiss, P.E. City of Fort Worth Project

More information

Dos Rios WRC Chlorine System Improvements

Dos Rios WRC Chlorine System Improvements Dos Rios WRC Chlorine System Improvements Ila E. Drzymala, Ph.D., PE SAWS Engineer Non-mandatory Pre-submittal Conference Disclaimer Oral statements or discussion during the pre-proposal meeting will not

More information

Request for Qualifications Statements

Request for Qualifications Statements Request for Qualifications Statements BND WATER DISTRIBUTION AND WASTEWATER TREATMENT ENGINEERING STATEMENTS ENGINEERING DESIGN SERVICES FOR BND WATER DISTRIBUTION AND WASTEWATER TREATMENT The Brownsville

More information

RRC SELF-EVALUATION. A tool for Michigan communities seeking RRC certification

RRC SELF-EVALUATION. A tool for Michigan communities seeking RRC certification RRC SELF-EVALUATION A tool for Michigan communities seeking RRC certification The Redevelopment Ready Communities (RRC) best practices self-evaluation is a tool for communities seeking RRC certification.

More information

Request for Qualifications for Master Agreement

Request for Qualifications for Master Agreement Page 1 of 10 Request for Qualifications for Master Agreement ON-CALL ARCHITECTURAL SERVICES Submittal Deadline: April 28, 2017 at 3:00 p.m. The University of Washington is soliciting Statements of Qualifications

More information

Strategic Intermodal System (SIS) and Shared Use Non Motorized (SUN) Trail Program Update

Strategic Intermodal System (SIS) and Shared Use Non Motorized (SUN) Trail Program Update Strategic Intermodal System (SIS) and Shared Use Non Motorized (SUN) Trail Program Update presented to MPOAC presented by Jim Wood Chief Planner, FDOT November 7, 2017 SIS Structure and Criteria 2016 SIS

More information

PRECLUSIONS PEPS Conference. Dan M. Neal II, P.E., P.G. November 28, PEPS Conference November 28, 2018

PRECLUSIONS PEPS Conference. Dan M. Neal II, P.E., P.G. November 28, PEPS Conference November 28, 2018 2018 PEPS Conference PRECLUSIONS Dan M. Neal II, P.E., P.G. November 28, 2018 2018 PEPS Conference November 28, 2018 Presentation Topics 1 2 3 4 5 What is a Preclusion? Conflicts of Interest Types of Conflicts

More information

2018 Sanitary Sewer Overflow and Reduction Program (SSORP) Engineering Design Services Small Diameter

2018 Sanitary Sewer Overflow and Reduction Program (SSORP) Engineering Design Services Small Diameter 2018 Sanitary Sewer Overflow and Reduction Program (SSORP) Engineering Design Services Small Diameter Antonio Leyva, P.E. Engineering Manager Marisol V. Robles Manager SMWVB Program Stella Manzello Contract

More information

Statement of Work Analyst

Statement of Work Analyst TEXAS COMPTROLLER OF PUBLIC ACCOUNTS invites applications for the position of: Statement of Work Analyst JOB POSTING #: 2Q3201.16 STATE CLASSIFICATION #: 1960 STATE CLASSIFICATION TITLE: SALARY GROUP:

More information

CUSTOMER SATISFACTION SURVEY

CUSTOMER SATISFACTION SURVEY CUSTOMER SATISFACTION SURVEY Conducted for the Texas Department of Transportation (TxDOT) Prepared by Cooper Consulting Company May 2018 Agenda 1 Introduction 2 Description of Study 3 4 5 6 7 8 Summary

More information

Management Consulting and Auditing Services Pre-Response Conference. ITN No A August 23, :00 AM

Management Consulting and Auditing Services Pre-Response Conference. ITN No A August 23, :00 AM Management Consulting and Auditing Services Pre-Response Conference ITN No. 02-973-000-A August 23, 2012 9:00 AM What is the purpose of this meeting? During this meeting, the Department intends to provide

More information

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES WITH GUARANTEED MAXIMUM PRICE

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES WITH GUARANTEED MAXIMUM PRICE CAYUCOS SANITARY DISTRICT 200 Ash Avenue P.O. Box 333, Cayucos, California 93430-0333 www.cayucossd.org 805-995-3290 REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES WITH GUARANTEED

More information

UNIVERSITY OF NEBRASKA. CAPITAL PLANNING and DEVELOPMENT ARCHITECTURAL OR ENGINEERING PROFESSIONAL SERVICES FOUR-YEAR CONTRACTS SELECTION PROCEDURES

UNIVERSITY OF NEBRASKA. CAPITAL PLANNING and DEVELOPMENT ARCHITECTURAL OR ENGINEERING PROFESSIONAL SERVICES FOUR-YEAR CONTRACTS SELECTION PROCEDURES UNIVERSITY OF NEBRASKA CAPITAL PLANNING and DEVELOPMENT ARCHITECTURAL OR ENGINEERING PROFESSIONAL SERVICES FOUR-YEAR CONTRACTS SELECTION PROCEDURES UNFP 6.3.2.2 I. Reference and Application A. Nebraska

More information

Town of Brandon, Vermont US Route 7 (Center Street) Bridge 114 Improvements

Town of Brandon, Vermont US Route 7 (Center Street) Bridge 114 Improvements Town of Brandon, Vermont US Route 7 (Center Street) Bridge 114 Improvements Request for Qualifications Construction Owners Representative & Inspection Services Issued: January 11, 2018 Due: February 5,

More information

SH 183 Managed Lanes Project RFQ Q & A MATRIX #2. (June 4, 2013)

SH 183 Managed Lanes Project RFQ Q & A MATRIX #2. (June 4, 2013) SH 183 Managed Lanes Project RFQ Q & A MATRIX #2 (June 4, 2013) No. Current language states: Project experience provided by a parent or sister company of the Lead Engineering Firm, Lead Contractor or Lead

More information

BREAKING GROUND WITH ALTERNATIVE DELIVERY

BREAKING GROUND WITH ALTERNATIVE DELIVERY BREAKING GROUND WITH ALTERNATIVE DELIVERY Matt McCarter and Mike Midkiff October 10, 2017 Agenda 1 2 What is Design-Build What we can do our design-build legislative authority 3-9 10 3 4 5 What makes a

More information

Truck Parking Information Management System (TPIMS) Glossary

Truck Parking Information Management System (TPIMS) Glossary Truck Parking Information Management System (TPIMS) Glossary AASHTO American Association of State Highway and Transportation Officials is the organization that provides recommendations for a variety of

More information

Request for Proposal for Construction Management Services

Request for Proposal for Construction Management Services Request for Proposal for Construction Management Services Sauk Rapid-Rice Public Schools is soliciting Construction Management (CM) proposals for safety and security projects to be completed at each of

More information

CONSTRUCTRION MANAGEMENT AT RISK ASHE December 13, 2011 Julio Alvarado Construction State Engineer

CONSTRUCTRION MANAGEMENT AT RISK ASHE December 13, 2011 Julio Alvarado Construction State Engineer CONSTRUCTRION MANAGEMENT AT RISK CM@R ASHE December 13, 2011 Julio Alvarado Construction State Engineer 1 Agenda Background What leads DOT s to CMAR? ADOT s Outlook on CMAR Project Updates CMAR Benefits

More information

Request for Proposal for GC/CM Consultant Services Ferndale School District. Secondary High School GC/CM Program. October 19, 2018

Request for Proposal for GC/CM Consultant Services Ferndale School District. Secondary High School GC/CM Program. October 19, 2018 Request for Proposal for GC/CM Consultant Services Ferndale School District Secondary High School GC/CM Program October 19, 2018 The Ferndale School District is requesting proposals for project management,

More information

Town of Bennington, Vermont Pleasant Street and School Street Sidewalk Installation STP EH08(11)

Town of Bennington, Vermont Pleasant Street and School Street Sidewalk Installation STP EH08(11) , Vermont Pleasant Street and School Street Sidewalk Installation STP EH08(11) Request for Qualifications Construction Inspection and Testing Services Issued: January 3, 2017 Due: January 24, 2017 I. INTRODUCTION

More information

Chapter 7 Short List Evaluations (Interviews and Proposals)

Chapter 7 Short List Evaluations (Interviews and Proposals) Chapter 7 Short List Evaluations (Interviews and Contents: Section 1 Overview... 7-2 Application Regarding Selection Processes... 7-2 Related Resources... 7-2 Section 2 Required Interviews... 7-3 IGC Issuance,

More information

Source Selection for Construction and AE Contracts

Source Selection for Construction and AE Contracts Source Selection for Construction and AE Contracts Shea Zahner, PE Deputy Assistant Operations Officer NAVFAC SE Mike Davis, PE Senior Project Manager NAVFAC SE Camilla Baker Supervisory Contract Specialist

More information

Table of Contents PERMIAN BASIN MPO TIP 2

Table of Contents PERMIAN BASIN MPO TIP 2 Table of Contents Permian Basin MPO Membership and Structure... 3 Mission Statement... 3 Vision Statement... 3 Transportation Improvement Program (TIP)... 4 Year of Expenditure (YOE) Trends... 4 Total

More information

RFP NO. H37-RAS

RFP NO. H37-RAS PRE-PROPOSAL CONFERENCE REQUEST FOR PROPOSAL (RFP) PASSENGER AND PARKER RESEARCH AND ANALYTICS SERVICES RFP NO. H37-RAS-2017-006 Andre Morrow, C.P.M., CPPB Sr. Procurement Specialist Houston Airport System

More information

PUBLIC HEARING LOOP 9

PUBLIC HEARING LOOP 9 PUBLIC HEARING LOOP 9 From Interstate (I)-35E to I-45 Dallas and Ellis Counties, Texas CSJ: Loop 2964-10-005 9: I-35E to I-45 Tuesday, June 20, 20, 2017 2017 Public Hearing Introductions ELECTED & PUBLIC

More information