WASTEWATER TREATMENT PLANT

Size: px
Start display at page:

Download "WASTEWATER TREATMENT PLANT"

Transcription

1 1

2 Tofino s Wastewater Treatment Plant Project consists of The wastewater treatment plant (on DL 117, north east end of Industrial Way) Conveyance System: group of pipes and pump stations needed to take the sewage to and from the plant Outfall: New ocean outfall located in Duffin Passage Solids Handling Facility: a biosolids facility located at the existing landfill site 2

3 WASTEWATER TREATMENT PLANT The plant itself YEW WOOD INDUSTRIAL WAY 3

4 4

5 WASTEWATER TREATMENT PLANT Conveyance System Conveyance System: 4 km of new pipe Four new lift stations: 1. First Dock 2. Main St 3. First St near Arnet Rd 4. Pacific Rim Highway near Gas n Go station 6

6 Outfall The new proposed outfall: will be 500m long will be made of 350mm HDPE DR17 will include a set of diffusers at a depth of 31.3m (relative to chart datum) The existing outfall at the end of First Street will be abandoned. 7

7 Residual solids Facility The facility will consist of a biosolids/wood waste blend. It will be 20m x 75m (65 ft x 240 ft) Current design consists of: Aerated bin Agitated bed composting Aerated Channel Composting Wood Waste storage Curing Process Pictured Here: Ladysmith solids handling facility. About twice the size proposed 8

8 Previous Cost Estimates Liquid Waste Management Plan November 2017 Project Component Base Cost TOTAL Wastewater Treatment Plant $ 12,700,000 $ 12,700,000 Conveyance including Outfall $ 5,700,000 $ 5,700,000 Solids Handling Facility $ 2,500,000 $ 2,500,000 Upgrades and Others $ 800,000 $ 800,000 $ 21,700,000 What changed? Population projection changed from 5,300 to 10,000 (yr 2038 to account for seasonal population Current market conditions are strong for Vancouver Island contractors and cost of materials are rising. Sample analysis on sewage revealed stronger than anticipated levels of BOD as high as 400mg/L. Typical residential strength is 200 mg/l Additional concrete required for Tofino seismic conditions Pre-Design Stage, Class 'C' Cost Estimate March 2018 Project Component Base Cost Contingency TOTAL Wastewater Treatment $ 23,300,000 $ 8,200,000 (35%) $ 31,500,000 Plant Conveyance $ 6,900,000 $ 2,400,000 (35%) $ 9,300,000 Outfall $ 603,000 $ 181,000 (30%) $ 784,000 Solids Handling Facility $ 1,770,000 $ 530,000 (30%) $ 2,300,000 $ 43,884,000 60% Design Stage, Draft Class 'B' Cost Estimate June 2018 What changed? Project Component Base Cost General Requirements, Fees & Allowances TOTAL Wastewater Treatment Plant $ 26,692,700 $ 15,725,775 (59%) $ 42,418,475 Conveyance $ 7,326,646 $ 4,249,454 (59%) $ 11,576,100 Outfall $ 544,304 $ 315,696 (59%) $ 860,000 Solids Handling Facility $ 1,438,244 $ 834,181 (59%) $ 2,272,425 $ 57,127,000 Notice how the base costs stayed relatively the same as March The estimates for general requirements and allowances changed format, instead of contingency it is now: 18% General Requirement: Costs any contractor must incur to complete a large-scale project that are not built into the project itself Such as supervision, temporarily facilities, site safety, and project management. 5% Fee: This is for the contractor s expected profit. Compounded 6% 10% Design Allowance: For detail revisions between current pre-design drawings to final, tender-ready drawings. Compounded 12% 6% Escalation Allowance: For the rising costs of construction and remoteness anticipated between June 2018 and a tender date in Compounded 8% 10% Construction Allowance: For hidden conditions onsite and change orders. Compounded 15% 9

9 Current Cost Estimate Class 'B' Cost Estimate August 2018 Project Component TOTAL Wastewater Treatment Plant $ 38,700,000± Conveyance $ 10,360,000± Outfall $ 860,000± Compost Handling Facility $ 3,400,000± Construction Admin and Testing $ 1,600,000± $ 54,909,000 Annual Operating Cost Wastewater Treatment Plant & Compost Handling Facility Ineligible Capital Costs TOTAL $ 612,000 TOTAL Legal, Hiring, Furniture, DCCs, Permit Fees, Land Acquisition, etc. $ 315,000 Funding 73.33% by Grant ($40,264,800) 26.67% by DoT ($14,644,200)* * Contributions from users outside of the District which include, Parks Canada, Ahousaht First Nation and Tla-o-qui-aht, are to be determined and assumed to be $0 for the purposes of this presentation. Funding 100% by DoT ($315,000)* 10

10 Schedule Grant Application Submitted (Aug ) We are here right now. 11

11 Financial Implications Annual Operating Costs Operating Costs: Operating the wastewater treatment plant will significantly increase the sewer component of utility bills. Current information indicates that this will be as much as a 91% increase. Current Annual Sewer Charge Total New Charge (+91%) Average Residential Customer (216 m 3 ) Residential with B&B (274 m 3 ) Commercial Recreation (600 m 3 ) $290 $554 $417 $796 $984 $1,879 Commercial Hotel (15,170 m 3 ) $21,382 $40,840 12

12 Property Tax Impact Capital Costs Assumptions: Project Cost: $60,000,000* 73.33% Grant: $43,998,000 26,67% Debt: $16,002,000 $0 contributions from other users (likely to change) Annual Debt Servicing: $896, year debt 3.5% Property Class Tax Rate Residential Utility Business Recreation/Nonprofit Farm * $60M is rounded up from current project estimate for simplicity How to calculate your portion of the capital cost: Use the following formula to calculate your annual cost for the capital cost of the Wastewater Treatment Plant: Assessment value of your property/1000 x tax rate 13

13 Estimated Tax Increase Capital Cost Residential Class - 11% Increase: Business Class - 12% increase: Value 2018 Tax Bill WWTP Debt Servicing Value 2018 Tax Bill WWTP Debt Servicing $ 500,000 $ 2,870 $ 326 $ 750,000 $ 4,305 $ 490 $ 1,000,000 $ 5,740 $ 653 $ 1,250,000 $ 7,175 $ 816 $ 500,000 $ 7,941 $ 955 $ 750,000 $ 11,912 $ 1,433 $ 1,000,000 $ 15,882 $ 1,911 $ 1,250,000 $ 19,853 $ 2,387 14