Operation of a 2-Mg/Year Heavy-Water Detritiation Plant

Size: px
Start display at page:

Download "Operation of a 2-Mg/Year Heavy-Water Detritiation Plant"

Transcription

1 Operation of a 2-Mg/Year Heavy-Water Detritiation Plant W. T. Shmayda, C. R. Shmayda, C. Waddington, and R. D. Gallagher University of Rochester Laboratory for Laser Energetics Tyne Engineering Nuclear Source & Services Inc. (NSSI) 8th International Conference on Tritium Science and Technology Rochester, NY September 2007

2 Summary A Combined-Electrolysis Catalytic-Exchange (CECE) process is used to remove tritium from heavy water at NSSI The CECE system has processed 1.3 metric tons of heavy water per month between January June 2007 The activity of the processed water is below 0.2 MBq/kg (5 nci/kg) Plant throughput can be doubled with negligible cost E16086

3 Electrolysis, isotope separation, and the LPCE columns have been integrated to function as a CECE system Recombiner Tank D 2 O D 2 O 2 DT O 2 D 2 T 2 Facility design parameters detritiation factor (DF) > product activity <0.2 MBq/kg maximum D 2 gas flow = 100 slpm G/L = 1.05 production rate: 2 metric tons/a duty factor: 290 days Product drum Feed drum D 2 /DT E system ISS Column height (m) Maximum electrolyte activity: 0.6 TBq/kg (15 Ci/kg) DF = 10 7 Actual column height Design column height DF = DF = Product (metric tons/a) E16087

4 The LPCE column detritiation factor exceeds with a G/L = 1.05 Condensor G/L = 1.33 D 2 O product (L) D 2 Recombiner 10 7 LPCE column DTO feed DT O 2 DT to ISS Detritiation factor Design target MarchApril April April May May May Aug Electrolysis system 2007 E16088

5 Columns, control systems, and recombiner are housed in separate ventilated enclosures for safety Three 8.3-m column sets are housed in an insulated and ventilated enclosure. D 2 /O 2 recombiner and cooling tanks are located in a separate enclosure above the roof line. Electrolyzer behind wall in tritium lab. LPCE and recombiner control systems Control systems sealed from hydrogen environment E16089

6 Heat removal limits the electrolysis system to 50% of its design throughput E16090 ISS DTO feed LPCE columns Drier D 2 /DT O 2 Drier Drier TM Heat exchanger Electrolysis system System design parameters D 2 production 100 slpm (5.4 liters/h) 45 to 140 psig DP of ISS stream < 60 C DP of LPCE stream <10 C O 2 production DP of recombiner stream < 80 C Electrolyte <15 Ci/kg The current electrolyte activity is 13 Ci/kg. Recombiner Dew-point sensor

7 H 2 oxidation at 95 slpm in the recombiner has been demonstrated in steady state O 2 H 2 16 kw of heat is removed in steady state at 80 slpm Recombiner H 2 O 100 Collector H/X Temperature ( C) Upper middle Bottom Lower middle Top Optimum operating temperature range E H 2 (LPM) O 2 (LPM) H 2 O (LPM) Time (min)

8 Trace DT is removed from the D 2 stream leaving the ISS in the LPCE columns Recombiner D 2 O D 2 D 2 /trace DT DT D 2 /DT E system ISS T 2 Modes of operation on cryogenic mole sieve stripping DT from D 2 /DT mixtures (ppb to ppm) volume reduction (ppm to 0.1%) 90 Temperature ( C) Flow (slpm)( 10 3 ) D 2 Recombiner top Recombiner bottom E Time (min)

9 Operating in column set in total reflux yields a detritiation factor of with G/L = 1.05 Recombiner Tank O 2 D D 2 O Product activity (nci/kg) Electrolyte activity ~4 Ci/kg System inventory ~200 kg Design target Sample D 2 O electrolyzed (metric tons) E16093

10 The plant is maturing toward the design throughput Recombiner and electrolyzer cooling power limit the plant capacity factor to 50%. D 2 O processed (metric tons) CECE commissioning Total reflux Production Jan Feb March April May June July Aug Sept Oct Nov Dec Jan Feb March April May Percent Capacity factor Plant availability Jan Feb March April May June July Aug Sept Oct Nov Dec Jan Feb March April May Plant availability = operating hours/duty factor Capacity factor = quantity processed/design limit E16094

11 Optimizing facility operations can increase the production rate above 2 metric tons/a DF degradation with increased product draw is tolerable increase G/L from 1.05 to 1.1 to double the production rate The CECE throughput is tailored to meet the ISS throughput increasing the electrolyte activity improves ISS throughput - 15 to 20 Ci/kg improves production rate by 30% Increase the molar flux in the LPCE columns to increase production rate operating value ~10 mol/m 2 -s but 40 mol/m 2 -s is acceptable increasing molar flux improves LPCE performance E16095

12 The strategy to increase production capability will be staged: first optimize the process, then evaluate the need for upgrades Process optimization: Staged low-cost efforts increase G/L from 1.05 to 1.1 increase the electrolyte activity from 15 to 20 Ci/kg 1.8 to 4.6 mt/a is achievable but contingent on ISS performance Upgrade electrolyzer from 7 sm 3 /h to 30 sm 3 /h: modest cost effort molar flux over LPCE catalyst ~60 mol/m 2 /s But it requires a larger recombiner an ISS scale-up 4.6 to 20 mt/a E16096

13 Summary/Conclusions A Combined-Electrolysis Catalytic-Exchange (CECE) process is used to remove tritium from heavy water at NSSI The CECE system has processed 1.3 metric tons of heavy water per month between January June 2007 The activity of the processed water is below 0.2 MBq/kg (5 nci/kg) Plant throughput can be doubled with negligible cost E16086