Siemens Building Technologies New Campus in Zug. Unrestricted Siemens Switzerland Ltd 2017

Size: px
Start display at page:

Download "Siemens Building Technologies New Campus in Zug. Unrestricted Siemens Switzerland Ltd 2017"

Transcription

1 Siemens Building Technologies New Campus in Zug Unrestricted Siemens Switzerland Ltd 2017

2 Siemens Building Technologies Long Term Investments in Zug Consolidation of the Production Site Volketswil in Zug ~ CHF Total Investment Relocation of Production Facilities on site in Zug 05/ /2018 in 2021 Construction Office and Production Building Refurbishment of the existing Office Building «Highest Sustainability Goals LEED Platinum / Gold Certification Heating and Cooling with lake water Page 2

3 Highest requirements in terms of urban development and sustainability Urban Development Attraktive Aussenraumgestaltung Aufenthaltsqualiäten Öffentliche Nutzungen gewünscht Master plan considering the adjacent residential area Integration of the existing building (C) in the campus area Attractive outside areas to encourage interaction with the environment Eindeutige Clear entrance situation to all buildings Zugangssituation the campus Separierung Underground parking with 250 parking Fussgänger / Autos / lots Velos beneath / Anlieferung office building (A) Generous atrium in the office building (A) for best natural light infiltration to the office space Delivery Einbindung zone of the production (B) integrated Bestandsgebäude in building A C Öffentliche Durchwegung in Nord-Süd Richtung Rücksicht auf Nachbarschaft B Sustainability CO 2 neutral campus Use of lake water for cooling and heating purpose Efficient heat pumps Total refurbishment of existing building (C) according to LEED in 2021 Photovoltaic installation for show case Vegetated rooftops Rain water usage at the office building (A) Sustainable waste management concept for the entire Campus Integrated building automation system including energy optimization (based on Desigo CC) Page 3

4 The Office Building a new landmark in a growing residential area Key facts Total Floor Area: approx. 18,200 m 2 Footprint approx. 55 x 55 m Building height 25 m Atrium approx. 16 x 20 m Underground parking with 250 pp (additional 50 pp above ground) Ground floor / 1 st floor and 5 th /6 th floor occupied by SIEMENS 2 nd to 4 th floor for external rent (approx. 7,500 m 2 ) Semi-public use of ground floor with Reception and public café Siemens Visitor Center (Forum) Building Structure Flexible use from singe-office to open office space (including technical infrastructure) Cavity- / double floor for easy retrofitting High Fit-Out Standards Air Conditioning with hybrid cooling & heating panels (preinstalled and connected) Advanced cooling and space conditioning capacities for best room comfort LED light solutions integrated in building automation system Interior glare protection Page 4

5 The state-of-the-art Production Building Key facts Total Floor Area: approx. 18,400 m² Footprint approx. 125 x 50 m Building height ~16 m Production on 2 Floors (ground floor and 1 st Floor) Labs on 2 nd floor (in cooperation with Lucerne University of Applied Sciences) Nitrogen Tanks and waste container hidden behind facade Technical Installation All technical equipment installed in the building no emissions Media grid network for all technical media installed on the ceiling: flexible connection of equipment w/o interruption Energy Air compressor units with waste heat recovery used for hot water generation Photovoltaic showcase Infrastructure Scalable storage and buffering solution for highly efficient goods supply of the production areas Integral fire protection and safety solution Video surveillance, reservation system and digital signage Page 5

6 Certified Quality our Contribution to a sustainable Urban Development Efficient Supply Use of lake water (direct cooling) BT HQ office Water Reference DGNB Generation of heat and hot water with heat pumps, supplied by lake water. No fossil heat generation needed HVAC units equipped with cool & heat recovery systems LEED / Minergie BT HQ production m³/person a Office: 3,500 m 3 /a drinking water & 267,000 m 3 /a lake water (for heating & cooling) Production: 700 m 3 /a drinking water & m 3 /a lake water Office: 1,400 MWh/a Total electricity consumption Production: 6,800 MWh/a Total electricity consumption Production building: show case photovoltaic (30kW peak ) Primary Energy Reference EnEV Existing Building LEED Swiss Label LEED Platinum for the Office Building LEED Gold for the Production Building Minergie label focused on building shell and energy consumption for both buildings >200 BT HQ office / production ~64 kwh/m²a / ~150 kwh/m²a <0.1 kg CO ² /m²a 350 kwh/m²a 80 kg CO²/m²a kwh/m²a Primary Energy Need 50% below EnEV Criteria of low-energy standard fulfilled HP Office: 170 MWh/a Electricity, 600 MWh/a Heating, 590 MWh/a Cooling HP Production: 130 MWh/a Electricity, 530 MWh/a Heating, MWh/a Cooling Page 6

7 Implementation of the BIM methodology in the project Key Facts 3D Model is one of the first Siemens new construction projects using Building Information Modelling (BIM) Local SRE BIM team supported by experts and local FM provider Alignment with Siemens BT Big Room on site, used for common team work in the BIM model Work packages Office building: Execution planning on BIM model and definition of FM model & database Production building: Collection of building design data and definition of FM model & database Closed BIM mainly based on Autodesk tool set Benefits (amongst others) Early clash detections Control of planed to executed time schedule Digital twin with all information for operation Page 7

8 Christoph Leitgeb Siemens Schweiz AG Siemens Real Estate Tel: +41 (0) Page 8