Second European Working Meeting of the White Certificates Club

Size: px
Start display at page:

Download "Second European Working Meeting of the White Certificates Club"

Transcription

1 Second European Working Meeting of the White Certificates Club Study case comparison ITALY Ing Sergio LA MURA Technical Director R&D Milan ITALY Red. S LA MURA M ROVATI A GREPPI WCC Working Meeting 12 June

2 Introduction about the incentives in Italy incentive tools: Account energy photovoltaic (PV), Electrical Renewable Energy Sources (non-pv). (before Green Certificates, now Unique Fee); Thermal energy bill; Fiscal Deduction 55% (now 65%) for energy saving measures Fiscal Deduction 50% to undertake restructuring White Certificate (WHC), High Efficiency Cogeneration CAR WCC Working Meeting 12 June

3 from FIRE WCC Working Meeting 12 June

4 Now GSE Now GSE from FIRE WCC Working Meeting 12 June

5 Now GSE Now GSE from FIRE WCC Working Meeting 12 June

6 from FIRE WCC Working Meeting 12 June

7 from FIRE WCC Working Meeting 12 June

8 from FIRE WCC Working Meeting 12 June

9 High Efficiency Cogeneration (CAR) Ministerial Decree DM of 5 September 2011: Cogeneration units have the right, for each calendar year in which they meet the requirements of High Efficiency Cogeneration (CAR), to apply for energy efficiency certificates (or White Certificates) of type II, whose number is proportional to the energy savings achieved, if positive. White Certificates can be used to fulfill the obligation referred to DM 20 July 2004 or may be subject to exchange and bargaining. Alternatively, the operator may request the withdrawal by the GSE of White Certificates to which he is entitled. The withdrawal price shall be that applicable at the time of the entry into operation of the unit and remains constant throughout the incentive period. Only for units already in use before the Ministerial Decree of 5 September 2011, the withdrawal price shall be that applicable on the date of entry into force of the same Decree. WCC Working Meeting 12 June

10 NEW Ministerial Decree of Ministry of Economic Development 28 December 2012 (entered into force Jan. 3, 2013) New aspects: Transfer of the management of White Certificate system from AEEG to GSE; Modification of certain aspects of the Guidelines (cumulation, possibility of reporting from 2014 only projects under construction or to be made, etc..); Allocation to Enea's task to prepare and publish operational guidelines relating to the method in the final balance, with particular reference to certain industrial sectors and the definition of specific measures of support; Approval of 18 cards produced by Enea simplified in industry, civil as well as agriculture and transport; Introduction of a simplified procedure for large project (36,000 toe and technical life> 20 years) From 2015: obligation to UNI CEI for Energy Services Company (SSE) and SEM and to Energy Management Experts (EGE) UNI Access to the mechanism to firms in the industrial, civil, agricultural and service sectors that have appointed the Energy Manager (EM) or are equipped with energy management system ISO WCC Working Meeting 12 June

11 Activities leading up to the request of the WhC - TEE Energy Audit to identify interventions; Energy Service Contract between the end-customer and ESCO; Design and Permissions; Procurement of components and implemantation of the actions; Testing of interventions and issue of the relevant documentation; WCC Working Meeting 12 June

12 Procedure for recognition of WhC - TEE (1/5) Accreditation by the GSE ( / en / CertificatiBianchi / Pages / default.aspx) of the Applicant of the Obliged or Volunteer Subject, who is going to make the application. Insertion of new requests via portal GSE ( / en / CertificatiBianchi / Pages / default.aspx): Request for Verification and Certification of Standard Action (RVC-S) (only once) Request for Verification and Certification Analytical Action (RVC-A) (first time and then sometimes later) Project Proposal and Program Measurement (PPPM) (first time and then sometimes later) Request for Preliminary verifications (RVP) for PPPM (in oder to preliminarly check how many TEEs you can get from PPPM) According to the Case-Study, we considered Standard and Analytical Actions WCC Working Meeting 12 June

13 Procedure for recognition of WhC - TEE (2/5) Home Menu of GSE-TEE website Accreditation Form of SIRAM WCC Working Meeting 12 June

14 Procedure for recognition of WhC - TEE (3/5) Minimum threshold of savings: to get the TEE projects must achieve a minimum value of savings: - Standard projects: saving> 20 toe; - Analytical projects: saving> 40 toe during the reference period of the first request; - Final projects: saving> 60 toe in the first 12 months of the measure. To reach these thresholds, you can: - aggregate measures of the same type (ie belonging to the same card) that run on different subjects; - aggregate measures of different types (ie belonging to different cards), but in the same case (ie standard or assay) performed on the same subject; I- n the case of aggregation of ANALYTICAL +STANDARD Project Proposal and Program Measurement (PPPM) > 20 tep > 40 tep PPPM Ʃ Standard projects X Ʃ Analytical projects Y > 20 tep > 40 tep Ʃ Standard Projects: X + + Z Ʃ Analytical projects Y + + W Ʃ Standard + Analytical projects WCC Working Meeting 12 June

15 Procedure for recognition of WhC - TEE (4/5) Documentation to be submitted: Draft Standard (once): Information about the owner of the project; Information relating to key employees; Information on possible financial contributions; Description of the intervention or interventions included in the project; Date of start of the project; Prospectus reporting: activation date, number of units installed, specific savings,...; Analytical Project (first request): Information about the owner of the project; Information relating to key employees; Information on possible financial contributions; Description of the intervention or interventions included in the project; Prospectus reporting: activation date, the reporting period, the measured data of consumption and production,...; Analytical Project (requests after the first one): Any changes or modifications; Statement of accounting: reporting period, measured data of consumption and production; WCC Working Meeting 12 June

16 Procedure for recognition of WhC - TEE (5/5) Deadlines for requesting TEE: Standard Projects: within 180 days from the date of start of the project; Analytical Projects: within 180 days after the end of the reporting period; Actual Projects: Based on the PPPM approved; Certification of savings and emission of TEE: - GSE certifies the share of savings achieved within 60 days from receipt of the request; - Subsequently the GME (Energy Markets) emits the TEE in favor of the person who owns the project on account of this. Types of TEE recognized: -Type I: save on final consumption of electricity; - Type II: savings in natural gas consumption; - Type III: savings in primary energy consumption other than electricity and gas for vehicles; - Type IV and V: savings in primary energy consumption for transport. WCC Working Meeting 12 June

17 List of actions applicable to building for civil use: WCC Working Meeting 12 June

18 Study case: definition Global retrofit of a social collective housing Indicative characteristics of the housing 60 apartments (4 levels including ground floor) Collective heating Year of construction: 1970s Heated surface m 2 : 4000 m 2 WCC Working Meeting 12 June

19 Study case Choice of energy savings actions 1. ACTIONS regarding the Thermal Power Plant: 1. Centralized heating or cooling system of building for civil use (sch 26T, analytical) 2. Replacing water heater electric water heater with gas (sch. 02T, standard) 2. ACTION regarding the Building; 1. Replacement of single glazing with double glazing (sch. 05T, standard) 2. Insulation in walls and roofs (sch.06t, standard) WCC Working Meeting 12 June

20 recognition of WhC Centralized heating or cooling system of building for civil use (sch 26T, analytical) Description of the action Calculation of Savings and TEE Technical data Summary report: Volume: m 3, zona E (Milan) Action: change of the heater (natural gas) TEE (1 year): 23 TEE it s necessary to put together more actions for the 1 period TEE (5 years): about 100 TEE WCC Working Meeting 12 June

21 recognition of WhC Replacing water heater electric water heater with gas (sch. 02T, standard) Input e output scheda 02T Summary report: Number of boilers: 60 TEE (1 period): 6 TEEs 1 year 12 TEEs it s necessary to put together more actions TEE (further years): 10 TEEs/y WCC Working Meeting 12 June

22 recognition of WhC Replacement of single glazing with double glazing (sch. 05T, standard) Input e output scheda 05 T Summary report: Volume: m 3, zona E (Milan) Window surface: 360 m 2 Action: Replacement single glazing/double TEE (1 period): 8 TEEs 1 year 16 TEEs it s necessary to put together more actions TEE (further years): 8 TEEs/y WCC Working Meeting 12 June

23 recognition of WhC Insulation in walls and roofs (sch.06t, standard) Input e output scheda 06T Summary report: Volume: m 3, zona E (Milan) External surface: 1330 m 2 (without windows) Action: Insulation in walls and roofs TEE (1 period): 9 TEEs 1 year 18 TEEs it s necessary to put together more actions TEE (further years): 10 TEEs/y WCC Working Meeting 12 June

24 Summary of Procedure for recognition of WhC Ʃ Analytical projects Centralized heating or cooling system Ʃ Standard projects Replacing water heater electric water heater with gas Ʃ Standard projects X Replacement of single glazing with double glazing Ʃ Standard projects Y Insulation in walls and roofs Build = 46 > 40 2 Build = 24 > 20 2 Build = 24 > 20 2 Build = 36 > 20 Ʃ Standard Projects: 46 > 20 > 40 Ʃ Analytical projects 23 Ʃ Standard + Analytical 6 Project Proposal and Program Measurement (PPPM) WCC Working Meeting 12 June

25 thanks for your attention Sergio La Mura WCC Working Meeting 12 June