TRANS-SIBERIAN GOLD PLC

Size: px
Start display at page:

Download "TRANS-SIBERIAN GOLD PLC"

Transcription

1 PLC June 2011 Asacha Gold Project

2 ASACHA Project Status Construction Mine development proceeds steadily and stoping started in June 2011 Plant building construction is complete, plant equipment is installed and technological piping is in place Construction of plant engineering systems (ventilation, water, power and heat supply, sewage) is close to completion Infrastructure ready to ensure the plant start-up Cyanide and other reagents have been delivered to site 381 personnel at site, including 180 contractors 2

3 Underground Mine FULL-SCALE STOPING STARTED IN JUNE 2011: more than 700 tonnes extracted with about 40g/t grade As of 1 June 2011: - >4,800 metres/50,000 m 3 done since total ore ready for processing > 68,000 tonnes - mining activity with two shifts since Feb 2011 According to 2011 Mining Plan: ->3,300 metres/29,000 m 3 to be done - >100,000 tonnes of ore to be extracted (including 75,000 tonnes from stoping activities) -mine development is focused on preparing ore extraction works in

4 MINE Underground activities (metres)

5 MINE Underground activities (m 3 )

6 MINE Ore extracted by 1 June 2011: more than 68,000 tonnes with average grade 8.5 g/t, equals to 580 kg of Au ,

7 Plant Construction Plant building (outside) completed: foundations, sandwich panels walls, multi-layer roof with thermal insulation, concrete walls, windows Plant building (inside) completed: concrete inner walls, flooring, major metalwork, stairs, etc. Finishing operations (painting, smoothing, gypsum board walls erection, etc.) are going on Coarse ore bin and conveyor gallery completed, conveyor and feed bin installed Technological piping is being finalised Supply and engineering systems (power, water, heating, sewage, ventilation ) are being finalised Plant equipment assembled, mills installation and operation of electrolysis and desorption area checked by the manufacturer (checks in December 2010, June 2011 and in July 2011) 7

8 Plant Construction (1) December 2009 Coarse ore bin and conveyor gallery June

9 Plant Construction (2) 9

10 Plant Construction (3) Plant June

11 Infrastructure Objects Construction Tailings Storage Facility Dam construction laid down > 330,000 m 3 of gravel and rock material Geomembrane screen laying 76,400m 2 done Pipes are being laid, pumps, measuring equipment are being installed 11

12 Infrastructure Objects Construction Tailings Storage Facility June

13 Infrastructure Objects Construction Cold storage hangars - completed Sewage treatment facilities (Biodisk) completed Cyanide storage commissioned, cyanides at the site Explosives storage commissioned Pump water stations 1 st level pump station is ready; 2 nd level station is being finalised, assembled pumps unit to be installed Water, power, heat supply, sewage networks construction is being finalised Power station and power lines diesel gensets installed and checked, cables channel to the plant completed Fuel storage facility tanks installed, hydraulically checked, thermal insulation is being installed Repairs shop building with thermal insulation is ready, concrete floors and equipment foundations completed Grid power lines to the mine site, tailings storage facility site, etc. built Fire station at the plant site tanks installed and checked, the building completed, thermal insulation works are going on, pumps unit assembled and ready for installation 13

14 Infrastructure Objects Construction (1) Pump water station of the second level Switchboard at the camp s boilers unit Cables channel along the plant wall 14

15 Infrastructure Objects Construction (2) Fuel Storage Facility Fire Protection Station at the plant site. Thermal insulation of reservoirs. Heat pipeline constructed 15

16 Infrastructure Objects Construction (3) Biodisk-350 sewage treatment facility Cyanide storage facility commissioned Auxiliary cyanide storage ground 16 Small Fuel Storage Facility

17 ASACHA Project Status Related issues Personnel (plant personnel, security, etc.) hired Contract agreed with gold/silver refinery Gold/silver purchase contract under negotiation with Sberbank Metal Dore transportation contract agreed Permits obtained and commissioning of objects started (e.g. cyanide storage facility, explosives storage facility) Documentation for commissioning of other infrastructure objects is being obtained (fuel storage facility, camp, power system, storage facilities) Geologic audit by Wardell Armstrong is under way; site visit and data collection stages completed Rodnikovoe Geologic Report and Pre-feasibility Study approved by the Kamchatka Agency for Subsoil Use and submitted to the State Commission for Reserves in June

18 Production plans for 2011 Launch of the plant Sustainability and efficiency of technology: reaching ore processing volume and gold recovery ratio Production gold > 20,000 oz silver - > 30,000 oz 18

19 Plant Start-up Stages - Individual tests of equipment items - Hydraulic (liquid-operated) tests - Tests with waste rock - Operation with low grade ore - Operation with blended ore 19

20 Expected Plant Start-up Schedule - Start-up July First gold August