Consolidated Statement on various Environmental Aspects for Construction Project

Size: px
Start display at page:

Download "Consolidated Statement on various Environmental Aspects for Construction Project"

Transcription

1 Consolidated Statement on various Environmental Aspects for Construction Project S.N. Particular 1 Name of Project Development of IKEA Store in Navi Mumbai, India 2 Name, contact number & address of proponent Name: Mr. Sunil Verma Address: IKEA India Pvt. Ltd. 15 th Floor, DLF Building no. 9A, DLF Cyber City, Sec 24, Gurgaon, Haryana Telephone Number: Mobile Number: ID: sunil.verma@ikea.com 3 Name, contact number & address of Consultant 4 Accreditation of consultant (NABET Accreditation) 5 Type of project : Housing project/industrial Estate/SRA scheme/mhada/towns hip or Others EIA Coordinator: Ms Neetu S Nigam Co. Name:ERM India Private Limited Address: Building 10 A, 4th Floor, DLF Cyber City, Gurgaon Telephone Number: Mobile: ID: subir.gupta@erm.com ERM India Private Limited. The company is NABET accredited including for building and large construction projects vide letter NABET/EIA/1316/RA007. Others Commercial Establishment (IKEA Store) 6 Location of the Project Plot no 15, 15a, 15b, 15c, Turbhe MIDC, Taluka: Panvel District: Raigarh State: Maharashtra 7 Whether in Corporation/Municipal/ other area The Project site is located within Turbhe MIDC area, Thane Belapur Road, Raigarh District. 8 Applicability of the DCR The Project is located in MIDC area. DCR applies to the MIDC area within which proposed Project site is located. 9 Note on the initiated work (if applicable) Total constructed work (FSI+ Non FSI): Nil Date and area details in the necessary approvals issued by the competent authority (attach scan copies): Not 10 LOI/NOC from MHADA/Other approvals (if applicable) 11 Total Plot Area (sq. m) Deduction Net Plot Area Applicable Date and construction area details mentioned in the approved letter: Not Applicable 96,250.0 Sq.M 1

2 12 Permissible FSI (including TDR ) 13 Proposed built-up area (FSI & Non-FSI) 1.5 Proposed Built-up Area (Sq.M): 92,840 Sq.M FSI Area (Sq.M): 92,440 Sq.M Non FSI area (Sq.M): 400 Sq.M 14 Ground Coverage ~ 32% Percentage (%) (Note: Percentage of plot not open to sky 15 Estimated Cost of the INR 1,416 Crores (including Land Cost) project 16 Number of buildings & 1 Building (1 Basement + 1 Stilt + 2 Store Levels) its configuration(s) 17 Number of tenants and Not applicable shops 18 Number of expected 10,358 (including staff and visitors) residents/users 19 Tenant density per hectare Not applicable 20 Height of the building (s) 22 M (AMSL) 21 Right of way (Width of 12 M the road from nearest fire station to the proposed building (s)) 22 Turning radius for easy 12 M access of fire tender movement from all around the building excluding the width of plantation 23 Existing structures (s) Proposed site was earlier an industrial site. Structures existing on site will be demolished for the purpose of this project. These structures include tanks, treatment plants, utility rooms, parking sheds, storage areas and administrative buildings. 24 Details of the demolition with disposal (If applicable) Demolition debris: 5000 m 3 Demolition scrap: 100 MT Wooden scrap: 4 MT The demolition waste will be managed in accordance to Construction and Demolition Waste Management Rules,

3 25 Total water requirement Dry Season: Fresh water (CMD): 338 Cu.M/day & Source: MIDC Recycle water (CMD): 239 Cu.M/day Total water requirement (CMD): 577 Cu.M/day Swimming pool make up: NIL Fire Fighting (Cum) :1000 Cu.M 26 Rain water harvesting (RWH) Wet Season: Fresh water (CMD): 215 Cu.M/day & Source: MIDC Recycle water (CMD): 239 Cu.M/day Total water requirement (CMD): 454 Cu.M/day Swimming pool make - up: NIL Fire Fighting (Cum): 1000 Cu.M Level of Ground water table: Approximately 0.7 M below Road Level Size and no of RWH tank (s): 700 Cum and Quantity: One Location of the RWH tank (s): Refer to Annex A Size, no of recharge pits and Quantity: Nil Budgetary allocation (Capital Cost & O&M Cost): Capital cost: INR 20 Lakhs O&M cost: INR 3 Lakhs 27 UGT Tanks Location (s) of the UGT tank (s): 2 No. ; Refer to Annex A 28 Storm water drainage Natural water drainage pattern: Existing natural drainage pattern will be maintained. Quantity of Storm water: Designed for Cu.M/hour Size of SWD: 800 MM Diameter 29 Sewage and wastewater Sewage generation:264 m 3 /day Capacity of the STP: 265 m 3 /day STP Technology: Aerobic Moving Bed Bio Reactor system. DG Set (during emergency): 4 DG Set of 1250 KVA capacity each for power back Budgetary allocation (Capital cost and O&M cost): Capital cost: INR 50 Lakhs O&M cost: INR 15 Lakhs 3

4 30 Solid waste management Waste generation in the Pre Construction and Construction Phase Waste generation: 750 tonnes of construction debris and 90 kg/day of municipal waste Quantity of the top soil to be preserved: The site is a brownfield site with mostly rocky strata. Disposal of the construction way debris: The recyclable waste such as metal scrap, plastics will be sold out to vendors. About 90% of the debris will used to level low lying areas within the project site and the rest will be disposed to designated disposal site as approved by local authority. Waste generation in the operation phase: Dry waste (kg/day): 600 kg/day Wet waste (Kg/day): 1400 kg/day E-waste (Kg/month): 1000 kg/month Hazardous waste (Kg/month): 250 kg/month Biomedical waste (Kg/month) (If applicable): Not applicable STP Sludge (Dry sludge) (Kg/day): 500 kg/day Mode of disposal of waste Dry waste: Scrap dealer Wet waste: to be used for generation of bio gas E-waste: Authorised recycler Hazardous waste: To authorized vendors for disposal at TSDF as per MPCB approval Biomedical waste (If applicable): Not Applicable STP Sludge (Dry sludge): filter press for preparing compost Area requirement : Location (s) and total area provided for the storage and treatment of the solid waste: An area of 28.6 sq m has been earmarked for storage. Budgetary Allocation: Capital cost: INR 70 Lakhs O&M cost: INR 10 Lakhs 4

5 31 Green Belt Development Total RG area: 1. RG area other than greenbelt (Please specify playground, etc.):13,655 Sq.M 2. RG area under green belt: RG on the ground (sq. m):9,650 Sq.M RG on the podium (sq. m): Nil 3. Plantation: Number and list of trees species to be planted in the ground RG: 960 nos. of trees will be planted Azadirachta indica: 56 Alstonia scholaris: 177 Bahunia purpurea: 49 Bahunia racemose: 39 Cassia spectabilis: 09 Cordla sebestena: 98 Delonix regia: 05 Ehretla laevis: 86 Filicium decipiens: 04 Michelia champca: 35 Millingtonia hortensis: 04 Mesua ferrea: 20 Pongamia glabra: 24 Putranjiva roxburghii: 34 Peltophorum ferrugineum : 37 Plumeria alba: 206 Saraca indica: 65 Terminalia catappa: 09 Number and list of shrubs and bushes species to be planted in the podium RG: Nil Number and list of trees species to be planted around the border of nallah/stream/pond (if any): Botanical Name Common No Name Azadirachta indica Neem 56 Number, size, age and species of trees to be cut, trees to be transplanted: Trees to be cut down: 28 nos. Trees to be transplanted: 115 nos. Trees to be retained: 145 nos. NOC for the tree cutting/transplantation /compensatory plantation, if any: Necessary permissions will be obtained as required 4. Budgetary allocation (Capital Cost and O&M cost) Capital Cost : Capital cost: INR 80 Lakhs O&M cost: INR 10 Lakhs 5

6 32 Energy Power Supply: Maximum Demand :4.0 MW Connected Load: 5.9 MW Source: Maharashtra State Electricity Distribution Company Ltd. Energy saving measures by non-conventional method Detail calculation & % of saving: 20-25% Compliance of the ECBC guidelines: (Yes/No) (If yes, then submit compliance in tabular form): Yes Budgetary allocation (Capital and O&M cost): Capital Cost: 75 Lakhs O&M cost: 5 Lakhs 33 Environmental Management Plan Budgetary Allocation DG Set: Type and capacity of the DG Sets to be used: 4 nos. of 1250 KVA each Type of fuel required: HSD for DG sets Construction Phase (with Break-up): Capital Cost: INR 180 Lakhs O&M cost (Please ensure manpower and other details): INR 40 Lakhs Operation Phase (with Break-up) Capital cost: INR 135 Lakhs O&M cost (Please ensure manpower and other details): INR 77 Lakhs Quantum and generation of Corpus fund and Commitment: Not Applicable Responsibility for further O&M: As recommended SEIAA/MPCB 34 Traffic Management Nos. of the junction to the main road & design of confluence Two junction on Thane- Belapur road Parking details: Number and area of basement: 1 Basement; 24,200 Sq.M Number and area of Stilt: 1 Stilt; 28,072 Sq.M Total parking area: 32,509 Sq.M Area per Car: 12.5 Sq.M 2-Wheeler: 2,444 Sq.M 4-Wheeler: 29,975 Sq.M Public Transport: 90 Sq.M 35 CRZ/RRZ clearance obtain, if any Width of all internal roads (m): 6 M Not applicable 6

7 36 Distance from Protected Areas/Critically Polluted areas/eco-sensitive areas/inter-state boundaries Sanjay Gandhi National Park: ~ 16 km aerial distance; Navi Mumbai Critically Polluted Area: ~11 km aerial distance 7

8

9 Summary of project proposal 1. Plot Area 96,250 Sq.M 2. Total built-up area 92, 440 Sq.M 3. FSI Consumed Nos. of Buildings One (01) 5. Maximum height of building Area and nos. of the basement 1 basement of 32,200 Sq.M area 7. Area and nos. of podium Nil 8. Area of amenity space - Nil 9. Nos. of phases for project execution: Single Phase 10. Expected nos. of residents/users : (including staff and visitors) 9

10 Annex A Location of Rain Water Harvesting Tank and Water Tanks

11 Figure 1 Location of Water tank Raw water and treated water tanks RWH tank