CONCEPTUAL PLAN. Modification of Group Housing Project Trident Embassy. Plot no. 5 B, Sector 1, District Gautam Budh Nagar, Greater Noida, U.P.

Size: px
Start display at page:

Download "CONCEPTUAL PLAN. Modification of Group Housing Project Trident Embassy. Plot no. 5 B, Sector 1, District Gautam Budh Nagar, Greater Noida, U.P."

Transcription

1 Modification of Group Housing Project Trident Embassy At Plot no. 5 B, Sector 1, District Gautam Budh Nagar, For M/s Trident Infra Homes Pvt. Ltd Prepared By GRASS ROOTS RESEARCH & CREATION INDIA (P) LTD. (An ISO 9001:2008 Certified Co.: Accredited by QCI / NABET: Approved by MoEF, GoI) F , Sector-63, Noida, U.P. Ph.: , Telefax: eia@grc-india.com, grc.enviro@gmail.com Website: GRC INDIA TRAINING & ANALYTICAL LABORATORY (Accrediated by NABL & Recognized by MoEFCC, GoI) A unit of GRC India

2 INTRODUCTION M/s. Trident Infra Homes Pvt. Ltd. proposes modification of the Group Housing Project Trident Embassy which is located at Plot no. 5 B, Sector 1, District Gautam Budh Nagar, Greater Noida, U.P. The company has vast experience in planning and construction of Residential & Commercial projects. The project was earlier granted Environment Clearance by SEIAA, U.P. vide letter no. 1574Parya/SEAC/1492/2012/DD (Sh) dated 07 th October 2013 for Plot area 30,480 sqm (7.531 acre) and Built-up area 1,66, sqm. A copy of the EC letter is enclosed as Annexure I. The project has undergone some revision in planning due to which the built-up area will reduce to 1,66, sqm. However, the plot area remains same. Therefore, the application is being submitted for amendment in Environment Clearance as a result of proposed modification of the project. SITE LOCATION AND SURROUNDING The project site is located at Plot no. 5 B, Sector 1, Greater Noida, District Gautam Budh Nagar, Uttar Pradesh. The geographical co-ordinates of the project site are 28 34' 15.98" N & 77 26' 45.49" E. Google earth image depicting 500 m & SoI Toposheet depicting 10 & 15 km around project site are enclosed as Annexure - II (a) & (b) respectively. CONNECTIVITY The project site is well connected through Noida Greater Noida Link Road. Dadri and Pusta Road are approx 4.09 km and 3.88 km away from project site towards South and South West direction, respectively. NH 91 is approx km away from project site towards North East direction. The nearest railway station is Ghaziabad Railway station, which is approx km away towards North. Indira Gandhi International Airport is at a distance of approx km from the project site towards West direction. M/s Trident Infra Homes Pvt. Ltd 1

3 AREA STATEMENT The total area of project site is 30, m 2 (or acre). The detailed area statement is provided below in Table 1. S. No. Particulars Table 1: Comparative Detailed Area Statement Value as per earlier EC (m 2 ) Modification (m 2 ) Total Area (m 2 ) Percentage 1. Total Plot Area 30, Permissible Ground Coverage (35%) 10, Proposed Ground Coverage Total Permissible FAR Area including purchasable FAR for Residential (@ = 3.5) 1,06, Permissible FAR Area for Commercial (@1% of permissible FAR for Residential) Permissible Facility/Ancillary FAR Area (@15% of total permissible FAR for Residential) 16, Total Proposed FAR (@ 3.492) 1,05, ,06, Residential Commercial Connecting Bridge Community area/club 1,04, Nil * 1,05, * 8. Basement Area 26, , Podium Area 23, , Stilt Area M/s Trident Infra Homes Pvt. Ltd 2

4 11. Proposed Facility/Ancillary FAR Area (Club + Fire Staircase + Lift lobby + Mumty + Machine Room + Lift wells + Cupboard + Guard room + Overhead Tank + STP) 12. Total Built-up area ( ) 13. Required Green area (@50% of Open area) 1,66, ,66, , , Open Area 25, , Landscape Area (52.51% of Open Area) Paved/road area 12, , , , % 38.62% 15. No. of DUs No. of Towers 12 Nil Maximum Building Height (m) 69 (G+24) (G+26) *Counted in Facility FAR area S. No. Description 1. Total Proposed FAR (@ ) Table 1: Comparative Built-Up Area Value as per earlier EC (m 2 ) 1,05, Modification (m 2 ) Total Area (m 2 ) 1,06, Residential 1,04, ,05, Commercial Connecting Bridge Community area/club Nil * * 2. Basement Area 26, , Podium Area 23, , M/s Trident Infra Homes Pvt. Ltd 3

5 4. Stilt Area Permissible Facility/Ancillary FAR Area (Club + Fire Staircase + Lift lobby + Mumty + Machine Room + Lift wells + Cupboard + Guard room + Overhead Tank + STP) Total Built-up area 1,66, ,66, *Counted in Facility FAR area POPULATION DENSITY The total population of project after proposed modification will be 6849 persons. The detailed comparative population break-up is given below in Table 3 and population break-up (post modification) is given in Table 4: Table 3: Comparative Population Break-up S. No. Description Value as per Modification Population earlier EC 1 Residents (@4.5/DU) 2 Staff (Maintenance + Commercial) 3 Visitors Total Population M/s Trident Infra Homes Pvt. Ltd 4

6 Table 2: Population Break up (Post Modification) S. No. Description DU PPU Population 1. Residents Staff 2. (Maintenance Commercial) 3. Visitors 824 Grand Total Population 6849 PROJECT COST The total estimated cost of the project (post modification) is approx. INR 320 Crore including cost land as well as development. WATER REQUIREMENT AND SUPPLY SYSTEM The total water requirement for the project (post modification) will be approx. 554 KLD out of which domestic water demand is 497 KLD. The fresh water requirement will be 353 KLD. However, one time fresh water demand for the project will be 554 KLD. The water will be supplied by Local Authority. The comparative water calculation is given below in Table 5. S. No. Description Table 3: Comparative Water Calculation Value as per earlier EC (KLD) Modification (KLD) Quantity (KLD) 1. Total water demand Domestic water Fresh water Waste water STP Capacity M/s Trident Infra Homes Pvt. Ltd 5

7 Table 6: Calculation for Daily Water Demand (Post Modification) S. No. Description Occupancy Rate of Water Demand (lpcd) Water Requirement (KLD) A. Domestic Water Residents Staff (Maintenance + Commercial) Visitors Total Domestic Water 497 KLD B. Horticulture (13, m 2 ) 3 l/sqm 39 C. DG Cooling* (2 x x 625) 0.9 l/kva/hr 18 Grand Total (A+B+C) 554 KLD *Considering 6 hrs operation/day for DG sets Table 7: Waste Water Calculation (Post Modification) Domestic Water Requirement Fresh (70% of domestic) Flushing (30% of domestic) Waste Water Generated (80% fresh + 100% flushing) 497 KLD 348 KLD 149 KLD = 427 KLD The water balance diagram of project (post modification) during rainy and non-rainy season are shown below in figure 1 & 2: M/s Trident Infra Homes Pvt. Ltd 6

8 FRESH WATER (348 KLD) (70% of Domestic water) FLUSHING (149 KLD) (30% of Domestic water) HORTICULTURE ( % 149 KLD 39 KLD WASTE WATER GENERATED (427 KLD) STP CAPACITY KLD DG COOLING (18 KLD) 18 KLD CSTP (178 KLD) Waste water Treated effluent Figure 1: Water Balance Diagram (Non-rainy season) M/s Trident Infra Homes Pvt. Ltd 7

9 FRESH WATER (348 KLD) (70% of Domestic 80% WASTE WATER GENERATED (427 KLD) STP CAPACITY % FLUSHING (149 KLD) (30% of Domestic water) KLD DG COOLING (18 KLD) 18 KLD CSTP (217 KLD) Waste water Treated effluent Figure 2: Water Balance Diagram (Rainy season) Wastewater Generation & Treatment It is expected that the project (post modification) will generate approx. 427 KLD of wastewater. The wastewater will be treated in onsite STP of 515 KLD capacity. The treated effluent will be reused for flushing, horticulture & DG cooling. Surplus will be discharged to CSTP of Greater Noida Authority. SEWAGE TREATMENT PLANT SAFF TECHNOLOGY Sewerage System An external sewage network shall collect the sewage from all units, and flow by gravity to the proposed sewage treatment plant. M/s Trident Infra Homes Pvt. Ltd 8

10 Following are the benefits of providing the Sewage Treatment Plant in the present circumstances: Reduced net daily water requirements, source for Horticultural purposes by utilization of the treated waste water. This shall consequently lead to a lower withdrawal from the underground aquifer water sources. Reduced dependence on the public utilities for water supply and sewerage systems. Sludge generated from the Sewage Treatment Plant shall be rich in organic content and an excellent fertilizer for horticultural purposes. a. Waste Water Details (a) Daily load : 427 KLD (b) Duration of flow to STP : 24 hours (c) Temperature : Maximum 32 o C (d) ph : (e) Colour : Mild (f) T.S.S. (mg/l) : mg/l (g) BOD 5 (mg/l) : mg/l (h) COD (mg/l) : mg/l b. Final discharge characteristics (a) ph : 6.5 to 8.5 (b) B.O.D. : <10 mg/l (c) C.O.D. : <30 mg/l (d) Total Suspended Solids : <50 mg/l Treatment technology is based on the Submerged Aerobic Fixed film reactor. The main advantages of SAFF technology is that having the combination of the fixed film technologies and fine bubble diffused aeration techniques. With the higher surface area of bio media, higher organic loading rates are enabled, thus reducing the overall size required of the aeration tank. Raw sewage will be collected under gravity into the sump after allowing to pass through the bar screen. The bar screen, by removing coarse solids from the sewage help in protecting the raw sewage pump. The raw sewage sump, through temporarily holding the incoming sewage facilitates both pumping of sewage through the STP and dampening the flow variation in the received sewage. The sewage collected in equalization tank is pumped and passed through the Aeration tank. From M/s Trident Infra Homes Pvt. Ltd 9

11 the aeration tank, the raw sewage goes to a settling tank (Clarifier) to allow gravity separation of the mixed liquor suspended solids from the treated wastewater. Settled MLSS are then recycled to the aeration tank. Excess sludge from the system is drained out. The excess sludge will be dewatered and used as manure for green belt development. The effluent coming after treatment will be passed through the flocculation cum settling tank to capacity. Treated effluent coming out from the tank will be passed through softening plant followed with disinfection. Figure 3: STP Design Sewer System The alignment and slope of the sewer line will follow the road network, drains or natural ground surface and will be connected to the trunk sewers. The discharge point will be a treatment plant, a pumping station, a water course or an intercepting sewer. Pumping stations would be provided at places where the natural slope of the terrain is insufficient to permit gravity flow or the cost of excavation is uneconomical to do the same. M/s Trident Infra Homes Pvt. Ltd 10

12 RAIN WATER HARVESTING The storm water collection system for the premises shall be self-sufficient to avoid any collection/stagnation and flooding of water. The amount of storm water run-off depends upon many factors such as intensity and duration of precipitation, characteristics of the tributary area and the time required for such flow to reach the drains. The drains shall be located near the carriage way along either side of the roads. Taking the advantage of road camber, the rainfall run off from roads shall flow towards the drains. Storm water from various plots/shall be connected to adjacent drain by a pipe through catch basins. Therefore, it is proposed to provide 4 RWH pits at selected locations, which will catch the entire run-off from site. 1) Since the existing topography is congenial to surface disposal, a network of storm water pipe drains is planned adjacent to roads. All building roof water will be brought down through rain water pipes. 2) Proposed storm water system consists of pipe drain, catch basins and seepage pits at regular intervals for rain water harvesting and ground water recharging. 3) For basement parking, the rainwater from ramps will be collected in the basement storm water storage tank. This water will be pumped out to the nearest external storm water drain. 4) Peak Hourly rainfall of 40 mm/hr shall be considered for designing the storm water drainage system. Rain water harvesting has been catered to and designed as per the guideline of CGWA. Peak hourly rainfall has been considered as 45 mm/hr. The recharge pit of 3 m diameter and 4 m depth is constructed for recharging the water. Inside the recharge pit, a recharge bore is constructed having mm diameter with 160 mm PVC slotted pipe up to a layer where sandy aquifer/ deeper aquifer permeable layer exist. The bottom of the recharge structure will be kept 5 m above this level. At the bottom of the recharge well, a filter media is provided to avoid choking of the recharge bore. Design specifications of the rain water harvesting plan are as follows: Catchments/roofs would be accessible for regular cleaning. The roof will have smooth, hard and dense surface which is less likely to be damaged allowing release of material into the water. Roof painting has been avoided since most paints contain toxic substances and may peel off. M/s Trident Infra Homes Pvt. Ltd 11

13 All gutter ends will be fitted with a wire mesh screen and a first flush device would be installed. Most of the debris carried by the water from the rooftop like leaves, plastic bags and paper pieces will get arrested by the mesh at the terrace outlet and to prevent contamination by ensuring that the runoff from the first minutes of rainfall is flushed off. No sewage or wastewater would be admitted into the system. No wastewater from areas likely to have oil, grease, or other pollutants has been connected to the system. Calculations for storm water load - Roof-top area = Ground Coverage = m 2 Green Area = 13, m 2 Paved Area = Total Plot Area (Roof-top Area + Green Area) = 30, ( , ) = 11, m 2 Run-off from green and paved area: Green Area = 13, = 58 m 3 /hr Paved Area = 11, = 397 m 3 /hr Total Run-off from green and paved area = = 455 m 3 /hr Taking 15 minutes retention time, total volume of storm water = 455/4 = 114 m 3 Taking the effective dia and depth of a Recharge pit 3 m and 4 m respectively, Volume of a single Recharge pit = π r 2 h = = 28 m 3 Hence no. of pits required = 114 / 28 = Pits = 4 pits 4 Rain Water Harvesting pits are proposed for artificial ground water recharge. M/s Trident Infra Homes Pvt. Ltd 12

14 Figure 4: Rain Water Harvesting Pit Design Run-off from roof top: Monthly rain water harvesting potential of roof-top area = Roof-top area Max m monthly rainfall (m) runoff coefficient = = 512 m 3 Considering storage facility for 2 days run-off = 512/15 = 34 m 3 Volume of a tank (3 2 4 m) = 24 m 3 Hence no. of tanks required = 34/24 = tanks are proposed for harvesting run-off from rooftop area. M/s Trident Infra Homes Pvt. Ltd 13

15 PARKING FACILITIES Adequate provision will be made for parking within the project site. Parking details are provided below: PARKING REQUIRED: As per MoEFCC norms = 1 ECS/ 100 m 2 Proposed FAR area = 1,05, /100 = 1056 ECS Total parking required as per MoEFCC norms = 1056 ECS As per bye-laws = 1 ECS/80 m 2 of Permissible FAR = /80 = 1334 ECS Total Parking required as per bye-laws = 1334 ECS PARKING PROPOSED: Area proposed for Stilt parking = m 2 Area proposed for 1 ECS of Stilt parking = 30 m² Parking proposed for Stilt parking = 108 ECS Area proposed for Podium Parking = m 2 Area proposed for 1 ECS of Podium Parking = 30 m² Parking proposed for Podium Parking = 510 ECS Area proposed for Basement Parking = m 2 Area proposed for 1 ECS of Basement Parking = 30 m² Parking proposed for Basement Parking = 732 ECS TOTAL PARKING PROPOSED = = 1350 ECS M/s Trident Infra Homes Pvt. Ltd 14

16 POWER REQUIREMENT The power requirement shall be met from Noida Power Company Limited. The total power requirement for the project post modification will be 5137 KVA. Details of D.G Set There is provision of 4 no. of DG sets of total 3270 KVA (2 X X 625) capacity for power back up in the project. The DG sets will be equipped with acoustic enclosure to minimize noise generation and adequate stack height for proper dispersion. SOLID WASTE GENERATION Solid waste would be generated both during the construction as well as operation phase. The solid waste during the construction phase comprise of excavated materials, used bags, bricks, concrete, MS rods, tiles, wood etc. The following steps are proposed to be followed for the management solid waste: Construction yards have been provided for storage of construction material within project site. The excavated material such as topsoil and stones are being reused for construction. Excavated top soil is being reused for landscaping development. M/s Trident Infra Homes Pvt. Ltd 15

17 Solid Waste Construction Waste Food Waste Construction waste, Broken Bricks, Waste Plaster Empty Cement Bags Excavated Soil As per MSW Rules, 2016 Used in re-filling, raising site level For Road making purpose Top soil conserved for landscaping, balance & re-filling Figure 5: Solid Waste Management Scheme (Construction Phase) During the operation phase, waste will comprise of domestic as well as horticultural waste. The solid waste generated from the project shall be approx kg per day 0.50 kg per capita per day for 0.15 kg per capita per day for 0.25 kg per capita per day for staff and landscape 0.2 kg/acre/day). Following arrangements will be made at the site in accordance to Municipal Solid Waste (Management and Handling) Rules, Table 8: Calculation for Solid Waste Generation from Project (Operation Phase) S. No. Category Occupancy Per Capita Waste Generation (kg/day) Waste generated (kg/day) M/s Trident Infra Homes Pvt. Ltd 16

18 1. Residents Staff Visitors Landscape waste kg/acre/day 1 5. STP sludge 43 TOTAL SOLID WASTE 3085 kg/day Collection and Segregation of waste 1. A door to door collection system will be provided for collection of domestic waste from household units. 2. Local vendor will be hired to provide separate colored bins for dry recyclable and Biodegradable waste. 3. Adequate number of colored bins (Green, Blue, and Dark Grey bins separate for Biodegradable and Non Bio-degradable) are proposed to be provided at the strategic location within the complex. 4. Litter bin will also be provided in open areas like parks, etc. Treatment of waste Bio-Degradable waste 1. Bio-degradable waste will be subjected to composting through Organic Waste Converter to form manure for use in gardening/horticulture. 2. STP sludge is proposed to be used as manure. 3. Horticultural waste is proposed to be composted and used for gardening purpose. Recyclable waste 1. Grass Recycling The cropped grass will be spread on the green area. It will act as manure after decomposition. 2. Recyclable wastes like paper, plastic, metals etc. will be sold off to recyclers. Non-Recyclable waste Non-Recyclable waste will be disposed through a local approved agency. The solid waste management scheme for Operation Phase is depicted in the figure below: M/s Trident Infra Homes Pvt. Ltd 17

19 Figure 6: Solid Waste Management Scheme (Operation Phase) Organic Waste Converter A waste converter is a machine used for the treatment and recycling of solid and liquid refuse material. A converter is a self-contained system capable of performing the following functions: pasteurization of organic waste; sterilization of pathogenic or biohazard waste; grinding and pulverization of refuse into unrecognizable output; trash compaction; dehydration. Benefits of organic waste converter: 1. Large quantity of solid waste is converted to manure in a very short period 2. Manure can be used as compost for gardening 3. Machine requires less space and the efficiency is high 4. Manpower and maintenance is very less 5. This is one of the latest techniques of managing biodegradable solid waste. M/s Trident Infra Homes Pvt. Ltd 18

20 Operation cost of OWC: Organic Waste Converter (Dim. 3m 4m) is proposed to be used for composting waste 120kg/batch or 3000 kg/day & it requires electricity of about 13.5 HP. No. of batches /day = 3000/20 = 150 No. of batches to convert 1697 kg/day = 1697/20 = 85 Monthly per capita Operation Cost of OWC: The operating cost of OWC-300 = 90,000 INR/month Cost/day = 90,000/30 = 3000/- (i.e. 30 batch/day = 3000/-) 1 batch/day cost = 3000/30 = 100 INR Cost for 85 batch/day = /- = 8500/- Monthly operating cost = = 2,55,000/- Total residential population of the project = 5643 Operating cost of OWC-300 = 2,55,000 INR/month Monthly per capita cost = Monthly operating cost/total Residential population of the project (i.e. 5643) = 2,55,000/5643 = INR 45/month GREEN AREA The total green area measures 13, m 2 (41 % of plot area) which includes area under greenbelt plantation, avenue plantation and parks. Evergreen tall and ornamental trees have been proposed to be planted. List of the plantation is given below in Table 9. M/s Trident Infra Homes Pvt. Ltd 19

21 Table 9: Proposed Plantation List S. No. Scientific Name Local Name 1 Cassia fistula Amaltas 2 Delonix regia Gulmohar 3 Buhinia purpurea Koenar 4 Bauhinia variegata Kachnar 5 Peltophorum ferrugineum Copperpod 6 Jacaranda ferrugineum Jacaranda 7 Lagerstroe flosreginae Banaba 8 Grevillea robusta Silver Oak 9 Callistemon lanceolatus Bottle brush 10 Anthocephatus cadamba Kadamb 11 Polyalthia longifolia False Ashok 12 Putranjiva roxburghii Putranjiva 13 Sterculia alata Cola nut 14 Melia azadirachta Bainkan 15 Tamarindus indica Imli DETAILS OF CONSTRUCTION MATERIAL 1. Coarse sand 2. Fine sand 3. Stone aggregate 4. Stone for masonry work 5. Cement 6. Reinforcement steel 7. Pipe scaffolding (cup lock system) 8. Bricks M/s Trident Infra Homes Pvt. Ltd 20

22 9. CLC fly ash blocks 10. Crazy (white marble) in grey cement 11. P.V.C. conduit 12. MDS, MCBs 13. PVC overhead water tanks /2' thick red colour paver tiles 15. PPR (ISI marked) 16. PVC waste water lines 17. S.W. sewer line up to main sewer 18. UPVC is being used as the Sewer pipe material 19. PVC rain water down take 20. Stainless steel sink in kitchen 21. Joinery hardware- ISI marked LIST OF MACHINERY USED DURING CONSTRUCTION (i) Dumper (ii) Concrete mixer with hopper (iii) Excavator (iv) Concrete Batching Plant (v) Cranes (vi) Road roller (vii) Bulldozer (viii) RMC Plant (ix) Tower Cranes (x) Hoist (xi) Labor Lifts (xii) Pile Boring Machines (xiii) Concrete pressure pumps (xiv) Mobile transit mixer M/s Trident Infra Homes Pvt. Ltd 21