1 Hunters Point Site Project Advisory Committee Meeting October 27,

2 Agenda Welcome and Introductions Safety Moment Project Status Upcoming/Current Work NOW Hunters Point/Interim Uses Local Hiring Continued Communications Q&A 2

3 Introductions Project Advisory Committee Members PG&E Rob Saur, Remediation Project Manager Andrea Gooden, Manager, Stakeholder Engagement Susana Razo, Communications Lead Contractors JBR Partners James Bryant (Community Outreach) ERM John Cavanaugh (Remediation Contractor) ERM Rob Dyer (Remediation Contractor) envelope a+d Nathan John (Architect) envelope a+d Allegra Madsen (Program Designer) 3

4 Committed to Safety Room Safety Site Safety Public Safety Temporary walkway provides pedestrian safety during Area J work 4

5 Hunters Point Site 5

6 Project Status Groundwater cleanup work: Completed. Monitoring and polishing work ongoing Area J Retaining Wall Area: Cleanup underway. Complete early Shoreline Area: Awaiting final permits Interim use events: Ongoing 6

7 Groundwater Treatment Program Treatment of the off-site area (White Cap and Jennings) completed at the end of 2014 Polishing work ongoing Periodic monitoring and sampling to confirm treatments are effective DTSC oversight and confirmation Groundwater Monitoring Area Off-Site Groundwater Remediation Area 7

8 Area J Retaining Wall Area Cleanup Majority of Area J soil cleanup completed in 2011 Excavating soil near the retaining wall and installing a durable cover Air monitoring and dust control during soil disturbing work Anticipated completion: early

9 Area J Cleanup Pedestrian/Auto Safety 9

10 Air Monitoring and Dust Control Air monitoring and dust control during soil disturbing work - Perimeter misters - Manual misters - Air monitors - Covered stockpiles and trucks Targeted mindful use of water; misters with specialized nozzles Air monitoring results reported to BAAQMD, uploaded to 10

11 Area J Streetscape Improvements New pedestrian plaza at the corner of Evans Ave. and Jennings St. Neighborhood public space New plaza will serve as overlook to Site and Bay 11

12 Area J Streetscape Improvements 12

13 Shoreline Area Cleanup Cleanup to address impacted soils in parts of the Shoreline Area Restoration to follow Cleanup Performed over two construction seasons (September 1 - January 31) Permitting with USACE, Regional Board, BCDC, and other agencies DTSC Work Notice to be distributed before work begins 13

14 Shoreline Area Cleanup: Soil Removal Planning to begin soil removal in November, pending receipt of permits Removal of top two feet of accessible soil (in six areas) Off-site soil disposal, covered trucks using established truck routes Clean soil or rock placed where impacted soil is removed Air monitoring, dust control and soil management 14

15 Shoreline Area Cleanup: Restoration Begin in Fall 2016 Enhanced public path and other features 15

16 Interim Uses: NOW Hunters Point Launched in 2013 Local youth + labor (APRI / JBR) 29 events to date First evening events, job training, health activities Over 4,000 participants Learn more: 16

17 17

18 Local Hiring Local Hiring Goal: 30 percent Use of local contractors when possible Coordinate local hires with SF CityBuild program ( ) PG&E worker requirements: - Go to Local Jobs tab 18

19 Ongoing Communications updates PAC Meetings + Follow-Up Newsletters PGE.com/hunterspoint Project Hotline/ June 2015 PAC Meeting 19

20 Contacts For More Information (Cleanup): Environmental Remediation Response Line: Project Project Website: Interim Use Team: NOW Hunters Point: (415) ; Website: California Department of Toxic Substances Control Contacts: Robert (Bob) Boggs: (510) ; Wayne Hagen: (510) ; 20

21 PG&E Contacts Customer Service: (1-800-PGE-5000) Electric Outage Information: IF YOU SMELL NATURAL GAS, see downed power lines, or suspect another emergency situation, leave the area immediately and then call and PG&E at

22 Thank You!