Boundary Dam Integrated Carbon Capture Demonstration Project

Size: px
Start display at page:

Download "Boundary Dam Integrated Carbon Capture Demonstration Project"

Transcription

1 Boundary Dam Integrated Carbon Capture Demonstration Project Status of Carbon Capture Programs and Technology August 26, 2010 Presented by Michael J. Monea, Vice President, Integrated Carbon Capture & Sequestration Projects for Saskatchewan Power Corporation 1

2 SaskPower Mandate Crown Corporation Owned by Government of Saskatchewan Mandate is to Customers SaskPower's mission is to provide safe, reliable and sustainable power to the people of Saskatchewan. Providing customers with power at the lowest possible cost. 2

3 100 MW 451,713 customers. 155,818 km of T&D lines 3668 MW generation 6.5% Peak Load Growth MW Lignite 150 MW 4

4 MW SaskPower Capacity Position Forecast Demand Committed Capacity Drops Due to Coal Retirements? 2000 Natural gas (+wind?) 1500 Near Term Base Clean coal 1000 Polygeneration Load Generating DSM 500 Need Biomass 0 Imports Hydro Nuclear 4

5 Greenhouse Gas Air Emission Regulations Greenhouse Gas (GHG) Regulations GHG Requirements (discussed to date): 17% below 2005 levels by 2020 Performance standard applies to new coal in 2015 and old coal beyond 45 year end of life Federal Policy to be determined in 2010 regulations potentially set in 2015 Saskatchewan in alignment with Federal government on environmental regulations 5

6 Nat Gas Combined Cycle New Coal Refurbish Refurbish & Cleaner Refurbish & Capture Refurbish, Capture & Sell Cost of Electricity CO2 Not Sold CO2 Sold baseline is cost of new natural gas generation 9

7 Why BD3? BD ICCS Demonstration 1) Valuable Existing Assets lowers capital costs = lower cost of electricity 2) Right Size 1 million tonnes of CO 2 per year matches enhanced oil recovery (EOR) market 3) BD3 reaches major decision in 2013 If no action default is retirement 0 MWs 4) Applicable to other aging coal fired units 7

8 SaskPower Clean Coal Objectives To develop environmentally sustainable electricity supply options that utilize Saskatchewan s coal resource. To ensure that the cost of electricity (COE) from clean coal is lower than the cost from other options. 8

9 BD ICCS Demonstration Five Key Deliverables: 1) Life Extension - Refurbish Unit 3 to allow an additional 30 years of reliable, safe operation 2) Performance Upgrades - Upgrade Unit 3 criteria emissions control (SOx, NOx) as well as improve efficiency 3) CO 2 Capture Technology incorporate technology that best meets our overall Corporate objectives both near and long term 4) Competitive COE all of the above to be accomplished with a COE at or below that of the next lowest supply option likely Nat. Gas CC. Likely require a CO 2 sale for EOR to achieve 5) In-Service

10 Project Economics Cost of Electricity (COE)= lifetime costs lifetime nonelectricity revenues Costs: capital cost of the designing, procuring and erecting the plant lifetime expenses to operate and maintain the plant lifetime cost of fuel Revenues: revenue from the sale of CO 2 avoided green house gas emissions credit subsidy funding from government for first of a kind project 14

11

12 Unit #3 21

13 CO 2 Capture Plant 22

14 Construction Forces Estimated 1,100 person-years of work; Work will begin almost immediately after project approval, late 2010; Peak construction period: mid-2011 through mid-2013 average in range of 300 to 400 people, peaking at approximately 600 people. 27

15 Boundary Dam Project Capital Cost Breakdown CO 2 Capture 43% Refurbishment 30% Emissions Controls Efficiency Upgrades 27%

16 Saskatchewan Experience in CO 2 Storage Weyburn-Midale CO 2 Monitoring and Storage Project 31

17 Mbbls/d (Gross) Total Oil Production at Weyburn Around 30,000 bbl/day: a 35-year high 20,000 bbl/d are due to the CO 2 flood Prim ary & Waterflood Current production at 35 year high Vertical Infills Pre CO2 Hz Infills CO2 EOR Waterflo o d Impro vement 0 Jan-55 Jan-61 Jan-67 Jan-73 Jan-79 Jan-85 Jan-91 Jan-97 Jan-03 Jan-09 Jan-15 CO2 stored equivalent to removing more than 8 million cars off the road for a year 32

18 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Existing Power Plant Turbine Commitment Specify, Design, Awardx SaskPower Balance of Plant Repair Planning and Mobilization Process Design, Condition Design Turbine Install and BOP repairs Engineering & Procurement Authorization Process Equipment Select CO2 System (vendor & technology) Detailed CO2 system design CO2 Capture Award Process Equipment Supply Contracts Proposals Detailed design, construction Requested contracts ready Construct phase 1 (.5 Mtpy) Commission phase 1 Procure/Construct/comm'n phase 2 SaskPower mobilization plan on schedule EIA, Water License EOR - Phase 1 Shortlist CO2 Capture SaskPower/E&R/Oil Co#1 agreement Systems Oil Co # 1 - detailed - Complete modelling Site Design Install Pilot Facilities Oil Co #1 - Pilot testing Final Geo Modelling Finalize CO2 sale agreement #1 Engineer, Procure, Construct Environmental Approval - surface/eor Turbine Contract Awarded x Model x x Env Approval Eng EOR Pilot Env Approval x Model x Procure, Construct x Shut down Environmental/regulatory issues resolved EPC Capture Train #1 Start Up CO2 sale or partnership complete Major equipment contracts in place Decision to Construct EPC Major Commitment - release for construction CO2 System Selected EOR - Phase 2 Planning, Piloting EPC, Start Up EOR side Carbon Capture Train #2 EPC Capture Plant Train #2 Public Consultation In Service

19 35