Pre- Feasibility RepoRt

Size: px
Start display at page:

Download "Pre- Feasibility RepoRt"

Transcription

1 Pre- Feasibility RepoRt AREA ACRE (24.0 HA) FOR KEN RIVER SAND/MORRUM MINING AT BLOCK NO-09 KHAND NO-03 GATA NO-337 VILLAGE- KANWARA TEHSIL-BANDA, DISTRICT- BANDA(U.P) SHRI RAVINDRA NATH SINGH JULY 2018

2 Table of Contents 1 Executive summary: INTRODUCTION OF THE PROJECT/ PROJECT BACKGROUND INTRODUCTION OF THE PROJECT Need of the project and its importance to the country and or region: Demand supply Gap: Export Possibility: Domestic / Export Markets: Employment Generation (Direct and indirect) Due to project: Project description: Type of project including interlinked and interdependent projects, if any: Location of Project: Details of alternate sites considered and the basis of selecting the proposed site, particularly the environment considerations gone into should be highlighted Size or Magnitude of operation Raw material required along with estimated quantity, likely source, marketing area, of final product/ s, mode of transport of raw material and finished product Availability of water, its sources Waste generation and disposal of waste Generation of waste water Site Analysis Planning Brief and Mining process Drilling & Blasting Green Belt Development Rehabilitation and resettlement (R & R) Plan Project Schedule and cost estimates Khasra Map & Road Map of the Mining area... 9 Road Map...

3 1 Executive summary: S. No Information Details 1. Project Name Area Acre (24.0ha) For Ken River Sand/Morrum Mining At Block No-09 Khand No- 03Gata No-337 Village- Kanwara Tehsil-Banda, District-Banda(U.P) 2. Project Proponent& Mailing Address 3. Location Village Tehsil District State 4. Toposheet No. 5. Coordinates Prakash Infraventure Pvt. Ltd. Sri Ravindra Nath Singh R/o- House No-6/159, Vineet Khand Gomti Nagar Lucknow U.P. Block No-09 Khand No-03Gata No-337 Kanwara Banda Banda Uttar Pradesh 54C/6 Area Acre (24.0ha) For Ken River Sand/Morrum Mining At Block No-09 Khand No- 03Gata No-337 Village-Kanwara Tehsil-Banda, District-Banda(U.P) Point Latitude Longitude A 25 31'28.11"N 80 16'56.66"E B 25 31'5.38"N 80 17'12.34"E C 25 30'58.91"N 80 17'3.67"E D 25 31'27.89"N 80 16'48.97"E 6. Name of the Mineral Mined Sand/Morrum 7. Capacity of Production Proposed Production 4,80,000 m3 / Annum or, 8,64,000TPA ( at Tonnage Factor of 1.8) 8. Drilling Blasting Not Applicable 9. Land utilization Pattern The area falls on River bed of Ken river.the land non agriculture land/waste land/ Govt Land. Mineral will be excavated from area by manual/semi Mechanized Mining method 10. Water requirements and source KLD through Tankers 1.28 KLD For drinking (for LPCD 12.0 KLD for Dust 2 lts/ SQM for 1000 mts road) 2.54 KLD Approx for Green Belt 634Trees) 11. Power Requirement Solar lights will be used for site office only 12. Man Power Requirement 128

4 13. Lease Period Five Years 14 Project Cost 1.61 Crore. (Approximate) 2 INTRODUCTION OF THE PROJECT/ PROJECT BACKGROUND 2.1 INTRODUCTION OF THE PROJECT Name & Location of project:area Acre (24.ha) For Ken River Sand/Morrum Mining At Block No-09 Khand No. 03 Gata No-337 Village- Kanwara, Tehsil-Banda, District- Banda (U.P) 2.2 Brief description of the nature of project The Project is mining of minor mineral in the form of Sand/Morrum Mining from Non agricultural/waste/govt. land. This is used as building material. 2.3 Need of the project and its importance to the country and or region: The mined out River Sand/morrum will be used as building material, roofing flooring, road making and there is huge demand in infrastructure industry & Township Projects. 2.4 Demand supply Gap: As river Sand/Morrum are used as Building material, the demand of mineral is increasing day by day. It is important to have the mining project to sustain the uninterrupted supply and also provide employment to people of nearby areas. 2.5 Export Possibility: Since the produced mineral will be sufficiently consumed in nearby area as well as other parts of India, so no need of export. 2.6 Domestic / Export Markets: Out of total production used in India. The domestic demand of the mineral is very high so no possibility of export in present time. 2.7 Employment Generation (Direct and indirect) Due to project: The project directly generates the employment for the local people and indirectly for the others. Also the marketing of the product generates the employment for peoples of nearby areas. 3 Project description: 3.1 Type of project including interlinked and interdependent projects, if any: The project involves mining of River Sand/Morrum and it is not interlinked project. 3.2 Location of Project: Location (map showing general location, specific location and project boundary layout) incorporated in the figure given below:-

5 Map showing general and specific location of the mining site 3.3 Details of alternate sites considered and the basis of selecting the proposed site, particularly the environment considerations gone into should be highlighted. No other site is considered for the proposed project. The land has been allocated by government for the mining only. Size or Magnitude of operation:

6 The size of the lease area is Total Area AREA Acre (24.0ha) For River Sand/Morrum Mining At Block No-09, Khand No. 03, Gata No-337, Village-Kanwara, Tehsil-Banda, District- Banda (U.P) Raw material required along with estimated quantity, likely source, marketing area, of final product/ s, mode of transport of raw material and finished product. It is project of river Sand/ Morrum mining so No raw material is required during the mining process. 3.4 Availability of water, its sources The total water requirement for the project will be met out through Tanker for drinking purposes and for dust suppression. 3.5 Waste generation and disposal of waste This project is for river Sand/ Morrum mining so there is very less generation of waste in from Sand/Morrum deposits, mobile toilets will be provided and very small amount of municipal waste will be generated; however collection bins will be provided for the same and will be dumped in a proper way Generation of waste water There is waste water generation during the process, waste water collected after hand and feet washing will be used for dust suppression. Site Analysis (i) (ii) (iii) (iv) Connectivity: The site is away fromnh-76, 3.90 km (SE).This project is located near KanwaraVillage.This site is easily accessible. Land form, land use and land ownership The lease area is located in river bed of Ken. The lease area is dominated by Sand/Morrum surface.this land is good for mining. After mining the open pits will be naturally replenished with Sand/Morrumin rainy season with flow of water. The land/ project site is on leasing, area comprises of Govt. waste land. there is no habitation occurs in the area. Topography Along With Maps: The highest and lowest elevations the lease area are 102.0mts AMSL and 100.0mtsAMSL

7 NO-09 KHAND NO.-03 GATA NO-337,VILLAGE-TEHSIL-BANDA, DISTRICT 5.0 Km Radius Map on Google 10km radius toposheet map

8 (iv). Existing land use pattern and distances from forests, CRZ, etc. The mining lease area is neither agricultural nor forest land and there is plenty of mineral available in this area. The distance from the forests roads is given below- Nearest National / State Highway- NH-76, 4.71 km (SE). Nearest Railway Station- Banda Junction Railway Station 6.10 Km in SE Nearest Airport Choudhary Charan Singh Airport Km NE National Park, Wild life Sanctuary Biosphere reserve with In 5 km- none Nearest forest None Nearest River, Water Body- Ken River Nearest National Park / Sanctuary None in 5 Km (v). Existing infrastructure (vi). Soil classification: In Banda district loose sediments as well as black cotton soil is found. Black cotton soil is prominent in the central part. Four major type of soil a) Rakar, b) Mar, c) Kabar and d) Padua are dominant in the district. (vii). Climate and Rainfall: The average annual rainfall is mm. The climate is typical subtropical penetrated by long and intense summers. About 80% of the annual rainfall is received from south-west monsoon. May is the hottest month with mercury shooting upto 47.00C. With the advance of monsoon by mid-june, temperature starts decreasing. January is usually the coldest month with temperature going up to 5.80C. The relative humidity is highest in August about 85% and lowest in April. Social infrastructure Available Existing: The project site is located in the Kanwaa Village. The primary school is present in village- Kanwara which is 1.85 km in NE direction from the project site. High schooling and above education, colleges are present in Banda.A dispensary is present in the village. Police Station: Police station is situated Bandain which is approximately 6.00 km from the village in SE Direction from the project site. Water Supply: The major source of water is ground water for the peoples. Ground water is used for drinking and other purposes. 4 Planning Briefand Mining process Local villagers will be employed for the exploitation and mining operation of the mineral. The project involves the mining of River Sand/Morrum Mining.

9 NO-09 KHAND NO.-03 GATA NO-337,VILLAGE-TEHSIL-BANDA, DISTRICT Mining will be done in manual manner. A minimum of 7.5m buffer will be kept. Maximum depth will be as per mining plan 4.1 Drilling & Blasting Drilling &Blasting not required for River Sand/Morrum Mining 5.2 Green Belt Development To prevent different impact of mining process a 7.5 m wide green belt will be provided within the mine lease area. Native trees will be planted on site to maximize the survival rate. Plantation will also be done on connecting road as per permission of Govt. 5 Rehabilitation and resettlement (R & R) Plan R & R plan is not applicable for this project as the mines in nearby areas are under operation for many years. The land is non-forest barren land. Local people will be employed for mining work. Economic and social status of the local people will be improved after mining work, because local people get employment. 7. Project Schedule and cost estimates The Environment Clearance is sought for Excavation in lease area. Once the EC is granted the Excavation of mineral will be done. All the mining process will be done during day time only, mining will be done from October to May month of the year. There will be no mining in rainy season. The project Cost will be approximately 1.61 Crore 8. Khasra Map & Road Map of the Mining area