Snapfinger Creek. Raymond J. Wilke, P.E. Engineer of Record
|
|
- Rodney Hampton
- 5 years ago
- Views:
Transcription
1 Snapfinger Creek Paul E. Simpson, P.E. GeoRay, Inc. Raymond J. Wilke, P.E. Engineer of Record
2 The Project Team City of Pine Lake Dekalb County GeoRay Willmer Engineering Register-Nelson GEFA Ga DNR USACOE
3 Upper Wetlands Runoff Pollutants scsts
4
5 Timeline 2005 Watershed studies ID Snapfinger Creek Issues 2007 City constructs first wetlands along creek 2008 Obtains 319h grant to improve upstream wetlands, provides pre-treatment of flows to Lake 2009 GeoRay engaged to design project 2010 construction of 0.8 ac lower (west) wetlands in floodplain (Phase 1), treats runoff, Lake discharges 2010 Balance of project to bid 2010 Application to GEFA for ARRA funding 2011 GEFA loan for $1,500,000 approved 2012 Project completed
6 About the Project at Pine Lake Goal: Protect and Improve water quality, habitat, biology Methods: infiltration trench, bioretention of run-on, natural channel design, streambank stabilization, lake sediments removal, & constructed wetlands
7 About Snapfinger Creek Watershed Improvement Plan ID s TMDL s Fecal Coliform, Bio M County STEP Laterals/Creek crossings Parallel Trunk Sewer Lines
8 Water Quality Data
9 Table 6-2. Summary of TMDL Allocation for DeKalb County Fecal Coliform-Listed Streams Stream Segment Current Load (counts/ 30 days) WLA (counts/ 30 days) WLAsw (counts/ 30 days) LA (counts/ 30 days) MOS (counts/ 30 days) TMDL (counts/ 30 days) Percent Required Reduction Arrow Creek Ball Mill Creek Bubbling Creek 6.87E E E E E Burnt Fork Creek Lullwater Creek Nancy Creek North Fork Peachtree Creek 2.49E E E E E E E E E E E E E E E Peavine Creek 3.45E E E E E South Fork Peachtree Creek Camp Creek Cobbs Creek Conley Creek Doolittle Creek Honey Creek Intrenchment Creek Shoal Creek Snapfinger Creek South River, Atlanta to Flakes Mill Rd 2.70E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E South River, Flakes Mill Rd to Pole Bridge Creek 6.89E E E E E E E E E E Sugar Creek Swift Creek Yellow River Doless 2.45E E E E E Creek Little Stone Mountain Creek 3.52E E E E E E E E E E Stone Mountain Creek 7.16E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E E
10 Funding GEFA Loan Recipient: City of Pine Lake Item Total CWSRF Loan Construction $ 1,300,000 $ 1,300,000 Contingency $ 125,000 $ 125,000 Engineering & Inspection $ 150,000 $ 150,000 Administrative/Legal $ 50,000 $ 50,000 TOTAL $ 1,625,000 $ 1,625,000 City will be charged a 2% closing fee of $32,500
11 Costs Original Construction Bid $689,991 Owner Requested Changes/Adds $302,947 Field Engineering, Const Administration $129,735 Landscaping, Trail & Park Amenities $157,281 Total $ 1,279,954
12
13 TMDL s Fecal Coliform Water Quality
14 Funding Sources City Dekalb GEFA
15
16 Schematic Design
17
18 Berm Lake Considerations Streambank
19 Geotech Borings
20 Berm Considerations Large Trees Aesthetics, Pedestrian Trail Fishing access Unknown/questionable fill (1920 s construction) Plugged outlet works No emergency spillway
21
22 Streambank Considerations Scallops Benching Parallel trunk sewer Sewer easement Strip of City-owned land adjacent to creek
23 Flood Map
24 Lake Considerations 12.1 Acres Dredging of 13,500 cy accumulated sediments Improve habitat Trees on dam providing a lot of shade fish friendly Slope of beach and swimming area depth Ability to isolate swimming area New outlet works Ability to discharge to wetlands or creek Able to feed wetlands during dry periods
25 Geotechnical Redundant Flows Multiple Treatment Options BioRetention Dredging Permitting
26
27 Infiltration Trench Section at Bioretention
28
29 Paul E. Simpson, P.E. Brain J. Rainwater, P.E.
30 What did it take to get to here?
31 Existing Conditions
32 Scour & Washout
33 Bank Scour
34 Beaver Damage
35 Downstream Conditions
36 Full Pool
37 Draining the Lake
38 Inside the Swimming Area
39 Almost There
40 More Draining
41 Wildlife
42 Grass Carp + Low Water = Turtle Dinner
43 Canadian Geese
44 Other Wildlife
45 Surveying for Base Topography in Dry(ish) Lake Bottom
46 Almost As Dry As It Got
47 French Drain Pit with Well Point Style Pump System
48 Clearing the Berm
49 Continuous Geotechnical Presence
50 Continuous Interface with Client
51 Initial Clearing & Sediment Removal from East Side
52 Cross Vein Installation
53 Completed Cross Vein
54 Bank Stabilization at Cross Vein
55 Continuous Compaction & Testing
56 The Muddy Phase
57 Creekside Bank Stabilization
58 Reuse of Cut Logs for Fish Habitat
59 Stabilized Channel
60 Dressed Walkway & Slopes
61 Hydroseeding Slopes
62 Hydroseed Eating Contest
63 New Natural Channel Developing
64 Existing Original Weir Controls
65 Completed New Inlet Control
66 Completed Walkway
67 Completed Bioretention Feature
68 Phil Howland, City Manager & Director of Public Works Greg Zarus, Mayor, fmr JoAnn Macrina, P.E., Dekalb County Watershed Mgmt, fmr. Jason Bodwell,GEFA Tom Roos, GaDNR