WATER AND SANITATION SERVICES IMPROVEMENT PROJECT ADDITIONAL FINANCING (WaSSIP AF) PROCUREMENT PLAN

Size: px
Start display at page:

Download "WATER AND SANITATION SERVICES IMPROVEMENT PROJECT ADDITIONAL FINANCING (WaSSIP AF) PROCUREMENT PLAN"

Transcription

1 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized WATER AND SANITATION SERVICES IMPROVEMENT PROJECT ADDITIONAL FINANCING (WaSSIP AF) I. General PROCUREMENT PLAN The following procurement plan has been developed for project implementation during the period July 01 to December 0 and provides the basis for the procurement methods and prior/post review thresholds. The plan will be updated when need arises to reflect the actual project implementation needs. It covers the three categories, namely, Works; Consultancies; and Goods. 1. Project information: a. Country: KENYA b. Borrower: Government of Kenya c. Project Name: Water and Sanitation Service Improvement Project Additional d. Loan/Credit No., IDA103-KE e. Project Implementing Agencies: Financing (AF) i. Athi Water Services Board (AWSB) ii. Coast Water Services Board (CWSB) iii. Lake Victoria North Water Services Board (LVNWSB). s approval Date of the procurement Plan: February 9, 01 (during negotiations) 3. Date of General Notice: March 6, Period covered by this procurement plan: July 01 to December 0 II Thresholds for s and Prior Review 40 Goods, Works, Non Consulting Services, Consulting Services The Table below summarizes the Prior Review Threshold for which Decisions are subject to Prior the are as stated in Appendix 1 to the Guidelines for.

2 Prior Review Threshold in US Dollars Comments 1. ICB and LIB (Goods) 00,000 ICB (Works),000,000 3 QCBS / CQS (Consultancy Services) 00,000 4 ICS (Consultancy Services) 0,000 SS (Consultancy Services) All In addition, all Terms of Reference will be subject to prior review. III Packages with s and Time Schedule (Summary) ATHI WATER SERVICES BOARD (AWSB) (A) WORKS No Works Description Status d in Date Bulk Water Supply to Nairobi : Construction of Northern Collector Phase 1 (River abstraction/intake structures and 1km tunnels) Construction of Raw Water and Treated water (Thika- Ngorongo TW-Kabete) water transfer Phase 1 Development of 4deep (600m) and 4 shallower (0m) Exploratory/pilot Wells at Ruiru and Kiunyu Development of Energy Generation Innovations at Dandora Wastewater Treatment Plant Construction of Independent Community Water Supply along the Northern Collector Tunnel Phase 1 to Thika Dam,00,000 ICB Prior 1-Oct- 6,600,000 ICB Prior 10-May- 3,000,000 NCB Post 19-Sep-,00,000 ICB Prior -Oct- 4,100,000 NCB Post -May-

3 No Works Description Status d in Date Improvement of Water and Sanitation in the informal settlements in Nairobi Hydropower generation scheme at Chania Outfall Construction of Kiambu Water Supply (intake weirs, pipelines, treatment works, storage, transmission pipelines Runda water reservoir) Construction of Community water supply downstream of Thika Dam Construction of the Water Reticulation Sytem for Ruiru and Juja towns Water treatment works for Theta Dam Development of Kikuyu springs water source for Kikuyu town Renovation and Construction of Water Appeal Board s offices/courts (Narok, Kisumu, Eldoret, Kitui, Kakamega) Drilling and Equipping of 14 Boreholes and Civil Works in Athi WSB Area Drilling and Equipping of Boreholes and Civil Works in Tana WSB Area Drilling and Equipping of 0 Boreholes and Civil Works in Tanathi WSB Area Rehabilitation and expansion of Wote in Tanathi WSB area Rehabilitation and expansion of Mwala Water 4,400,000 NCB Post 10-Oct-1 3,000,000 NCB Post 14-Dec-,100,000 ICB Prior 11-Jan-14 3,400,000 NCB Post 0-Dec-1 1,00,000 NCB Post -Jun-,900,000 NCB Post 1-Sep- 00,000 NCB Post 0-Jul- 30,000 NCB Post 11-Sep-,60,000 NCB Post 16-Jul- 90,000 NCB Post 1-Jul- 3,0,000 NCB Post 1-Jul- 1,140,000 NCB Post 4-Jul- 0,000 NCB Post 4-Jul-

4 No Works Description Status d in Date Supply in Tanathi WSB Area Rehabilitation of Amboseli Pastrolist Water Supply in Kajiado in County Tanathi WSB Area Construction of Mwea- Makima Water Supply in Tana WSB area Installation of water tanks, construction of tank-base and guttering for rainwater harvesting in AWSB area Installation of water tanks, construction of tank-base and guttering for rainwater harvesting in Tanathi WSB area Installation of water tanks, construction of tank-base and guttering for rainwater harvesting in Tana WSB area 0,000 NCB Post -Aug- 0,000 NCB Post 1-Jul- 00,000 NCB Post 4-Nov-1 00,000 NCB Post 4-Nov-1 0,000 Shopping Post 4-Dec-1 (B) GOODS No Goods Description Status d in Procurem ent (Prior/Post ) Submissio n of bids opening 1 3 Water Metering Programme for WSPs (in Lots) Lot 1: Ordinary and Bulk Meters, Lot : Automatic Remote Read Meters and Pressure Data Loggers, and Lot 3: Leak detection equipment and Repair Tool Kits for WSPs Supply of 1,10 Plastic Tanks in 3 Lots. (Capacity 10,000litres) Supply of water pipes and fittings for WSPs 1,900,000 ICB Prior 3-Oct-1 11-Apr- 1,60,000 ICB Prior 1-Jul-1 -Jan- ICB Prior 1,000,000 ICB Prior -Oct-1 30-Apr-

5 No Goods Description Status d in Procurem ent (Prior/Post ) Submissio n of bids opening 4 Project Communication materials - Lot 1: T-Shirts 1000, Umbrellas 1000, caps 1000, carrier bags 1000, Lot : Annual Report 00, Bomba Newsletter,000, and Best practices Handbook , Lot 3 Brochures 6000, pens 000, paper folders 6000, Fliers 10000, Lot 4: Banners 30, Billboards, Lot : media campaigns 1, documentaries 3, Lot 6: Diaries 1000, Calendars 000 and seasons cards 1000 Supply and Installation of ICT Equipment and Software for AWSB, WSPs, WASREB and WAB 300,000 NCB Post 1-Oct-1 19-Mar- 40,000 NCB Post 0-Sep-1 -Mar Supply of Lot1: Nine (9) Lorries, Lot : Five () Water tankers, and Lot 3: Single Double Cab Pick ups; Lot 4: Twelve (1) operational vehicles; and Lot : Twelve 1 Motor Cycles Provision of 1 mobile treatments units Supply of 10 collapsible (potable) water tanks:,000 to 10,000 litres of Stand-by generating sets: various ratings of Stand-by submersible pumps 1,930,000 ICB Prior -Aug-1 -Mar- 00,000 ICB Prior 1-Sep-1 30-Mar-,000 NCB Post 9-Aug-1 14-Feb- 3,000 NCB Post 14-Sep-1 -Mar- 1,000 NCB Post 14-Sep-1 -Mar- (C) CONSULTANCY SERVICES No Consultancy Description Status Selection RFP 1 Design, supervision and coordination of Works of Northern Collector Tunnel Phase 1 (River intake structures and tunnels) 6,610,000 QCBS Prior 4-Oct-1 10-Jan- Design Review and Supervision of Construction of Independent 300,000 QCBS Prior 9-Nov-1 -Mar-

6 No Consultancy Description Status 3 Community Water Supply along the Northern Collector Tunnel Phase 1 to Thika Dam Environmental Impact Assessment (EIA) and Resettlement Action Plan (RAP) for Raw Water and Treated Water Pipelines (Thika Dam - Ngorongo-Kabete) and EIA for Northern Collector Tunnel Phase 1 Selection RFP 0,000 QCBS Prior 14-Sep-1 1-Dec- 1 4 Design Review, Supervision and Coordination of Northern Collector System Raw Water and Treated Water Pipelines (Thika Dam - Ngorongo- Kabete) Project Monitoring Evaluation and Preparation of Project Completion Report,000,000 QCBS Prior 6-Oct-1 1-Feb- 300,000 QCBS Prior -Dec-1 16-Mar- 6 Review of Designs and Supervision of the Development of Exploratory/pillot Wells 00,000 QCBS Prior 19-Dec-1 -Mar Environmental Impact Assessment (EIA) and Resettlement Action Plan (RAP) for development of exploratory/pilot wells Energy Audits for Water Service Providers in AWSB Area Customer Identification Survey and Infrastructure Mapping for Water Service Providers Environmental Impact Assessment for Development of Energy Generation at Dandora Wastewater Treatment Plant Supervision of Works for Development of Energy Generation at Dandora Wastewater Treatment Plants Feasibility study and preparation of a strategy for Setting-up Sewer Connections Revolving Fund for Nairobi 100,000 CQS Post -Sep-1 -Jan- 10,000 CQS Post 30-Jul-1 19-Jan- 0,000 QCBS Prior 10-Nov-1 10,000 QCBS Post -Jan- 0,000 QCBS Prior 1-Jan- 16-Feb- 16-Mar- 3-Mar- 10,000 CQS Post 4-Sep-1 4-Feb-

7 No Consultancy Description Status Selection RFP Implementation of Resettlement Action Plan (RAP) and Environment and Social Management Frameworks (ESMF) including Legal services for Establishing and Registering water and sewer Wayleaves 10,000 QCBS Post -Oct-1 -Jan- 1 Integration of Nairobi City Water Sewerage Company s Customer Management System to Geographical Information Systems (GIS). 10,000 QCBS Post 31-Jan- 11-Apr Updating of Nairobi City Water Sewerage Company s GIS Maps, Water Network Model and Training of Staff Updating the Nairobi City Sewerage Masterplan and Preparation of Masterplan for Selected Satellite towns 10,000 QCBS Post 3-Mar- 1-May- 4,000 QCBS Prior 30-Oct-1 -Feb- 0 Design and Supervision of the Construction of Hydropower Power Generation Station at Chania Outfall/Thika Dam 390,000 QCBS Prior 1-Mar- 1-Jun- 1 Environmental Impact Assessment for Hydropower generation station at Chania outfall/thika Dam 10,000 QCBS Post 1-Feb- 6-May Review of Design and supervision of Kiambu Water Supply System Supervision of Independent Community water supply downstream of Thika Dam (Intakes on Kimakia and Kiama Rivers for Gatanga WSP and treatment plant at Gatura Mkt) Supervision of Water Reticulation Sytem for Ruiru and Juja towns Design of Automatic Meter Reading and Prepaid Services system by MPesa in Nairobi Design and supervision of water treatment works for Theta Dam Review of Design and Supervision of Kikuyu springs water source for 400,000 QCBS Prior 31-Dec-1 -Apr- 0,000 QCBS Prior 30-Nov-1 -Mar- 160,000 QCBS Post 31-Oct-1 6-Feb- 0,000 ICS/CQS Post -Mar- -Jun- 40,000 QCBS Prior 31-Dec-1 -Apr- 10,000 QCBS Post 1-Dec-1 6-Mar-

8 No Consultancy Description Status Selection RFP Kikuyu town Review of the Environmental Impact Assessment and Preparation of Resettlement Action Plan for Ruiru sewerage works 160,000 QCBS Post -Jul-1 -Oct- 1 9 Updating Ruiru Sewerage Design, detailed design for Juja and Thika Municipality and Supervision of Ruiru Sewerage Works 610,000 QCBS Prior 1-Aug-1 3-Nov Carry out strategic drought Mitigation studies/plan for Athi Water Services Board, Tana and Tanathi Water Service Board areas Design review of Wote water supply, Design of Amboseli Pastoralist and Mwala water Supply and Supervision of works in Tanathi WSB Area Environmental Impact Assessment for Wote, Amboseli Pastoralist and Mwala water supply works Design review and supervision of Mwea-Makima Water Supply works in Tana Water Services Board area Environmental Impact Assessment for Mwea-Makima water supply work Hydrogeological studies, design, document preparation and supervision of construction of Boreholes and elevated water tanks in Athi Water Services Board area 600,000 QCBS Prior -Oct-1 14-Jan- 0,000 QCBS Prior -Nov-1 -Feb- 100,000 CQS Post -Aug-1 0-Jan- 10,000 QCBS Post 1-Oct-1 6-Jan- 0,000 ICS/CQS Post 30-Aug-1 3-Jan- 10,000 QCBS Post 1-Nov-1 0-Feb- 36 Hydrogeological studies, design, document preparation and supervision of construction of boreholes and elevated steel water tanks in Tanathi Water Services Board area 10,000 QCBS Post -Nov-1 1-Feb- 3 Hydrogeological studies, design, document preparation and supervision of construction of boreholes and elevated steel water tanks in Tana Water Services Board area 10,000 CQS Post 9-Sep-1 -Feb-

9 COAST WATER SERVICES BOARD (CWSB) (A) WORKS Contract sum 1 Augmentation of Baricho Water Production Works,000,000 ICB Prior 6-Apr Construction of Mombasa - Sabaki Pipeline Construction of Malindi - Kilifi Interconnection Pipeline Swabbing of the Sabaki - Mombasa and Sabaki - Malindi Transmission mains Rehabilitation of the Bulk Water Pipeline System for Sabaki, Mzima, Tiwi, and Marere Construction of the Sabaki - Gogoni Water Supply in Malindi (WaSSIP Component) 0,,000 9,00,000 1,00,000 4,600,000,000,000 ICB Prior 6-Apr-14 ICB Prior 0-Nov- NCB Post 3-Jul- NCB Post 1-Sep-1 NCB Post 9-May- Construction of extended works to informal settlements in Mombasa 31,900 NCB Post 1-Nov-1 9 Construction of office block for CWSB Construction of office blocks for Tavevo and Lamu WSPs 0, ,000 NCB Post 3-Sep-1 NCB Post -Sep-1 10 Rehabilitation of Kizingo WWTP 4,40,000 NCB Prior -Dec- 11 Rehabilitation of Mazeras- Changamwe Pipeline 1,00,000 NCB Post 1-Dec- 1 Construction of Mazeras- Nguu Tatu Interconnection 3,00,000 NCB Post 9-Oct-1 Construction of MOWASCO GIS Office 0,000 NCB Post 1-Dec-1

10 Contract sum 14 1 Construction of Water Supplies in Drought Areas Lot 1: Equipping of Existing Boreholes Lot : Development Equipping of New Boreholes Lot 3: Construction of Elevated Tanks at Existing Borehole Locations Construction of underground rain water harvesting tanks (Djabias), 10m3 with cemented collection apron,40,000 10,000 ICB Prior 6-Oct-1 NCB Post 1-Sep-1 16 Construction of surface water tanks (pressed steel tanks), 1000m3 capacity,00,000 NCB Post -Oct-1 1 Construction of small earth dams (pans) 0,000 NCB Post -Sep-1 1 Extension/Construction of Water Supply pipelines 1,00,000 NCB Post 6-Sep-1 19 Installation of Plastics Tanks gutters and Fittings at Various Sites 00,000 NCB Post 6-Sep-1 0 Construction of extended works to informal settlements in Malindi 3,900 NCB Post -Nov-1 (B) GOODS Contract Review Submission of bids opening 1 Supply of Bulk water equipments and tools Supply of 30,000 ordinary consumer and bulk water meters for WSPs 30,000 NCB Post 6-Oct-1 1,400,000 ICB Prior -Sep-1 Supply of 30 motorcycles for 3 meter reading and general 40,000 NCB Post 11-Oct-1 operations of the WSPs 4 Supply of No Jet Vacuum 300,000 NCB Post -Oct-1

11 trucks and sewer cleaning equipments for Mowasco Supply of 4No. Sets of Leak detection equipments and associated hand tools Supply of 0No 000ltrs plastic (with gutters, downpipes, fittings and concrete base) and or collapsible water tanks for schools in arid areas Supply and Installation of Billing Systems for 6WSPs (Malindi, Kilifi, Kwale, Tavevo, Lamu and Tana River) Supply and Installation of GIS Systems for 6WSPs (Malindi, Kilifi, Kwale, Tavevo, Lamu and Tana River) Office Equipment for CWSB, Bulk Company and WSPs Supply of 100 No. collapsible water tanks (capacity or 10m3) including hosepipes and petrol pump-sets drought prone areas of Coast and Northern WSB Supply of 00No. 10m3 plastic water tanks to public schools and institutions in drought prone areas for rain water harvesting including gutters, downpipes, fittings and concrete base Supply of 1No. utility minilorries for carrying pipes, collapsible tanks,no Water Bowsers and 6No. 4WD Drought monitoring vehicles Hardtops to all counties within Coast and Northern WSBs Supply of No. mobile water treatment units for both silty river water and saline water from boreholes (to be pulled by pickup) to all counties within Coast and Northern WSBs Supply of No.water trucking boats (with engine power) for Lamu and Wasini Islands Contract Review Submission of bids opening 300,000 NCB Post -Oct-1 400,000 NCB Post 1-Oct-1 600,000 ICB Prior -Nov-1 0,000 NCB Post 6-Nov-1 400,000 NCB Post 6-Dec-1 30,000 NCB Post 6-Sep-1 1,34,00 ICB Prior 6-Oct-1 1,00,000 ICB Prior 10-Sep-1,00 ICB Prior 1-Oct-1 ICB Prior 10,000 NCB Post 1-Sep-1 of 0 No. standby generating sets: various 0,000 NCB Post -Dec-1

12 16 1 schemes within Coast and Northern WSBs Supply of standby submersible pumps Supply Delivery of Backhoe Excavator and Low Loader trailer/mover Contract Review Submission of bids opening 0,000 Shopping Post -Dec-1 600,000 ICB Post -Dec-1 (C) CONSULTANCY SERVICES Contract sum Design and Supervisi on Procureme nt method Review Submission of proposals by consultants Review and updating of water resources studies, conceptual and detailed design, tender documents and construction supervision for expansion of baricho water production wellfields and sabaki-nguu tatu transmission main Detailed designs and works supervision of the Malindi - Kilifi interconnection pipeline Detailed designs and works supervision of swabbing of Sabaki-Malindi and Sabaki- Mombasa pipelines Supervision of repair of leaks and installation of bulk meters and valves for the bulk water system,3,000 QCBS Prior -Oct-1 QCBS Prior 60,000 QCBS Prior -Dec-1 360,000 QCBS Prior 1-Dec-1 40,000 QCBS Prior -Nov-1 6 Energy audits in water utilities (WSPs) Customer identification survey and infrastructure mapping for all WSPs 110,000 CQS Post 16-Sept-1 10,000 QCBS Post 4-Nov-1 QCBS Post Metering (Installation, reading and Maintenance) programme 360,000 QCBS Prior -Dec-1

13 for 6WSPs (Kilifi, Malindi, Lamu, Tavevo, Kwale and Tana River) Billing and revenue collection and integration of customer management system to GIS Study on incentive based performance for Mowasco and 6WSPs Staff Development of Waste water master plan for Mombasa and other selected towns Detailed design of the preferred option of the water supply master plan in Mombasa and Coast Region Identification and mapping of catchment areas of Mzima, Tiwi, Marere and Baricho Systems Contract sum Design and Supervisi on Procureme nt method Review Submission of proposals by consultants 00,000 QCBS Prior 3-Dec-1,000 CQS Post 6-Sep-1 60,000 QCBS Prior 11-Dec-1 900,000 QCBS Prior 1-Jan- 40,000 QCBS Prior -Feb Preparation/Review of strategic plans for CWSB and WSPs Establishment and registration of wayleaves for water facilities and assistance in the implementation of Resettlement Action Plan (RAP) for various works Reduction of NRW and Network modeling in WSPs Design and Supervision of the rehabilitation of Mazeras- Changamwe pipeline 90,000 CQS Post 9-Aug-1 CQS Post 100,000 CQS Post 11-Sept-1 0,000 QCBS Prior 6-Jan- 0,000 QCBS Prior 16-Dec-1 1 Review of designs, tender documentation and works supervision for Sabaki-Gogoni Water Supply System 40,000 QCBS Prior 16-Dec-1 Detailed Designs, Tender 1 Documentation and 90,000 QCBS Prior 1-Nov-1 Supervision of Mazeras-Nguu Tatu Interconnection 19 Design Review and Supervision QCBS Prior 1-Nov-1

14 Contract sum Design and Supervisi on of Kipevu WWTP 360,000 0 Technical Support of CWSB on technical services Procureme nt method Review Submission of proposals by consultants 1,30,000 QCBS Prior 1-Jan- 1 3 Drought Mitigation Study (Plan) for CWSB region Ground Water Study for the Merti Acquifer in Wajir Supervision of Drought Response civll works 300,000 QCBS Prior 19-Oct-1 QCBS Prior 600,000 QCBS Prior 4-Dec-1 0,000 QCBS Prior 16-Dec-1 LAKE VICTORIA NORTH WATER SERVICES BOARD (LVNWSB) A. WORKS No Project Description Status d 1 Construction of Elligirini Pipeline and Upstream and downstream Treatment works extension. Construction of Kipkarren Treatment works and Distribution. 1,3,000 NCB Post 9-Oct-1 1,0,000 NCB Post 1-Nov Construction of Expanded Kapsoya Treatment Works Construction of Power Generation Works at Waste Water Treat Plant Eldoret Construction of Eldoret Water Distribution Lines under Contract B Construction of Water and Sanitation facilities for Informal Settlements in Mumias Construction of Water and Sanitation facilities for Informal Settlements in Eldoret Construction of Upstream Water Treatment Works and DistrIibution Lines, (Additional investment in Kapcherop/Kapsowar) 3,00,000 NCB Post 6-Nov-1,000,000 NCB Post 1-Jan-,0,000 ICB Prior 6-Nov-1 00,000 NCB Post 10-Dec-1,000,000 NCB Post -Nov-1 3,000 NCB Post 1-Jan- 9 Construction of Kimilili Water 300,000 NCB Post -Jan-

15 No Project Description Status d Distribution System Drilling and equiping of Drought Boreholes and Civil Works LVNWSB, RVWSB LVSWSB Rehabilitation/Expansion of Water Supplies for LVNWSB - Kwanza Water Supply,90,000 ICB Prior 4-Feb-,60,000 NCB Post 9-May-1 NCB Post 1-Jun-1 B. GOODS d Water Metering Programme for WSPs (in Lots) Lot 1: 40,000 Ordinary Meters and Lot :,000 Automatic Remote Read Meters Supply and Installation for LVNWSB and WSPs (a) office equipment (b) Integrated Information system/ electronic information system (c) Specialized Software of communication materials and equipment of Intranet system for the Board, Voice over internet protocol VoIP software Procure/Upgrade billing/accounting software for WSPs of 1m3 Water Bowsers and 10 tonnes Lorry Purchase of Operational Vehicles 00,000 ICB Prior 9-Nov-1 40,000 NCB Post -Nov-1 0,000 NCB Post -Oct-1,000 Shopping Post -Sep-1 0,000 NCB Post 6-Sep-1 4,30,000 ICB Prior 16-Nov-1 0,000 ICB Prior -Nov-1 Purchase of Plastic Tanks (400 No) 600,000 ICB Prior -Jul-1 ICB Prior C. CONSULTANCY SERVICES No Project Description Status Selection RFP 1 Supervision/EIA of Drought,63 CQS Post 6-Oct-1

16 No Project Description Status Selection RFP Boreholes Supervision of Eldoret Contract B- Distribution Lines 43,00 QCBS Prior 19-Feb- Design and Supervision Informal Settlements in Eldoret 10,000 QCBS Post -Dec-1 4 Ditto Informal Settlements in Mumias 10,000 QCBS Post -Dec-1 Design of Energy Generation from WWTP in Eldoret 0,000 QCBS Prior -Mar- 6 Design and Supervision of Kapsoya T Works and Supervision of Elligirine Pipeline 1,0 QCBS Prior -Feb- Customer/Employee Satisfaction Survey 0,000 CQS Post 6-Dec-1 Kipkarren Dam Inspection,FS and Final Design for Kipkarren Dam T Works and Associated Distribution lines 30,000 QCBS Prior -Feb Design and Tender Documemtation Kapsowar/Kacherop IP water projects to be identified Consultancy services for communication 30,000 QCBS Prior 1-Mar- 100,000 CQS Post 1-Jan- 11 Intergration of customer management systems to GIS and updating of GIS maps and network model for Eldoret, Kitale, Webuye, Bungoma, Kakamega and Busia 360,000 QCBS Prior -Apr- 1 Project Management Consultant - Monitoring and Evaluation of Project Indicators Carrying out of SPA Audits 14 Carry out Staffing Needs Assessment for the Board (Human Resources Department) 90,000 ICS Post 1-Jan- 90,000 ICS Post 3-Jan- 90,000 ICS Post 1-Jan- 1 Preparation of Risk Management Assessment 90,000 ICS Post -Nov-1 16 Carry out strategic drought mitigation studies/plan 900, QCBS Prior -Oct-1 QCBS Prior 1 Supervision and preparation of EIA 40,000 QCBS Prior 1-Mar-

17 No Project Description Status Selection RFP Reports for Drought Boreholes