SEMI-AEROBIC WASTE LANDFILL APPLICATION IN THE PACIFIC REGION
|
|
- Audrey Chandler
- 5 years ago
- Views:
Transcription
1 SEMI-AEROBIC WASTE LANDFILL APPLICATION IN THE PACIFIC REGION SAMOA, VANUATU, FIJI, SOLOMON, PAPUA NEW GUINEA, TONGA, PALAU AND FEDERAL STATES OF MICRONESIA (YAP, KOSRAE, CHUUK AND POHNPEI) 1
2 Japanese Techrnical Cooperation Project for Promotion of Regional Initiati JAJapan Regional Technical Cooperation Project on the Promotion of Regional Initiatives on Solid Waste Management (J-PRISM) Solid Waste Management in Pacific Island Countries Faafetai Sagapolutele Assistant Chief Adviser 2
3 NAMARA DUMPSITE, LABASA, FIJI NOV
4 PROJECT COST - About FJ$250,000+ (AusAid) (i). New Office and E-waste Storage Building (ii).construction of Waste Disposal Cells (3) (iii).construction of Access Road within the Site (iv). Improvement of the Access Road Other Costs (i). Labasa Town Council - Water & Power Supply, Fence & Landscaping by Labasa Town Council (ii). JICA - Technical Assistance (Project Drawings and Designing &, Supervision of Construction Works) 4
5 SITE`S BACKGROUND INFORMATION Located on a Mangrove Area About 2ha (20,000m2) Has been used as a Dumping area for 30+ years About 1.5m above sea-level Within the flooding zone PILOTED CLIMATE CHANGE ADAPTATION MEASURES FOR LOWLAND WASTE DUMPSITES 5
6 WASTEWATER SEEN ALL OVER THE AREA ESPECIALLY DURING RAINY SEASON 6
7 NO CONTROL ON THE INCOMING WASTE ON GOING POLLUTION OF THE MANGROVE ENVIRONMENT BREEDING SITE FOR FLIES PILOTED CLIMATE CHANGE ADAPTATION MEASURES FOR LOWLAND WASTE DUMPSITES 7
8 VERY POOR ACCESS TO THE SITE RESULTING TO INCOMING WASTE BEING DISPOSED WHEREVER CARS CAN REACH 8
9 KEY STRATEGIC MEASURES FOR IMPROVEMENT WORKS 1. Protection of the site from flooding 2. All weather-condition access roads 3. Control on the Incoming Waste 4. Control on the generated leachate. 5. Control on the generated methane gas 9
10 PLANNING OF IMPROVEMENT WORKS TO INCORPORATE STRATEGIC MEASURES FOR IMPROVEMENT OF THE SITE USING THE FUKUOKA METHOD PILOTED CLIMATE CHANGE ADAPTATION MEASURES FOR LOWLAND WASTE DUMPSITES 10
11 FINAL LAYOUT OF PROPOSED IMPROVEMENTS AFTER SEVERAL CONCEPTUAL PLANS DISCUSSION PILOTED CLIMATE CHANGE ADAPTATION MEASURES FOR LOWLAND WASTE DUMPSITES 11
12 6. CONSTRUCTION WORKS BEING CARRIED OUT RAISING THE BASE + CONSTRUCTED SURROUNDING EMBANKMENTS TO ISOLATE THE SITE FROM THE NEARBY MANGROVE ENVIRONMENT PILOTED CLIMATE CHANGE ADAPTATION MEASURES FOR LOWLAND WASTE DUMPSITES 12
13 PLACING THE ACCESS ROAD ON TOP OF THE SIDE EMBANKMENTS TO AVOID FLOODING AND WATERLOGGED CONDITIONS PILOTED CLIMATE CHANGE ADAPTATION MEASURES FOR LOWLAND WASTE DUMPSITES 13
14 CONSTRUCTION OF 3 WASTE CELLS FOR THE DISPOSAL OF WASTE PILOTED CLIMATE CHANGE ADAPTATION MEASURES FOR LOWLAND WASTE DUMPSITES 14
15 CONSTRUCTION OF FACILITIES FOR COLLECTION OF THE GENERATED LEACHATE OR WASTEWATER PILOTED CLIMATE CHANGE ADAPTATION MEASURES FOR LOWLAND WASTE DUMPSITES 15
16 PILOTED CLIMATE CHANGE ADAPTATION MEASURES FOR LOWLAND WASTE DUMPSITES 16
17 PILOTED CLIMATE CHANGE ADAPTATION MEASURES FOR LOWLAND WASTE DUMPSITES 17
18 Oxygen 18
19 PILOTED CLIMATE CHANGE ADAPTATION MEASURES FOR LOWLAND WASTE DUMPSITES 19
20 PILOTED CLIMATE CHANGE ADAPTATION MEASURES FOR LOWLAND WASTE DUMPSITES 20
21 21
22 THE NEW FACE OF NAMARA WASTE DISPOSAL FACILITY FROM AN OPEN DUMPSITE TO A SEMIAEROBIC WASTE LANDFILL STRUCTURE 22
23 SIMILAR WORKS HAVE BEEN IMPLEMENTED IN OTHER PACIFIC ISLANDS SAMOA (2003) - PALAU - VANUATU - POHNPEI (FSM) - KOSRAE (FSM) - VAVAU ISLAND (TONGA) - SIGATOKA & LAUTOKA (FIJI) - PORT MORESBY (PNG) - HONIARA (SOLOMON ISLAND) 23
24 KALAKA DUMPSITE ON VAVAU ISLAND, TONGA IN 2013 PILOTED CLIMATE CHANGE ADAPTATION MEASURES FOR LOWLAND WASTE DUMPSITES 24
25 PILOTED CLIMATE CHANGE ADAPTATION MEASURES FOR LOWLAND WASTE DUMPSITES 25
26 PILOTED CLIMATE CHANGE ADAPTATION MEASURES FOR LOWLAND WASTE DUMPSITES 26
27 PILOTED CLIMATE CHANGE ADAPTATION MEASURES FOR LOWLAND WASTE DUMPSITES 27
28 PILOTED CLIMATE CHANGE ADAPTATION MEASURES FOR LOWLAND WASTE DUMPSITES 28
29 PILOTED CLIMATE CHANGE ADAPTATION MEASURES FOR LOWLAND WASTE DUMPSITES 29
30 30
31 POHNPEI IMPROVEMENT WORKS IN 2013 PILOTED CLIMATE CHANGE ADAPTATION MEASURES FOR LOWLAND WASTE DUMPSITES 31
32 PILOTED CLIMATE CHANGE ADAPTATION MEASURES FOR LOWLAND WASTE DUMPSITES 32
33 PILOTED CLIMATE CHANGE ADAPTATION MEASURES FOR LOWLAND WASTE DUMPSITES 33
34 THANK YOU 34