1 Environmental Management Plan For Mining of Laterite Over an extent of 12.5 Ha at Sy No. 176/P of Siddulur Payaga (V) & Sy.no. 90 of Siddulur Munagal (V), Vikarabad (M), Rangareddy (D), T.S. Proponent M/s G. Bal Reddy Prepared by M/s G. Bal Reddy

2

3 Table of Contents 1 Introduction Details of Project Reserves Estimation and Life of Mine Method for estimation of reserves Total Mineable Reserves Total Geological Reserves Mineable Reserves... Error! Bookmark not defined. 3.3 Life of the MIne Production details Land Usage details Environmental Management Plan Air pollution management Measures taken to reduce pollution Noise Pollution management Water Pollution Management Green belt development Environmental Monitoring program Mine closure plan: Occupational health and safety Other management aspects EMP Budget i

4 List of Tables Table 2-1: Salient features... 4 Table 3-1 : Total Reserves... 8 Table 4-1 : Land usage details... 9 Table 4-3 : Man power requirement... 9 Table 5-1: Proposed Green belt & corresponding water requirement Table 5-2 : Suggested trees for green belt List of Figures Figure 2.1 : 5 Km TOPOMAP... Error! Bookmark not defined. ii

5 1 Introduction The report discusses the management plan for mitigation of adverse environmental impacts and increases the beneficial impacts due to mining of Laterite The environmental impacts can be categorized as either primary or secondary. Primary impacts are those, which are attributable directly to the project, secondary impacts are those, which are indirectly induced and typically include the associated investment and changed pattern of social and economic activities by the proposed action. The objective of preparing environment management plan is to define effective measures to control and to mitigate the environmental pollution. This report presents the environment management plan, detailing the environmentally sound technology and the measures needed to mitigate the anticipated environmental impacts due to the project. Sri G. Balreddy Mg. Partnet of M/s. Sampooran Minerals (Formally Smt.N.MD.Zarina Begum) was granted a transfer of Mining lease held earlier by Smt.N.MD.Zarina Begum, over an extent of 12.5 Ha in Sy No. 176/P of Siddulur Payaga (V) & Sy.no. 90 of Siddulur Munagal (V), Vikarabad (M), Rangareddy (D), T.S.. The transfer of Mining lease is granted for the unexpired period upto ;vide DMG Memo No 3746/MS/RR/2015 dated and. The Lease was executed by ADMG proceedings No. 5189/OMCA/QL/2013, Dt The lessee has obtained Environmental Clearance under the provisions of EIA Notifications 2006, vide Lr.No. SEIA/AP/RRD-115/2013, dated The Lessee has also obtained C.F.E. and C.F.O. and its renewal from T.S.P.C.B., 739-RR- I/TSPCB/ZOH/CFO/ dated It is previously proposed to conduct open cast semi mechanized method for quarrying Laterite with the production capacity of Laterite 30,000 TPA & within the lease period. Now the proponent wants to increase the capacity of Laterite: TPA TPA Details of Project 3

6 Table 1-1: Salient features Description Details Site Location Sy No. 13/2,14/2,31/2, 32/2, 33/2 & 35/2 to 37/2, Mallampally (V), Mulugu (M),Warangal (D),T.S. Production Proposed Laterite: TPA TPA Existing Capacity Laterite :30,000 TPA Mine Lease Area Latitude Longitude Mean Sea Level 12.5 Hectares Latitude N Longitude "E 738 m Top sheet No. 56 G / 15 Temperature variation Seismic Zone Water level Nearest railway line Airport Road/ Highway Hospital Nearest Town Neatest Habitant & Village o C Zone-II (Least Active) 30 M BGL Vikarabad -8 km Shamshabad, 100 Km Hyderabad to Tandur -2.2 Km Vikarabad-8 km Vikarabad-8 km Pirampalli village 1.0 km Nearest Water Bodies Nearest Reserve Forest Historical Places Meerzapur Chervu ( 3.0 km NE), Pond (2.0 km S). None within 5 km radius, Open Jungle at 2.0 Km NE Nil Method of Mining Opencast semi mechanized method Capital cost Rs. 130 Lakhs ( No increase in capital cost since no new facility is required for expansion) EMP Cost Existing Proposed 4

7 App. 8.0 Lakhs App Lakhs Recurring EMP cost App. 2 Lakhs App.5 Lakhs. 5

8 6

9 2 Reserves Estimation and Life of Mine Geological traverses in the quarry and the study exposures in the vicinity of quarries facilitated to access the shape and size of the deposit in the area. It is a hill deposit rising 19 M above ground level within the quarry lease area (The highest contour is 235 M). The surface of sheet rock is wavy and irregular. 2.1 Method for estimation of reserves Dolomite Deposit: The Dolomite outcrops are predominantly seen in the northeastern corner of the lease area. Towards south western direction and is concealed under a thin shale cover. The Dolomite is grey and buff in color and massive. The shale is purple colored, thinly laminated, flaggy and contains inter beds of Chert. Dolomite is overlain by shale, gritty conglomerate, sandstone BIF and Laterite. The thickness of Dolomite is expected to be 10 m. Laterite Deposit: The Laterite occurs as capping in the central and southern part of the lease area. It contains lithomarge clay and occurs as blanket like deposit with fairly uniform thickness of about 10m beneath a thin veneer of laterite soil cover. The laterite is steel grey, reddish brown & yellowish brown in color, hard compact and massive. The structure is pisolitic and is porous with cavities. The Top 1.5 to 2.0 m thick laterite occurs as loose, disjointed blocks with fine laterite gravel filling the gap and joints. Below this horizon pinkish and buff colored soft lithomarge clay occurs down to a depth of 8 m as evidenced from the pit dug in the central part of the area by the lessee. The laterite grades into lithomarge clay and both the units are commercially exploitable. 7

10 2.2 Total Mineable Reserves Total Geological Reserves Table 2-1 : Total Reserves 2.3 Life of the MIne Life of the Laterite = total mineable reserves/ Annual production rate Life of the Mine =30,83,105 / = or 14. = OR SAY 8 YEARS As per the AMP of Pg.18 8

11 3 Production details 3.1 Land Usage details Land Use Pattern of the quarry area during the next 5 years will be as follows Table 3-1 : Land usage details Head Area used upto Previous plan (Ha) Area required in present plan (Ha) Total Area (Ha) Mining Area Over Burden / Market Rejects Mineral Storage 0.129` Infrastructure Roads Green belt Unused land Total Table 3-2 : Man power requirement S.No. Category No. of Persons 1. Mines Manager 1 2. Mine Supervisor 1 3. Skilled Workers 5 4. Semi Skilled Workers 5 5. Un-skilled 8 9

12 10

13 4 Environmental Management Plan Mining of Laterite involves using heavy machinery and impacts the surrounding environment. In order to reduce the impact, we assessed the possible impacts on surrounding environment and suggested possible preventive measures by categorizing as Air, Noise and Water. The details of the possible causes and measures taken to reduce them are as follows. In addition to these measures a green belt will also be developed to remedy the biomass loss occurring due to the mining process. 4.1 Air pollution management In the process of mining heavy machinery such as excavators, Tippers,etc are used. These result in air pollution at various stages, which are stated as follows 1. Particulate matter generation from the mining process, 2. Particulate matter generation due to hauling, loading & unloading of mined Laterite & Dolomite 3. NOx & Sox generation form the consumption of fossil fuels in heavy machinery and transportation vehicles Measures taken to reduce pollution During mining: Particulate matter generation during mining is mainly from drilling holes which can be controlled by covering the drill holes with cloth. Transportation: a. To minimize the particulate mixing in air during hauling the vehicles are never overloaded and covered with a tarpal b. The particulate generation from the vehicular movement is suppressed by sprinkling water twice a day and conducting regular road repairs Additionally the proposed green belt would act as sinks for particulate matter. 11

14 4.2 Noise Pollution management The major source of noise pollution is due to i. Drilling, ii. Blasting and iii. Vehicular movements. Regular maintenance of noise generating units (repairing, greasing and minimiza- tion vibrations) will be taken to minimize noise levels. During blasting operations the noise level may increase (short time exposures). Blasting will be carried out during daytime to avoid noise intensity to the sur- rounding people at night time. Personal protective equipment like earplugs and other protective devices will be provided to workers those who are working near by the noise generating sources (drill machine operators). But as with distance away from the mining operations, the noise levels will reduce and the anticipated noise levels falls below the day and night residential standard limits set by CPCB (day Leq 55 and night Leq 45 db(a)). Dense vegetation is planned at the periphery of the lease area to minimize the impact of blasting in the surrounding environment. 4.3 Water Pollution Management The ground water table in this belt is 30 m below from the surface and since the quarry depth will not reach upto this depth in the near future flooding by ground water is not anticipated. However, during rainy months, there is a possibility of wet conditions developing in the working pit. This will be minimized if not altogether eliminated by adopting simple techniques like digging trenches all round to drain off rainwater and preventing surface run off from entering and flooding working pit. The water from the will be pumped by deploying suitable pumps, if and when required, the mine drainage can be effectively managed and the pit kept dry to keep up the production schedule. 4.4 Green belt development The whole area is occupied by scattered sparse vegetation of thorny trees and small bushes. In the quarry lease area no wild animals are witnessed as per the statements 12

15 collected from the local population, since 50 years. There will be loss of biomass due to clearing of existing vegetation, but will be compensated by the given afforestation plan. As the site is near to human settlement other than domestic animals no important wild life is found that need to take special attention. However due to planned development of green belt, the area attracts more avifauna and also gives shelter to other domestic animals. Table 4-1: Proposed Green belt & corresponding water requirement Year Trees at the end of year (No.) Water L/tree (KLD) 1st year nd year rd year Yearly average 0.22 Table 4-2 : Suggested trees for green belt No. Botanical Name Common Height Color of the Flowering Name (m) flower time 1 Acacia Arabica Nalla thumma Yellow March-May 2 Azadirachta indica Neem White January- May 3 Terminalia catappa Badam White March - April 13

16 4 Nerium odorum Ganneru Red, white Febraury- March 5 Tectona GRANDIs Teak White June - september 6 Annona squamosa Sethaphalam Creamish yellow May- August 7 Eucalyptus citridora Eucalyptus White July- August 4.5 Environmental Monitoring program The survey of air pollution comprises of the following monitoring aspects; i. Ambient air quality survey ii. Noise Level Monitoring Ambient air quality and noise level Monitoring will be carried out at minimum three stations, one station within mine site and two stations nearby residential areas out- side the mine. Parameters like suspended particulate matter, sulphur dioxide, oxides of nitrogen carbon monoxide and lead will be monitored. The frequency of monitoring is preferably once in three months on 24 hour basis. The samples will be collected in accordance with the procedures given by CPCB. 4.6 Mine closure plan: Reclamation The top soil or the waste generated from the mine will be used to refill the pit and since it wont be sufficient to fill the mine. The mining pit will be developed as water logged areas with suitable fencing all along the boundaries. Storage of rain water in the mine it will help to improve the ground water table in the area. As this 14

17 area always experiences acute drought situation, this water body can act as a source of water. The aqua fauna like files, prawns,etc. will be developed in the hydro-reclaimed areas by migrating them from the area having similar type of environment. The pit will be fenced appropriately keeping in view the most important aspect of safety. 4.7 Occupational health and safety Health and safety aspects of the mine will be taken care off as per the World Bank (WB) guidelines on open pit mining. The guidelines provide the detailed informa- tion on the aspects that are required to be taken into account for maintaining proper health and safety issues. The workers continuously exposed to dust will be provided with some protective devices like dust mask to prevent respiratory disorders. The workers continuously exposed to a high noise will be provided with ear muffs/ earplugs. Green belt in and around the mining area will be developed to attenuate noise and dust impact. The blasting carried out in the mine area will be carefully planned and executed under the supervision of a responsible officer, to avoid any accidents. Drinking water supply for the employees will be provided by the project authority. The standard of the drinking water will be per WHO guidelines. Periodical training programme to inform the employees about their task, associated risk, and safe working practices will be undertaken. Training will also include information on accident prevention, proper control and maintenance of equipment and safe material handling practices. A regular monitoring of the Occupational Health and Safety will reduce the chances of accidents in the mine. Records of job related accidents and illness should be maintained. This information will be reviewed and evaluated to improve the effectiveness of Environmental Health and Safety programme. 4.8 Other management aspects Records will be maintained for the analysis of ambient air quality and noise levels. These records are not only required for the perusal of the Pollution Control Board authorities. The management will maintain the records as per the hazardous waste regulations and EPA regulations and apply for the annual consents for air and water, and renewal of 15

18 authorization for the storage of hazardous waste as per the Hazardous Waste (Handling & Management) Rules, The records of hazardous waste manifest will be maintained. The format of the same is enclosed in appendix. The mine shall obtain the consent for operation (CFO) as required under section 25/26 of the Water act, 1974 and under section 21/22 of Air Act, 1981, before trial production and commissioning from the State Pollution Control Board. The CFO will be renewed each year by the management. The mine will submit environmental statement every year before September 30. The management ensures that it will comply with all the directions and regulations issued by the Ministry of Environment and Forests, New Delhi, State and Centre Pollution Control Boards. The Consent for Establishment & Consent for Operation will be displayed in a conspicuous location for reference to the inspecting authorities of different departments. 16

19 4.9 Cost of Environmental Management Plan The total project cost is Rs.130 Lakhs and an amount of Rs. 13 lakhs per annum towards environmental action plan and the details of the same are given below. Capital cost Project Cost Break up No. Description of Item Recurring Cost (Lakhs) Land Plant & Machinary Building & Facility EMP Implementation EMP Recurring Total Lease 100 Lakhs 10 Lakhs 15 Lakhs 5 Lakhs 130 Lakhs 17

20 EMP Budget Description Air pollution Item Nose masks 25 No's - Rs. 25/- each Cloth for drillers 8 no's 1.0 m each Gunny bags for covering the surface of jackhammer holes Capital cost (Rs.) Recurring cost (Rs.) Road 1 tanker Remarks Once a week. Replaceable, and cost can increase with time Once a week. Replaceable, and cost can increase with time As and when needed, Lump sum. Water tanker one tanker per day for 300 days Plantation on road side - 2m interval and buffer zone - 3m interval plus maintenance ( 96 Greenbelt and nursery development Water pollution Construction of Septic Tank Noise pollution Maintenance of machinery suitably Re-plant the non-surviving plants, watering and protection from animals Cost of construction of wall around the dip side of the dump Included in main cost PPE s like Ear muffs Once in three months 18

21 Description Item Capital cost (Rs.) Recurring cost (Rs.) Remarks Providing First aid kits 2 No s and fire extinguishers 2 No s Once in year, replace by conducting periodical checkup Occupational Safety and Health Providing Personal protective equipments to all employees (hand Rs. 30, safety Rs. 750 and Rs. 200) Training and awareness programs on risk factors during emergencies by the experts Safety shoe twice in a year, helmets once in three years and hand gloves thrice in a year Once in six months and create sign boards about the risk and safety precautions regularly Periodical medical checkup and supply of medicines Once in a year and supply of medicines for every three months Infrastructure Road Repairs and lightening Once in year especially during monsoon Environmental monitoring Ambient air quality studies Once in six months 2 locations Water quality studies Once a year 2 Locations Noise studies Once in six months 2 Locations Vibration studies Once in year 1 locations Miselenous Grand Total Hence the total capital cost for the first year is Rs /- Will be done through MoEF laboratories 19