Limestone Mining Project (Area: ha) at Near Village: Bhod, Taluka Ranavav, District Porbandar (Gujarat) Pre-feasibility Report

Size: px
Start display at page:

Download "Limestone Mining Project (Area: ha) at Near Village: Bhod, Taluka Ranavav, District Porbandar (Gujarat) Pre-feasibility Report"

Transcription

1 Limestone Mining Project (Area: ha) at Near Village: Bhod, Taluka Ranavav, District Porbandar PRE - FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE For MINING ACTIVITY CATEGORY B2 UNDER THE EIA NOTIFICATION 2006 AND AS AMENDED FROM TIME TO TIME TO SHRI ASHOKKUMAR BABULAL SINDHAV LOCATED AT S. No. 358/3 Area: hect. at Vill: Bhod Tal: Ranavav, Dist: Porbandar. March

2 INDEX CHAPTER NO. TITLE PAGE NO. 1. Executive Summary 3 2. Introduction of the project/ Background information 4 3. Project Description 6 4. Site Analysis 9 5. Planning Brief Planning Concept Proposed Infrastructure Rehabilitation and Resettlement (R & R) Plan Project Schedule & Cost Estimates Analysis of proposal (Final Recommendations) 15 2

3 1. Executive Summary The mining lease was granted for mineral Lime Stone in favour of Shri Ashok babulal Sindhav, P.O. Ranavav, Distt.- Porbandar State-Gujarat, for area of Hect. near village Bhod, Taluka-Ranavav, District Porbandar. The lease is expired and application for renewal is already done. The quarry will be worked upon by open cast semi-mechanized method. Proposed rate of production is 1,24,032 TPA. The project cost is Rs.8, 00,000. Limestone has many industrial uses and can be used as mined or processed into a wide variety of products. It is the raw material for a large variety of construction, agricultural, environmental, and industrial materials. Project area is ha, hence it is treated as Category B2 Project and to be dealt at the level of SEIAA, Gujarat, thus Environmental Clearance for the project is to be grant by the State Environment Impact Assessment Authority; as per EIA Notification dated & as amended from time to time. Table-1 Salient features of the Project S. No. Particulars Details A. Mining Lease Details 1. Name of the Project Limestone Mining project 2. Mineral Limestone 3. Mining Lease Area ha 4. Lease Holder Shri Ashok babulal Sindhav (Proposed) B Location 5. Village Bhod 6. Taluka Ranavav 3

4 S. No. Particulars Details 7. District Porbandar 8. State Gujarat 9. Latitude &Longitude Geographical Extends: C. Other details Latitude : N Longitude: E 10. Cost of the project Rs. 8, 00,000/- 11. Cost for Environmental Protection Measures Rs. 4,000/- 12. ESR Cost Rs. 16,000/- 13. Seismic Zone III as per IS: 1893 (Part-I) : Introduction of the project/ Background information The mining lease was granted for mineral Lime Stone in favour of Shri Ashok babulal Sindhav, P.O. Ranavav, Distt.- Porbandar State-Gujarat, for area of Hect. near village Bhod, Taluka-Ranavav, District Porbandar. The lease is expired and application for renewal is already done. The quarry will be worked upon by open cast semi-mechanized method. Proposed rate of production is 1,24,032 TPA. The project cost is Rs.8, 00, Brief description of nature of the project. The lease area is ha. The total mineable reserves available here are 43,56,800 tons. Water requirement for project for domestic use, dust suppression and plantation will be 5.0 KLD which will be met from nearby villages. 4

5 2.2 Need for the project and its importance to the country and/or region. Limestone is used as a construction material worldwide. Limestone is used as raw material in construction of building and infrastructure projects. In India, mining Industry contributes significantly to its economy. The GDP (Gross Domestic Product) contribution of mining industry varies from 2.2% to 2.5% only but total industrial sector contributes around 10% to 11%.Even small scaled mining contributes 6% to the entire cost of minerals production. The working mine contribute in the State s minerals production and improve the GDP with a positive & important effect on the region. 2.3 Demand-Supply Gap. As is used as raw material in construction of building and infrastructure projects, the demand of is increasing day by day. In past, demand was not too much but now a days due to rapid industrialization and urbanization its demand increasing with peace of time. At present, demand of is more than the supply. 2.4 Imports vs. Indigenous production. There will be no import for the project. The indigenously produced machinery will be used and the excavated mineral will be for domestic market. 2.5 Export Possibility. There are no export possibilities from the proposed mining activity. 2.6 Domestic / export Markets. At present limestone is used in all type of constructions projects. 2.7 Employment generation (direct and indirect) due to the project Around 100 workers will be employed directly in the proposed project. 5

6 Transportation is required. Hence jobs and business opportunities in logistical activities have come up. 3. Project Description 3.1 Type of project including interlinked and interdependent projects, if any. Project is a small scale semi mechanized mining project. This project does not have interlink or interdependency on any other project. 3.2 Location (map showing general location, specific location, and project boundary & project site layout) with coordinates. The lease area is situated near village Bhod, Taluka Ranavav and District Porbandar. The lease area falls within the Survey of India top sheet no. 41G14 The location of the mine boundary lies between the following geographical co- ordinates:- Latitude Longitude N E 3.3 Details of alternate sites considered and the basis of selecting the proposed site, particularly the environmental considerations gone into should be highlighted. This is working opencast mine. No alternate sites were considered as this is site specific project. 3.4 Size or magnitude of operation. Production of Sand 1,24,032 TPA from this mine is proposed and mining will be done by opencast semi mechanized method. 6

7 S. No. Particulars Details Table - 2 Salient Features of the Project 1. Name of the Project Limestone mining project 2. Mineral Limestone 3. Mining Lease Area ha 4. Lease Holder (Proposed) Shri Ashokbhai babulal Sindhav 5. Method of mining Open cast Semi mechanized Method 6. Total Mineable Reserve 43,56,800 Tons 3.5 Geology Regional Geology Top most formations are of Milliolitic Limestone. These are very well exposed in the entire area of segment C of the lease area. Formation is in form of elongated ridge running East-West, rising to highest elevation of 48 m above mean sea level. GAJ FORMATIONS This consists of yellow coloured siliceous limestone followed by khakhi coloured clays. Gaj Lime Stone are exposed in the part of the area,in this part of the lease area milliolitic limestone appears to have been washed away due to cutting action of the rain water. The well have encountered yellow coloured limestone 1 m followed by yellow coloured gaj clay. Gaj formation have been deposited unconformably over the Deccan traps.due to undulating surfaces of the deccan traps thickness of gaj formations are varying in thickness. Thickness of gaj formations increases towards sea. 7

8 Exploration During mining in past it has been observed that the mineral is continuing in depth in the entire lease hold Mineral Reserves:- The Mineral reserve of the lease area 43,56,800 tons Production Parameters:- The proposed capacity / year are 1,24,032 TPA. 3.6 Project description with process details (a schematic diagram/ flow chart showing the project layout, components of the project etc. should be given Method for developing and working the deposits The mine will be worked by means of opencast semi-mechanized method which includes drilling, loading and transportation. Opencast mining The proposed operations will be carried out by open cast semi-mechanized method. At present the semi-mechanized opencast mining will be carried out. There is no overburden in the area. Mining in general will be carried out by semimechanized open cast method by forming benches up to 6.0 meter height. The excavation in lease area will be done through jack hammers. This limestone will be loaded in trippers through proclaim. All haulage roads, the alignment of which keeps on changing depending upon the working in the pit, joins the existing surface roads of the lease hold. The mineral transported out of the lease hold will be with the help of tippers and trucks. All pit working will be securely fenced as per the standards prescribed by DGMS. Approach roads to pit faces shall be maintained as required. 8

9 General No. of working days per year 300 No. of shifts per day Raw material required along with estimated quantity, likely source, marketing area of final product/s, Mode of transport of raw Material and Finished Product. No raw material will be required for the production of mineral. 3.8 Resource optimization/ recycling and reuse envisaged in the project, if any, should be briefly outlined. No wastage will be generated from mining operation. 3.9 Availability of water its source, Energy/ power requirement and source should be given. Water is required for drinking purpose. No Power Requirement for operation Purposes Quantity of wastes to be generated (liquid and solid) and scheme for their Management/disposal. As stated earlier, there will be no generation of waste in the area. 4. Site Analysis 4.1 Connectivity. The lease area is located in the Porbandar District, Ranavav Taluka and all market facilities are available in Ranavav city which is at a distance of about 4.5 km. in west direction. Porbandar airport is the nearest airport from the mine site at about 15 km in SW direction.. Railway facilities available in Ranavav which is around 4.5 km in W direction. 9

10 4.2 Land Form, Land use and Land ownership. Present land comprises of limestone mining. It is a government wasteland. 4.3 Topography. The land for the lease hold area is a non agriculture government wasteland. 4.4 Existing land use pattern (agriculture, non-agriculture, forest, water bodies (including area under CRZ)), shortest distances from the periphery of the project to periphery of the forests, national park, wild life sanctuary, eco sensitive areas, water bodies (distance from the HFL of the river), CRZ. In case of notified industrial area, a copy of the Gazette notification should be given. Not Applicable as the lease area is under government waste land and there is no habitation in the area.. Table - 3 Environmental Settings S. No. Particular Details 1. Nearest city/ town Ranavav at about 4.5 kms in West direction Nearest Railway Station Ranavav Junction at a distance of around 4.5 km in W direction. Nearest Airport Porbandar Airport at a distance of around 15 km in SW direction. 4. Archaeological Place Important 5. Ecological Sensitive Areas (National Park, Wildlife Sanctuary, Biosphere Reserve etc.) No such area is located within the 15 km radius of the mining lease area. Barda Wildlife Sanctuary within close proximity from project site 10

11 7. Reserved/Protected Forest within 10 km. radius 1. Naliyadhar reserved forest at a distance of around 1.0 km in N direction. 2. Jambuda reserved forest at a distance of around 7 km in N direction. 3. Protected forest at a distance of around 4.5 km in N direction. 4. Reserved forest at a distance of around 5.0 km in N direction. 8. Nearest River / water body 1. Dhangva Nadi at a distance of around 5 km Source: Preliminary Site visit and SOI Toposheet in NE direction. 2. Bileshwari Nadi at a distance of around 8 km in NE direction. 3. Minsar Nadi at a distance of around 10 km in E direction. 4. Khambhala talav at a distance of around 6.0 km in NW direction. 11

12 5. Planning Brief 5.1 Planning Concept (type of industries, facilities, Transportation etc.) Town and Country Planning/Development authority Classification It is a mining industry in which open cast semi-mechanized mining method will be practiced. 5.2 Population Projection There will be recruitment of local workers. There will be no change in the population projection of the most nearest & further most villages of the project. 5.3 Assessment of Infrastructure Demand (Physical & Social). Lease will assess the demand of infrastructure in nearby area of the mine site and same will be developed under social work. 12

13 5.4 Amenities/Facilities. Lease will develop the amenities/facilities in the nearby area of the mine site as per requirements of local people of the nearby areas under corporate social responsibility programs. 6. Proposed Infrastructure 6.1 Industrial Area (Processing Area). The area is very well connected by road network to the mines, District headquarter etc. The area is self sufficient to cater the needs of the project. Hence, no infrastructure is proposed. 6.2 Green Belt. Green belt will be developed in consultation with local forest office and CPCB guidelines. 6.3 Connectivity (Traffic and Transportation Road/ Rail/Metro/Water ways etc) The lease area is well connected through roads. No Railway, metro, water transportation is required. 6.4 Drinking Water Management (Source & Supply of water) Villages nearby the lease area will provide the water for all the purposes. 6.5 Sewerage System. No sewage generation will take place. 6.6 Industrial Waste Management. As there is no industrial waste, hence not applicable 13

14 6.7 Solid Waste Management. As stated earlier, there will be no generation of waste in the area. Because no waste is generated even rubbles are also to the grinding unit. 6.8 Power Requirement & Supply / source. No power will be required for proposed project. 7. Rehabilitation and Resettlement (R & R) Plan Policy to be adopted (Central/State) in respect of the project affected persons including home oustees, land oustees and landless laborers (a brief outline to be given). Not Applicable as there is any displacement or dislocation. 8. Project Schedule & Cost Estimates The mining activity will be started after obtaining Environmental Clearance from SEIAA, Gujarat and acquiring the valid mining lease from Mines and Geology Department of the State Government. Estimated Project Cost Along With Analysis In Terms Of Economic Viability of the Project Cost of the Project: Rs. 8, 00,000/- Cost for Environmental Protection Measures: Rs. 4,000/- ESR/CSR cost: Rs. 16,000/- Details of activities & budgetary allocation for CSR activities and labourer welfare activities are detailed in below table: Table - 4 ENTRPRENEUR SOCIAL RESPONSIBILITY ACTIVITIES & BUDGETARY ALLOCATION 14

15 S. No Particulars Activities to be done by PP Total Expenditure 1. Education Distribution of free books & stationary to village students of primary and schools nearby village PP will contribute in repairing work in toilets for girls in Govt. Sec School of nearby village 5,000 /- 2. Water PP will contribute in digging and repairing hand pumps 5,000 /- 3. Health Care Health awareness programme will be conducted to improve health and hygiene standards 2,000 /- 4. Social forestry Plantation work in Schools and Govt buildings Campus of Village. 4,000/- Total Contribution in CSR Activities 16,000/- 9. Analysis of proposal (Final Recommendations) Financial and social benefits with special emphasis on the benefit to the local people including tribal population, if any, in the area. The Project will bring economic benefits to the state by the way of royalty for mineral. The mining operations shall be providing employment to approximately 100 persons directly in the excavation. Most of the local people are likely to be benefited. This project operation will provide livelihood to the poorest section of the society. Mining is expected to have positive impact on socio-economic life of people living in nearby villages. Signature of applicant 15

PREFEASIBILITY REPORT

PREFEASIBILITY REPORT (B) PREFEASIBILITY REPORT OF EXISTING SAND MINING PROJECT OF RAJESHBHAI BHAGUBHAI PATEL AT VILLAGE:- Panchlai, TALUKA:- Pardi, DIST.:-Valdad. 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXECUTIVE SUMMARY

More information

(B) PREFEASIBILITY REPORT OF EXISTING BLACK TRAP PROJECT OF

(B) PREFEASIBILITY REPORT OF EXISTING BLACK TRAP PROJECT OF (B) PREFEASIBILITY REPORT OF EXISTING BLACK TRAP PROJECT OF Makwana Dineshbhai Khimjibhai AT VILLAGE:- Tithava, TALUKA:- Wankaner, DIST.:- Morbi 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXCUTIVE SUMMARY

More information

EXISTING PROJECT FOR ORDINARY SAND MINING

EXISTING PROJECT FOR ORDINARY SAND MINING (C) PROJECT REPORT OF EXISTING PROJECT FOR ORDINARY SAND MINING OF JASHUBEN CHHAGANBHAI OAD AT VILLAGE:-TIMBA, TALUKA:- KAMREJ, DIST.:- SURAT 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXECUTIVE SUMMARY

More information

PREFEASIBILITY REPORT OF EXISTING SILICA SAND MINING PROJECT OF MANGUBEN KANTILAL THAKKAR

PREFEASIBILITY REPORT OF EXISTING SILICA SAND MINING PROJECT OF MANGUBEN KANTILAL THAKKAR PREFEASIBILITY REPORT OF EXISTING SILICA SAND MINING PROJECT OF MANGUBEN KANTILAL THAKKAR AT VILLAGE:- BRAHMPURI, TALUKA:- Sayla, DIST.:-Surendranagar 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXECUTIVE

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT Of Shri Upendra Suryawanshi At Khasra No. 413/1, 413/3 Vill.-Ambada, Tehsil-Amla, District-Betul (M.P.) Production Capacity: Max 6,320 Cu.mt/year Area 1.00Hectare Proponent Name

More information

PRE-FEASIBILITY REPORT FOR ORDINARY SAND

PRE-FEASIBILITY REPORT FOR ORDINARY SAND PRE-FEASIBILITY REPORT FOR ORDINARY SAND Proponent NISANT TRADERS At- Opp. Survey No.- 3 Panam River Area-2.50.00 Hectare Village-Ramji-ni-Nal, Taluka- Shahera Dist.- Panchmahal Mob.- +91924040782 CONTENTS

More information

Pre-Feasibility Report

Pre-Feasibility Report Pre-Feasibility Report 1. Executive Summary Residential, Commercial, Retail and Hotel projects and an IT/ITES. The Project has already obtained an Environmental Clearance from Ministry of Environment &

More information

PRE-FEASIBILITY REPORT. Name of Company / Mine Owner Shri Jayant Kumar Choudhary Location

PRE-FEASIBILITY REPORT. Name of Company / Mine Owner Shri Jayant Kumar Choudhary Location 1. SUMMARY PRE-FEASIBILITY REPORT Project Stone Quarry Name of Company / Mine Owner Shri Jayant Kumar Choudhary Location Village Taluka District State Rupapali Basna Mahasamund Chhattisgarh 1 Mining Lease

More information

STONE QUARRY Survey No. : 57/5, Village : Dhadhade, Tehsil: Vikramgad, District Thane, Maharashtra Area (2.0 Ha)

STONE QUARRY Survey No. : 57/5, Village : Dhadhade, Tehsil: Vikramgad, District Thane, Maharashtra Area (2.0 Ha) Pre Feasibility Report On STONE QUARRY Survey No. : 57/5, Village : Dhadhade, Tehsil: Vikramgad, District Thane, Maharashtra Area (2.0 Ha) Submitted to MINISTRY OF ENVIRONMENT & FOREST STATE LEVEL ENVIRONMENTAL

More information

EXECUTIVE SUMMARY. Kumardeipur Sand Quarry Cum ' 13.3" N to 20 44' 20.7"N Longitude " E to 85 35'27.5 "E

EXECUTIVE SUMMARY. Kumardeipur Sand Quarry Cum ' 13.3 N to 20 44' 20.7N Longitude  E to 85 35'27.5 E EXECUTIVE SUMMARY 1.0 INTRODUCTION Sri Mahesh Prasad Mishra proposes to mine Sand Quarry from an approved Mining Lease over an area of 14.85 Ac or 6.01 hectares (Non-Forest Land) which is located in at

More information

PRE FEASIBILITY REPORT. Company of production capacity: 14,40,000 CFT/ Year located at Khasra No near Village:

PRE FEASIBILITY REPORT. Company of production capacity: 14,40,000 CFT/ Year located at Khasra No near Village: PRE FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY In our Masonry Stone Mining Lease (M.L. No. 15/96, Area: 1.0 ha), Production capacity of masonry stone: 142920 TPA and existing Stone Crusher Unit named M/s.

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT Page1 PRE FEASIBILITY REPORT KALDA FLAG STONE QUARRY AREA OF -1.55 HACTARE STRICTLY AS PER MOEF GUIDELINE DATE 30/12/2006 IN TERMS OF PROVISIONS OF EIA NOTIFICATION 2006 VILLAGE KALDA TEHSIL PAWAI DISTRICT

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project of MANUFACTURING OF SYNTHETIC ORGANIC DYES (5 f B IND II) By SHREEJI BAPA DYE CHEM PLOT NO 1319 & 1320, PHASE-III, GIDC, VATVA, AHEMADABAD-382445, GUJARAT,

More information

PRE-FEASIBILITY REPORT OF SAND QUARRY

PRE-FEASIBILITY REPORT OF SAND QUARRY PRE-FEASIBILITY REPORT OF SAND QUARRY Survey No Village Taluka District Lease area : 1 Paiki : Marigana : Anjar, : Kutch, Gujarat, : 2.00 Ha. Submitted to MINISTRY OF ENVIRONMENT & FORESTS STATE LEVEL

More information

MODIFIED QUARRYING PLAN FOR "SHINGATALOOR SAND MINING BLOCK-2" EXTENT Acres (4.86 Ha) IN TUNGABHADRA RIVER BED ADJ ACENT TO SY.

MODIFIED QUARRYING PLAN FOR SHINGATALOOR SAND MINING BLOCK-2 EXTENT Acres (4.86 Ha) IN TUNGABHADRA RIVER BED ADJ ACENT TO SY. MODIFIED QUARRYING PLAN FOR "SHINGATALOOR SAND MINING BLOCK-2" EXTENT -12.00 Acres (4.86 Ha) IN TUNGABHADRA RIVER BED ADJ ACENT TO SY.NO - 129 & 131OF SHINGATALOOR - VILLAGE MUNDARGI - TALUK GADAG - DISTRICT

More information

Table 1.1: The Salient Features of the Project Proposed Quartz Mine Of M/s. Viswanadha Stone Crusher & 16 others

Table 1.1: The Salient Features of the Project Proposed Quartz Mine Of M/s. Viswanadha Stone Crusher & 16 others 1. EXECUTIVE SUMMARY 1.1 Introduction The Road Metal Quarries was granted in Guntur District, Andhra Pradesh has been allotted to M/s. Viswanadha Stone Crusher & 16 others by Assistant Director of Mines

More information

Masonry Stone Mining Project, M. L. No. 27/09, M. L. Area 1.0 ha. Near Village: Velangri, Tehsil & District-Sirohi (Rajasthan) PRE FEASIBILITY REPORT

Masonry Stone Mining Project, M. L. No. 27/09, M. L. Area 1.0 ha. Near Village: Velangri, Tehsil & District-Sirohi (Rajasthan) PRE FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY PRE FEASIBILITY REPORT This is an existing mine, proposal for obtaining Environmental Clearance for Masonry Stone with production capacity 37,300 TPA Near Village: Velangri, Tehsil-Sirohi,

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT 1. Introduction 1. Identification of project and project proponent The Pahanbarri Sand Quarry area is located in the Tawa River at Village- Pahanbarri, Tehsil- Itarsi & District-

More information

PRE-FEASIBILITY REPORT. 1. SUMMARY Kudeli Brick Earth Quarry Name of Company / Mine Owner Smt. Premawati Location 744, 760/1, 760/4, 750/1, 750/2

PRE-FEASIBILITY REPORT. 1. SUMMARY Kudeli Brick Earth Quarry Name of Company / Mine Owner Smt. Premawati Location 744, 760/1, 760/4, 750/1, 750/2 PRE-FEASIBILITY REPORT 1. SUMMARY Project Kudeli Brick Earth Quarry Name of Company / Mine Owner Smt. Premawati Location 744, 760/1, 760/4, 750/1, 750/2 Village Kudeli Taluka Baikunthpur District Koriya

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT 0.0 EXECUTIVE SUMMARY Shri Ashok Patel Partner of M/s. Patel Polymers is planning to manufacture organic chemical Different Types of Resins, for proposed expansion project at Plot

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY M/s Arti Chemical Industries is a project located at Plot No. E-22, Vilayat G.I.D.C. Tal: Vagra area of Bharuch district in Gujarat. M/s Arti Chemical Industries

More information

PRE FEASIBILITY REPORT OF KUMHARI STONE MINE, LESSEE M/s VINOD KUMAR JAIN VILLAGE KUMHARI, P.O. BASIA, P.S. BASIA, DIST. - GUMLA, JHARKHAND

PRE FEASIBILITY REPORT OF KUMHARI STONE MINE, LESSEE M/s VINOD KUMAR JAIN VILLAGE KUMHARI, P.O. BASIA, P.S. BASIA, DIST. - GUMLA, JHARKHAND EXECUTIVE SUMMARY Kumhari Stone Mine is situated in Village - Kumhari, P.O. Basia, P.S. - Basia, District : Gumla, Jharkhand over an area of 2.02 Hectares or 5.00 Acres [ Plot no. 2085(P)]. Kumhari Stone

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT for PROPOSED PROJECT FOR DYES, PIGMENTS AND DYE INTERMEDIATES MANUFACTURING PLANT IN GIDC, DAHEJ-II Of M/s. SHREEJI INDUSTRIES Plot No. D2/CH/24, Dahej-II, GIDC Industrial Estate,

More information

2. PRE-FEASIBILITY REPORT

2. PRE-FEASIBILITY REPORT 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary Sri D. Ujjinappa has applied for quarry lease for extracting of Building stone in Sy No. 19/2, Chatnihalli Village, Harpanahalli Taluk, Davangere District,

More information

PRE FEASIBILITY REPORT FOR. Silica Sand Beneficiation Plant

PRE FEASIBILITY REPORT FOR. Silica Sand Beneficiation Plant PRE FEASIBILITY REPORT FOR Silica Sand Beneficiation Plant BY Shree Silicaam Minerals LLP VILLAGE : CHOKI TALUKA : JAGADIA DIST : BHARUCH GUJARAT (INDIA) PRE-FEASIBILITY REPORT: SILICA SAND BENIFICIATION

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT For PROPOSED EXPANSION OF BAKELITE POWDER MANUFACTURING UNIT of M/S. HINDUSTAN BAKELITE COMPANY PLOT NO. J-3436, GIDC ESTATE, ANKLESHWAR, DISTRICT: BHARUCH-393002, GUJARAT 0 CONTENTS

More information

2. PRE-FEASIBILITY REPORT

2. PRE-FEASIBILITY REPORT 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary Smt. J N Rukmini, has applied for extracting of Building stone in Sy No. 40, Kuroda Bore Kavala village, Hassan Taluk & District, Karnataka over an extent

More information

1. PRE-FEASIBILITY REPORT

1. PRE-FEASIBILITY REPORT 1. PRE-FEASIBILITY REPORT 1.1 Executive Summary Sri. T. Thimmegowda, has applies quarry lisence for extracting of Building Stone Quarry in Sy No. 33/2, Kurodbore Kaval village, Hassan Taluk, Hassan District,

More information

Pre-Feasibility Report For

Pre-Feasibility Report For Pre-Feasibility Report For Proposed New Project for manufacturing of Intermediates of Agro Chemicals & Synthetic Organic Chemicals. By M/s. MANBRO POLYMERS LIMITED, Plot No. D-2/CH-275, INDUSTRIAL ESTATE,

More information

CONTENTS 3.0 INTRODUCTION OF THE PROJECT /BACKGROUND INFORMATION 8.0 REHABILITATION AND RESETTLEMENT (R & R) PLAN

CONTENTS 3.0 INTRODUCTION OF THE PROJECT /BACKGROUND INFORMATION 8.0 REHABILITATION AND RESETTLEMENT (R & R) PLAN CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXECUTIVE SUMMARY 3.0 INTRODUCTION OF THE PROJECT /BACKGROUND INFORMATION 4.0 PROJECT DESCRIPTION 4.0 AVAILABLITY OF RAW MATERIAL 5.0 SELECTION OF SITE & LOCATION

More information

PRE - FEASIBILITY REPORT

PRE - FEASIBILITY REPORT PRE - FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE For EXISTING MINING ACTIVITY CATEGARY B2 UNDER THE EIA NOTIFICATION 2006 AMENDED ON 31/05/2012 TO PIRABHAI VALABHAI NANDASANIYA LOCATED

More information

Pre- Feasibility RepoRt

Pre- Feasibility RepoRt Pre- Feasibility RepoRt AREA- 59.28 ACRE (24.0 HA) FOR KEN RIVER SAND/MORRUM MINING AT BLOCK NO-09 KHAND NO-03 GATA NO-337 VILLAGE- KANWARA TEHSIL-BANDA, DISTRICT- BANDA(U.P) SHRI RAVINDRA NATH SINGH JULY

More information

PRE - FEASIBILITY REPORT

PRE - FEASIBILITY REPORT PRE - FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE For EXISTING BLACK TRAP MINING ACTIVITY CATEGARY B2 UNDER THE EIA NOTIFICATION 2006 AMENDED ON 15/01/2016 TO REKHABEN YOGESHKUMAR JOSHI

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT BANDOL CRUSHER STONE QUARRY OF SHRI TULSIRAM SAHU AT Khasra No. 15/2,23/2 Village Bandol Tehsil District State Madhya Pradesh Production Capacity 45030 M3/Year Area 3.150 Hectare

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT M/S. VANAS INFRA PROJECTS PVT. LTD SURVEY NO. 598, CHINTALAPALLY VILLAGE, KOLLAPUR MANDAL, NAGARKURNOOL DISTRICT, TELANGANA PRE-FEASIBILITY REPORT SUBMITTED BY M/s. Sri Soma Jitendra H. No. 7-1-397/150,

More information

Proposed Project of Halcyon Labs Pvt Ltd D-2/CH : 335,336,337, GIDC-Dahej-2, DIst: Bharuch, Gujarat Ramans Enviro Services Pvt Ltd Ahmedabad

Proposed Project of Halcyon Labs Pvt Ltd D-2/CH : 335,336,337, GIDC-Dahej-2, DIst: Bharuch, Gujarat Ramans Enviro Services Pvt Ltd Ahmedabad 1. EXECUTIVE SUMMARY OF THE PROJECT BRIEF SUMMARY OF THE PROJECT : TYPE OF PROJECT : Proposed Project for manufacturing of pharma intermediates by Halcyon Labs Pvt.Ltd. LOCATION : Proposed Project of Halcyon

More information

SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH

SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT (OPENCAST QUARTZ MINE 40.313 ha) SUBMITTED BY Sri Door No. 39/49/39,

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT GRANITE BUILDING STONE QUARRY MINING PROJECT STATE : KERALA DISTRICT : KANNUR THALUK : THALASSERY VILLAGE : THRIPPANGOTTUR BLOCK NO. : NIL SURVEY NO. : 275/1A MINERAL : GRANITE BUILDING

More information

Table 1.1: The Salient Features of the Project. Proposed Quartz Mine Of Sri. Syed Masthan Basha

Table 1.1: The Salient Features of the Project. Proposed Quartz Mine Of Sri. Syed Masthan Basha 1. EXECUTIVE SUMMARY 1.1 Introduction The Eknampuram Quartz mine of 89.80 Acres/ 36.34 ha is located in Sy. No. 60, Eknampuram Village, C.S. Puram Mandal, Prakasam District, Andhra Pradesh has been allotted

More information

M/S. Dain Colour Chem

M/S. Dain Colour Chem PRE FEASIBILITY REPORT For PROPOSED EXPANSION IN EXISTING MANUFACTURING PLANT Of M/S. Dain Colour Chem Plot No.: 5, Nilkanth Estate, Village: Dhanot, Ta.: Kalol, Dist.: Gandhinagar-382729, Gujarat 1 CONTENTS

More information

PREFEASIBILITY REPORT OF EXISTING BENTONITE PROJECT OF

PREFEASIBILITY REPORT OF EXISTING BENTONITE PROJECT OF PREFEASIBILITY REPORT OF EXISTING BENTONITE PROJECT OF TRICHEMIN ASSOCIATES AT VILLAGE:- SATAPAR, TALUKA:- KALYANPUR, DIST.:- DEVBHUMI DWARKA 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXECUTIVE SUMMARY

More information

Pre- FEASIBILITY REPORT

Pre- FEASIBILITY REPORT Pre- FEASIBILITY REPORT In Respect Of KATIKELA RIVER SAND BED OVER 15.00 ACRES OR 6.070 HA IN VILLAGE KATIKELA, JHARSUGUDA TAHASIL OF JHARSUGUDA DISTRICT, ODISHA (For the Financial Year-2015-16 to 2019-20)

More information

PRE- FEASIBILITY REPORT

PRE- FEASIBILITY REPORT PRE- FEASIBILITY REPORT EXECUTIVE SUMMARY 1.0 Executive Summary The Mining lease was granted in favour of Shri Mukesh Kumar S/o Shri Harish Chandra, R/o Tatol vaya Bagra, Tehsil - Bhinmal, Dist.-Jalore

More information

PRE FEASIBILITY REPORT OF KANIYAKULAM EARTH QUARRY

PRE FEASIBILITY REPORT OF KANIYAKULAM EARTH QUARRY PRE FEASIBILITY REPORT OF AZHAGAPPAPURAM EARTH FOR OVER AN EXTENT OF 0.61.0HA IN AZHAGAPPAPURAM VILLAGE, AGASTEESWARAM TALUK, KANNIYAKUMARI DISTRICT, TAMIL NADU OF, (Under the Guidelines of Ministry of

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY PRE FEASIBILITY REPORT This is an existing mine. Proposal for obtaining Environmental Clearance for marble with production capacity 72860 TPA Near Village: Sankotra, Tehsil-Jamwa

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For Excavation of Brick Earth (Total Mining Area 1.112Ha.) (For Manufacturing of Bricks) Submitted By M/s New Kaptan Brick Field Shri Krishna Kr. Singh S/o Shri Brahma DevSingh Pure

More information

PREFEASIBILITY REPORT OF PROPOSED BUILDING LIMESTONE PROJECT OF

PREFEASIBILITY REPORT OF PROPOSED BUILDING LIMESTONE PROJECT OF PREFEASIBILITY REPORT OF PROPOSED BUILDING LIMESTONE PROJECT OF Indulal C. Vora AT VILLAGE:- Palakhda, TALUKA:- Porbandar, DIST.:-Porbandar 1 (B) CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXECUTIVE SUMMARY

More information

PRE-FEASIBILTY REPORT

PRE-FEASIBILTY REPORT Aug 2018 PRE-FEASIBILTY REPORT OF M/S. J.M.R.MINES (MINING OF FELDSPAR, QUARTZ & MICA MINE) Lease Area : 5.78 Hectares(14.29 Acres) Sy.No.941,942,943 &947 Giddalur (V), Sydapuram (M), SPSR Nellore District

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY PRE FEASIBILITY REPORT The proposal for obtaining Environmental Clearance for Marble Mining Project M. L. No. 56/02, Area 4.0 ha with production capacity 40,000 TPA Near Village:

More information

EXECUTIVE SUMMARY. 1.1 Executive Summary

EXECUTIVE SUMMARY. 1.1 Executive Summary 1.1 Executive Summary EXECUTIVE SUMMARY Chobe ki Guwari Sand Stone Mining Project (M.L. No- 26-R-01/2001) is situated near village Chobe ki Guwari, Tehsil Sapotra, District Karoli, State Rajasthan over

More information

PREFEASIBILITY REPORT FOR BRICK EARTH MINE

PREFEASIBILITY REPORT FOR BRICK EARTH MINE Page 1 PREFEASIBILITY REPORT FOR BRICK EARTH MINE Developed By- Village-Chandauhan, Tehsil-Phulpur, District-Allhabaad, Uttar Pradesh. RAI ENVIROMENTAL SERVICES PVT. LTD. Website: www.raienviro.com Email

More information

PRE-FEASIBILIY REPORT

PRE-FEASIBILIY REPORT BENDRI LIMESTONE QUARRY NO. - 4 3 (Quarry No. 1) (Quarry No. 1)MINERALS - DOLOMITE (LEASE PERIOD 20.05.2002 TO 19. 05.2022) LEASE AREA - 42.754 HECTARES MINING PROJECT - CATEGORY- B PRE-FEASIBILIY REPORT

More information

PRE-FEASIBILTY REPORT SUNATHAR STONE QUARRY. VILLAGE: Sunathar. TAHASIL: Purushottampur. DIST: Ganjam LESSEE SRI KAPILA CHANDRA SAHU

PRE-FEASIBILTY REPORT SUNATHAR STONE QUARRY. VILLAGE: Sunathar. TAHASIL: Purushottampur. DIST: Ganjam LESSEE SRI KAPILA CHANDRA SAHU PRE-FEASIBILTY REPORT OF SUNATHAR STONE QUARRY VILLAGE: Sunathar TAHASIL: Purushottampur DIST: Ganjam LESSEE SRI KAPILA CHANDRA SAHU Vill/Po- Gandala, P.S.- Hinjili, Dist.-Ganjam Odisha. CONTENTS CHAPTER

More information

Table 1.1 : Salient features of the project. Sy. No. 379/1, Perecherla Village, Medikonduru Mandal, Guntur District, Andhra Pradesh.

Table 1.1 : Salient features of the project. Sy. No. 379/1, Perecherla Village, Medikonduru Mandal, Guntur District, Andhra Pradesh. 1.0 EXECUTIVE SUMMARY 1.1 Introduction Road Metal of M/s. Lakshmi Stone Crusher covering an extent of 2.10 Ac is located at Sy. No. 379/1 of Perecherla Village, Medikonduru Mandal, Guntur District, Andhra

More information

PROPOSED BULK DRUG & BULK DRUG INTERMEDIATES MANUFACTURING UNIT

PROPOSED BULK DRUG & BULK DRUG INTERMEDIATES MANUFACTURING UNIT PRE - FEASIBILITY REPORT For PROPOSED BULK DRUG & BULK DRUG INTERMEDIATES MANUFACTURING UNIT Of M/s. SHREE RAM INDUSTRIES PLOT NO.5117, GIDC-ANKLESHWAR, PIN-393002 TAL: ANKLESHWAR, DIST: BHARUCH, GUJARAT

More information

Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.)

Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.) Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.) 1) Executive Summary Project Name of Company / Mine Owner Location Village Taluka District State Girgita Limestone Mine M/s KJS

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT For NEW PROJECT (PIGMENT MANUFACTURING PLANT) Of M/s. SHREY INDUSTRIES Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat) CONTENTS Sr.

More information

PRE-FEASIBILITY REPORT GHODACH SOAPSTONE & DOLOMITE MINES (APPLICANT: M/S KASTURI MINERALS)

PRE-FEASIBILITY REPORT GHODACH SOAPSTONE & DOLOMITE MINES (APPLICANT: M/S KASTURI MINERALS) 20 PRE-FEASIBILITY REPORT OF GHODACH SOAPSTONE & DOLOMITE MINES (APPLICANT: M/S KASTURI MINERALS) 1. EXECUTIVE SUMMARY: The project is for mining of Ghodach soapstone & Dolomite Mine M.L. No. 69/2010 Near

More information

PRE-FEASIBILITY REPORT. for

PRE-FEASIBILITY REPORT. for PRE-FEASIBILITY REPORT for PROPOSED COMMON EFFLUENT TREATMETN PLANT (CETP) of M/s. VIKASHTEX ENVIROTECH CETP PVT. LTD. Block No. 523, Village: Hathoda, Taluka: Mangrol, Dist: Surat - 394 405 (Guj.) Prepared

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project of MANUFACTURING OF SYNTHETIC ORGANICCHEMICALS (RESINS) (5 f B IND II) By M/s M R INDUSTRIES SURVEY NO. 58/1 & 58/3 OPPOSITE WHOLESOME FOOD PVT. LTD.,

More information

GHODAPALANA SAND QUARRY (IN GANJAM DISTRICT OF ODISHA)

GHODAPALANA SAND QUARRY (IN GANJAM DISTRICT OF ODISHA) PRE FEASIBILITY REPORT ON GHODAPALANA SAND QUARRY (IN GANJAM DISTRICT OF ODISHA) Lease Area: 18.687 acres or 7.562 Ha. of Sri Rama chandra Dash Polasara CHAPTER 1 EXECUTIVE SUMMARY Ghodapalana sand Quarry

More information

PROJECT FEASIBILITY REPORT

PROJECT FEASIBILITY REPORT PROJECT FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE For PROPOSED CHEMICAL MANUFACTURING UNIT From M/s. MORADIA BROTHERS CHEM PVT LTD LOCATED AT: Block No.: 45, JalBhumi Industrial Estate,

More information

ENVIRONMENTAL MANAGEMENT PLAN FOR DALPATPUR STONE QUARRY AT VILLAGE DALPUTPUR TEHSIL KHURAI AND DISTRICT SAGAR [MP], AREA (0.

ENVIRONMENTAL MANAGEMENT PLAN FOR DALPATPUR STONE QUARRY AT VILLAGE DALPUTPUR TEHSIL KHURAI AND DISTRICT SAGAR [MP], AREA (0. ENVIRONMENTAL MANAGEMENT PLAN FOR DALPATPUR STONE QUARRY AT VILLAGE DALPUTPUR TEHSIL KHURAI AND DISTRICT SAGAR [MP], AREA (0.920ha) 1.1 Introduction The subject quarry is proposed for metal stone on 0.920

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN At Narmada River Mining Project:-Category B2 Lease Area: 20.000 Hect. Khasra No. 735 Vill.-Boras, Tehsil- Udaipura District- Raisen (M.P) Project Proponent M/s Shiva Corporation

More information

PRE FEASIBILITY REPORT OF ANAIMALLUR ROUGH STONE QUARRY LEASE APPLIED AREA FOR OVER AN EXTENT OF

PRE FEASIBILITY REPORT OF ANAIMALLUR ROUGH STONE QUARRY LEASE APPLIED AREA FOR OVER AN EXTENT OF PRE FEASIBILITY REPORT OF ANAIMALLUR ROUGH STONE QUARRY LEASE APPLIED AREA FOR OVER AN EXTENT OF 0.80.0Ha IN ANAIMALLUR VILLAGE, ARCOT TALUK, VELLORE DISTRICT, TAMILNADU OF THIRU.R.VINOTHKUMAR, (Under

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT For EXPANSION IN EXISTING MANUFACTURING PLANT Of M/s. SHIVA DYE STUFF PVT. LTD Plot no. A2-11/6104,G.I.D.C. Industrial Estate, Ankleshwar-393002, Gujarat. 1 CONTENTS Sr. No. Description

More information

S. No Parameter Details 1 Name & Address of the Applicant

S. No Parameter Details 1 Name & Address of the Applicant 1. EXECUTIVE SUMMARY S. No Parameter Details 1 Name & Address of the Applicant M/s AMULYA GRANITES Prop: Smt CH.SARALA H. No. FLAT NO.207 Roja Kishore Residency, Chenchupet, Tenali, AP-522 202 Guntur District,

More information

PRE FEASIBILITY REPORT OF R.PUDUPATTI ROUGH STONE QUARRY UNDER EIA NOTIFICATION 2006

PRE FEASIBILITY REPORT OF R.PUDUPATTI ROUGH STONE QUARRY UNDER EIA NOTIFICATION 2006 LEASE APPLIED AREA FOR OVER AN EXTENT OF 1.49.0Ha IN R.PUDUPATTI VILLAGE, RASIPURAM TALUK, NAMAKKAL DISTRICT, TAMILNADU OF THIRU.K.K.PERUMAL, (Under the Guidelines of Ministry of Environment and Forest

More information

ENVIRONMENT MANAGEMENT PLAN FOR STONE MINING

ENVIRONMENT MANAGEMENT PLAN FOR STONE MINING ENVIRONMENT MANAGEMENT PLAN FOR STONE MINING 1. Name and Address of Quarry Lease Holder: a. Name of applicant Priyesh Singh Thakur S/o Shri Karan Singh Thakur b. Designation of applicant Owner c. Name

More information

EIA-EMP REPORT GRAVEL QUARRY (Category-B2)

EIA-EMP REPORT GRAVEL QUARRY (Category-B2) EIA-EMP REPORT GRAVEL QUARRY (Category-B2) EXTENT : 4.00.0 Hectares S. F. No : 436/1A (P) VILLAGE TALUK DISTRICT STATE : IYANPAPPAKKUDI : MADURAI : MADURAI : TAMIL NADU PROJECT PROPONENT Thiru P. Ayyanar

More information

Pre-Feasibility Report for Granite Building stone Quarry

Pre-Feasibility Report for Granite Building stone Quarry Pre-Feasibility Report for Granite Building stone Quarry SURVEY NO. : 53/6 & 53/8-1, 53/8-2 & 53/13 VILLAGE TALUK DISTRICT STATE EXTENT : AYYAMPUZHA : ALUVA : ERNAKULAM : KERALA : 0.9842 HA LAND STATUS

More information

M/s Saurashtra Calcine Bauxite. mining lease for Bauxite

M/s Saurashtra Calcine Bauxite. mining lease for Bauxite CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXECUTIVE SUMMARY 3.0 INTRODUCTION OF THE PROJECT /BACKGROUND INFORMATION 4.0 PROJECT DESCRIPTION 4.0 AVAILABLITY OF RAW MATERIAL 5.0 SELECTION OF SITE & LOCATION

More information

Table 1.1 : Salient features of the project. Sy. No. 379/1, Perecherla Village, Medikonduru Mandal, Guntur District, Andhra Pradesh.

Table 1.1 : Salient features of the project. Sy. No. 379/1, Perecherla Village, Medikonduru Mandal, Guntur District, Andhra Pradesh. 1.0 EXECUTIVESUMMARY 1.1 Introduction Road Metal of M/s. Venkata Ramana Stone Crusher covering an extent of 0.89 Ac is located at Sy.No.379/1 of Perecherla Village, Medikonduru Mandal, Guntur District,

More information

PRE-FEASIBILITY REPORT FOR M/s FIXEM CEMENT PRIVATE LIMITED

PRE-FEASIBILITY REPORT FOR M/s FIXEM CEMENT PRIVATE LIMITED PRE-FEASIBILITY REPORT FOR M/s FIXEM CEMENT PRIVATE LIMITED 1. SUMMARY Kacari Silica Sand,Khanda,Stone And Moram Project at Khsara No.-144,145,146,147, 148,150, 309, 310, 311,312,313,314,315,316,317,318,320,399,403,404,405,

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN OF ALAMPUR THIKARIYA SAND DEPOSIT QUARRY KHASRA NO. 149, TOTAL AREA- 8.0 Hect. (MALENI RIVER) AT VILLAGE- ALAMPUR THIKARIYA, TEHSIL-JAORA, DISTRICT- RATLAM, STATE-MADHYA PRADESH

More information

Table 1-1:- Salient Features of the Project

Table 1-1:- Salient Features of the Project PRE FEASIBILITY REPORT OF LAMBA & BHATIA BAUXITE MINE MINERALS - BAUXITE LAMBA SURVEY. NO. 30/P, 415/A, 949, BHATIA-358 (LEASE PERIOD 14.06.2000 TO 13. 06.2020) LEASE AREA 54.0861 HECTARE MINING PROJECT

More information

Salient features of the Project. S. No. A. Mining Lease Details. iii Mining Lease Number M.L. No 20/2004. iv Mining Lease Area

Salient features of the Project. S. No. A. Mining Lease Details. iii Mining Lease Number M.L. No 20/2004. iv Mining Lease Area PRE FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY This is an existing mine, proposal of obtaining Environmental Clearance with production capacity 196800 TPA Near Village: Modi, Tehsil: Khetri, District: Jhunjhunu.

More information

PRE-FEASIBILITY REPORT FOR M/s FIXEM CEMENT PRIVATE LIMITED

PRE-FEASIBILITY REPORT FOR M/s FIXEM CEMENT PRIVATE LIMITED PRE-FEASIBILITY REPORT FOR M/s FIXEM CEMENT PRIVATE LIMITED 1. SUMMARY Kacari Silica Sand,Khanda,Geeti And Moram Project at Khasra No.-10,11,12,13,101, 102,122, 126, 127,128,129,130,131, 167,568,570,571,572,

More information

INDEX 1 EXECUTIVE SUMMARY INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION PROJECT DESCRIPTION... 9

INDEX 1 EXECUTIVE SUMMARY INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION PROJECT DESCRIPTION... 9 Index INDEX 1 EXECUTIVE SUMMARY... 4 2 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION... 7 2.1 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT... 7 2.2 NEED FOR THE PROJECT & ITS IMPORTANCE TO THE

More information

PRE FEASIBILITY REPORT (PFR)

PRE FEASIBILITY REPORT (PFR) APPLICANT : M/s PLANTERS AGGREGATES 27 PRE FEASIBILITY REPORT (PFR) APPLICANT : M/s PLANTERS AGGREGATES 28 INDEX S. No. Contents Page No. 1.0 EXECUTIVE SUMMARY 30 2.0 INTRODUCTION OF THE PROJECT / BACKGROUND

More information

Shri Hari Dyes & Chemicals Plot No.: 439/1,417, Phase No. II, GIDC Estate, Vatva , Ahmedabad

Shri Hari Dyes & Chemicals Plot No.: 439/1,417, Phase No. II, GIDC Estate, Vatva , Ahmedabad Annexure Prefeasibility Report (PFR) File PRE FEASIBILITY REPORT For PROPOSED EXPANSION IN EXISTING MANUFACTURING PLANT Of Shri Hari Dyes & Chemicals Work & Regd. Office: CONTENTS Sr. No. Description 1.

More information

PREFEASIBILITY REPORT

PREFEASIBILITY REPORT PREFEASIBILITY REPORT For ToR Application of Expansion Project For MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS (Dyes Intermediates) Proposed By: M/s. Plot No. C/1/B-145-3 Phase-II, GIDC Estate, Naroda,

More information

Guralas Masonary Stone Mine Project M.L. No. 139/2008 Lease Area 1.00 Ha Proposed Capacity TPA (ROM) FORM-1M

Guralas Masonary Stone Mine Project M.L. No. 139/2008 Lease Area 1.00 Ha Proposed Capacity TPA (ROM) FORM-1M FORM-1M 1 (I) Basic Information S.No. Item Details 1. Name of the project/s Guralas Masonary Stone Mine ML No. 139/2008 2. S.No. in the schedule 1(a) as per MoEF EIA notification dated 14 th 3. Proposed

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT FOR AMJHAR LATERITE DEPOSIT M. L. Area 4.897 ha. In Village - Amjhar Tehsil - Amarpatan, District- Satna State - Madhya Pradesh Proposed Capacity 32256 TPA Lessee - Shri Vikram Singh

More information

PRE- FEASIBILITY REPORT FOR PROPOSED ORDINARY EARTH EXCAVATION PROJECT (94.59 ARES) of Shri Saji Sebastian, Madeckal House, Kizhakambalam P.

PRE- FEASIBILITY REPORT FOR PROPOSED ORDINARY EARTH EXCAVATION PROJECT (94.59 ARES) of Shri Saji Sebastian, Madeckal House, Kizhakambalam P. PRE- FEASIBILITY REPORT FOR PROPOSED ORDINARY EARTH EXCAVATION PROJECT (94.59 ARES) of Shri Saji Sebastian, Madeckal House, Kizhakambalam P.O, Ernakulam (Dist.) Survey No. 129/1-4,129/2-1, Arakuzha Village,

More information

PRE FEASIBILTY REPORT

PRE FEASIBILTY REPORT PRE FEASIBILTY REPORT FOR ENVIRONMENT CLEARANCE OF PROPOSED NEW PROJECT S. O. CHEMICALS (5 f Category) Proposed By: COREL PHARMA CHEM PVT. LTD. SURVEY NO. 473 & 481, BORISANA, KADI THOL ROAD, KADI, DIST

More information

INDEX S.NO DESCRIPTION PAGE NO. 1. EXECUTIVE SUMMARY 1 2. INTRODUCTION OF THE PROJECT /BACKGROUND INFORMATION 3 3. PROJECT DESCRIPTION 5

INDEX S.NO DESCRIPTION PAGE NO. 1. EXECUTIVE SUMMARY 1 2. INTRODUCTION OF THE PROJECT /BACKGROUND INFORMATION 3 3. PROJECT DESCRIPTION 5 pfr INDEX S.NO DESCRIPTION PAGE NO. 1. EXECUTIVE SUMMARY 1 2. INTRODUCTION OF THE PROJECT /BACKGROUND INFORMATION 3 3. PROJECT DESCRIPTION 5 4. SITE ANALYSIS 15 5. PLANNING BRIEF 18 6. PROPOSED INFRASTRUCTURE

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN OF Shri Krishna Construction Company AT Khasra No.1046 Vill.-Pipalya Hamir, Tehsil-Barod, District-Agar Malwa (M.P.) Production Capacity: 40000 Cu.mt Crusher Stone for 18 Months

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For M/s. Shah Shah Mines & Minerals, SY. NO. 206/1, Gangireddipalli Village, Thamballapalli Mandal, Chittoor District, Andhra Pradesh. INDEX ITEM PAGE NO. 1. EXECUTIVE SUMMARY 3

More information

Grey Granite (Paradiso) Mine

Grey Granite (Paradiso) Mine Grey Granite (Paradiso) Mine PROJECT PROPONENT M/s. Karunai Granites Private Limited., Jagadevipalayam Village & Post, Krishnagiri Taluk, Krishnagiri District 635 203. Extent : 11.59.0 Hectares S.F. No.

More information

SHRI.LAKSHMAN NAMDEV KOLI

SHRI.LAKSHMAN NAMDEV KOLI PRE-FEASIBILITY REPORT (PFR) FOR PROPOSED STONE QUARRY BY SHRI.LAKSHMAN NAMDEV KOLI AREA. 1.00 HA., GAT. NO. 811/2 PART, VILLAGE BASTAWADE, TAL.: TASGAON, DIST.: SANGLI PREPARED BY EQUINOX ENVIRONMENTS

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN VILLAGE - KUNDLA TEHSIL - NAGDA DISTRICT - UJJAIN STATE - MADHYA PRADESH KHASRA NO. - 574 AREA - 8.00 Hectare PRODUCTION - 98800 cu.m/ Year PREPARED UNDER RULE 42 C OF MP MINOR

More information

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION Jaypee Group is a leading Business House of the country with its presence in Core industries and Service Sectors like Cement, Infrastructure development,

More information

Riverbed Sand/Morrum Mining at Gata No. 747/16, Village- Patharehta, Tehsil- Kalpi, District- Jalaun, U.P. Area: 22 Acres (8.

Riverbed Sand/Morrum Mining at Gata No. 747/16, Village- Patharehta, Tehsil- Kalpi, District- Jalaun, U.P. Area: 22 Acres (8. PRE-FEASIBILITY EXECUTIVE SUMMARY Shri Vishwas Parmani S/o Shri H. Parmani is the lessee for the RBM (River Betwa) for an area of 22 Acres (8.90 Ha) in Gata No. 747/16,Village- Patharehta, Tehsil- Kalpi,

More information

CONTENT LIST 3.0 PROJECT DESCRIPTION 7 TYPE OF PROJECT INCLUDING INTERLINKED AND INDEPENDENT PROJECTS, IF ANY

CONTENT LIST 3.0 PROJECT DESCRIPTION 7 TYPE OF PROJECT INCLUDING INTERLINKED AND INDEPENDENT PROJECTS, IF ANY CONTENT LIST S. NO. CONTENTS PAGE NO. 1.0 EXECUTIVE SUMMARY 1 2.0 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION 3 (i) IDENTIFICATION OF PROJECT & PROJECT PROPONENT 3 (ii) BRIEF DESCRIPTION OF NATURE

More information

INDEX 1 EXECUTIVE SUMMARY INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION PROJECT DESCRIPTION... 32

INDEX 1 EXECUTIVE SUMMARY INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION PROJECT DESCRIPTION... 32 M.L. Area- 4.0580ha., Near Village- Indawar, Tehsil Merta, District - Nagaur (Raj.) Index INDEX 1 EXECUTIVE SUMMARY... 28 2 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION... 30 2.1 IDENTIFICATION

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN ENVIRONMENT MANAGEMENT PLAN FOR VILLAGE TEHSIL DISTRICT AREA MINERAL : Pathari Basouda : Basouda : Vidisha (M.P.) : 2.00 Hectare : Stone KHASRA No : 177/1/2 PRODUCTION CAP : 10000 Cu.mt/year Stone APPLICANT

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project Of MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS of 850 MT/Month By PASHUPATI INDUSTRIES 169/1/A2, Phase 1, Opposite Telephone Exchange, GIDC Naroda, Ahmedabad-382330

More information

Environment Consultant:

Environment Consultant: MODERNIZATION CUM EXPANSION OF INDUCTION FURNACE PRODUCTION(2,05,000 TPA TO 6,00,000 TPA) AND ROLLING MILL PRODUCTION (3, 69,000 TPA TO 6,00,000 TPA) at Sy. No. 158 (part) 159 (part), 166 170, village

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT FOR STONE QUARRY - 3.40 ha VILLAGE - MARSUL T. SENDURSENA, TALUKA VASMAT DISTRICT HINGOLI MR. ASHISH ASHOK KASAT ENVIRO TECHNO CONSULT PVT.LTD. 68, MAHAKALI NAGAR MANEWADA HINGOLI