Detour Lake Gold Mine Project Follow-up Program

Size: px
Start display at page:

Download "Detour Lake Gold Mine Project Follow-up Program"

Transcription

1 Detour Lake Gold Mine Project Follow-up Program Last revised: June 2014

2 CONTENTS 1 Context Purpose of the Detour Lake Gold Mine Follow-up Program Ensuring Implementation of the Follow-up Program Follow-up Program Duration Decision Making Site Visits Evaluating Follow-up Program Success Follow-up Program Modifications Roles and Responsibilities in the Follow-up Program Proponent: Detour Gold Corporation Responsible Authorities: Natural Resources Canada and Fisheries and Oceans Canada Federal Authorities: Environment Canada and Health Canada Participation in the Follow-up Program Participation of Aboriginal Groups Participation of Ontario Ministries Follow-up Program Local Water Courses, Lakes and Wetlands: Water Quality; Fish and Fish Habitat Local Water Courses, Lakes and Wetlands: Watercourse Flows and Water Levels; Fish Habitat Local Water Courses, Lakes and Wetlands: Sediment Quality Groundwater System: Water Quality and Quantity Terrestrial Environment: Migratory Birds Species-at-Risk: Caribou Resource Harvesting (Country Foods): Local Fish Resource Harvesting (Country Foods): Wildlife and Plants (Caribou, Moose and Beaver) Land and Resource Use: Reclamation Air Quality, Noise and Greenhouse Gases Public Health and Safety: Road Traffic List of Abbreviations References

3 1 CONTEXT Detour Gold Corporation ( DGC ) is in the process of developing and operating a 61,200 tonnes per day open pit gold mine known as the Detour Lake Mine Project ( Project ). The Project is anticipated to have a minimum mine life of 16 years and is located approximately 185 km northeast of the town of Cochrane in a remote area of northern Ontario. The Project consists of an open pit mine, an ore processing plant, tailings and waste rock storage facilities. It also includes site access roads, power transmission lines, an explosives factory and storage areas, water management facilities, ancillary mine infrastructure, and associated activities. Pursuant to provisions under the Canadian Environmental Assessment Act, 1992 ( former CEAA ), the Project was subject to a comprehensive study environmental assessment ( EA ). A comprehensive study report 1 ( CSR ) was prepared by the Canadian Environmental Assessment Agency ( CEA Agency ) in November 2011 describing the EA process and the predicted potential environmental effects, proposed mitigation measures, determination of significance of environmental effects and a Follow-up Program Framework ( FUPF ) for the Project. The Project also underwent a number of EAs under Ontario s Environmental Assessment Act. In accordance with the Canada Ontario Agreement on Environmental Assessment Cooperation, cooperative EA processes involving both jurisdictions were conducted. In December 2011, when taking into account mitigation measures and the implementation of the FUPF described in the CSR 2, the federal Minister of the Environment determined that the Project was not likely to result in significant environmental effects. Under section 37 of the former CEAA, the Project was then referred back to Responsible Authorities ( RAs ), Natural Resources Canada ( NRCan ) and Fisheries and Oceans Canada ( DFO ), who then took a course of action decision in relation to the Project. Under the former CEAA, NRCan and DFO are required to ensure the implementation of mitigation measures and the design and implementation of a FUP for the Project to verify the accuracy of the predictions contained in the CSR. 2 PURPOSE OF THE DETOUR LAKE GOLD MINE FOLLOW-UP PROGRAM The former CEAA defines a FUP as a tool to: (1) verify the accuracy of the EA of a project; and, (2) determine the effectiveness of any measures taken to mitigate adverse environmental effects. The former CEAA also provides that the results of a FUP may be used for implementing adaptive management measures or for improving the quality of future EAs. Adaptive management is defined as a: planned and systematic process for continuously improving environmental management practices by learning about their outcomes. Adaptive management provides the flexibility to identify and implement new mitigation measures or to modify existing ones during the life of a project 3. The CSR provided a framework for the components to be included in the Project FUP and a number of environmental commitments made by DGC to implement mitigation measures, including a commitment to undertake the FUP, as set out in the October 11, 2011 letter to the CEA Agency 4. The implementation of the FUP will verify the predictions of the CSR, prepared in accordance with the former CEAA. Should any unanticipated potentially significant adverse environmental effects be identified, section 6 of this FUP outlines adaptive management measures to mitigate those effects to ensure they do not become significant. This FUP document is intended to provide a cooperative plan between RAs, FAs and DGC to ensure its communication, review and implementation. It provides measures to ensure the implementation of the FUP, a description of the roles and responsibilities of DGC, RAs and FAs in the FUP, the participation of involved Ontario ministries and Aboriginal groups in the FUP as well as specific details of the program in relation to the Valued Ecosystem Components ( VECs ) and Valued Socioeconomic Components ( VSECs ) that fall under the scope of this FUP. 1 Canadian Environmental Assessment Agency. (November 2011). Comprehensive Study Report Detour Lake Gold Mine, (Ottawa: Minister of Public Works and Government Services Canada, 2011). 2 Ibid., pp Adaptive under the Canadian Environmental Assessment Act, Operational Policy Statement, Canadian Environmental Assessment Agency, Ibid. 1, pp

4 3 ENSURING IMPLEMENTATION OF THE FOLLOW-UP PROGRAM 3.1 Follow-up Program Duration The FUP is set to begin following the submission of the first Annual FUP Report in June The FUP duration will depend on the individual VECs and VSECs identified in the FUP and will be reviewed and adjusted accordingly based on the mine life, including potential Project changes such as an increase in its duration or the early cessation of mining activities; and, considerations for decommissioning, reclamation and post-closure activities. In general, any of the elements of the postconstruction monitoring program described in Section 6 of the FUP may be extended, altered or added to if unanticipated potentially significant adverse environmental effects are confirmed and additional study is deemed necessary by the RAs. Each element of the post-construction monitoring program will be considered independently, and will also be reviewed as a whole, which includes cross-analysis of survey results. Nevertheless, extension of one survey type to an additional year does not imply the entire program will be extended. In other cases, where impacts are continually at or below the levels predicted in the CSR, an aspect of the program may be shortened or revised accordingly in these select areas. Proposals to extend or shorten aspects of the FUP are to be presented in the Annual FUP reports so they can be considered during the 90 day review period of the report. 3.2 Decision Making NRCan and DFO are responsible for ensuring the implementation of the FUP as per subsection 38(1) of the former CEAA and, as appropriate, will consult with federal and provincial authorities as well as involved Aboriginal groups, and will determine whether DGC has implemented the FUP as described in this document. 3.3 Site Visits To ensure implementation of the FUP, NRCan and DFO will mainly rely on inspection, compliance and monitoring reporting mandated by applicable federal and provincial legislative and regulatory instruments and summarized in the Annual FUP Report. If necessary, involved federal authorities will conduct site visits and/or review detailed federal and provincial reporting requirements to ensure implementation of the FUP. 3.4 Evaluating Follow-up Program Success The success of the FUP is dependent on the following considerations: EA predictions are being accomplished throughout the life of the project based on the mitigation measures that are put in place by DGC and set out for the 11 VEC and VSEC described in section 6 of the FUP; In situations where the criteria for considering adaptive management described in the FUP are being achieved, potential actions are being undertaken by DGC. These are outlined in section 4 of the FUP, and in more detail for each VEC and VSEC in section 6. In all cases where potential adaptive management measures are to be implemented, DGC must ensure that it has obtained the necessary federal and/or provincial approvals prior to adopting these measures. The yearly review of the Annual FUP Report is providing interested parties with the opportunity to assess whether the criteria for considering adaptive management by DGC have been achieved and to make recommendations to DGC, including on adaptive management. 3.5 Follow-up Program Modifications The FUP and adaptive management measures may require amendment or updates during the life of the Project to address changes in environmental conditions as a result of observed effects on the environment and/or modified based on new science, future federal and provincial permits, licenses, authorizations and/or approvals. To that effect, the FUP will be reviewed every five years by DFO and NRCan in collaboration with Federal Authorities ( FAs ) and DGC. As part of consultation on the FUP modifications, DFO and NRCan will also engage involved Ontario ministries and Aboriginal groups. It is anticipated that through the yearly reporting being submitted by DGC, NRCan and DFO will consider the comments submitted on the yearly reporting and identify whether changes are required prior to the 5-year review process. Any changes to the FUP will be communicated directly with those involved, as described in section 4 of this FUP. 4

5 4 ROLES AND RESPONSIBILITIES IN THE FOLLOW-UP PROGRAM 4.1 Proponent: Detour Gold Corporation As the proponent of the Project, DGC has been delegated aspects of the design and implementation of the FUP by the RAs, pursuant to s.17 of the former CEAA. The design and implementation of the FUP must be done to the satisfaction of the RAs and, if necessary, DGC will be responsible for implementing adaptive management measures and/or mitigation measures described in the FUP. To ensure implementation of the FUP, DGC is responsible for preparing and distributing not later than June 30 of each year an Annual FUP Report to the RAs. A copy of the full report shall also be distributed to FAs and Ontario ministries and Aboriginal groups described in this section. To facilitate access of the FUP to the public, a summary of the FUP will be made available for download through the DGC website. At a minimum, the Annual FUP Report will include the following information: 1. Plain language executive summary that provides a general background and summary of the Annual FUP Report s findings. In the executive summary, DGC is asked to provide an overview of how the FUP is successful based on considerations in section 3.4; 2. Rolling summary of project activities that includes the mine operations facilities and activities, major components for the mine and associated infrastructure and related information regarding permitting; 3. Summary of monitoring results, including illustration of trends, in relation to the FUP. In the monitoring results summary, DGC will specify requirements of monitoring such as part of federal/provincial regulatory approval/conditions as well commitments outlined by DGC in the CSR. This section will constitute the main body of the report and should provide an overview of the various monitoring programs, their results and interpretations for each of the 11 VECs and VSECs that fall under the scope of the FUP; 4. Summary of all supporting information, data and results from the FUP, and all studies and research. This includes references to where more details can be found validating the results and trends illustrated in the Annual FUP Report, including a summary of study and research programs which go beyond those specifically required by permits, where applicable; 5. Summary of all compliance reports required by the Project s regulatory instruments applicable for the reporting period; 6. Actions taken or planned to address environmental effects or compliance problems which are set out in the Annual FUP; 7. Comparison of the project effects to those predicted in the EA. This section should provide an overview of how the Project has performed, in an environmental capacity, relative to expectations defined through the federal EA process and related permitting; 8. Determination of effectiveness of mitigation measures at avoiding environmental effects designed to protect the environment; 9. Summary and evaluation of all Adaptive Environmental measures; 10. Rationale for and summary of new technologies investigated to reduce and/or avoid environmental effects that considers new environmental monitoring or mitigation technologies investigated during the reporting period; 11. Summary of Aboriginal, government and public concerns related to environmental effects and responses to those concerns. This section should also include a summary of comments received on the last iteration of the Annual FUP Report and how DGC resolved these comments. Upon receipt of the Annual FUP Report and no later than 90 days after its receipt, comments will be submitted directly to DGC. Comments on the Annual FUP Report shall be submitted to DGC, and if applicable, copied to NRCan and DFO. DGC will then work directly with those involved in addressing the comments and issues that arise. A summary of the comments received and how they were addressed should be included in the next iteration of the Annual FUP Report by DGC. Finally, in situations where the criteria for accepting the EA predictions described in section 6 of the FUP are not being achieved, the following actions will be considered and initiated by DGC, as necessary: 1) If possible, take immediate action (i.e. short term approaches) to correct problems. Include a discussion of the actions taken, their effectiveness and lessons learned. 2) Where immediate action is not suitable, the proponent will submit proposal for adaptive management: 5

6 a. Relevant federal departments to review and approve adaptive management approach, as appropriate. DGC will make best efforts to involve Aboriginal groups in the review and approval of proposed adaptive management approaches, where possible; b. Proponent to implement adaptive management, including monitoring protocol; c. Proponent to submit interim monitoring to verify effectiveness of adaptive management. 4.2 Responsible Authorities: Natural Resources Canada and Fisheries and Oceans Canada As the RAs for the Project, NRCan and DFO are responsible for the design of the FUP and to ensure it is implemented. Following the receipt of the Annual FUP Report from DGC, the RAs will review and provide comments to DGC in aspects which involve their mandates and interests no later than 90 days after receipt of the report. The RAs will draw on the expertise of the Federal Authorities to ensure the FUP s implementation, and if applicable, may also draw on the expertise of Ontario ministries, as described in sections 4.3 and 5.2 of the FUP, respectively. At any time, concerns associated with the implementation of the FUP can be brought to NRCan and DFO s attention. Should issues arise during the implementation of the program, NRCan and DFO may, at their discretion, coordinate and facilitate issue resolution to the extent possible. NRCan is responsible for including a description of how the program and its results may be obtained on the Canadian Environmental Assessment Registry Internet Site. 4.3 Federal Authorities: Environment Canada and Health Canada Following the receipt of the Annual FUP Report from DGC, the FAs, Environment Canada (EC) and Health Canada (HC), will assist in the review of the document and provide advice with respect to aspects which involve their mandates and interests. If warranted, comments on the Annual FUP Report shall be submitted to DGC, copied to NRCan and DFO no later than 90 days after receipt of the report. EC will be responsible for providing, on request, to NRCan and DFO specialist or expert information or knowledge in its possession. EC will also be responsible for providing any assistance requested by NRCan and DFO concerning the implementation of the FUP on which NRCan, DFO and EC have agreed. EC s jurisdictional responsibilities in the context of the DGC project relate to the protection of: Migratory birds and species at risk as mandated by the Migratory Birds Convention Act, 1994, and the Species at Risk Act (SARA), respectively; and, Water quality in context of the pollution prevention provisions of the Fisheries Act, including the Metal Mining Effluent Regulations. HC does not have jurisdictional responsibilities in the context of the DGC. However, upon receiving a request from the RAs, HC may assist in reviewing the objectives, design and results of monitoring studies, and may provide advice on proposed adaptive management measures in the follow-up when the monitoring results demonstrate that the environmental effects differ from predictions. 6

7 5 PARTICIPATION IN THE FOLLOW-UP PROGRAM 5.1 Participation of Aboriginal Groups In this FUP, Aboriginal Groups refer to the First Nations and Métis groups who participated in the consultation activities during the federal EA process, including the Moose Cree First Nation ( MCFN ), Taykwa Tagamou Nation ( TTN ), Wahgoshig First Nation ( WFN ), Timmins Métis and Northern Lights Métis Community Councils as represented by the Métis Nation of Ontario ( MNO ), and Waskaganish First Nation ( Waskaganish ). Each will receive a copy of the Annual FUP Report from DGC and may submit their comments to DGC no later than 90 days following receipt of the report, if applicable. At any time, Aboriginal groups can bring to NRCan and DFO s attention any concerns associated with the implementation of the FUP. 5.2 Participation of Ontario Ministries In this FUP, Ontario Ministries refers to the Ministry of the Environment (MOE), Ministry of Natural Resources (MNR), Ministry of Northern Development and Mines (MNDM). Each ministry will receive a copy of the Annual FUP Report. NRCan and DFO may draw on the expertise of provincial ministries by inviting the ministries, in writing, for advisory or technical support for matters relating to the respective ministries area of provincial responsibility, as appropriate. If applicable, the provincial ministries may provide comments on the Annual FUP Report; these shall be submitted to NRCan no later than 90 days following receipt of the report. At any time, Ontario ministries can bring to NRCan and DFO s attention any concerns associated with the implementation of the FUP. 7

8 6 FOLLOW-UP PROGRAM As described in the Project CSR, the elements included in the FUP were determined through consideration of the following factors, including: the potential residual adverse effects; the extent to which public and Aboriginal group concerns were raised during the federal and provincial EAs, including comments raised by the participant funding recipients; areas of federal interest; whether provincial approvals, permits or plans do include, or are reasonably predicted to include, monitoring and followup requirements; whether provincial and federal regulatory instruments exist to help ensure the effectiveness of mitigation measures; and, the extent to which mitigation measures are innovative in their approach as opposed to being common and well understood, or where the effectiveness of the proposed mitigation is difficult to predict with a high degree of certainty. Based on the CSR FUPF, the FUP includes the implementation of mitigation measures and adaptive management measures for the following VECs and VSECs: 6.1 Local Water Courses, Lakes and Wetlands: Water Quality; Fish and Fish Habitat; 6.2 Local Water Courses, Lakes and Wetlands: Watercourse Flows and Water Levels; Fish & Fish Habitat; 6.3 Local Water Courses, Lakes and Wetlands: Sediment Quality; 6.4 Groundwater system: Water quality and quantity; 6.5 Terrestrial Environment: Migratory Birds; 6.6 Species-at-risk: Caribou; 6.7 Resource Harvesting (Country Foods): Local Fish; 6.8 Resource Harvesting (Country Foods): Wildlife & Plants; 6.9 Reclamation: Land and Resource Use. At a minimum, the FUP should cover the VECs and VSECs, identified above. The following additional VECs and VSEC were included in the FUP by the RAs in consultation with DGC only as they relate to the Project s environmental effects: 6.10 Air Quality; 6.11 Public Health and Safety: Road Traffic. 8

9 6.1 Local Water Courses, Lakes and Wetlands: Water Quality; Fish and Fish Habitat Valued Ecosystem Component Aspect EA Prediction Rationale for Inclusion in FUP: Potential Residual Effect or Concern Verification / Assessment Methods Current Mitigation Local Water Courses, Lakes and Wetlands Water Quality; Fish and Fish Habitat (aspect of Project CSR FUPF) Effluent discharges expected to meet applicable regulatory thresholds defined through legislation, or site-specific permits and approvals; Receiving water quality expected to meet background conditions, or applicable criteria for the protection of aquatic life criteria; Effluent discharges will not compromise fish habitat. Tailings Impoundment Areas (TIA) discharge may adversely affect East Creek / Sunday Creek system water quality; Stockpile runoff and seepage may adversely affect receiving water quality; Potentially acid generating (PAG) waste rock may adversely affect water quality via acid rock drainage (ARD). Stormwater runoff / seepage from other Project components (including snowmelt) may adversely affect receiving water quality; Non-regulated discharges from transmission line construction & operations, including spills may adversely affect receiving water quality; Airborne emissions may adversely affect receiving water quality; Potable water quality may be impaired. Regular water quality sampling, analysis and data interpretation as dictated by legislation, or applicable site specific permits and approvals. This includes water quality monitoring of stockpile runoff and seepage to ensure acceptable quality for direct discharge to local watercourses after settling pond treatment; As an upstream, early warning indicator, regularly monitor and report on the effectiveness of the in-plant cyanide destruction and heavy metals precipitation system (e.g. monthly grab sampling for free cyanide and dissolved copper, lead, and cadmium of the TMA effluent); Development and implementation of a waste rock management plan (WRMP) with annual reporting that includes any recommended adaptive management measures needed to prevent and/or mitigate ARD. In-plant destruction of cyanide, and precipitation of heavy metals; TIA water management and recycle measures; TIA seepage collection, containment and/or treatment; Stockpile runoff and seepage collection, containment and/or treatment; Mine operations area runoff and seepage collection, containment and/or treatment; 9

10 General sediment and erosion control measures; 120 m vegetated mine site buffer zone bordering watercourses (excluding seepage collection system footprints); Waste rock management program to segregate PAG materials to the extent practicable, remaining PAG materials to be blended; Dust suppression; Construction restrictions at or near creek crossings; Routine inspection of construction areas near watercourses; Water treatment plant(s) for potable water; Water quality management to protect fish habitat as per the MMER. Criteria for Considering Adaptive Potential Adaptive Applicable Regulatory Instrument(s)/ Departments involved in FUP Effluent (seepage and surface water) discharges exceed applicable regulatory thresholds defined through legislation, or site specific permits and approvals; and/or, Receiving water quality exceeds background conditions, or applicable criteria for the protection of aquatic life. Further optimize efficiencies of in-plant effluent treatment; Further optimize TIA water management and recycle; Further optimize runoff and seepage collection system efficiencies; Divert portions of runoff and seepage effluent that are of concern to the TIA; Further optimize dust suppression efficiencies; Refine and optimize waste rock management plan to reduce potential for ARD; Further optimize water quality management. MMER; MOE ECA or CofA; MNDM Closure Plan; 10

11 Responsibilities In the Annual FUP Report, DGC will provide a summary of follow-up and monitoring information as outlined in the verification / assessment methods. DGC is also responsible for implementing mitigation measures and, if necessary, potential adaptive management measures described above. The Annual FUP Report prepared by DGC will also include relevant summary information regarding submissions and project performance to demonstrate the effectiveness of mitigation in relation to: EC s MMER requirements, including EEM data; MOE ECA or CofA permits/ approvals and submissions from DGC; and, MNDM s Closure Plan implementation, required under the Ontario Mining Act. This includes results from the waste rock management and tailings monitoring programs that are included as part of the annual closure report. 11

12 6.2 Local Water Courses, Lakes and Wetlands: Watercourse Flows and Water Levels; Fish Habitat Valued Ecosystem Component Aspect EA Prediction Rationale for Inclusion in FUP: Potential Residual Effect or Concern Verification / Assessment Methods Local Water Courses, Lakes and Wetlands Watercourse Flows and Water Levels; Fish and Fish Habitat (aspect of Project CSR FUPF) Dewatering of the open pit is expected to reduce Karel Creek and Linden Creek flows by 830 m 3 /d and 300 m 3 /d, respectively (base case), with a more conservative (but less likely) flow reduction estimate for Karel Creek of 2,160 m 3 /d; fish habitat compensation to be provided; Pit dewatering induced flow reductions expected to occur in close proximity to the open pit based on modeling of the 1 m groundwater drawdown isopleths; Interception of stockpile runoff and seepage not expected to have a significant adverse effect on fish habitat; Fish habitat associated with development of the TIA and MRS #2 to be completely displaced; fish habitat compensation to be provided; Water takings from local watercourses will not adversely affect watercourse flows or levels, to the extent that fish habitat would be significantly affected; Fish habitat compensation measures will function as intended. Dewatering of the open pit has the potential to reduce watercourse flows and/or watercourse (or lake) water levels, and affect associated fish habitat beyond those predicted by modeling during the EA processes; Interception of stockpile runoff and seepage may reduce receiving water flows, and associated fish habitat, beyond that predicted in the EAs, if it is necessary to divert stockpile runoff and seepage (other than that associated with MRS #1) to the TIA for further water quality treatment; Water takings from local watercourses beyond those provided for in the EA have the potential to reduce downstream water flows (or levels) such that unanticipated fish habitat effects could potentially occur; Redirection of a portion of Karel Creek flows (during high water conditions) to accelerate open pit flooding at mine closure could potentially affect fish habitat; Fish habitat compensation measures may not function as proposed. Periodic re-running of the open pit groundwater model at two year intervals during the first five years of pit dewatering, and periodically thereafter as determined by provincial approvals; Conduct groundwater modeling; Site area surface water flow and level monitoring ; Conduct statistical analyses of flow monitoring data as appropriate to the data to determine monthly and annual average flows, and return period statistics for extreme flows; 12

13 EEM requirements under MMER and monitoring consistent with provincial approvals; Periodic visual inspection of watercourse flows, water levels and habitat conditions; Consistency with DFO Letters of Advice and Fisheries Act Authorizations, including any reporting requirement terms and conditions therein; Annual assessment of compensatory fish habitat function during the first three years following installation, and periodic assessment thereafter consistent with provincial permitting and EEM requirements. Current Mitigation Criteria for Considering Adaptive Potential Adaptive Applicable Regulatory Instrument(s) Responsibilities Fish habitat compensation is being provided for anticipated flow-induced fish habitat losses to Karel Creek linked to open pit dewatering; Fish habitat compensation is being provided for the direct displacement of fish habitat resulting from development of the TIA and MRS #2. Follow-up groundwater modeling and field monitoring exceeds predicted open pit dewatering flow reduction effects on Karel Creek and Linden Creek; Water flows and /or levels are affected by water takings from local watercourses beyond levels predicted in the CSR; Fish habitat compensation measures are not functioning as intended. Provide additional fish habitat compensation plan for approval by DFO; If water levels drop below thresholds required for fish passage, line that portion of Karel Creek which is closest to the open pit, to allow for continued, seasonal fish passage between upstream and downstream portions of the creek, as per normal fish movement cycles; If water levels drop below thresholds required for fish passage, provide flow supplementation from nearby, unaffected water sources, including possible groundwater sources; Relocate affected watercourses further from the open pit area of dewatering influence, if water levels drop below thresholds required for fish passage; Redirect a portion of Karel Creek flows to the open pit at mine closure, if it can occur without adversely affecting Karel Creek fish habitat functions. DFO Fisheries Act Authorizations and Letters of Advice; MMER; MOE PTTW and ECA (or CofA); MNDM Closure Plan. In the Annual FUP Report, DGC will provide a summary of follow-up and monitoring information as outlined in the verification / assessment methods. DGC is also responsible for implementing mitigation measures and, if necessary, potential adaptive management measures described above. The Annual FUP Report prepared by DGC will also include relevant summary information regarding submissions and project performance in relation to: 13

14 EC s MMER requirements as well as EEM data (effluent criteria and water quantity/quality); DFO s fish habitat functions requirements; MOE PTTW and ECA requirements; and MNDM s Closure Plan implementation, required under the Ontario Mining Act. 14

15 6.3 Local Water Courses, Lakes and Wetlands: Sediment Quality Aspect EA Prediction Rationale for Inclusion in FUP: Potential Residual Effect or Concern Verification / Assessment Methods Current Mitigation Criteria for Considering Adaptive Potential Adaptive Valued Ecosystem Component Local Water Courses, Lakes and Wetlands Sediment Quality (aspect of Project CSR FUPF) No explicit sediment quality predictions stated through the EA process; Implied that receiving water sediment quality would not be adversely affected as receiving water quality expected to meet background conditions, or applicable criteria for the protection of aquatic life. Sediments in waters downstream of the TIA could be further impacted by TIA effluent discharges associated with Project effluents; Sediments in waters downstream of other Project components such as mineral stockpiles could potentially be affected by runoff and seepage releases, as well as by airborne dust. EC s MMER EEM and MOE s ECA monitoring programs include sediment and benthos sampling and reporting. Annual sediment sampling in the on-site collection ponds downstream of MRS #1. Water quality treatment and management as described in FUP table 6.1; Receiving water quality exceeds background conditions, or applicable criteria for the protection of aquatic life criteria; Sediment sampling shows a significant increase in metals concentrations beyond current background conditions; Further optimize water quality treatment and management as described in the FUP table 6.1; Develop further measures derived from the study of waters downstream of the TIA as provided for in the provincial ECA; Changes to effluent, runoff and seepage discharge locations and arrangements to reduce chances of sediment re-suspension; Further optimize dust suppression efficiencies. Applicable Regulatory Instrument(s) MMER EEM; MOE ECA; MNDM Closure Plan. 15

16 Responsibilities In the Annual Follow-up Report, DGC will provide a summary of follow-up and monitoring information as outlined in the verification / assessment methods. DGC is also responsible for implementing mitigation measures and, if necessary, potential adaptive management measures described above. The Annual FUP Report prepared by DGC will also include relevant summary information regarding submissions and project performance in relation to: EC s MMER requirements as well as EEM data; MOE ECA requirements; and MNDM s Closure Plan implementation, required under the Ontario Mining Act. 16

17 6.4 Groundwater System: Water Quality and Quantity Aspect EA Prediction Rationale for Inclusion in FUP: Potential Residual Effect or Concern Verification / Assessment Methods Current Mitigation Criteria for Considering Adaptive Valued Ecosystem Component Groundwater System Water Quality and Quantity (aspect of Project CSR FUPF) Open pit dewatering expected to reduce Karel Creek and Linden Creek flows by 830 m 3 /d and 300 m 3 /d, respectively (base case), with a more conservative (but less likely) flow reduction estimate for Karel Creek of 2,160 m 3 /d; fish habitat compensation to be provided; Pit dewatering induced flow reductions expected to occur in close proximity to the open pit based on modeling of the 1 m groundwater drawdown isopleths; Except as described below, precipitation entering mine rock and overburden stockpiles, after intersecting native ground, is expected to flow mainly in a lateral gradient, thereby directing seepage to the perimeter runoff and seepage collection facilities; A substantial portion of seepage from portions of MRS#1 located near to the open pit expected to drain subsurface to the open pit because of pit-induced dewatering gradients (mine water is to be pumped to the TIA); Runoff and seepage collection systems expected to intercept runoff and seepage such that the groundwater system does not become contaminated. Dewatering of the open pit has the potential to reduce watercourse flows, and/or watercourse (or lake) water levels, and associated fish habitat, beyond those predicted by modeling during the EA process; Seepage from the TIA and MRS has the potential to contaminate the local groundwater system. Periodic re-running of the open pit groundwater model at two year intervals during the first five years of pit dewatering, and periodically thereafter as determined by provincial approvals; MMER and open pit dewatering PTTW monitoring as per regulation and permit conditions; Undertake annual detailed water quality survey of runoff and seepage collection systems related to the TIA and MRS, during summer low flow conditions, with sampling intervals spaced at approximately 250 m, and with sampling to be conducted for a set of key parameters (ph, hardness, sulphate, copper, iron, lead, nickel, zinc, and weak acid total cyanide for TIA samples). Fish habitat compensation for potential adverse dewatering effects on Karel Creek and Linden Creek; TIA seepage collection; Stockpile runoff (MRS and low grade ore) and seepage collection. Follow-up groundwater modeling exceeds predicted open pit dewatering flow reduction effects on Karel Creek and Linden Creek; Groundwater shows signs of contamination outside of the Mine Operation Area as defined under MMER and delineated in the CSR. 17

18 Potential Adaptive Applicable Regulatory Instrument(s) Responsibilities Potential adaptive management measures applicable to maintaining fish habitat as per the FUP table 6.2; Further optimize runoff and seepage collection system efficiencies; Installation of additional monitoring wells. MMER; MOE PTTW; MNDM Closure Plan. In the Annual FUP Report, DGC will provide a summary of follow-up and monitoring information as outlined in the verification / assessment methods. DGC is also responsible for implementing mitigation measures and, if necessary, potential adaptive management measures described above. The Annual FUP Report prepared by DGC will also include relevant summary information regarding submissions and project performance in relation to: EC s MMER requirements and EEM data; DFO s fish habitat functions requirements; MOE PTTW requirements; and MNDM s Closure Plan implementation, required under the Ontario Mining Act. 18

19 6.5 Terrestrial Environment: Migratory Birds Valued Ecosystem Component Aspect EA Prediction Rationale for Inclusion in FUP: Potential Residual Effect or Concern Verification / Assessment Methods Current Mitigation Terrestrial Environment Migratory Birds (aspect of Project CSR FUPF) Mine site development will displace approximately 19.4 km 2 of previously undisturbed forest habitat; Transmission line development will displace a further approximately 3.26 km 2 of undisturbed forest habitat; Ground cover will be retained during construction of the transmission line; Riparian habitats bordering watercourses and lakes will be left largely intact, with the exception of lands taken up by runoff and seepage collection facilities; Noise propagation is such that 30 dba approximate sound levels are expected to be attained at the outer boundary of a 5 to 10 km buffer zone around the Project site; Site reclamation at closure will provide habitats suitable for a variety of migratory birds and other wildlife; Toxicity related to tailings ponds will not likely be a concern, as cyanide concentrations in the tailings ponds are expected to be less than 1 mg/l, well below any toxicity threshold; cyanide concentrations of less than 50 mg/l are considered safe for wildlife (Donato et al., 2007). Mine development has the potential to displace a greater area of migratory bird habitat than predicted during the EA process; Noise from site operations beyond that considered during the EA process has the potential to cause additional disturbance to breeding migratory birds, and potentially to interfere with the hunting success of owl species (a few of which are migratory). Periodic satellite imagery of the Project mine site area to confirm the physical displacement of previously undeveloped forest habitat; As-built dimensions of the transmission line right-of-way; Monitor avian species-at-risk at four year intervals, starting in 2013; Noise surveys to be conducted in summer and winter starting one year following commercial production, and at two-year intervals thereafter, to confirm noise model predictions; noise to be measured at representative stations positioned at 5 km and 10 km from the Project site centroid in each of the four cardinal directions, as limited by access; Monitoring of success of post-closure revegetation at the beginning and end of each growing season for post-closure years one through three; and annually for post-closure years four through ten; and at five-year intervals thereafter for an additional period of fifteen years. The MNDM Notice of Project Status will confirm the commencement of closure activities. Mine site developed as much as possible on previously disturbed areas, and in as compact an arrangement as practicable to limit disturbance to new habitat and to limit noise propagation; 19

20 Retain ground cover along transmission line by utilizing winter road access for primary construction; Maintain to the extent practicable, a 120 m mine site buffer zone adjacent to watercourses and lakes; Restore disturbed habitats at mine closure to habitats capable of supporting a diversity of wildlife species, including an emphasis on the development of Common Nighthawk habitat; Avoid tree clearing and land disturbance during the bird nesting season; Avoid disturbance to raptor nest sites; Pre-treat the mill effluent discharge to prevent wildlife toxicity. Criteria for Considering Adaptive Potential Adaptive Applicable Regulatory Instrument(s) Responsibilities Mine site and transmission line development displace larger than anticipated quantity (area) of previously undeveloped forest habitat; Ground cover not retained along transmission line right-of-way; Riparian habitats are impacted beyond boundaries predicted in the CSR; Noise propagation is such that 30 dba approximate sound levels are not expected to be attained at the outer boundary of a 5 to 10 km buffer zone around the Project site; Site reclamation at closure does not provide habitats suitable for a variety of migratory birds and other wildlife. Undertake trial test work to determine optimal site revegetation approaches for reclamation; Improve noise mitigation if and as required; EC Migratory Birds Convention Act, 1994; EC s SARA; MOE ECA Air (possibly); MNDM Closure Plan requirements. In the Annual FUP Report, DGC will provide a summary of follow-up and monitoring information as outlined in the verification / assessment methods. DGC is also responsible for implementing mitigation measures and, if necessary, potential adaptive management measures described above. The Annual FUP Report prepared by DGC will also include relevant summary information regarding submissions and project performance in relation to: EC s SARA and Migratory Birds Convention Act, 1994 requirements; MOE ECA requirements, if applicable; and MNDM s Closure Plan implementation, required under the Ontario Mining Act. 20

21 6.6 Species-at-Risk: Caribou Valued Ecosystem Component Aspect EA Prediction Rationale for Inclusion in FUP: Potential Residual Effect or Concern Verification / Assessment Methods Species-at-Risk (aspect of CSR FUPF) Caribou (aspect of Project CSR FUPF) Mine site development will displace approximately 19.4 km 2 of previously undisturbed forest habitat, including approximately 5.6 km 2 of Black Spruce Jack Pine forest which provides favoured late winter habitat for Caribou; Transmission line development will displace a further approximately 3.26 km 2 of undisturbed forest habitat; Caribou may avoid or show diminished use of, habitats within 5 to 10 km of the principal Project mine site area; Noise propagation is such that 30 dba approximate sound levels are expected to be attained at the outer boundary of a 5 to 10 km buffer zone around the Project site; Site reclamation at closure to provide habitats suitable for Caribou, with an emphasis on patchy lichen habitats to be developed on MRS (pending site trial success). Mine related noise emissions and other disturbances have the potential to displace Woodland Caribou to a greater extent than predicted during the EA process; Habitats developed for Caribou at closure are not utilized to the extent expected. Periodic satellite imagery of the Project mine site area to confirm the physical displacement of previously undeveloped forest habitat; As-built dimensions of the transmission line right-of-way; Early and late winter aerial helicopter surveys of Caribou (as well as Moose and Wolves), with such survey to be conducted annually through to the first two years of mine operations, and biannually (every two years) thereafter until the end of active mine closure; Possibly provide support to MNR s Caribou radio-telemetry program; Noise surveys to be conducted in summer and winter starting one year following commercial production, and at two-year intervals thereafter, to confirm noise model predictions; noise to be measured at representative stations positioned at 5 km and 10 km from the Project site centroid in each of the four cardinal directions, as limited by access; Monitor success of post-closure revegetation at the beginning and end of each growing season for post-closure years one through three, and annually for post-closure years four through ten; and at five-year intervals thereafter for an additional period of fifteen years. The MNDM Notice of Project Status will confirm the commencement of closure activities; Maintain wildlife log of general observations including sightings along access roads; Determine effects of mine-related dust on area lichen growth / survival; Conduct vegetation trials (test plots) to assess a variety of overburden / soil amendments directed at establishing lichen and other 21

22 vegetative communities for MRS reclamation; Complete satellite and noise monitoring, helicopter surveys, dust and vegetation surveys, revegetation trials (test plots) and revegetation at closure. Current Mitigation Criteria for Considering Adaptive Potential Adaptive Applicable Regulatory Instrument(s) Responsibilities Mine site developed as much as possible on previously disturbed areas, and in as compact an arrangement as practicable to limit disturbance to new habitat and to limit noise propagation; Avoid disturbance to known habitats for Caribou calving; Avoidance of development of new major access corridors (transmission line and roads); Implement wildlife management protocols to limit unnecessary disturbance to Caribou; Restore disturbed habitats at closure to habitats capable of supporting a diversity of wildlife species with a focus on Caribou as practical. Mine site and transmission line development displace the more quantity (area) of previously undeveloped forest habitat than anticipated in the CSR; When compared to the levels observed in baseline conditions, caribou are not being observed utilizing habitats beyond a buffer zone of 5 to 10 km of the principal Project mine site area and are not utilizing habitats within the buffer zone more sparingly; Noise propagation is such that 30 dba approximate sound levels are not expected to be attained at the outer boundary of a 5 to 10 km buffer zone around the Project site; Site reclamation at closure does not provide habitats which are suited to, and utilized by Caribou. Undertake trial test work to determine optimal site revegetation measures for reclamation including the development of specific habitats for Caribou; Improve noise mitigation if and as required. EC Species at Risk Act (SARA) and associated Boreal Woodland Caribou SARA Recovery Strategy; MNR Endangered Species Act and associated Woodland Caribou Conservation Plan; MNDM Closure Plan requirements. In the Annual FUP Report, DGC will provide a summary of follow-up and monitoring information as outlined in the verification / assessment methods. DGC is also responsible for implementing mitigation measures and, if necessary, potential adaptive management measures described above. The Annual FUP Report prepared by DGC will also include relevant summary information regarding submissions and project performance in relation to: EC s SARA requirements in accordance with the Boreal Woodland Caribou Recovery Strategy; MNR s Endangered Species Act and associated Woodland Caribou Conservation Plan requirements; and MNDM s Closure Plan implementation, required under the Ontario Mining Act. 22

23 6.7 Resource Harvesting (Country Foods): Local Fish Valued Ecosystem Component Aspect EA Prediction Rationale for Inclusion in FUP: Potential Residual Effect or Concern Verification / Assessment Methods Current Mitigation Criteria for Considering Adaptive Resource Harvesting (Country Foods) Local Fish (aspect of Project CSR FUPF) Effluent discharges expected to meet applicable regulatory thresholds defined through legislation or site specific permits and approvals; Receiving water quality expected to meet background conditions, or applicable criteria for the protection of aquatic life criteria; Mercury, lead and cadmium levels in fish (Northern Pike as the sentinel species) to remain below thresholds that would be of concern for human consumption. Fish numbers in downstream waters reduced; Fish in downstream waters of mine site activities could potentially accumulate heavy metals to levels unsuited for human consumption. Regular water quality sampling, analysis and data interpretation as dictated by legislation or applicable site specific permits and approvals; MMER EEM and ECA monitoring programs include sediment and benthos sampling and reporting; Fish flesh (Northern Pike) sampling for mercury in East Lake and downstream East Creek / Sunday Creek system waters as per ECA requirements; Local Aboriginal people to voluntarily submit fish for sampling and analysis. Consider engaging and funding Aboriginal people in the conduct of a harvesting and contaminant analysis program for country foods including pickerel/walleye, moose, beaver, and caribou. Water quality treatment and management as described in the FUP table 6.1; Maintain open dialogue with Aboriginal representatives and local fishermen; Conduct additional TK studies. Receiving water quality exceeds background conditions, or applicable criteria for the protection of aquatic life criteria; Sediment sampling shows a significant increase in metals concentrations beyond current background conditions; Fish sampling (northern pike) sampling for mercury, lead and cadmium to identify whether levels are above thresholds of concern for human consumption in East Lake and downstream East Creek/Sunday Creek system waters; Area fish samples (and species) turned in by Aboriginal fishermen show mercury, lead and cadmium levels above thresholds of concern 23

Detour Lake Gold Mine Environmental Effects Summary. April Prepared by: Canadian Environmental Assessment Agency CEAR

Detour Lake Gold Mine Environmental Effects Summary. April Prepared by: Canadian Environmental Assessment Agency CEAR Detour Lake Gold Mine Environmental Effects Summary Prepared by: Canadian Environmental Assessment Agency CEAR 10 03 52262 Introduction The purpose of this Environmental Effects Summary is to support public

More information

Environmental Regulation & Mine Permitting in Ontario

Environmental Regulation & Mine Permitting in Ontario Environmental Regulation & Mine Permitting in Ontario A Presentation to the Ad Hoc Committee on Mining Lake Superior Work Group Mark O Brien, Mineral Development Consultant MNDMF, Thunder Bay Agenda Regulatory

More information

Magino Project Environmental Impact Statement. Technical Support Document Draft Fish Habitat Compensation Plan

Magino Project Environmental Impact Statement. Technical Support Document Draft Fish Habitat Compensation Plan Magino Project Environmental Impact Statement Technical Support Document 20-14 Rev. No. Revision Date Approved 0 Document issued for EIS Table of Contents SECTION 1.0 INTRODUCTION... 1 SECTION 2.0 BACKGROUND...

More information

Comprehensive Study Report

Comprehensive Study Report Canadian Environmental Assessment Agency Agence canadienne d évaluation environnementale Comprehensive Study Report Detour Lake Gold Mine Canadian Environmental Assessment Agency November 2011 Photos are

More information

Comprehensive Study Scoping Document. for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number:

Comprehensive Study Scoping Document. for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number: Comprehensive Study Scoping Document for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number: 07-03-26302 Prepared pursuant to Subsection 21(1) of the Canadian Environmental Assessment

More information

24.0 FOLLOW-UP MONITORING AND ENVIRONMENTAL MANAGEMENT PLANS

24.0 FOLLOW-UP MONITORING AND ENVIRONMENTAL MANAGEMENT PLANS 24.0 FOLLOW-UP MONITORING AND ENVIRONMENTAL MANAGEMENT PLANS 24.1 OBJECTIVES AND CONTEXT Under CEAA 2012, an EA must consider the need for, and the requirements of, follow-up monitoring. A follow-up program

More information

APPENDIX D EA Conditions Review D-1: Federal EA Conditions Review D-2: Provincial EA Conditions Review

APPENDIX D EA Conditions Review D-1: Federal EA Conditions Review D-2: Provincial EA Conditions Review APPENDIX D EA Conditions Review D-1: D-2: Provincial EA Conditions Review Côté Gold Project Environmental Effects Review Report September 2018 EA: EA 05-09-02; EAIMS: 13022; CEAA: 80036 D-1: CÔTÉ GOLD

More information

Draft Mine Closure Plan. 17 October 2018 Longlac & Geraldton

Draft Mine Closure Plan. 17 October 2018 Longlac & Geraldton Draft Mine Closure Plan 17 October 2018 Longlac & Geraldton Project Update Federal EA Decision report was issued on October 1 st and Provincial Report is expected to be issued Oct 22 nd Federal approval

More information

AND WHEREAS the Minister is satisfied that all the requirements of the Act have been met, including those required of Premier Tech;

AND WHEREAS the Minister is satisfied that all the requirements of the Act have been met, including those required of Premier Tech; PROVINCE OF SASKATCHEWAN MINISTRY OF ENVIRONMENT MINISTERIAL APPROVAL PURSUANT TO SECTION 15(1)(a) THE ENVIRONMENTAL ASSESSMENT ACT PREMIER TECH HORTICULTURE LTD. SMOKEY RIDGE PEAT HARVESTING PROJECT WHEREAS

More information

Shell Quest Carbon Capture and Storage Project. Shell Canada Limited

Shell Quest Carbon Capture and Storage Project. Shell Canada Limited SCREENING SCOPING DOCUMENT For the proposed Shell Quest Carbon Capture and Storage Project Shell Canada Limited Prepared by: Canadian Environmental Assessment Agency Natural Resources Canada Fisheries

More information

Magino Project Environmental Impact Statement. Technical Support Document Water Management Plan

Magino Project Environmental Impact Statement. Technical Support Document Water Management Plan EIS Techni cal Support Document 20-12 Magino Project Environmental Impact Statement Technical Support Document 20-12 Rev. No. Revision Date Approved 0 Document issued for EIS Table of Contents SECTION

More information

to Nemaska Lithium Inc. c/o Guy Bourassa President and Chief Operating Officer 450 De la Gare-du-Palais Street, 1 st Floor Quebec, Quebec G1K 3X2

to Nemaska Lithium Inc. c/o Guy Bourassa President and Chief Operating Officer 450 De la Gare-du-Palais Street, 1 st Floor Quebec, Quebec G1K 3X2 Decision Statement Issued under Section 54 of the Canadian Environmental Assessment Act, 2012 to Nemaska Lithium Inc. c/o Guy Bourassa President and Chief Operating Officer 450 De la Gare-du-Palais Street,

More information

GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN WATERBODIES AND ON WATERBODY BANKS

GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN WATERBODIES AND ON WATERBODY BANKS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 182 NOVEMBER 2012 GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN WATERBODIES AND ON WATERBODY BANKS TABLE OF CONTENTS

More information

PROJECT AGREEMENT FOR THE BURNCO AGGREGATE MINE IN BRITISH COLUMBIA

PROJECT AGREEMENT FOR THE BURNCO AGGREGATE MINE IN BRITISH COLUMBIA PROJECT AGREEMENT FOR THE BURNCO AGGREGATE MINE IN BRITISH COLUMBIA PREAMBLE WHEREAS the Government of Canada is committed to improving the efficiency of federal environmental assessment (EA) and regulatory

More information

LNG Canada Development Inc.

LNG Canada Development Inc. LNG Canada Development Inc. Shell Centre 32 nd Floor 400 4 th Avenue SW PO Box 100, Station M Calgary AB T2P 2H5 Canada Submitted electronically to: compliance.conformite@ceaa-acee.gc.ca April 20, 2016

More information

The Federal Environmental Impact Statement (EIS) Guidelines require that the Environmental Assessment (EA) Report include:

The Federal Environmental Impact Statement (EIS) Guidelines require that the Environmental Assessment (EA) Report include: 11.0 SUMMARY OF RESIDUAL EFFECTS AND CONCERNS 11.1 Changes to the Project since Initially Proposed The Environmental Impact Statement (EIS) Guidelines require that the Environmental Assessment (EA) Report

More information

Labrador Iron Mines Holdings Limited

Labrador Iron Mines Holdings Limited Labrador Iron Mines Holdings Limited Rehabilitation and Closure May 10, 2016 Re-establishing Flow to the Un-named Tributary Evolution of the Un-named Tributary James Mine Dewatering was required to lower

More information

The following potential environmental receptors and impacts form the basis of TRCA s review under Ontario Regulation 166/06 and the Fisheries Act:

The following potential environmental receptors and impacts form the basis of TRCA s review under Ontario Regulation 166/06 and the Fisheries Act: Interim TRCA Technical Guidelines for the Development of Environmental Management Plans for Dewatering September 2013 Rationale: The Technical Guidelines for the Development of Environmental Management

More information

REASONS FOR DECISION MINISTERIAL APPROVAL PURSUANT TO SECTION 15(1)(a) THE ENVIRONMENTAL ASSESSMENT ACT

REASONS FOR DECISION MINISTERIAL APPROVAL PURSUANT TO SECTION 15(1)(a) THE ENVIRONMENTAL ASSESSMENT ACT REASONS FOR DECISION MINISTERIAL APPROVAL PURSUANT TO SECTION 15(1)(a) THE ENVIRONMENTAL ASSESSMENT ACT SASKATCHEWAN WATER CORPORATION BUFFALO POUND NON-POTABLE WATER SUPPLY SYSTEM EXPANSION PROJECT Introduction

More information

APPENDIX O COMPREHENSIVE ALTERNATIVES ASSESSMENT TABLES. RAINY RIVER PROJECT Final Environmental Assessment Report

APPENDIX O COMPREHENSIVE ALTERNATIVES ASSESSMENT TABLES. RAINY RIVER PROJECT Final Environmental Assessment Report APPENDIX O COMPREHENSIVE ALTERNATIVES ASSESSMENT TABLES RAINY RIVER PROJECT APPENDIX O: COMPARATIVE ALTERNATIVES ANALYSIS GLOSSARY AND ABBREVIATIONS ARD EA EC DFO GHG HONI MMER MOE MTO NA NLSA NPAG NRSA

More information

Base Metal and Iron Ore Mining

Base Metal and Iron Ore Mining Multilateral Investment Guarantee Agency Environmental Guidelines for Base Metal and Iron Ore Mining Industry Description and Practices This document addresses the mining of base metal ores (copper, lead

More information

Santoy 8 Satellite Mine at the Seabee Gold Mine. Technical Review Comments. on the. Environmental Impact Statement.

Santoy 8 Satellite Mine at the Seabee Gold Mine. Technical Review Comments. on the. Environmental Impact Statement. Environmental Impact Assessment Technical Review Comments on the Environmental Impact Statement as submitted by Claude Resources Inc. Saskatchewan Ministry of Environment December, 2009 1. INTRODUCTION

More information

The following potential environmental receptors and impacts form the basis of TRCA s review under Ontario Regulation 166/06 and the Fisheries Act:

The following potential environmental receptors and impacts form the basis of TRCA s review under Ontario Regulation 166/06 and the Fisheries Act: TRCA Technical Guidelines for the Development of Environmental Management Plans for Dewatering September 2013 Rationale: The Technical Guidelines for the Development of Environmental Management Plans for

More information

Operations Mine Site, Tote Road and Railway

Operations Mine Site, Tote Road and Railway Operations Mine Site, Tote Road and Railway 2 Panel Members Michael Anderson Richard Cook John Binns Fernand Beaulac Steve Walker Mike Lepage Michael Sheahan 3 The Panel will address: FEIS Volumes 3, 5,

More information

LNG Canada submitted a formal update as per Condition 11.2 of the CEAA Decision Statement on June 30, 2017:

LNG Canada submitted a formal update as per Condition 11.2 of the CEAA Decision Statement on June 30, 2017: LNG Canada Development Inc. Shell Centre 32 nd Floor 400 4 th Avenue SW PO Box 100, Station M Calgary AB T2P 2H5 Canada Submitted electronically to: compliance.conformite@ceaa-acee.gc.ca July 4, 2018 Canadian

More information

GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN AND AROUND WATERBODIES AND ON WATERBODY BANKS

GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN AND AROUND WATERBODIES AND ON WATERBODY BANKS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 182 APRIL 2017 GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN AND AROUND WATERBODIES AND ON WATERBODY BANKS TABLE OF CONTENTS

More information

NICO COBALT-GOLD-BISMUTH-COPPER PROJECT Community Scoping Session Environmental Overview

NICO COBALT-GOLD-BISMUTH-COPPER PROJECT Community Scoping Session Environmental Overview NICO COBALT-GOLD-BISMUTH-COPPER PROJECT Community Scoping Session Environmental Overview 1 INTRODUCTION Screening level environmental impact assessment provided in application package Many of the potential

More information

BACKGROUND INFORMATION. for the INITIAL FEDERAL PUBLIC COMMENT PERIOD. on the

BACKGROUND INFORMATION. for the INITIAL FEDERAL PUBLIC COMMENT PERIOD. on the BACKGROUND INFORMATION for the INITIAL FEDERAL PUBLIC COMMENT PERIOD on the Comprehensive Study pursuant to the Canadian Environmental Assessment Act of the Ajax Mine Project Kamloops, British Columbia

More information

PROJECT AGREEMENT FOR THE VICTOR DIAMOND MINE EXTENSION IN ONTARIO

PROJECT AGREEMENT FOR THE VICTOR DIAMOND MINE EXTENSION IN ONTARIO PROJECT AGREEMENT FOR THE VICTOR DIAMOND MINE EXTENSION IN ONTARIO PREAMBLE The Canadian Environmental Assessment Agency (CEA Agency) has commenced an environmental assessment (EA) pursuant to the Canadian

More information

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK PROVINCE OF NEW BRUNSWICK DEPARTMENT OF ENERGY AND RESOURCE DEVELOPMENT Minerals and Petroleum Development Branch GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK Guide to the

More information

Noront Ferrochrome Production Facility (FPF) Environmental Issues and Approach. October 2017

Noront Ferrochrome Production Facility (FPF) Environmental Issues and Approach. October 2017 Noront Ferrochrome Production Facility (FPF) Environmental Issues and Approach October 2017 (Simulated FPF) INTRODUCTION Noront is proposing to develop a Ferrochrome Production Facility (FPF) in Northern

More information

Independent Expert Engineering Investigation and Review Panel. Report on Mount Polley Tailings Storage Facility Breach. Appendix G: Water Balance

Independent Expert Engineering Investigation and Review Panel. Report on Mount Polley Tailings Storage Facility Breach. Appendix G: Water Balance Independent Expert Engineering Investigation and Review Panel Report on Mount Polley Tailings Storage Facility Breach Appendix G: Water Balance January 30, 2015 Report on Mount Polley Tailings Storage

More information

Golf Course and Recreational Facilities Best Management Guidelines. Regional Official Plan Guidelines

Golf Course and Recreational Facilities Best Management Guidelines. Regional Official Plan Guidelines Golf Course and Recreational Facilities Best Management Guidelines Regional Official Plan Guidelines Halton Region Official Plan Guidelines The Regional Official Plan (ROP) is Halton s guiding document

More information

ENVIRONMENTAL ASSESSMENT TRACK REPORT GALORE CREEK COPPER-GOLD-SILVER MINE PROJECT. Northwestern British Columbia

ENVIRONMENTAL ASSESSMENT TRACK REPORT GALORE CREEK COPPER-GOLD-SILVER MINE PROJECT. Northwestern British Columbia ENVIRONMENTAL ASSESSMENT TRACK REPORT FOR THE GALORE CREEK COPPER-GOLD-SILVER MINE PROJECT IN Northwestern British Columbia CEA Registry Reference Number: 05-03-8858 SUBMITTED TO THE MINISTER OF THE ENVIRONMENT

More information

TERMS OF REFERENCE FOR THE PREPARATION OF A FOCUS REPORT. Regarding the Goldboro Gold Project Proposed by Anaconda Mining Inc.

TERMS OF REFERENCE FOR THE PREPARATION OF A FOCUS REPORT. Regarding the Goldboro Gold Project Proposed by Anaconda Mining Inc. TERMS OF REFERENCE FOR THE PREPARATION OF A FOCUS REPORT Regarding the Goldboro Gold Project Proposed by Anaconda Mining Inc. NOVA SCOTIA ENVIRONMENT October 14, 2018 1.0 INTRODUCTION The Goldboro Gold

More information

ENVIRONMENTAL SCREENING REPORT

ENVIRONMENTAL SCREENING REPORT ENVIRONMENTAL SCREENING REPORT Pursuant to the Canadian Environmental Assessment Act (CEA Act) SCREENING SUMMARY TransCanada PipeLines Limited (TransCanada) is proposing to conduct a contaminant sampling

More information

APPENDIX C Updated Mitigation and Monitoring Commitments

APPENDIX C Updated Mitigation and Monitoring Commitments APPENDIX C Updated Mitigation and Monitoring Commitments C-1: C-2: Site-Specific Mitigation Measures and Future Work for Archaeological Sites C-3: Summary of Monitoring Commitments Côté Gold Project Environmental

More information

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS Beaver Bank Bypass Highway 101 to the Beaver Bank Road Halifax County, NS NOVA SCOTIA DEPARTMENT OF THE ENVIRONMENT

More information

The last update was March 4, 2016.

The last update was March 4, 2016. From: To: Subject: Date: Long Lake Stewardship longlakesudbury@gmail.com LONG LAKE STEWARDSHIP - Gold Mine Site Reclamation Work - Project Update May 29, 2017 6:14:57 PM Hello - Some of you will remember

More information

Activities that may Require Permit/Approval. Permit/Approval Required Electrical Safety Authority. Approval (CAA) process.

Activities that may Require Permit/Approval. Permit/Approval Required Electrical Safety Authority. Approval (CAA) process. 10.0 Table 10-1 represents a preliminary list of anticipated permits and approvals required to implement the Project and additional details regarding each anticipated permit/approval including the agency

More information

UNDERGROUND UTILITY CROSSING (TRENCHLESS) General Submission Requirements

UNDERGROUND UTILITY CROSSING (TRENCHLESS) General Submission Requirements COMPLETE APPLICATION CHECKLIST Jan 2016 UNDERGROUND UTILITY CROSSING (TRENCHLESS) The following checklist has been compiled to assist the applicant in preparing their application for approval pursuant

More information

PROJECT AGREEMENT FOR THE MAGINO GOLD MINE IN ONTARIO

PROJECT AGREEMENT FOR THE MAGINO GOLD MINE IN ONTARIO PROJECT AGREEMENT FOR THE MAGINO GOLD MINE IN ONTARIO PREAMBLE The Canadian Environmental Assessment ( ) has commenced an environmental assessment (EA) pursuant to the Canadian Environmental Assessment

More information

Review of ML/ARD Geochemistry & Water Quality Predictions

Review of ML/ARD Geochemistry & Water Quality Predictions Review of ML/ARD Geochemistry & Water Quality Predictions Presented by Kim Bellefontaine, M.Sc., P.Geo. Senior Mine Review Geologist, MEMPR With contributions from: Kelly Sexsmith, M.S., P.Geo. Senior

More information

City of Mississauga Environmental Impact Studies Terms of Reference 2002

City of Mississauga Environmental Impact Studies Terms of Reference 2002 City of Mississauga Environmental Impact Studies Terms of Reference 2002 1.0 INTRODUCTION To ensure in so far as possible, both private and public developments are consistent with Natural Heritage and

More information

Chapter 10 Summary of Project Effects

Chapter 10 Summary of Project Effects Chapter 10 Summary of Project Effects MINAGO PROJECT Environmental Impact Statement i TABLE OF CONTENTS 10. SUMMARY OF PROJECT EFFECTS 10-1 10.1 Key Findings 10-1 10.1.1 Aquatic Habitat 10-1 10.1.2 Wildlife

More information

3.1 Conservation Authorities Act

3.1 Conservation Authorities Act 3 Legislative Foundation 3 Legislative Foundation 3.1 Conservation Authorities Act 12 3.1.1 Objects of a Conservation Authority 12 3.1.2 Powers of a Conservation Authority 12 3.1.3 Regulations of a Conservation

More information

COMPREHENSIVE STUDY REPORT BRUCE HEAVY WATER PLANT DECOMMISSIONING PROJECT

COMPREHENSIVE STUDY REPORT BRUCE HEAVY WATER PLANT DECOMMISSIONING PROJECT COMPREHENSIVE STUDY REPORT BRUCE HEAVY WATER PLANT DECOMMISSIONING PROJECT Prepared by: Canadian Nuclear Safety Commission March 2003 TABLE OF CONTENTS page 1.0 INTRODUCTION.. 1 2.0 BACKGROUND 1 2.1 Project.

More information

Scoping Document for the Environmental Assessment. BP Exploration (Canada) Ltd. Tangier 3D Seismic Survey

Scoping Document for the Environmental Assessment. BP Exploration (Canada) Ltd. Tangier 3D Seismic Survey Scoping Document for the Environmental Assessment BP Exploration (Canada) Ltd. Tangier 3D Seismic Survey Exploration Licenses 2431, 2432, 2433, and 2434 August 2013 Contents 1.0 Purpose... 2 2.0 Regulatory

More information

The Halifax Harbour Solutions Project Provision of Sewage Treatment

The Halifax Harbour Solutions Project Provision of Sewage Treatment The Halifax Harbour Solutions Project Provision of Sewage Treatment ENVIRONMENTAL SCREENING PURSUANT TO THE CANADIAN ENVIRONMENTAL ASSESSMENT ACT Prepared by Halifax Regional Municipality June, 2000 Revised

More information

Town of Perth Landfill Expansion Environmental Screening

Town of Perth Landfill Expansion Environmental Screening Town of Perth Landfill Expansion Environmental Screening Public Information Centre Thursday September 29, 2016 4:00 to 6:00 p.m. and 7:00 to 9:00 p.m. Perth Town Hall Main Floor Welcome to the Public Information

More information

available in multiple formats Environmental Self-Assessment Handbook for Rail Infrastructure Projects

available in multiple formats Environmental Self-Assessment Handbook for Rail Infrastructure Projects available in multiple formats Environmental Self-Assessment Handbook for Rail Infrastructure Projects This document and other Canadian Transportation Agency publications are available on our Web site at

More information

RAINY RIVER PROJECT COMMITMENTS REGISTRY (VER. 12)

RAINY RIVER PROJECT COMMITMENTS REGISTRY (VER. 12) # / Mitigation Source 1 Air quality and greenhouse gases Sound and vibration 1. The Rainy River (RRP) will monitor and mitigate air emissions, particularly dust, through implementation of current industry

More information

ENVIRONMENTAL IMPACT STATEMENT EXECUTIVE SUMMARY. Town of Shelburne Long-Term Well for Additional Water Supply Project

ENVIRONMENTAL IMPACT STATEMENT EXECUTIVE SUMMARY. Town of Shelburne Long-Term Well for Additional Water Supply Project ENVIRONMENTAL IMPACT STATEMENT EXECUTIVE SUMMARY Town of Shelburne Long-Term Well for Additional Water Supply Project EXECUTIVE SUMMARY Introduction Project Summary In order to accommodate future growth

More information

Star Orion South Diamond Project ENVIRONMENTAL IMPACT STATEMENT SUMMARY

Star Orion South Diamond Project ENVIRONMENTAL IMPACT STATEMENT SUMMARY Star Orion South Diamond ENVIRONMENTAL IMPACT STATEMENT SUMMARY Summary of the Environmental Impact Statement of the Star Orion South Diamond proposed by Shore Gold Inc. August 2013 CEAR 46277 This page

More information

DETAILED IMPACT ANALYSIS OF MARMOT BASIN LONG RANGE PLAN

DETAILED IMPACT ANALYSIS OF MARMOT BASIN LONG RANGE PLAN 2.0 JURISDICTION Parks Canada s decisions about the acceptability of proposals presented in the LRP are guided by a number of regulatory instruments and policies, the most relevant of which are described

More information

Canada. Record of Proceedings, Including Reasons for Decision. Cameco Corp_o_ra_ti_o_n. Proponent

Canada. Record of Proceedings, Including Reasons for Decision. Cameco Corp_o_ra_ti_o_n. Proponent Canadian Nuclear Safety Commission Commission canadienne de sorete nucleaire Record of Proceedings, Including Reasons for Decision Proponent Cameco Corp_o_ra_ti_o_n _ Subject Comprehensive Study Report

More information

10.0 MITIGATION MEASURES

10.0 MITIGATION MEASURES 10.0 MITIGATION MEASURES Mitigation measures proposed herein are the result of an iterative process that took place between the environmental effects prediction and the engineering design teams. Based

More information

Attachment 1 WORLD BANK ENVIRONMENT, HEALTH AND SAFETY GUIDELINES 1 MINING AND MILLING UNDERGROUND (INTERIM)

Attachment 1 WORLD BANK ENVIRONMENT, HEALTH AND SAFETY GUIDELINES 1 MINING AND MILLING UNDERGROUND (INTERIM) TAILINGS DISPOSAL Attachment 1 WORLD BANK ENVIRONMENT, HEALTH AND SAFETY GUIDELINES 1 MINING AND MILLING UNDERGROUND (INTERIM) Tailings must be disposed of in a manner that optimizes protection of human

More information

Amendment to the Environmental Impact Statement (EIS) - Kami Iron Ore Project

Amendment to the Environmental Impact Statement (EIS) - Kami Iron Ore Project Amendment to the Environmental Impact Statement (EIS) - Kami Iron Ore Project We are pleased to provide you with a copy of the Amendment to the EIS for the Kami Iron Ore Project. This Amendment has been

More information

Terms of Reference. As Required by the Environment Act For Preparation of an Environmental Assessment Report

Terms of Reference. As Required by the Environment Act For Preparation of an Environmental Assessment Report The public is invited to submit comments on this draft Terms of Reference until : Comments should be submitted to : January 21, 2008 Environmental Assessment Branch Nova Scotia Environment and Labour PO

More information

HARDROCK PROJECT Final Environmental Impact Statement / Environmental Assessment

HARDROCK PROJECT Final Environmental Impact Statement / Environmental Assessment Final Environmental Impact Statement / Environmental Assessment Chapter 23.0: Follow-Up and Monitoring Programs and Environmental Management Plans Prepared for: Greenstone Gold Mines GP Inc. 365 Bay Street

More information

Appendix 4. Soil Management Plan

Appendix 4. Soil Management Plan Appendix 4 Soil Management Plan Soil Management Plan This Soil Management Plan (SMP) has been developed for the Giscome Quarry and Lime Plant Project. The SMP is a living document and will be updated as

More information

September 2016 ID Competency Statement Type

September 2016 ID Competency Statement Type September 06 Ensures that the impact assessment scope, criteria and conditions (geographic, environmental, economic, social, and cultural) are defined adequately. Develops a project management plan for

More information

Information Request 37

Information Request 37 Information Request 37 Information Request 37 37-1 Response to Information Request 37 Response to Information Requests 37a Response to Information Requests 37b 37-3 37-5 Federal Review Panel Information

More information

February 15, Mr. Kyle Stanfield Prodigy Gold Incorporated Box 209, 3 Dree Road Dubreuilville, ON P05 1BO

February 15, Mr. Kyle Stanfield Prodigy Gold Incorporated Box 209, 3 Dree Road Dubreuilville, ON P05 1BO Environmental Assessment Canadian Agency Agence canadienne devaluation environnementale Ontario Regional Office Bureau regional de Ontario 55 St. Clair Avenue East, 55, avenue St-Clair est, Room 907 bureau

More information

Preliminary Disclosure; Application for Approval; Operating Permits, Volume 2: Licences and Approvals; and Abandonment Approval and

Preliminary Disclosure; Application for Approval; Operating Permits, Volume 2: Licences and Approvals; and Abandonment Approval and Information required by EUB Guide G-23 1.0 GENERAL INFORMATION 1.1 INTRODUCTION The application should include: a brief project summary, objectives, approvals requested, technical and economic details,

More information

Preface. MNR # Queen s Printer for Ontario, 2012 ISBN (PRINT) ISBN (PDF)

Preface. MNR # Queen s Printer for Ontario, 2012 ISBN (PRINT) ISBN (PDF) Preface In 2008, the inter-agency Drainage Act & Section 28 Regulations Team (DART) was established by the Ministry of Natural Resources (MNR) and the Ministry of Agriculture, Food and Rural Affairs (OMAFRA)

More information

NEED MORE INFORMATION?

NEED MORE INFORMATION? NEED MORE INFORMATION? Public Record Locations The public record for this environmental assessment can be reviewed during normal business hours at the following ministry office: Ministry of the Environment

More information

NORONT RESOURCES LTD. EAGLE S NEST PROJECT

NORONT RESOURCES LTD. EAGLE S NEST PROJECT NORONT RESOURCES LTD. EAGLE S NEST PROJECT TERMS OF REFERENCE NORONT RESOURCES LTD. EAGLE S NEST PROJECT TERMS OF REFERENCE (REF. NO. ) TABLE OF CONTENTS PAGE SECTION 1.0 - INTRODUCTION... 1 1.1 INTRODUCTION...

More information

Environmental Assessment Approval

Environmental Assessment Approval Environmental Assessment Approval Approval Date: Original Dated April 20, 2012 Trimper Sand and Gravel Pit Expansion Ivan H. Trimper Construction Ltd., Proponent Annapolis County, Nova Scotia The Trimper

More information

Nottawasaga Valley Conservation Authority

Nottawasaga Valley Conservation Authority Nottawasaga Valley Conservation Authority PROCEDURAL GUIDELINE FOR THE PLACEMENT OF LARGE QUANTITIES OF FILL Effective: October 28, 2011 Nottawasaga Valley Conservation Authority 8195 8th Line, Utopia,

More information

Strength. Performance. Passion. Paris Pit CAP. September 25, 2012

Strength. Performance. Passion. Paris Pit CAP. September 25, 2012 Strength. Performance. Passion. Paris Pit CAP September 25, 2012 2012 Holcim 2012 (Canada) Holcim (Canada) Inc. Inc. Agenda Introductions Minutes from Last Meeting Dufferin Paris Pit - General Update Holcim

More information

APPENDIX 2. Nova Scotia Department of Environment and Labour Environmental Assessment Terms and Conditions for Environmental Assessment Approval

APPENDIX 2. Nova Scotia Department of Environment and Labour Environmental Assessment Terms and Conditions for Environmental Assessment Approval APPENDIX 2 Nova Scotia Department of Environment and Labour Terms and Conditions for Approval Approval Approval Date: March 14, 2007 Keltic Petrochemicals Inc. LNG and Petrochemical Plant Facilities Keltic

More information

APPENDIX A. CEAA Scoping Document

APPENDIX A. CEAA Scoping Document APPENDIX A CEAA Scoping Document Transport Canada - Surface Programs Scoping Document for the Mississauga BRT project, Mississauga Ontario. Introduction Transport Canada and Infrastructure Canada propose

More information

(No. of pages excluding this page = 10)

(No. of pages excluding this page = 10) SPECIALIST CONSULTANT STUDIES 3-65 BIG ISLAND MINING PTY LTD (No. of pages excluding this page = 10) Ltd BIG ISLAND MINING PTY LTD 3-66 SPECIALIST CONSULTANT STUDIES This page has intentionally been left

More information

FISHERIES AND OCEANS CANADA

FISHERIES AND OCEANS CANADA FISHERIES AND OCEANS CANADA Final Submission/Technical Report EA1415-01 Prairie Creek All Season Road Canadian Zinc Submitted to: Mackenzie Valley Environmental Impact Review Board (MVEIRB) March 10, 2017

More information

PROJECT AGREEMENT FOR THE HOWSE PROPERTY IRON MINE IN NEWFOUNDLAND AND LABRADOR

PROJECT AGREEMENT FOR THE HOWSE PROPERTY IRON MINE IN NEWFOUNDLAND AND LABRADOR PREAMBLE PROJECT AGREEMENT FOR THE HOWSE PROPERTY IRON MINE IN NEWFOUNDLAND AND LABRADOR The Canadian Environmental Assessment Agency (CEA Agency) has commenced an environmental assessment (EA) pursuant

More information

Wolverine Project TEMPORARY CLOSURE UPDATE TO RECLAMATION AND CLOSURE PLAN AS REQUIRED BY QML-0006

Wolverine Project TEMPORARY CLOSURE UPDATE TO RECLAMATION AND CLOSURE PLAN AS REQUIRED BY QML-0006 TEMPORARY CLOSURE UPDATE TO RECLAMATION AND CLOSURE PLAN 2006-01 AS REQUIRED BY Prepared by: Yukon Zinc Corporation Vancouver, British Columbia In Association with: Lorax Environmental Services Ltd. Vancouver,

More information

Reasons for Ministers Decision

Reasons for Ministers Decision In the matter of the Environmental Assessment Act S.B.C. 2002, c. 43 (Act) and In the matter of an Application for an Environmental Assessment Certificate (Application) by Teck Coal Limited (Proponent)

More information

EVOLUTION OF RECLAMATION FOR WILDLIFE HABITAT AT SULPHIDE MINES IN BRITISH COLUMBIA, CANADA. Natalie Tashe November 9, 2012

EVOLUTION OF RECLAMATION FOR WILDLIFE HABITAT AT SULPHIDE MINES IN BRITISH COLUMBIA, CANADA. Natalie Tashe November 9, 2012 EVOLUTION OF RECLAMATION FOR WILDLIFE HABITAT AT SULPHIDE MINES IN BRITISH COLUMBIA, CANADA Natalie Tashe November 9, 2012 1 GEOGRAPHIC CONTEXT 2 DEFINING WILDLIFE HABITAT 3 OUTLINE 1. Mine Cycle for reclamation

More information

Potential Impacts and Mitigations from a Saline Discharge into Marine Environment

Potential Impacts and Mitigations from a Saline Discharge into Marine Environment Meliadine Division Potential Impacts and Mitigations from a Saline Discharge into Marine Environment DECEMBER 2017 VERSION 1 Table 1: Potential Impacts and Mitigations Marine Environment Benthic Invertebrates

More information

EAGLE S NEST PROJECT

EAGLE S NEST PROJECT A Federal/Provincial Environmental Impact Statement/Environmental Assessment Report Draft Copy December 20, 2013 VOLUME 1 EXECUTIVE SUMMARY PAGE EXECUTIVE SUMMARY... 1-1 1 INTRODUCTION... 1-1 1.1 PROJECT

More information

Construction Environmental Management Plan (CEMP) for Potash Overland Conveyor

Construction Environmental Management Plan (CEMP) for Potash Overland Conveyor Construction Environmental Management Plan (CEMP) for Potash Overland Conveyor Stephanie Jay K2 Environmental Engineer The Mosaic Company Esterhazy, Saskatchewan, S0A 0X0 Matt Tyree Operations Manager

More information

Fisheries and Oceans Canada Species at Risk Act. Directive on the Identification of Critical Habitat for Aquatic Species at Risk

Fisheries and Oceans Canada Species at Risk Act. Directive on the Identification of Critical Habitat for Aquatic Species at Risk Fisheries and Oceans Canada Species at Risk Act Directive on the Identification of Critical Habitat for Aquatic Species at Risk January 2015 Species at Risk Program Programme d espèces en péril To be read

More information

Fish Habitat Design, Operation and Reclamation Workbook and Worksheets for Placer Mining in the Yukon Territory

Fish Habitat Design, Operation and Reclamation Workbook and Worksheets for Placer Mining in the Yukon Territory Fish Habitat Design, Operation and Reclamation Workbook and Worksheets for Placer Mining in the Yukon Territory Version 1.0 April 2008 This document is available from the Yukon Placer Secretariat, Yukon

More information

HARDROCK PROJECT CONSULTATION PLAN for Long Lake #58 First Nation

HARDROCK PROJECT CONSULTATION PLAN for Long Lake #58 First Nation GREENSTONE GOLD MINES GP INC. 2016 HARDROCK PROJECT CONSULTATION PLAN for Long Lake #58 First Nation LONG LAKE #58 FIRST NATION JANUARY 2016 Contents Section Page 1. Introduction... 2-1 1.1 Project Background...

More information

T a b l e o f C o n t e n t s

T a b l e o f C o n t e n t s T a b l e o f C o n t e n t s Executive Summary English Executive Summary French page 1. Introduction and Background... 1-1 1.1 Introduction...1-1 1.2 The Proponent Waste Management of Canada Corporation...1-2

More information

Environmental Assessment Approval. Alton Natural Gas Storage Project

Environmental Assessment Approval. Alton Natural Gas Storage Project Approval Approval Date: Original Dated December 18, 2007 Alton Natural Gas Storage Project Alton Natural Gas Storage LP, Proponent Colchester County, Nova Scotia Alton Natural Gas Storage (the Undertaking

More information

SCHEDULE A DOCUMENTATION AND CORRESPONDENCE FOR THE PROSPERITY GOLD-COPPER PROJECT (Project) Produced by or for Taseko Mines Limited March 17, 2009 Ap

SCHEDULE A DOCUMENTATION AND CORRESPONDENCE FOR THE PROSPERITY GOLD-COPPER PROJECT (Project) Produced by or for Taseko Mines Limited March 17, 2009 Ap SCHEDULE A DOCUMENTATION AND CORRESPONDENCE FOR THE PROSPERITY GOLD-COPPER PROJECT (Project) Produced by or for Taseko Mines Limited March 17, 2009 April 2009 April 13, 2009 April 16, 2009 April 20, 2009

More information

Facilities Environmental Protection Plan: Burnaby Terminal

Facilities Environmental Protection Plan: Burnaby Terminal Facilities Environmental Protection Plan: Burnaby Terminal 1 Facilities Environmental Protection Plan: Overview What The Environmental Protection Plan (EPP) communicates environmental procedures and mitigation

More information

HIGHWAY 905 ALL WEATHER ROADWAY STONY RAPIDS TO LAKE ATHABASCA NEAR FOND DU LAC

HIGHWAY 905 ALL WEATHER ROADWAY STONY RAPIDS TO LAKE ATHABASCA NEAR FOND DU LAC PROJECT-SPECIFIC GUIDELINES FOR THE PREPARATION OF AN ENVIRONMENTAL IMPACT STATEMENT AND CANADIAN ENVIRONMENTAL ASSESSMENT ACT COMPREHENSIVE STUDY SCOPING DOCUMENT HIGHWAY 905 ALL WEATHER ROADWAY STONY

More information

Fish Habitat Design, Operation and Reclamation Workbook and Worksheets for Placer Mining in the Yukon Territory

Fish Habitat Design, Operation and Reclamation Workbook and Worksheets for Placer Mining in the Yukon Territory Fish Habitat Design, Operation and Reclamation Workbook and Worksheets for Placer Mining in the Yukon Territory Version 1.3 November 2010 This document is available from: Yukon Placer Secretariat, 206B

More information

Fish Habitat Protection Development Permit Area

Fish Habitat Protection Development Permit Area Appendix A2 3 Fish Habitat Protection Development Permit Area 1.0 PURPOSE: The area shown on Map No. 7 as the Fish Habitat Protection Development Permit Area is designated for the purpose of protecting

More information

Background Information & Mitigation Guidelines MANURE STORAGE IMPROVEMENTS and MORTALITY MANAGEMENT

Background Information & Mitigation Guidelines MANURE STORAGE IMPROVEMENTS and MORTALITY MANAGEMENT Background Information & Mitigation Guidelines MANURE STORAGE IMPROVEMENTS and MORTALITY MANAGEMENT I. BACKGROUND FOR MANURE STORAGE AND HANDLING SYSTEMS Supplementary Information Form on sizing and safety

More information

Chapter 4. Airport Authority Governance, Statutes and Policies

Chapter 4. Airport Authority Governance, Statutes and Policies Chapter 4 Airport Authority Governance, Statutes and Policies Table of Contents 4. Airport Authority Governance, Statutes and Policies... 4-1 4.1 The Federal Government and Airport Authorities... 4-1 4.2

More information

Scoping Document for the Environmental Assessment Statoil Waverley 3D Seismic Survey Exploration Licenses 2435 and 2436

Scoping Document for the Environmental Assessment Statoil Waverley 3D Seismic Survey Exploration Licenses 2435 and 2436 Scoping Document for the Environmental Assessment Statoil Waverley 3D Seismic Survey Exploration Licenses 2435 and 2436 September 1, 2017 Page 1 This page is intentionally left blank Table of Contents

More information

1 A A 5? 4 9 I = E A 5? F D D A = 1 J 1 C 4 D

1 A A 5? 4 9 I = E  A 5? F D D A = 1 J 1 C 4 D 1 A A 5? 4 9 I = E 1? 3 @ @ A 5? 8 @ F D 5 4 9 D A = 1 J 2 @ 1 C 4 D Tantalum Mining Corporation of Canada Ltd. (TANCO) is 100% owned by Cabot Corporation. Cabot Corp. is a global performance materials

More information

The GNWT recommends Canada reject this recommendation in favour of commitments made by the GNWT during the environmental impact review process.

The GNWT recommends Canada reject this recommendation in favour of commitments made by the GNWT during the environmental impact review process. GOVERNMENT OF THE NORTHWEST TERRITORIES RESPONSE TO THE RECOMMENDATIONS IN THE FINAL REPORT OF THE PANEL FOR THE SUBSTITUTED ENVIRONMENTAL IMPACT REVIEW OF THE HAMLET OF TUKTOYAKTUK, TOWN OF INUVIK AND

More information

Record of Proceedings, Including Reasons for Decision

Record of Proceedings, Including Reasons for Decision Record of Proceedings, Including Reasons for Decision In the Matter of Applicant Ontario Power Generation Inc. Subject Environmental Assessment Guidelines (Scope of Project and Assessment) for the Proposed

More information

ENVIRONMENTAL ASSESSMENT ACT SECTION 9 NOTICE OF APPROVAL TO PROCEED WITH THE UNDERTAKING (AND ORDER UNDER SUBSECTION 12.4(3))

ENVIRONMENTAL ASSESSMENT ACT SECTION 9 NOTICE OF APPROVAL TO PROCEED WITH THE UNDERTAKING (AND ORDER UNDER SUBSECTION 12.4(3)) ENVIRONMENTAL ASSESSMENT ACT SECTION 9 NOTICE OF APPROVAL TO PROCEED WITH THE UNDERTAKING (AND ORDER UNDER SUBSECTION 12.4(3)) RE: Proponent: EA File No.: An Environmental Assessment for the Rainy River

More information