TROJAN DECOMMISSIONING STATUS. OPUC Meeting March 8, 2005 (draft)

Size: px
Start display at page:

Download "TROJAN DECOMMISSIONING STATUS. OPUC Meeting March 8, 2005 (draft)"

Transcription

1 TROJAN DECOMMISSIONING STATUS OPUC Meeting March 8, 2005 (draft) 1

2 Meeting Agenda Trojan Decommissioning Overview History Major Projects Overall Performance Remaining Major Activities Current Issues USDOE Fuel Storage Non-radiological Building Demolition Regulatory Preview 2

3 Decommissioning History Permanent Shutdown Jan 1993 Large Component Removal Nov 1995 Decommissioning Plan NRC Approval Apr 1996 Reactor Vessel Removal Aug 1999 Containment Building Concrete Removal Jan 2001 ISFSI Fully Loaded Sep 2003 Major Radiological Bldg Remediation Cp Jul 2004 All Radiological Remediation Complete Sep 2004 Final Survey Data Collection Complete Nov 2004 All Final Survey Reports Submitted to NRC Dec

4 Trojan Site Layout 4

5 Trojan Structures 5

6 Large Component Removal 6

7 Large Component Removal 7

8 Large Component Removal 8

9 Reactor Vessel and Internals Removal Project (RVAIR) 9

10 RVAIR Project 10

11 RVAIR Project 2000 Project Management Institute (PMI) International Project of the Year 11

12 Containment Concrete Removal 12

13 Containment Concrete Removal 13

14 Containment Building Pre/Post

15 Refueling Water Storage Tank 15

16 Independent Spent Fuel Storage Installation (ISFSI) Fuel Loading 16

17 Multi-Purpose Canister (MPC) Operations 17

18 Moving the Multi-Purpose Canister 18

19 ISFSI Pad with Loaded Casks 19

20 Spent Fuel Pool Before After Spent Fuel Pool Cask Load Pit 20

21 Radwaste Evaporator Room Before After 21

22 Main Steam Support Structure A Cubicle - 59 level Before After 22

23 Miscellaneous Buildings Warehouse Maintenance Building 23

24 Turbine Building 24

25 Trojan Visitors Center 25

26 Final Radiological Survey Plant divided into 9 survey groups Containment MSSS/EPA/SGBD (between Containment, Turbine, and Control Bldgs.) Turbine and Control Buildings Embedded Pipe Auxiliary Building Fuel Building Support Facilities and Site Grounds Spent Fuel Pool Impacted Areas Plant Systems Key Statistics 250,000 Square meters of surface area surveyed 26,000 Surveyor hours to collect data 62,000 Survey measurements collected NRC Confirmation Surveys NRC Review and Evaluation of Final Reports 26

27 Decom. Cost Estimate Comparison ($1997) Category TDF Update TDF Update TDF Update UE-102 Dec 99 Dec. 04 DECON Non-Rad. Decom ISFSI Const./Fuel Load ISFSI Long Term Ops Financing Subtotal Project Reserve Total

28 Project Completion Percentage Decommissioning Planning Large Component Removal RVAIR 100% 100% 100% Percent Complete thru 12/31/04 Aux/ Fuel/ Other Building Equipment Removal Containment Building Equipment Removal 100% 100% TDF Remaining Estimate as of 01/05 All Buildings - Floor Drains 100% All Buildings - Surface Decon Radioactive Waste Disposal 100% 100% Utility/ Contractor Staff 92% Corporate Overhead Undistributable Costs 95%. 96% Site Termination Survey 100% Non Radiological Decommissioning 63% Building Demolition 12% ISFSI Constr uction and Loading 100% ISFSI Decommiss ioning 0% ISFSI Long Ter m Oper ations 17% Decommissioning Financing 100% 0 10,000 20,000 30,000 40,000 50,000 60,000 70,000 80,000 90,000 $ x 1,000 28

29 Decommissioning Cost Estimate as of December 2004 ($1997) Category Actual to Date To Complete TDF Update DECON Non-Rad Decom ISFSI Const./Fuel Load ISFSI Long Term Ops Financing Subtotal Project Reserve Total

30 Decommissioning Cost Comparison (all costs in millions '03 $'s) Big Rock 1 Yankee Rowe San Onofre 1 Facility Haddam Neck Maine Yankee 4 Rancho Average 3 Seco Trojan 2 (5 PWR's) Thermal Rating (MWt) ,347 1,825 2,700 2,772 3,411 Total Cost NRC- Required Activities NRC Funding Level Requirement (waste processors) Cost of NRC- Required Activities v. NRC Funding Level Requirements (%) 86% 161% 139% 149% 126% 116% 97% 137% Cost Per Thermal Megawatt Note 1: only BWR reactor in group Note 2: only PWR located in Northwest Compact in group Note 3: only PWR's not located in Northwest Compact Note 4: does not reflect a $44 million credit received from performance and payment bond settlement 30

31 Schedule, Staffing, Performance Overall Radiological Decommissioning Schedule Performance ISFSI Project delayed approx. 3.5 years Overall project delayed approx. 2.5 years Overall Radiological Decommissioning Cost Performance Approx. 8% under budget Awarded Project Management Institute Project of the Year Staffing PGE and Contract Personnel January December Additional layoffs thru Staffing at the end of radiological decommissioning project ISFSI Long-term staff 31

32 Remaining Major Activities Complete Radiological Decom. June 2005 NRC Terminate Part 50 License June 2005 On-going Fuel Storage Operations thru 2018 Fuel Shipment Based on Original Decom. Plan Building/ISFSI Demo. and Site Restoration Based on Original Decom. Plan 32

33 Current Issues ISFSI operations will continue until 2023 (current projection) due to delays with the High Level Waste Repository USDOE scheduled to open repository in 2010 Significant uncertainty with this schedule Based on fuel shipment allotment, first PGE fuel ships in 2013 Final shipment projected in 2023 ISFSI Decommissioning in 2024 Prompt Building Demolition Proposal Complete major building demolition in versus end of project. (Cooling Tower, Turbine Building, Control Building, Auxiliary Building, Fuel Building, and Containment) Currently obtaining co-owner approval of change Plan to proceed following management approval 33

34 Rationale for Prompt Demolition Advantages of Prompt Demolition Resolves uncertainty for a significant portion of remaining costs Uses Trojan experience-base while still available Shares resources for demolition and remaining radiological decom. Avoids out-year costs of inspections and maintenance Mitigates increase in out-year cost/risk from longer ISFSI storage Expresses PGE s environmental stewardship Provides jobs for near term regional economic health Risks of Stay-the-Course or Delayed Demolition: Increases in costs Demolition Regulation Inspection of remaining structures Maintenance of remaining structures Less costly and risky buildings will remain for later demolition. 34

35 Regulatory Preview Continued Updates with OPUC Commission and Staff Audits Staff Internal Re-evaluate NDT contribution with next General Rate Case Contribution continues through 2006 Update contribution with next general filing Review work yet to be completed Re-evaluate contribution for 2007 and beyond 35

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona USA. Factors Impacting Decommissioning Costs 13576

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona USA. Factors Impacting Decommissioning Costs 13576 Factors Impacting Decommissioning Costs 13576 Karen Kim*, Richard McGrath* *Electric Power Research Institute, 342 Hillview Ave., Palo Alto, California. USA. kkim@epri.com, rmcgrath@epri.com ABSTRACT The

More information

ICFD Session 2, Cost Estimation Stockholm, Sweden - 21 September 2016 Michael Lackey P.E. Vice President - Nuclear Operations

ICFD Session 2, Cost Estimation Stockholm, Sweden - 21 September 2016 Michael Lackey P.E. Vice President - Nuclear Operations ICFD Session 2, Cost Estimation Stockholm, Sweden - 21 September 2016 Michael Lackey P.E. Vice President - Nuclear Operations Experience of Cost Estimation and Costs for NPP Decommissioning in the USA

More information

State of the Nuclear Industry Decontamination & Decommissioning Are We Ready. April 25, Presented by: Michael Frediani

State of the Nuclear Industry Decontamination & Decommissioning Are We Ready. April 25, Presented by: Michael Frediani State of the Nuclear Industry Decontamination & Decommissioning Are We Ready April 25, 2018 Presented by: Michael Frediani Special Thanks!!! This presentation was developed in collaboration with Sargent

More information

Power Reactor Decommissioning: U.S. Perspective on Regulatory Insights and Challenges

Power Reactor Decommissioning: U.S. Perspective on Regulatory Insights and Challenges Power Reactor Decommissioning: U.S. Perspective on Regulatory Insights and Challenges Scott W. Moore Deputy Director, Office of Nuclear Material Safety and Safeguards (NMSS), USNRC Japan Nuclear Regulation

More information

Humboldt Bay Power Plant Decommissioning Progress Update

Humboldt Bay Power Plant Decommissioning Progress Update Humboldt Bay Power Plant Decommissioning Progress Update EPRI 2016 Conference Presented by Kerry Rod, P. E. Decommissioning Manager June 20, 2016 Pacific Gas and Electric Company Presentation Objectives

More information

RANCHO SECO TRANSITION TO FULL DECOMMISSIONING. Dennis E. Gardiner, Decommissioning Project Manager, SMUD John M. Newey, CHP, President, NewRad, Inc.

RANCHO SECO TRANSITION TO FULL DECOMMISSIONING. Dennis E. Gardiner, Decommissioning Project Manager, SMUD John M. Newey, CHP, President, NewRad, Inc. ABSTRACT RANCHO SECO TRANSITION TO FULL DECOMMISSIONING Dennis E. Gardiner, Decommissioning Project Manager, SMUD John M. Newey, CHP, President, NewRad, Inc. The Rancho Seco Nuclear Generating Station

More information

Zion Project Overview S. Chris Baker VP EH&S

Zion Project Overview S. Chris Baker VP EH&S Zion Project Overview S. Chris Baker VP EH&S 1 Agenda Asset Sale Agreement Organization Nuclear Decommissioning Process Overview of Zion Station Decommissioning Schedule Near Term Activities Spent Fuel

More information

Two Approaches to Reactor Decommissioning: 10 CFR Part 50 License Termination and License Amendment, Lessons Learned from the Regulatory Perspective

Two Approaches to Reactor Decommissioning: 10 CFR Part 50 License Termination and License Amendment, Lessons Learned from the Regulatory Perspective Two Approaches to Reactor Decommissioning: 10 CFR Part 50 License Termination and License Amendment, Lessons Learned from the Regulatory Perspective B.A. Watson, J.T. Buckley, C.M. Craig U.S. Nuclear Regulatory

More information

Perspective of Decommissioning Worldwide in View of Metrological Needs

Perspective of Decommissioning Worldwide in View of Metrological Needs Perspective of Decommissioning Worldwide in View of Metrological Needs Vladimir Michal Team leader, Decommissioning and Environmental Remediation, Waste Technology Section, NE Department Global Status

More information

DECOMMISSIONING LESSONS LEARNED AT YANKEE ROWE. M. S. Terrell, D. McGee, Duke Engineering and Services (USA)

DECOMMISSIONING LESSONS LEARNED AT YANKEE ROWE. M. S. Terrell, D. McGee, Duke Engineering and Services (USA) DECOMMISSIONING LESSONS LEARNED AT YANKEE ROWE M. S. Terrell, D. McGee, Duke Engineering and Services (USA) ABSTRACT The experiences and lessons learned in the decommissioning of Yankee Rowe span almost

More information

U.S. NUCLEAR POWER PLANT DECOMMISSIONING

U.S. NUCLEAR POWER PLANT DECOMMISSIONING U.S. NUCLEAR POWER PLANT DECOMMISSIONING Workshop on Decommissioning of Nuclear Power Plants Tokyo, Japan June 30, 2017 PAUL T. DICKMAN Senior Policy Fellow, Washington DC Office Argonne National Laboratory

More information

Spent Nuclear Fuel, Low Level Radioactive Waste and Decommissioning

Spent Nuclear Fuel, Low Level Radioactive Waste and Decommissioning Spent Nuclear Fuel, Low Level Radioactive Waste and Decommissioning Vermont Legislature January 29, 2009 - Revised Montpelier, Vermont Presented by Bruce Lacy 1 Topics Spent Nuclear Fuel Low Level Radioactive

More information

Remediation and Decommissioning Technology

Remediation and Decommissioning Technology Remediation and Decommissioning Technology Program Description Program Overview Nuclear power plant operations can lead to releases of radionuclides into the site soil and groundwater that may need to

More information

W R I T T E N S T A T E M E N T O F R U S S E L L A

W R I T T E N S T A T E M E N T O F R U S S E L L A WRITTEN STATEMENT OF RUSSELL A. MELLOR PRESIDENT & CHIEF EXECUTIVE OFFICER YANKEE ATOMIC ELECTRIC COMPANY CONNECTICUT YANKEE ATOMIC POWER COMPANY THE UNITED STATES SENATE ENERGY & NATURAL RESOURCES COMMITTEE

More information

SOLUTIONS. Role of Radioactive Waste Management in D&D. Colin Austin (Senior Vice President, International Business)

SOLUTIONS. Role of Radioactive Waste Management in D&D. Colin Austin (Senior Vice President, International Business) Y SO Role of Radioactive Waste Management in D&D Colin Austin (Senior Vice President, International Business) August 25 th, 2017 Introduction to nergysolutions Acquisition and Integration of Companies

More information

WM2015 Conference, March 15 19, 2015, Phoenix, Arizona, USA

WM2015 Conference, March 15 19, 2015, Phoenix, Arizona, USA Preliminary Evaluation of Removing Used Nuclear Fuel from Shutdown Sites 15568 Steven Maheras *, Ralph Best **, Steven Ross *, Jeff England ***, L. Mel Massaro ****, Philip Jensen * * Pacific Northwest

More information

2014 Decommissioning Cost Analysis of the San Onofre Nuclear Generating Station Units 2 & 3

2014 Decommissioning Cost Analysis of the San Onofre Nuclear Generating Station Units 2 & 3 Document No. 164001-DCE-001 2014 Decommissioning Cost Analysis of the San Onofre Nuclear Generating Station Units 2 & 3 Project No. 164001 Prepared for: Southern California Edison. 2244 Walnut Grove Avenue

More information

Comparison of estimated and actual decommissioning cost of José Cabrera NPP

Comparison of estimated and actual decommissioning cost of José Cabrera NPP Comparison of estimated and actual decommissioning cost of José Cabrera NPP International Conference on the Financing of Decommissioning Stockholm, 20-21 September 2016 Emilio García, Jorge Borque, Adolfo

More information

San Onofre Unit 1 Decommissioning

San Onofre Unit 1 Decommissioning San Onofre Unit 1 Decommissioning Eric M. Goldin, Ph.D., CHP Southern California Edison P. O. Box 128 San Clemente, CA 92674-0128 USA Introduction Nuclear plant decommissioning presents several challenges

More information

Current Status of Shutdown Sites Activities. San Onofre Nuclear Generating Station (SONGS) Site Visit

Current Status of Shutdown Sites Activities. San Onofre Nuclear Generating Station (SONGS) Site Visit Current Status of Shutdown Sites Activities San Onofre Nuclear Generating Station (SONGS) Site Visit Steve Maheras Pacific Northwest National Laboratory Midyear Tribal Caucus Meeting and Quarterly Meeting

More information

WM2016 Conference, March 6 10, 2016, Phoenix, Arizona, USA. Preliminary Evaluation of Removing Used Nuclear Fuel from Shutdown Sites An Update 16057

WM2016 Conference, March 6 10, 2016, Phoenix, Arizona, USA. Preliminary Evaluation of Removing Used Nuclear Fuel from Shutdown Sites An Update 16057 Preliminary Evaluation of Removing Used Nuclear Fuel from Shutdown Sites An Update 16057 Steven Maheras *, Ralph Best **, Steven Ross *, Jeff England ***, L. Mel Massaro ****, Philip Jensen * * Pacific

More information

Nuclear Energy. Nuclear Fuels Storage and Transportation Planning Project Transportation System Development Overview. Matt Feldman

Nuclear Energy. Nuclear Fuels Storage and Transportation Planning Project Transportation System Development Overview. Matt Feldman Nuclear Fuels Storage & Transportation Planning Project Office of Fuel Cycle Technologies Nuclear Energy Nuclear Fuels Storage and Transportation Planning Project Transportation System Development Overview

More information

Testimony On 2016 SONGS 1 Decommissioning Cost Estimate

Testimony On 2016 SONGS 1 Decommissioning Cost Estimate Application No.: Exhibit No.: Witnesses: 16-03-XXX SCE-04 Jose L. Perez (U 338-E) Testimony On 2016 SONGS 1 Decommissioning Cost Estimate Before the Public Utilities Commission of the State of California

More information

Maria Taranger Foto: Kävlinge Municipality

Maria Taranger Foto: Kävlinge Municipality Maria Taranger Foto: Kävlinge Municipality The icon of nuclear power in Sweden The beginning and the end Type: BWR Capacity: 1800 MWt / 615MWe First connection to the grid: May 15, 1975 / March 21, 1977

More information

S z5a MPC&D July 31, U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C

S z5a MPC&D July 31, U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C -1 SMUD SACRAMENTO MUNICIPAL UTILITY DISTRICT 7 P. 0. Box 15830, Sacramento CA 95852-1830, (916) 452-3211 AN ELECTRIC SYSTEM SERVING THE HEART OF CALIFORNIA MPC&D 03-088 July 31, 2003 U. S. Nuclear Regulatory

More information

Lessons Learned from EPRI Decommissioning Program Decommissioning Pre-Planning Overview

Lessons Learned from EPRI Decommissioning Program Decommissioning Pre-Planning Overview Lessons Learned from EPRI Decommissioning Program Decommissioning Pre-Planning Overview Richard McGrath Principal Technical Leader EPRI IAEA Technical Meeting on Plant Life Management During the Transition

More information

BRIEF HISTORY OF THE RETS [RADIOLOGICAL EFFLUENT TECHNICAL SPECIFICATIONS]

BRIEF HISTORY OF THE RETS [RADIOLOGICAL EFFLUENT TECHNICAL SPECIFICATIONS] BRIEF HISTORY OF THE RETS [RADIOLOGICAL EFFLUENT TECHNICAL SPECIFICATIONS] 13 th Annual RETS-REMP Meeting Dr. Jason C. Jang US Nuclear Regulatory Commission June 23-25, 2003 Pittsburgh, Pennsylvania Capturing

More information

DECOMMISSIONING LICENSING PROCESS OF NUCLEAR INSTALLATIONS IN SPAIN

DECOMMISSIONING LICENSING PROCESS OF NUCLEAR INSTALLATIONS IN SPAIN DECOMMISSIONING LICENSING PROCESS OF NUCLEAR INSTALLATIONS IN SPAIN Preparation for decommissioning symposium February 16-18, Lyon France Cristina Correa Sáinz ccos@enresa.es 1 TABLE OF CONTENT TABLE OF

More information

PLANNING FOR THE EARLY RETIREMENT OF THE OYSTER CREEK NUCLEAR GENERATING STATION ENGINEERING ISSUES

PLANNING FOR THE EARLY RETIREMENT OF THE OYSTER CREEK NUCLEAR GENERATING STATION ENGINEERING ISSUES PLANNING FOR THE EARLY RETIREMENT OF THE OYSTER CREEK NUCLEAR GENERATING STATION ENGINEERING ISSUES J. J. Curry Sc.D., P.E. Mgr. Decommissioning Engineering Oyster Creek Nuclear Generating Station Forked

More information

Activities of the NRC s Division of Spent Fuel Management: An Overview

Activities of the NRC s Division of Spent Fuel Management: An Overview Activities of the NRC s Division of Spent Fuel Management: An Overview David W. Pstrak Senior Project Manager Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards

More information

Spent Power Reactor Fuel:

Spent Power Reactor Fuel: Spent Power Reactor Fuel: Pre-Disposal Issues Robert Alvarez Institute for Policy Studies July 16, 2018 Why we should be concerned about spent power reactor fuel. After 60 years (1957-2017), nuclear power

More information

Your Partner for Successful D&D PROVEN PROGRAMS EFFECTIVE TRANSITION WORLD-CLASS PERFORMANCE

Your Partner for Successful D&D PROVEN PROGRAMS EFFECTIVE TRANSITION WORLD-CLASS PERFORMANCE Your Partner for Successful D&D PROVEN PROGRAMS EFFECTIVE TRANSITION WORLD-CLASS PERFORMANCE We understand the complexities, costs, and risks associated with all phases of decommissioning, and we can support

More information

RESUME of SCOTT ATWATER

RESUME of SCOTT ATWATER RESUME of SCOTT ATWATER Scott is a nuclear industry veteran with 37 years of commercial nuclear experience covering 27 nuclear power stations, two Department of Energy sites, and the Nuclear Regulatory

More information

Community Engagement Panel ISFSI Location and Technology Option Update July 17, For internal use only

Community Engagement Panel ISFSI Location and Technology Option Update July 17, For internal use only Community Engagement Panel ISFSI Location and Technology Option Update July 17, 2014 - For internal use only Content Independent Spent Fuel Storage Installation (ISFSI) Location Evaluation Technologies

More information

Status of Decommissioning Preparation for Kori #1

Status of Decommissioning Preparation for Kori #1 Status of Decommissioning Preparation for Kori #1 http://www.khnp.co.kr December 6, 2017 KHNP Overview (1/2) AA (S&P), Aa2 (Moody s) KHNP Overview (2/2) Power Plants Operational status in Korea 24 22,529

More information

NuScale SMR Technology

NuScale SMR Technology NuScale SMR Technology UK IN SMR; SMR IN UK Conference - Manchester, UK Tom Mundy, EVP Program Development September 25, 2014 Acknowledgement & Disclaimer This material is based upon work supported by

More information

Waste Management for Decommissioning of Nuclear Power Plants An EPRI Decommissioning Project Report

Waste Management for Decommissioning of Nuclear Power Plants An EPRI Decommissioning Project Report Waste Management for Decommissioning of Nuclear Power Plants An EPRI Decommissioning Project Report Rich McGrath (Presenter) - EPRI Consulting Employee Rick Reid, PhD - Senior Technical Leader Symposium

More information

CGoEd. June 1, U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555

CGoEd. June 1, U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555 (on'rnonxc alth Edison (Copan, t i I Opus 'Pl:icc I)uDw'rs Grove, 11. ()()5 15-57l)l CGoEd June 1, 1998 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555 Subject:

More information

Spent Fuel Storage: Defining the Problem. Commissioner Tim Echols Georgia Public Service Commission

Spent Fuel Storage: Defining the Problem. Commissioner Tim Echols Georgia Public Service Commission Spent Fuel Storage: Defining the Problem Commissioner Tim Echols Georgia Public Service Commission The Politics of Nuclear Waste Recycling Yucca Mountain Blue Ribbon Commission Source: United States Nuclear

More information

Salem/Hope Creek License Renewal Presentation to the NRC March 16, 2009

Salem/Hope Creek License Renewal Presentation to the NRC March 16, 2009 Salem/Hope Creek License Renewal Presentation to the NRC March 16, 2009 1 Agenda Welcome - Carl Fricker Introductions - Carl Fricker Purpose of the Meeting - Carl Fricker Overview of Salem & Hope Creek

More information

RANCHO SECO DECOMMISSIONING UPDATE

RANCHO SECO DECOMMISSIONING UPDATE John M. Newey, NewRad, Inc. 916-732-4859, 916-732-6095(fax), jnewey@smud.org RANCHO SECO DECOMMISSIONING UPDATE Michael W. Snyder, Superintendent Radwaste Operations, SMUD John M. Newey, CHP, President,

More information

CONNECTICUT YANKEE ATOMIC POWER COMPANY

CONNECTICUT YANKEE ATOMIC POWER COMPANY CONNECTICUT YANKEE ATOMIC POWER COMPANY HADDAM NECK PLANT 362 INJUN HOLLOW ROAD EAST HAMPTON, CT 06424-3099 August 22, 1997 Docket No. 50-213 CY-97-075 Re: 10CFR50.82 U.S. Nuclear Regulatory Commission

More information

Strategy for the Management and Disposal of Used Nuclear Fuel and High-Level Radioactive Waste

Strategy for the Management and Disposal of Used Nuclear Fuel and High-Level Radioactive Waste Strategy for the Management and Disposal of Used Nuclear Fuel and High-Level Radioactive Waste Jeff Williams Project Director Nuclear Fuels Storage and Transportation (NFST) Planning Project U.S. Department

More information

Decommissioning Worldwide and NEA Activities

Decommissioning Worldwide and NEA Activities Decommissioning Worldwide and NEA Activities Claudio Pescatore - Ivo Tripputi NEA Principal Administrator - NEA CPD Management Board Chair WM Symposia, Phoenix, 2-6 March 2014 Decommissioning: what does

More information

S T A T E O F M I C H I G A N BEFORE THE MICHIGAN PUBLIC SERVICE COMMISSION DIRECT TESTIMONY THOMAS S. LAGUARDIA ON BEHALF OF CONSUMERS ENERGY COMPANY

S T A T E O F M I C H I G A N BEFORE THE MICHIGAN PUBLIC SERVICE COMMISSION DIRECT TESTIMONY THOMAS S. LAGUARDIA ON BEHALF OF CONSUMERS ENERGY COMPANY S T A T E O F M I C H I G A N BEFORE THE MICHIGAN PUBLIC SERVICE COMMISSION In the Matter of the Application of ) CONSUMERS ENERGY COMPANY ) for Adjustment of its Surcharges for ) Case No. U-1415 Nuclear

More information

SMART Standard Design Approval inspection result July. 4 th

SMART Standard Design Approval inspection result July. 4 th SMART Standard Design Approval inspection result 2012. July. 4 th Content Ⅰ. Inspection outline. 1 Ⅱ. Inspection proceedings 2 Ⅲ. SMART Standard Design features. 3 Ⅳ. Standard Design inspection result

More information

SYSTEMATIC APPROACH FOR DECOMMISSIONING PLANNING AND ESTIMATING

SYSTEMATIC APPROACH FOR DECOMMISSIONING PLANNING AND ESTIMATING ABSTRACT SYSTEMATIC APPROACH FOR DECOMMISSIONING PLANNING AND ESTIMATING A. Scott Dam, P. E. JUPITER Corporation 2730 University Boulevard West, Suite 900 Wheaton, MD 20702 Nuclear facility decommissioning,

More information

San Onofre Nuclear Generating Station Units 2 and 3 Post-Shutdown Decommissioning Activities Report

San Onofre Nuclear Generating Station Units 2 and 3 Post-Shutdown Decommissioning Activities Report TABLE OF CONTENTS I. INTRODUCTION AND SUMMARY... 4 A. INTRODUCTION... 4 1. Community Engagement... 4 2. Regulatory Basis... 5 B. BACKGROUND... 6 C. SUMMARY OF DECOMMISSIONING ALTERNATIVES... 7 II. DESCRIPTION

More information

Post Shutdown Decommissioning Activities Report Vermont Yankee Nuclear Power Station Docket No License No. DPR-28

Post Shutdown Decommissioning Activities Report Vermont Yankee Nuclear Power Station Docket No License No. DPR-28 Entergy Nuclear Operations, Inc. Vermont Yankee 320 Governor Hunt Rd Vernon, VT 05354 Tel 802 257 7711 BVY 14-078 Christopher J. Wamser Site Vice President 10 CFR 50.82(a)(4) December 19, 2014 U.S. Nuclear

More information

Nuclear Energy. Consolidated Interim Storage Facility Design Concepts In the United States. Nuclear Fuels Storage and Transportation Planning Project

Nuclear Energy. Consolidated Interim Storage Facility Design Concepts In the United States. Nuclear Fuels Storage and Transportation Planning Project Consolidated Interim Storage Facility Design Concepts In the United States Nuclear Fuels Storage & Transportation Planning Project Office of Fuel Cycle Technologies Nuclear Energy Nuclear Fuels Storage

More information

RANCHO SECO PLANNING FOR LARGE COMPONENTS

RANCHO SECO PLANNING FOR LARGE COMPONENTS RANCHO SECO PLANNING FOR LARGE COMPONENTS Dennis E. Gardiner, Decommissioning Project Manager, SMUD John M. Newey, CHP, President, NewRad, Inc. Michael W. Snyder, Superintendent Radwaste Operations, SMUD

More information

The Electric Power Research Institute (EPRI) is the

The Electric Power Research Institute (EPRI) is the EPRI s Decommissioning Technology Program The EPRI Decommissioning Technology Program assists nuclear plant operators in their efforts to minimize the cost and risks of decommissioning through enhanced

More information

Interim Storage of Used Nuclear Fuel. The Nuclear Energy Institute

Interim Storage of Used Nuclear Fuel. The Nuclear Energy Institute Interim Storage of Used Nuclear Fuel January 2008 The Nuclear Energy Institute NEI is the organization responsible for establishing unified nuclear industry policy on matters affecting the nuclear energy

More information

Best practices for preparing vessel internals segmentation projects

Best practices for preparing vessel internals segmentation projects Best practices for preparing vessel internals segmentation projects Joseph BOUCAU a*, Per SEGERUD b, Moisés SANCHEZ c a Westinghouse Electric Company, 43 rue de l Industrie, 1400 Nivelles, Belgium b Westinghouse

More information

FIG. 1. Fort St. Vrain Nuclear Generation Station.

FIG. 1. Fort St. Vrain Nuclear Generation Station. Invited Paper XA9848067 FORT ST. VRAIN DECOMMISSIONING PROJECT M. FISHER Public Service Company of Colorado, Denver, Colorado, USA Abstract Public Service Company of Colorado (PSCo), owner of the Fort

More information

Spent Nuclear Fuel and Low Level Radioactive Waste: Current and Future Storage Options

Spent Nuclear Fuel and Low Level Radioactive Waste: Current and Future Storage Options Spent Nuclear Fuel and Low Level Radioactive Waste: Current and Future Storage Options State of Vermont: Senate Committee on Finance, and Senate Committee on Natural Resources and Energy October 26, 2009

More information

WM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA

WM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA Waste Management System Architecture Evaluations 14564 William Nutt *, Edgar Morris *, Francesc Puig *, Robert Howard **, Joshua Jarrell **, Robert Joseph III **, Thomas Cotton *** * Argonne National Laboratory

More information

IMPACT OF LACK OF CONSISTENT FREE RELEASE STANDARDS ON DECOMMISSIONING PROJECTS AND COSTS

IMPACT OF LACK OF CONSISTENT FREE RELEASE STANDARDS ON DECOMMISSIONING PROJECTS AND COSTS ABSTRACT IMPACT OF LACK OF CONSISTENT FREE RELEASE STANDARDS ON DECOMMISSIONING PROJECTS AND COSTS Jas S. Devgun, Ph.D. Senior Project Engineer/Program Manager Sargent & Lundy LLC 55 E. Monroe St. Chicago,

More information

ROMANIA National Commission for Nuclear Activities Control (CNCAN) Report. on in Decommissioning Activities. Dr. Lucian BIRO Director General

ROMANIA National Commission for Nuclear Activities Control (CNCAN) Report. on in Decommissioning Activities. Dr. Lucian BIRO Director General ROMANIA National Commission for Nuclear Activities Control (CNCAN) Progress in Report on in Decommissioning Activities Dr. Lucian BIRO Director General IAEA R²D²P Workshop on Cost Estimates Manila, 30

More information

Decommissioning of Nuclear Installations

Decommissioning of Nuclear Installations Decommissioning of Nuclear Installations Definition of Decommissioning The administrative and technical actions taken to allow the removal of some or all of the regulatory controls from a nuclear facility

More information

EDF DECOMMISSIONING PROGRAMME - A PREREQUISITE FOR THE ERECTION OF NEW NUCLEAR POWER PLANTS IN FRANCE

EDF DECOMMISSIONING PROGRAMME - A PREREQUISITE FOR THE ERECTION OF NEW NUCLEAR POWER PLANTS IN FRANCE EDF DECOMMISSIONING PROGRAMME - A PREREQUISITE FOR THE ERECTION OF NEW NUCLEAR POWER PLANTS IN FRANCE J.-J. Grenouillet Electricité de France Dismantling, Waste management & Environment Engineering Center

More information

Introduction. Status of Worldwide Nuclear Power Plants*

Introduction. Status of Worldwide Nuclear Power Plants* KAIF-JAIF 24 th International Joint Forum Conference Nuclear on Structural Power Plant Mechanics Safety and in Decommissioning Reactor Technology 1 Introduction Status of Worldwide Nuclear Power Plants*

More information

Supplemental Testimony of Southern California Edison and San Diego Gas & Electric Regarding Updates to the Milestone Framework

Supplemental Testimony of Southern California Edison and San Diego Gas & Electric Regarding Updates to the Milestone Framework Application No.: 8-0-009 Exhibit No.: SCE-SDGE-0 J. Perez, SCE S. Garcia, SDGE (U 8-E) Supplemental Testimony of Southern California Edison and San Diego Gas & Electric Regarding Updates to the Milestone

More information

REPORT ON THE DECOMMISSIONING OF THE JOSÉ CABRERA NPP

REPORT ON THE DECOMMISSIONING OF THE JOSÉ CABRERA NPP 2010 REPORT ON THE DECOMMISSIONING OF THE JOSÉ CABRERA NPP performed Activities 2010-2015 2015 ISSUED BY Empresa Nacional de Residuos Radiactivos S.A. C/ Emilio Vargas 7, 28043 Madrid. www.enresa.es Text

More information

Safety and Licensing for Decommissioning

Safety and Licensing for Decommissioning Safety and Licensing for Decommissioning Simon Bastin Manager Systems Safety and Reliability, ANSTO & Alamgir Kabir Systems Safety and Reliability Analyst, ANSTO Outline Background Moata Licensing requirements

More information

THE ROLE OF THE WORLD'S LARGEST INTERIM STORAGE FOR WASTE AND FUEL WITHIN THE DECOM PROJECT OF 6 WWER REACTORS IN GREIFSWALD AND RHEINSBERG (GERMANY)

THE ROLE OF THE WORLD'S LARGEST INTERIM STORAGE FOR WASTE AND FUEL WITHIN THE DECOM PROJECT OF 6 WWER REACTORS IN GREIFSWALD AND RHEINSBERG (GERMANY) THE ROLE OF THE WORLD'S LARGEST INTERIM STORAGE FOR WASTE AND FUEL WITHIN THE DECOM PROJECT OF 6 WWER REACTORS IN GREIFSWALD AND RHEINSBERG (GERMANY) Hartmann, Burkhard Leushacke, Dieter F. Dr Energiewerke

More information

NUCLEAR REGULATORY COMMISSION. [Docket Nos and ; NRC ] Entergy Nuclear Indian Point Unit 2, LLC

NUCLEAR REGULATORY COMMISSION. [Docket Nos and ; NRC ] Entergy Nuclear Indian Point Unit 2, LLC This document is scheduled to be published in the Federal Register on 07/13/2012 and available online at http://federalregister.gov/a/2012-17110, and on FDsys.gov [7590-01-P] NUCLEAR REGULATORY COMMISSION

More information

Spent Power Reactor Fuel:

Spent Power Reactor Fuel: Spent Power Reactor Fuel: Pre-Disposal Issues Robert Alvarez Johns Hopkins School of Advanced International Studies April 29, 2017 Spent nuclear power fuel is bound up in more than 244,000 long rectangular

More information

TABLE OF ACRONYMS / ABBREVIATIONS

TABLE OF ACRONYMS / ABBREVIATIONS Page vi of xxi TABLE OF ACRONYMS / ABBREVIATIONS Atomic Industrial Forum document delineating a AIF/NESP-036 standardized cost estimating model for decommissioning ALARA As-Low-As-Reasonably-Achievable

More information

ICEM DEVELOPMENT OF THE ENVI SIMULATOR TO ESTIMATE KOREAN SNF FLOW AND ITS COST

ICEM DEVELOPMENT OF THE ENVI SIMULATOR TO ESTIMATE KOREAN SNF FLOW AND ITS COST Proceedings of the 12 th International Conference on Environmental Remediation And Radioactive Waste Management ICEM 2009 October 11-15, 2009, Liverpool, England, UK ICEM 2009 16060 DEVELOPMENT OF THE

More information

CHARACTERISTICS AND COMMON VULNERABILITIES INFRASTRUCTURE CATEGORY: NUCLEAR SPENT FUEL STORAGE FACILITIES

CHARACTERISTICS AND COMMON VULNERABILITIES INFRASTRUCTURE CATEGORY: NUCLEAR SPENT FUEL STORAGE FACILITIES CHARACTERISTICS AND COMMON VULNERABILITIES INFRASTRUCTURE CATEGORY: NUCLEAR SPENT FUEL STORAGE FACILITIES Protective Security Division Department of Homeland Security Version 2, September 22, 2003 Introduction

More information

Ignalina NPP. Ignalina NPP decommissioning activities are co-financed by European Union

Ignalina NPP. Ignalina NPP decommissioning activities are co-financed by European Union Workshop on Decommissioning of Uranium Contaminated Facilities, Pretoria, SAF 22-26 August 2011 Ignalina Ignalina overview I Decommissioning Strategy What are we going to do? How are we going to do it?

More information

The Question of Queue: Implications for Best Practice in Cross-country Transport of Commercial Spent Nuclear Fuel 9402

The Question of Queue: Implications for Best Practice in Cross-country Transport of Commercial Spent Nuclear Fuel 9402 WM2009 Conference, March 1-5, 2009, Phoenix, AZ The Question of Queue: Implications for Best Practice in Cross-country Transport of Commercial Spent Nuclear Fuel 9402 ABSTRACT J. M. Williams Western Interstate

More information

The Question of Queue: Implications for Best Practice in Cross-country Transport of Commercial Spent Nuclear Fuel 9402

The Question of Queue: Implications for Best Practice in Cross-country Transport of Commercial Spent Nuclear Fuel 9402 Copyright by WM Symposia, Inc. All Rights Reserved. Reprinted with permission. The Question of Queue: Implications for Best Practice in Cross-country Transport of Commercial Spent Nuclear Fuel 9402 ABSTRACT

More information

Watts Bar Nuclear Plant Unit 2 Completion Project

Watts Bar Nuclear Plant Unit 2 Completion Project Watts Bar Nuclear Plant Unit 2 Completion Project Ninth Quarterly Update to the Estimate to Complete May - July 2014 Published October 2014 Table of Contents Section 1 - Executive Summary... 3 Section

More information

Applicability of EPRI Decommissioning Pre-Planning Manual to International Decommissioning Projects

Applicability of EPRI Decommissioning Pre-Planning Manual to International Decommissioning Projects Applicability of EPRI Decommissioning Pre-Planning Manual to International Decommissioning Projects Leo Lessard Manager, Commercial Decommissioning Operations, AREVA Inc. 16th February 2016 International

More information

Plant Life Management in Transition from Operation to Decommissioning of Nuclear Power Plants. National experience, Finland.

Plant Life Management in Transition from Operation to Decommissioning of Nuclear Power Plants. National experience, Finland. Plant Life Management in Transition from Operation to Decommissioning of Nuclear Power Plants. National experience, Finland. Jari Tuunanen, 30 Aug.2016 Contents Background Status of decommissioning plans

More information

Decommissioning three main strategies: Immediate dismantling, Safe enclosure (Deferred dismantling), Entombment

Decommissioning three main strategies: Immediate dismantling, Safe enclosure (Deferred dismantling), Entombment : Immediate dismantling, Safe enclosure (Deferred dismantling), Entombment Dr. M Knaack TÜV NORD GmbH, Hamburg / Germany Overwiew Decommissioning when and why? Law, regulations and guidelines Three main

More information

15 April 2015 Nuclear Regulation Authority, Japan. 1. Overview

15 April 2015 Nuclear Regulation Authority, Japan. 1. Overview Evaluation of the report of Tokyo Electric Power Company regarding the inflow of water that accumulated in the process main building into the incineration building at the Fukushima Daiichi Nuclear Power

More information

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona USA. Progress in Decommissioning the Humboldt Bay Power Plant 13604

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona USA. Progress in Decommissioning the Humboldt Bay Power Plant 13604 Progress in Decommissioning the Humboldt Bay Power Plant 13604 Kerry Rod*, Steven K. Shelanskey ** and Dr. John Kristofzski *** * PG&E Utility, Humboldt Bay Power Plant, 1000 King Salmon Ave. Eureka, CA

More information

NDT AUDIT Z LLC. An EnergySoluitons Company. Audit Status. Interviewed 3 Finalist. Close to Awarding the Audit

NDT AUDIT Z LLC. An EnergySoluitons Company. Audit Status. Interviewed 3 Finalist. Close to Awarding the Audit NDT AUDIT OLUT Audit Status Mailed RFP to 8 Chicago Area CPA Firms Interviewed 3 Finalist Close to Awarding the Audit Commence ASAP to Ensure Report by Year End 33 Design Standards for ISFSI OLUT 34 Now

More information

Considerations for Disposition of Dry Cask Storage System Materials at End of Storage System Life

Considerations for Disposition of Dry Cask Storage System Materials at End of Storage System Life Considerations for Disposition of Dry Cask Storage System Materials at End of Storage System Life Nuclear Fuels Storage & Transportation Planning Project Office of Fuel Cycle Technologies Nuclear Energy

More information

LLC An EnergySolutions Company. ZCAP Update

LLC An EnergySolutions Company. ZCAP Update An EnergySolutions Company CAP Update May 21, 2012 Agenda Status update of the project Overview of Reactor Vessel Internals Segmentation Environmental update 2 2012 Safety Statistics 2012 Statistics 6

More information

Risks of long term irradiated. on site at nuclear power plants

Risks of long term irradiated. on site at nuclear power plants Risks of long term irradiated MOX fuel storage in pools on site at nuclear power plants Kevin Kamps Radioactive Waste Watchdog Beyond Nuclear August, 2010 Irradiated nuclear fuel pool storage in the U.S.

More information

The Social and Economic Impacts of Nuclear Power Plant Closures Jonathan Cooper & Jen Stromsten Institute for Nuclear Host Communities

The Social and Economic Impacts of Nuclear Power Plant Closures Jonathan Cooper & Jen Stromsten Institute for Nuclear Host Communities The Social and Economic Impacts of Nuclear Power Plant Closures Jonathan Cooper & Jen Stromsten Institute for Nuclear Host Communities Presentation to the Indian Point Task Force Cortlandt Manor, New York

More information

Spanish strategy for the management of Spent Nuclear Fuel ATC Project. IAEA, Vienna, June 2015

Spanish strategy for the management of Spent Nuclear Fuel ATC Project. IAEA, Vienna, June 2015 Spanish strategy for the management of Spent Nuclear Fuel ATC Project IAEA, Vienna, June 2015 1 Contents Nuclear Energy in Spain Overview SNF& HLW Management Policy Interim Storage at Reactor Sites Centralized

More information

CONNECTICUT YANKEE UPDATE. February 20, 2002 DECOMMISSIONING UPDATE. Decommissioning Activities:

CONNECTICUT YANKEE UPDATE. February 20, 2002 DECOMMISSIONING UPDATE. Decommissioning Activities: CONNECTICUT YANKEE UPDATE KEN HEIDER February 20, 2002 DECOMMISSIONING UPDATE Decommissioning Activities: Containment?? Sluicing garnet to High Integrity Containers (HIC) continues and the 11 th debris

More information

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C SAFETY EVALUATION REPORT

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C SAFETY EVALUATION REPORT UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 SAFETY EVALUATION REPORT Docket No. 72-1040 HI-STORM UMAX Canister Storage System Holtec International, Inc. Certificate of Compliance

More information

Waste Management Nuclear Project Management Training course, Managing Risks in Projects, Dr. Jas Devgun

Waste Management Nuclear Project Management Training course, Managing Risks in Projects, Dr. Jas Devgun 1 RESUME OF ALEXANDER M. HAY EDUCATION: 1996 University of New Haven Engineering Sciences 1979 University of Maine at Orono Engineering Sciences Waste Management Nuclear Project Management Training course,

More information

Economic Analysis of the Modular Pebble Bed Reactor

Economic Analysis of the Modular Pebble Bed Reactor Pebble Bed Reactor Project MIT Nuclear Engineering Department Economic Analysis of the Modular Pebble Bed Reactor These slides present the conclusions of a preliminary study based d on existing cost data

More information

Decommissioning Pilgrim What is Decommissioning, and What Should be Done to Protect our Communities?

Decommissioning Pilgrim What is Decommissioning, and What Should be Done to Protect our Communities? Mary Lampert Pilgrim Watch Decommissioning Pilgrim What is Decommissioning, and What Should be Done to Protect our Communities? Overview What is likely to happen at Pilgrim? Spent Fuel Site Restoration

More information

BIG ROCK POINT DECOMMISSIONING. Ken Powers, site general manager Tim Petrosky, public affairs director

BIG ROCK POINT DECOMMISSIONING. Ken Powers, site general manager Tim Petrosky, public affairs director ABSTRACT BIG ROCK POINT DECOMMISSIONING Ken Powers, site general manager Tim Petrosky, public affairs director Consumers Energy s Big Rock Point station was our country s fifth commercial nuclear plant

More information

Fukushima Accident Summary(4) 2011-August-02, Ritsuo Yoshioka

Fukushima Accident Summary(4) 2011-August-02, Ritsuo Yoshioka No.58 Fukushima Accident Summary(4) 2011-August-02, Ritsuo Yoshioka 3.4 Fukushima-4 Reactor When the earthquake and tsunami occurred on March 11th, Fukushima Unit 4 (F4) was in its periodic shut-down stage,

More information

Decommissioning in Germany: Greifswald NPPs. Bernd Rehs Federal Office for Radiation Protection (BfS)

Decommissioning in Germany: Greifswald NPPs. Bernd Rehs Federal Office for Radiation Protection (BfS) Decommissioning in Germany: Greifswald NPPs Bernd Rehs Federal Office for Radiation Protection (BfS) 12 th Meeting of the Working Party on Decommissioning and Dismantling (WPDD), 15 th -17 th November

More information

RADIOACTIVE WASTE AND MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES SWEDEN [2010] NATIONAL NUCLEAR ENERGY CONTEXT

RADIOACTIVE WASTE AND MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES SWEDEN [2010] NATIONAL NUCLEAR ENERGY CONTEXT RADIOACTIVE WASTE AND MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES SWEDEN [2010] NATIONAL NUCLEAR ENERGY CONTEXT Commercial utilisation of nuclear power in Sweden started in 1972 and as of 2010 ten

More information

DESIGNING DECOMMISSIONING INTO NEW REACTOR DESIGNS 1

DESIGNING DECOMMISSIONING INTO NEW REACTOR DESIGNS 1 DESIGNING DECOMMISSIONING INTO NEW REACTOR DESIGNS 1 Dr. J.S. Devgun, Ph.D., CHMM Nuclear Power Technologies Sargent & Lundy LLC 55 E. Monroe St Chicago, IL 60603 U.S.A. ABSTRACT One of the lessons learned

More information

Safety and Security of Spent Fuel Storage in the United States Edwin Lyman Senior Scientist Union of Concerned Scientists

Safety and Security of Spent Fuel Storage in the United States Edwin Lyman Senior Scientist Union of Concerned Scientists Safety and Security of Spent Fuel Storage in the United States Edwin Lyman Senior Scientist Union of Concerned Scientists Presentation to the NAS Fukushima Lessons Learned Panel (Phase 2) Washington, DC

More information

A Liquidation Strategy of Fukushima Daiichi Nuclear Power Plant: A new In-Situ Entombment Plan proposed

A Liquidation Strategy of Fukushima Daiichi Nuclear Power Plant: A new In-Situ Entombment Plan proposed A Liquidation Strategy of Fukushima Daiichi Nuclear Power Plant: A new In-Situ Entombment Plan proposed May 27, 2011 Satoshi Sato satoshi@sato@iacdc.com International Access Corporation Abstract I studied

More information

June 28, 2013 TM CFR CFR 50.82

June 28, 2013 TM CFR CFR 50.82 OGP(F mý NUCLEAR June 28, 2013 TM1-1 3-041 10 CFR 50.51 10 CFR 50.82 GPU Three Nuclear, Mile Island Inc. Nuclear Station Route 441 South Post Office Box 480 Middletown, PA 17057-0480 Tel 717-948-8461 Attn:

More information

Licensing a Centralized Spent Fuel Storage Facility

Licensing a Centralized Spent Fuel Storage Facility International Workshop on the Development and Application of a Safety Case for Dual Purpose Casks for Spent Nuclear Fuel. IAEA Headquarters. Vienna, Austria. Licensing a Centralized Spent Fuel Storage

More information