EIA for Proposed Additional Butibori Industrial Area, Tehsil and District Nagpur, State Maharashtra.
|
|
- Delphia Carroll
- 6 years ago
- Views:
Transcription
1 PUBLIC CONSULTATION PUBLIC HEARING According to EIA Notification 2006 and its subsequent amendments, the proposed project comes under the project activity of 7 (c) & (a), Industrial estates /parks, complexes/area export processing zone (EPZs), Special Economic Zones (SEZs), Biotech park, Leather Complexes and Building & Construction projects under category A (Special condition apply) and is located at Butibori Industrial Area, Tehsil, District Nagpur, MIDC Nagpur has therefore initiated the process of Environmental Clearance and as per above notification, Public Hearing process was initiated on submission of draft EIA report along with executive summary English and Marathi to State Pollution Control Board. The public hearing was conducted on 10/7/2015 at Shree Hanuman Mandir Devsthan Sabhagruh, Dudha Grampanchayat (Dudha-Mangli) Tehsil and District Nagpur under the Chairmanship of Shri Ravindra Kumbhare Addl. District Magistrate (A representative nominated by the District Collector, Nagpur). Shri Kiran Hasabnis, Sub-Regional Officer, Maharashtra Pollution Control Board, Nagpur-2, acted as a Convener of the Environmental Public Hearing Panel. Shri Atul P. Satfale, Field Officer, a representative of Regional Officer, MPCB Board, started public hearing processing at 3.00 p.m. with the permission of Chairman of the Public Hearing Panel. Attendance sheet was circulate and attached as Annexure VII. With the permission of chairman of Public Hearing, Shri Mahindra Pattebahadur, Field Officer, MPCB, Nagpur welcomed the Chairman and Member of the Public Hearing Panel, local citizens from the villages and others present. He explained the purpose of conducting this public hearing that as per MOEF, GOI, Notification SO 60(E), of 27 th January, 1994 and amended on 14 th Sept The notices of the public hearing were published in two local widely circulated newspapers i.e. the Hitavada (English) and Tarun Bharat (Marathi) on 8 th June Copies of the advertisement are enclosed as Annexure VIII. Copies of the executive summary / EIA summery containing salient features of the projects and EIA both in English and in Marathi and other information / documents were made available to the public by making these documents available in various Govt. offices as well as local Gram Panchayat as per MoEF, GOI, Notification. Suggestions, comments and objections of the public were called in writing before the date of Public Hearing from the publication of the notice. The public hearing panel was constituted vide MPC Board s Office Order No. E-196/2015 vide letter no.bo/jd (WPC/PH/B-2895) dtd.26/06/2015. A copy of the same is enclosed as Annexure IX. Shri Mahendra Pattebahadur, Field Officer, Sub- Regional Office, MPCB, Nagpur-II requested to Project Proponent to give detailed presentation about the project. Thereafter, representative of the project proponent explained in local language regarding Proposed Project, Need of Environmental Clearance and approval, Project, Project location map, Map showing project site, Arial view of the project site, Index map, Map showing irrigation area, Map showing catchment area, Salient features of the project, Project site environmental monitoring, location map of 10 km radius, Environmental setting of study area, Monitoring sites for Air, Water and Noise, Map chowing Air directions, Air Environment, Water Environment, Noise Environment, Soil Environment, Environment Impact on nearby area, Benefits of the project, Development programme, Socio Economic Environment and management plan to mitigate the adverse impacts arising due to project activities was presented. Public Haring 1
2 Shri Kiran Hasabnis, Sub- Regional Officer-2, MPCB Nagpur and Convener of the Environmental Public Hearing Panel with permission of the Chairman requested public present to put their views / opinions in free manner. The issues raised by the public and clarification given by the proponent / consultant are presented below. ISSUES AND COMPLIANCE OF PUBLIC HEARING Sr. Name of the No. person 1. Shri Sudhir Hande, Village Dudha Issues Change in name as Dudha Industrial Area, Instead of Additional Butibori industrial Area. Demand of School, Temple and Parking place in Dudha village Clarification Not possible as the name has been recorded in the MIDC proposal itself MIDC will create the facilities in association with the incoming industries. Related to demand of road near Dudha, the proposal is in consideration with MIDC Employment to one person whose land is acquired Provision will be made in association with the incoming industries 2. Shri Babarao Hande Village Dudha 3. Shri Mohan Deoraoji Village Dudha 4. Shri Manoj Aatram Village Dudha Land acquired at the rate of Rs.13 lacs per acre, but demand is for Rs 17 lacs per acre, payment of difference in balance Rs. 4 lacs Related to employment of village people specially young generation Availability of transport facility Large scale industries should be away from the village Development of village in the area Related to pollution problem due to proposed additional Butibori Industrial Area Development Payment has been made already as per decision taken by MIDC in consultation with the collector MIDC will take care of employment to the youth of the villages. MIDC will insist the incoming industries to make provision for employment of local people in their industries Not in the purview of MIDC. However connectivity of roads will be made available Provision will be made regarding large scale industries away from the villages MIDC will take care of this. Proper facilities related to the development will be provided by MIDC Proper measures will be taken by the incoming industries and MPCB will be taking care to monitor the pollution load and will take action accordingly Public Haring 2
3 Sr. Name of the No. person 5. Shri Nitin lonkar Secretary, Butibori Manufacturing Association Issues Training to skilled labour creation of of std 10 th and 12 th pass out Capacity of CETP be increased to 10 MLD Establishment of ESIS Hospital in Industrial Area Proposed metro train facility up to Butibori Construction of a separate road way from Nagpur Airport to Butibori Industrial Area Clarification Provision will be made through incoming industries for training to skilled labour Provision has already been made to build-up CETP as per central Govt. rule A proposal for giving plot for ESIS Hospitals under consideration. The proposal has already sent to HQ for approval Not in purview of MIDC Not in purview of MIDC Request for flyover Not in purview of MIDC 6. Vidarbha Jankalyan & Vikas Santha 1st Floor, Gokul- Gopal Enclave, Mate Square, Gopal Nagar, Nagpur 1. Planning and development of world class exhibition cum convention center with full amenities in an area of 25 Ha. This will help the local industries and the other Indian industries to showcase their products. Min 25 Hec. area is must considering the future demands. 2. Metro rail up to Butibori (under the jurisdiction of metro-rail authority), Network covering main points in Butibori MIDC as a whole. 3. Well-equipped ESIC hospitals with 24 hourly emergency preparedness facilities. 4. Strengthening of city bus services covering entire Butibori area, with separate provision of Bus station (park). 5. Grant of incentives to existing industrial Butibori for solar power generation, providing one Most of the issues are already taken in to consideration is the planning stage however regarding issues 2,5,7 MIDC will discuss with authority and accordingly action will be taken. Public Haring 3
4 Sr. No. Name of the person 7. Butibori Manufacturers Association Udyam P- 5 Midc Industrial Area Near Fire Station, Butibori, Nagpur Issues window clearance for speedy industrial growth. State Government to evolve special policy for Butibori MIDC considering backward region with incentives/subsidy, as the cost of electricity is higher as compared to adjoining states. 6. Providing reflective sign boards with plot nos and directions at all main turning points in Butibori MIDC area for easy traceability. 7. Planning new approach road to Butibori via Airport, Shivangaon, Mihan, via Gumgaon, Kirmiti. This will curtail nearly 12 Km distance there by saving precious time and fuel on daily basis Mihan and PWD authorities should be involved. 1. Planning and development of world class exhibition cum convention center with amenities, in an area of 25 Ha. This will help the local industries and the other Indian industries to showcase their products and promote economic activities. There is no such adequate center in MIDC at present. Min 25 Hec area is must considering the future demands. 2. Strengthening of existing electrical supply in order to regulate power on 24X7 hourly basis. Presently electrical cost is almost double than the adjoining states. Maharashtra Government should consider special incentives/subsidy due to enhanced cost to Many industries have migrated to Clarification Most of the points/ issues are taken care in the MIDC policy decision and action plan. However for issues 2, 3 (e, g, k, n) and 4, MIDC will discuss with the authority and accordingly action will be take Public Haring 4
5 Sr. No. Name of the person Issues adjoining state due to lack of attention of policy makers despite ample coal and thermal power availability in the region. This disparity must be overcome at the earliest possible time. 3. Strengthening the utilities of existing and proposed MIDC covering the followings a) DG set back-up for entire water supply system as an auxiliary energy source. b) For existing and proposed wastewater treatment, tertiary treatment for CETP for better augmentation and recycling system to comply zero discharge norms being a statutory requirements. c) Policy for provision for drinking water outlets for pedestrian as desired by industries at selected locations. Local industry to take up this activity as their CSR. d) Road widening is to 5-6 meters in Butibori food park area, as the existing road width is just 3 meters which is inadequate creating traffic congestion. Existing foot paths should be removed for road widening, as it is unutilized. e) Metro rail up to key covering areas of Butibori (under the jurisdiction of metro-rail authority), Network covering main points in Butibori MIDC as whole. f) Well-equipped ESIC hospitals with 24 hourly emergency preparedness facilities with accessibility to the surrounding local people. g) Strengthening of city bus services covering entire Butibori area, with separate provision of Bus station Clarification Public Haring 5
6 Sr. No. Name of the person Issues (park). h) Strengthening of greenbelt and landscaping with proper maintenance throughout the year in road side, PU land and increase in aesthetics of the Butibori MIDC area. i) Proper maintenance of storm water drainage lines and regular maintenance before rainy season to avoid water logging in low lying areas. j) Strengthening of streetlights using LED and stress on solar system on identified locations (Road side, traffic signals and vehicle parks). k) Grant of incentives to existing industrial Butibori for solar power generation, providing one window clearance for speedy industrial growth. State Government to evolve special policy for Butibori MIDC considering backword region with incentives/subsidy l) Providing reflective sign boards with plot nos and directions at all main turning points in Butibori MIDC area for easy traceability for commuters. m) Traffic nuisance due to movement of heavy trailers driving in wrong direction creates fear of accident, recent repeated episodes are the evidences and permanent solution to provide in consultation with concerned authorities n) Planning new approach road to Butibori via Airport, Shivangaon, Mihan, via Gumgaon, Kirmiti. This will curtail nearly 12 Km distance there by saving precious time and fuel on daily basis. Clarification Public Haring 6
7 Sr. No. Name of the person Issues o) Proper measures as per the industry specific for pollution abatement avoiding odour and smell problems at few hot spots (MIDC, SPCB and PP in association) 4. There is heavy traffic congestion at the point of entry to Butibori MIDC in front of Butibori Police Station. All the heavy vehicles, Buses, local vehicles pass through Road there by creating a traffic chaos. This location has also became an accident prone Zone. Hence we demand that a Fly-over be constructed on this spot so that Heavy vehicles and other traffic which does not enter Butibori MIDC can pass over this Fly over there by easing the traffic at the entrance of Butibori MIDC. Clarification Shri Ravindra Kumbhare, Additional Dist. Magistrate and Chairman of the Public Hearing panel said that there is only point related to the large industrial set up away from the villages, which will be taken care by MIDC. Other points i.e. land acquisition, control of air and water pollution which will be solved at the local level and MIDC will play a positive role. The chairman thanks the MIDC authorities, MPCB authorities, consultant and public who had attended the public hearing and Mr Mahendra Pattebahadur, Field Officer, Sub- Regional office II MPCB, Nagpur declared the Public Hearing is over with thanks to chair. Public Hearing photographs are shown in Plate 1. Public Haring 7
8 Public Haring 8
9 PLATE 7.1: PHOTOGRAPHS SHOWING PUBLIC HEARING Public Haring 9
10 PLATE 7.1: PHOTOGRAPHS SHOWING PUBLIC HEARING (Contd...) Public Haring 10
11 Annexure-VII PH Attendance Sheet AN-VII-1
12 Annexure-VII PH Attendance Sheet AN-VII-2
13 Annexure-VII PH Attendance Sheet AN-VII-3
14 Annexure-VII PH Attendance Sheet AN-VII-4
15 Annexure-VII PH Attendance Sheet AN-VII-5
16 Annexure-VII PH Attendance Sheet AN-VII-6
17 Annexure-VII PH Attendance Sheet AN-VII-7
18 Annexure-VIII PH Advertisement AN-VIII-1
19 Annexure-VIII PH Advertisement AN-VIII-2
20 Annexure-IX PH Panel AN-IX-1
21 Annexure-IX PH Panel AN-IX-2
ENVIRONMENTAL IMPACT ASSESSMENT AND YOU
ENVIRONMENTAL IMPACT ASSESSMENT AND YOU PARTICIPATING IN PUBLIC CONSULTATIONS FOR: COAL FUELED THERMAL POWER PLANTS C A G Citizen consumer and civic Action Group 1. What are Thermal Power Plants? Electricity
More informationSIX MONTHLY COMPLIANCE REPORT JUNE- 2015
Six Monthly Compliance Report June-2015 M/s Mahagun Real Estate Pvt. Ltd SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 Group Housing Complex Mahagunpuram AT VILLAGE Mehrauli, Dasna, Ghaziabad, U.P. Being developed
More informationADDITIONAL STUDIES PUBLIC CONSULTATION As per EIA notification 14 th September 2006 and ToR issued by Expert Appraisal Committee (EAC) Ministry
ADDITIONAL STUDIES 7 7.1. PUBLIC CONSULTATION As per EIA notification 14 th September 2006 and ToR issued by Expert Appraisal Committee (EAC) Ministry of Environment, Forest and Climate Change (MoEFCC),
More informationPre-Feasibility Report For
Pre-Feasibility Report For Proposed New Project for manufacturing of Intermediates of Agro Chemicals & Synthetic Organic Chemicals. By M/s. MANBRO POLYMERS LIMITED, Plot No. D-2/CH-275, INDUSTRIAL ESTATE,
More informationANNEXURE-6. Public Hearing details such as Advertisement, Minutes of PH, Attendance sheet, photographs and query & answer raised in public hearing
ANNEXURE-6 Public Hearing details such as Advertisement, Minutes of PH, Attendance sheet, photographs and query & answer raised in public hearing Advertisement Minutes of Public Hearing Photographs
More informationShri Gurudatt Sugars Ltd., Gat No. 61/A, Akiwat - Takaliwadi Road, Takaliwadi , Taluka - Shirol, Dist Kolhapur, Maharashtra
Shri Gurudatt Sugars Ltd., Gat No. 61/A, Akiwat - Takaliwadi Road, Takaliwadi - 416108, Taluka - Shirol, Dist Kolhapur, Maharashtra Compliance of Conditions Stipulated in environmental clearance granted
More informationSIX MONTHLY COMPLIANCE REPORT JUNE- 2015
SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 Group Housing Complex My woods AT Plot no. GH-04, Sector -16 C, Noida Extension, Greater Noida, U.P. Being developed by M/s Mahagun India Pvt. Ltd. A-19, Sector-63,
More informationPublic Consultation: Environmental Impact Assessment (EIA) Indian Perspective
Public Consultation: Environmental Impact Assessment (EIA) Indian Perspective G.V.Reddy*, M.Srinivasa Reddy and J.Jyothirmai TEAM LABS AND CONSULTANTS B- 115-117 & 509, Aditya Enclave, Ameerpet, Hyderabad,
More informationPRE FEASIBILITY REPORT. Company of production capacity: 14,40,000 CFT/ Year located at Khasra No near Village:
PRE FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY In our Masonry Stone Mining Lease (M.L. No. 15/96, Area: 1.0 ha), Production capacity of masonry stone: 142920 TPA and existing Stone Crusher Unit named M/s.
More informationProposed Project of Halcyon Labs Pvt Ltd D-2/CH : 335,336,337, GIDC-Dahej-2, DIst: Bharuch, Gujarat Ramans Enviro Services Pvt Ltd Ahmedabad
1. EXECUTIVE SUMMARY OF THE PROJECT BRIEF SUMMARY OF THE PROJECT : TYPE OF PROJECT : Proposed Project for manufacturing of pharma intermediates by Halcyon Labs Pvt.Ltd. LOCATION : Proposed Project of Halcyon
More informationSr. No. Date of starting the project and completion schedule. January 2012 January 2017 (Tentative)
Six Monthly Progress Report reg. Construction of Group Housing Colony at village Sarai Aurangabad in Sector 3-A, Bahadurgarh (Distt. Jhajjar), Haryana by M/s Prabhu Shanti Real Estate Pvt. Ltd., due in
More informationDuring the discussions, the Committee finalized the following additional TOR for further study:
Finalization of ToR for development of Visakhapatnam?Kakinada Corridor for the Establishment of Petroleum, Chemicals and Petrochemicals Investment Region (VK- PCPIR), Andhra Pradesh by M/s VK- PCPIR Special
More informationRef: Environment Department, MS, SEIAA Letter SEAC 2010/CR.824/TC-2 Dated 2 nd Nov 2011
Ref.No:POL/U-II/EC/12-13/176 Date : 23.11.2012 To, Dr. A. Mehrotra, Director (S) Ministry of Environment & Forests, Regional Office, Western Region, Kendriya Paryavaran Bhavan Link Road No.3, E-5, Ravi
More information2. The expected cost of the project is Rs.50 crores.
Subject Application for obtaining Environmental Clearance for development of an "Integrated Municipal Solid Waste Management System for Pathankot Cluster" by Municipal Council, Pathankot at Village Kalanaur,
More informationChemplast Sanmar Limited Marine Terminal Facility, Chitrapettai Village Cuddalore District, Tamil Nadu
Chemplast Sanmar Limited Marine Terminal Facility, Chitrapettai Village Cuddalore District, Tamil Nadu Compliance Report for Environmental Clearance No.11.63/2005.1A.III dated 19.12.2005 Specific Conditions
More informationNIMZ Guidelines :- From : CA Ratan Moondra. Presentation on National Investment & Manufacturing Zone
NIMZ Guidelines :- From : CA Ratan Moondra Presentation on National Investment & Manufacturing Zone GUIDELINES FOR ESTABLISHMENT OF NATIONAL INVESTMENT & MANUFACTURING ZONES (NIMZS) o Background o Application
More informationSite Hadbast No (5-16), 97 (7-16), 102/1 (2-9)
STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-
More informationSTATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB
STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-
More informationPhase II (BIA Phase-II),
PROJECT PREFEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENTAL CLEARENCE IN TERMS OF PROVISIONS OF EIA NOTIFICATION-2006 1.0 EXECUTIVE SUMMARY OF THE PROJECT Sr. No Description Details 1 Proposed project
More informationENVIRONMENTAL IMPACT ASSESSMENT AND YOU
ENVIRONMENTAL IMPACT ASSESSMENT AND YOU PETROCHEMICAL PLANTS C A G Citizen consumer and civic Action Group 1. What are the pollution problems associated with petrochemical plants? Petrochemical plants
More informationTelefax: 011: Dated:10 th May, 2013
F. No. J-11011/41/2011-IA-II (I) Government of India Ministry of Environment and Forests (I.A. Division) Paryavaran Bhawan CGO Complex, Lodhi Road New Delhi 110 003 E-mail:vp.upadhyay@nic.in Telefax: 011:
More informationINVITING EXPRESSION OF INTEREST
INVITING EXPRESSION OF INTEREST Tender Specification No. CGM/E&S/1x800MW/Umred Project/SIA/EOI-1 2018-19 Name of work: Mahagenco's proposed 1x800 MW Ultra Supercritical Thermal Power Project at Umred WCL
More informationCOMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF APRIL 2013 TO SEPTEMBER M/s. Subham Planners Ltd.
COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF APRIL 2013 TO SEPTEMBER 2013 Name of The Company : M/s. Subham Planners Ltd. Project : Construction of group housing project at Village Betkuchi,
More informationmeeting held on meeting held on The SEAC observed that:
Excerpt pertaining to item no. 147.14 of 147 th meeting of SEAC held on 30.06.2016 Item no.147.14: Application for obtaining Environmental Clearance under EIA notification dated 14.09.2006 for area development
More informationNo. SEIAA/2015/5519 Dated:
STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-
More informationPRE-FEASIBILITY REPORT
PRE-FEASIBILITY REPORT For Polyurethane Foam Manufacturing Facility Of M/s. KRISHNA MARUTI LTD. At Plot No-13, SMG JV Park, Block No- 334,335 Vill- Hansalpur, Tal - Mandal Dist.: Ahmedabad, Gujarat INDEX
More informationSTATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB. Ministry of Environment and Forests, Government of India
STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-
More informationNo. SEIAA/2016/859 Dated: To M/s Uggarsain BKO, Sh. Varinder Kumar, Village Kakrala, Tehsil & Distt. Patiala.
STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-
More informationTATA STEEL LIMITED. Environment Compliance Report (Oct 2017 to Mar 2018)
TATA STEEL LIMITED Construction of Residential Complex For Tata Steel Plant located at Kalinganagar Industrial Complex, at Environment Compliance Report (Oct 2017 to Mar 2018) Environment Department Tata
More information.in Dated 9th August, Sharma ;
F. No. J-11011/151/2010-IA II (I) Government of India Ministry of Environment and Forests (I.A. Division) Paryavaran Bhawan CGO Complex, Lodhi Road New Delhi -110 003.. To, Ankleshwar E-mail: pb.rastoai@nic.in
More informationNo //6/2/2(1-1), 27//14(7-11), 15(7-7), 16(8-0), 33//4/3(2-4),5(8-0),6/1
STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-
More informationCRZ Clearance for Proposed Construction of RO RO Jetties at Narangi-Kharawadashri, Tal. & Dist. palghar by MMB
Environment department, Room No. 217, 2nd floor, Mantralaya, Annexe, Mumbai- 400 032. Date:August 2, 2017 To, Chief Executive Officer,Maharashtra Maritime Board,Indian Mercantile Chambers,3rd Floor,Ramjibhai
More informationNo. SEIAA/3757 Dated: To Sh. Bhushan Kumar, M/s Mangla BKO, Bhagat Ram Joshi Street, Near PNB, Barnala.
STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-
More informationCOMPLIANCE STATUS REPORT
COMPLIANCE STATUS REPORT Sona Alloys Pvt. Ltd. Additional Director (IA) Ministry of Environment & Forests, Paryavaran Bhavan, CGO Complex, Lodhi Road, New Delhi 11003 Date: 08.02.2014 Sub: Compliance Status
More information* Note: You may add your areas of interest to the above list.
VED - A Mission Vidarbha, the centrally located region of India has tremendous potential to develop into an economic force. Its rich natural resources, the mineral & forest wealth, rich cultivable land,
More informationCOMPLIANCE TO THE CONDITIONS LAID BY MoEF VIDE CRZ CLEARANCE No.11/32/2009-IA.III dated
COMPLIANCE TO THE CONDITIONS LAID BY MoEF VIDE CRZ CLEARANCE No.11/32/2009-IA.III dated 10.08.2009 Period : January 2018 to June 2018 Sl.No. CONDITIONS STIPULATED BY MoEF COMPLIENCE Specific Conditions
More information97MW TASHIDING HYDRO ELECTRIC PROJECT
97MW TASHIDING HYDRO ELECTRIC PROJECT DATA SHEET For period ending November 2017 Details Sl.No. Particulars 1. Project Type Run- of- River Scheme 2. Name of the Project 97MW Tashiding Hydro Electric Project
More informationFor PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra
Draft Terms of References (ToR) (Based on the model TOR given in Environmental Impact Assessment Guidance Manual for building construction projects by MoEF & CC) For PROPOSED IT PARK By M/s.Balewadi Tech
More informationCHECKLIST FOR ENVIRONMENTAL PUBLIC HEARINGS and PUBLIC CONSULTATION UNDER EIA NOTIFICATION,
CHECKLIST FOR ENVIRONMENTAL PUBLIC HEARINGS and PUBLIC CONSULTATION UNDER EIA NOTIFICATION, 2006 1 The EIA notification, 2006 specifies four stages for the environment clearance of development and industrial
More informationTo M/s Jai Ganesh BKO, Sh. Mohinder Kumar, # 1057, Sec-21-B, Chandigarh.
STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-
More informationManufacture of Products like Phthalic Anhydride, Benzoic Acid and Power.
Ref EC No. J-11013/14/2007-IAII (I) dated 12.06.2007. To For Status IG Petrochemicals Ltd, T-2, MIDC Taloja Manufacture of Products like Phthalic Anhydride, Benzoic Acid and Power. Project Implementation
More informationPRE-FEASIBILITY REPORT
PRE-FEASIBILITY REPORT For ToR of Proposed Project of MANUFACTURING OF SYNTHETIC ORGANIC DYES (5 f B IND II) By SHREEJI BAPA DYE CHEM PLOT NO 1319 & 1320, PHASE-III, GIDC, VATVA, AHEMADABAD-382445, GUJARAT,
More informationPRESENTATION ON DEVELOPMENT OF NEW POWER PROJECTS APPROACH & WAY FORWARD
PRESENTATION ON DEVELOPMENT OF NEW POWER PROJECTS APPROACH & WAY FORWARD Presentation By N.K.Srivastava General Manager (Engg. Services & R&M) 20.04.2012 PROJECT DEVELOPMENT AT NTPC PROJECT IS DEVELOPED
More informationPRE FEASIBILITY REPORT
Page1 PRE FEASIBILITY REPORT KALDA FLAG STONE QUARRY AREA OF -1.55 HACTARE STRICTLY AS PER MOEF GUIDELINE DATE 30/12/2006 IN TERMS OF PROVISIONS OF EIA NOTIFICATION 2006 VILLAGE KALDA TEHSIL PAWAI DISTRICT
More informationSTATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India
STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-
More informationHind Energy & Coal Beneficiation (India) Ltd.
SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. 0.96 MTPA Wet type Coal Washery at Birgahani Village, Baloda Tehsil Janjgir-Champa District, Chhattisgarh
More informationRegistered. M/s Baba Jiwan Singh Baba Dalip Singh Educational Trust, Goindwal Sahib Road, Tarn Taran.
No. SEIAA/ 2309 To STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road,
More informationSTATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB
No. SEIAA/ 2634 To Subject: STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha
More informationEnvironment Clearance for Proposed Inland Water Transport along East Coast of Mumbai.
To, Maharashtra Maritime Board at Ferry Wharf (Bhaucha Dhakka), Nerul and Mandwa Environment department, Room No. 217, 2nd floor, Mantralaya, Annexe, Mumbai- 400 032. Date:April 10, 2017 Subject: Sir,
More informationSTATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB
STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-
More informationGENERAL CONDITIONS. 7. The Applicant will adopt the prescribed norms, and standards provided in the national Building Code of India 2005.
GENERAL CONDITIONS 1. The Project Proponent shall comply with all the conditions stipulated in the building approval letter. 2. The applicant (Project proponent) will take necessary measures for preventions,
More informationProposed Draft Terms of Reference for Preparation of EIA & EMP for Louis Pharmaceuticals Pvt Ltd STANDARD TERMS OF REFERENCE
Proposed Draft Terms of Reference for Preparation of EIA & EMP for Louis Pharmaceuticals Pvt Ltd 1. Executive Summary 2. Introduction STANDARD TERMS OF REFERENCE I. Details of the EIA Consultant including
More informationEnvironment Impact Assessment (EIA) The proposed project falls in category 8 (a) B2 as per schedule of EIA Notification, 2006.
Environment Impact Assessment (EIA) The proposed project falls in category 8 (a) B2 as per schedule of EIA Notification, 2006. Thus, EIA is not applicable for proposed project. We have derived project
More informationPrincipal Secretary, IDD extended welcome to the Members present.
Proceedings of the 4th Meeting of the State Level Single Window Agency for PPP projects held on September 9, 2008 at 3.30 'PM under the Chairmanship of the Chief Secretary to Government of Karnataka Members
More informationEnvironment department, Room No. 217, 2nd floor, Mantralaya, Annexe, Mumbai Date:November 6, 2018
To, Mr. Anil Mane at Plot No. 113/114 MIDC Dhatav Industrial Estate. Dhatav village, Roha Taluka, Raigad Environment department, Room No. 217, 2nd floor, Mantralaya, Annexe, Mumbai- 400 032. Date:November
More informationBRIGADE RESIDENTIAL DEVELOPMENT
BRIGADE RESIDENTIAL DEVELOPMENT Terms of Reference (TOR) At Plot No. R5 and Plot No. R8, Hi Tech, Defense and Aerospace park (Hardware Sector), KIADB Industrial Area, Jala Hobli, Yelahanka Bengaluru North
More informationEIA NOTIFICATION
EIA NOTIFICATION - 2006 Building Construction projects/ Area Development projects and Townships New Delhi, 12 th August 2010. BHARAT BHUSHAN DIRECTOR, Ministry of Environment & Forests, Government of India,
More informationSTATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India. Registered
STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-
More informationEXECUTIVE SUMMARY. Kumardeipur Sand Quarry Cum ' 13.3" N to 20 44' 20.7"N Longitude " E to 85 35'27.5 "E
EXECUTIVE SUMMARY 1.0 INTRODUCTION Sri Mahesh Prasad Mishra proposes to mine Sand Quarry from an approved Mining Lease over an area of 14.85 Ac or 6.01 hectares (Non-Forest Land) which is located in at
More informationPREFEASIBILITY REPORT
PREFEASIBILITY REPORT For ToR Application of Expansion Project For MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS (Dyes Intermediates) Proposed By: M/s. Plot No. C/1/B-145-3 Phase-II, GIDC Estate, Naroda,
More informationCheck list for construction Project of EC [Category 8(a)]:
Check list for construction Project of EC [Category 8(a)]: Provide authenticated (with stamp & Signature) hard copy of this check-list during submission of hard copy of ToR application. Sr. no. Checklist
More informationJ-11011/45/2009- IA II (I)
SL SPECIFIC CONDITIONS STATUS 1 Continuous stack monitoring facilities to monitor gaseous emissions from all the stacks shall be provided. The particulate emissions shall be controlled within 50 mg/nm
More informationEXECUTIVE SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT
EXECUTIVE SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT For CHHATTISGARH ENVIRONMENT CONSERVATION BOARD CHHATTISGARH 0 P a g e 1.0 INTRODUCTION SUMIT ISPAT PVT. LTD. has proposed to establish Submerged
More informationFrom : April 2015 To : October 2015 Status of conditions stipulated in Environmental and CRZ clearance. Adani Vizag Coal Terminal Private Limited
Page 1 of 27 Half yearly Compliance report for Environment and CRZ Clearance for development of East quay -1 (EQ-l) by replacing the existing EQ-l berth and part of EQ-2 berth. Sr. No. Conditions Compliance
More informationPROPOSED TERMS OF REFERENCE
ENVIRONMENTAL IMPACT ASSESSMENT FOR RESIDENTIAL TOWNSHIP WITH VACATION RESORTS PROJECT AT ALIBAUG, RAIGAD, MAHARASHTRA PROPOSED TERMS OF REFERENCE Submitted to State Level Environment Impact Assessment
More informationSTATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB
STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-
More informationSIA/PB/NCP/53462/2016)
Item No.148.08: Application for environmental clearance under EIA notification dated 14.09.2006 for the development of group housing project namely SSL Highway Towers at Chandigarh-AmbalaHighway, Dera
More information7.2 PUBLIC CONSULTATION
PROPOSED GREENFIELD PROJECT OF CHLOR-ALKALI AND CAPTIVE POWER PLANT AT VILL: LANDHA, AMBALA, HARYANA CH-7: ADDITIONAL STUDIES 7.2 PUBLIC CONSULTATION An application for conduct of public hearing was made
More informationNo. SEIAA/M.S./2014/692 Dated M/s Jolly Bricks & Tiles., Vill. Chajalwadi, Tehsil Baba Bakala, Distt. Amritsar.
STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-
More informationCOMPLIANCE REPORT TO THE CONDITIONS LAID IN THE ENVIRONMENTAL CLEARANCE
COMPLIANCE REPORT TO THE CONDITIONS LAID IN THE ENVIRONMENTAL CLEARANCE PREAMBLE: EIA follow up commonly referred to as Compliance reporting is the process of monitoring, evaluation and validation of the
More informationReport on Damage Assessment and. Remediation Plan and Natural & Community Augmentation Plan
Report on 1. PROJECT LOCATION & LAND USE The Ganesh Park 3 is a residential building project constructed on plot 608 to 613/5 Vil: GIDC Ankleshwar in Bharuch district of Gujarat state. The project land
More informationCOMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF OCTOBER TO MARCH-2017
COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF OCTOBER - 2016 TO MARCH-2017 F.No. SEIAA 281/2014/EC/110 SUBMITTED BY- M/S. TERON CONSTRUCTION PVT. LTD MAA PADMA COMMERCIAL COMPLEX, H/N-
More informationMINUTES OF THE 43rd MEETING OF MAHARASHTRA COASTAL ZONE MANAGEMENT AUTHORITY HELD ON 7th March, 2008
MINUTES OF THE 43rd MEETING OF MAHARASHTRA COASTAL ZONE MANAGEMENT AUTHORITY HELD ON 7th March, 2008 The following were present The Secretary, Environment Department, Mantralaya, Mumbai-400 032 Secretary
More informationDESCRIPTIVE REPORT ON STATUS OF COMPLIANCE TO THE CONDITIONS OF ENVIRONMENTAL CLEARANCE AND ENVIRONMENTAL MANAGEMENT
DESCRIPTIVE REPORT ON STATUS OF COMPLIANCE TO THE CONDITIONS OF ENVIRONMENTAL CLEARANCE AND ENVIRONMENTAL MANAGEMENT Subject: Compliance report of Environmental Clearance for Plant 3 Reference: J-11011/603/2010-IA,
More informationADDITIONAL STUDIES PUBLIC CONSULTATION As per EIA notification 14 th September 2006 and ToR issued by Expert Appraisal Committee (EAC) Ministry
ADDITIONAL STUDIES 7 7.1 PUBLIC CONSULTATION As per EIA notification 14 th September 2006 and ToR issued by Expert Appraisal Committee (EAC) Ministry of Environment, Forest and Climate Change (MoEFCC),
More informationRegistered. M/s N.H. Matcon Pvt. Ltd., S.C.O-3, Royal Estate, Chandigarh-Ambala Highway, Zirakpur, District SAS Nagar
State Level Environment Impact Assessment Authority, Punjab, Government of India Ministry of Environment and Forests Vatavaran Bhawan, Nabha Road, Patiala-147001 Telefax:- 0175-2215802 No. SEIAA/2013/2751
More informationScanned with CamScanner
MINUTES OF MEETING OF PUBLIC HEARING FOR EC FOR EXPANSION OF AIRPORT PROJECT HELD ON DATE 02/06/2018 BY M/S AIRPORT AUTHORITY OF INDIA, JOLLYGRANT AIRPORT, DISTRICT DEHRADUN The Public Hearing was Conducted
More informationDated: 22 nd June, To The Director, Mjs Vulcan Waste Management Pvt. Ltd., 1046, Sector-31, Gurgaon, Haryana
F.No.10-12/201S-IA.III Government of India Ministry of Environment, Forest & Climate Change (IA.IIISection) Indira Paryavaran Bhawan, Jor Bagh Road, New Delhi - 110 003. To The Director, Mjs Vulcan Waste
More informationCOMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF APRIL-2016 TO SEPTEMBER F. No. J-11011/309/2011-IA-ll (I)
COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF APRIL-2016 TO SEPTEMBER-2016 F. No. J-11011/309/2011-IA-ll (I) SUBMITTED BY- M/S. GASGEN FERRO ALLOYS LLP LOHIA HOUSE, 2ND FLOOR M.G.ROAD,
More informationM/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA
1.0 INTRODUCTION M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA dry type of coal washery at Village: Hindadih, Tehsil: Masturi, District: Bilaspur (C.G.) for which
More information(1) LAND ENVIRONMENT (Attach panoramic view of the project site and the vicinity)
[Vide Paragraph - 6 of Notification dated 14 th September 2006, only for construction projects listed under item 8 of the Schedule] (1) LAND ENVIRONMENT (Attach panoramic view of the project site and the
More informationEnvironment protection measures / technology
Sr. No. Conditions A. Specific Conditions: i. The gaseous and particulate matter emissions from various units should conform to the standards prescribed by the State Pollution Control Board. At no time,
More informationM/s. SAL STEEL LTD Survey no.245/p, Village:-Bharapar, Taluka:- Gandhidham, District:-Kutch, Gujarat.
Pre-Feasibility Study Report For Proposed Fly Ash Co-processing clinker grinding cement Unit of 40,000 MT/month Production capacity within our Existing Premises for M/s. SAL STEEL LTD Survey no.245/p,
More informationDate: M/S Desh Bhakt Ratnappa Kumbhar Panchaganga SSK Ltd, Inchalkaranji, Kolhapur.
Date: 04.06.2018 M/S Desh Bhakt Ratnappa Kumbhar Panchaganga SSK Ltd, Inchalkaraji, Kolhapur. Compliance to the Environmental Clearance for Co-generation Plant 30 MW. Ref: SEAC 2009/CR16/TC2, Dated: 18
More informationGUIDELINES ON ENERGY CONSERVATION IN SEZs
1 GUIDELINES ON ENERGY CONSERVATION IN SEZs SEZs are special enclaves aimed at creating world class infrastructure. The guidelines and certification for SEZs is to be implemented as follows: Entire SEZ
More informationMONITORING THE IMPLEMENTATION OF ENVIRONMENTAL SAFEGUARDS Ministry of Environment & Forests Regional Office (W), Bhopal Monitoring Report Part-I
MONITORING THE IMPLEMENTATION OF ENVIRONMENTAL SAFEGUARDS Ministry of Environment & Forests Regional Office (W), Bhopal Monitoring Report Part-I DATA SHEET 01 Project type : Cement Date: 24.11.2015 02
More informationMAHARASHTRA METRO RAIL CORPORATION LTD.
MAHARASHTRA METRO RAIL CORPORATION LTD. ADVT NO: Maha-Metro/HR/07/2017 DATED: 16 th May, 2017 Maharashtra Metro Rail Corporation Ltd (Maha Metro), A joint Venture Company with equal participation from
More informationCOMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF MARCH TO AUGUST -2013
COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE Name of Company : FOR THE PERIOD OF MARCH -2013 TO AUGUST -2013 M/s. GNRC Institute of Medical Sciences (a unit of GNRC Ltd). Project : Construction of Medical
More informationCRZ Clearance for Proposed construction of Ghodbundar Jetty, Thane by MMB
Environment department, Room No. 217, 2nd floor, Mantralaya, Annexe, Mumbai- 400 032. Date:August 9, 2017 To, Chief Executive Officer,Maharashtra Maritime Board,Indian Mercantile Chambers,3rd Floor,Ramjibhai
More informationHind Energy & Coal Beneficiation (India) Ltd.
SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. (Change in Technology) at Hindadih Village, Masturi Tehsil Bilaspur District, Chhattisgarh Submitted to
More informationNAGPUR METRO RAIL CORPORATION LTD.
NAGPUR METRO RAIL CORPORATION LTD. Annexure - I ADVT NO: NMRCL/HR/05/2016 DATE: 09 th Nov, 2016 REQUIREMENT OF EXPERIENCED EMPLOYEES FROM METRO RAIL / GOVT. ORGANIZATION/ RAILWAY PSU's / RAILWAY RELATED
More informationSubject: Environmental and CRZ clearance for expansion of Karaikal Port (Phase-II) at Puducherry by MIs. Karaikal Port Pvt. Ltd. - Reg.
No. 10-42/2009-IA.III Government of India Ministry of Environment & Forests (IA Division) Paryavaran Bhawan, CGO Complex, Lodhi Road, New Delhi - 110003. I i I I I Dated: 22 nd September, 2009. To MIs.
More informationSTANDARD OPERATING PROCEDURE
STANDARD OPERATING PROCEDURE Consent to Established/Operate Procedural Guidelines Consent to Establish NOC Check List Consent to Operate NOC Check List Renewal to Consent to Operate Check List Time Frame
More informationEnvironmental Clearance for mining of minor minerals (brick clay) in the revenue estate of Vill. Juglan, Tehsil Budhlada, Distt. Mansa.
STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-
More informationGOVERNMENT RAJASTHAN POLICY FOR PROMOTING GENERATION THROUGH NON-CONVENTIONAL ENERGY SOURCES Sl. No 1 Order Energy Deptt. letter no. F.
GOVERNMENT RAJASTHAN POLICY FOR PROMOTING GENERATION THROUGH NON-CONVENTIONAL ENERGY SOURCES Sl. No Description Summary 1 Order Energy Deptt. letter no. F.20 (4) Energy/2004 dated 25.10.2004 and amended
More informationPRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD
PRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD PLOT No. F-1,2,3,8,9,10, ADDL. MIDC, PHASE II, AND GUT NO. 46 & 63, VILLAGE DAREGAON, TEHSIL: JALNA DIST: JALNA, MAHARASHTRA 2014-15 1. Executive
More informationSTATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India
STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-
More informationSEIAA KARNATAKA CHECK LIST FOR BUILDING & CONSTRUCTION PROJECTS
Annexure No - 13 SEIAA KARNATAKA CHECK LIST FOR BUILDING & CONSTRUCTION PROJECTS File No : Name of the Project: Proposed Commercial project called Bagmane Tech Park RIO Campus of M/s. Bagmane Developers
More informationNo. SEIAA/M.S./ 8278 Dated
STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:-
More informationGovernment Of Maharashtra Tribal Development Department, Mumbai.
Government Of Maharashtra Tribal Development Department, Mumbai. Name Action of the Plan state. For the implementation of Forest Rights Act 2006 in view of the amendments made in the Forest Rights Rules
More information