LOLE Fundamentals Loss of Load Expectation (LOLE) Fundamentals

Size: px
Start display at page:

Download "LOLE Fundamentals Loss of Load Expectation (LOLE) Fundamentals"

Transcription

1 Loss of Load Expectation (LOLE) Fundamentals March 13, 2014 Last material update: 03/12/2014

2 LOLE Agenda 2 Loss of Load Expectation (LOLE) Fundamentals Sections LOLE Background LOLE Study Connections to other MISO Processes LOLE Software & Modeling GE MARS Takeaways Reference Materials

3 LOLE Background 3 Historical Generation & Transmission Adequacy Issues

4 LOLE Background 4 Loss of Load Expectation (LOLE) Definition LOLE is the measure of how long, on average, the available generation capacity is likely to fall short of the load demand Loss of Load Probability (LOLP) is the probability in a given hour Sum of the Daily Peak LOLP values is an expectation (LOLE) Sum of all LOLP values is called Loss of Load Hours (LOLH) LOLE is used to study Generation (Resource) Adequacy Generally considered to be the existence of sufficient resources, within a system, to satisfy consumer demand. A product of unit availability, perfect storm

5 LOLE Background 5 1-day in 10-years LOLE Criteria MISO Resource Adequacy criteria for Planning Reserve target is the industry standard LOLE objective: <1-day in 10-years NERC Standard BAL-502-RFC-02 Calculate a planning reserve margin that will result in the sum of the probabilities for loss of Load for the integrated peak hour for all days of each planning year analyzed being equal to 0.1. (This is comparable to a one day in 10 year criterion).

6 LOLE Background 6 Common Terminology Misconceptions 1 day in 10 years LOLE 24 hours in 10 years LOLH. Example: 2 hours of firm load shed = 2 loss of load hours and 1 day of loss of load. By definition 1 day/ 10 years LOLE 24 hours / 10 years LOLH. Cannot calculate Loss of Energy Expectation (LOEE) from LOLH without running complete analysis.

7 LOLE Background 7 Deterministic vs. Probabilistic Deterministic: to determine, fix, resolve, settle, regulate, limit, define Examples: % Reserve, (N-1), Worst case Condition Probability: likelihood of an event, the expected relative frequency of occurrence of a specified event in a very large collection of possible outcomes. A quantitative measure of the likelihood of an event A quantitative measure of the uncertainty associated with the event occurring A quantitative indicator of uncertainty Probability concepts provide the ability to quantitatively incorporate uncertainty in the planning of power systems, which cannot be done using deterministic methods and criteria.

8 LOLE Study Connections to other MISO Processes 8 LOLE Connections to Various MISO Processes LOLE Planning Reserve Margin (PRM) Study Assessments Resource Adequacy Tariff Module E-1 Capacity Market NERC Assessments MISO Informational Forums Planning Studies Resource Forecasting MTEP Study

9 LOLE Study Connections to other MISO Processes 9 MISO Value Based Planning STEP 1: MULTI-FUTURE REGIONAL RESOURCE FORECASTING STEP 7: COST ALLOCATION ANALYSIS STEP 2: SITE-GENERATION AND PLACE IN POWERFLOW MODEL STEP 6: EVALUATE CONCEPTUAL TRANSMISSION FOR RELIABILITY STEP 3: DESIGN CONCEPTUAL TRANSMISSION OVERLAYS BY FUTURE IF NECESSARY STEP 4: TEST CONCEPTUAL TRANSMISSION FOR ROBUSTNESS STEP 5: CONSOLIDATE & SEQUENCE TRANSMISSION PLANS

10 LOLE Study Connections to other MISO Processes 10 Resource Adequacy Impact on Transmission Service Request (TSR) Before the Resource Adequacy construct Point-to-Point TSRs were the predominant way Capacity was designated to serve Load (TSR) With the implementation of the Resource Adequacy construct Reduced TSR requests Allows any market deliverable capacity to be designated by load to meet Planning Reserve Margin Requirements (PRMR) PRMR = Load + PRM

11 LOLE Study Connections to other MISO Processes 11 Resource Adequacy Overview Achieving reliability in the bulk electric systems requires that the amount of resources exceeds customer demand by an adequate margin Margins necessary to promote Resource Adequacy need to be assessed on: Longer-term planning basis Near-term operational basis Focus of MISO s RA Construct is on the longerterm planning margins used to provide sufficient resources to reliably serve Load on a forward-looking basis Resources dedicated to meet Demand have an obligation to be available to meet real-time customer demand and contingencies

12 LOLE Study Connections to other MISO Processes 12 Planning Reserve Margins (PRMs) Planned maintenance Variations in customer demands or forecast demand uncertainty Planning Reserve Margins must be sufficient to cover: Unplanned or forced outages of generating equipment System effects due to reasonably anticipated variations in weather Deratings in the capabilities of Generation resources and Demand Response Resources

13 LOLE Study Connections to other MISO Processes 13 Overview of MISO Resource Adequacy Requirements Peak Demand and Planning Reserve Margin Generation, Load, and Resource Credits PRMR LSE Obligation Planning resources

14 LOLE Study Connections to other MISO Processes 14 Reserve Margin Analysis and Determination of PRM Annual Technical Analysis Results published by November 1 st Considers several factors Common industry reliability standard Utilize probabilistic LOLE study Uses MISO planning area zones Coordinate with LSEs Only entity other than MISO that can establish a PRM Technical Analysis MISO LOLE Analysis + LOLEWG Coordination State Authority

15 LOLE Software & Modeling LOLE Model Inputs Include 15 Study System Zone & Pool definition Zone Tie Limits (Import & Export) External System Model Generation Resources Operating Parameters Unit Forced Outage Rates Planned Maintenance Schedules & Rates Energy Limits for DR and Interruptible Load Load Demand and Energy Forecast Load Shape/Profile Load Forecast Uncertainty (LFU) LOLE Model Inputs

16 LOLE Software & Modeling 16 Source of LOLE Model Input Data Generation Resources Generator Availability Data System (GADS) Unit perform statistics used to calculate forced outage rates Data is uploaded into the MISO system one month after each quarter end Generation Verification Test Capacity (GVTC) Units need to demonstration maximum output level Load Monthly Peak Demand, MISO Coincident Demand and Energy Forecast are uploaded by Load Serving Entities (LSEs) into the Module-E Capacity Tracking (MECT) Tool (deadline Nov. 1st) MISO reviews Forecast and Finalize review by March

17 LOLE Software & Modeling 17 Planning Reserve Margin LOLE Study Analysis Flowchart GADS Max Capacity Ratings GVTC EFORd Unforced Capacity(UCAP) XEFORd MECT tool Peak Load & Demand data Load Modifying Resources Behind the Meter Gen Demand Response Interruptible Load External Designated Resources Transfer Analysis Capacity Import Limit (CIL) Capacity Export Limit (CEL) MISO System LOLE Model Non-constrained MISO system copper-sheet External System Equivalent Historic Load Analysis Load Forecast Uncertainty(LFU) NERC Bandwidth Method Historic Hourly Load Profiles typical load pattern/shape Local Resource Zone LOLE Model Individually Isolated LRZs NO LOLE=0. 1? YES YES LOLE=0. 1? NO Resource Adequacy Planning Reserve Margin MISO System PRM Target at LOLE = 0.1 day/year Local Reliability Requirement Local Clearing Requirement LCR = LRR CIL

18 LOLE Software & Modeling 18 LOLE Models Utilize an Equivalized Transportation Model Detailed Transmission Model Typical Load/Power Flow model used in transmission studies Retains transmission system details with a system of voltage specific buses and voltage specific branches Loads are modeled at bus level Equivalized Transportation LOLE Model Retains individual generating unit details System of interconnected zones/areas Aggregated load at a zonal level model representation Zones are grouped to represent electrical systems to help establish assistance priority

19 LOLE Software & Modeling 19 MISO System LOLE Model LRZ-2 External LRZ-1 LRZ-3 LRZ-9 MISO- Hub LRZ-4 LRZ-8 LRZ-5 LRZ-7 LRZ-6

20 LOLE Software & Modeling 20 Local Resource Zone LOLE Model LRZ-2 LRZ-1 LRZ-3 LRZ-9 LRZ-4 LRZ-8 LRZ-5 LRZ-7 LRZ-6

21 LOLE Software & Modeling 21 MISO Wind Capacity Credit Analysis Two-step Process Step-1 Probabilistic approach Calculates MISO system-wide Effective Load Carrying Capability (ELCC) value for all wind resources in the MISO footprint Step-2 Deterministic Period Metric Results in a value for each wind resource on the MISO system

22 LOLE Software & Modeling 22 MISO Wind Capacity Credit Analysis Examples of Probabilistic Approach Example System With & Without New Resource Base System LOLE = 0.15 days/yr (or 1½ days in 10 yrs) Base System LOLE = 0.08 days/yr (or 0.8 days in 10 yrs) + New Resource (Wind) ELCC Example System at the same LOLE Decreased Load -200 MW Load Increased +100 MW Base System LOLE = 0.1 days/yr (or 1 day in 10 yrs) Base System LOLE = 0.1 days/yr (or 1 day in 10 yrs) + New Resource (Wind) 1000 MW Nameplate

23 LOLE Software & Modeling 23 Planning Year ELCC

24 24 MISO Uses Multi-Area Reliability Simulation Program (MARS) Software General Electric Company product Originally developed for New York State Uses a sequential Monte Carlo simulation Steps through time chronologically and randomly drawing unit availability Replicating simulation with different sets of random events until statistical convergence is obtained Ability to analyze reliability of interconnected generation systems Benefits of diversity Tie-line effectiveness Utilizes a flat file input format and multiple text file outputs Most widely used LOLE software in the Power Systems Industry

25 25 Analytical vs. Monte Carlo approach to analysis Analytical methods work well for small systems and represent a system using mathematical model (A direct mathematical solution). Monte Carlo methods simulate the actual process and repeat simulation until convergence criteria is met. For complex systems, a Monte Carlo brute force approach is more appropriate.

26 26 Types of Monte Carlo Analysis Non-Sequential Monte Carlo Simulation Each hour is independent of every other hour. Inability to model time-correlated issues. Inability to calculate frequency and duration indices. Sequential Monte Carlo Simulation Steps through time chronologically. Ability to model time correlated issues and calculate frequency and duration indices. Requires more detailed system data.

27 27 Monte Carlo Simulation Overview Initialize Data for Study Year Read Monte Carlo Interface File Determine Capacity State of Units Schedule Firm Contracts Replication All Months All Hours Determine Area Capacities and Margins Collect Isolated Statistics Schedule Curtailable Contracts Calculate Emergency Assistance and Resulting Area Margins Collect Interconnected Statistics Calculate Annual Indices Test for Convergence

28 28 Load Modeling LOLE model uses forecasts to adjust historical load shapes. Historical shape as well as forecasts directly impact the resulting reserve margin target. Use 50/50 load as well as load forecast uncertainty to capture uncertainty. Diversity captured is product of forecasts and historical load.

29 29 MISO Load Shape Progression 35 Historical LBA Load Shapes Apply Module-E Monthly Forecasts to Historic LBA Load 35 Forecasted LBA Load Shapes 9 LRZ Forecasted Load Shapes

30 30 Historical MISO LBA Load Shape 35 hourly historical load shapes by LBA for MISO ** 2005 historical load shape..

31 31 Application of Module-E Monthly Forecasts to Historic LBA Load Load shapes are adjusted by Module-E submitted monthly non-coincident peak forecasts

32 Load [MW] GE MARS 32 Application of Module-E Monthly Forecasts to Historic LBA Load Example LBA July Daily Peak Load Historical Forecasted Hour

33 LRZ Forecasted Load Shapes 33 LBA forecasted load shapes are summed up by LRZ 35 LBA load shapes 9 LRZ load shapes LRZ load shapes input into MARs Each LRZ has individual load forecast uncertainty

34 34 Introduction to Load Forecast Uncertainty A standard deviation statistical coefficient, applied to base 50/50 load forecast to represent the various probabilistic load levels. MISO adapted the NERC Bandwidth Methodology to perform Load Forecast Uncertainty study. A univariate time series model in which the projection of demand is modeled as a function of past demand. MISO developed upper and lower 80 percent confidence bands. 80 percent chance of future demand occurring within these bands, a 10 percent chance of occurring below the lower band, and 10 percent chance of occurring above the upper band.

35 35 Prior to PY 14/15 LFU Modeling Methodology One MISO LFU was calculated to determine the MISO wide PRM and seven zonal LFU values were used to calculate the LRZ LRRs. Historically, LFU for MISO Midwest region had been around 4%. This year, an LFU of 3.8% was calculated for Midwest region. Adding South Region companies, MISO wide LFU for was reduced to about 3%. o Aggregation inherently dampened uncertainty effects. o Assumes available transmission capability to socialize uncertainty. Latest LFU values calculated by NERC for RFC, SERC, and MRO- US were 5%, 3.4%, and 4.6%.

36 LFU Modeling Methodology for PY Zonal construct was aligned with the MISO system PRM Nine individual LRZ LFU values were modeled as part of the MISO PRM analysis. More granular zonal LFU values appropriately applies each LRZ s LFU to that LRZ s hourly load. This application of LFU more accurately reflects the uncertainty impacts of each LRZ s geographic area.

37 37 Modeling Methodologies of PY vs. Previous Years 1. Zonal vs. Overall LFUs in MARS One common LFU value was applied to every LRZ in the zonal method. The same LFU value to MISO overall system in the old method. 50/50 loads were driven away by three standard deviations in both methods. Results of both methods were the same With Similar LFU values, MARS does not treat a model with zonal LFU any different from a model with a single system wide LFU

38 38 Modeling Methodologies of PY vs. Previous Years 2. System wide LFU equivalent to the zonal methodology =3.9%. 50/50 hourly load of each LRZ was increased by its LFU(one σ). Aggregated up to one hourly load for MISO footprint. Resulted hourly load less 50/50 MISO hourly load= Hourly σ for MISO overall Average of hourly σs was 3.9% o Effective LFU for MISO Midwest close to the 3.8% calculated in the old method. o Validated that MISO Midwest LFU should not reduce as a result of MISO South integration, knowing the existing transmission limits between the two regions.

39 Effect of LFU in PRM Calculation PRMs calculated for MISO with varying LFUs. 39 MISO system was treated as an island with no capacity transaction. Results show that for LFU ranges of 3% to 4% a 1 percent increase in LFU contributes to an increase of about 2 percent in PRM UCAP.

40 LFU Modeling in MARS 40 7 levels of uncertainty are modeled with a corresponding annual probability of occurrence. 7 LFU levels are applied to every hour. Reliability indices are calculated for each load level (LFU). Weighted average value used for system/zone indices and to test convergence.

41 41 LFU Probability Distribution

42 42 LRZ Forecasted Load with LFU Bands

43 43 Inherent MISO LFU in MARS Mean : 3.922% Median: 3.925% Std. Dev:.027% Max: Min: 3.819%

44 44 Load Forecast Uncertainty Expected Value =.1 Days/Year

45 45 Unit Data Unit Name Unit Physical Local Resource Zone (LRZ) Installation Date Retirement Date Type ( Thermal, Energy Limited, Demand Side) Unit Summary Type Thermal (Combustion Turbine, Combined Cycle, Pump Storage, Fluidized Bed, Hydro, Nuclear, Steam Turbine, Diesel) Energy Limited (Demand Response and Energy Efficiency) Demand Side (Intermittent Resources such as Wind, Run-of-River Hydro, and Biomass) Thermal Units Utilize the Generator Verification Test Capacity (GVTC) for a peak capacity and each unit s monthly Net Dependable Capacity (NDC) submitted in PowerGADS determines each unit s monthly capacity profile

46 46 Forced Outage Rates & Unit Maintenance Thermal Units Only Forced Outage Rates Unit Name Transition Matrix EFORd (5 year) Unit Maintenance Unit Name Maintenance Cycle # Fixed Maintenance Typically Nuclear Units Month & Year Unit Name Begin Date Stop Date Planned Outage Rates Total Number of Cycles for that Unit Planned Outage Rate (Planned Outage Factor + Maintenance Outage Factor from PowerGADS)

47 47 Maintenance Scheduling Levelize Reserves

48 48 Energy-Limited Units Demand Response (DR) & Energy Efficiency (EE) Month & Year Unit Name Minimum Megawatt (MW) Zero Maximum Megawatt (MW) Monthly Profile Energy (MWh) Maximum Annual Energy Maximum Interruptions * Maximum Duration * Maximum Monthly Capacity Storage (MWh)

49 49 Demand Side Management (DSM) Net Hourly Load Modification Unit Name Specify net hourly load modification for a typical week 168 (# of Hours in Week) * MW Positive values decrease load

50 50 External System Modeling 7 external areas with their own generation and load. Each external area represents one or more 1 st tier MISO external Balancing Areas. External areas reserve margin targets are adjusted by purchases, sales, and DSM. Each area has tie line to MISO hub. Tie line limit set using previous years hourly NSI Import limit to MISO capped at summer on-peak hours NSI maximum. Export limit out of MISO set to zero. Simultaneous flow on multiple interfaces also set using NSI.

51 51 External System and Ties Model

52 52 Firm Imports/ Purchases External purchases claimed in MECT are included in LOLE modeling. External purchases are modeled as firm non-curtailable contracts. Modeled from external region to MISO. Firm imports are only modeled in MISO PRM model and not zonal LRR model. Firm imports do effect tie line capacity.

53 53 Firm Exports/ Sales Capacity that is ineligible for MISO PRA is excluded from MISO and zonal models. Currently, only units that clear in PJM Reliability Pricing Model (RPM) are designated as sold in the LOLE model. Units are removed from physical LRZ and capacity is added to external area where sold.

54 54 Simulation Stopping Criterion Index Daily LOLE Hourly LOLE LOEE Isolated or Interconnected for an Area, Pool or Area Group MISO LRZ s Convergence tolerance (Standard error of the mean) days/year LOLE Can set minimum and maximum number of replications Typically, ~ 5,000 replications to minimize the standard error

55 55 Output Summaries Summary of Input Data Used in calculations of PRM and Local Reliability Requirements (LRR) Includes: Monthly load data by Area Installed Capacity by type, month and Area Unit data Weekly maintenance schedules LOLE and LOEE for each replication year

56 56 GE MARS Capacity Adjustment Flowchart

57 57 PRM Calculation PRM ICAP = [Installed capacity + ICAP Adjustment to meet 0.1 days / year LOLE + Firm Contracts] MISO Peak Demand MISO Peak Demand PRM UCAP = [Unforced capacity + UCAP Adjustment to meet 0.1 days / year LOLE + Firm Contracts] MISO Peak Demand MISO Peak Demand

58 Takeaways 58 Important Takeaways LOLE is the measure of how long, on average, the available generation capacity is likely to fall short of the load demand LOLE is used to study Generation(Resource) Adequacy Probabilistic analysis accurately captures uncertainty risk MISO Resource Adequacy criteria for Planning Reserve target is the industry standard LOLE objective: <1-day in 10-years Aligns with NERC standards Achieving reliability in the bulk electric systems requires that the amount of resources exceeds customer demand by an adequate margin (Planning Reserve Margin) LOLE models utilize an Equivalized Transportation Model to determine Planning Reserve Margin and Local Reliability Requirements All Market Participants are encouraged to participate in the stakeholder process through LOLEWG

59 Reference Materials 59 Reference Materials Loss of Load Expectation Reports Loss of Load Expectation (LOLE) Study Reports s/resourceadequacystudies.aspx Loss of Load Expectation Working Group (LOLEWG) staskforces/lolewg/pages/home.aspx 2014 Wind Capacity Report ind%20capacity%20report.pdf Resource Adequacy Documents BPM usinesspracticesmanuals.aspx BPM Resource Adequacy MISO Tariff: Module E NERC Standard BAL-502-RFC-02

LOLE is expressed as hours per year with the usual target criteria being (0.1 days/year) or 1- day in 10-years MISO Tariff: Module E-1 - The

LOLE is expressed as hours per year with the usual target criteria being (0.1 days/year) or 1- day in 10-years MISO Tariff: Module E-1 - The 1 2 3 4 LOLE is expressed as hours per year with the usual target criteria being (0.1 days/year) or 1- day in 10-years MISO Tariff: Module E-1 - The Transmission Provider will calculate and post the Planning

More information

2016 Probabilistic Assessment. December 5, 2016 Southwest Power Pool

2016 Probabilistic Assessment. December 5, 2016 Southwest Power Pool 2016 Probabilistic Assessment December 5, 2016 Southwest Power Pool Table of Contents 1. Summary...2 a. SPP Planning Coordinator Footprint...2 b. Seasonal Capacity Totals... Error! Bookmark not defined.

More information

Midwest ISO Resource Adequacy Overview ATC Network Customer Meeting. Kevin Larson Sr. Manager Resource Adequacy October 20, 2010

Midwest ISO Resource Adequacy Overview ATC Network Customer Meeting. Kevin Larson Sr. Manager Resource Adequacy October 20, 2010 Midwest ISO Resource Adequacy Overview ATC Network Customer Meeting Kevin Larson Sr. Manager Resource Adequacy October 20, 2010 Agenda Role of Resource Adequacy Planning Reserve Margin Requirements LSE

More information

Business Practice Manual RESOURCE ADEQUACY Planning Years 2013 and beyond

Business Practice Manual RESOURCE ADEQUACY Planning Years 2013 and beyond 0 Manual No. 011 RESOURCE ADEQUACY Planning Years 2013 and beyond 0 Disclaimer This document is prepared for informational purposes only to support the development application of enhancements to MISO s

More information

Planning Year Loss of Load Expectation Study Report. Loss of Load Expectation Working Group

Planning Year Loss of Load Expectation Study Report. Loss of Load Expectation Working Group Planning Year 2018-2019 Loss of Load Expectation Study Report Loss of Load Expectation Working Group Contents 1 Executive Summary... 5 2 LOLE Study Process Overview... 6 2.1 Study Enhancements... 7 2.2

More information

April 27, Ms. Mary Jo Kunkle Executive Secretary Michigan Public Service Commission 6546 Mercantile Way P.O. Box Lansing, MI 48909

April 27, Ms. Mary Jo Kunkle Executive Secretary Michigan Public Service Commission 6546 Mercantile Way P.O. Box Lansing, MI 48909 Matthew R. Dorsett Corporate Counsel Direct Dial: 317-249-5299 E-mail: mdorsett@misoenergy.org April 27, 2011 Ms. Mary Jo Kunkle Executive Secretary Michigan Public Service Commission 6546 Mercantile Way

More information

2011 Probabilistic Assessment. 11JAN12 Interregional Coordination

2011 Probabilistic Assessment. 11JAN12 Interregional Coordination The 2011 Probabilistic Assessment was a pilot study performed by SPP at NERC s request to voluntarily conduct an assessment to determine reliability indices using probabilistic methods. The majority of

More information

ERCOT Public LTRA Probabilistic Reliability Assessment. Final Report

ERCOT Public LTRA Probabilistic Reliability Assessment. Final Report ERCOT Public 2016 LTRA Probabilistic Reliability Assessment Final Report November 21, 2016 Contents Summary... 1 Software Model Description... 3 Demand Modeling... 3 Controllable Capacity Demand Response

More information

GADS and LOLE Considerations in Gas- Electric Coordination. ENGCTF June 13, 2013

GADS and LOLE Considerations in Gas- Electric Coordination. ENGCTF June 13, 2013 GADS and LOLE Considerations in Gas- Electric Coordination ENGCTF June 13, 2013 Generating Availability Data System (GADS) National database of electric generator performance, produced by the North American

More information

ISO New England Inc. February /19 ICR Related Values 1

ISO New England Inc. February /19 ICR Related Values 1 ISO New England Installed Capacity Requirement, Local Sourcing Requirements and Capacity Requirement Values for the System-Wide Capacity Demand Curve for the 2018/19 Capacity Commitment Period ISO New

More information

Load Forecast Uncertainty Kick-Off Discussion. February 13, 2013 LOLEWG Item-3

Load Forecast Uncertainty Kick-Off Discussion. February 13, 2013 LOLEWG Item-3 Load Forecast Uncertainty Kick-Off Discussion February 13, 2013 LOLEWG Item-3 LFU Overview Load Forecast Uncertainty (LFU) is the amount of load variance modeled within the Loss of Load Expectation (LOLE)

More information

Review of Interconnection Assistance Reliability Benefits. May 12, NPCC CP-5 Working Group

Review of Interconnection Assistance Reliability Benefits. May 12, NPCC CP-5 Working Group Review of Interconnection Assistance Reliability Benefits May 12, 1999 NPCC CP-5 Working Group NORTHEAST POWER COORDINATING COUNCIL WORKING GROUP CP-5 REVIEW OF INTERCONNECTION ASSISTANCE RELIABILITY BENEFITS

More information

MISO LOLE Modeling of Wind and Demand Response. Item-9b LOLE Best Practices Working Group July 26-27, 2012

MISO LOLE Modeling of Wind and Demand Response. Item-9b LOLE Best Practices Working Group July 26-27, 2012 MISO LOLE Modeling of Wind and Demand Response Item-9b LOLE Best Practices Working Group July 26-27, 2012 1 Overview Wind Capacity Modeling MISO performs a detailed analysis to determine what the capacity

More information

Comparison of Installed Capacity (ICAP) & Unforced Capacity (UCAP) Capacity Value Calculation Methods. Eligibility WG Meeting #3 July 4, 2017

Comparison of Installed Capacity (ICAP) & Unforced Capacity (UCAP) Capacity Value Calculation Methods. Eligibility WG Meeting #3 July 4, 2017 Comparison of Installed Capacity (ICAP) & Unforced Capacity (UCAP) Capacity Value Calculation Methods Eligibility WG Meeting #3 July 4, 2017 Overview The following materials provide an examination of the

More information

Methodology to Perform Long Term Assessments

Methodology to Perform Long Term Assessments Methodology to Perform Long Term Assessments MARCH 21, 2017 March 21, 2017 Public Page 1 Caution and Disclaimer The contents of these materials are for discussion and information purposes and are provided

More information

Appendices. New York Control Area Installed Capacity Requirement. December 2, For the Period May 2017 To April 2018

Appendices. New York Control Area Installed Capacity Requirement. December 2, For the Period May 2017 To April 2018 Appendices New York Control Area Installed Capacity Requirement For the Period May 2017 To April 2018 December 2, 2016 New York State Reliability Council, LLC Installed Capacity Subcommittee NYSRC: NYCA

More information

Maintenance and Planned Outages Capacity Accreditation Under Seasonal Construct Workshop Agenda Item 03c, 3d, 3e.

Maintenance and Planned Outages Capacity Accreditation Under Seasonal Construct Workshop Agenda Item 03c, 3d, 3e. Maintenance and Planned Outages Capacity Accreditation Under Seasonal Construct Workshop Agenda Item 03c, 3d, 3e April 22 nd, 2016 Seasonal Objective: Accurately represent capacity available to serve summer

More information

Capacity Accreditation and External Resource Zones 06/30/2016

Capacity Accreditation and External Resource Zones 06/30/2016 Capacity Accreditation and External Resource Zones 06/30/2016 Overview MISO requested guidance on areas that require additional discussion and resolution in the seasonal / locational proposal In the last

More information

Eastern Wind Integration and Transmission Study

Eastern Wind Integration and Transmission Study Eastern Wind Integration and Transmission Study NPCC Governmental/Regulatory Affairs Advisory Group February 23rd, 2010 Dave Corbus National Renewable Energy Lab 1 What is Needed to Integrate 20% Wind

More information

NPCC 2017 Québec Balancing Authority Area Comprehensive Review of Resource Adequacy

NPCC 2017 Québec Balancing Authority Area Comprehensive Review of Resource Adequacy 2017 Québec Balancing Authority Area Comprehensive Review of Resource Adequacy NPCC 2017 Québec Balancing Authority Area Comprehensive Review of Resource Adequacy Prepared by Planification et fiabilité

More information

UCAP Calculation Comparison

UCAP Calculation Comparison UCAP Calculation Comparison Dispatchable resources within PJM, NYISO, & MISO September 2017 Draft for Discussion Overview map British Columbia Alberta Manitoba Newfoundland Labrador Ontario Quebec PEI

More information

May 4, 2017 PLANNING COMMITTEE. Dear Committee Members:

May 4, 2017 PLANNING COMMITTEE. Dear Committee Members: 2750 Monroe Blvd. Audubon, PA 19403 May 4, 2017 PLANNING COMMITTEE Dear Committee Members: 2017 PJM RESERVE REQUIREMENT STUDY - DETERMINATION OF THE PJM INSTALLED RESERVE MARGIN, FORECAST POOL REQUIREMENT

More information

2018 PJM RESERVE REQUIREMENT STUDY - DETERMINATION OF THE PJM INSTALLED RESERVE MARGIN AND FORECAST POOL REQUIREMENT FOR FUTURE DELIVERY YEARS

2018 PJM RESERVE REQUIREMENT STUDY - DETERMINATION OF THE PJM INSTALLED RESERVE MARGIN AND FORECAST POOL REQUIREMENT FOR FUTURE DELIVERY YEARS 2750 Monroe Blvd. Audubon, PA 19403 May 3, 2018 PLANNING COMMITTEE Dear Committee Members: 2018 PJM RESERVE REQUIREMENT STUDY - DETERMINATION OF THE PJM INSTALLED RESERVE MARGIN AND FORECAST POOL REQUIREMENT

More information

Reliability Modelling: Review Process & Methodology

Reliability Modelling: Review Process & Methodology Reliability Modelling: Review Process & Methodology Adequacy and Demand Curve Workgroup Sept 20 th, 2017 Public Reliability Modelling Background Per SAM 2.0: AESO is the responsible party for modelling

More information

NPCC 2018 Ontario Comprehensive Review Of Resource Adequacy FOR THE PERIOD FROM 2019 TO 2023 APPROVED BY THE RCC ON DECEMBER 4, 2018

NPCC 2018 Ontario Comprehensive Review Of Resource Adequacy FOR THE PERIOD FROM 2019 TO 2023 APPROVED BY THE RCC ON DECEMBER 4, 2018 NPCC 2018 Ontario Comprehensive Review Of Resource Adequacy FOR THE PERIOD FROM 2019 TO 2023 APPROVED BY THE RCC ON DECEMBER 4, 2018 This page intentionally left blank. ii Document Change History Issue

More information

2012 Probabilistic Assessment

2012 Probabilistic Assessment 2012 Probabilistic Assessment Methods and Assumptions June 2013 1 of 100 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 Table of Contents Table of Contents... i ERCOT... 1 FRCC... 9 MISO...

More information

Approved by the RCC November 27, Review of Interconnection Assistance Reliability Benefits. November 6, NPCC CP-8 Working Group

Approved by the RCC November 27, Review of Interconnection Assistance Reliability Benefits. November 6, NPCC CP-8 Working Group Approved by the RCC November 27, 27 Review of Interconnection Assistance Reliability Benefits November 6, 27 NPCC CP-8 Working Group NORTHEAST POWER COORDINATING COUNCIL, Inc. CP-8 WORKING GROUP REVIEW

More information

PJM Manual 21: Rules and Procedures for Determination of Generating Capability Revision: 12 Effective Date: January 1, 2017

PJM Manual 21: Rules and Procedures for Determination of Generating Capability Revision: 12 Effective Date: January 1, 2017 PJM Manual 21: Rules and Procedures for Determination of Generating Capability Revision: 12 Effective Date: January 1, 2017 Prepared by System Planning Department PJM 2017 Table of Contents Table of Contents

More information

Expanding Capacity Eligibility

Expanding Capacity Eligibility Expanding Capacity Eligibility Zachary T. Smith Manager, Capacity Market Design ICAPWG/MIWG March 7 th, 2019 Agenda Background Installed Capacity Supplier Payment Structure Peak Load Windows Counting MWs

More information

NERC Probabilistic Assessments Overview & Future Improvements

NERC Probabilistic Assessments Overview & Future Improvements NERC Probabilistic Assessments Overview & Future Improvements Noha Abdel-Karim, PhD. NERC IEEE LOLEWG Meeting July 31, 2015 Overview NERC Probabilistic Assessment (ProbA) reports extend the LTRA data with

More information

Standard BAL-502-RFC-02

Standard BAL-502-RFC-02 A. Introduction 1. Title: Planning Analysis, Assessment and Documentation 2. Number: BAL-502-RFC-02 3. Purpose: To establish common criteria, based on one day in ten year loss of Load expectation principles,

More information

Introduction to the PJM Markets

Introduction to the PJM Markets Introduction to the PJM Markets PJM 2015 1 Objectives Students will be able to: Describe some of the basic functions of PJM PJM 2015 The History of PJM EKPC joins PJM 2013 PJM 2015 3 Our Responsibility

More information

August 15, Mary Jo Kunkle Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway Lansing, Michigan, 48917

August 15, Mary Jo Kunkle Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway Lansing, Michigan, 48917 Melissa Seymour Regional Executive Central Region Direct Dial: 317-249-5709 Email: mseymour@misoenergy.org Mary Jo Kunkle Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway

More information

Rules and Procedures for Determination of Generating Capability

Rules and Procedures for Determination of Generating Capability PJM Manual 21 Rules and Procedures for Determination of Generating Capability Revision: 11 Effective Date: March 5, 2014 Prepared by System Planning Department PJM 2014 PJM 2007 Revision 05, Effective

More information

Using GE-MARS to estimate resource need for 33% RPS scenarios. January 2012

Using GE-MARS to estimate resource need for 33% RPS scenarios. January 2012 Using GE-MARS to estimate resource need for 33% RPS scenarios January 2012 Overview of methodology Uses GE-MARS, a loss-of-load probability (LOLP) model, to estimate the capacity needed to satisfy loss

More information

Ancillary Services Matrix

Ancillary Services Matrix Ancillary Services Matrix ERCOT Primary frequency response is not an Ancillary Service Market Product. All online Generation Resources must have their turbine governors in service and unblocked. is deployed

More information

Capacity Performance Training. June 24, 2015

Capacity Performance Training. June 24, 2015 Capacity Performance Training June 24, 2015 Training Objectives Provide Capacity Market Sellers with information necessary to participate in the Reliability Pricing Model (RPM) under a Capacity Performance

More information

4 Calculation of Demand Curve Parameters

4 Calculation of Demand Curve Parameters 4 Calculation of Demand Curve Parameters This section addresses the demand curve for the Alberta capacity market, including the calculations for the components of the demand curve. 4.1 Resource adequacy

More information

APRIL 23, Capacity Value of Wind Assumptions and Planning Reserve Margin

APRIL 23, Capacity Value of Wind Assumptions and Planning Reserve Margin APRIL 23, 2014 Capacity Value of Wind Assumptions and Planning Reserve Margin Executive Summary Effective Load Carrying Capacity (ELCC), or capacity value, of variable generation and required planning

More information

NPCC 2014 Québec Balancing Authority Area Comprehensive Review of Resource Adequacy

NPCC 2014 Québec Balancing Authority Area Comprehensive Review of Resource Adequacy 2014 Québec Balancing Authority Area Approved by the RCC - December 2, 2014 Comprehensive Review of Resource Adequacy NPCC 2014 Québec Balancing Authority Area Comprehensive Review of Resource Adequacy

More information

RPM 301 Performance in Reliability Pricing Model

RPM 301 Performance in Reliability Pricing Model RPM 301 Performance in Reliability Pricing Model PJM State & Member Training Dept. PJM 2017 Disclaimer: PJM has made all efforts possible to accurately document all information in this presentation. The

More information

RRS Education Session #1

RRS Education Session #1 RRS Education Session #1 Patricio Rocha Garrido Sr. Engineer Resource Adequacy Planning 11/24/2015 IRM/FPR Basics - Rationale IRM/FPR are computed for future delivery years. And the future is uncertain

More information

Capacity Performance FAQ Response

Capacity Performance FAQ Response PJM Interconnection September 15, 2014 This page is intentionally left blank. PJM 2014 www.pjm.com 2 P age Contents FAQ Response Introduction... 4 Capacity Products... 4 Methodology for Establishing Maximum

More information

RELIABILITY AND SECURITY ISSUES OF MODERN ELECTRIC POWER SYSTEMS WITH HIGH PENETRATION OF RENEWABLE ENERGY SOURCES

RELIABILITY AND SECURITY ISSUES OF MODERN ELECTRIC POWER SYSTEMS WITH HIGH PENETRATION OF RENEWABLE ENERGY SOURCES RELIABILITY AND SECURITY ISSUES OF MODERN ELECTRIC POWER SYSTEMS WITH HIGH PENETRATION OF RENEWABLE ENERGY SOURCES Evangelos Dialynas Professor in the National Technical University of Athens Greece dialynas@power.ece.ntua.gr

More information

Module E-1 Capacity Tracking Tool

Module E-1 Capacity Tracking Tool Module E-1 Capacity Tracking Tool Page 1 of 82 I. Disclaimer... 4 II. Document Change History... 5 1. INTRODUCTION... 6 1.1. Purpose... 6 1.2. Scope... 7 2. OVERVIEW... 7 3. RELATED DOCUMENTS AND REQUIREMENTS...

More information

Capacity Performance Training. March 16, 2015

Capacity Performance Training. March 16, 2015 Capacity Performance Training March 16, 2015 Training Objectives Provide Capacity Market Sellers with information necessary to participate in the Reliability Pricing Model (RPM) under a Capacity Performance

More information

MISO South Local Resource Zones (LRZ) Discussion. LOLE Working Group 5/8/2013

MISO South Local Resource Zones (LRZ) Discussion. LOLE Working Group 5/8/2013 MISO South Local Resource Zones (LRZ) Discussion LOLE Working Group 5/8/2013 Overview: Background Modeling Data Source MISO South Local Resource Zone Evaluations Proof of Concept Study Results Capacity

More information

2018/2019 NYSRC RELIABILITY RULE A.2 REQUIREMENTS R1, R2, R3 COMPLIANCE SUBMITTAL

2018/2019 NYSRC RELIABILITY RULE A.2 REQUIREMENTS R1, R2, R3 COMPLIANCE SUBMITTAL 2018/2019 NYSRC RELIABILITY RULE A.2 REQUIREMENTS R1, R2, R3 COMPLIANCE SUBMITTAL COVERING THE NEW YORK CONTROL AREA For the 2018 2019 Capability Year Presented to the Reliability Compliance Monitoring

More information

Standard BAL-502-RF-03

Standard BAL-502-RF-03 A. Introduction 1. Title: Planning Analysis, Assessment and Documentation 2. Number: BAL-502-RF-03 3. Purpose: To establish common criteria, based on one day in ten year loss of Load expectation principles,

More information

Load Modifying Resources. Capacity Instruments affecting Resource Availability and Need

Load Modifying Resources. Capacity Instruments affecting Resource Availability and Need Capacity Instruments affecting Resource Availability and Need May 25, 2018 Purpose Statement Review the participation and historic performance of Load Modifying Resources (LMRs) in MISO s Capacity and

More information

NPCC 2016 Ontario Interim Review Of Resource Adequacy

NPCC 2016 Ontario Interim Review Of Resource Adequacy Approved by the RCC December 6, 2016 NPCC 2016 Ontario Interim Review Of Resource Adequacy FOR THE PERIOD FROM 2017 TO 2020 DECEMBER 2016 [Type here] This page intentionally left blank. ii Document Change

More information

IMO Year 2003 Comprehensive Review of Ontario Resource Adequacy

IMO Year 2003 Comprehensive Review of Ontario Resource Adequacy Agenda Item 4.1 IMO Year 2003 Comprehensive Review of Ontario Resource Adequacy for the period 2004-2008 July 23, 2003 Public This page intentionally left blank. 1.0 EXECUTIVE SUMMARY 1.1 Major Findings

More information

APPENDIX I PLANNING RESERVE MARGIN STUDY

APPENDIX I PLANNING RESERVE MARGIN STUDY APPENDIX I PLANNING RESERVE MARGIN STUDY Introduction The planning reserve margin (), measured as a percentage of coincident system peak load, is a parameter used in resource planning to ensure there are

More information

Assessment of Marginal and Long-term Surplus Power in Orissa A Case Study

Assessment of Marginal and Long-term Surplus Power in Orissa A Case Study 1 Chandra 16th NATIONAL POWER SYSTEMS CONFERENCE, 15th-17th DECEMBER, 2010 103 Assessment of Marginal and Long-term in Orissa A Case Study Chandra Shekhar Reddy Atla, A.C. Mallik, Dr. Balaraman K and Dr.

More information

ATC Stakeholder Update 2019 PROMOD Study Assumptions. Tom Dagenais Todd Tadych ATC Economic Planning

ATC Stakeholder Update 2019 PROMOD Study Assumptions. Tom Dagenais Todd Tadych ATC Economic Planning ATC Stakeholder Update 2019 PROMOD Study Assumptions Tom Dagenais Todd Tadych ATC Economic Planning 7-10-09 1 Agenda / Introduction MISO RGOS Model Description MISO RGOS Model History and Background MISO

More information

PJM Resource Adequacy Analysis

PJM Resource Adequacy Analysis PJM Manual 20: PJM Resource Adequacy Analysis Revision: 05 Effective Date: February 1, 2013 Prepared by Resource Adequacy Planning PJM 2013 1 PJM Manual 20: Manual 20: PJM Resource Adequacy Analysis Table

More information

PJM Manual 20: PJM Resource Adequacy Analysis Revision: 08 Effective Date: July 1, Prepared by Resource Adequacy Planning

PJM Manual 20: PJM Resource Adequacy Analysis Revision: 08 Effective Date: July 1, Prepared by Resource Adequacy Planning PJM Manual 20: PJM Resource Adequacy Analysis Revision: 08 Effective Date: July 1, 2017 Prepared by Resource Adequacy Planning PJM 2017 Table of Contents Table of Contents Table of Exhibits...4 Approval...5

More information

NPCC 2015 Ontario Comprehensive Review Of Resource Adequacy FOR THE PERIOD FROM 2016 TO 2020 DECEMBER 2015

NPCC 2015 Ontario Comprehensive Review Of Resource Adequacy FOR THE PERIOD FROM 2016 TO 2020 DECEMBER 2015 NPCC 2015 Ontario Comprehensive Review Of Resource Adequacy FOR THE PERIOD FROM 2016 TO 2020 DECEMBER 2015 This page intentionally left blank. ii Document Change History Issue Reason for Issue Date 1.0

More information

PJM Organization and Markets. Saudi Delegation Columbus Ohio May 22, 2012

PJM Organization and Markets. Saudi Delegation Columbus Ohio May 22, 2012 PJM Organization and Markets Saudi Delegation Columbus Ohio May 22, 2012 Agenda Introduction & Governance Energy Markets LMP FTRs/ARRs Two Settlement Virtual Bids Ancillary Capacity - Reliability Pricing

More information

Deleted: RFC-02 12/04/08

Deleted: RFC-02 12/04/08 A. Introduction 1. Title: Planning Resource Adequacy Analysis, Assessment and Documentation 2. Number: BAL-502-RF-03 3. Purpose: To establish common criteria, based on one day in ten year loss of Load

More information

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) Background On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) The CAISO s deliverability study methodology for resource adequacy purposes was discussed extensively in the CPUC

More information

Integrating High Levels of Variable Renewable Energy Sources

Integrating High Levels of Variable Renewable Energy Sources Integrating High Levels of Variable Renewable Energy Sources Erik Ela EPRI Grid Ops and Planning eela@epri.com NYISO Environmental Advisory Council Troy, NY May 6, 2016 EPRI Grid Operations & Planning

More information

Adequate Summer Electricity Supplies Projected

Adequate Summer Electricity Supplies Projected Adequate Summer Electricity Supplies Projected Summer 2017 Reliability Assessment Overview The comprehensive reliability assessment conducted by the Northeast Power Coordinating Council, Inc. (NPCC) projects

More information

2010 Loss of Load Expectation Report PUBLISHED: 10/01/2010 LATEST REVISION: 10/08/2010

2010 Loss of Load Expectation Report PUBLISHED: 10/01/2010 LATEST REVISION: 10/08/2010 PUBLISHED: 10/01/2010 LATEST REVISION: 10/08/2010 Table of Contents Introduction... 2 Objective... 2 Background... 2 Study Assumptions... 3 Data discussion... 3 Topology... 3 Load... 3 Generation... 3

More information

STATE OF THE MARKET REPORT 2005

STATE OF THE MARKET REPORT 2005 STATE OF THE MARKET REPORT 2005 MRC Baltimore, MD March 15, 2006 Joseph E. Bowring Market Monitor Figure 4-4 - PJM s evolving footprint and its interfaces 1 PJM Market Monitoring Unit Independent Internal

More information

NPCC 2017 Ontario Interim Review of Resource Adequacy

NPCC 2017 Ontario Interim Review of Resource Adequacy NPCC 2017 Ontario Interim Review FOR THE PERIOD FROM 2018 TO 2020 APPROVED BY THE RCC ON DECEMBER 5, 2017 This page intentionally left blank. ii Document Change History Issue Reason for Issue Date 1.0

More information

Optimizing the Generation Capacity Expansion. Cost in the German Electricity Market

Optimizing the Generation Capacity Expansion. Cost in the German Electricity Market Optimizing the Generation Capacity Expansion Cost in the German Electricity Market Hamid Aghaie Research Scientist, AIT Austrian Institute of Technology Novemebr 2017 1 Motivation Energy-only Market Generators

More information

2013/2014 RPM Base Residual Auction Planning Period Parameters

2013/2014 RPM Base Residual Auction Planning Period Parameters Introduction The RPM Base Residual Auction (BRA) for the 2013/2014 Delivery Year is scheduled to be conducted in May of 2010. The planning period parameters to be used as input into the 2013/2014 BRA are

More information

CUSTOMER GUIDE TO PJM BILLING

CUSTOMER GUIDE TO PJM BILLING CUSTOMER GUIDE TO PJM BILLING Billing Line Items include PJM Open Access Tariff (OATT) references, PJM Operating Agreement (OpAgr) references, and PJM Manual references. Reports are available for viewing,

More information

Reliability Pricing Model (RPM) DRAFT Business Rules

Reliability Pricing Model (RPM) DRAFT Business Rules Definition and Purpose of Reliability Pricing Model (RPM) 1. The purpose of the RPM is to develop a long term pricing signal for capacity resources and LSE obligations that is consistent with the PJM Regional

More information

Resource Availability and Need

Resource Availability and Need Resource Availability and Need Issues Statement Whitepaper March 30, 2018 Table of Contents 1. Executive Summary... 2 2. Aging and Retirement of the Portfolio s Generating Units... 5 2.1. Retirements reduce

More information

Market Settlements - Advanced

Market Settlements - Advanced Market Settlements - Advanced RPM Module PJM State & Member Training Dept. PJM 2017 Capacity vs. Energy Capacity A commitment of a resource to provide energy during PJM emergency under the capped energy

More information

MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING

MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING December 22, 2014 Training Objectives To Provide an Overview of: The Market Efficiency proposal window process The critical modeling inputs

More information

2005 Integrated Electricity Plan. Resource Options Workshop #2 Planning Criteria March 09, 2005

2005 Integrated Electricity Plan. Resource Options Workshop #2 Planning Criteria March 09, 2005 2005 Integrated Electricity Plan Resource Options Workshop #2 Planning Criteria March 09, 2005 Agenda for Presentation Introduction Review industry reliability standards and regulatory Generation Reliability

More information

PJM Manual 20: PJM Resource Adequacy Analysis Revision: 0910 Effective Date: July 1, 2017March 21, Prepared by Resource Adequacy Planning

PJM Manual 20: PJM Resource Adequacy Analysis Revision: 0910 Effective Date: July 1, 2017March 21, Prepared by Resource Adequacy Planning PJM Manual 20: PJM Resource Adequacy Analysis Revision: 0910 Effective Date: July 1, 2017March 21, 2019 Prepared by Resource Adequacy Planning PJM 20182019 Table of Contents Table of Contents Table of

More information

2016 NERC Probabilistic Assessment - PJM RTO Region

2016 NERC Probabilistic Assessment - PJM RTO Region 2016 NERC Probabilistic Assessment - PJM RTO Region 2018 and 2020 Delivery Years December 5, 2016 Analysis conducted with assistance from the NPCC CP-8 WG Report written by PJM Staff Legal Notices PJM

More information

PJM Manual 18: PJM Capacity Market

PJM Manual 18: PJM Capacity Market PJM Manual 18: PJM Capacity Market Revision: 23 Effective Date: June 1, 2014 Prepared by PJM Capacity Market Operations PJM 2014 PJM 2014 i PJM Manual 18: PJM Capacity Market Manual 18: PJM Capacity Market

More information

CAPACITY MARKETS 5. Overview. RPM Capacity Market Market Design. Market Structure

CAPACITY MARKETS 5. Overview. RPM Capacity Market Market Design. Market Structure 2009 Quarterly State of the Market Report for PJM: January through September Section 5 - Capacity Markets Each organization serving PJM load must meet its capacity obligations by acquiring capacity resources

More information

2013 PJM Reserve Requirement Study

2013 PJM Reserve Requirement Study 2013 PJM Reserve Requirement Study 11-year Planning Horizon: June 1 st 2013 - May 31 st 2024 Analysis Performed by PJM Staff October 3, 2013 Reviewed by Resource Adequacy Analysis Subcommittee (RAAS) DOCS

More information

Capacity and Flexibility Needs under Higher Renewables

Capacity and Flexibility Needs under Higher Renewables Capacity and Flexibility Needs under Higher Renewables Project Deliverable October 1, 2015 Arne Olson, Partner Ana Mileva, Senior Consultant Elaine Hart, Managing Consultant Defining today s planning problem

More information

CONTENTS. Forward Executive Summary The Council s Resource Adequacy Standard Recent Adequacy Assessments... 8

CONTENTS. Forward Executive Summary The Council s Resource Adequacy Standard Recent Adequacy Assessments... 8 CONTENTS Forward... 4 Executive Summary... 5 The Council s Resource Adequacy Standard... 7 Recent Adequacy Assessments... 8 2023 Resource Adequacy Assessment...10 Sensitivity Analysis...10 Monthly Analysis...12

More information

1.3 Planning Assumptions and Model Development

1.3 Planning Assumptions and Model Development Section 1: Process Overview In addition, projects that originate through local Transmission Owner planning will be posted on the PJM web site. This site will include all currently planned transmission

More information

Evolution of the Grid in MISO Region. Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017

Evolution of the Grid in MISO Region. Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017 Evolution of the Grid in MISO Region Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017 1 MISO s mission is to ensure reliable delivery of low-cost energy through efficient,

More information

June 5, 2018 MEMORANDUM. Council Members. John Fazio, Senior Systems Analyst. SUBJECT: Briefing on Adequacy Analysis and Report BACKGROUND:

June 5, 2018 MEMORANDUM. Council Members. John Fazio, Senior Systems Analyst. SUBJECT: Briefing on Adequacy Analysis and Report BACKGROUND: James Yost Chair Idaho W. Bill Booth Idaho Guy Norman Washington Tom Karier Washington Jennifer Anders Vice Chair Montana Tim Baker Montana Ted Ferrioli Oregon Richard Devlin Oregon June 5, 208 MEMORANDUM

More information

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA For Compliance with NERC Reliability Standard: TPL-001-4 1/10/2017 Version: 4.2 Table of Contents 1 Revision and Approval History... 2 1.1 Revision

More information

Review of PJM Modeled LOLE AI John Adams NYSRC Consultant 5/4/2016

Review of PJM Modeled LOLE AI John Adams NYSRC Consultant 5/4/2016 Review of PJM Modeled LOLE AI-181-1.2 John Adams NYSRC Consultant 5/4/2016 Background The question was raised concerning whether PJM should be modeled at its 2016 LOLE value or the nominal criteria value

More information

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017 Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017 Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2

More information

2018/2019 RPM Base Residual Auction Planning Period Parameters

2018/2019 RPM Base Residual Auction Planning Period Parameters Introduction The planning parameters for the 2018/2019 RPM Base Residual Auction (BRA) that is to be conducted in May of 2015 were posted on the PJM RPM website on January 30, 2015. Two versions of the

More information

2008 QUÉBEC AREA COMPREHENSIVE REVIEW OF RESOURCE ADEQUACY

2008 QUÉBEC AREA COMPREHENSIVE REVIEW OF RESOURCE ADEQUACY 2008 QUÉBEC AREA COMPREHENSIVE REVIEW OF RESOURCE ADEQUACY Approved by the RCC, March 11, 2009 Prepared by Planning and Reliability Direction Electricity Supply Hydro-Québec Distribution March 2009 1.

More information

Background: ERCOT studies in 80 s and 90 s using NARP (N Area Reliability Program): o Small model in which each node represented a major load center

Background: ERCOT studies in 80 s and 90 s using NARP (N Area Reliability Program): o Small model in which each node represented a major load center A Direct High Speed Calculation Procedure For Determining LOLE, LOLH, and EUE For Fossil, Wind, and Solar Generation With A Suggested Procedure For Also Including Transmission Constraints a presentation

More information

Keith Beall; Edith L. Bandy;

Keith Beall; Edith L. Bandy; From: Kim McCloud To: MPSCEDOCKETS; CC: Keith Beall; Edith L. Bandy; Subject: Date: Attachments: U-16160 Midwest ISO 2010 Summer Assess Comments Thursday, April 29, 2010 6:16:08 PM Midwest ISO 2010 Summer

More information

Appendix 1 PRELIMINARY DELIVERABILITY BASELINE ANALYSIS STUDY REPORT

Appendix 1 PRELIMINARY DELIVERABILITY BASELINE ANALYSIS STUDY REPORT Generation and Import Deliverability to the Aggregate of Load (Baseline) Study Methodology Executive Summary Deliverability is an essential element of any resource adequacy requirement. Specifically, Load

More information

Concepts for Behind-the- Meter Net Generation

Concepts for Behind-the- Meter Net Generation Concepts for Behind-the- Meter Net Generation Pradip Ganesan Donna Pratt New York Independent System Operator Joint Meeting of Installed Capacity, Market Issues and Price Responsive Load Working Groups

More information

Resource Adequacy Modeling update. Technical Workgroup #4 June 14, 2018 AESO External

Resource Adequacy Modeling update. Technical Workgroup #4 June 14, 2018 AESO External Resource Adequacy Modeling update Technical Workgroup #4 June 14, 2018 Demand Curve Workgroup Objective: AESO Resource Adequacy Model Through the WG process, AESO seeks workgroup members review and feedback

More information

NPCC 2016 MARITIMES AREA COMPREHENSIVE REVIEW OF RESOURCE ADEQUACY Approved by RCC December 6, 2016

NPCC 2016 MARITIMES AREA COMPREHENSIVE REVIEW OF RESOURCE ADEQUACY Approved by RCC December 6, 2016 NPCC 2016 MARITIMES AREA COMPREHENSIVE REVIEW OF RESOURCE ADEQUACY Approved by RCC December 6, 2016 NEW BRUNSWICK POWER CORP. NOVA SCOTIA POWER INCORPORATED MARITIME ELECTRIC COMPANY, LIMITED NORTHERN

More information

A Revised Resource Adequacy Standard for the Pacific Northwest. NERC LOLE Work Group November 7-8, 2011 Austin, TX

A Revised Resource Adequacy Standard for the Pacific Northwest. NERC LOLE Work Group November 7-8, 2011 Austin, TX A Revised Resource Adequacy Standard for the Pacific Northwest NERC LOLE Work Group November 7-8, 2011 Austin, TX OUTLINE Makeup of the PNW s Power Supply NERC Definition for Adequacy PNW s Approach Sample

More information

Discussion Paper: Alberta Capacity Market Resource Adequacy

Discussion Paper: Alberta Capacity Market Resource Adequacy Discussion Paper: Alberta Capacity Market Resource Adequacy Background This document is part of Alberta Energy s stakeholder engagement on the resource adequacy standard as a factor in the reliability

More information

Day-ahead ahead Scheduling Reserve (DASR) Market

Day-ahead ahead Scheduling Reserve (DASR) Market Day-ahead ahead Scheduling Reserve (DASR) Market Agenda Implementation Overview of the DASR Market Market Clearing Process Market Clearing Example Performance Compliance Market Settlements Appendix: emkt

More information

2012 PJM Reserve Requirement Study

2012 PJM Reserve Requirement Study 2012 PJM Reserve Requirement Study 11-year Planning Horizon: June 1 st 2012 - May 31 st 2023 Analysis Performed by PJM Staff October 5, 2012 Reviewed by Resource Adequacy Analysis Subcommittee (RAAS) DOCS

More information

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved.

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. ASSOCIATED NERC STANDARD(S): TPL-001-4 (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. Phase in of individual TPL-001 requirements will be based on the effective dates

More information