GMR Holdings Private Limited

Size: px
Start display at page:

Download "GMR Holdings Private Limited"

Transcription

1 GMR Holdings Private Limited Development of LNG Facility at Kakinada Deep Water Port Pre-Feasibility Report April 2016 Submitted By: L&T Infrastructure Engineering Limited (formerly known as L&T-Ramboll Consulting Engineers Limited) RP001, Rev 0

2 Client: L&T Infrastructure Engineering Ltd. GMR Holdings Private Limited Project: Development of LNG Facility at Kakinada Deep Water Port Title: Pre-Feasibility Report (PFR) Project No.: Document No.: RP001 Rev.: 0 This document is the property of L&T Infrastructure Engineering Ltd. (formerly known as L&T-Rambøll Consulting Engineers Limited) and must not be passed on to any person or body not authorised by us to receive it nor be copied or otherwise made use of either in full or in part by such person or body without our prior permission in writing. Notes: 1. File path: document1 Revision Details: First Submission ALJ SAP CVS Init. Sign. Init. Sign. Init. Sign. Rev. Date Details Prepared Checked Approved

3 Table of Contents

4 TABLE OF CONTENTS 1 Executive Summary Introduction Project Background Need and Justification of the Project Employment Generation Organisation of the Report Consultants Appointed Project Description General Location Overview of LNG Facility LNG Handling Capacity LNG Storage LNG Unloading and Regasification Analysis of Alternatives Scenario Scenario Scenario Advantages of Selected Scenario Site Analysis General Connectivity to Site Topography Existing Land use Pattern Existing Kakinada Deep Water Port Meteorological and Oceanographic Parameters Meteorological Conditions Oceanographic Conditions Planning Brief Layout of the LNG Facility Vessel Characteristics Channel Requirements Turning Circle Dredging and Disposal Breasting/Mooring Dolphins Unloading Platforms LNG Storage Cryogenic Pipeline Regasification Facility/Technology At Location At Location Distribution Details Utilities Power Water Environment Management HTL/LTL and CRZ Map Resettlement and Rehabilitation Plan Project Schedule and Cost Estimates Project Implementation Cost Estimates Analysis of Proposal Table of Contents Page i

5 LIST OF FIGURES Figure 1: Regasification Facility Options...6 Figure 2: Location 1 Unloading and Regasification facility at Berth 7 of KDWP...9 Figure 3: Location 2 Unloading at Berth 7 and Regasification facility at Barge Mounted Power Plant Figure FD0101: Project Layout Figure FD0102: HTL/LTL and CRZ Map LIST OF TABLES Table 1: Natural Gas Demand Projects...4 Table 2: Demand and Potential LNG Requirement in India...4 Table 3: Regional LNG Requirement for Base Case...4 Table 4: Landuse Pattern in the Study Area Table 5: Depression/Storms in Kakinada region ( ) Table 6: Depression/Storms in Kakinada region ( ) Table 7: Vessel Characteristics of cum Table of Contents Page ii

6 1 Executive Summary The Indian economy presently is believed to have established itself on a healthy growth path and this would increase going forward the energy consumption in the country. This increase in consumption is expected to be supplemented by an alteration in the primary energy mix of India on account of the substitution of oil by natural gas. As per Vision 2030 Natural Gas Infrastructure in India Report by Industry Group for Petroleum & Natural Gas Regulatory Board, In future, the natural gas demand is all set to grow significantly at a CAGR of 6.8% from MMSCMD in to 746 MMSCMD in Currently the natural gas demand far exceeds domestic supply in India and the situation is likely to prevail in future as well. Given that there are very few new domestic sources available, additional demand is to be catered through RLNG. The natural gas deficit arising from the demand-supply mismatch is the potential that can be catered to by imported gas (i.e., regasified LNG). Southern region LNG demand deficit will be 19% in FY25 and 15% in FY35. Therefore, it is proposed to import liquefied natural gas (LNG) to Kakinada Deepwater Port and re-gasify it to meet the needs of GMR Energy Limited three power plants and other existing/ upcoming power plants and other industries would also benefit from the proposed LNG facility at Kakinada Port. With this, the project envisages to import 1.75 MTPA of LNG for the captive use of GEL power plants and the balance for other domestic users. The LNG facility is proposed to be developed at Berth 7 of KDWP. Berth 7 is already constructed and facilities required for LNG import need to be developed. At the ToR stage, two locations for regasification facility are being examined i.e. Location 1 being setting up regasification facility in the backup area available behind Berth 7 and Location 2 being setting up the regasification facility within the available land of GMR barge mounted power plant. Land required for development of LNG facility including regasification is ~48.1 acres in case of Location 1 and ~52 acres in case of Location 2. Considering location 2 as an eventual choice for regasification facility it would be necessary to lay on shore insulated cryogenic pipeline of ~3.2 km length. The LNG Carrier (LNGC) ranging in size from 80,000-90,000 m³ will be handled. The volumes of dredging would be limited to about 1.5 million cum considering the widening of the approach channel and turning circle. The construction and operation phase power requirement will be of the tune of 500 KW and 8 MW. The construction phase water requirement will be ~900 KL which will be sourced from existing supply of KDWP. Freshwater requirement during the operation phase of the project is 3.24 KLD and will be met through existing supply of KDWP. A sewage treatment plant (STP) of 2.5 KLD will be developed for treatment of sewage and reuse of treated wastewater will be carried out for irrigation of greenbelt and green areas. The estimated project cost for Location 1 is approximately INR 471 crores and Location 2 is INR 651 crores. Construction work will take around 6 months for development of 1.75 MTPA of LNG facility. The project envisages to generate direct employment of 72 and indirect employment of around Introduction GMR Holdings Private Limited (GHPL) and LNG Express India Pvt. Ltd. through their SPV are proposing to import LNG at Kakinada Deep Water Port (KDWP) in the state of Andhra Pradesh and supply LNG/RLNG to meet the demand of domestic customers. 1 Executive Summary Page 1

7 It is imperative to utilize the global softening of LNG prices for benefit/obligation of the industries meeting the emission norms using clean energy. Some of the industries are facing environmental concerns, Maintenance & Operational problems by using coal, rice husk, coal gas, biofuel bricks and other fuels. By bringing the LNG in to these above sectors, it will minimize and eliminate the above issues to a larger extent over a period of time thereby reducing greenhouse gases. GMR Energy Limited has been operating three power plants i.e. 220 MW barge mounted power plant near KDWP and 1138 MW gas based power plants at Vemagiri. Proposed LNG facility will cater gas requirements of the power plants to operate at optimum plant load. Additionally, it is envisaged that other existing and upcoming power plants would also benefit from the proposed LNG facility at Kakinada Port. 2.1 Project Background The Indian economy presently is believed to have established itself on a healthy growth path and this would increase going forward the energy consumption in the country. This increase in consumption is expected to be supplemented by an alteration in the primary energy mix of India on account of the substitution of oil by natural gas. The share of natural gas in the energy mix of India is expected to increase to 20% in 2025 as compared to 11% in 2010 (As per the Hydrocarbon Vision 2025 report). However, given that all the plans for expansion in natural gas supply in the country with the help of additional RLNG terminals, nationwide transmission pipeline network and transnational pipelines are expected to materialize by 2025, it is envisaged that the share of natural gas in the primary energy mix would reach 20% till 2030 if not more. In recent years the demand for natural gas in India has increased significantly due to its higher availability, development of transmission and distribution infrastructure, the savings from the usage of natural gas in place of alternate fuels, the environment friendly characteristics of natural gas as a fuel and the overall favourable economics of supplying gas at reasonable prices to end consumers. In future, the natural gas demand is all set to grow significantly at a CAGR of 6.8% from MMSCMD in to 746 MMSCMD in The supply of natural gas is likely to increase in future with the help of increase in domestic gas production and imported LNG. However, the expected increase in domestic production at present is significantly lower than earlier projections due to a steady reduction in gas output from the KG D6 field. Currently the natural gas demand far exceeds domestic supply in India and the situation is likely to prevail in future as well. Given that there are very few new domestic sources available, additional demand is to be catered through RLNG. Kakinada Deep Water Port is situated on East Coast of India (Latitude ' N Longitude 'E) which is an all-weather Port developed in a naturally sheltered bay called as Godavari Sand Spit (also called as Hope Island). Kakinada Bay, with water spread of about 2.5 sq.km is encircled and protected up to three quarters of its perimeter by the mainland and the "Hope Island". Hope Island had originated about 200 years ago from the mouth of the river littoral drift along the shoreline and had extended to a length about 11 nautical miles so far, thus forming into a natural breakwater protecting the entire eastern portion from the fury of the sea and providing tranquillity and shelter to the ships which are berthed at anchor in 1 Vision 2030 Natural Gas Infrastructure in India Report by Industry Group for Petroleum & Natural Gas Regulatory Board 2 Introduction Page 2

8 the Kakinada Bay. Thus, the Port of Kakinada has become one of the safest natural harbours on the East Coast of India. Kakinada Deep Water Port offers a very strategic location for development of LNG import handling facility and related infrastructure to meet the natural gas demand of the power plants and other domestic users in the region. The regasified LNG will be supplied to existing gas grid pipeline running parallel to Kakinada Port and some quantity of LNG in cryogenic state will also be transported to domestic customers using mobile tankers who are not connected through natural gas pipeline. 2.2 Need and Justification of the Project The Indian natural gas industry is relatively unseasoned, accounting for only 8 9% of the total energy consumption, while the world average is around 23.5%. In developed countries, the share of natural gas in the total energy basket is around 28 34%, while in other emerging countries like China, natural gas contribution to the total energy mix is as high as 33%. In India, consumption of natural gas has been steadily growing at 8.9% between 2001 and 2012 and is expected to grow further due to the advantages of lower costs and lower emissions. Natural gas consumption witnessed a steep year-on year increase of 21.5% at 56 Million Tonne Oil Equivalent (mtoe) in 2010 over 46 mtoe in 2009 and 25.5% year on year over 2008 owing to the cost-effective and cleaner nature of gas and the increased availability due to commencement of production from Reliance Industries Limited (RIL) in the Krishna- Godavari (KG) Basin. Natural gas is mainly consumed in the power generation and fertilizer industry, together accounting for 77% of the total consumption. The power sector consumption in 2010 was more than 45%. In the power sector, natural gas consumption grew by more than 69% in as compared to (Ministry of Petroleum and Natural Gas), which can be attributed to the increased allotment of gas from the KG Basin to power plants, following the commencement of production from the RIL KG Basin block. Other major users include the petrochemicals industry and the city gas distribution (CGD) network. While the domestic demand has been growing steadily, production has not grown on par to meet this demand, making way for LNG imports. LNG traffic through Indian ports has been growing rapidly over the past five years posting a CAGR of 14.8%. Demand for natural gas is also expected to grow given the higher level of overall economic activity in the country, lower volatility of gas prices as compared to liquid fuels, and rising environmental concerns, which increases the demand for cleaner fuels like gas. Power, fertilizer, and CGD sectors are expected to continue as the major consumer sectors of natural gas accounting for 86% of the natural gas demand. Growth in use of natural gas consumption in the country is expected to be driven by increased usage of gas in the above sectors and the growing demand from CGD. Based on the study conducted, the natural gas demand projections are given below: 2 Introduction Page 3

9 Table 1: Natural Gas Demand Projects FY16 FY17 FY20 FY25 FY30 FY35 FY40 Base Case Demand Optimistic Demand Note 1: Figures in mmscmd; Source: CRIS Analysis Note 2: For the optimistic case, the additional demand from power sector slippages have been added to the base case demand. The natural gas deficit arising from the demand-supply mismatch is the potential that can be catered to by imported gas (i.e., regasified LNG). The potential for LNG imports that can meet this demand is given below: Table 2: Demand and Potential LNG Requirement in India Units FY16 FY17 FY20 FY25 FY30 FY35 FY40 Base Case Demand mmscmd Production mmscmd Deficit mmscmd LNG Import Potential MT Optimistic Case Demand mmscmd Production mmscmd Deficit mmscmd LNG Import Potential MT Source: CRISIL Infrastructure Advisory Regional shares of the nationwide demand deficit and the volumes of LNG required based on the distribution of consumers are as shown below: Table 3: Regional LNG Requirement for Base Case Region FY25 FY35 FY25 FY35 Percentage LNG Demand East 7% 3% 5 8 North 32% 28% South 19% 15% West 42% 54% Source: CRISIL Infrastructure Advisory Under this strategy, it is proposed to import liquefied natural gas (LNG) at Kakinada Deep Water Port and re-gasify it to meet the needs of GMR Energy Limited two power plants and other existing/upcoming power plants and other industries will benefit from the proposed LNG facility at Kakinada Port. The project envisages to import 1.75 MTPA of LNG at KDWP, 0.85 MTPA is for the captive use of GEL power plants and the balance for other domestic users. 2.3 Employment Generation The project envisages to generate direct employment of 72 and indirect employment of around Organisation of the Report The PFR is prepared as per the Guidelines issued by the Ministry of Environment and Forests (Guidelines for preparation of Pre-Feasibility report for obtaining prior environmental 2 Introduction Page 4

10 clearance in terms of the provisions of EIA notification, 2006) dated December 30, In accordance with the guidelines, this report is structured into the following sections 2 : Chapter 1 : Executive Summary Chapter 2 : Introduction Chapter 3 : Project Description Chapter 4 : Site Analysis Chapter 5 : Planning Brief Chapter 6 : Resettlement & Rehabilitation Plan Chapter 7 : Project Schedule & Cost Estimate Chapter 8 : Analysis of Proposal 2.5 Consultants Appointed GHPL had appointed Engineers India Limited (EIL) to carry out pre-feasibility study for setting up the LNG facility at Kakinada Port. L&T Infrastructure Engineering Limited (LNTIEL) was appointed as EIA consultant and also for the preparation of Pre-Feasibility Report (PFR) as per the guidelines issued by Ministry of Environment, Forests and Climate Change (MoEF&CC). 3 Project Description 3.1 General In this chapter, a brief description of location, overview of LNG facility, site conditions, meteorological conditions and oceanographic conditions of project site are presented. 3.2 Location The LNG facility is proposed to be developed at Berth 7 of KDWP. Berth 7 is already constructed and facilities required for LNG import need to be developed. At the ToR stage, two locations for regasification facility are being examined which would be subject to further study during the DPR stage and the options are given below and shown in Figure 1: Regasification Location Option 1: The first location being examined is setting up regasification facility in the backup area available behind Berth 7. Regasification Location Option 2: The second location being examined is setting up the regasification facility within the available land of GMR barge mounted power plant located at ~1.5 km from Berth 7. 2 The subsections under each section have also been structured as per the Guidelines as applicable to the current project 3 Project Description Page 5

11 Figure 1: Regasification Facility Options 3.3 Overview of LNG Facility The proposed LNG facility consists of the following: Development of necessary facilities/equipment for ship berthing and mooring, LNG unloading arms with all safety measures LNG Storage and transportation Onshore Insulated Cryogenic Pipeline LNG Regasification Facility Control room Pig receiver and launcher/filter Pressure control system Metering Skid Pipeline for connectivity to existing gas distribution grid LNG Handling Capacity The project envisages a start-up capacity of 1.75 MTPA which comprises of a captive use by GMR Energy Limited to the tune of ~0.85 MTPA and the balance would comprise of domestic piped and non-piped domestic users within radius of 450 km LNG Storage LNG storage of 15,000 cum will be developed at Berth 7. The LNG storage tank shall operate at slightly above atmospheric pressure and approximately at (-) 162 C. The boil-off gas (BOG) handling system will be available at Berth 7. In case of regasification facility at 3 Project Description Page 6

12 Location 2, an additional storage of 1000 cum will be developed near barge mounted power plant LNG Unloading and Regasification The LNG Carrier (LNGC) ranging in size from 80,000-90,000 m³ will be handled. LNG will be unloaded continuously at a discharge rate of 400 to 500 m 3 /hr or less and pumped to LNG storage and regasification facility. In Location 1, unloading of LNG and regasification facility will be at Berth 7 of KDWP and in Location 2, unloading will be at Berth 7 and regasification facility will be at barge mounted power plant. The details of both are given below: Location 1 Unloading and Regasification Facility at Berth 7 Conventional LNG vessels will be moored at Berth 7 of KDWP and entire facility will be installed on Berth 7 for storage of LNG, Re-gas and Tanker loading. Multilayer Super Insulated Vacuum Jacketed LNG Transfer Pipeline shall connect the shore side of unloading arm with inlet flange of shore based flat bottom LNG storage tank. Flat bottom LNG storage tank shall have net capacity of m 3 capacity. The Boil off gas generated during transfer and storage of LNG shall be vaporized using Ambient Air Vaporizers and after due compression with the help of Boil off gas compressors transfer to high pressure gas pipeline through natural gas buffer storage tanks and required pressure control mechanism, and metering. High pressure centrifugal multi stage LNG pumps connected with Flat Bottom Storage Tank shall be utilized for boosting pressure of LNG. High pressure LNG will be transferred to regasification station to be developed at Berth 7. LNG regasification facility will utilize high pressure stainless steel lined aluminum finned fan forced ambient air cryogenic vaporizers. Tanker loading terminal will receive low pressure LNG with the help of low pressure stream of LNG centrifugal pumps connected to the flat bottom storage tank. The tanker loading terminal will enable loading LNG into 40 and 50 m 3 LNG tankers having pay load of 15.5 and 20 MT each for onward transmission to end user customers. The tankers plying on the road shall comply with required safety standards, codes, regulations and performance. The flow diagram is given in Figure Location 2 Unloading at Berth 7 and Regasification facility at Barge Mounted Power Plant Conventional LNG vessels will be moored at KSPL Port Berth 7. Multilayer Super Insulated Vacuum Jacketed LNG Transfer Pipeline shall connect the shore side of the unloading arm with inlet flange of shore based flat bottom LNG storage tank. Flat bottom LNG storage tank shall have net capacity of m 3 of LNG. The Boil off gas generated during transfer and storage of LNG shall be vaporized using Ambient Air Vaporizers and after due compression with the help of Boil off gas compressors transfer to high pressure gas pipeline through natural gas buffer storage tanks and required pressure control mechanism, and metering. Tanker loading terminal will receive low pressure LNG with the help of low pressure stream of LNG centrifugal pumps connected to the flat bottom storage tank. The tanker loading terminal will enable loading LNG into 40 and 50 m 3 LNG tankers having pay load of 15.5 and 20 MT each for onward transmission to end user customers. The tankers plying on the road shall comply with required safety standards, codes, regulations and performance. LNG will be transported through cryogenic pipeline of ~3.2km from Berth 7 to the storage tank at barge mounted power plant. Vacuum Insulted Cryogenic storage tank of 1000 m 3 3 Project Description Page 7

13 capacity will be installed at Barge Mounted Power Plant. High pressure centrifugal multi stage LNG pumps connected with 1000 m 3 Storage Tank shall be utilized for boosting pressure of LNG. High pressure LNG will be transferred to regasification stations. Two (02) types of Re-gas systems i.e. Hot Water Bath Regasification System and Fan Forced Ambient Air Vaporizer will be utilised. The re-gasified LNG in the form of high pressure natural gas will be transferred to custody metering station and inject natural gas into the gas grid for onwards transmission to end user consumers connected to pipeline. The flow diagram for option 2 is given in Figure 3. 3 Project Description Page 8

14 Figure 2: Location 1 Unloading and Regasification facility at Berth 7 of KDWP 3 Project Description Page 9

15 Figure 3: Location 2 Unloading at Berth 7 and Regasification facility at Barge Mounted Power Plant 3 Project Description Page 10

16 3.4 Analysis of Alternatives Scenario 1 Scenario 1 includes the mooring of LNG vessel of size to cum capacity with buoys to the west of Hope Island in open sea conditions for ship to ship (STS) operations. Thereafter, transportation of LNG by smaller shuttle tankers to LNG floating storage tanker stationed at the proposed jetty near the barge power plant site. In this scenario, Regasification facility is proposed in area adjacent to barge mounted power plant Scenario 2 Scenario 2 includes the mooring of LNG vessel of size to cum capacity with buoys to the west of Hope Island in open sea conditions for ship to ship (STS) operations. Thereafter, transportation of LNG by smaller shuttle tankers to LNG tanker stationed at berth number 7 of KDWP jetty. In this scenario, Re-gasification facility is proposed at area behind berth number 7 of KDWP Scenario 3 Scenario 3 includes berthing of LNG vessel of size to cum at Berth No. 7 of KDWP Port. The vessel will use the existing navigation channel of KDWP to reach Berth No. 7. In this scenario the regasification facility will be either behind Berth 7 or near barge mounted power plant Advantages of Selected Scenario Above three scenarios have been studied for the location of proposed LNG facility. Based on the following aspects, Scenario 3 has been finalised: LNG vessel will be berthing at Berth No.7 by using the existing navigation channel with some widening. Dredging requirement will be less and therefore disposal of material will also be less No disturbance to movement of fisher crafts because in Scenario 1 & 2 mooring of mother vessel and shuttle tanker movements will cause hindrance to fishing crafts. Construction activities are limited to development of LNG import facilities as Berth No. 7 is already available. Activity will be away from Hope Island and Eco-sensitive Zone of Coringa wildlife sanctuary No requirement of new navigation channel and turning circle for the feeder LNG shuttles Less number of vessel movements In case of Scenario 3, Boil off gas from the LNG Carrier can be completely recovered, pre-heated, compressed and utilized compared to scenario 1 and 2 where STS operations are planned. As water required for Hot water bath heater will be sourced from barge mounted power plant, therefore, cryogenic energy in LNG can be recovered to improve efficiency of barge mounted power plant and this will meet National cold conversion program from Government of India which inline is complied with and also meeting the requirements of OISD 194 (Part 4.9) 3 Project Description Page 11

17 4 Site Analysis 4.1 General The prevailing environmental parameters of the project site are essential to assess suitability of site and for planning. This chapter details the location of site, connectivity, existing features, meteorological conditions, oceanographic conditions, environmental aspects and other infrastructure. 4.2 Connectivity to Site KDWP is located on the Kakinada to Samalkot arterial road connecting to NH-5. Road connectivity from Kakinada is good and includes the National Highway 214 (NH-214) from Kathipudi to Ongole which also joins National Highway 16 (NH-16). Two state highways connect Kakinada to Rajahmundry. The nearest airport to Kakinada is at Rajahmundry, which is located approximately 65 km from the city, and has flight services to Chennai, Hyderabad and Vijayawada. The nearest major airport is at Visakhapatnam, which is at a distance of 145 km and has the services of many airline operators flying to major cities across the country and outside India. Kakinada is well connected by broad gauge railway to Hyderabad, Visakhapatnam and Chennai. Through a branch line, Kakinada is connected to Samalkot Junction (13 km) which is on the Chennai-Howrah trunk line, where most express trains stop and provide connectivity to Kakinada with major regional towns and cities. A railway connection exists at Kakinada Port Railway station. Connection to the deep water port has been taken at NFCL. A Reception and Dispatch yard and two spurs to the berths have been provided for facilitating movement of bulk cargo to the stacking yards behind the berths. 4.3 Topography The land near the coast, both at Kakinada Harbour and the area around the Bay of Kakinada is flat with sandy soil and with an average level of ~2.5 m above mean sea level. 4.4 Existing Land use Pattern Only 53% of 10 km radius is land area and the remaining 47% is Bay of Bengal. The table below presents the land use. Table 4: Landuse Pattern in the Study Area S. No. Landuse Area in Acres Percentage (%) 1 Hope Island Agricultural Land Settlements Plantations Industrial Area Mud Flats Barren Lands Water Bodies Salt Pans Forest (Mangroves) Dry water bodies Port Area Others Total Site Analysis Page 12

18 The land use distribution depicts about 33% is agricultural land and about 15% area is under plantations. Casuarina and cashew plantation are observed along the coast. 4.5 Existing Kakinada Deep Water Port Kakinada deep water port (KDWP) is located on the coast of Kakinada, Bay of Bengal in Andhra Pradesh. The geographical location of the Port is 16 58'35" N and '45" E. The port is naturally protected by Hope Island towards eastern side. Main Jetty has Six (06) berths and One (01) OSV berth. Total length of quay (7 berths) is ~1900 m and the length of OSV berth is 58m. The OSV Jetty has two finger jetties of 4 x 90m with berthing faces of 2 x 40 m. NRW extension with multipurpose berth of length 635 m (North)/ 150 m (South). The port has the navigation facilities i.e. navigation channel of length 10 km and channel of m depth, berthing area of depth m and turning circle diameter is 500 m. Liquid bulk imports include of POL products edible oil, phosphoric acid, sulphuric acid and ammonia. Dry bulk cargo imports include fertiliser raw material, coal, wood and pulp. Exports of cargo include iron ore, cement, clinker, white minerals such as bentonite, feldspar and general cargo like steel coils, billets, slabs, granites, grains, OSV rings etc. 4.6 Meteorological and Oceanographic Parameters Meteorological Conditions The climate in the area is tropical monsoon type. Wind patterns are governed by the SW & NE monsoons and transition periods between them, dividing the year into four seasons. The two transition periods, March-May (pre-monsoon / summer) and October-November (postmonsoon) are characterized by occurrence of Cyclonic storms, the latter period being more active. The South-West monsoon (June-September) is characterized by strong, persistent wind and rough seas. Majority of the annual rainfall in the region is during South-West monsoon (June-September). The general climatological condition as per recorded data at Kakinada is presented below: The highest recorded temperature is C (May-June) and lowest C (December) Relative humidity varies from 61% to 90% The average annual rainfall in Kakinada area is about 1115 mm ( mm). The highest recorded monthly rainfall is mm in October, 1994 The predominant wind direction during North-East monsoon is from North through East. Wind speeds greater than 30 kmph are for about 22% of the time, while the transitional periods are characterized by low speed variable winds, when there are no storms. The tropical depressions / cyclones in Bay of Bengal occur very frequent especially during post-monsoon season (October-November-December). Though occur rarely, the cyclones during pre-monsoon and SW monsoon are generally more intense in nature. The most severe storm effected the project region was in November 1996 which tracked across in the southern part with sustained wind speeds of 115 knots (59 m/s). The weather is hot and humid during most part of the year. The hottest part of the year is May & 1 st week of June with maximum temperatures around C. The coolest part of the year is January, with minimum temperatures around C. The project area gets most of the annual rainfall during southwest monsoon season (June-September) although a significant rainfall occurs during the northeast monsoon season from mid-october to mid- December. Tropical Depressions & Cyclones in the Bay of Bengal are frequent, few of which 4 Site Analysis Page 13

19 affect the project area. Prevailing winds in Kakinada are usually south westerly for most part of the year except during October to January when wind blows from northeast and east. Kakinada recorded an average annual rainfall between 1100 mm and 1150 mm in the last 10 years. The climatology of the area do not pose any constraint for the project apart from cyclones Oceanographic Conditions Bathymetry The bathymetry of the region is reduced to Chart Datum using predicted tides at Kakinada Port. The bathymetry inside the Hope Island varies from a minimum of 1.5m from Light House at Hope island and 1.8m at Southwest corner to a maximum depth of 15.7m from Kilometre Point (KP) The Main KDWP Inner channel is marked with depth ranging between 13.4 KP and KP and shoals up to either side of the channel with a general slope of approximately 1:25. The Main KDWP Outer Channel is marked with depths ranging between KP and 15.7 at KP and shoals up to either side of the channel with a general slope of approximately 1:22 except nearer to Hope Island region. Towards the Hope Island region between KP and KP 6.000, in the eastern side of the survey area, depth decreases to 1.5m with a slope of approximately 1:12. In the Main Berth and Turning circle area, the depth ranges between 11.2 and 14.5 m. Approach Basin is marked by the depth varying between 4.2m and 13m Geo-Technical Conditions Kakinada Deep Water Port had undertaken marine geotechnical investigations within the harbour area and the soil classification up to a depth of 8.5 m from the sea bed consist of very soft silty clay with traces of shell fragments and with low N values. The layer between 8.5 to 10m consist of silt with sand and clay particles and low to moderate SPT. Beyond 10m very stiff clay with moderate to high SPT is observed Tides Near Kakinada tides are semi-diurnal with a mean spring range of 1.3m and mean neap tidal range of 0.5m. The maximum current speeds are 0.4 m/s during spring tide and 0.15 m/s during neap tide. The tidal levels with respect to chart datum as reported in Naval Hydrographic Chart No are as follows: Mean High Water Spring m w.r.t CD Mean High Water Neap m w.r.t CD Mean Low Water Neap m w.r.t CD Mean Low Water Spring m w.r.t CD Mean Sea Level m w.r.t CD During October, the spring tide heights are notably higher reaching 2.0 m mainly due to persistent northeast winds. The above values clearly indicate that tidal variation is limited to 1.3m Currents The currents monitored during monsoon season in Kakinada bay, the maximum current speed at mid-depth was observed as 0.7 m/s. and the directions varies between northeast and southwest. The reported current values are within permissible limits for the project activities. 4 Site Analysis Page 14

20 Waves The rough sea conditions prevail during SW monsoon season with waves >2m height during 68% of time and also in NE monsoon season with waves >2m height for about 32% of time. These however do not affect Kakinada Bay area (project site), as it is protected by Hope Island from the east as well as south sides. The predominant offshore wave directions: During November March waves are predominantly from Northeast During March September waves from Southwest are predominant During October (transition period) waves from SW and from NE are equally common Significant wave heights during the NE monsoon vary between 0.2 m to 0.8 m and the corresponding wave periods vary between 5 and 7 seconds. These ranges in wave Height and period account for more than 90% of the observations indicating that waves during the NE monsoon are generally low. Significant wave heights during SW monsoon are slightly higher with heights between 0.4 m to 1.2 m, the corresponding wave periods 6 9 seconds. Long waves with periods between 9 and 11 seconds are also observed during both the monsoons and their percentage of occurrence is only 11% and 18% time during the NE and SW monsoons respectively. The near shore waves on annual basis are predominant in eastsoutheast directions. Based on the above wave data, it can be prima-facie concluded that tranquil conditions prevail in the basin for mooring and ship navigation Wind The average wind speed does not exceed 19 kmph for about 87% of time and the direction of wind varies with period of monsoon. In general wind speeds are stronger in the evening. Wind are mainly from NE (29.6%), SW (20.4%), E(15.8%) and S(11%) During south west monsoon, the wind speeds are weak averaging 1.5 m/sec and during NE monsoon, windare moderate to average (3m/sec). The land and sea breeze effect is characteristics to the NE monsoon causing the average wind speed to increase from m/sec at 8.00 hrs to m/sec at hrs. The direction is from landward during the day and seaward during the night Depression/Storms in Bay of Bengal The data on number of cyclones and depressions in Kakinada region for 80 years indicate the risk of severe cyclones is highest in may and june and from September till November. The number storms and depressions that have developed in the Bay of Bengal in the Kakinada region during is given below Table 5: Depression/Storms in Kakinada region ( ) S. No Month Storms Depressions Total 1 January February March April May Jine July August September October November December Total Site Analysis Page 15

21 It can be seen there from that a total of 83 storms and depressions have been observed near Kakinada during the above period of which 33 were cyclonic storms. During the cyclone of 1969, maximum wind speed exceeded 12 on the Beaufort scale and wave heights exceeded 5m outside Kakinada Bay. The sea level rise during the passage of the storm was reported to be 3.35 m, which is 1.86 above the normal spring tide level. Information on cyclonic storms are available in the E-Atlas for the period 1972 and 2007 Storm data from UNISYS for the period 2008 and Between 2008 and 2010, UNISYS shows only one storm during May 2010, and no depressions. Frequency of Occurrence of Storms and depressions in the vicinity of Kakinada Port in 2 x 2 Degree Sector (Source: IMD E-Atlas and UNISYS ) Table 6: Depression/Storms in Kakinada region ( ) Month Storms Depression Total January February March April May June July August September October November December Total A very severe cyclonic storm, Phailin, occurred from October 8 to 14, 2013 and made a landfall close to Gopalpur, Orissa. The cyclonic storm recorded wind speeds of 200 kmph with a maximum storm surge of 2 m above the astronomical tide. The cyclonic storm had an impact on Kakinada with a heavy intensity of rainfall recording up to 180 mm in a period of 24 hr. However, the storm surge at Kakinada was negligible. A severe cyclonic storm, Helen, made a landfall at Machilipatnam during November 18 to 21, Wind speed of 120 kmph was recorded between Kakinada and Machilipatnam with a maximum storm surge of 1.5 m above the astronomical tide. Another severe cyclonic storm, Hudhud, made a landfall at Visakhapatnam on October 12, Wind speeds of 80 kmph were recorded between Kakinada and Machilipatnam with a maximum storm surge of 1.5 m above the astronomical tide. 5 Planning Brief The development is planned for the following activities Extension of existing Berth 7 of KDWP to the southern side (Details of extension would be finalised during the DPR stage) To carry out widening of the approach channel based upon ship sizes and PIANC guidelines (the necessity of widening would be determined during the DPR stage by way of ship navigation simulation studies) On shore Insulated Cryogenic pipeline in case regasification skid is located at barge mounted power plant Establishment of regasification skid Pipeline for connectivity to existing gas grid 5 Planning Brief Page 16

22 5.1 Layout of the LNG Facility The layout of the LNG facility at Kakinada Deep Water Port is given as FD0101. Land required for development of LNG facility including regasification is ~48.1 acres in case of Location 1 and ~52 acres in case of Location Vessel Characteristics It is proposed to handle LNG vessel of size to cum. The characteristics of 90,000 cum LNG vessel are given below: Table 7: Vessel Characteristics of cum S. No Parameter Dimensions 1. Length 240m 2. Breadth 40m 3. Draft 11.0m 4. Dead weight tonne Channel Requirements The existing navigation channel within Kakinada Deep Water Port has a bed width of 160 m with adequate side slopes. The navigational requirement as per PIANC guidelines stipulates channel width of 5 times the beam of design vessel. It is therefore necessary to take up navigation simulation study to ascertaining the widening of approach channel and the extent thereof. 5.4 Turning Circle The existing turning circle has a diameter of 500 m and considering the LOA of the design vessel as 240m. The turning circle requirement of LNGC is 480m which is twice the LOA of design vessel. 5.5 Dredging and Disposal The volumes of dredging are minimal and the extent would be limited to about 1.5 M cum considering the widening of the approach channel and turning circle. During the DPR stage the dredged disposal study would be undertaken by way of mathematical modelling analysis and the disposal area would be determined. The existing designated dumping area of KDWP would also be made use of. 5.6 Breasting/Mooring Dolphins The detailed project report would undertake the detailed analysis of the existing length of Berth 7 and by duly considering the safety radius as per OISD guidelines, determine the extension towards the south. The extension would be required for safe mooring of the vessel and suitable mooring dolphins with an approach platform would be developed. 5.7 Unloading Platforms As berth 7 is available and same will be used as unloading platform, only suitable number of unloading arms would be provided on the platform. 5 Planning Brief Page 17

23 5.8 LNG Storage LNG storage of 15,000 cum. will be installed at Berth 7. The LNG storage tank shall operate at slightly above atmospheric pressure and approximately at (-) 162 C. An additional storage of 1000 cum will be developed in case of development of regasification facility at barge mounted power plant. 5.9 Cryogenic Pipeline Considering Location 2 as an eventual choice for regasification facility it would be necessary to lay onshore cryogenic pipeline of ~3.2 km length Regasification Facility/Technology At Location 1 Fan Forced Ambient Air Regasification facility will be used. In this technology, multiple banks of fan forced ambient cryogenic vaporizers are used in parallel and serious combinations. Cryogenic LNG is fed into the inlet manifold system and distributed through banks of fan forced vaporizers. Fans on the top of the ambient vaporizers force down fresh ambient air from the top at all times and this provides required energy to re-gasify the LNG. Outlet temperature of RLNG remains 10 to 15 lower than ambient air. During the process moisture condenses surrounding the fins and after a few hours banks of vaporizers are interchanged and switched over for operations. The banks of vaporizers which have completed their duty go through a cycle of defrosting and after this cycle of defrosting they are ready for the next cycle LNG regasification operation. Interconnecting piping on inlet and outlet along with valves, instrumentation are provided for accurate distribution of LNG for re-gasification. Forced air circulation allows for accurate heat exchanger and also prevents excessive ice build-up around the heat exchanger fins. Shorter switching cycles also ensure that the ambient temperature surrounding the Regasification station remain closer to discharge temperature of gas. It is estimated that air temperature surrounding regasification station up to 10 Meters of distance, which will be well within boundary limits of the regasification station shall be approximately 15 to 20 below ambient depending on moderate wind condition and wind velocity At Location 2 A combination of Hot Water Bath Regasification system and Fan Forced Regasification System will be used. Hot water from the power plant is required to be cooled and also chilled for the process cooling requirement. In regular practice, cooling towers are used for cooling the hot water to a temperature near ambient temperature. For further reducing the water temperature, chillers are used. Since cryogenic energy is available in the form of LNG stored at -162 C, the process water will be cooled to the required temperature. This available differential temperature in the form of LNG is quite large, therefore it is possible to achieve very low temperature to obtain highest efficiency of cooling and power production. The system deploys a water bath made out of concrete construction in which all stainless steel heat exchanger is submerged along with required tabulators and agitators. Hot water from the power plant runs into the bath and cold water from the bath is sent back to the power plant. Stream of high pressure LNG is run through multiple passes through the heat exchangers and in the process LNG is regasified. Adequate number of temperature sensors, 5 Planning Brief Page 18

24 water level indicators and sensors, valves and gauges, etc. are installed on the equipment for the operating and safety requirements. Therefore from the concept development stage it is decided to recover cold from LNG in the form of cryogenic energy and utilize the same for process cooling for the barge mounted power plant, to improve the cooling efficiency covering the NCCD initiatives and OISD 194 (Part 4). Fan forced ambient air regasification system will be used to re-gas the balance quantity of LNG after utilizing the cryogenic energy at hot water bath Distribution Details The LNG and RLNG distribution details are provided in sections and and are shown in Figure 2 and Figure Utilities Power The construction phase power requirement will be of the tune of 500 KW and will be sourced from existing grid or KDWP power supply. During operation phase 8 MW of power will be met partly from existing grid and partly from power generators by using Boil off gas Water The construction phase water requirement will be ~900 KL which will be sourced from existing supply of KDWP. In case of Location 2 regasification facility, the water requirement for Hot Water Bath Regasification system will be 3280 m 3 /hr. This is a close loop water circulation system received from the barge mounted power plant and cooled water is supplied back to the power plant. Potable water requirement during the operation phase will be around 3.24 KLD and will be met through existing supply of KDWP Environment Management There is no waste water generation in the LNG Storage and Re-gasification system; however, during the process of fan forced re-gasification system there is clean water generation for which a collection and utilization plan will be prepared. This clean water is the result of moisture condensed, iced deiced and collected in the trench below the regasification station. Utilising of this clean water for potable use will be explored. Alternatively, this trench can be connected to storm water drainage if no use is envisaged. A sewage treatment plant (STP) of 2.5 KLD will be developed for treatment of sewage and reuse of treated wastewater will be carried out for irrigation of greenbelt and green areas HTL/LTL and CRZ Map The HTL/LTL and CRZ Map with proposed LNG facility is given as FD Resettlement and Rehabilitation Plan There will not be any land acquisition and hence no R&R Issues with the project development. 6 Resettlement and Rehabilitation Plan Page 19

25 7 Project Schedule and Cost Estimates 7.1 Project Implementation After obtaining necessary clearances from statutory authorities, the development of LNG facility will be completed within 6 months. 7.2 Cost Estimates The estimated project cost for Location 1 is approximately INR 471 crores and Location 2 is INR 651 crores. 8 Analysis of Proposal Demand for natural gas is also expected to grow given the higher level of overall economic activity in the country, lower volatility of gas prices as compared to liquid fuels, and rising environmental concerns, which increases the demand for cleaner fuels like gas. Power, fertilizer, and CGD sectors are expected to continue as the major consumer sectors of natural gas accounting for 86% of the natural gas demand. Growth in use of natural gas consumption in the country is expected to be driven by increased usage of gas in the above sectors and the growing demand from CGD. Presently the consumers who are connected through gas grid are getting benefits of natural gas. As laying a new pipeline to small scale industries is not a viable option, therefore, we propose to transport considerable volumes of LNG to all potential users in extremely safe conditions by road tankers. This enables use clean and environment friendly fuel at optimum level. Under this strategy, it is proposed to import liquefied natural gas (LNG) at Kakinada Deep Water Port and re-gasify it to meet the needs of GMR Energy Limited three power plants and other existing/upcoming power plants and other industries will benefit from the proposed LNG facility at Kakinada Port. 7 Project Schedule and Cost Estimates Page 20

26 FIGURES

27

28

29 L&T INFRASTRUCTURE ENGINEERING LIMITED (Formerly Known as L&T-RAMBØLL CONSULTING ENGINEERS LIMITED) /1/1, 5 th Floor, Block No.3, White House, Kundan Bagh, Begumpet, Hyderabad Ph: ; Fax:

Petronet LNG Ltd., India. LNG Terminal Design- Major Design Considerations

Petronet LNG Ltd., India. LNG Terminal Design- Major Design Considerations Petronet LNG Ltd., India LNG Terminal Design- Major Design Considerations OVERVIEW 1. What is LNG and LNG Chain 2. Project Development & Site Selection 3. Studies Required 4. Marine Facilities 5. Storage

More information

CHAPTER 3: GENERAL DESCRIPTION OF THE PROPOSED COEGA INTEGRATED POWER PROJECT

CHAPTER 3: GENERAL DESCRIPTION OF THE PROPOSED COEGA INTEGRATED POWER PROJECT : GENERAL DESCRIPTION OF THE PROPOSED COEGA INTEGRATED POWER PROJECT CONTENTS 3. GENERAL DESCRIPTION OF THE PROPOSED COEGA 3-1 3.1 Overview of the Coega Integrated Power Project 3-1 3.2 Description of

More information

GMR Holdings Private Limited

GMR Holdings Private Limited GMR Holdings Private Limited Development of LNG Facility at Kakinada Deep Water Port PROPOSED TERMS OF REFERENCE April 2016 Submitted By: L&T Infrastructure Engineering Limited (formerly known as L&T-Ramboll

More information

Marine Facilities for LNG Carrier Transfer Alternatives

Marine Facilities for LNG Carrier Transfer Alternatives 2.3.3.2 Marine Facilities for LNG Carrier Transfer Alternatives Two alternatives were considered for the marine facilities to support the transfer of LNG between the LNG carriers and onshore storage tanks.

More information

Lars Odeskaug - TORP CEO

Lars Odeskaug - TORP CEO Lars Odeskaug - TORP CEO Agenda Introduction TORP s EasyLNG Regas Terminal Solution LNG Vaporizers Compliance Alternative Klaipeda Lay-Outs Schedule LNG Ship Bunker Station & Road Depots 2 30 Years of

More information

Appendix A: Project Characteristics

Appendix A: Project Characteristics Gorgon Fourth Train Expansion Proposal Appendix A: Project Characteristics Appendices Project Characteristics A Key Characteristics table has been prepared to describe the elements of the Foundation Project

More information

AL-AMEEN ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK

AL-AMEEN ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK AL-AMEEN ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE 6604 - RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK UNIT 1 RAILWAY PLANNING PART A 1. Define Permanent way. 2. List out the elements

More information

Accord Energy Corporation India Pvt. Ltd.

Accord Energy Corporation India Pvt. Ltd. Accord Energy Corporation India Pvt. Ltd. PRE-FEASIBILITY REPORT ON ENVIRONMENTAL ASPECTS OF PROPOSED INCREASE IN CAPACITY 2 x 150 MW to 2 x 180 MW OF EXISTING ENVIRONMENTAL CLEARANCE ( J-13012/107/ 2009-IA-II

More information

Terms of reference for Improving the capacity utilization of OR-I & OR-II berths at Visakhapatnam port trust (VPT), Andhra Pradesh, India.

Terms of reference for Improving the capacity utilization of OR-I & OR-II berths at Visakhapatnam port trust (VPT), Andhra Pradesh, India. Proposed Terms of Reference for EIA studies: Terms of reference for Improving the capacity utilization of OR-I & OR-II berths at Visakhapatnam port trust (VPT), Andhra Pradesh, India. 1.0 INTRODUCTION:

More information

LNG Business In India

LNG Business In India LNG Business In India 2016 Topics Gas Demand / Supply Balance in India. Sector wise demand & sensitivity to price. Pricing of LNG ( Henry Hub, NBP, Long term ) Pipeline Infrastructure. Regasification Terminal

More information

On Board Regasification for LNG Ships. 22 nd World Gas Conference WS 3-2 Tokyo 2003 Wayne Perry

On Board Regasification for LNG Ships. 22 nd World Gas Conference WS 3-2 Tokyo 2003 Wayne Perry On Board Regasification for LNG Ships 22 nd World Gas Conference WS 3-2 Tokyo 2003 Wayne Perry New Greenfield U.S. Terminals Will Be Almost Impossible to Site Key opportunity is to solve U.S. terminalling

More information

Kadam Environmental Consultants w w w. k a d a m e n v i r o. c o m

Kadam Environmental Consultants w w w. k a d a m e n v i r o. c o m AHIR SALT AND ALLIED PRODUCTS PVT. LTD. Pre-feasibility report for Revival of Existing Jetty with Liquid Storage Terminal, Pipeline, road connectivity, Railway line and sidings at Mithirohar near (Kandla),

More information

During the discussions, the Committee finalized the following additional TOR for further study:

During the discussions, the Committee finalized the following additional TOR for further study: Finalization of ToR for development of Visakhapatnam?Kakinada Corridor for the Establishment of Petroleum, Chemicals and Petrochemicals Investment Region (VK- PCPIR), Andhra Pradesh by M/s VK- PCPIR Special

More information

INVESTMENT POTENTIAL INVEST IN PORT TERMINALS AT THE PORT OF WALVIS BAY NORTH PORT PROGRAM DATE: 29 AUGUST 2016 REVISION: 1

INVESTMENT POTENTIAL INVEST IN PORT TERMINALS AT THE PORT OF WALVIS BAY NORTH PORT PROGRAM DATE: 29 AUGUST 2016 REVISION: 1 INVESTMENT POTENTIAL INVEST IN PORT TERMINALS AT THE PORT OF WALVIS BAY NORTH PORT PROGRAM DATE: 29 AUGUST 2016 REVISION: 1 CONTENTS 1 Port of Walvis Bay North Port Development Program Overview 1.1 Brief

More information

TEMA LIQUEFIED NATURAL GAS PROJECT ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT

TEMA LIQUEFIED NATURAL GAS PROJECT ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT TEMA LIQUEFIED NATURAL GAS PROJECT ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT Final Scoping Report - Non-Technical Summary Introduction Quantum Ghana Gas Limited (Quantum) proposes to develop the Tema

More information

Woodfibre LNG Limited Response to SIGTTO LNG Ports and Risk Reduction Options

Woodfibre LNG Limited Response to SIGTTO LNG Ports and Risk Reduction Options Woodfibre LNG Limited Response to SIGTTO LNG Ports and Risk Reduction Options Introduction: The following is in response to the Environmental Assessment Office request for the Society of International

More information

VALLIAMMAI ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK

VALLIAMMAI ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK VALLIAMMAI ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE 6604 - RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK UNIT 1 RAILWAY PLANNING 1. Define Permanent way. 2. List out the elements

More information

Fortnightly Water Quality Report

Fortnightly Water Quality Report 0 Fortnightly Water Quality Report Ichthys Nearshore Environmental Monitoring Program Weeks 85/86: April 2014 to 20 April 2014 Weeks 85/86: 7 April 2014 to 20 April 2014 Prepared for INPEX October 2014

More information

THE TRANSFER OF LNG IN OFFSHORE CONDITIONS. SAME SONG NEW SOUND

THE TRANSFER OF LNG IN OFFSHORE CONDITIONS. SAME SONG NEW SOUND THE TRANSFER OF LNG IN OFFSHORE CONDITIONS. SAME SONG NEW SOUND Leendert Poldervaart Business Development Manager James Ellis Business Development Manager Single Buoy Moorings Gas Business Development

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT 1. Introduction 1. Identification of project and project proponent The Pahanbarri Sand Quarry area is located in the Tawa River at Village- Pahanbarri, Tehsil- Itarsi & District-

More information

B.C. TOWBOAT INDUSTRY CONFERENCE

B.C. TOWBOAT INDUSTRY CONFERENCE LN G T erm inals on C ana da s W est C oast Kitimat LNG LN G T erm inals on C ana da s W est C oast Presentation to 17 th B.C. TOWBOAT INDUSTRY CONFERENCE Whistler, BC Kitimat LNG Alfred Sorensen Kitimat

More information

V: PROJECT SCOPING & METHODOLOGY

V: PROJECT SCOPING & METHODOLOGY V: PROJECT SCOPING & METHODOLOGY 5.0 INTRODUCTION The scoping exercise is carried out to define the focus and scope of the EIA Study. The scoping exercise is required to understand the type of activities

More information

Green FSRU for the future

Green FSRU for the future Green FSRU for the future Presentation at GREEN4SEA Athens April 6 th 2016 Dr. John Kokarakis Vice President Technology & Business Development, Africa, S. Europe Hellenic, Black Sea & Middle East Zone

More information

ECO-FRIENDLY LNG SRV: COMPLETION OF THE REGAS TRIAL

ECO-FRIENDLY LNG SRV: COMPLETION OF THE REGAS TRIAL International Gas Union Research Conference 2011 ECO-FRIENDLY LNG SRV: COMPLETION OF THE REGAS TRIAL Youngchul.Eum Seunghyuk.Kim Kyoungmin.Doh MunKeun.Ha SAMSUNG HEAVY INDUSTRIES, Geoje-Si, Gyeongsangnam-do,

More information

LNG Terminal in Świnoujście. Mutual Joint Visit Workshop for Seveso Inspections 26 September 2017, Nicosia, Cyprus

LNG Terminal in Świnoujście. Mutual Joint Visit Workshop for Seveso Inspections 26 September 2017, Nicosia, Cyprus LNG Terminal in Świnoujście Mutual Joint Visit Workshop for Seveso Inspections 26 September 2017, Nicosia, Cyprus Contents 1. Polskie LNG COMPANY PRESENTATION 2. LNG supply chain 3. Key technical parameters

More information

Pre- Feasibility RepoRt

Pre- Feasibility RepoRt Pre- Feasibility RepoRt AREA- 59.28 ACRE (24.0 HA) FOR KEN RIVER SAND/MORRUM MINING AT BLOCK NO-09 KHAND NO-03 GATA NO-337 VILLAGE- KANWARA TEHSIL-BANDA, DISTRICT- BANDA(U.P) SHRI RAVINDRA NATH SINGH JULY

More information

Fortnightly Water Quality Report

Fortnightly Water Quality Report Fortnightly Water Quality Report Ichthys Nearshore Environmental Monitoring Program Weeks 66/67: 25 November 2013 to December 2013 Weeks 66/67: 25 November 2013 to 8 December 2013 Prepared for INPEX October

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. (Change in Technology) at Hindadih Village, Masturi Tehsil Bilaspur District, Chhattisgarh Submitted to

More information

Water Quality in Cleveland Bay. Frequently Asked Questions

Water Quality in Cleveland Bay. Frequently Asked Questions Water Quality in Cleveland Bay Frequently Asked Questions 1 NATURAL WATER QUALITY IN CLEVELAND BAY What is turbidity and how does it relate to water quality? Turbidity is caused by particles suspended

More information

Table 1.1: The Salient Features of the Project Proposed Quartz Mine Of M/s. Viswanadha Stone Crusher & 16 others

Table 1.1: The Salient Features of the Project Proposed Quartz Mine Of M/s. Viswanadha Stone Crusher & 16 others 1. EXECUTIVE SUMMARY 1.1 Introduction The Road Metal Quarries was granted in Guntur District, Andhra Pradesh has been allotted to M/s. Viswanadha Stone Crusher & 16 others by Assistant Director of Mines

More information

SHAPING THE NATURAL GAS MARKET OF CYPRUS

SHAPING THE NATURAL GAS MARKET OF CYPRUS NATURAL GAS PUBLIC COMPANY (DEFA) SHAPING THE NATURAL GAS MARKET OF CYPRUS Dr. Symeon Kassianides Chairman Natural Gas Public Company New York 11/29/2017 SHAPING THE NATURAL GAS MARKET OF CYPRUS 1. Current

More information

LNG Import Facility Infrastructure Options

LNG Import Facility Infrastructure Options LNG Import Facility Infrastructure Options Mangesh Patankar (Head of Business Development Galway Group) 28 th April 2016 www.galwaygroup.com Agenda Introduction to Galway Group Types of Regas terminals

More information

PERP Program LNG Receiving Terminals New Report Alert

PERP Program LNG Receiving Terminals New Report Alert PERP Program LNG Receiving Terminals New Report Alert February 2007 Nexant s ChemSystems Process Evaluation/Research Planning program has published a new report, LNG Receiving Terminals (05/06S12). To

More information

V International Seminar on Port Engineering, Concepción, Chile. Site Selection & Design of Marine Terminals

V International Seminar on Port Engineering, Concepción, Chile. Site Selection & Design of Marine Terminals V International Seminar on Port Engineering, Concepción, Chile Site Selection & Design of Marine Terminals by Dr C. Skipper 1, Captain Stephen Gyi 2 ABSTRACT This paper considers the site selection and

More information

FOR IMPROVING THE CAPACITY UTILIZATION OF OR-I & OR-II AT VISAKHAPATNAM PORT TRUST (VPT), ANDHRA PRADESH, INDIA.

FOR IMPROVING THE CAPACITY UTILIZATION OF OR-I & OR-II AT VISAKHAPATNAM PORT TRUST (VPT), ANDHRA PRADESH, INDIA. TECHNO-ECONOMIC FEASIBILITY REPORT (TEFR): FOR IMPROVING THE CAPACITY UTILIZATION OF OR-I & OR-II AT VISAKHAPATNAM PORT TRUST (VPT), ANDHRA PRADESH, INDIA. Final Draft Report AUG -2016, Rev No: 02 Client:

More information

The general design of a LNG-terminal. Background

The general design of a LNG-terminal. Background The general design of a LNG-terminal Project MAGALOG (Marin Gas Logistics) is a contribution to addressing port emission problems in Europe, with a special focus on the Baltic Sea, through the establishment

More information

Fortnightly Water Quality Report

Fortnightly Water Quality Report 0 Fortnightly Water Quality Report Ichthys Nearshore Environmental Monitoring Program Weeks 79/80: 24 February 2014 to March 2014 Weeks 79/80: 24 February 2014 to 9 March 2014 Prepared for INPEX October

More information

SAMSUNG Energy Plant: All-in-One Solution for Floating Power Plants with Gas-fired Combined Cycle Gas Turbines

SAMSUNG Energy Plant: All-in-One Solution for Floating Power Plants with Gas-fired Combined Cycle Gas Turbines SAMSUNG Energy Plant: All-in-One Solution for Floating Power Plants with Gas-fired Combined Cycle Gas Turbines Myung-Kwan Song, Yongseok Song, Jeong Oh Hwang, Changwoo Lee, and Wonkyu Lee 5 th April 2017

More information

Pre-Feasibility Report For

Pre-Feasibility Report For Pre-Feasibility Report For Proposed New Project for manufacturing of Intermediates of Agro Chemicals & Synthetic Organic Chemicals. By M/s. MANBRO POLYMERS LIMITED, Plot No. D-2/CH-275, INDUSTRIAL ESTATE,

More information

Fortnightly Water Quality Report

Fortnightly Water Quality Report Fortnightly Water Quality Report Ichthys Nearshore Environmental Monitoring Program Weeks 20/21: to 20 January 2013 Weeks 20/21: 7 to 20 January 2013 Prepared for INPEX June 2013 Fortnightly Water Quality

More information

HINDUJA NATIONAL POWER CORPORATION LIMITED. HNPCL, (2X520 MW). VIZAG Technical Enquiry Specification for PU Coated Pipe For Ash Water Recovery System

HINDUJA NATIONAL POWER CORPORATION LIMITED. HNPCL, (2X520 MW). VIZAG Technical Enquiry Specification for PU Coated Pipe For Ash Water Recovery System HNPCL, (2X520 MW). VIZAG THERMAL POWER PROJECT TECHNICAL ENQUIRY SPECIFICATION FOR MS ERW 45O NB POLYURETHANE COATED PIPE FOR ASH WATER RECOVERY SYSTEM Prepared By Checked by Approved by Ashok Kumar Ashok

More information

Poole Harbour Channel Deepening and Beneficial Use Review of Physical monitoring in Poole Bay Technical Note 1 WITHOUT PREJUDICE

Poole Harbour Channel Deepening and Beneficial Use Review of Physical monitoring in Poole Bay Technical Note 1 WITHOUT PREJUDICE 1. Introduction Poole Harbour Channel Deepening and Beneficial Use Review of Physical monitoring in Poole Bay Technical Note 1 WITHOUT PREJUDICE This technical note reviews the physical data that was collected

More information

Proposed Terms of reference for EIA studies ToR for EIA studies in respect of the isolated storages, which are involved in handling of hazardous

Proposed Terms of reference for EIA studies ToR for EIA studies in respect of the isolated storages, which are involved in handling of hazardous Proposed Terms of reference for EIA studies ToR for EIA studies in respect of the isolated storages, which are involved in handling of hazardous chemicals may include, but not limited to the following

More information

Amended Background Information Document

Amended Background Information Document 1 Amended Background Information Document Proposed construction of the Xaris Gas Fired Power Plant and Gas Supply Facility in Walvis Bay P u r p o s e o f t h i s d o c u m e n t : This is the second version

More information

M/s. LAKSHMANAN CEMENTS PVT LTD, Survey Number 69-3, 69-4, Pachanapalli Village, Chittoor Mandal and District, Andhra Pradesh

M/s. LAKSHMANAN CEMENTS PVT LTD, Survey Number 69-3, 69-4, Pachanapalli Village, Chittoor Mandal and District, Andhra Pradesh M/s. LAKSHMANAN CEMENTS PVT LTD, Survey Number 69-3, 69-4, Pachanapalli Village, Chittoor Mandal and District, Andhra Pradesh EXECUTIVE SUMMARY SUBMITTED BY M/s. Lakshmanan Cements Pvt Ltd No. 58-A, 25

More information

Distribution Restriction Statement Approved for public release; distribution is unlimited.

Distribution Restriction Statement Approved for public release; distribution is unlimited. CECW-EH-D Regulation No. 1110-2-1404 Department of the Army U.S. Army Corps of Engineers Washington, DC 20314-1000 Engineering and Design HYDRAULIC DESIGN OF DEEP-DRAFT NAVIGATION PROJECTS Distribution

More information

NAMPORT (NAMIBIAN PORTS AUTHORITY) N th ROAD PO Box 361 WALVIS BAY NAMIBIA

NAMPORT (NAMIBIAN PORTS AUTHORITY) N th ROAD PO Box 361 WALVIS BAY NAMIBIA NAMPORT (NAMIBIAN PORTS AUTHORITY) N 17 13 th ROAD PO Box 361 WALVIS BAY NAMIBIA Phone +264 64 208 210 Fax +264 64 208 242 E-mail: jerome@namport.com.na Web: www.namport.com Namport, a state-owned organisation,

More information

PRE-FEASIBILITY REPORT FOR REVISED MASTER PLAN OF DHAMRA PORT

PRE-FEASIBILITY REPORT FOR REVISED MASTER PLAN OF DHAMRA PORT 4500 2016 PRE-FEASIBILITY REPORT FOR REVISED MASTER PLAN OF DHAMRA PORT January 2016 CLIENT Dharma Port Company Ltd. PROJECT Dhamra Master Plan TITLE Pre-feasibility Report On Revised Master Plan for Dhamra

More information

Pre-Feasibility Report [Application submitted for obtaining Terms of Reference for Prior Environment Clearance]

Pre-Feasibility Report [Application submitted for obtaining Terms of Reference for Prior Environment Clearance] Pre-Feasibility Report [Application submitted for obtaining Terms of Reference for Prior Environment Clearance] Project Proposal: Expansion of Cement Plant capacity from 1.5 to 2.20 MTPA of Clinker and

More information

Proposed Project of Halcyon Labs Pvt Ltd D-2/CH : 335,336,337, GIDC-Dahej-2, DIst: Bharuch, Gujarat Ramans Enviro Services Pvt Ltd Ahmedabad

Proposed Project of Halcyon Labs Pvt Ltd D-2/CH : 335,336,337, GIDC-Dahej-2, DIst: Bharuch, Gujarat Ramans Enviro Services Pvt Ltd Ahmedabad 1. EXECUTIVE SUMMARY OF THE PROJECT BRIEF SUMMARY OF THE PROJECT : TYPE OF PROJECT : Proposed Project for manufacturing of pharma intermediates by Halcyon Labs Pvt.Ltd. LOCATION : Proposed Project of Halcyon

More information

PART 3 TERMINAL INFORMATION

PART 3 TERMINAL INFORMATION International Safety Guide Part 3 Terminal information PART 3 TERMINAL INFORMATION Edition 1-2010 CCNR/OCIMF 2010 Page 235 International Safety Guide Part 3 Terminal information Edition 1-2010 CCNR/OCIMF

More information

SITING STUDY FOR THE GRASSY POINT LNG TRANSSHIPMENT AND STORAGE TERMINAL

SITING STUDY FOR THE GRASSY POINT LNG TRANSSHIPMENT AND STORAGE TERMINAL SITING STUDY FOR THE GRASSY POINT LNG TRANSSHIPMENT AND STORAGE TERMINAL Prepared For Newfoundland LNG LTD. Suite 302, Baine Johnston Centre 10 Fort William Place St. John's, NL Canada A1C 1K4 Prepared

More information

CHAPTER 135 MAJOR RECLAMATION SCHEME FOR MARINA CITY, SINGAPORE

CHAPTER 135 MAJOR RECLAMATION SCHEME FOR MARINA CITY, SINGAPORE CHAPTER 135 MAJOR RECLAMATION SCHEME FOR MARINA CITY, SINGAPORE S.Y. CHEW Manager, Building and Development Division, Housing and Development Board, Singapore and J. WEI Principal Civil Engineer, Building

More information

ENVIRONMENTAL IMPACT ASSESSMENT (BASIC ASSESSMENT) PROCESS: PROPOSED REVERSE OSMOSIS PLANT, IRON ORE HANDLING FACILITY, PORT OF SALDANHA

ENVIRONMENTAL IMPACT ASSESSMENT (BASIC ASSESSMENT) PROCESS: PROPOSED REVERSE OSMOSIS PLANT, IRON ORE HANDLING FACILITY, PORT OF SALDANHA ENVIRONMENTAL IMPACT ASSESSMENT (BASIC ASSESSMENT) PROCESS: PROPOSED REVERSE OSMOSIS PLANT, IRON ORE HANDLING FACILITY, PORT OF SALDANHA BACKGROUND INFORMATION DOCUMENT SRK Project 364470/42G June 2007

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT M/S. VANAS INFRA PROJECTS PVT. LTD SURVEY NO. 598, CHINTALAPALLY VILLAGE, KOLLAPUR MANDAL, NAGARKURNOOL DISTRICT, TELANGANA PRE-FEASIBILITY REPORT SUBMITTED BY M/s. Sri Soma Jitendra H. No. 7-1-397/150,

More information

Environment Consultant:

Environment Consultant: MODERNIZATION CUM EXPANSION OF INDUCTION FURNACE PRODUCTION(2,05,000 TPA TO 6,00,000 TPA) AND ROLLING MILL PRODUCTION (3, 69,000 TPA TO 6,00,000 TPA) at Sy. No. 158 (part) 159 (part), 166 170, village

More information

FOR. Mer (MOST) (E.I.A)

FOR. Mer (MOST) (E.I.A) PROPOSED OIL FARM of 250000 MT CAPACITY AT MER ROUGE Mer FOR Rouge Oil Storage Terminal (MOST) ENVIRONMENTAL IMPACT ASSESSMENT REPORT (E.I.A) December 2014 TABLE OF CONTENTS Title Page (i) Table of Contents

More information

Wharf structures and Quay Deck landing areas, will be built in stages to accommodate the following transport fleet:

Wharf structures and Quay Deck landing areas, will be built in stages to accommodate the following transport fleet: 8C Noise Design Assumptions and Source Data 8C.1 Construction Predicted noise levels at the nearest noise sensitive receptors from construction activities have been modelled and presented as noise contours,

More information

BS 6349:Part 1.1: 1: General Code of practice for planning and design for operations. David Veale

BS 6349:Part 1.1: 1: General Code of practice for planning and design for operations. David Veale : 1: Principal Technical Expert for Marine Facilities Engineering Shell Projects and Technology OCIMF Representative on CB502 OCIMF The Oil Companies OCIMF mission is to be the International Marine Forum

More information

Dheeru Powergen Private Limited.

Dheeru Powergen Private Limited. Executive Summary Of The Proposed 2 x 300 MW Dhanras Thermal Power Station At Dhanras Village Katgora Taluk, Korba District, Chhattisgarh. Implemented By Dheeru Powergen Private Limited. Submitted to CHHATTISGARH

More information

Pre-Feasibility Report. for. Mangaluru Integrated Gas Project

Pre-Feasibility Report. for. Mangaluru Integrated Gas Project Pre-Feasibility Report for Mangaluru Integrated Gas Project Submitted to: Submitted by: Ministry of Environment, Forests, and Climate Change (MoEF&CC) H-Energy Private Limited March, 2018 Table of Contents

More information

PREFEASIBILITY PROJECT REPORT (PPR) INSTALLATION OF LNG STORAGE AND REGASIFICATION FACILITY SEPTEMBER 2016

PREFEASIBILITY PROJECT REPORT (PPR) INSTALLATION OF LNG STORAGE AND REGASIFICATION FACILITY SEPTEMBER 2016 PREFEASIBILITY PROJECT REPORT (PPR) ON INSTALLATION OF LNG STORAGE AND REGASIFICATION FACILITY SEPTEMBER 2016 MANGALORE CHEMICALS & FERTILIZERS LIMITED PANAMBUR, MANGALORE 575 010. Page 1 of 6 Index Sl.

More information

PREFEASIBILITY REPORT FOR BRICK EARTH MINE

PREFEASIBILITY REPORT FOR BRICK EARTH MINE Page 1 PREFEASIBILITY REPORT FOR BRICK EARTH MINE Developed By- Village-Chandauhan, Tehsil-Phulpur, District-Allhabaad, Uttar Pradesh. RAI ENVIROMENTAL SERVICES PVT. LTD. Website: www.raienviro.com Email

More information

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA 1.0 INTRODUCTION M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA dry type of coal washery at Village: Hindadih, Tehsil: Masturi, District: Bilaspur (C.G.) for which

More information

2. TECHNICAL DESCRIPTION OF THE PROJECT

2. TECHNICAL DESCRIPTION OF THE PROJECT 2. TECHNICAL DESCRIPTION OF THE PROJECT 2.1. What is a Combined Cycle Gas Turbine (CCGT) Plant? A CCGT power plant uses a cycle configuration of gas turbines, heat recovery steam generators (HRSGs) and

More information

LNG TERMINALLING PROGRAMME.

LNG TERMINALLING PROGRAMME. LNG TERMINALLING PROGRAMME Based on Article 203 of the Royal Decree of 23 December 2010 on the Code of Conduct regarding access to natural gas transmission networks www.fluxys.com TABLE OF CONTENTS TABLE

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. 0.96 MTPA Wet type Coal Washery at Birgahani Village, Baloda Tehsil Janjgir-Champa District, Chhattisgarh

More information

Pre-Feasibility Report for Construction of Additional Tankage at POL Terminal Partapur, Meerut, M/s IOCL PRE-FEASIBILITY REPORT

Pre-Feasibility Report for Construction of Additional Tankage at POL Terminal Partapur, Meerut, M/s IOCL PRE-FEASIBILITY REPORT PREAMBLE Pre-Feasibility Report for Construction of Additional PRE-FEASIBILITY REPORT Indian Oil Corporation Limited (IOCL) is India's largest commercial enterprise, with a sales turnover of Rs. 4,38,710

More information

UNIT 1 QUESTION BANK. Part A

UNIT 1 QUESTION BANK. Part A QUESTION BANK UNIT 1 Part A 1. Why is railway track termed as permanent way? 2. What is coning of wheels? What is its purpose? 3. Define Creep of rail and mention its causes. 4. Distinguish between double

More information

Innovations for the Global LNG Industry Bringing Continents of Energy Together Marine Technology Society March 22, 2007

Innovations for the Global LNG Industry Bringing Continents of Energy Together Marine Technology Society March 22, 2007 Innovations for the Global LNG Industry Bringing Continents of Energy Together Marine Technology Society March 22, 2007 Kathleen Eisbrenner President and Chief Executive Officer Excelerate Energy Excelerate

More information

Natural Gas. and the Liquefaction Process

Natural Gas. and the Liquefaction Process Natural Gas and the Liquefaction Process Table of Contents Cameron LNG.................... 2 Liquefied Natural Gas................ 4 LNG Safety...................... 5 Environmental Safety................

More information

Bharat Heavy Electricals Limited Heavy Plates & Vessels Plant, Visakhapatnam Andhra Pradesh.

Bharat Heavy Electricals Limited Heavy Plates & Vessels Plant, Visakhapatnam Andhra Pradesh. Subject: Expression of Interest for Providing Techno-Commercial Data concerning Cryogenic s executed in the past or under execution in India. 1) INTRODUCTION This Expression of Interest (EoI) seeks response

More information

Domestic seaborne distribution systems in Asia

Domestic seaborne distribution systems in Asia Domestic seaborne distribution systems in Asia Ad Ligthart Cement Distribution Consultants 26 June 2013 Contents of presentation Introduction Overview of Asian cement and clinker trade and domestic distribution

More information

AT A GLANCE. Cairns Shipping Development Project. Revised Draft Environmental Impact Statement Fact Sheet July 2017.

AT A GLANCE. Cairns Shipping Development Project. Revised Draft Environmental Impact Statement Fact Sheet July 2017. Cairns Shipping Development Project Revised Draft Environmental Impact Statement Fact Sheet July 2017 AT A GLANCE > An additional 70 cruise ships into Port of Cairns each year by 2031 > Project design

More information

Mangaluru Integrated Gas Project

Mangaluru Integrated Gas Project Mangaluru Integrated Gas Project Proposed Terms of Regerence (ToR) submitted with Form I to Ministry of Environment, Forests & Climate Change (MoEF&CC) I. Objectives of EIA Studies The overall objectives

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project of MANUFACTURING OF SYNTHETIC ORGANIC DYES (5 f B IND II) By SHREEJI BAPA DYE CHEM PLOT NO 1319 & 1320, PHASE-III, GIDC, VATVA, AHEMADABAD-382445, GUJARAT,

More information

ELIGIBILITY CRITERIA FOR QUALIFICATION OF EPC CONTRACTORS FOR LNG TERMINAL AT GANGAVARAM, VISAKHAPATNAM, ANDHRA PRADESH (INDIA)

ELIGIBILITY CRITERIA FOR QUALIFICATION OF EPC CONTRACTORS FOR LNG TERMINAL AT GANGAVARAM, VISAKHAPATNAM, ANDHRA PRADESH (INDIA) ELIGIBILITY CRITERIA FOR QUALIFICATION OF EPC CONTRACTORS FOR LNG TERMINAL AT GANGAVARAM, VISAKHAPATNAM, ANDHRA PRADESH (INDIA) Petronet LNG Limited intends to undertake International Competitive Bidding

More information

Background Information Document

Background Information Document Background Information Document Independent Power Producer Programme: EIA for a Floating Power Plant and EIA for LNG Import Facilities, Port of Saldanha: ERM Ref Number: 0320754 Purpose of this Background

More information

LG POLYMERS INDIA PVT. LTD. SY. NO.S 29 TO 45, 83/1 AND 83/3, RR VENKATAPURAM VILLAGE, PENDURTI MANDAL, VISAKHAPATNAM DISTRICT, ANDHRA PRADESH

LG POLYMERS INDIA PVT. LTD. SY. NO.S 29 TO 45, 83/1 AND 83/3, RR VENKATAPURAM VILLAGE, PENDURTI MANDAL, VISAKHAPATNAM DISTRICT, ANDHRA PRADESH LG POLYMERS INDIA PVT. LTD. SY. NO.S 29 TO 45, 83/1 AND 83/3, RR VENKATAPURAM VILLAGE, PENDURTI MANDAL, VISAKHAPATNAM DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT LG Polymers India Pvt. Ltd. Sy. No.s

More information

Terminal Particulars Questionnaire

Terminal Particulars Questionnaire Terminal Particulars Questionnaire Terminal Port Port authority Last updated Terminal General Date this TPQ document was completed/updated Specify units used Port Details Port Name UN LOCODE 3. Country

More information

INTEGRATION OF A NEW CCGT PLANT AND AN EXISTING LNG TERMINAL AT BARCELONA PORT Abstract ID Number: 155

INTEGRATION OF A NEW CCGT PLANT AND AN EXISTING LNG TERMINAL AT BARCELONA PORT Abstract ID Number: 155 INTEGRATION OF A NEW CCGT PLANT AND AN EXISTING LNG TERMINAL AT BARCELONA PORT Abstract ID Number: 155 Authors: Rafael Peiró Ripoll, Foster Wheeler Iberia, S.A., Spain Joaquín Gil Abad, Foster Wheeler

More information

Connecting. markets. you to key

Connecting. markets. you to key Essar Ports Ltd. Essar House, Keshavrao Khadye Marg Mahalaxmi Mumbai - 400 034 Maharashtra, India Telephone: (+9 22) - 50000 / 666000 Fax: (+9 22) - 6660809 Email: eptlbdm@essar.com www.essarports.com

More information

MODIFIED QUARRYING PLAN FOR "SHINGATALOOR SAND MINING BLOCK-2" EXTENT Acres (4.86 Ha) IN TUNGABHADRA RIVER BED ADJ ACENT TO SY.

MODIFIED QUARRYING PLAN FOR SHINGATALOOR SAND MINING BLOCK-2 EXTENT Acres (4.86 Ha) IN TUNGABHADRA RIVER BED ADJ ACENT TO SY. MODIFIED QUARRYING PLAN FOR "SHINGATALOOR SAND MINING BLOCK-2" EXTENT -12.00 Acres (4.86 Ha) IN TUNGABHADRA RIVER BED ADJ ACENT TO SY.NO - 129 & 131OF SHINGATALOOR - VILLAGE MUNDARGI - TALUK GADAG - DISTRICT

More information

Estimation of Boil-off-Gas BOG from Refrigerated Vessels in Liquefied Natural Gas Plant

Estimation of Boil-off-Gas BOG from Refrigerated Vessels in Liquefied Natural Gas Plant International Journal of Engineering and Technology Volume 3 No. 1, January, 2013 Estimation of Boil-off-Gas BOG from Refrigerated Vessels in Liquefied Natural Gas Plant Wordu, A. A, Peterside, B Department

More information

Development of Efficient, Environmentally Friendly and Flexible Shipboard Regasification Vessel

Development of Efficient, Environmentally Friendly and Flexible Shipboard Regasification Vessel 13 Development of Efficient, Environmentally Friendly and Flexible Shipboard Regasification Vessel KENJI TSUMURA *1 MASARU OKA *1 TOSHIO OGATA *2 MAKOTO TABIRA *2 Mitsubishi Heavy Industries, Ltd., (MHI)

More information

ANNEXURE. Annexure 1: Production Details. Annexure 2: Site Location Map. Annexure 3: Site Layout Map & Area breakup for Terminal

ANNEXURE. Annexure 1: Production Details. Annexure 2: Site Location Map. Annexure 3: Site Layout Map & Area breakup for Terminal ANNEXURE Annexure 1: Production Details Annexure 2: Site Location Map Annexure 3: Site Layout Map & Area breakup for Terminal Annexure 4: Operation Philosophy Annexure 5: Copy of Consent to Operate Annexure

More information

Small Scale LNG From Concept to Reality. Chris Johnson, General Manager, LNG New Markets, Shell

Small Scale LNG From Concept to Reality. Chris Johnson, General Manager, LNG New Markets, Shell Small Scale LNG From Concept to Reality Chris Johnson, General Manager, LNG New Markets, Shell 0 Table of Contents Table of Contents... 1 Background... 1 Aims... 4 Methods... 5 Results... 11 Conclusions...

More information

Cook Inlet Navigation Channel

Cook Inlet Navigation Channel Cook Inlet Navigation Channel Cook Inlet Navigation Channel Page 2 of 9 Condition of Improvements 31 December 2017 Cook Inlet Navigation Channel, Alaska (CWIS No. 010324, 010534) Authorization (1) Water

More information

OUTLINE OF MIZUSHIMA LNG RECEIVING TERMINAL AND MAIN CHARACTERISTIC OF EQUIPMENT COST REDUCTION

OUTLINE OF MIZUSHIMA LNG RECEIVING TERMINAL AND MAIN CHARACTERISTIC OF EQUIPMENT COST REDUCTION OUTLINE OF MIZUSHIMA LNG RECEIVING TERMINAL AND MAIN CHARACTERISC OF EQUIPMENT COST REDUCON Kenichi Tadano Senior Engineer Yoshifumi Numata Engineering Manager Daisuke Wada Engineer Chiyoda Corporation

More information

Background Information Document

Background Information Document Background Information Document Independent Power Producer Programme: EIA for a Floating Power Plant and EIA for LNG Import Facilities, Port of Richards Bay: ERM Ref Number: 0320839 Purpose of this Background

More information

Freeport LNG Liquefaction Project

Freeport LNG Liquefaction Project 17 th INTERNATIONAL CONFERENCE & EXHIBITION ON 17LIQUEFIED th INTERNATIONAL NATURAL CONFERENCE GAS (LNG & EXHIBITION 17) ON LIQUEFIED NATURAL GAS (LNG 17) Freeport LNG Liquefaction Project

More information

S. No Parameter Details 1 Name & Address of the Applicant

S. No Parameter Details 1 Name & Address of the Applicant 1. EXECUTIVE SUMMARY S. No Parameter Details 1 Name & Address of the Applicant M/s AMULYA GRANITES Prop: Smt CH.SARALA H. No. FLAT NO.207 Roja Kishore Residency, Chenchupet, Tenali, AP-522 202 Guntur District,

More information

FORM-1 AND PRE-FEASIBILITY REPORTs

FORM-1 AND PRE-FEASIBILITY REPORTs FORM-1 AND PRE-FEASIBILITY REPORTs Development of Integrated Facilities (stage-ii) within the Existing Kandla Port Trust Limit at Kutch District of Gujarat: 1. Setting up of Barge Port at Veera; 2. Setting

More information

PRE-FEASIBILTY REPORT

PRE-FEASIBILTY REPORT Aug 2018 PRE-FEASIBILTY REPORT OF M/S. J.M.R.MINES (MINING OF FELDSPAR, QUARTZ & MICA MINE) Lease Area : 5.78 Hectares(14.29 Acres) Sy.No.941,942,943 &947 Giddalur (V), Sydapuram (M), SPSR Nellore District

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT VENSUB LABORATORIES PRIVATE LIMITED SY. NO. 29, TUPAKULAGUDEM VILLAGE, TALLAPUDI MANDAL, WEST GODAVARI DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT VENSUB LABORATORIES PRIVATE LIMITED Duplex No. 12,

More information

COMPLETING THE LNG VALUE CHAIN

COMPLETING THE LNG VALUE CHAIN COMPLETING THE LNG VALUE CHAIN Reidar Strande, Director, LNG, Wärtsilä Oil & Gas Systems Tord Johnsson, Area Business Development Manager, Oil and Gas Business, Wärtsilä Power Plants [ ENERGY & MARINE

More information

COMPLIANCE TO THE CONDITIONS LAID BY MoEF VIDE CRZ CLEARANCE No.11/32/2009-IA.III dated

COMPLIANCE TO THE CONDITIONS LAID BY MoEF VIDE CRZ CLEARANCE No.11/32/2009-IA.III dated COMPLIANCE TO THE CONDITIONS LAID BY MoEF VIDE CRZ CLEARANCE No.11/32/2009-IA.III dated 10.08.2009 Period : January 2018 to June 2018 Sl.No. CONDITIONS STIPULATED BY MoEF COMPLIENCE Specific Conditions

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project of MANUFACTURING OF SYNTHETIC ORGANICCHEMICALS (RESINS) (5 f B IND II) By M/s M R INDUSTRIES SURVEY NO. 58/1 & 58/3 OPPOSITE WHOLESOME FOOD PVT. LTD.,

More information

4 th Annual LNG Transport, Handling and Storage Conference May By Akkapon Pinkaew NGV Business and Product Development Manager

4 th Annual LNG Transport, Handling and Storage Conference May By Akkapon Pinkaew NGV Business and Product Development Manager 4 th Annual LNG Transport, Handling and Storage Conference 19-21 May 2014 By Akkapon Pinkaew NGV Business and Product Development Manager Topics Overview PTT Natural Gas Business Thailand Energy Consumption

More information

Environmental and Social Impact Assessment [ESIA] for Proposed Liquefied Natural Gas (LNG) Project at Tema in the Greater Accra Region of Ghana

Environmental and Social Impact Assessment [ESIA] for Proposed Liquefied Natural Gas (LNG) Project at Tema in the Greater Accra Region of Ghana BACKGROUND INFORMATION DOCUMENT QUANTUM POWER OPERATIONS LIMITED Environmental and Social Impact Assessment [ESIA] for Proposed Liquefied Natural Gas (LNG) Project at Tema in the Greater Accra Region of

More information