1 Turbine Northwest Energy Workshop August 3rd, 2006 University of Minnesota Crookston Mark Lindquist The Minnesota Project

2 The Model Ordinance Project Collaboration of: The Minnesota Project Minnesota Association of County Planning and Administrators Southwest Regional Development Commission Three Rivers RC&D Developing Two Products: Model Ordinance Supporting document that outlines the basis the ordinance language

3 Project Process Small work group appointed by MACPZA, District D did the research and drafting. Work group has contacted various stakeholders input Documents were submitted to and approved by MACPZA Documents are posted on and MACPZA web sites.

4 Why do a model ordinance? Several CERTS teams identified zoning as an issue or barrier clean energy County staff in in SW were interested in updating their ordinances The Minnesota Project staff background

5 Who Regulates Turbines? Under 5 MW Local government usually a county Over 5 MW MN Public Utilities Commission / Dept of Commerce North Dakota 100 MW threshold state permitting

6 Who Regulates Turbines? What about Aggregated Projects where each wind turbine is owned by a separate individual or partnership? The Law is absolutely clear! The problem is that the clear law is being read differently by different parties. State reading of law and rules is that aggregated projects over 5 MW are under state jurisdiction. Some wind developers read the law to authorize local government to permit any legal structure under 5 MW.

7 Local Authority and Purpose Counties, Cities, and Townships are enabled to regulate land use under Minnesota Statutes 394 and 462 the purpose of: promoting the health, safety, morals, and general welfare of the community Local Governments powers are broad and substantial subject to due process constraints

8 Why is Important Commercial turbines are a significant expanding land use in rural Minnesota. Good ordinances are needed: To facilitate development. To ensure that ill-considered projects do not harm the public. To ensure that ill-considered projects do not harm public support wind development. Model Ordinance on-line at:

9 If wind is good, what s the problem? There are needs to address various issues. Compatibility with surrounding land use. Public safety Visual Impact Noise Impacts to public services Other Nuisance

10 Summary of Standards Distinguish between Commercial and Non-Commercial 40 kw or 100 kw Threshold

11 Summary of Standards = keeping non-compatible land uses apart. Early 20 th Century response to industrialization. Two approaches: 1) Determine if these are permitted, conditionally permitted or not permitted in each existing land use district. 2) Look hard at the county and create an overlay district where turbines are acceptable.

12 Summary of Standards Commercial Conditionally Permitted Ag Industrial Not Permitted Rural Residential General Business Conservation like Shoreland, Wild and Scenic River etc Urban Expansion Non-Commercial Permitted Ag. Industrial Conditionally Permitted Rural Residential Highway Commercial Shoreland Urban Expansion Not permitted General Business Rural Town Site

13 Summary of Standards Setbacks - Commercial Homes 750 feet Property Lines X total height Road Rights of Way 1 X total height Other ROWs to be considered Conservation Lands 600 feet Certain wetlands 600 feet Setbacks Non-Commercial Property Lines 1.1 X total height Road ROWs 1 X total height or fall zone + 10

14 Summary of Standards Setbacks primary tool public safety and nuisance Catastrophic Failure If they fall down or a blade comes off it won t land on a house or road. Nuisance Visual impact including shadow flicker Bluff top setbacks Noise attenuation TV Reception Impact on adjacent property wind resource

15 Summary of Standards 5 RD Setback 1.65 MW turbine requires ¼ section. 11 parcels 6 cannot meet setbacks.

16 Summary of Standards Safety Standards Engineers Certification Minimum ground clearance Markings on Guy Wires Met tower painting Primary protection public safety is setbacks

17 Summary of Standards Design Standards Tubular towers commercial Turbines White, grey or non-obtrusive color Lighting limited to FAA requirement Signage limited Power lines up to 35 kv buried Substation comply with essential services ordinance

18 Summary of Standards Other Standards Decommissioning and abandonment Plan in the application Abandon after 1 year 90 days to remove Comply with FAA regulations, electrical code and state noise rule Noise - MN Rule = 50 decibels at a farm house.

19 Summary of Standards Infrastructure Impacts Minimize or mitigate interference with telecommunications Microwaves a major concern Military Radar Not a local issue Road Damage mitigation Drainage system mitigation

20 Other Ordinance Language Definitions Procedures Interpretation and severability clauses Encement

21 Bird and Bats There is no free lunch. Direct mortality Habitat impacts The Altamont Pass - Birds Bad siting leads to bad outcomes Wooded Eastern Ridge Tops - Bats Bad siting leads to bad outcomes Bat Study on BR found about 2 bats killed per turbine per year.

22 Birds and Bats Grassland Birds and Habitat use: Generally, grassland birds don t like to be near tall stuff. turbines are tall. Reduced nesting impacts DNR recommendation 600 foot setback.

23 Birds and Bats MCBS Native Plant Communities

24 is good!

Commercial WECS: A WECS of equal to or greater than [100/40] kw in name plate generating capacity. Wind Energy Conversion System Ordinance

Commercial WECS: A WECS of equal to or greater than [100/40] kw in name plate generating capacity. Wind Energy Conversion System Ordinance Interest and development of wind energy has increased in Minnesota, both in the volume and geographically. During the 1990 s, several counties adopted wind ordinances to address local wind development.

More information

ORDINANCE NO. Commercial WECS: A WECS of equal to or greater than 15 kw in total name plate generating capacity.

ORDINANCE NO. Commercial WECS: A WECS of equal to or greater than 15 kw in total name plate generating capacity. ORDINANCE NO. AN ORDINANCE AMENDING ORDINANCE NO. 1060 KNOWN AS THE WILLMAR ZONING ORDINANCE BY ADDING SECTION 11 RELATING TO WIND ENERGY CONVERSION SYSTEMS (WECS) The City of Willmar does ordain as follows:

More information

MINNESOTA LOCAL GOVERNMENT WIND TOOLKIT

MINNESOTA LOCAL GOVERNMENT WIND TOOLKIT MINNESOTA LOCAL GOVERNMENT WIND TOOLKIT Prepared for the Minnesota Department of Commerce, by the Great Plains Institute July 2017 INTRODUCTION Wind energy is now the least expensive way to generate electricity,

More information

SECTION 25: WIND ENERGY CONVERSION SYSTEMS (WECS)

SECTION 25: WIND ENERGY CONVERSION SYSTEMS (WECS) SECTION 25: WIND ENERGY CONVERSION SYSTEMS (WECS) This Ordinance is established to regulate the installation and operation of Wind Energy Conversion Systems (WECS) within Cottonwood County not otherwise

More information

INTRODUCTION. Understand Your Goals. Large WECS, Small WECS. Model Wind Energy Standards. Model Wind Energy Ordinance

INTRODUCTION. Understand Your Goals. Large WECS, Small WECS. Model Wind Energy Standards. Model Wind Energy Ordinance INTRODUCTION The growth in the number of wind energy conversion systems (WECS) in Minnesota over the last 15 years is a remarkable measurement of sustainability. Wind energy has no harmful emissions, reduces

More information

MURRAY COUNTY WIND ENERGY ORDINANCE

MURRAY COUNTY WIND ENERGY ORDINANCE MURRAY COUNTY WIND ENERGY ORDINANCE SECTION 1 TITLE The title of this ordinance is the, and will be referred to herein as this Ordinance. SECTION 2 PURPOSE This ordinance is established to set forth processes

More information

ARTICLE 16 - WIND ENERGY CONVERSION FACILITIES

ARTICLE 16 - WIND ENERGY CONVERSION FACILITIES ARTICLE 16 - WIND ENERGY CONVERSION FACILITIES SECTION 1601 Wind Energy Installation In any zoning district, a conditional use permit or building permit may be granted to allow a wind energy conversion

More information

Humboldt County Ordinance #68 Commercial/Utility Grade Wind Energy Conversion Systems (WECS) PURPOSE DEFINITIONS

Humboldt County Ordinance #68 Commercial/Utility Grade Wind Energy Conversion Systems (WECS) PURPOSE DEFINITIONS Humboldt County Ordinance #68 Commercial/Utility Grade Wind Energy Conversion Systems (WECS) PURPOSE The purpose of this Ordinance is to provide an orderly process for regulating the development and operation

More information

SECTION SPECIAL REQUIREMENTS FOR WIND ENERGY CONVERSION SYSTEM

SECTION SPECIAL REQUIREMENTS FOR WIND ENERGY CONVERSION SYSTEM SECTION 14-18.5 SPECIAL REQUIREMENTS FOR WIND ENERGY CONVERSION SYSTEM Purpose The purpose of this section is to set forth a process for permitting wind energy facilities with a rated capacity of 100 kw

More information

Nance County Zoning Regulations for Wind Energy Conversion Systems

Nance County Zoning Regulations for Wind Energy Conversion Systems Nance County Zoning Regulations for Wind Energy Conversion Systems ARTICLE 1: SMALL / NON-COMMERCIAL WIND ENERGY SYSTEMS Section 1. Purpose It is the purpose of this regulation to promote safe, effective

More information

Zoning Regulations for Large and Small Wind that are Working

Zoning Regulations for Large and Small Wind that are Working Zoning Regulations for Large and Small Wind that are Working Highlights of City and County Regulations Nebraska Wind Power 2009 Conference Kearney, Nebraska November 9, 2009 Oii Origination in Nebraska

More information

Minnesota State Permitting Process for Large Wind Energy Conversion Systems

Minnesota State Permitting Process for Large Wind Energy Conversion Systems Minnesota State Permitting Process for Large Wind Energy Conversion Systems Deborah Pile, supervisor Energy Facility Permitting Office of Energy Security Minnesota Department of Commerce Minnesota Energy

More information

CARLTON COUNTY RENEWABLE ENERGY ORDINANCE #32

CARLTON COUNTY RENEWABLE ENERGY ORDINANCE #32 CARLTON COUNTY RENEWABLE ENERGY ORDINANCE #32 Adopted: December 1, 2017 Carlton County Renewable Energy Ordinance # 32 Table of Contents ARTICLE 1. TITLE, AUTHORITY, PURPOSE, SCOPE AND SEVERABILITY...

More information

Wind Energy Conversion System Ordinance of Otter Tail County Effective February 15, 2011

Wind Energy Conversion System Ordinance of Otter Tail County Effective February 15, 2011 Wind Energy Conversion System Ordinance of Otter Tail County TABLE OF CONTENTS Page I. GENERAL PROVISIONS... 2 1. Title... 2 2. Purpose... 2 3. Statutory Authorization... 2 4. Legal Authority/Jurisdiction...

More information

WIND ENERGY CONVERSION SYSTEMS

WIND ENERGY CONVERSION SYSTEMS CHAPTER 159 WIND ENERGY CONVERSION SYSTEMS 159.01 Purpose and Intent 159.05 Location 159.02 Definitions 159.06 Design and Technical Standards 159.03 General Regulations 159.07 Abandonment and Removal Procedure

More information

SECTION 12 WINDPOWER MANAGEMENT ADOPTED: FEBRUARY 15, 2005 TABLE OF CONTENTS SUBDIVISIONS... PAGE

SECTION 12 WINDPOWER MANAGEMENT ADOPTED: FEBRUARY 15, 2005 TABLE OF CONTENTS SUBDIVISIONS... PAGE Section 12, Page i SECTION 12 WINDPOWER MANAGEMENT ADOPTED: FEBRUARY 15, 2005 TABLE OF CONTENTS SUBDIVISIONS... PAGE 12.1. Subdivision 1 Purpose... 1 12.2. Subdivision 2 Definitions... 1 12.3. Subdivision

More information

Clustering: The grouping of wind turbines positioned or occurring closely together around a particular dwelling.

Clustering: The grouping of wind turbines positioned or occurring closely together around a particular dwelling. Section *.** Commercial/Utility Grade Wind Energy Systems PROPOSED BY CO BOARD 1-16-18 *.**.01Purpose: It is the purpose of this regulation to promote the safe, effective and efficient use of commercial/utility

More information

TOWNSHIP OF LOWER, COUNTY OF CAPE MAY, STATE OF NEW JERSEY ORDINANCE NO

TOWNSHIP OF LOWER, COUNTY OF CAPE MAY, STATE OF NEW JERSEY ORDINANCE NO TOWNSHIP OF LOWER, COUNTY OF CAPE MAY, STATE OF NEW JERSEY ORDINANCE NO. 2009-13 AN ORDINANCE REPLACING CHAPTER 400, SECTION 41 OF THE CODE OF THE TOWNSHIP OF LOWER TO UPDATE AND CLARIFY THE REPEALED STANDARDS

More information

Sample Zoning for Wind Energy Systems April 16, 2008

Sample Zoning for Wind Energy Systems April 16, 2008 Sample Zoning for Wind Energy Systems April 16, 2008 Introduction These guidelines have been developed by the Energy Office, Michigan Dept. of Labor and Economic Growth (DLEG) to assist local governments

More information

Minnesota Energy Facility Permitting

Minnesota Energy Facility Permitting Minnesota Energy Facility Permitting Large Wind Energy Conversion Systems Large Electric Power Generating Plants High Voltage Transmission Lines Pipelines Wind Development In Minnesota 1,299 MW in Minnesota.

More information

SANTA BARBARA COUNTY PLANNING COMMISSION Small Wind Energy Systems Ordinance Amendment

SANTA BARBARA COUNTY PLANNING COMMISSION Small Wind Energy Systems Ordinance Amendment SANTA BARBARA COUNTY PLANNING COMMISSION Small Wind Energy Systems Ordinance Amendment Hearing Date: November 10, 2010 Development Services Director: Dianne Black Staff Report Date: November 1, 2010 Staff

More information

ORDINANCE NO. VI-III A WIND ENERGY DEVICE ORDINANCE EMMET COUNTY, IOWA AN ORDINANCE ADDRESSING STANDARDS, CONDITIONS, APPLICATION, REVIEW AND

ORDINANCE NO. VI-III A WIND ENERGY DEVICE ORDINANCE EMMET COUNTY, IOWA AN ORDINANCE ADDRESSING STANDARDS, CONDITIONS, APPLICATION, REVIEW AND ORDINANCE NO. VI-III A WIND ENERGY DEVICE ORDINANCE EMMET COUNTY, IOWA AN ORDINANCE ADDRESSING STANDARDS, CONDITIONS, APPLICATION, REVIEW AND APPROVAL FOR THE CONSTRUCTION AND MAINTENANCE OF WIND ENERGY

More information

EXCERPT FROM EMMET COUNTY ZONING ORDINANCE. A. Definitions For purposes of this section, the following definitions shall apply:

EXCERPT FROM EMMET COUNTY ZONING ORDINANCE. A. Definitions For purposes of this section, the following definitions shall apply: EXCERPT FROM EMMET COUNTY ZONING ORDINANCE SECTION 2102-16 WIND ENERGY SYSTEMS (WES S) 16. WIND ENERGY SYSTEMS (WES S) A. Definitions For purposes of this section, the following definitions shall apply:

More information

SECTION 25: RENEWABLE ENERGY ORDINANCE

SECTION 25: RENEWABLE ENERGY ORDINANCE SECTION 25: RENEWABLE ENERGY ORDINANCE This Ordinance is established to regulate the installation and operation of Renewable Energy Systems within Cottonwood County not otherwise subject to siting and

More information

3.0 UNAVOIDABLE ADVERSE IMPACTS. 3.1 General Mitigation Measures

3.0 UNAVOIDABLE ADVERSE IMPACTS. 3.1 General Mitigation Measures 3.0 UNAVOIDABLE ADVERSE IMPACTS The purpose of the Project is to create a reliable and profitable wind-powered electric generation facility that will provide a significant source of clean, renewable energy

More information

Article 57 WIND GENERATION AND WIRELESS COMMUNICATION TOWERS

Article 57 WIND GENERATION AND WIRELESS COMMUNICATION TOWERS Article 57 WIND GENERATION AND WIRELESS COMMUNICATION TOWERS SECTION 57.010, PURPOSE: The purpose of this article is to establish wind generation and wireless communication tower (Hereafter referred to

More information

WILSON TOWNSHIP ZONING ORDINANCE AMENDMENT: WIND ENERGY

WILSON TOWNSHIP ZONING ORDINANCE AMENDMENT: WIND ENERGY WILSON TOWNSHIP ZONING ORDINANCE AMENDMENT: WIND ENERGY (ADD TO ARTICLE 2) WIND ENERGY DEFINITIONS: Ambient: Ambient is defined as the sound pressure level exceeded ninety (90) percent of the time. Anemometer:

More information

CHAPTER 28 WIND ENERGY CONVERSION SYSTEMS (WECS)

CHAPTER 28 WIND ENERGY CONVERSION SYSTEMS (WECS) CHAPTER 28 WIND ENERGY CONVERSION SYSTEMS (WECS) SECTION: 10-28-1: Purpose 10-28-2: Application 10-28-3: Declaration of Conditions 10-28-4: Site Plan Drawing 10-28-5: Compliance with State Building Code

More information

Wind Energy Ordinances

Wind Energy Ordinances INFORMATION GUIDE: Wind Energy Ordinances Wind turbines are multiplying across the U.S., and most are installed in rural areas overlooking crops, cattle, timber, and lakes. Rural communities have experienced

More information

CITY OF DELANO COUNTY OF WRIGHT STATE OF MINNESOTA ORDINANCE NO.

CITY OF DELANO COUNTY OF WRIGHT STATE OF MINNESOTA ORDINANCE NO. CITY OF DELANO COUNTY OF WRIGHT STATE OF MINNESOTA ORDINANCE NO. AN ORDINANCE AMENDING SECTION 51.01 (DEFINITIONS) AND ADDING SUBDIVISION O TO SECTION 51.03 (GENERAL PROVISIONS) OF THE ZONING ORDINANCE

More information

Section 2202 Applicability. This regulation applies to all lands within the boundaries of Austintown Township, Mahoning County, State of Ohio.

Section 2202 Applicability. This regulation applies to all lands within the boundaries of Austintown Township, Mahoning County, State of Ohio. ARTICLE XXII- SMALL WIND ENERGY PROJECT REGULATION (Adopted January 23, 2012) Section 2200. This regulation may be referred to as the Small Wind Energy Project Regulation. Section 2201 Purpose. The purpose

More information

CITY OF TONKA BAY COUNTY OF HENNEPIN STATE OF MINNESOTA ORDINANCE NO

CITY OF TONKA BAY COUNTY OF HENNEPIN STATE OF MINNESOTA ORDINANCE NO CITY OF TONKA BAY COUNTY OF HENNEPIN STATE OF MINNESOTA ORDINANCE NO. 2017- AN ORDINANCE AMENDING CHAPTER X, ZONING, SECTION 1011, GENERAL DEVELOPMENT AND PERFORMANCE STANDARDS WIND ENERGY CONVERSION SYSTEMS

More information

Wind Energy Facility Siting and Permitting in South Dakota

Wind Energy Facility Siting and Permitting in South Dakota Wind Energy Facility Siting and Permitting in South Dakota Tim Binder Staff Analyst Tim.Binder@state.sd.us 21 October 2009 Large Wind Wind Energy Basics Wind Farms: Buffalo Ridge, Hyde County Small Wind

More information

WIND ENERGY CONVERSION SYSTEMS (Section Added by Ordinance 52-M, Effective ) (As Amended by Ordinance 52-P, Adopted )

WIND ENERGY CONVERSION SYSTEMS (Section Added by Ordinance 52-M, Effective ) (As Amended by Ordinance 52-P, Adopted ) (c) Lastly, no variances shall be granted by the Zoning Board of Appeals to any of the requirements contained herein. This section specifically is attempting to address state statutory regulations regarding

More information

Article 18 Wind Energy Conversion System Regulations

Article 18 Wind Energy Conversion System Regulations Article 18 Wind Energy Conversion System Regulations SECTION 1. PURPOSE Purpose This ordinance is established to regulate the installation and operation of Wind Energy Conversion Systems (WECS) within

More information

Proposed UNION COUNTY ORDINANCE # 73

Proposed UNION COUNTY ORDINANCE # 73 3112019 Proposed UNION COUNTY ORDINANCE # 73 AN ORDINANCE REGULATING THE PLACEMENT OF WIND ENERGY CONVERSION SYSTEMS (WECS) ON PROPERTY LOCATED IN THE UNINCORPORATED AREAS OF UNION COUNTY, IOWA BE IT ENACTED

More information

Wind Energy ARTICLE XL - WIND ENERGY AN ORDINANCE REGULATING THE DEVELOPMENT OF WIND ENERGY SYSTEMS

Wind Energy ARTICLE XL - WIND ENERGY AN ORDINANCE REGULATING THE DEVELOPMENT OF WIND ENERGY SYSTEMS Wind Energy ARTICLE XL - WIND ENERGY AN ORDINANCE REGULATING THE DEVELOPMENT OF WIND ENERGY SYSTEMS 40.0 Authority. 40.1 Purpose. 40.2 Applicability. 40.3 Definitions. 40.4 Standards. 40.5 Permit Requirements.

More information

ORDINANCE NO

ORDINANCE NO CITY OF NORTH BRANCH STATE OF MINNESOTA COUNTY OF CHISAGO ORDINANCE NO. 211-14 AN ORDINANCE AMENDING THE NORTH BRANCH ZONING ORDINANCE BY ADDING STANDARDS AND DEFINITIONS FOR SOLAR ENERGY SYSTEMS, SOLAR

More information

Cheshire, MA SMALL WIND ENERGY SYSTEMS 12.0 SMALL WIND ENERGY SYSTEMS

Cheshire, MA SMALL WIND ENERGY SYSTEMS 12.0 SMALL WIND ENERGY SYSTEMS 12.0 12.1 Purpose The purpose of this section is to provide a permitting process for small wind energy systems (SWES) for individual homeowners so that they may be utilized in a cost-effective, efficient,

More information

CUP APPLICATION WIND ENERGY CONVERSION SYSTEMS (WECS) Commercial or Non-Commercial

CUP APPLICATION WIND ENERGY CONVERSION SYSTEMS (WECS) Commercial or Non-Commercial Application Fee $ 500.00 Dodge County Environmental Services Recorder Fee $46.00 721 Main St N, Dept. 123 Date Received Mantorville, MN 55955 Received by Phone 507-635-6272 www.co.dodge.mn.us CUP APPLICATION

More information

TABLE OF CONTENTS PAGE SECTION

TABLE OF CONTENTS PAGE SECTION TABLE OF CONTENTS SECTION PAGE 1.0 EXECUTIVE SUMMARY... 1 1.1 Project Description... 1 1.2 Project Applicant... 1 1.3 Summary of Project Purpose and Need... 2 1.4 Summary of Proposed Alternative... 2 1.5

More information

2.04 Applicability. This ordinance applies to all unincorporated lands within the boundaries of Henry County.

2.04 Applicability. This ordinance applies to all unincorporated lands within the boundaries of Henry County. Henry County Zoning Ordinance Appendix B Wind Energy As Amended December 12, 2009 Appendix B Wind Energy 2.01 Title. Wind Energy Ordinance 2.02 Authority. 2.03 Purpose. 2.04 Applicability. 2.05 Definitions.

More information

Town of Allegany Wind Energy Regulations. Proposed Amendments to the Town s Zoning Ordinance Draft: February 13, 2007

Town of Allegany Wind Energy Regulations. Proposed Amendments to the Town s Zoning Ordinance Draft: February 13, 2007 Town of Allegany Wind Energy Regulations Proposed Amendments to the Town s Zoning Ordinance Draft: February 13, 2007 Amend Article II, Rules and Definitions, Section 2.02 Definition of Terms, to add the

More information

ARTICLE XXIII SMALL WIND ENERGY SYSTEMS 85

ARTICLE XXIII SMALL WIND ENERGY SYSTEMS 85 ARTICLE XXIII SMALL WIND ENERGY SYSTEMS 85 Section 1. Purpose and Intent The purpose of this article is to regulate the placement, construction and modification of small wind energy systems while promoting

More information

In May of 2011, Council completed a three year project to develop regulations for largescale wind turbines in the County.

In May of 2011, Council completed a three year project to develop regulations for largescale wind turbines in the County. Municipality of the County of Kings Report to the Planning Advisory Committee Large-Scale Wind Turbine Policy, Post-PPM Report Prepared by Planning Services May 14 th, 2012 1. BACKGROUND In May of 2011,

More information

BEFORE THE OHIO POWER SITING BOARD

BEFORE THE OHIO POWER SITING BOARD BEFORE THE OHIO POWER SITING BOARD Application of a Certificate of Environmental Compatibility and Public Need Table of Contents Page No. List of Figures... xii List of Tables... xiii List of Appendices...xv

More information

SECTION ENERGY SYSTEMS (WIND AND SOLAR)

SECTION ENERGY SYSTEMS (WIND AND SOLAR) Section 1107.18 Page 1 SECTION 1107.18 ENERGY SYSTEMS (WIND AND SOLAR) 1107.18 SUBD. 1. PURPOSE. The purpose of this Section is to establish standards and procedures by which the installation and operation

More information

Box Elder County Land Use Management & Development Code WIND ORDINANCE

Box Elder County Land Use Management & Development Code WIND ORDINANCE Article 5: SMALL & LARGE WIND SYSTEMS Chapter 5-4. Wind System Regulations Box Elder Zoning Ordinance 339 as Adopted July 29, 2010 Part 1. General 2. Temporary Meteorological Towers (MET Towers) 3. Small

More information

List of Figures... xii. List of Tables... xiii. List of Appendices...xv. Glossary... xvii Project Summary and Facility Overview...

List of Figures... xii. List of Tables... xiii. List of Appendices...xv. Glossary... xvii Project Summary and Facility Overview... BEFORE THE OHIO POWER SITING BOARD Application of a Certificate of Environmental Compatibility and Public Need Blue Creek Wind Farm Amendment Table of Contents Text sections that have been updated for

More information

# Central States Tower/ Verizon Wireless Special Use Permit & Zoning Variation Project Review for Planning and Zoning Commission

# Central States Tower/ Verizon Wireless Special Use Permit & Zoning Variation Project Review for Planning and Zoning Commission #2015-47 Central States Tower/ Verizon Wireless Special Use Permit & Zoning Variation Project Review for Planning and Zoning Commission Meeting Date: August 19, 2015 Request: Location: Acreage: Existing

More information

C O M M E R C I A L W I N D E N E R G Y R E G U L A T I O N S - R E V I S E D : 3 / 3 0 / 1 6

C O M M E R C I A L W I N D E N E R G Y R E G U L A T I O N S - R E V I S E D : 3 / 3 0 / 1 6 C O M M E R C I A L W I N D E N E R G Y R E G U L A T I O N S - R E V I S E D : 3 / 3 0 / 1 6 6.6 Small and Commercial Wind Energy Conversion Systems 6.61 Intent: In order to balance the need for clean,

More information

ORDINANCE NO. THE LENT TOWNSHIP BOARD OF SUPERVISORS ORDAINS: The following language is hereby added to the Lent Township Zoning Ordinance:

ORDINANCE NO. THE LENT TOWNSHIP BOARD OF SUPERVISORS ORDAINS: The following language is hereby added to the Lent Township Zoning Ordinance: ORDINANCE NO. AMENDING THE LENT TOWNSHIP ZONING ORDINANCE BY ADDING STANDARDS AND DEFINITIONS FOR SOLAR ENERGY SYSTEMS, SOLAR ENERGY FARMS AND FOR THEIR INSTALATION AND USE IN LENT TOWNSHIP THE LENT TOWNSHIP

More information

CHAPTER 725. Solar Farms.

CHAPTER 725. Solar Farms. CHAPTER 725 Solar Farms. The following provisions shall apply to all solar farms in Carroll County, IL. A Solar Farm is defined as a power station using photovoltaic modules and inverters for utility electricity

More information

BOARD OF COUNTY COMMISSIONERS FOR SOMERSET COUNTY, MARYLAND ORDINANCE NO.

BOARD OF COUNTY COMMISSIONERS FOR SOMERSET COUNTY, MARYLAND ORDINANCE NO. BOARD OF COUNTY COMMISSIONERS FOR SOMERSET COUNTY, MARYLAND ORDINANCE NO. AN ORDINANCE AMENDING THE SOMERSET COUNTY ZONING ORDINANCE NO. 741 BY ADDING PROVISIONS DEALING WITH INDUSTRIAL WIND ENERGY CONVERSION

More information

CHIPPEWA COUNTY LAND AND RELATED RESOURCE MANAGEMENT ORDINANCE SECTION 16 SOLAR POWER MANAGEMENT TABLE OF CONTENTS SUBDIVISION 1.

CHIPPEWA COUNTY LAND AND RELATED RESOURCE MANAGEMENT ORDINANCE SECTION 16 SOLAR POWER MANAGEMENT TABLE OF CONTENTS SUBDIVISION 1. CHIPPEWA COUNTY LAND AND RELATED RESOURCE MANAGEMENT ORDINANCE SECTION 16 SOLAR POWER MANAGEMENT TABLE OF CONTENTS PAGE SUBDIVISION 1. TITLE 1 SUBDIVISION 2. PURPOSE 1 SUBDIVISION 3. JURISDICTION 1 SUBDIVISION

More information

9.2 Definitions. The following terms are defined, for purposes of Section 9, as follows:

9.2 Definitions. The following terms are defined, for purposes of Section 9, as follows: SECTION 9. COMMERCIAL WIND ENERGY FACILITIES 9.1 Purpose. The purpose of this Section 9 of the Zoning Bylaw is to provide by special permit for the construction and operation of commercial wind facilities

More information

CHAPTER 14 WIND AND SOLAR ENERGY

CHAPTER 14 WIND AND SOLAR ENERGY CHAPTER 14 WIND AND SOLAR ENERGY Section 1400.00 Section 1400.01 Wind and Solar Energy Purpose Small solar and wind energy systems shall be permitted in all zoning districts, in accordance with the requirements

More information

Solar Permitting in Minnesota GERONIMO ENERGY TENA MONSON MANAGER OF SOLAR DEVELOPMENT

Solar Permitting in Minnesota GERONIMO ENERGY TENA MONSON MANAGER OF SOLAR DEVELOPMENT Solar Permitting in Minnesota GERONIMO ENERGY TENA MONSON MANAGER OF SOLAR DEVELOPMENT Presentation Agenda SOLAR ENERGY Industry Update State Permitting Solar Ordinance Local Land Use Permitting Geronimo

More information

OPEN HOUSE PROJECT OVERVIEW OPEN HOUSE NOVEMBER 16, :00-8:00 PM FALL 2017

OPEN HOUSE PROJECT OVERVIEW OPEN HOUSE NOVEMBER 16, :00-8:00 PM FALL 2017 FALL 2017 PROJECT OVERVIEW EDF EN Canada is proposing to develop, construct, and operate the Cypress Wind Power Project with 243.6 megawatts (MW) of generating capacity. The Project is south of Dunmore,

More information

ARTICLE 16 CITY OF EUDORA ZONING REGULATIONS

ARTICLE 16 CITY OF EUDORA ZONING REGULATIONS TABLE OF CONTENTS ARTICLE 16 CITY OF EUDORA ZONING REGULATIONS TABLE OF CONTENTS ``````````````````````````````````````````````````````````````````` SECTION 1. GENERAL PROVISIONS... 1! 16-101!Short Title...

More information

IT IS HEREBY ENACTED AND ORDAINED by Paradise Township, York County, Pennsylvania as follows:

IT IS HEREBY ENACTED AND ORDAINED by Paradise Township, York County, Pennsylvania as follows: PARADISE TOWNSHIP, YORK COUNTY PENNSYLVANIA ORDINANCE NO. 2015-02 ENERGY PRODUCING SYSTEMS ORDINANCE WHEREAS, Paradise Township, York County Pennsylvania, herein referred to as the Township, seeks to promote

More information

17. Commercial WECS S P X X X X X X X X B C

17. Commercial WECS S P X X X X X X X X B C Please note that all standards that are approved with this ordinance change must be met. If there are any standards not met they must go to the Board of Zoning Appeals for a public hearing. Table A: AG

More information

WINTHROP, MAINE SMALL WIND ENERGY SYSTEMS ORDINANCE

WINTHROP, MAINE SMALL WIND ENERGY SYSTEMS ORDINANCE WINTHROP, MAINE SMALL WIND ENERGY SYSTEMS ORDINANCE I. Title This ordinance shall be known and cited as the "SMALL WIND ENERGY SYSTEMS ORDINANCE" of the Town of Winthrop, Maine, (hereinafter referred to

More information

Project siting. Lanfine. Wind resource assessment. Wind Power Project

Project siting. Lanfine. Wind resource assessment. Wind Power Project Project siting Wind resource assessment This assessment determines how much electrical energy can be extracted from the wind Meteorological towers are installed on site to measure wind speed and direction

More information

PAINT TOWNSHIP SOMERSET COUNTY, PENNSYLVANIA. ORDINANCE NO. OS ai? - I \

PAINT TOWNSHIP SOMERSET COUNTY, PENNSYLVANIA. ORDINANCE NO. OS ai? - I \ .,.. ' PAINT TOWNSHIP SOMERSET COUNTY, PENNSYLVANIA ORDINANCE NO. OS ai? - I \ AN ORDINANCE OF THE TOWNSHIP OF PAINT PROVIDING FOR THE REGULATION OF CONSTRUCTION, PLACEMENT AND OPERATION OF RESIDENTIAL

More information

6.5 SMALL WIND ENERGY SYSTEMS

6.5 SMALL WIND ENERGY SYSTEMS 6.5 SMALL WIND ENERGY SYSTEMS 6.5.1 Purpose. The purpose of this subsection is to provide a permitting process for Small Wind Energy Systems (SWES) so that they may be utilized in a cost-effective, efficient,

More information

Summit Repower Siting Process - Update to August 23, 2016 and November 10, 2016 reports.

Summit Repower Siting Process - Update to August 23, 2016 and November 10, 2016 reports. Summit Repower Siting Process - Update to August 23, 2016 and November 10, 2016 reports. June 29, 2017 Introduction This document addresses the siting work outstanding as of the November 10 th, 2016 siting

More information

The breach of any condition shall be cause for the Planning Commission to revoke Special Approval Use Permit.

The breach of any condition shall be cause for the Planning Commission to revoke Special Approval Use Permit. Add to the end of Section 15.01 (Procedures for Special Approval Uses) The scale drawing submitted with the application shall be prepared in conformance to Article XIV (Site Plan Review Requirements) of

More information

Chapter 750 WIND POWER GENERATION FACILITIES

Chapter 750 WIND POWER GENERATION FACILITIES Chapter 750 WIND POWER GENERATION FACILITIES 750.01 Purpose 750.02 Definitions 750.03 Designated Areas 750.04 Permitted Uses 750.05 Conditional Uses 750.06 Construction Standards 750.07 Application Requirements

More information

HEIGHT, TOTAL SYSTEM: The height above grade of the system, including the generating unit and the highest vertical extension of any blades or rotors.

HEIGHT, TOTAL SYSTEM: The height above grade of the system, including the generating unit and the highest vertical extension of any blades or rotors. SECTION I - INTENT The intent of this ordinance is to balance the need for clean, renewable energy resources and the necessity to protect the public health, safety and welfare of the community. The [City/County]

More information

1.0 INTRODUCTION 1.1 SUMMARY OF SEQRA PROCESS

1.0 INTRODUCTION 1.1 SUMMARY OF SEQRA PROCESS 1.0 INTRODUCTION This is prepared for the Jericho Rise Wind Farm (hereafter, the Project ) pursuant to the New York State Environmental Quality Review Act (SEQRA) and its implementing regulations, 6 NYCRR

More information

6.6 RESIDENTIALLY-SCALED, LAND-BASED WIND ENERGY CONVERSION FACILITIES

6.6 RESIDENTIALLY-SCALED, LAND-BASED WIND ENERGY CONVERSION FACILITIES 6.6 RESIDENTIALLY-SCALED, LAND-BASED WIND ENERGY CONVERSION FACILITIES 6.6.1 Purpose and Intent It is the express purpose of this Section to accommodate residentially-scaled, land-based wind energy conversion

More information

# Space Management Annexation Project Review for Planning and Zoning Commission

# Space Management Annexation Project Review for Planning and Zoning Commission #2012-75 Space Management Annexation Project Review for Planning and Zoning Commission Meeting Date: September 7, 2016 Request: Location: Acreage: Existing Zoning: Requested Zoning: 1) Rezoning upon annexation

More information

West Mead Township Crawford County, Pennsylvania Ordinance No

West Mead Township Crawford County, Pennsylvania Ordinance No West Mead Township Crawford County, Pennsylvania Ordinance No. 2001-4 ORDINANCE TO AMEND THE WEST MEAD TOWNSHIP ZONING ORDINANCE TO ADD LAND USE REGULATIONS FOR COMMUNICATIONS TOWERS Whereas, the Board

More information

DOÑA ANA COUNTY Community Development Department Intra-Departmental Memorandum

DOÑA ANA COUNTY Community Development Department Intra-Departmental Memorandum DOÑA ANA COUNTY Community Development Department Intra-Departmental Memorandum To: Planning and Zoning Commission Date: April 17, 2012 From: Steve Meadows, Planner Subject: Proposed Wireless Telecommunications

More information

Pteragen Canada Inc.

Pteragen Canada Inc. Decision 2013-171 May 7, 2013 The Alberta Utilities Commission Decision 2013-171: Application No. 1608907 Proceeding ID No. 2181 May 7, 2013 Published by The Alberta Utilities Commission Fifth Avenue Place,

More information

CONSIDERATIONS RELATED TO INVESTING IN SMALL WIND SYSTEMS

CONSIDERATIONS RELATED TO INVESTING IN SMALL WIND SYSTEMS CONSIDERATIONS RELATED TO INVESTING IN SMALL WIND SYSTEMS Stephen B. Harsh Department of Agricultural, Food and Resource Economics State University Copyright 2016 Energy Meeting, 2016 FOCUS OF PRESENTATION

More information

Cassadaga Wind Project Exhibit 6. Wind Power Facilities

Cassadaga Wind Project Exhibit 6. Wind Power Facilities Case No. 14-F-0490 1001.6 Exhibit 6 Wind Power Facilities WIND POWER FACILITIES (a) Factors Considered During Placement of Wind Turbines (Setback Requirements/Recommendations/Fall-Down Distances) The primary

More information

State code 23: Wind farm development

State code 23: Wind farm development 23.1 Purpose statement The purpose of the code is to protect individuals, communities and the environment from adverse impacts as a result of the construction, operation and decommissioning of wind farm

More information

ORDINANCE NO. BEAVER TOWNSHIP, BAY COUNTY, MICHIGAN, ORDAINS:

ORDINANCE NO. BEAVER TOWNSHIP, BAY COUNTY, MICHIGAN, ORDAINS: ORDINANCE NO. An ordinance amending Beaver Township Ordinance No. 15, as amended, the Township Zoning Ordinance, in the following particulars: by changing Chapter II by adding Section 2.60 to provide a

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22781-D01-2017 Newell Solar Power Plant November 15, 2017 Alberta Utilities Commission Decision 22781-D01-2017 Newell Solar Power Plant Proceeding 22781 Application 22781-A001 November 15, 2017

More information

Abandonment means to discontinue use with no intentions of rehabilitation of use or reinstating use within the next 18 months.

Abandonment means to discontinue use with no intentions of rehabilitation of use or reinstating use within the next 18 months. 18.xx.010 Title. This chapter shall be known and may be cited as the Cowlitz County Small Wind Energy System Chapter. 18.xx.020 Purpose and Intent. Cowlitz County is committed to developing an alternative

More information

D-1. SOUTH PEACE EAST AND WEST SOP PROJECTS PATRICK HENN, DEVELOPMENT MANAGER PRRD Board of Directors Meeting, April

D-1. SOUTH PEACE EAST AND WEST SOP PROJECTS PATRICK HENN, DEVELOPMENT MANAGER PRRD Board of Directors Meeting, April SOUTH PEACE EAST AND WEST SOP PROJECTS PATRICK HENN, DEVELOPMENT MANAGER PRRD Board of Directors Meeting, April 28 2016 Renewable Energy Systems (RES) In Canada for more than 12 years Family-owned company

More information

Wind Energy and Wildlife: Frequently Asked Questions

Wind Energy and Wildlife: Frequently Asked Questions Wind Energy and Wildlife: Frequently Asked Questions Q: How does wind energy work? How is electricity generated from the wind? A: A wind energy system transforms the kinetic energy of the wind into mechanical

More information

4.10 LAND USE ENVIRONMENTAL SETTING

4.10 LAND USE ENVIRONMENTAL SETTING 4.10 LAND USE 4.10.1 ENVIRONMENTAL SETTING The proposed Project consists of construction and operation of two 8-inch crude oil pipelines (within one trench) and equipment for storage and pumping from the

More information

Appendix E. Development Regulation Amendments. Klickitat County Energy Overlay Environmental Impact Statement

Appendix E. Development Regulation Amendments. Klickitat County Energy Overlay Environmental Impact Statement Appendix E Development Regulation Amendments Klickitat County Energy Overlay Environmental Impact Statement PROPOSED AMENDMENTS TO DEVELOPMENT REGULATIONS ENERGY OVERLAY NEW SECTION (Chapter 19.39 Klickitat

More information

BILL NO. B ORDINANCE NO TOWNSHIP OF O HARA ALLEGHENY COUNTY, PENNSYLVANIA

BILL NO. B ORDINANCE NO TOWNSHIP OF O HARA ALLEGHENY COUNTY, PENNSYLVANIA TOWNSHIP OF O HARA ALLEGHENY COUNTY, PENNSYLVANIA AN ORDINANCE OF THE TOWNSHIP OF O HARA AMENDING AND RESTATING ORDINANCE NO. 1237 WHICH AMENDED THE ZONING ORDINANCE NO. 1091 TO PROVIDE REGULATIONS OF

More information

MAKING WIND POWER MORE BIODIVERSITY- FRIENDLY: RECENT LESSONS FROM WORLD BANK EXPERIENCE

MAKING WIND POWER MORE BIODIVERSITY- FRIENDLY: RECENT LESSONS FROM WORLD BANK EXPERIENCE (The views expressed here are those of the author and should not be attributed to the World Bank Group.) MAKING WIND POWER MORE BIODIVERSITY- FRIENDLY: RECENT LESSONS FROM WORLD BANK EXPERIENCE George

More information

5.6- LAND-BASED WIND ENERGY CONVERSION FACILITIES

5.6- LAND-BASED WIND ENERGY CONVERSION FACILITIES WIND ENERGY CONVERSION FACILITIES BYLAW TOWN OF CHESTER Adopted at November 13, 2006 Special Town Meeting Approved by Attorney General on March 27, 2007 5.6- LAND-BASED WIND ENERGY CONVERSION FACILITIES

More information

(1) The proposed commercial solar energy generation facility is either

(1) The proposed commercial solar energy generation facility is either (2) The design and siting of these facilities shall avoid the placement of turbines on or immediately adjacent to the upwind side of ridge crests; (3) The design may include other design features to minimize

More information

Wind Development: Benefits and Constraints

Wind Development: Benefits and Constraints Wind Development: Benefits and Constraints Joseph Fischl And Charles Malaniak Tetra Tech EC, Inc. 1 Objective Benefits of wind energy Define small vs. big wind Identify setbacks and development constraints

More information

Town of Rensselaerville LOCAL LAW NO. 2 OF THE YEAR 2009

Town of Rensselaerville LOCAL LAW NO. 2 OF THE YEAR 2009 LOCAL LAW FILING NEW YORK STATE DEPARTMENT OF STATE 41 State Street, Albany NY 12231 Town of Rensselaerville LOCAL LAW NO. 2 OF THE YEAR 2009 A Local Law entitled Non-Commercial Wind Power Facilities Law

More information

The requirements set forth in this Section shall govern the construction and/or installation of all Renewable Energy Systems:

The requirements set forth in this Section shall govern the construction and/or installation of all Renewable Energy Systems: CHAPTER 408: RENEWABLE ENERGY SYSTEMS Renewable Energy Systems are accessory uses which include Solar Energy Systems and Wind Energy Systems that provide supplemental energy to residential, nonresidential,

More information

AN ORENDA WHITEPAPER. Rural Siting of Wind Turbines: Improve Performance and Mitigate Risk

AN ORENDA WHITEPAPER. Rural Siting of Wind Turbines: Improve Performance and Mitigate Risk AN ORENDA WHITEPAPER Rural Siting of Wind Turbines: Improve Performance and Mitigate Risk Rural Siting of Wind Turbines - Improve Performance and Mitigate Risk Wind power is a clean energy source that

More information

SMALL WIND ENERGY FACILITIES ORDINANCE. Ordinance No

SMALL WIND ENERGY FACILITIES ORDINANCE. Ordinance No SMALL WIND ENERGY FACILITIES ORDINANCE Ordinance No. 070806.1 1. PURPOSE The purpose of this Ordinance is to provide a regulatory scheme for the construction and operation of Small Wind Energy Facilities

More information

Summit Repower Siting Process August 23, 2016

Summit Repower Siting Process August 23, 2016 Summit Repower Siting Process August 23, 2016 Introduction This document describes the process used by Altamont Winds LLC to locate turbines for the proposed Summit repowering project. Micro-siting is

More information

Environmental Assessment Approval

Environmental Assessment Approval presented in the Registration Document. dispose of this Approval without the written consent of the Minister. The sale of a controlling interest of a business or a transfer of an approval following conditions

More information

Section 7.25 REGULATION OF SOLAR FARMS AND SOLAR PANELS

Section 7.25 REGULATION OF SOLAR FARMS AND SOLAR PANELS Section 7.25 REGULATION OF SOLAR FARMS AND SOLAR PANELS This amendment Solar Energy is hereby added to the Montcalm Township Zoning Ordinance to state as follows: A. INTENT AND PURPOSE This section is

More information

MARTIN COUNTY WIRELESS COMMUNICATION FACILITIES

MARTIN COUNTY WIRELESS COMMUNICATION FACILITIES MARTIN COUNTY WIRELESS COMMUNICATION FACILITIES Section 1. PURPOSE The purpose of the regulations and requirements of this Ordinance are to: Subpart 1. Accommodate the communication needs of the residents

More information

WIND ENERGY CONVERSION SYSTEMS APPLICATION

WIND ENERGY CONVERSION SYSTEMS APPLICATION Community Planning and Economic Development Development Services Division 250 South 4 th Street, Room 300 Minneapolis MN 55415-1316 612-673-3000 WIND ENERGY CONVERSION SYSTEMS APPLICATION 535.690. Purpose.

More information