Hydrocarbon Management PROCEDURE

Size: px
Start display at page:

Download "Hydrocarbon Management PROCEDURE"

Transcription

1 Hydrocarbon Management PROCEDURE Doc No: Approved: PRO-0380 Operations Manager

2 Table of Contents 1. PURPOSE SCOPE REFERENCES LEGISLATION/STANDARDS DEFINITIONS HYDROCARBON MANAGEMENT SYSTEM BIOREMEDIATION AREA MATERIAL TO BE TREATED REQUIREMENT TO NOTIFY SOIL CONTAMINATION ASSESSMENT OF REQUIREMENT TO LAND FARM TRANSFER OF CONTAMINATED SOIL TO LAND FARM LOCATION LAND FARM LOCATION PILE PARAMETERS COMPLETION OF LAND FARMING PROCESS MONITORING AND MANAGEMENT PROGRAM... 6 MONTHLY... 6 QUARTERLY... 6 ANNUALLY ACCOUNTABILITIES DOCUMENT CONTROL COMMUNICATION & CONSULTATION August August of 8

3 1. PURPOSE Integra Coal Operations (ICO) uses a number of hazardous substances including diesel, lubricating oils, grease, solvents, paints, coolants and flocculant. The purpose of this Hydrocarbon Management Procedure is to ensure that operations at ICO are undertaken in a manner that minimises hydrocarbon and chemical spills and provides information regarding management and reporting requirements if a spill occurs. 2. SCOPE This procedure applies to the management, storage and handling of hydrocarbon materials and the bioremediation treatment of hydrocarbon contaminated soils across the site. 3. REFERENCES 3.1 LEGISLATION/STANDARDS NSW Contaminated Land Act 1997 Protection of the Environment Operations Act 1997 State Environmental Planning Policy (SEPP) 55 Remediation of Lands National Environmental Protection Measure (NEPM) Schedule B1 Guideline on Investigation Levels for Soil and Groundwater AS : The storage and handling of flammable and combustible liquids 4. DEFINITIONS Accountability Hazardous Material Hydrocarbon A function of a person s role, for which he or she is answerable to their supervisor or manager. Anything that, when produced, stored, moved, used or otherwise dealt with without adequate safeguards to prevent it from escaping, may cause injury or death or damage to life, property or the environment. An organic compound or chemical compound consisting entirely of hydrogen and carbon. Hydrocarbons are the main constituents of fuels and oils. For the purposes of this procedure Coal is not included in the management of hydrocarbons as a number of other procedures deal with the volatility and environmental concerns of coal extraction and storage. 10 August August of 8

4 5. HYDROCARBON MANAGEMENT SYSTEM To provide proficient procedures, training personnel and equipment for the storage and handling of hydrocarbon materials on the mine site. Actions All employees to be advised of the potential impact of hydrocarbons during inductions and toolbox talks Documentation of record of induction, toolbox talks and training shall be maintained on site Where fuel, oil or chemicals are to be stored on site, a secure and imperviously bunded area (110% of volume of largest vessel) shall be provided. Minimum separation distances between hydrocarbons and other storage facilities and ignition sources shall be maintained Spill kits shall be readily accessible and maintained at storage and fill/drainage points. Where practical a hardstand location shall be utilised for the draining of spent hydrocarbons. Refuelling of mobile plant and equipment should be undertaken, where feasible, on designated hardstand areas or provided with temporary bunding to contain any spillages MSDS for all chemicals stored on site and available Oil water separators for drainage from workshops/washdown areas must be maintained Responsibility Advisor / Training Advisor / Training Advisor / Maintenance Advisor / Maintenance Advisor / Store Maintenance Operations and contractors All personnel Maintenance 6. BIOREMEDIATION AREA 6.1 MATERIAL TO BE TREATED Material requiring treatment is any topsoil, subsoil, clay, rock or other solid media (for the purposes of this procedure, referred to as soil ) which has been impacted by a hydrocarbon substance (e.g. diesel, hydraulic oil, engine oil, gearbox oil, grease etc). 6.2 REQUIREMENT TO NOTIFY SOIL CONTAMINATION All personnel must notify their supervisor of all hydrocarbons spills which result in soil contamination regardless of volume. The Supervisor or Advisor (ECA) will record the following details of the incident in the "Hydrocarbon Incident Register". 1. Location of Spill 2. Estimated volume of hydrocarbon involved. (litres) 10 August August of 8

5 3. Estimated soil contaminated (m3) 4. Action taken (area bunded, absorbent material spread, hydrocarbon contained, material removed offsite by certified waste contractor, material removed to bio-remediation site). 5. Person/s involved. 7. ASSESSMENT OF REQUIREMENT TO LAND FARM A supervisor, once aware of an incident of hydrocarbon contamination of soils, will decide whether land farming is an appropriate form of soil treatment. The ECA can assist the supervisor in this assessment, if required. 8. TRANSFER OF CONTAMINATED SOIL TO LAND FARM LOCATION Prior to the opportunity to transfer the contaminated soil to the land farm site being available, contaminated soil should be delineated to prevent it being handled as uncontaminated soil (such as waste rock overburden/interburden). The hydrocarbon and contaminated material must be contained prior to removal. The supervisor is to authorise the transfer of the contaminated soil to the land farming location at a time when practical to do so. 9. LAND FARM LOCATION The location for land farming should be one which is readily accessible by plant (trucks, excavator etc), where contaminated material can reside for an extended period (as a guide, 1-2 years), is removed from any clean water system and is not at risk of being buried by waste emplacement activity. The bioremediation area should be clay bunded and designed so that it does not drain freely. Typically the land farm should have delineated areas ( bays ) to support individual treatment of either contamination by different hydrocarbon types, different degrees of contamination and/or different stages of land framing progress. Treatment locations should be areas which would not be expected to receive significant overland drainage (ie get flooded) and be within an area that is not to be impacted by dumping, rehabilitation or other disturbances such as road construction etc. for at least 3 years. The location of the Open Cut land farming site is currently in the vicinity of the RL100 dump area. The location of the Underground land farming site is in vicinity of the stowe emplacement area (below the RL100m ROM coal handling area). 10. PILE PARAMETERS To maximise the performance of the land farming process to remove hydrocarbon contamination from soils, it is important to: 10 August August of 8

6 Limit pile depth a maximum height of 1m is recommended (a lower pile height will accelerate hydrocarbon degradation, a higher pile will slow down degradation etc); Ensure pile is not compacted; and Periodically turn the pile (more frequent turnings will accelerate degradation of hydrocarbons). Hydrocarbon degradation can also be accelerated by addition of water to the pile beyond that afforded by incident rainfall and addition of nutrient such as chicken manure. 11. COMPLETION OF LAND FARMING PROCESS Satisfactory completion of land farming is considered to be when hydrocarbon concentration within the pile has reached less than 1000ppm TPH (total petroleum hydrocarbon) concentration. This is verified through chemical analysis by a commercial analytical laboratory. A Hydrocarbon Management Register must be kept by the ECA containing the following information: 1. Test results from a NATA certified Laboratory of all remediated soil prior to disposal to in pit waste dump. 2. Volume of material taken to in pit waste dump. 3. Date and location of dumped material 4. Name of Supervisor and ECA. Material should be block tipped on the inner part of the dump and not at or over the tip face. The material must be dumped at an RL at least 20 metres above the groundwater level which is predicted after mine closure, and at least 10 metres below final design surface. (Rehabilitated surface). Refer to NEPM Schedule B1 Guideline, Section 2.4.2, Ecological Screening Levels for "Urban Residential and public open space" (coarse limits should be used given the nature of overburden material). Once the material is considered suitable, it can be transported and either direct placed or merged with topsoil stockpiles for future use in rehabilitation activities. 12. MONITORING AND MANAGEMENT PROGRAM Monthly Visual inspection by the ECA of land farm area. Note condition of area generally, pile height, degree of compaction, bunding condition, moisture levels. ECA to arrange any necessary corrective works through the area supervisor. Quarterly If required, ECA to arrange turning and mixing of the piles through the area supervisor. 10 August August of 8

7 Annually If required, ECA to collect representative soil samples from piles and obtain TPH concentrations. ECA to advise supervisor of ability to remove any successfully decontaminated soil material from the area on the basis of analytical results, as appropriate. The ECA will be responsible for recording information. 10 August August of 8

8 13. ACCOUNTABILITIES ROLE ACCOUNTABILITIES Environment & Community Advisor Works with document control to ensure procedure is kept up to date and the latest version is kept on Integra s Intranet. Arranges for relevant people to be trained on this procedure. Monitoring and oversight of the land farm facility. Technical assistance to area supervisors. Facilitating spoil pile turning, watering, nutrient addition etc in conjunction with area supervisor. Maintain the Hydrocarbon Management Register and Hydrocarbon Incident Register Supervisor Reporting of spill incidents to the Environment & Community Advisor. Ensure contaminated soil is not handled as normal (uncontaminated) waste. Facilitating transfer of hydrocarbon contaminated soil to the land farm facility. Facilitating spoil pile turning, watering, nutrient addition etc in conjunction with the Environment & Community Advisor. All persons Report hydrocarbon spills to area supervisor or ECA. 14. DOCUMENT CONTROL This procedure is to be reviewed every three (3) years and modified as necessary. 15. COMMUNICATION & CONSULTATION This procedure is to be circulated to all key stakeholders for comment, prior to finalisation. 10 August August of 8

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP)

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) Established 1907 POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) DATE: JULY 2018 Version Date Section Modified 1 July 2018 All Reason for Modification Original Management Plan Review Team MCC Environmental,

More information

left over, or an unwanted by-product, from an industrial, commercial, domestic or other activity; or

left over, or an unwanted by-product, from an industrial, commercial, domestic or other activity; or 14. Waste Management 14.1. Waste Management Regulations The regulatory requirements governing waste management are provided within the EP Act, the EPR and associated Environmental Protection (Waste Management)

More information

APRIL 2015 CONTINGENCY PLANS

APRIL 2015 CONTINGENCY PLANS APRIL 2015 CONTINGENCY PLANS Prepared by: TERRATEST (PTY) LTD PO Box 794 HILTON Postal code 3245 Telephone:0333436789 Email:terratest@terratest.co.za Project director: Simon Johnson TABLE OF CONTENTS 1

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PUBLIC)

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PUBLIC) Environmental Management System Integra Coal Operations Pty Ltd POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PUBLIC) 2012 Doc No: Doc Owner: EMP_2014-2 Environmental Advisor Integra Coal Operations Approval:

More information

Pollution Incident Response Management Plan

Pollution Incident Response Management Plan Pollution Incident Response Management Plan Gunnedah Quarry Products Pty Ltd Prepared by Tim MacKellar, Gunnedah Quarry Products Document created 13.10.13 Reviewed 10.10.14 Reviewed 12.10.15 Reviewed 02.02.18

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN MET Recycling Pty Ltd Lease Areas 3 & 4 Corner of Newton St North & Carnarvon St Silverwater NSW 2128 Lot 1 in DP 713708 1 Revision History Revision Date Author/Reviewer

More information

QP50.67 Revision 3 ENVIRONMENT

QP50.67 Revision 3 ENVIRONMENT 1.0 PURPOSE This procedure provides information so that business units and contractors can take adequate steps to co-ordinate a response in case of an actual or potential incident, including the actions

More information

Crushing and Screening Management Procedure Environment

Crushing and Screening Management Procedure Environment 1 Purpose and Scope This procedure specifies the operational environmental requirements relating to crushing and screening management at the Roy Hill Project. This procedure applies to all personnel involved

More information

Tasman Extension Project Environmental Impact Statement APPENDIX N PRELIMINARY HAZARD ANALYSIS

Tasman Extension Project Environmental Impact Statement APPENDIX N PRELIMINARY HAZARD ANALYSIS Tasman Extension Project Environmental Impact Statement APPENDIX N PRELIMINARY HAZARD ANALYSIS TASMAN EXTENSION PROJECT PRELIMINARY HAZARD ANALYSIS FEBRUARY 2012 Project No. DCL-09-01 Document No. PHA-C

More information

Construction Environment Management Plan

Construction Environment Management Plan Construction Environment Management Plan Guidance Material July 2013 ABSTRACT This CEMP guidance material has been prepared by MAC to assist the identification and management of environmental risks associated

More information

Borrow Pit and Quarry Management Procedure Environmental

Borrow Pit and Quarry Management Procedure Environmental 1 Purpose and Scope This procedure specifies the operational environmental requirements relating to borrow pit (BP) and quarry management at the Roy Hill Project. This procedure applies to all personnel

More information

White Bay 6 Marine Park & Refuelling Facility

White Bay 6 Marine Park & Refuelling Facility White Bay 6 Marine Park & Refuelling Facility Pollution Incident Response Plan White Bay 6 Wharf, Balmain, NSW 2041 1 1 Pollution Incident Response Plan Spill response procedures have been detailed in

More information

QP50.67 Revision 4 Environment

QP50.67 Revision 4 Environment 1.0 PURPOSE This procedure provides information so that business units and contractors can take adequate steps to co-ordinate a response in case of an actual or potential incident, including the actions

More information

Papua New Guinea LNG Project. Environmental and Social Management Plan Appendix 6: Spill Prevention and Response Plan PGGP-EH-SPENV

Papua New Guinea LNG Project. Environmental and Social Management Plan Appendix 6: Spill Prevention and Response Plan PGGP-EH-SPENV Esso Highlands Limited Papua New Guinea LNG Project Environmental and Social Management Plan Appendix 6: Spill Prevention and Response Plan PGGP-EH-SPENV-000018-008 LNG Project Page 2 of 14 CONTENTS 1.0

More information

BENGALLA Mining Company. Contamination Assessment

BENGALLA Mining Company. Contamination Assessment BENGALLA Mining Company U Contamination Assessment U CONTINUATION OF BENGALLA MINE PRELIMINARY CONTAMINATION ASSESSMENT Prepared by: HANSEN BAILEY 6 / 127 129 John Street SINGLETON NSW 2330 July 2013 For:

More information

To reduce the consumption of energy and the emission of greenhouse gases associated with Transit Systems NSW s activities.

To reduce the consumption of energy and the emission of greenhouse gases associated with Transit Systems NSW s activities. Transit Systems NSW Environmental Management Plan GOAL 1: REDUCE THE GREENHOUSE IMPACT OF ENERGY USE To reduce the consumption of energy and the emission of greenhouse gases associated with Transit Systems

More information

DOORNVALLEI EXT 5 & 6

DOORNVALLEI EXT 5 & 6 DOORNVALLEI EXT 5 & 6 Proposed township establishment on portion 107 the farm Doornkloof 391 JR Sewer Pipe Crossings - Sesmylspruit Construction Method Statement April 2016 Revision 3 PREPARED FOR: PREPARED

More information

This report was prepared by Stanley Abraham, Bioremediation of Hydrocarbon-Contaminated Soil

This report was prepared by Stanley Abraham, Bioremediation of Hydrocarbon-Contaminated Soil This report was prepared by Stanley Abraham, Vice President, Industrial Systems Corp. LLC, PO Box 61, Postal Code 134, Shattia, Muscat, Sultanate of Oman, Oman. Bioremediation of Hydrocarbon-Contaminated

More information

Environmental Assessment Chapter 8 Surface Water

Environmental Assessment Chapter 8 Surface Water Environmental Assessment Chapter 8 Surface Water 8.2.7 Rainfall and Evaporation Based on recorded data for the area of interest, the mean annual rainfall is about 700mm, with maximum monthly rainfalls

More information

Construction, Demolition & Excavation Works Doc Reference: DoMN-WHSMS 3.14 Version Number: 2.2

Construction, Demolition & Excavation Works Doc Reference: DoMN-WHSMS 3.14 Version Number: 2.2 Purpose This procedure provides guidance to the Diocese of Maitland Newcastle (DoMN), principal contractors and other persons conducting a business or undertaking (PCBU) who commission or carry out construction,

More information

Pollution Incident Response Management Plan - Summary. Medway Mine Medway

Pollution Incident Response Management Plan - Summary. Medway Mine Medway Pollution Incident Response Management Plan - Summary Medway Mine Medway Table of Contents 1. General Information... 3 1.1 Foreword... 3 1.2 Background and legislative requirements... 3 1.3 Definition

More information

Sulcor Pollution Incident Response Management Plan (PIRMP)

Sulcor Pollution Incident Response Management Plan (PIRMP) Sulcor Pollution Incident Response Management Plan (PIRMP) The Sulcor Limestone open cut mine is located 30Km north-west of Tamworth NSW. The limestone mined by conventional drill and blast processes is

More information

ACAPMA Best Practice Guidelines

ACAPMA Best Practice Guidelines ADVOCACY EMPLOYMENT EVENTS NEWS TRAINING ACAPMA Best Practice Guidelines Management of Hydrocarbons in Stormwater at Retail Fuel Outlets 2017 Version ACAPMA The Voice of Downstream Petroleum ABOUT THIS

More information

Soil Treatment Facility Design and Operation for Bioremediation of Hydrocarbon Contaminated Soil. Version 1.0

Soil Treatment Facility Design and Operation for Bioremediation of Hydrocarbon Contaminated Soil. Version 1.0 PROTOCOL 15 FOR CONTAMINATED SITES Soil Treatment Facility Design and Operation for Bioremediation of Hydrocarbon Contaminated Soil Version 1.0 Prepared pursuant to Section 64 of the Environmental Management

More information

Surface Water Management Procedure Environment

Surface Water Management Procedure Environment 1 Purpose and Scope This procedure specifies the operational environmental requirements that relate to surface water management at the Roy Hill Project. This procedure applies to all personnel involved

More information

AM-PR-003 Construction Environmental Management Plan (C-EMP)

AM-PR-003 Construction Environmental Management Plan (C-EMP) OMS Procedure AM-PR-003 Construction Environmental Management Plan (C-EMP) Revision: 1 Prepared by: Shannon Holroyd Authorised by: Marcus Manning Authorisation Date: 18th May 2015 This document has been

More information

Pollution Incident Response Management Plan

Pollution Incident Response Management Plan Pollution Incident Response Management Plan Lot 3 DP 619374, and Lots 102, 103, 110, 120 DP 755418 Buckaroo Lane, Mudgee Pollution Incident Response Plan 1 Oct 2012 Oct 2013 Minespex B Murdoch 2 Feb 2014

More information

5 ASSESSMENT No. 1 Open Cut Extension No. 2 Open Cut Management Review... 10

5 ASSESSMENT No. 1 Open Cut Extension No. 2 Open Cut Management Review... 10 Contents 1 INTRODUCTION... 2 2 OCCURRENCE OF SPONTANEOUS COMBUSTION... 3 2.1 No.1 Open Cut Extension... 3 2.2 No.2 Open Cut... 3 2.3 Monthly Treatment - Capping, Mining and Water Infusion Areas... 4 3

More information

Millennium Expansion Project Environmental Impact Statement CHAPTER 9: WASTE

Millennium Expansion Project Environmental Impact Statement CHAPTER 9: WASTE Environmental Impact Statement CHAPTER 9: WASTE TABLE OF CONTENTS 9.0 WASTE MANAGEMENT... 9-1 9.1 EXECUTIVE SUMMARY... 9-1 9.1.1 Values... 9-1 9.1.2 Issues... 9-1 9.1.3 Mitigation Strategies... 9-1 9.1.3.1

More information

Papua New Guinea LNG Project. Environmental and Social Management Plan Appendix 11: Reinstatement Management Plan PGGP-EH-SPENV

Papua New Guinea LNG Project. Environmental and Social Management Plan Appendix 11: Reinstatement Management Plan PGGP-EH-SPENV Esso Highlands Limited Papua New Guinea LNG Project Environmental and Social Management Plan Appendix 11: PGGP-EH-SPENV-000018-013 LNG Project Page 2 of 13 CONTENTS 1.0 Objectives... 3 2.0 Legal and Other

More information

1993 Specifications CSJ SPECIAL SPECIFICATION ITEM 4417 DEWATERING IN CONTAMINATED GROUNDWATER

1993 Specifications CSJ SPECIAL SPECIFICATION ITEM 4417 DEWATERING IN CONTAMINATED GROUNDWATER 1993 Specifications CSJ 8015-24-003 SPECIAL SPECIFICATION TO ITEM 4417 DEWATERING IN CONTAMINATED GROUNDWATER 1. DESCRIPTION. This item shall govern all work required to remove groundwater encountered

More information

WI-ENV-PER-0013 GROUND DISTURBANCE PERMIT

WI-ENV-PER-0013 GROUND DISTURBANCE PERMIT WI-ENV-PER-0013 GROUND DISTURBANCE PERMIT PERMIT NUMBER PERMIT NAME DATE RECEIVED PERMIT APPROVAL DATE PERMIT EXPIRY DATE GDP- (Office use only) This Ground Disturbance Permit (GDP) is to be completed

More information

PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENERGY AND MINES

PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENERGY AND MINES PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENERGY AND MINES SAND AND GRAVEL PERMIT APPROVING WORK SYSTEM AND RECLAMATION PROGRAM (Issued pursuant to Section 10 of the Mines Act R.S.B.C. 1996, C.293) Permit:

More information

Pollution Incident Response Management Plan for Southern Roadbase Quarry

Pollution Incident Response Management Plan for Southern Roadbase Quarry Pollution Incident Response Management Plan for Southern Roadbase Quarry EPL number: 12045 Contents 1. OVERVIEW... 2 2. EVALUATION... 6 3. HAZARD, LIKELIHOOD AND PRE-EMPTIVE ACTIONS TO PREVENT POLLUTION

More information

Management Plan. Environmental Management Strategy

Management Plan. Environmental Management Strategy 3-3544 No. 9 31 Oct 18 PSE Manager Management Plan Environmental Management Strategy Risk Statement: High This document will be reviewed on a yearly basis, unless a process change occurs earlier than this

More information

Environmental Conditions Laboratories (for commercial use) Group

Environmental Conditions Laboratories (for commercial use) Group GBR No. 20 Environmental Conditions Laboratories (for commercial use) Group ERA regulates the environmental impact of enterprises through two key mechanisms. Smaller scale activities are regulated through

More information

Thermal Desorption of Hydrocarbon Contaminated Soil How to Successfully Use this Technology. By Cal Faminow, CTech

Thermal Desorption of Hydrocarbon Contaminated Soil How to Successfully Use this Technology. By Cal Faminow, CTech Thermal Desorption of Hydrocarbon Contaminated Soil How to Successfully Use this Technology By Cal Faminow, CTech Presentation Outline 1. Introduction 2. Site Summary 3. Assessment 4. Remedial Options

More information

Waste Management Plan

Waste Management Plan Boral Cement Limited Berrima Works Waste Management Plan Document Filename: Document Owner: Approved By: CMT-ENV-006 Berrima Waste Management Plan HSE Advisor, Berrima Works Operations Manager, Berrima

More information

ENVIRONMENTAL ASSESSMENT

ENVIRONMENTAL ASSESSMENT ENVIRONMENTAL ASSESSMENT Duralie Extension Project APPENDIX L PRELIMINARY HAZARD ANALYSIS GLOUCESTER COAL DURALIE EXTENSION PROJECT APPENDIX L PRELIMINARY HAZARD ANALYSIS NOVEMBER 2009 Document No. PHA-E.DOC

More information

Pollution Prevention: Private, commercial and military airfields.

Pollution Prevention: Private, commercial and military airfields. Pollution Prevention: Private, commercial and military airfields. The following notes are intended to give broad guidance on the potential for pollution at airfields and its prevention. 1. INTRODUCTION

More information

Surface water run-off from the operational areas has the potential to provide a pathway for contamination to reach the waters of Twofold Bay.

Surface water run-off from the operational areas has the potential to provide a pathway for contamination to reach the waters of Twofold Bay. Page 1 of 12 1. Background Australian Marshalling Services (AMS) conducts log storage and export activities on land controlled by NSW Maritime at William Allan Drive. The land occupied by this commercial

More information

CON APPENDIX C USAG HI Storm Water Pollution Prevention Plan Content Review Checklist

CON APPENDIX C USAG HI Storm Water Pollution Prevention Plan Content Review Checklist Con Appendix FINAL US Army Garrison, Hawaii October 2015 CON APPENDIX C USAG HI Storm Water Pollution Prevention Plan Content Review Checklist Storm Water Management Plan CON Appendix C U.S. Army Garrison-Hawaii

More information

Environmental Management Plan Introduction Environmental Management Objectives Structure, Implementation and Review

Environmental Management Plan Introduction Environmental Management Objectives Structure, Implementation and Review Environmental Management Plan Introduction This Environmental Management Plan (EMP) has been prepared for SEF Energy Co. Ltd. for the purpose of providing a stand-alone plan for managing the potential

More information

Water Pollution Control for Work in Sensitive Areas

Water Pollution Control for Work in Sensitive Areas Water Pollution Control for Work in Sensitive Areas 10-1. WATER POLLUTION CONTROL The Contractor is advised that failure to fully comply with the provisions of this Section, and all requirements listed

More information

METHOD STATEMENT. MVV O&M GmBH, South West Devon Waste Partnership & Kier Construction Limited. Document No: CMS/ E0788 /003 FOR

METHOD STATEMENT. MVV O&M GmBH, South West Devon Waste Partnership & Kier Construction Limited. Document No: CMS/ E0788 /003 FOR METHOD STATEMENT, South West Devon Waste Partnership & Kier Construction Limited Document No: CMS/ E0788 /003 FOR Construction of Bull Point Access Road DOCUMENT HISTORY DATE ISSUE COMMENTS ORIGINATOR

More information

EnviroLeg cc NATIONAL WATER Reg p 1

EnviroLeg cc NATIONAL WATER Reg p 1 EnviroLeg cc NATIONAL WATER Reg p 1 GN. 704 GG20119 4 June 1999 NATIONAL WATER ACT, 1998 (ACT NO. 36 OF 1998) REGULATIONS ON USE OF WATER FOR MINING AND RELATED ACTIVITIES AIMED AT THE PROTECTION OF WATER

More information

Pollution prevention (land and water)

Pollution prevention (land and water) 1 Purpose This document provides information on how to effectively manage pollutants for those working in Design, Construction and Maintenance activities. This guidance is to support the Level 2 Environment

More information

MANAGING STORMWATER. What you and your business need to know. Anything but rainwater down our stormwater drains pollutes our rivers and streams

MANAGING STORMWATER. What you and your business need to know. Anything but rainwater down our stormwater drains pollutes our rivers and streams MANAGING STORMWATER What you and your business need to know Anything but rainwater down our stormwater drains pollutes our rivers and streams MANAGING STORMWATER Did you know that Nelson City Council s

More information

IXPER 70C Calcium Peroxide CASE STUDY

IXPER 70C Calcium Peroxide CASE STUDY IXPER 70C INTRODUCTION TO ENHANCED AEROBIC BIOREMEDIATION Enhanced aerobic bioremediation is a well-established and viable remediation technology for in situ degradation of a variety of petroleum hydrocarbon

More information

Aberdeen Harbour Expansion Project. Construction Environmental Management Document

Aberdeen Harbour Expansion Project. Construction Environmental Management Document Aberdeen Harbour Expansion Project Construction Environmental Management Document 11th May 2017 Contents Chapter 1 Chapter 2 Chapter 3 Chapter 4 Chapter 5 Chapter 6 Chapter 7 Chapter 8 Chapter 9 Chapter

More information

UNDERGROUND OPERATION

UNDERGROUND OPERATION UNDERGROUND OPERATION Approved Mine Manager Date: Environmental Adviser Date: Integra Coal Underground ENVIRONMENTAL MANAGEMENT STRATEGY TABLE OF CONTENTS 1 GENERAL 5 C:\Users\oshan\AppData\Local\Microsoft\Windows\Temporary

More information

Hazardous Waste Management

Hazardous Waste Management Objectives EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Objective

More information

TECHNOLOGIES FOR BIOREMEDIATION OF SOILS CONTAMINATED WITH PETROLEUM PRODUCTS

TECHNOLOGIES FOR BIOREMEDIATION OF SOILS CONTAMINATED WITH PETROLEUM PRODUCTS TECHNOLOGIES FOR BIOREMEDIATION OF SOILS CONTAMINATED WITH PETROLEUM PRODUCTS Lecturer PhD., Roxana Gabriela POPA, University Constantin Brâncuși of Tg-Jiu, roxanna_popa@yahoo.com Associate Professor PhD,

More information

15A NCAC 02T.1501 is proposed for readoption without substantive changes as follows:

15A NCAC 02T.1501 is proposed for readoption without substantive changes as follows: 1 1 1 1 1 1 1 1 0 1 SECTION.0 SOIL REMEDIATION 1A NCAC 0T.1 is proposed for readoption without substantive changes as follows: 1A NCAC 0T.1 SCOPE The rules in this Section apply to the Disposal or Treatment

More information

JSP Construction Ltd CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN City Road Cardiff CF24 3BJ

JSP Construction Ltd CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN City Road Cardiff CF24 3BJ CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN JSP Construction Ltd 11-13 City Road Cardiff CF24 3BJ Revisions Issue Description Approved By Signed Date 19/10/16 1st issue AN JP 19.10/16 Rev A Updated with

More information

PEABODY ENERGY WILPINJONG COAL WASTE MANAGEMENT PLAN

PEABODY ENERGY WILPINJONG COAL WASTE MANAGEMENT PLAN PEABODY ENERGY WILPINJONG COAL WASTE MANAGEMENT PLAN WI-ENV-MNP-0030 - Version 1 January 2016 Table of Contents 1 Introduction 1.1 Definitions 1.2 Purpose 1.3 Scope 1.4 Consultation 2 Statutory Requirements

More information

RemActiv Concentrate: Bioremediation Enhancer

RemActiv Concentrate: Bioremediation Enhancer RemActiv Product Overview RemActiv Concentrate: Bioremediation Enhancer Z100-03 08/15 RemScan RemActiv Contents Features and Benefits... 3 Specifications... 4 Case Study RemActiv Trials successful for

More information

Appendix C3 Spill Prevention, Containment, and Countermeasures Plan Framework

Appendix C3 Spill Prevention, Containment, and Countermeasures Plan Framework Appendix C3 Spill Prevention, Containment, and Countermeasures Plan Framework THIS PAGE INTENTIONALLY LEFT BLANK TABLE OF CONTENTS C3.1 Purpose... C3-1 C3.2 Responsibility of Implementation... C3-2 C3.3

More information

Best Management Practices. Vehicle Wash Operations

Best Management Practices. Vehicle Wash Operations Best Management Practices Vehicle Wash Operations Prepared by the Canadian Petroleum Products Institute (CPPI) March 2004 STATEMENT OF DISCLAIMER No responsibility is accepted by CPPI or any of its members

More information

17 Non-mining Waste 17-1

17 Non-mining Waste 17-1 Non-mining Waste17 CONTENTS 17 Non-mining Waste 17-1 17.1 17.1 Introduction Introduction 17-1 17-1 17.2 17.2 Waste Waste 17-1 17-1 17.2.1 Regulatory Requirements 17-1 17.2.1 Regulatory Requirements 17-1

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN FOR MT MAGOMETON QUARRY

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN FOR MT MAGOMETON QUARRY POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN FOR MT MAGOMETON QUARRY EPA License No. 1152 Edition 1/Revision 0 Page i ABOUT THIS RELEASE: Document Number: Edition 1/Revision 0 Document Title: Coonamble

More information

Dendrobium Mine. Waste Management Plan

Dendrobium Mine. Waste Management Plan Dendrobium Mine Waste Management Plan DOCUMENT SIGN OFF SHEET AND REVISION LOG Document Owner: Authorised by: Peter McMillan 25/06/2018 (Name) (Date) Peter McMillan 25/06/2018 (Name) (Date) VERSION HISTORY

More information

Kurnell Refinery Conversion Project

Kurnell Refinery Conversion Project Kurnell Refinery Conversion Project Contamination Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site

More information

Resource Consent Application - Removal/Remediation of Flare/Blowdown Pit at Kapuni Well site KA2 for Shell Todd Oil Services Ltd

Resource Consent Application - Removal/Remediation of Flare/Blowdown Pit at Kapuni Well site KA2 for Shell Todd Oil Services Ltd 27 March 2012 Project No. 42780930 South Taranaki District Council Private Bag 902 Hawera, 4640 Attention: Blair Sutherland Dear Blair Subject: Resource Consent Application - Removal/Remediation of Flare/Blowdown

More information

MINING OPERATION SERVICES

MINING OPERATION SERVICES METROMIX PTY LIMITED Lower Level Management Plan Prepared in conjunction with: MINING OPERATION SERVICES SEPTEMBER 2016 CONTENTS Page COMMONLY USED ACRONYMS... 4 1 INTRODUCTION... 5 2 APPROVED ACTIVITIES...

More information

SOP-002 (OP) POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP)

SOP-002 (OP) POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) SOP-002 (OP) POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) 1. PURPOSE Renewable Oil Services is licensed to conduct waste processing of hazardous and other wastes using non-thermal treatment and

More information

(this cover page left intentionally blank)

(this cover page left intentionally blank) 4. Siting the Well (this cover page left intentionally blank) 4. Siting the Well Chapter Table of Contents Chapter Table of Contents Chapter Description... 4 Regulatory Requirements Well Siting... 4 Relevant

More information

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5B

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5B Oweninny Wind Farm Oweninny Environmental Impact Statement Appendix 5B Access Tracks, Hardstanding Areas, Electrical Compounds, Borrow Pit And Cable Laying Construction Method Statement Copyright ESB International

More information

Refer to Chapter 3.0 (Description of Development) for a detailed site and development description.

Refer to Chapter 3.0 (Description of Development) for a detailed site and development description. 7. WATER: HYDROGEOLOGY & HYDROLOGY 7.1 Introduction This chapter of the EIAR comprises of an assessment of the likely impact of the proposed development on the surrounding surface water and hydrogeological

More information

Environment Incident Identification & Response (Mining Areas)

Environment Incident Identification & Response (Mining Areas) Environment Incident Identification & Response (Mining Areas) Environment / Sustainability Toolbox Presentation Environment Management Series: EMS004 Key Information: Environment Incident Identification

More information

Wastewater Management Procedure Environment

Wastewater Management Procedure Environment 1 Purpose and Scope This procedure specifies the operational environmental requirements relating to the management of wastewater and the operation and maintenance of Roy Hill wastewater treatment plants

More information

ARDILL PAYNE & P a r t n e r s ABN:

ARDILL PAYNE & P a r t n e r s   ABN: ARDILL PAYNE & P a r t n e r s www.ardillpayne.com.au e:info@ardillpayne.com.au ABN: 51 808 558 977 POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Submission to: NSW Environment Protection Authority At: Lot

More information

Development Approval 211/93 (as modified) Schedule Condition Commitment Audit Finding

Development Approval 211/93 (as modified) Schedule Condition Commitment Audit Finding Independent Environmental Audit Bengalla Mine Development Approval 211/93 (as modified) Schedule Condition Commitment Audit Finding 3 1 The Applicant shall ensure that the noise generated by the development

More information

Contents OCCURRENCE ACTIONS AND COMMUNITY COMPLAINTS... 5 FIGURE 1 FIGURE 2. Quarterly. Spontaneous.

Contents OCCURRENCE ACTIONS AND COMMUNITY COMPLAINTS... 5 FIGURE 1 FIGURE 2. Quarterly. Spontaneous. Muswellbrook Coal Company Limited Contents 1 INTRODUCTION... 1 2 OCCURRENCE OF SPONTANEOUS COMBUSTION... 1 2.1 No.1 Open Cut... 2 2.2 No.2 Open Cut... 2 2.3 Monthly Treatment Capping, Mining and Water

More information

Temporary Erosion and Sediment Control (TESC) Report and Stormwater Pollution Prevention Plan For Construction Activities

Temporary Erosion and Sediment Control (TESC) Report and Stormwater Pollution Prevention Plan For Construction Activities Development Services 1775 12 th Ave. NW P.O. Box 1307 Issaquah, WA 98027 425-837-3100 issaquahwa.gov Temporary Erosion and Sediment Control (TESC) Report and Stormwater Pollution Prevention Plan For Construction

More information

FF-8 MINOR CONSTRUCTION

FF-8 MINOR CONSTRUCTION FF-8 MINOR CONSTRUCTION The matrix below identifies required activity-specific Minimum Designated Best Management Practices (BMPs) and Pollution Prevention Methods (PPMs) for Municipal Minor Construction

More information

Appendix 8. Petroleum Hydrocarbon Products, Ammonium Nitrate and Explosives Management Plan

Appendix 8. Petroleum Hydrocarbon Products, Ammonium Nitrate and Explosives Management Plan Appendix 8 Petroleum Hydrocarbon Products, Ammonium Nitrate and Explosives Management Plan Petroleum Hydrocarbon Products, Ammonium Nitrate, and Explosives Management Plan This Petroleum Hydrocarbon Products,

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN CONTENTS Introduction... 2 Scope... 3 Definitions... 3 Notification to the Authority... 3 High or Extreme Risk Environmental Hazards... 4 Contact Information... 4 Reporting and Notification Protocol...

More information

ACCIDENT PREVENTION & EMERGENCY RESPONSE

ACCIDENT PREVENTION & EMERGENCY RESPONSE Attachment J ACCIDENT PREVENTION & EMERGENCY RESPONSE Cadbury Ireland Limited Project Ref: OES1061_01 Cadbury Ireland Limited February 2007 Attachment J J.1 Accidental Emissions Control Accidental emissions

More information

RemScan. Real-Time Measurement of TPH in Soil

RemScan. Real-Time Measurement of TPH in Soil RemScan Real-Time Measurement of TPH in Soil Presentation Outline Real-Time Data What is RemScan? Application Benefits Case Studies Demand for Real-Time Data More data, increased confidence Real-time,

More information

Appendix F. Framework Storage and Handling of Hazardous Substances Sub-Plan

Appendix F. Framework Storage and Handling of Hazardous Substances Sub-Plan Appendix F Framework Storage and Handling of Hazardous Substances Sub-Plan F1 FRAMEWORK STORAGE AND HANDLING OF HAZARDOUS SUBSTANCES PLAN F1.1 INTRODUCTION During the construction and operation of the

More information

DURALIE COAL MINE WASTE MANAGEMENT PLAN

DURALIE COAL MINE WASTE MANAGEMENT PLAN DURALIE COAL MINE WASTE MANAGEMENT PLAN DISTRIBUTION SUMMARY Section/Page/ Annexure Revision Number Amendment/Addition Distribution DP&E Approval Date All A Original DP&I March 2011 All WMP-R02-A Edits

More information

4.0 Material and Waste Controls

4.0 Material and Waste Controls 4.0 Material and Waste Controls 4.1 Material and Waste Control Description: Chemical management addresses the potential for stormwater to be polluted with chemical materials and wastes that are used or

More information

Inrushes and Subsidence

Inrushes and Subsidence PURPOSE AND SCOPE... 2 DETAILS... 2 Appendices... 11 A Definitions... 11 B Related Documents... 11 C Revision Information... 11 1. Responsibility... 2 2. Hazard Management Process... 3 2.1 Overview...3

More information

14. Waste Management

14. Waste Management 14. Waste Management Contents 14. Waste 14-1 14.1. Introduction 14-1 14.2. Environmental Value 14-1 14.3. Waste Management Legislation 14-1 14.3.1. Waste Definition 14-1 14.3.2. National Pollutant Inventory

More information

R.H.J.North, P.Eng./P.Geo. Keystone Environmental Ltd Shellbridge Way Richmond, B.C. V6X 2W8

R.H.J.North, P.Eng./P.Geo. Keystone Environmental Ltd Shellbridge Way Richmond, B.C. V6X 2W8 THE FIRST CERTIFICATE OF COMPLIANCE FOR A MINE SITE IN BRITISH COLUMBIA BHP MINERALS CANADA LTD. ISLAND COPPER MINE R.H.J.North, P.Eng./P.Geo. Keystone Environmental Ltd. 250-10691 Shellbridge Way Richmond,

More information

In-Pit Tailing Storage Facility Management Plan

In-Pit Tailing Storage Facility Management Plan J.1 In-Pit Tailing Storage Facility Management Plan IN-PIT TAILINGS STORAGE FACILITY MANAGEMENT PLAN New Acland Coal Mine Stage 3 Project JANUARY 2014 Contents 1. Introduction 2 1.1. Overview 2 1.2. Purpose

More information

Mining Work Plan for the Scribante Concrete (Pty) Ltd Sand Mining Operation along the Inxu River

Mining Work Plan for the Scribante Concrete (Pty) Ltd Sand Mining Operation along the Inxu River Mining Work Plan for the Scribante Concrete (Pty) Ltd Sand Mining Operation along the Inxu River Page 1 of 11 Index Page 2 Objective Page 3 Applicant Details Page 3 Executive Summary Page 5 Figure 1, Locality

More information

CW 3170 EARTHWORK AND GRADING TABLE OF CONTENTS

CW 3170 EARTHWORK AND GRADING TABLE OF CONTENTS CW 3170 EARTHWORK AND GRADING TABLE OF CONTENTS 1. GENERAL CONDITIONS...1 3. DESCRIPTION...1 5. MATERIALS...1 5.1 General...1 5.2 Handling and Storage of Materials...1 5.3 Testing and Approval...1 5.4

More information

Pollution Incident Response Plan

Pollution Incident Response Plan Procedure Pollution Incident Response Plan Table of Contents Pollution Incident Response Plan... 2 1 Purpose & Scope... 2 2 Process... 2 2.1 Definition of Pollution Incident...2 2.2 Description and Likelihood

More information

TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION TECHNICAL SPECIFICATION ITEM 04821 TEMPORARY VEHICLE AND EQUIPMENT FUELING AREA PART 1 - GENERAL 1.01 Description Installation of erosion and sediment control for a temporary vehicle and equipment fueling

More information

Spill Response & Reporting Plan

Spill Response & Reporting Plan Spill Response & Reporting Plan The owners of believe strongly in proper control, storage and Company Name disposal of hazardous and non-hazardous waste. Whenever possible we will utilize the Washington

More information

Environmental Management Plan (EMP)

Environmental Management Plan (EMP) SE DELI GS DRIFT MI E ORA GE RIVER MI ES MI I G ACTIVITIES A D PROPOSED EW I PIT SLIMES DISPOSAL Environmental Management Plan (EMP) Compiled for: Namdeb Diamond Corporation (Pty) Ltd Compiled by: Unit

More information

55.3 AGGREGATE PRODUCTION AND STOCKPILING

55.3 AGGREGATE PRODUCTION AND STOCKPILING 55.3 AGGREGATE PRODUCTION AND STOCKPILING 55.3.1 GENERAL The Work covers the general requirements for production, gradation, stockpiling, and pit operations for specified aggregate materials. 55.3.2 AGGREGATE

More information

WAMBO COAL PTY LTD ENVIRONMENTAL ASSESSMENT. ATTACHMENT 2 Relevant Environmental Planning Instruments and Government Policies

WAMBO COAL PTY LTD ENVIRONMENTAL ASSESSMENT. ATTACHMENT 2 Relevant Environmental Planning Instruments and Government Policies WAMBO COAL PTY LTD NORTH WAMBO UNDERGROUND MINE LONGWALL 10A MODIFICATION ENVIRONMENTAL ASSESSMENT ATTACHMENT 2 Relevant Environmental Planning Instruments and Government Policies A2 PLANNING FRAMEWORK

More information

RULE 4651 SOIL DECONTAMINATION OPERATIONS (Adopted April 16, 1992; Amended December 17, 1992; Amended September 20, 2007)

RULE 4651 SOIL DECONTAMINATION OPERATIONS (Adopted April 16, 1992; Amended December 17, 1992; Amended September 20, 2007) RULE 4651 SOIL DECONTAMINATION OPERATIONS (Adopted April 16, 1992; Amended December 17, 1992; Amended September 20, 2007) 1.0 Purpose The purpose of this rule is to limit volatile organic compound (VOC)

More information

WAMBO COAL ENVIRONMENTAL MANAGEMENT STRATEGY

WAMBO COAL ENVIRONMENTAL MANAGEMENT STRATEGY WAMBO COAL ENVIRONMENTAL MANAGEMENT STRATEGY Document No. WA-ENV-MNP-501 March 2018 Document Control Document No. Title General Description Document Owner WA-ENV-MNP-501 Outlines the strategic context

More information

Environmental Control Plan

Environmental Control Plan Environmental Control Plan Environmental Control Plan In accordance with Watts & Hughes Construction Waikato Bay of Plenty Limited. corporate strategies the Company has an Environment Control Plan which

More information

City of Dallas Contractor/Vendor/Consultant,

City of Dallas Contractor/Vendor/Consultant, ,. Adopted: December 1 2007 / Revised August 24, 2010 / Revision Number: 3 City Dallas City Dallas Contractor/Vendor/Consultant, In January 2005, the Dallas City Council adopted an Environmental Policy

More information

TDJV - Victorian Desalination Plant D&C Marine Area EMP - Environmental Inspection (Weekly Checklist) Week Commencing: Completed by:

TDJV - Victorian Desalination Plant D&C Marine Area EMP - Environmental Inspection (Weekly Checklist) Week Commencing: Completed by: D&C Marine Area EMP Attachment J2 Weekly Environmental Inspection Checklist TDJV - Victorian Desalination Plant D&C Marine Area EMP - Environmental Inspection (Weekly Checklist) Inspection of construction

More information