1 Asphalt Guidelines Courtney Rousseau, P.E. Lloyd Consulting Group, LLC
2 Objectives Review typical asphalt sections and other key components to ensure optimal material usage for your project Review hot mix asphalt (HMA) surface preparation and how to troubleshoot common issues prior to asphalt placement Understand the critical testing and quality control operations Explore various cost savings options for tight project budgets Image Source:
3 Materials Aggregate Base Angular crushed stone or gravel and well graded sand Proper subgrade preparation is critical Amend and compact to geotech. recommendations Slurry backfill on utility trenches Image Source: Tacking/Priming Tacking = between lifts Priming = atop aggregate base Image Source:
4 Materials (cont.) Base Course Max. aggregate size (MAS) ¾ 1 Leveling Course Variable thickness placement MAS no greater than the surface course Surface Course Set to all finished lines and grades Fine graded MAS ½ maximum Nominal 3/8 or smaller Minimum average 1 ½ thickness Absolute minimum 1 ¼ thickness **Exceptions allowable for some low volume, fine graded asphalt mixtures
5 HMA Mix Design Numerous mix design criteria (often looked over or trusted that manufacturer followed specifications correctly) Aggregate gradations Specific Gravity Asphalt Content Air voids Dust content Design specifications approved before and throughout production Source: ASBA Asphalt Guidelines
6 Ensuring the Best Product Qualified suppliers Approved and certified Strong track record Reliable point of contact Timely submittals Prior to and throughout construction Proper testing procedures Qualified technicians Follow and record quality control protocol Image Source:
7 Surface Preparation 1. Repair pavement failures and existing cracks 2. Grind or mill abutment edges to allow smooth transition 3. Evaluate the potential need for wedging 4. Clean the surface to be free of dirt, debris, dust, etc. 5. Scrape and treat oil or grease spots to prevent bleeding prior to applying tack coat 1) Sweep any excessive tack coat applications 2) Apply at rate as prescribed in the project specifications 6. Remove any moisture Source: MAG Standard Details **ALWAYS PERFORM WORK UNDER SUITABLE WEATHER CONDITIONS
8 Edge Transitions Synthetic Turf & Natural Grass Pavement Synthetic Turf Transition Landscaping Pavement Transition Landscaping Transition
9 Testing & Quality Control HMA material tests taken in the laboratory prior to mass manufacturing and throughout production Must complete submittal checklists required Temperature tests ensure HMA is between F Relative humidity Air void content <7 8% In place density testing taken every 400 tons or once daily Surface courses = % of Gmm Base/leveling courses = min. 92.0% of Gmm Base/leveling course joints = % individually, daily average of 98% Image Source: Google
10 Testing & Quality Control (cont.) Submit and follow an Asphalt Placement Work Plan to coordinate smooth execution of the work Record pertinent information throughout the project Temperatures, in place densities, rolling patterns, etc. Tolerances Base/leveling courses = 1/4 in 10 ft Surface course = 1/8 in 10 ft Ponding tolerances 1/8 in 10 ft
11 Cost Saving Opportunities In Place Asphalt Recycling Over 100M tons of recycled asphalt pavement (RAP) is used every year Many plants stockpile RAP for reuse Maximum 20% allowed in binder/base and leveling courses Maximum 15% allowed in surface course QC testing of RAP submitted to owner prior to mix design acceptance Estimated asphalt production cost categories. (source: FHWA)
12 Cost Saving Opportunities In Place Asphalt Recycling Benefits Reduce virgin aggregate and virgin asphalt binder needed Conserves energy/preserves resources Lower transportation costs/reduce haul off Challenges Potential existing contamination (must meet design specifications) Availability Tying into existing boundaries
13 Cost Saving Opportunities Manipulating Section Depths 1 Asphalt = 3 Asphalt Base Reduce high export costs from excavating for AB Image Source: Google
14 Questions? THANKS ASBA!
INDEX DESCRIPTION MATERIALS APPROVAL FOR BASE COURSE CONSTRUCTION MEASUREMENT PAYMENT 6
03005_Jan31_2018.pdf Page 1 of 6 INDEX Page 03005-1 DESCRIPTION 2 03005-2 MATERIALS 2 03005-3 APPROVAL FOR BASE COURSE 3 03005-4 CONSTRUCTION 3 03005-5 MEASUREMENT 6 03005-6 PAYMENT 6 03005_Jan31_2018.pdf
More informationSECTION 402 HOT MIX ASPHALT, HMA, PAVEMENT
SECTION 402 HOT MIX ASPHALT, HMA, PAVEMENT 402.01 Description. This work shall consist of one or more courses of HMA base, intermediate, or surface mixtures and miscellaneous courses for rumble strips,
More informationSECTION 402 PLANT MIX BITUMINOUS SURFACE LEVELING
SECTION 402 PLANT MIX BITUMINOUS SURFACE LEVELING 402.1 Description. This work shall consist of placing, spreading and compacting a bituminous mixture as shown on the plans or as directed by the engineer.
More informationStudent Services & Classroom Addition
SECTION 321216 - ASPHALT PAVING PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationItem 247 Flexible Base
Item Flexible Base 1. DESCRIPTION 2. MATERIALS Construct a foundation course composed of flexible base. Furnish uncontaminated materials of uniform quality that meet the requirements of the and specifications.
More informationItem 247 Flexible Base
Item Flexible Base 1. DESCRIPTION 2. MATERIALS Construct a foundation course composed of flexible base. Furnish uncontaminated materials of uniform quality that meet the requirements of the and specifications.
More informationSECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS
SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS The City of Blue Springs hereby adopts Section 2200 of the Kansas City Metropolitan Chapter of APWA Construction and Material
More informationROARING FORK & EAGLE VALLEY (RFEV) SECTION 4 ASPHALT MIXTURE REQUIRMENTS
ROARING FORK & EAGLE VALLEY (RFEV) SECTION 4 ASPHALT MIXTURE REQUIRMENTS DEFINITION OF TERMS Wherever the following abbreviations are used in the specifications or other Contract documents, the intent
More informationDraft Special Provision for. Asphalt Treated Permeable Base
Draft Special Provision for 1 0 1 0 1 Add the following new section: -0 ASPHALT TREATED PERMEABLE BASE (ATPB) (******) -0.1 Description Asphalt treated permeable base (ATPB) consists of a compacted course
More informationWarm Mix Asphalt (WMA) Guide Specification for Highway Construction
Warm Mix Asphalt (WMA) Guide Specification for Highway Construction Division 400 - Asphalt Pavements and Surface Treatments SECTION 4XX - WARM MIX ASPHALT (WMA) PAVEMENT Warm mix asphalt (WMA) is the generic
More informationSECTION ASPHALT PAVING
SECTION 32 1216 ASPHALT PAVING PART 1 - GENERAL 1.1 SUMMARY A. Includes But Not Limited To: 1. Prepare pavement sub-grade as described in Contract Documents to receive pavement base and paving. 2. Furnish
More informationSECTION ASPHALTIC CONCRETE PAVING
SECTION 02742 ASPHALTIC CONCRETE PAVING PART 1 GENERAL 1.1 SUMMARY A. Includes But Not Limited To 1. Prepare pavement sub-grade as described in Contract Documents to receive pavement base and paving. 2.
More informationasphalt (PWMA) processes in accordance with these Specifications. PWMA processes include organic 9
Proposed Special Provision for Description Section -0.1 is supplemented with the following: This Work shall consist of providing and placing one or more layers of plant-mixed porous hot mix asphalt (PHMA)
More informationSECTION ASPHALT PAVING AND SURFACING
SECTION 02500 ASPHALT PAVING AND SURFACING PART 1 - GENERAL 1.01 WORK INCLUDED A. Traffic control as required to divert vehicular and pedestrian traffic around construction. B. Spreading and compacting
More informationSECTION BITUMINOUS CONCRETE PAVEMENT
SECTION 321216 BITUMINOUS CONCRETE PAVEMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification
More informationCITY OF LETHBRIDGE SECTION INFRASTRUCTURE SERVICES Page 1 of 7 GRANULAR BASE PREP
INFRASTRUCTURE SERVICES Page 1 of 7 1.0 GRANULAR BASE AND SUB-BASE 1.1 DESCRIPTION.1 This section specifies requirements for supplying, producing, hauling placing and compacting processed gravel or quarried
More informationKU Medical Center 2018 PAVEMENT RESTORATION PROJECT Project No May 4, 2018
SECTION 321216 - ASPHALT PAVING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and General Requirements of the Contract apply to this Section. 1.2 SUMMARY A. Section Includes: 1. Cold milling of existing
More informationODOT District Pavement General Notes P401: ITEM PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN
P401: ITEM 254 - PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN P402: ITEM 254 - PAVEMENT PLANING, PORTLAND CEMENT CONCRETE, AS PER PLAN P403: ITEM 304 - AGGREGATE BASE, AS PER PLAN P404: DELETED P405:
More informationWork shall also include preparation and protection of subgrade, subbase and leveling course specific to PHMA/PWMA.
1 1 1 0 1 0 1 0 1 0 1-0 Hot Mix Asphalt -0.1 Description This Section is supplemented with the following: This Work shall also consist of providing and placing one or more layers of plant-mixed porous
More informationStanford University Facilities Design Guidelines SECTION SEAL COATS. C. Section : Traffic Striping and Pavement Markings
SECTION 32 12 36 SEAL COATS PART 1 GENERAL 1.1 RELATED WORK A. Section 31 10 00: Site Preparation B. Section 32 12 00: Flexible Paving C. Section 32 17 23 01: Traffic Striping and Pavement Markings 1.2
More informationDIVISION 32 EXTERIOR IMPROVMENTS
DIVISION 32 EXTERIOR IMPROVMENTS DIVISION 32 EXTERIOR IMPROVEMENTS PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions
More informationReclaimed Asphalt Pavement
Reclaimed Asphalt Pavement Roy Guevara CDOT Asphalt Pavement Program Rocky Mountain Asphalt Conference February 2010 Benefits of Using RAP Benefits of Using RAP Conservation of materials Benefits of Using
More informationINDIANA. So how do you make hot mix asphalt? Basics of HMA Pavement Performance. Basics of a Good Road Hot Mix Asphalt Pavement Materials Selection
Basics of a Good Road Hot Mix Asphalt Pavement Materials Selection Presented at 2004 Road School By M. Dudley Bonte March 10, 2004 Basics of HMA Pavement Performance Appropriate Specifications Adequate
More informationSPECIAL SPECIFICATION 3402 Reflective Crack Relief Interlayer (RCRI)
1993 Specifications CSJ 0451-02-023, etc. SPECIAL SPECIFICATION 3402 Reflective Crack Relief Interlayer (RCRI) 1. Description. This Item shall govern for the materials and construction requirements for
More informationA. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).
SECTION 32 12 16 ASPHALT CONCRETE PAVING PART 1 GENERAL 1.1 SCOPE OF WORK A. This Section specifies the requirements for placing a hot laid plant mix asphalt surface course upon either an asphalt stabilized
More informationStanford University Facilities Design Guidelines SECTION ASPHALT UNIT PAVING. A. ASTM C-33 Standard Specification for Concrete Aggregates.
SECTION 32 14 23 ASPHALT UNIT PAVING PART 1 GENERAL 1.1 DESCRIPTION Work Included: All labor, materials, appliances, tools, equipment, facilities, transportation, and services for and incidental to performing
More informationINDEX DESCRIPTION MATERIALS CONSTRUCTION MEASUREMENT PAYMENT 10
04060_Jan31_2018.pdf Page 1 of 12 INDEX Page 04060-1 DESCRIPTION 2 04060-2 MATERIALS 3 04060-3 CONSTRUCTION 4 04060-4 MEASUREMENT 8 04060-5 PAYMENT 10 04060_Jan31_2018.pdf Page 2 of 12 04060-1 DESCRIPTION
More informationTownline Road Middle Village Road then south 4800 feet.
05/10/2017 Townline Road Middle Village Road then south 4800 feet. Project: Project Stations: 0.91 miles of asphalt wedging and 2 inch HMA Paving, gravel 0+00 P.O.B. Middle Village Road shoulders, and
More informationSECTION ASPHALT CONCRETE
SECTION 02740 ASPHALT CONCRETE PART 1. GENERAL 1.01 SECTION INCLUDES A. Work includes but is not limited to the following: 1.02 RELATED SECTIONS 1. Provide all material, labor, and equipment to prepare
More informationSECTION EARTHWORK
SECTION 02200 EARTHWORK PART 1 - GENERAL 1.01 WORK INVOLVED A. Provide all labor, materials and equipment as required for all excavation, grading, providing borrow materials, hauling, placing and compacting
More informationA. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).
SECTION 32 01 16 ASPHALT OVERLAY PART 1 - GENERAL 1.1 SCOPE OF WORK A. This Section specifies the requirements for scarifying, grinding, sweeping and repair of existing asphalt concrete pavement to establish
More informationBASE CONSTRUCTION MATERIALS A Aggregate
BASE CONSTRUCTION 2211 AGGREGATE BASE 2211.1 DESCRIPTION This work consists of placing aggregate base. 2211.2 MATERIALS A Aggregate... 3138 Provide the class of aggregate as required by the contract. 2211.3
More informationReclaimed Asphalt Pavement (RAP)
Reclaimed Asphalt Pavement (RAP) 1 What is RAP An asphalt material removed from the road that is intended to be reused on the roadway. RAP could be used as base course material, shouldering material, and
More informationSECTION 503 TEMPORARY PAVEMENT RESTORATION
SECTION 503 TEMPORARY PAVEMENT RESTORATION 503-1 DESCRIPTION: This work consists of furnishing, placing, compacting, and maintaining a temporary pavement surface suitable for driving in accordance with
More informationIncreasing the Percentage of Recycled Hot Mix Asphalt. Rebecca McDaniel, NCSC Aggregate for a More Sustainable Environment, TRB January 11, 2009
Increasing the Percentage of Recycled Hot Mix Asphalt Rebecca McDaniel, NCSC Aggregate for a More Sustainable Environment, TRB January 11, 2009 Historically Reclaimed Asphalt Pavement (RAP) has been the
More informationSECTION ASPHALT PAVING
PART 1 - GENERAL 1.1 DESCRIPTION SECTION 32 12 16 ASPHALT PAVING SPEC WRITER NOTE: Delete or add information between // ---- // and any other items applicable to project. Any item added to the text shall
More informationITEM 404LVT (Low Volume Traffic) ASPHALT CONCRETE Revised June 5, 2015
Notes to Designers: ITEM 404LVT (Low Volume Traffic) ASPHALT CONCRETE Revised June 5, 2015 Here s what s new in this latest revision of 404LVT This revised specification includes the following changes:
More informationPlatinum Edition MMCD Supplemental Update Page 1 of 7
Platinum Edition MMCD Supplemental Update 2016-11-18 Page 1 of 7 Purpose of a Supplemental Update This Supplemental Update contains amendments to MMCD documents to correct errors and omissions that have
More informationSECTION FLEXIBLE PAVING
SECTION 321200 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. Include GENERAL CONDITIONS and applicable parts of Division 1 as part of this Section. B. Examine all Drawings and other Sections of the Specifications
More information2015 ACEC HMA Update. Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation
2015 ACEC HMA Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 2 5 15 Hot Mix Asphalt (HMA) Update Acceptance of HMA on Local Agency Projects HMA Quality Improvements
More informationSuperpave Design Guidelines for Using Hot-Mix Recycled Asphalt Pavement and Recycled Asphalt Shingles
APPENDIX H Superpave Design Guidelines for Using Hot-Mix Recycled Asphalt Pavement and Recycled Asphalt Shingles Recycling Hot-Mix Asphalt and Recycling Manufacturer Waste Asphalt Roofing Shingles General
More informationKU Design Guidelines APPENDIX II PERMEABLE BITUMINOUS PAVEMENT
PERMEABLE BITUMINOUS PAVEMENT PART 1: GENERAL 1.01. RELATED DOCUMENTS: A. Drawings and general provisions of Contract, including Special Requirements General Conditions and Division 1 Specifications Sections,
More informationSTANDARD SPECIFICATIONS JANUARY 2015 S-4 GRANULAR BASE and AGGREGATES TABLE OF CONTENTS
TABLE OF CONTENTS 4.01 SCOPE OF WORK... 1 4.02 RELATED DOCUMENTS AND REFERENCES... 1 4.03 MATERIALS... 1 4.04 GENERAL REQUIREMENTS... 2 4.05 HAULING AND PLACING... 5 4.05. COMPACTION... 5 4.06 COMPACTION
More informationSECTION BITUMINOUS CONCRETE PAVING
PART 1 GENERAL 1.1 SECTION INCLUDES: SECTION 02400 BITUMINOUS CONCRETE PAVING A. The intent of this specification section is to provide requirements for materials, equipment, and methods for constructing
More informationAggregate Specifications
Qualified Aggregate Technician Kentucky Specifications Aggregate Specifications State, FHWA, FAA, Contractor Kentucky Transportation Cabinet 107 Aggregate Size Designations Nominal Maximum Size The largest
More informationPRODUCT SPECIFICATIONS FOR CONIPUR ISP AN IMPERMEABLE POLYURETHANE BASE MAT STRUCTURAL SPRAY SYSTEM
PRODUCT SPECIFICATIONS FOR CONIPUR ISP AN IMPERMEABLE POLYURETHANE BASE MAT STRUCTURAL SPRAY SYSTEM PART 1 General 1.01 Work Included This work includes furnishing and installing an IAAF certified synthetic
More informationHOT MIX ASPHALT PAVEMENT
HOT MIX ASPHALT PAVEMENT PART 1 - GENERAL 1.01 SECTION INCLUDES A. Hot Mix Asphalt (HMA) Pavement B. Base Widening 1.02 DESCRIPTION OF WORK A. Includes the requirements for the construction of HMA surface,
More informationSECTION ASPHALT PAVING
SECTION 321216 ASPHALT PAVING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Hot-mix asphalt paving. 1.2 PRE-INSTALLATION MEETINGS A. Pre-installation Conference: Conduct conference at Project site.
More informationSPECIAL SPECIFICATION 3157 Cold Processed - Recycled Paving Material (RPM) for Use as Aggregate Base Course
1993 Specifications SPECIAL SPECIFICATION 3157 Cold Processed - Recycled Paving Material (RPM) for Use as Aggregate Base Course 1. Description. This Item, Cold Processed - Recycled Paving Material (RPM),
More information4-07 Asphalt Treated Permeable Base (ATPB)
1 1 0 1 0 1 Supplement Division with the following: (November 0,, APWA GSP) -0 Asphalt Treated Permeable Base (ATPB) -0.1 Description Asphalt treated permeable base (ATPB) consists of a compacted course
More informationAppendix D Roadway Construction Criteria and Testing Procedures Roadway Construction Criteria
Appendix D Roadway Construction Criteria and Testing Procedures Roadway Construction Criteria 1. All independent testing firm work required by this appendix shall be performed by firms on the current City
More informationNCAT PAVEMENT TEST TRACK
NCAT PAVEMENT TEST TRACK 1 REPLACEMENT SECTIONS Red Mill and Inlay New Mix Performance Sections (11) Blue Excavate and Install New Structural Sections (5) 2 RESEARCH SPONSORS (+ FHWA) 3 CHAIN OF COMMAND
More informationFULL DEPTH RECLAMATION
FULL DEPTH RECLAMATION PART 1 - GENERAL 1.01 SECTION INCLUDES Full depth reclamation of asphalt roadways 1.02 DESCRIPTION OF WORK Includes pulverizing and mixing of existing asphalt and underlying materials;
More informationITEM 340 DENSE-GRADED HOT-MIX ASPHALT (METHOD)
ITEM 340 DENSE-GRADED HOT-MIX ASPHALT (METHOD) 340.1. Description. Construct a pavement layer composed of a compacted, dense-graded mixture of aggregate and asphalt binder mixed hot in a mixing plant.
More informationAsphalt Pavement Recycling: US Experience. PSWNA Meeting Warsaw, Poland October 28, 2011
Asphalt Pavement Recycling: US Experience PSWNA Meeting Warsaw, Poland October 28, 2011 2 Rebecca S. McDaniel, PE, PhD Technical Director North Central Superpave Center Purdue University West Lafayette,
More informationQSD/ Anas Recycling Case Study
Qatar Branch QSD/ Anas Recycling Case Study Doha, March 2018 Encouraging the Use of RAP RAP is a valuable, high-quality material that can replace more expensive virgin aggregates and binders. The use of
More informationTRENDS IN RAP AND RAS USE:
TRENDS IN RAP AND RAS USE: BUILDING ON SUCCESS AND EXPANDING THE BOUNDARIES Rebecca S. McDaniel Arizona Pavements/Materials Conference November 13, 2013 2 BUILDING ON PAST SUCCESS Asphalt pavement is the
More informationNORTH HARRIS COUNTY REGIONAL WATER AUTHORITY. Section CEMENT STABILIZED BASE COURSE. 1. Foundation course of cement stabilized crushed stone.
PART 1 GENERAL 1.01 SUMMARY A. This section includes: Section 02712 1. Foundation course of cement stabilized crushed stone. 2. Foundation course of cement stabilized bank run gravel. 1.02 MEASUREMENT
More informationExpanded Usage. Developed Low Vol. Mix allowing 30% RAP Began allowing RAP in Superpave mixes
The IDOT Update RAP Improvements Expanded Usage Developed Low Vol. Mix allowing 30% RAP 2000 Began allowing RAP in Superpave mixes 2002 Worked w/ Dist 1 & Industry to improve RAP to expand usage Quality
More informationSPECIAL SPECIFICATION 3032 Reflective Crack Relief Interlayer (RCRI)
2004 Specifications CSJ 0197-02-097 SPECIAL SPECIFICATION 3032 Reflective Crack Relief Interlayer (RCRI) 1. Description. Produce and place a Reflective Crack Relief Bituminous Interlayer (RCRI) in one
More informationSPECIAL SPECIFICATION 3017 Reflective Crack Relief Interlayer (RCRI)
2004 Specifications CSJ 0027-12-130 SPECIAL SPECIFICATION 3017 Reflective Crack Relief Interlayer (RCRI) 1. Description. Produce and place a Reflective Crack Relief Bituminous Interlayer (RCRI) in one
More information7. Refer to Paragraph 3.08 for unit price adjustments.
Section 02741 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Surface course of compacted mixture of coarse and fine aggregates and asphaltic binder. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1. Payment
More informationChapter Eight. Minnesota Mix Specifications, Methods & Quality Control
Minnesota Mix Specifications, Methods & Quality Control Minnesota Mix Specifications, Methods & Quality Control This chapter of the Design Guide has been prepared to assist persons associated with designing
More informationWAPA Annual Conference December 1, Barry Paye, P.E. Wisconsin DOT
WAPA Annual Conference December 1, 2015 Barry Paye, P.E. Wisconsin DOT Projects Testing Successes Opportunities Next Steps Desire to improve the way we work with recycled materials Industry looking for
More informationB. Borrow: Satisfactory soil imported from off-site for use as fill or backfill.
SECTION 312000- EARTHWORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Special Conditions, apply to this Section. 1.2 SUMMARY This Section
More information.1 This section specifies the requirements for the supply of Superpave asphalt concrete paving.
INFRASTRUCTURE SERVICES PAGE 1 OF 31 1. GENERAL 1.1 Description.1 This section specifies the requirements for the supply of Superpave asphalt concrete paving..2 This specification describes the mix property
More informationSPECIFICATIONS FOR BONDED WEARING COURSE
SPECIFICATIONS FOR BONDED WEARING COURSE 1.0 DEFINITIONS The term Director [Superintendent, etc.] shall mean the Director of Public Works of the awarding authority. The term Designee shall mean an employee
More informationSection ASPHALTIC CONCRETE PAVEMENT
PART 1 GENERAL 1.01 SUMMARY Section 02741 This Section includes surface courses of compacted mixture of coarse and fine aggregates and asphaltic material. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1.
More informationPAVER PLACED SURFACE TREATMENT
PAVER PLACED SURFACE TREATMENT **From St. Johnsbury-Lyndon IM 091-3(50) DESCRIPTION. This work shall consist of applying a paver placed surface treatment, consisting of a warm polymer modified emulsified
More informationINDEX FOR SPECIFICATIONS FOR AGGREGATE FOR BITUMINOUS PAVEMENT SCOPE... 2
February 2017 No. 920(I) INDEX FOR SPECIFICATIONS FOR AGGREGATE FOR BITUMINOUS PAVEMENT 920. 1 SCOPE... 2 920. 3 MATERIALS 3.1 Source of Supply... 2 3.2 Aggregate Requirements... 2 3.3 Mix Design... 3
More informationOverlay Applications. Overlays and Asphaltic Surfaces. Base Conditions. Subgrade. Existing PCC Pavement. Base Course 7/6/2010
Overlay Applications Repair of existing surface Overlays and Asphaltic Surfaces Milling WisDOT/WAPA Asphalt Pavement Project Manager Training Rubblization June 2010 Base Conditions Mixtures to be placed
More informationProtect Your Pavement Asset Like the Rest! Is Pavement on your Radar Screen? Parking Lots & Low Volume Facilities
Pavement Rocky Mountain Asphalt Conference & Equipment Show Managing Parking Lot Pavements Preventive Maintenance and Rehabilitation Options Landscaping Roofing February 18, 2009 Denver, CO Presented by:
More informationCold-in-Place Recycling
Design Manual Chapter 5 - Roadway Design 5J - Pavement Rehabilitation Program 5J-2 Cold-in-Place Recycling A. General Cold-in-place recycling (CIR) is the process of recycling an asphalt pavement in-place
More information*Originating pavement shall be in accordance with FRICTION SURFACE AGGREGATE (D1), the most recently dated.
IL-4.75 Schaumburg Surface Friction Course: This work shall consist of constructing a 4.75 mm Hot- Mix Asphalt (HMA) surface friction course. Minimum lift thickness of this material shall be 1.0 inch.
More informationSUDAS Revision Submittal Form
SUDAS Revision Submittal Form Status Date: As of 5/18/2018 Topic: Cold-in-place recycling Manual: Design and Specs Manual Location: Design Section 5J-2; Spec Section 7090 Requested Revision: Reason for
More informationAsphalt Technology Division
Chandra Akisetty, Division Chief 443-572-5051 Rebeccah Smith, Assistant Division Chief Field Operations 443-572-5112 Robert Voelkel, Assistant Division Chief Laboratory 443-572-5113 Asphalt Additives Anti-Strip
More informationThinlay Definition Production Moisture Cold Feed Construction Tack Coat Paver Operation Compaction Temperature
Best Practices for Thin Lift Asphalt Production/Construction Thinlay Discussion Items Thinlay Definition Production Moisture Cold Feed Construction Tack Coat Paver Operation Compaction Temperature A LABAMA
More information.1 This section specifies the requirements for the supply of hot mix asphalt concrete paving.
INFRASTRUCTURE SERVICES PAGE 1 OF 28 1. GENERAL 1.1 Description.1 This section specifies the requirements for the supply of hot mix asphalt concrete paving..2 The work includes the supply of aggregates
More informationUtilization of RAP NORTH DAKOTA ASPHALT CONFERENCE APRIL 7, 2010 BISMARCK, ND. Ken Swedeen Dakota Asphalt Pavement Association
Utilization of RAP NORTH DAKOTA ASPHALT CONFERENCE APRIL 7, 2010 BISMARCK, ND Ken Swedeen Dakota Asphalt Pavement Association History Many recycled products have been utilized in HMA Glass Used Tires Roofing
More informationForeword... iii Table of Contents...v List of Figures...vii List of Tables...viii. Chapter 1 : Background...1
Foreword... iii Table of Contents...v List of Figures...vii List of Tables...viii Chapter 1 : Background...1 Introduction...1 Asphalt Mixtures... 2 Asphalt Binder Behavior... 2 Mineral Aggregate Behavior...
More informationHow to Select the Appropriate Pavement Rehabilitation Option. David Rettner, PE American Engineering Testing, Inc.
1 How to Select the Appropriate Pavement Rehabilitation Option David Rettner, PE American Engineering Testing, Inc. 2 Pavement Rehabilitation Selection Understanding the Problem 3 Pavement Assessment Pavement
More informationSECTION BITUMINOUS CONCRETE PAVING AND ATHLETIC SURFACING. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.
SECTION 321800 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting
More informationPAVEMENT REINFORCEMENT SYSTEM. GlasGrid TF. Installation Procedures SELF-ADHESIVE CRACK MITIGATION HIGH TENSILE STRENGTH UNIQUE PROTECTIVE COATING
PAVEMENT REINFORCEMENT SYSTEM GlasGrid TF Installation Procedures SELF-ADHESIVE CRACK MITIGATION HIGH TENSILE STRENGTH UNIQUE PROTECTIVE COATING 1 The installation manual sets general recommendations for
More informationMIDLAND COUNTY ROAD COMMISSION BID FORM
MIDLAND COUNTY ROAD COMMISSION BID FORM Sealed Proposals will be received at the office of the Board of Road Commissioners, County of Midland, at 2334 N. Meridian Road, Sanford, Michigan, 48657 until:
More informationITEM 252 IN-PLACE FULL DEPTH COLD FLEXIBLE PAVEMENT RECYCLING
AFTER NOVEMBER 1, 2008 ITEM 252 IN-PLACE FULL DEPTH COLD FLEXIBLE PAVEMENT RECYCLING 252.1 Description. This work shall consist of a stabilized base course composed of a mixture of the existing bituminous
More informationSECTION RIPRAP, BOULDERS, AND BEDDING
SECTION 31 37 00 RIPRAP, BOULDERS, AND BEDDING PART 1 GENERAL 1.01 SECTION INCLUDES A. The WORK includes excavation, grading, and installation of riprap, boulders, soil riprap, void-filled riprap, and
More informationFAA AC 150/ H Draft Principal Changes
FAA AC 150/5370-10H Draft Principal Changes 2018 Indiana Chapter ACPA Workshop Indianapolis, IN Gary L. Mitchell, P.E. Vice President American Concrete Pavement Association Credits Doug Johnson and Greg
More informationSECTION AGGREGATES
SECTION 32 05 00 AGGREGATES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Aggregate base 2. Engineered fill 3. Backfill 4. Fine filter aggregate (non-frost susceptible fill) 5. Riprap 6. Recreational
More informationPART 1 GENERAL 1.1 SUMMARY
SECTION 32 12 16 ASPHALT PAVING PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. This specification covers the furnishing of materials used in and the placement of the Asphaltic Concrete Surface Course
More information12/9/14. HMA Mix Design. Asphalt Mix Design. Volumetrics. HMA Mix Characteristics
Construction of Quality Hot Mix Asphalt Pavements - 1 Day Course HMA Mix Design Smooth Quite Ride Asphalt Mix Design Greg Harder, P.E. Asphalt Institute Regional Engineer Tully, NY Strength/ Stability
More informationMSCAA /04 ITEM P-219 RECYCLED CONCRETE CRUSHED AGGREGATE BASE COURSE DESCRIPTION MATERIALS
219-1.1 ITEM P-219 RECYCLED CONCRETE CRUSHED AGGREGATE BASE COURSE DESCRIPTION This item consists of a base course composed of crushed recycled concrete aggregate, crushed to meet a particular gradation,
More informationHOT MIX ASPHALT PAVEMENT
Section 700 - Hot Mix Asphalt Pavement HOT MIX ASPHALT PAVEMENT PART - GENERAL.0 SECTION INCLUDES A. Hot Mix Asphalt (HMA) Pavement B. Base Widening.0 DESCRIPTION OF WORK A. Includes the requirements for
More information2010 Midwestern Pavement Preservation Partnership Conference
2010 Midwestern Pavement Preservation Partnership Conference West Des Moines, Iowa October 27, 2010 Royce Fichtner, P.E. Field Engineer Asphalt Paving Association of Iowa Celebrating 55 Years! Celebrating
More informationSustainable Roadway Materials for the I-90 Project
Sustainable Roadway Materials for the I-90 Project Jay Behnke, P.E. S.T.A.T.E. Testing L.L.C. FHWA Tollway National Open House, August 20, 2013 Tollway Building GREEN Waste reduction work zone Striving
More informationThin Lift Overlays. Pavement Preservation 2/13/2013. Definition. A Maintenance Alternative
Thin Lift Overlays A Maintenance Alternative David R. Johnson, P.E. Regional Engineer Asphalt Institute Billings, Montana Definition A thin overlay, typically 3/4 to 1-1/2 inches thick, of a gap graded
More informationTHIN ASPHALT OVERLAYS FOR PAVEMENT PRESERVATION
THIN ASPHALT OVERLAYS FOR PAVEMENT PRESERVATION Why Thin Asphalt Overlays? Shift from new construction to renewal and preservation Functional improvements for safety and smoothness are needed more than
More informationCOLD IN PLACE RECYCLING
Sponsored by of New York COLD IN PLACE RECYCLING OVERVIEW What is Cold Recycling? Why Recycle? Types & Processes Candidate Selection Core Sampling Mix Design Economics WHAT IS COLD RECYCLING? Effective
More informationAsphalt Pavement Maintenance and Rehabilitation Strategies
Asphalt Pavement Maintenance and Rehabilitation Strategies 2016 CAPTG Workshop: How to Assess and Extend the Service Life of Airfield Pavements Presented by: Genevieve Long, P.E. Monday, September 19,
More informationTHIN ASPHALT OVERLAYS FOR PAVEMENT PRESERVATION
THIN ASPHALT OVERLAYS FOR PAVEMENT PRESERVATION Why Thin Asphalt Overlays? Shift from new construction to renewal and preservation Functional improvements for safety and smoothness are needed more than
More information