1 RESTORATION OF THE NORTHERN TIP OF MON LOUIS ISLAND Mobile Bay National Estuary Program Fowl River WMP Steering Committee May 19, 2015
2 Project Site / Background
3 Historical Maps (Note New Outlet ) 1889 Reference Map 1852 US Coast Survey
4 Source: Byrnes, M. R., Berlinghoff, J. L., & Griffee, S. F. (2013). Sediment Dynamics in Mobile Bay, Alabama: Development of an Operational Sediment Budget, Final Report.
5
6 Project Goals
7 Project Goals Stabilize the shoreline along the bay side of the northern tip of Mon Louis Island. Create/enhance aquatic, wetland, and upland habitats to the extent possible.
8 Investigations
9 Hydrographic and Topographic Survey
10 Geotechnical Investigations
11 Coastal Processes Evaluation
12 Alternatives Evaluation June 2014
13 Alternate Alignments for Shoreline Stabilization
14 Shoreline Stabilization Methods Alternative Breakwater / Living Shoreline Concepts Evaluated: Alternative 1 Alternative 2 Alternative 3 Continuous Rock Dike Breakwater Segmented Rock Dike Breakwaters Continuous OysterBreak TM Breakwater Selected Alternative - Continuous Rock Dike Breakwater
15 Justification for Alternative 1 - Continuous Rock Dike Breakwater: Tried and true measure for stabilizing shorelines in areas of high wave energy. Demonstrated longevity and durability. Aesthetics and public acceptance.
16 Sources of Fill for Marsh Creation Fowl River navigation channel sediments unsuitable Hauling by truck direct to site infeasible Transport and delivery to site by barge (mechanically unloaded) Beneficial use dredge material sites Commercial borrow sites Costs were estimated at ~$30 to $45 per cubic yard, and such fill sources were ruled out Sandier materials identified in surficial sediments at vibracore locations (SVB-7, 8, 9, and 10), and use of this area as a hydraulic dredging borrow source recommended.
17 Preliminary Design 50% Design Submittal August 2014
18
19 50% Design Features Fill Quantity (in place) Dredge Quantity Total Shoreline Stabilization Length Fill Area (Marsh Creation) 24,800 cubic yards 37,200 cubic yards 1,420 feet 4 acres
20
21 Permitting Considerations Pre-application meetings September-October 2014: Viability of proposed open water borrow site questioned. Additional evaluation of dredged material beneficial use sites as potential borrow sites requested. Evaluation of alternate transport and delivery methods suggested. Supplemental Evaluation of Alternatives Report issued February 2015.
22 Beneficial Use Dredge Material Areas Investigated
23
24 Comparison of Estimated Construction Costs Comparative Construction Cost Estimates With Contingencies Engineer s OPC Byrnewood Drive Staging Area (February 2015) $2,281,000 Engineer s OPC Open Water Borrow Alternate (August 2014) $1,654,000 Difference $ 627,000 Comparative Marsh Creation Construction Cost Estimates (Without Contingencies): Engineer s OPC February 2015 $ 1,092,100 Engineer s OPC August 2014 $ 552,000 Difference $ 540,100 For 4 acres of marsh creation: Engineer s OPC February 2015 Engineer s OPC August 2014 Difference $ 273,000 per acre $ 138,000 per acre $ 135,000 per acre
25 Combine MLI Restoration with Channel Maintenance Funding? Evaluation of Sediments from Fowl River Open Water Disposal Area (April 2015)
26 Combine MLI Restoration with Channel Maintenance Funding? Advantages: Mobilize one dredge for marsh creation fill and for channel maintenance dredging (cost savings) Environmental clearances already exist for Fowl River open water disposal area Potential impacts of open water borrow area hole (water quality, wave climate) avoided by replenishment with channel sediments
27 Supplemental Funding for Channel Dredging Requested April 2015; Approved May 2015 ($800,000)
28 Next Steps Regulatory Coordination and Permits Finalize Engineering Design Bidding and Procurement Construction Monitoring Timeline / Schedule
29 More Information? Thompson Engineering Emery Baya (251)
RESTORE Act Planning. Kyle Graham Executive Director CPRA. November 12, committed to our coast
RESTORE Act Planning Kyle Graham Executive Director CPRA November 12, 2014 committed to our coast committed to our coast Oil Spill Funds Allocated to Date NRDA - Early Restoration Project Name Basin Funded
More informationENVIRONMENTAL RESTORATION IN COASTAL MISSISSIPPI: MARSH RE-ESTABLISHMENT PROJECT HARRISON AND JACKSON COUNTIES, MISSISSIPPI
SECTION 404(b)(1) EVALUATION REPORT FOR THE SECTION 204 ECOSYSTEM RESTORATION PROJECT IN CONNECTION WITH CONSTRUCTION, OPERATION, OR MAINTENANCE DREDGING OF A FEDERALLY AUTHORIZED PROJECT ENVIRONMENTAL
More informationMs. Jenny Jacobson Mr. Justin McDonald. Delta Roundtable Five Rivers Delta Center June 17, 2015
Alabama Department of Conservation and Natural Resources Alabama-Mississippi Sea Grant Mobile Bay National Estuary Program U.S. Army Corps of Engineers, Mobile District Ms. Jenny Jacobson Mr. Justin McDonald
More informationMobile Bay National Estuary Program Project Implementation Committee Meeting
Mobile Bay National Estuary Program Project Implementation Committee Meeting Mobile Bay Interagency Working Group Activities Larry Parson U.S. Army Corps of Engineers, Mobile District February 18, 2016
More informationTampa Port Authority
McKay Bay Restoration (McKay Bay Mitigation Site and McKay Bay Dredge Hole Restoration) Tampa Port Authority 2014 AAPA Environmental Awards Competition June 2014 Contact: Andy Fobes, Director of Public
More informationRestore America s Estuaries October 24, 2012
Coordinating Dredged Material Management in the Pacific Coast s Largest Estuary with Construction of the Pacific Coast s Largest Tidal Wetland Restoration Project. Restore America s Estuaries October 24,
More informationDredging and Dredged Material Disposal Overview
Dredging and Dredged Material Disposal Overview Tim Welp Timothy.L.Welp@usace.army.mil 601.634.2083 The process of dredging consists of the following stages: - Excavation (loosening or dislodging) of the
More informationAPPENDIX C DESIGN & ENGINEERING
APPENDIX C DESIGN & ENGINEERING Study Authority. This study is authorized under Section 204 of the Water Resources Development Act of 1992, as amended. Study Description. This appendix presents the results
More informationTeam Member Affiliation WEDA Member Role
Summary: Dominion Cove Point LNG, LP (DCP) owns and operates the Cove Point Liquefied Natural Gas (LNG) Terminal (terminal), an LNG import terminal in Lusby, Maryland (Figure 1). The terminal includes
More informationPUBLIC NOTICE NO. FP13-AB03-05 August 30, 2013 CESAM-PD-EC JOINT PUBLIC NOTICE
DEPARTMENT OF THE ARMY MOBILE DISTRICT, CORPS OF ENGINEERS P.O. BOX 2288 MOBILE, ALABAMA 36628-0001 REPLY TO ATTENTION OF: JOINT PUBLIC NOTICE U. S. ARMY CORPS OF ENGINEERS, MOBILE DISTRICT AND FLORIDA
More informationCity of Ocean City Lagoon/Back Bay Dredging Town Hall Meeting
City of Ocean City Lagoon/Back Bay Dredging Town Hall Meeting Total Estimated Dredge Material required for North to South of the City 500,000 Cubic Yards of Dredge Material Includes: North to South of
More informationRiverine Sand Mining Scofield Island Restoration Project (BA-40)
Riverine Sand Mining Scofield Island Restoration Project (BA-40) Kenneth Bahlinger CPRA Project Manager Michael Poff CEC Project Engineer October 24, 2012 committed to our coast committed to our coast
More informationA World of Solutions
Project Goals Engineering, Economics, & Environmental Principles Minimization of execution risks Construction industry s highest standards Cost savings vs. conventional methods Consistency with Master
More informationContaminated sediment management in the U.S.
Contaminated sediment management in the U.S. Rebecca Gardner Anchor QEA, USA and Norway company logo comes here Contents Brief overview of beneficial use activities in the United States (U.S.) Relating
More informationExpedited Remediation of Coal Tar Containing Sediments: Design-to-Build Approach with a Beneficial Reuse
Expedited Remediation of Coal Tar Containing Sediments: Design-to-Build Approach with a Beneficial Reuse Mike Crystal Sevenson Environmental Services Kurt Paschl Beazer East Inc. Alan Fowler ARCADIS Presentation
More informationNew Haven Harbor, Connecticut Navigation Improvement Feasibility Study and Environmental Impact Statement
New Haven Harbor, Connecticut Navigation Improvement Feasibility Study and Environmental Impact Statement Public Informational Meeting NEPA Scoping 24 January 2017 Planning Division New England District
More informationCat Island Chain Restoration, Green Bay
Cat Island Chain Restoration, Green Bay Victoria Harris, UW Sea Grant January 27, 2005 Southern Green Bay historically provided diverse coastal wetland habitats for fish and wildlife Expansive emergent
More informationU. S. Steel Duluth Works - Spirit Lake Cleanup Plan FAQs
St. Louis River Area of Concern U. S. Steel Duluth Works - Spirit Lake Cleanup Plan FAQs Spirit Lake is a large, open area in the St. Louis River that has cultural, historical, and recreational significance
More informationNOTICE DATE: December 20, U.S. Army Corps of Engineers
US Army Corps of Engineers Memphis District Public Notice FILE NUMBER: MVM-2018-224 NOTICE DATE: December 20, 2018 Attn: Postmaster, Please Post Until EXPIRATION DATE: January 18, 2019 U.S. Army Corps
More informationDRAFT ENVIRONMENTAL ASSESSMENT AND SECTION 404(b)(1) EVALUATION
ENVIRONMENTAL ASSESSMENT AND SECTION 404(b)(1) EVALUATION MODIFICATION TO MOBILE HARBOR OPERATIONS AND MAINTENANCE ADDITION OF OPEN BAY THIN-LAYER DISPOSAL OPTION MOBILE COUNTY, ALABAMA A FEDERALLY AUTHORIZED
More informationLake Lou Yaeger Section 206 Study Aquatic Ecosystem Restoration
Lake Lou Yaeger Section 206 Study Aquatic Ecosystem Restoration Ashley Rasnic Michelle Kniep St. Louis District U.S. Army Corps of Engineers July 2, 2015 US Army Corps of Engineers Concerns Loss of lake
More informationSEPTEMBER 18, 2018 SUBMITTED TO: STATE OF NEW YORK DEPARTMENT OF STATE COASTAL ZONE MANAGEMENT PROGRAM
COASTAL ZONE MANAGEMENT CONSISTENCY DETERMINATION FOR THE IMPROVEMENT DREDGING OF THE NEW HAVEN HARBOR FEDERAL NAVIGATION PROJECT (NEW HAVEN, CONNECTICUT) SEPTEMBER 18, 2018 SUBMITTED TO: STATE OF NEW
More informationAppendix 1 CWA Section 404 Compliance Forms Section 404(b)(1) Guideline Short Form and Coastal Zone Consistency
Appendix 1 CWA Section 404 Compliance Forms Section 404(b)(1) Guideline Short Form and Coastal Zone Consistency HSC PDR for HSC Flare at Bayport Ship Channel Environmental Assessment This page left intentionally
More informationTHIS IS NOT A PAID ADVERTISEMENT. Public Notice. Public Notice No. CENAP-OP-R October 16, 2017
THIS IS NOT A PAID ADVERTISEMENT Public Notice Wanamaker Building 100 Penn Square East Philadelphia, PA 19107-3390 ATTN: CENAP-OP-R Public Notice No. Date CENAP-OP-R-2010-311-24 October 16, 2017 Application
More informationCESAM-RD-C April 24, 2013 PUBLIC NOTICE NO. SAM AFM JOINT PUBLIC NOTICE SAM AFM U.S. ARMY CORPS OF ENGINEERS
DEPARTMENT OF THE ARMY U.S. ARMY ENGINEER DISTRICT, MOBILE DISTRICT P.O. BOX 2288 MOBILE, ALABAMA 36628-0001 CESAM-RD-C April 24, 2013 PUBLIC NOTICE NO. SAM-2012-00731-AFM JOINT PUBLIC NOTICE SAM-2012-0731-AFM
More informationBeneficial Reuse of Dredged Sediments in the Middle Harbor Slip 1 Fill
Beneficial Reuse of Dredged Sediments in the Middle Harbor Slip 1 Fill Port of Long Beach Category: Environmental Enhancement Heather Tomley Director of Environmental Planning Port of Long Beach 4801 Airport
More informationBAPTISTE COLLETTE BAYOU NAVIGATION CHANNEL DEEPENING SECTION 203 FEASIBILITY STUDY
BAPTISTE COLLETTE BAYOU NAVIGATION CHANNEL DEEPENING SECTION 203 FEASIBILITY STUDY 2018 LOUISIANA TRANSPORTAION CONFERENCE February 28, 2018 Melissa Kennedy, PE AGENDA Project History Section 203 Feasibility
More informationCoastal Restoration and Protection Projects - SLFPA-East and Vicinity
Coastal Restoration and Protection Projects - SLFPA-East and Vicinity committed to our coast committed to our coast 2012 Master Plan Project Details 2012 Master Plan Projects in SLFPA-East Projects in
More informationMississippi Coastal Improvements Program (MsCIP) Comprehensive Barrier Island Restoration Plan
Mississippi Coastal Improvements Program (MsCIP) Comprehensive Barrier Island Restoration Plan BOEM Gulf of Mexico Sand Management Working Group October, 205 Justin McDonald, P.E. US Army Corps of Engineers
More informationEVALUATION OF SECTION 404(b)(1) GUIDELINES (SHORT FORM)
EVALUATION OF SECTION 404(b)(1) GUIDELINES (SHORT FORM) PROPOSED PROJECT: Matagorda Ship Channel Deficiency Study and Environmental Assessment (Nov 2017) 1. Review of Compliance (230.10(a)-(d)) A review
More informationDEPARTMENT OF THE ARMY CORPS OF ENGINEERS, MOBILE DISTRICT P.O. BOX 2288 MOBILE, AL
DEPARTMENT OF THE ARMY CORPS OF ENGINEERS, MOBILE DISTRICT P.O. BOX 2288 MOBILE, AL 36628-0001 CESAM RD-A April 15, 2018 PUBLIC NOTICE NO. SAM-2018-01191-DCH JOINT PUBLIC NOTICE U.S. ARMY CORPS OF ENGINEERS
More informationUpper Mississippi River Floodplain Island Restoration Details
Upper Mississippi River Floodplain Island Restoration Details Mississippi Makeover Meeting Citizens Advisory Group December 1, 2009 Hastings City Hall Community Room Scot Johnson Minnesota Department of
More informationEstuarine Restoration in San Francisco Bay: Design and Adaptive Management. Environmental Management of Enclosed Coastal Seas
Estuarine Restoration in San Francisco Bay: Design and Adaptive Management Environmental Management of Enclosed Coastal Seas August 31, 2011 Eric Jolliffe, Bill Brostoff, and Fari Tabatabai U. S. Army
More information2013 WEDA Environmental Excellence Award Deer Island Restoration Project U.S. Army Corps of Engineers, Mobile District
Award Category: Navigation Dredging 2013 WEDA Environmental Excellence Award Deer Island Restoration Project U.S. Army Corps of Engineers, Mobile District Project Summary: Deer Island is a 3.5-mile long
More informationAPPENDIX L PROJECT COST ESTIMATE
APPENDIX L PROJECT COST ESTIMATE GENERAL REEVALUATION REPORT (GRR) AND SUPPLEMENTAL ENVIRONMENTAL IMPACT STATEMENT (SEIS) FOR THE POPLAR ISLAND ENVIRONMENTAL RESTORATION PROJECT CHESAPEAKE BAY, TALBOT
More informationTHIS IS NOT A PAID ADVERTISEMENT. Public Notice. Public Notice No. CENAP-OP-R September 7, 2017
THIS IS NOT A PAID ADVERTISEMENT Public Notice Wanamaker Building 100 Penn Square East Philadelphia, PA 19107-3390 ATTN: CENAP-OP-R Public Notice No. Date CENAP-OP-R-2017-00042 September 7, 2017 Application
More informationThe USACE Dredged Material Management Decisions (D2M2) Tool
The USACE Dredged Material Management Decisions (D2M2) Tool DOTS Webinar Wednesday Jan 28, 2014 Presented by: Matthew Bates Matthew.E.Bates@usace.army.mil ERDC EL Risk and Decision Science Team Background
More informationGREAT KILLS HARBOR, STATEN ISLAND, NEW YORK FEDERAL NAVIGATION PROJECT MAINTENANCE DREDGING
Public Notice In replying refer to: Public Notice No. GREAT KILLS HARBOR FY13 Published: April 30, 2013, Expires: May 30, 2013 New York District 26 Federal Plaza New York, N.Y. 10278 ATTN: CENAN-OP-ST
More informationNew York- New Jersey Harbor Estuary. Lower Passaic River
Lower 8 Miles of the Lower Passaic River Focused Feasibility Study November 7, 2013 New York- New Jersey Harbor Estuary Lower Passaic River 2 Diamond Alkali Superfund Site: Contaminated with dioxins, PCBs,
More informationMay 4, Applicant: Lake Charles Harbor and Terminal District 150 Marine Street Lake Charles, Louisiana 70602
2011 Environmental Excellence Award Application May 4, 2011 Applicant: Lake Charles Harbor and Terminal District 150 Marine Street Lake Charles, Louisiana 70602 Contact: Mr. Channing Hayden, Jr. Director
More informationDredging Project Update
Dredging Project Update Fall 2009 Hadley SARATOGA WARREN Glens Falls Thompson Is. Dam Fort Miller Dam Northumberland Dam Schuylerville WASHINGTON Falls Bakers Falls Fort Edward Section 1 Section 2 Upper
More informationSECTION 404(b)(1) EVALUATION REPORT FOR THE FOR THE OPERATIONS AND MAINTENANCE OF THE FEDERALLY AUTHORIZED BILOXI HARBOR NAVIGATION PROJECT OTT BAYOU
SECTION 404(b)(1) EVALUATION REPORT FOR THE FOR THE OPERATIONS AND MAINTENANCE OF THE FEDERALLY AUTHORIZED BILOXI HARBOR NAVIGATION PROJECT OTT BAYOU HARRISON COUNTY, MISSISSIPPI I. PROJECT DESCRIPTION:
More informationProject Information. Pursuant to Section 404 of the Clean Water Act (33 U.S. Code 1344), notice is hereby given that
US ARMY Corps Of Engineers Little Rock District JOINT PUBLIC NOTICE CORPS OF ENGINEERS STATE OF ARKANSAS Application Number: 2014-00125 Date: July 22, 2014 Comments Due: August 18, 2014 TO WHOM IT MAY
More informationNewtown Creek. Restoration Ecology. February 6, 2014 John McLaughlin Director, Office of Ecological Services
Newtown Creek Restoration Ecology February 6, 2014 John McLaughlin Director, Office of Ecological Services Office of Ecological Services Mission Statement Statement To protect and improve the ecological
More informationUpper Mississippi River Floodplain Restoration Priorities in Pools 1, 2, 3, Upper 4 and Lower Vermillion River
Upper Mississippi River Floodplain Restoration Priorities in Pools 1, 2, 3, Upper 4 and Lower Vermillion River Minnesota Department of Natural Resources Interdivisional Meeting July 8, 2009 Lake City Area
More informationPublic Notice. Public Notice No. CENAP-OP-R June 19, 2017
Public Notice Wanamaker Building 100 Penn Square East Philadelphia, PA 19107-3390 ATTN: CENAP-OP-R Public Notice No. Date CENAP-OP-R-2017-178 June 19, 2017 Application No. In Reply Refer to: REGULATORY
More informationPROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM
PROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM Project Name: Essex Point Subdivision/Sellenriek Retention Project ID Number: 2-A Problem: The watershed above the Essex Point Subdivision
More informationPUBLIC NOTICE. Maintenance dredging with upland placement of dredged material Arthur Kill Road, Staten Island, Richmond County, New York
PUBLIC NOTICE US Army Corps of Engineers New York District Jacob K. Javits Federal Building New York, N.Y. 10278-0090 ATTN: Regulatory Branch In replying refer to: Public Notice Number: NAN-2018-00809-EKN
More informationU.S. Army Corps of Engineers Mobile District
U.S. Army Corps of Engineers Mobile District General Permit for Living Shorelines in Alabama Sandy P. Gibson Regulatory Specialist, Coastal Alabama Regulatory Division, Mobile District US Army Corps of
More informationMississippi Coastal Improvements Program A Comprehensive Plan for Coastal Resilience
Mississippi Coastal Improvements Program A Comprehensive Plan for Coastal Resilience 200 Coastal Resilience Symposium 26 May 200 US Army Corps of Engineers BUILDING STRONG Mississippi Coastal Improvements
More informationFORUM ON USE OF CAD CELLS IN NEWARK BAY VS. OFF-SITE DISPOSAL
FORUM ON USE OF CAD CELLS IN NEWARK BAY VS. OFF-SITE DISPOSAL July 22, 2014 New Jersey Institute of Technology 7/26/2014 Diamond Alkali Superfund Site Contaminated with dioxins, PCBs, pesticides, metals,
More informationPA-03. Honorable Mike Kelly. Pennsylvania 114th Congress. 3rd Congressional District. Miles
PA-03 Honorable Mike Kelly Pennsylvania 114th Congress 3rd Congressional District 2 3 & 1&& / 0 1, O&M, Erie Harbor 2, CG-CAP 204, Presque Isle Regional Sediment Management 3, CG, Presque Isle Shoreline
More informationReclamation Manual Design Data Collection Guidelines Chapter 5 Typical Design Data Package Template
Reclamation Manual The Introduction (Chapter 1) for these design data collection guidelines contains additional information concerning: preparing a design data collection request, design data collection
More informationWhere the Ocean Meets Land. Coastal Engineering
Where the Ocean Meets Land Coastal Engineering Photo credit : Rio Tinto Alcan Our Expertise MARINAS AND HARBOURS Design and repair of breakwaters Sedimentation and dredging studies Navigation guidelines
More informationU.S. ARMY CORPS OF ENGINEERS BUILDING STRONG LOS ANGELES DISTRICT
PUBLIC NOTICE U.S. ARMY CORPS OF ENGINEERS BUILDING STRONG LOS ANGELES DISTRICT APPLICATION FOR PERMIT Goat Canyon Sedimentation and Basin Maintenance Dredging Project Public Notice/Application No.: SPL-2005-02068-RRS
More informationDredged Material Management Categories for Tracking Beneficial Use
Dredged Material Management Categories for Tracking Beneficial Use by John L. Childs PURPOSE: Sediment dredged for navigation projects are relocated for either: (1) disposal; or (2) beneficial use. The
More informationENVIRONMENTAL IMPACT STATEMENT CLEVELAND HARBOR, CUYAHOGA COUNTY, OHIO DREDGED MATERIAL MANAGEMENT PLAN PUBLIC SCOPING INFORMATION PACKET
ENVIRONMENTAL IMPACT STATEMENT CLEVELAND HARBOR, CUYAHOGA COUNTY, OHIO DREDGED MATERIAL MANAGEMENT PLAN PUBLIC SCOPING INFORMATION PACKET March 16, 2006 ANNOUNCEMENT OF PUBLIC SCOPING MEETINGS The U.S.
More informationAppendix D 404(b) Analysis
Appendix D 404(b) Analysis Appendix D - Evaluation of Section 404(b)(1) Guidelines I. Project Description A. Location: Delaware Bay and New Jersey bayshore communities (Gandys Beach, Fortescue and Villas)
More informationAPPLICATION FOR 2013 WEDA ENVIRONMENTAL EXCELLENCE AWARD ENVIRONMENTAL DREDGING CATEGORY RIVER RAISIN AREA OF CONCERN PROJECT, MONROE, MICHIGAN
APPLICATION FOR 2013 WEDA ENVIRONMENTAL EXCELLENCE AWARD ENVIRONMENTAL DREDGING CATEGORY RIVER RAISIN AREA OF CONCERN PROJECT, MONROE, MICHIGAN SUMMARY The construction team of Environmental Restoration,
More informationHudson River Remedial Design Treatability Study Data Quality Objectives
Hudson River Remedial Design Treatability Study Data Quality Objectives USACE/USEPA/SMWG Joint Sediment Conference October 26-28, 2004 1 Hudson River: EPA Dredging Decision Remedy Decision (2/02 Record
More informationMobile Bay National Estuary Program Protecting Alabama s Most Valuable Resource
Mobile Bay National Estuary Program Protecting Alabama s Most Valuable Resource Roberta Swann, Director Mobile Bay National Estuary Program March 21, 2018 Regional Response Team The Mobile Bay Watershed
More informationAPPLICANT: Decatur Head Beach Association 1327 Decatur Head Drive Decatur Island Anacortes, WA Telephone: (425)
US Army Corps of Engineers Seattle District Joint Public Notice Application for a Department of the Army Permit and a Washington Department of Ecology Water Quality Certification and/or Coastal Zone Management
More informationTHIS IS NOT A PAID ADVERTISEMENT. Public Notice. Public Notice No. CENAP-OP-R September 20, 2018
THIS IS NOT A PAID ADVERTISEMENT Public Notice Wanamaker Building 100 Penn Square East Philadelphia, PA 19107-3390 ATTN: CENAP-OP-R Public Notice No. Date CENAP-OP-R-2018-0567-46 September 20, 2018 Application
More informationCoastal Science and Engineering Collaborative (CSEC) Overview
Coastal Science and Engineering Collaborative (CSEC) Overview 1 237 237 237 217 217 217 200 80 252 NNBF 200 119 174 200 Workshop 27.59 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 110 135 120 112
More informationJOINT PUBLIC NOTICE U.S. ARMY CORPS OF ENGINEERS AND STATE OF ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT
DEPARTMENT OF THE ARMY MOBILE DISTRICT, CORPS OF ENGINEERS P.O. BOX 2288 MOBILE, ALABAMA 36628-0001 REPLY TO ATTENTION OF CESAM-RD-A July 10, 2013 PUBLIC NOTICE NO. SAM-2013-00464-DEM JOINT PUBLIC NOTICE
More informationUpdates on EWN Activities and Opportunities: USACE, Galveston District (SWG)
Updates on EWN Activities and Opportunities: USACE, Galveston District (SWG) Coraggio Maglio Hydraulics and Hydrology Branch Chief USACE, Galveston District 26 July 2017 USACE SWG Mission and Area of Responsibility2
More informationPIANC Commission Working Group Report Reviews
PIANC Commission Working Group Report Reviews EnviCom Working Group report details Initial review: conclusion * If identified as potentially sensitive, please highlight the particular areas of potential
More informationStrategies for Implementing Regional Sediment Management: Using a Collaborative Approach to Implementing RSM Principles in Alabama
Strategies for Implementing Regional Sediment Management: Using a Collaborative Approach to Implementing RSM Principles in Alabama CEER 2014 New Orleans, Louisiana July 28, 2014 Carl Ferraro Biologist
More information30 DAY PUBLIC NOTICE MAINTENANCE DREDGING OF THE GUILFORD HARBOR FEDERAL NAVIGATION PROJECT GUILFORD, CONNECTICUT
US Army Corps of Engineers New England District 696 Virginia Road Concord, MA 1742-2751 Public Notice In Reply Refer to: Daniel Stenstream nae-pn-nav@usace.army.mil Programs/Project Management Division
More informationgeosystems for soil containment geotubes geocontainers geobags Marine Engineering Products TC Mirafi
geosystems for soil containment geocontainers geobags Marine Engineering Products TC Mirafi 1 Mirafi geosynthetics are used as integral components in the design and construction of a variety of marine
More informationCHAPTER 7. San Dieguito River Flooding Adaptation
CHAPTER 7 San Dieguito River Flooding Adaptation This chapter includes a range of adaptation measures to address vulnerabilities from flooding along the San Dieguito River, including the river valley,
More informationProcess to detemine the integrity of the Southern berm to support addition of dredge materials
1 2 ACT was contracted to support the City s 2015 dredging program. Initially, the team conducted a review of historic information and permits as well as a field inspection of the bay areas you may have
More informationPUBLIC NOTICE. A detailed description and plans of the applicant's activity are enclosed to assist in your review.
PUBLIC NOTICE US Army Corps of Engineers New York District Jacob K. Javits Federal Building New York, N.Y. 10278-0090 ATTN: Regulatory Branch In replying refer to: Public Notice Number: NAN-2016-00535-WOM
More informationHighland Lake Dredging Feasibility Study
Highland Lake Dredging Feasibility Study Final Report, September 2015 Prepared For: The Town of Highland Lake 612 Lakeshore Drive Oneonta, AL 35121 Prepared By: Tetra Tech 2110 Powers Ferry Road SE Suite
More informationComprehensive Barrier Island Restoration Plan
Mississippi Coastal Improvements Program (MsCIP) Comprehensive Barrier Island Restoration Plan 202 National Conference on Beach Preservation Technology February 0, 202 Justin McDonald, P.E. Lead Project
More informationAsharoken Coastal Storm Damage Risk Reduction Feasibility Study
Asharoken Coastal Storm Damage Risk Reduction Feasibility Study Megan Jadrosich Project Manager U.S. Army Corps of Engineers Project Progress New York District Public Update April 23, 2009 Outline Summary
More informationRESEARCH & DEVELOPMENT UPDATE
RESEARCH & DEVELOPMENT UPDATE 237 237 237 217 217 217 200 200 200 80 119 27 252 174.59 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 110 135 120 112 92 56 62 102 130 Patricia DiJoseph, PhD Harbors
More informationJanuary US Army Corps of Engineers Savannah District South Atlantic Division
ENVIRONMENTAL IMPACT STATEMENT APPENDIX T: US Fish and Wildlife Service Savannah National Wildlife Refuge Compatibility Determination SAVANNAH HARBOR EXPANSION PROJECT Chatham County, Georgia and Jasper
More informationTEXAS CITY CHANNEL DEEPENING A DESIGN-BUILD FIRST
TEXAS CITY CHANNEL DEEPENING A DESIGN-BUILD FIRST Larry A. Wise, P.E. 1 and Philip J. Burgmeier 2 ABSTRACT Chosen for its efficient delivery process, the Texas City Channel Deepening Project marks the
More information4. PLAN FORMULATION AND ALTERNATIVES DEVELOPMENT
4. PLAN FORMULATION AND ALTERNATIVES DEVELOPMENT Planning for Federal water resources projects constructed by the USACE is based on The Economic and Environmental Principles and Guidelines for Water and
More informationAshbridges Bay Erosion and Sediment Control Class EA: ABTP NLC Presentation June 17, 2013
Ashbridges Bay Erosion and Sediment Control Class EA: ABTP NLC Presentation June 17, 2013 Background Problem Identification Mid-1970 s: Ashbridge s Bay Park constructed Early 1980 s: Start of dredging
More informationBuffalo River Area of Concern Cleanup Public Meeting
Buffalo River Area of Concern Cleanup Public Meeting September 23, 2013 6:00 PM 8:00 PM Old First Ward Community Center 6:15 PM Opening Remarks Jill Jedlicka, Buffalo Niagara RIVERKEEPER John Morris, Honeywell
More informationSource Control Early Action Focused Feasibility Study
Source Control Early Action Focused Feasibility Study Engineering Presentation Scott E. Thompson, PE Malcolm Pirnie, Inc. Remedial Options Workgroup Meeting June 27, 2007 Outline Target Area Selection
More informationCHAPTER 7. San Dieguito River Flooding Adaptation
CHAPTER 7 San Dieguito River Flooding Adaptation This chapter includes a range of adaptation measures to address vulnerabilities from flooding along the San Dieguito River, including the river valley,
More informationAppendix I Cost Engineering Pigs Eye Lake Ramsey County, MN Section 204 DRAFT. Draft Feasibility Study Report with Integrated Environmental Assessment
Appendix I Cost Engineering Pigs Eye Lake Ramsey County, MN Section 204 Draft Feasibility Study Report with Integrated Environmental Assessment St. Paul District U.S. Army Corps of Engineers March 2018
More informationAddendum to Feasibility Study
Addendum to Feasibility Study Former Duluth Works and Spirit Lake Sediment Site Prepared for Great Lakes Legacy Act Partnership between United States Steel Corporation, United States, Environmental Protection
More informationDREDGING FOR BENEFICIAL USE
DREDGING FOR BENEFICIAL USE Linda S. Lillycrop Program Manager, Regional Sediment Management Program US Army Engineer Research and Development Center PIANC Inland Rivers, Ports and Terminals Annual Conference
More informationAPPENDIX A SECTION 404(B)(1) EVALUATION TYBEE ISLAND, GEORGIA SHORE PROTECTION PROJECT RENOURISHMENT
APPENDIX A SECTION 404(B)(1) EVALUATION TYBEE ISLAND, GEORGIA SHORE PROTECTION PROJECT 2014-2015 RENOURISHMENT U.S. ARMY CORPS OF ENGINEERS SAVANNAH DISTRICT JUNE 2014 This page intentionally blank. SECTION
More informationMid-Atlantic Contaminated Sediment Symposium: Navigating through Contaminated Sediments to Achieve our Vision of a World Class Harbor Estuary
Mid-Atlantic Contaminated Sediment Symposium: Navigating through Contaminated Sediments to Achieve our Vision of a World Class Harbor Estuary U.S. Army Corps of Engineers Lisa A. Baron 28 March 2012 US
More informationDOTS Webinar Thin Layer Placement
DOTS Webinar Thin Layer Placement By: Tim Welp, Coraggio Maglio, Trudy Estes, Damarys Acevedo-Acevedo http://el.erdc.usace.army.mil/thinlayer/ 30 July 2014 at 1 PM CDT US Army Corps of Engineers DOTS Request
More information30 DAY PUBLIC NOTICE MAINTENANCE DREDGING OF THE FEDERAL NAVIGATION PROJECT IN THE ROYAL RIVER, YARMOUTH, MAINE
PUBLIC NOTICE 696 Virginia Road Concord, MA 01742-2751 In Reply Refer to: Programs Project Management Division Email: nae-pn-nav@usace.army.mil Date: February 28, 2013 Comment Period Closes: April 1, 2013
More informationNotice No Closing Date: May 2, 2015
Public Notice U.S. Army Corps of Engineers Pittsburgh District In Reply Refer to Notice No. below US Army Corps of Engineers, Pittsburgh District 1000 Liberty Avenue Pittsburgh, PA 15222-4186 Application
More informationJ O I N T P U B L I C N O T I C E
J O I N T P U B L I C N O T I C E CHARLESTON DISTRICT, CORPS OF ENGINEERS 69A Hagood Avenue Charleston, SC 29403-5107 and THE S.C. DEPARTMENT OF HEALTH AND ENVIRONMENTAL CONTROL Office of Ocean and Coastal
More informationUpper Mississippi River Restoration:
Upper Mississippi River Restoration: Managing a Dual Purpose River for Fish and Wildlife Habitat Jeff Janvrin Wisconsin Dept. of Natural Resources Mississippi River Habitat Specialist Mud Lake HREP, Lower
More informationPUBLIC NOTICE. Figure 8 Beach Homeowners Association, Inc. C/o: Mr. David Kellam (Administrator) 15 Bridge Road Wilmington, North Carolina 28411
US Army Corps Of Engineers Wilmington District PUBLIC NOTICE Issue Date: June 29, 2016 Comment Deadline: August 1, 2016 Corps Action ID Number: SAW-2006-41158 All interested parties are herby advised that
More informationTHE U.S. ARMY CORPS OF ENGINEERS NEW ENGINEER MANUAL DREDGING AND DREDGED MATERIAL MANAGEMENT
THE U.S. ARMY CORPS OF ENGINEERS NEW ENGINEER MANUAL DREDGING AND DREDGED MATERIAL MANAGEMENT T. Welp 1, M. Palermo 2, and M. Landin 3 ABSTRACT The U.S. Army Corps of Engineers (USACE) has updated and
More informationTown of Duck North Carolina
Town of Duck North Carolina Town of Duck Shore Protection Project Photograph obtained by. (July 7, 2017). Beach Maintenance Plan August 2017 Updated September 2018 Prepared By:. 4038 Masonboro Loop Road
More informationNEW HAVEN HARBOR CONNECTICUT NAVIGATION IMPROVEMENT
NEW HAVEN HARBOR CONNECTICUT NAVIGATION IMPROVEMENT 255 255 255 237 237 237 0 0 0 217 217 217 163 163 163 200 200 200 INTEGRATED FEASIBILITY STUDY AND ENVIRONMENTAL IMPACT STATEMENT 131 132 122 PUBLIC
More informationUtilizing Dredge Material in Wetland and Estuarine Restoration. Bartholomew Wilson P.G. Delaware Center for the Inland Bays
Utilizing Dredge Material in Wetland and Estuarine Restoration Bartholomew Wilson P.G. Delaware Center for the Inland Bays Inland Bays Fringe Wetland Restoration Workgroup DNREC s Shoreline and Waterway,
More informationPUBLIC NOTICE. 696 Virginia Road Concord, MA
696 696 Virginia Road Concord, MA 01742-2751 PUBLIC NOTICE Comment Period Begins: July 28, 2015 Comment Period Ends: August 27, 2015 File Number: NAE-2014-259 In Reply Refer To: Phillip W. Nimeskern Phone:
More information