F. Impact on the Receiving Environment

Size: px
Start display at page:

Download "F. Impact on the Receiving Environment"

Transcription

1 F. Impact on the Receiving Environment Dredging is a necessity for the port to remain commercially active. However, over the past two decades the Port of Waterford has acquired numerous reports and investigations regarding the impact of this activity to ensure its potential impact on the local marine environment is minimal. Some of the reports included in Section E regarding the disposal site are pertinent to this Section regarding the greater environment. The relevant reports that should be referenced include: Benthic and Hydrographic Investigations in Waterford Harbour, September Attachment E.1(i); Photographic Survey of a Dredge Spoil Dump Site January Attachment E.1(v); Survey of Two Juvenile Lobster Release Grounds, January Attachment E.1(vi); Extracts from Environmental Impact of Dredging and Spoil Dumping, Delft H3544 Report, September Attachment E.1(vii); Environmental Impact of Annual Spoil Dumping at Sea off Hook Head, Delft Report H3822, March Attachment E.1(viii). Further to the above reports the following reports have also been compiled and included in Attachment F.1 as they provide further information regarding the impact on the local environment: Photographic Survey of a Mussel Bed located below Cheekpoint, Co. Waterford Pre and Post dredge surveys, Aquafact Ltd., Feb/March 2003; Extracts from Environmental Impact Assessment Section 4, Malone O Regan, February 1999; Cheekpoint Noise Level Reports; Duncannon Archaeological Status; 2013 Marine Sediment and Benthic Studies Report; 2013 Natura Impact Statement; Cheekpoint Monitoring Reports 2003 & 2013; Seasonal Restriction Report & Correspondence. Due to the substantial amount of information being provided the following table compiles the primary conclusion of all relevant reports included in Attachments E.1 and F.1. Anthony D Bates Partnership LLP 54 P a g e EPA Export :23:49:53

2 Report Benthic and Hydrographic Investigations in Waterford Harbour, 1989 Photographic Survey of a Dredge Spoil Dump Site Survey of Two Juvenile Lobster Release Grounds. Environmental Impact of Dredging and Spoil Dumping, Report H3544. Environmental Impact of Annual Spoil Dumping at Sea off Hook Head, Report H3822. Survey of Cheekpoint Mussel Bed, 2003 Extracts from Environmental Impact Assessment Section 4 Cheekpoint Noise Reports Duncannon Archaeological Status Conclusions it is most advisable that material to be dumped should be brought outside the line of Hook Head to Swines Head It is considered that the dredge material will have little impact on the fauna in the area as the bivalves will simply burrow their way upwards through the deposited sand..to dump up to 490,000m³ of dredge spoil would have little long term impact on the general environment within the dump site. This can be inferred from the coarse nature of the bottom sediments, the mobile nature of the bottom sediment, the removal of previously deposited fine sediments and the paucity of species recorded This area consists of a rich and diverse fauna and is typical of high-energy sites in this type of environment. There was no evidence in either the water column or settled to the bottom of fine sediments "The increases in suspended particulate matter (SPM) concentrations, as a result of the dredging and dumping activities are restricted to a local and temporal effect. The additional increases at various monitoring stations where (ecological) activities take place were computed for different model conditions It can be concluded that the additional increase in turbidity will have a negligible effect on the ecological functioning of the Suir". "that the effect of burial through continuous resuspension and subsequent sedimentation around the disposal site, also in this situation with more than one spoil dumping, is generally believed to be negligible. Some effect may be expected very close to the disposal site after several spoil dumpings" "Due to the general sedimentation pattern indicated by the models the herring spawning grounds area; at sea and the lobster release areas will not be affected at all by the redistribution of the dumped sand." The results of the qualitative surveys carried out on the mussel bed in Waterford Harbour would indicate that there was no significant difference in the mussel population between surveys. Please see included report for findings on the potential impacts on Human Beings, Flora and Fauna, Soils and Geology, Water, Air, Noise, Climate, Landscape, Cultural and Archaeological Heritage, Material Assets and NHA s, SPA s and SAC s. The estimated noise exposure is hours per year or less than 1% of the overall time. the noise from the dredging is similar to other passing shipping.. The measured noise levels from dredging activity at Cheekpoint are below the EPA guidelines both during the daytime and at night Comparison of the measured noise levels with the WHO: Guidelines for Community Noise broadly indicate compliance with the WHO noise levels Having considered all information supplied to date, the exclusion zone around the two wreck sites is working in that the depths over the two wreck sites appear to be maintaining its constant level. This suggests the seabed covering the two wrecks remains stable as the dredging activity is at such a remove as to prevent any direct or indirect impacts onto the wreck sites. We therefore have no issue with your application to have your maintenance dredging permit renewed. Anthony D Bates Partnership LLP 55 P a g e EPA Export :23:49:53

3 Report 2013 Marine Sediment and Benthic Studies Report 2013 Natura Impact Statement Cheekpoint Turbidity Monitoring Report 2003 Cheekpoint Turbidity Monitoring Report 2013 Seasonal Restriction Report & Correspondence Conclusions The dredging and disposal operations will disturb the benthic communities in the affected areas. The benthic communities in these areas are adapted to repeated disturbances by dredging and disposal and recovery begins almost immediately following the cessation of the activity. The proposed dredging and disposal operations will not negatively impact on the integrity of the Natura 2000 sites or their qualifying interests. High turbidity levels are shown to exist in the period of flood tide immediately before high water (HW) extending occasionally over high water. Turbidity values range from background values of zero to in excess of 700mg/l with elevated readings of about 100 to 300 mg/l under normal tidal conditions it is considered that naturally occurring turbidity elevations, induced by the flood tide, have a more significant and long term effect than periodic increased levels caused by dredging. Based on the data collected at the buoys upstream and downstream of the dredge site there appears to be no perceptible change in turbidity during dredging and no change in the water quality due to dredging. There appears to be no difference whether dredging occurs during a neap or spring tidal period. The naturally occurring variability in turbidity suggests that the ecosystem in this region is well adapted to high turbidity and high levels of resuspension and it is considered unlikely that dredging has any significant impact on the environment upstream and downstream of the dredge site. The area of dredging at Cheekpoint covers less than 1% of the total tidal limits; The width of the dredge box at Cheekpoint only accounts for approximately 12% of the channel width; The length of exposure from any potential suspended sediment from dredging is minimal with an average of two hours per day for a two week campaign at two campaigns a year; The evidence that suspended sediment is not a key factor in fish mortalities unless turbidity levels and exposure are vastly above those experienced during dredging using a trailing suction hopper dredger; Background turbidity levels at Cheekpoint regularly exceed those produced during dredging; Dissolved oxygen levels at Cheekpoint are not significantly affected due to dredging. Table 5 Primary Conclusions from Environmental Impact Reports compiled to date. These reports have comprehensively assessed the potential impact on the receiving environment for the current dredging characteristics (methodology, annual volumes, dump site), that have not changed in the past 17 years. During this period no claim has been made by any third party with regards to the environment being negatively affected. The Port has also considered whether the proposed works will comply with, or will not result in the contravention, of: The Water Framework Directive 2000/60/EC, The Marine Strategy Framework Directive 2008/56/EC, The Priority Substances Directive 2008/105/EC. Anthony D Bates Partnership LLP 56 P a g e EPA Export :23:49:53

4 These Directives have been considered in the production of the Natura Impact Statement and a brief comment potential impact and relevant supplementary information is provided here. As regards the Water Framework Directive (WFD), the proposed dredging works are an established pre-existing technique with no known effect on the local environment, including local river basins, or third parties. It is concluded that the proposed dredging will not cause a non-temporary deterioration in status at water body level or otherwise affect the ability of the water body to achieve either its WFD objectives or relevant water-related protected area objectives. Reports that should be referenced regarding sediment dispersion at the loading and dumping sites to substantiate this conclusion include: Dredging of Duncannon Bar - Environmental Impact of Dredging and Spoil Dumping, Report H3544, Deltares (Attachment E.1(viii)); 'WL Delft Hydraulics - Dredging of Suir and Barrow Rivers, Report H3822, Deltares, March 2001 (Attachment E.1(viii)); Cheekpoint Turbidity Monitoring Report 2003 & 2013 (Attachment F.1(vii)); Monitoring Report on Seasonal Restriction (Attachment F.1(viii)); The Marine Strategy Framework Directive (2008/56/EC) aims to achieve good environmental status of EU marine waters by 2021 and to safeguard the resource on which marine-related economic and social activities depend. The Port of Waterford is very conscience of the importance and value the local environment within its harbour limits contain. To reflect this view the port has undertaken periodic investigations to identify and protect the diverse species present, upon which marine related activities are based. Benthic Surveys were undertaken in 1989 and These reports recommend moving the previous dump site to its present location in order to protect a valuable diving area, used socially. Photographic surveys of the dumpsite were undertaken before and after the first dredging campaign using the current dumpsite in 1996 and subsequently again in This was followed by reports on both commercial mussel beds and lobster release areas to determine if the dredging activities were having any potential negative impact. A Benthic Survey was also carried out for the Natura Impact Statement undertaken for the Appropriate Assessment required for this application. This identifies the local species and determines that no significant impact is likely from the proposed dredging operations on the protected species or any commercially related species. Reference should be made to the following reports included in this submission: Benthic Survey 1989 (Attachment E.1(i)); Benthic Survey 1992 (attachment E.1(ii)); Survey of Two Juvenile Lobster Release Grounds (Attachment E.1(vi)); Cheekpoint Mussel Bed Survey(Attachment F.1(i)); Waterford Marine Sediment and Benthic Survey 2013(Attachment F.1(v)); Natura Impact Statement 2013 (Attachment F.1(vi)). The Priority Substances Directive sets environmental quality standards to help identify priority substances, and other pollutants, under the Water Framework Directive. The objective of this Directive is to establish common quality rules for chemical analysis and monitoring of water, sediment and biota carried out. As part of this application substantial physical and chemical analyses were undertaken as stipulated by the Marine Institute of Ireland. Radiological testing was also undertaken by Radiological Protection Institute of Ireland. The testing has not resulted in the Anthony D Bates Partnership LLP 57 P a g e EPA Export :23:49:53

5 highlighting of any parameter that could potentially negatively impact on the local water quality. The reports pertaining to the test results are available in Attachment B.1(ii). Anthony D Bates Partnership LLP 58 P a g e EPA Export :23:49:54

6 Attachment F.1(i): Cheekpoint Mussel Bed Surveys, Aquafact Ltd., Feb/March 2003 Note: Figures and Appendices available upon request if required. Anthony D Bates Partnership LLP 59 P a g e EPA Export :23:49:54

7 EPA Export :23:49:54

8 EPA Export :23:49:54

9 EPA Export :23:49:54

10 EPA Export :23:49:54

11 EPA Export :23:49:54

12 EPA Export :23:49:54

13 EPA Export :23:49:54

14 EPA Export :23:49:54

15 EPA Export :23:49:54

16 EPA Export :23:49:54

17 EPA Export :23:49:54

18 EPA Export :23:49:54

19 Attachment F.1(ii): Extracts from Environmental Impact Assessment Section 4, Malone O Regan, February 1999 Anthony D Bates Partnership LLP 60 P a g e EPA Export :23:49:54

20 EPA Export :23:49:54

21 EPA Export :23:49:54

22 EPA Export :23:49:54

23 EPA Export :23:49:54

24 EPA Export :23:49:54

25 EPA Export :23:49:54

26 EPA Export :23:49:54

27 EPA Export :23:49:54

28 EPA Export :23:49:54

29 EPA Export :23:49:54

30 EPA Export :23:49:54

31 EPA Export :23:49:54

32 EPA Export :23:49:54

33 EPA Export :23:49:54

34 EPA Export :23:49:54

35 EPA Export :23:49:54

36 EPA Export :23:49:54

37 EPA Export :23:49:54

38 EPA Export :23:49:54

39 EPA Export :23:49:54

40 EPA Export :23:49:55

41 EPA Export :23:49:55

42 EPA Export :23:49:55

43 EPA Export :23:49:55

44 EPA Export :23:49:55

45 EPA Export :23:49:55

46 EPA Export :23:49:55

47 EPA Export :23:49:55

48 EPA Export :23:49:55

49 EPA Export :23:49:55

50 EPA Export :23:49:55

51 EPA Export :23:49:55

52 EPA Export :23:49:55

53 EPA Export :23:49:55

54 EPA Export :23:49:55

55 EPA Export :23:49:55

56 EPA Export :23:49:55

57 EPA Export :23:49:55

58 EPA Export :23:49:55

59 EPA Export :23:49:55

60 EPA Export :23:49:55

61 EPA Export :23:49:55

62 EPA Export :23:49:55

63 EPA Export :23:49:55

64 EPA Export :23:49:55

65 EPA Export :23:49:55

66 EPA Export :23:49:55

67 EPA Export :23:49:55

68 EPA Export :23:49:55

Planning for Dredging and the Environment on the Tidal Thames

Planning for Dredging and the Environment on the Tidal Thames Planning for Dredging and the Environment on the Tidal Thames 1 INTRODUCTION This Information Note forms the final document in a set of three notes designed to inform berth operators and environmental

More information

Measured environmental impacts of dredging operations S.J. Priestley

Measured environmental impacts of dredging operations S.J. Priestley Measured environmental impacts of dredging operations S.J. Priestley Abstract Recent dredging operations in the port of Auckland, New Zealand were preceded by detailed environmental impact assessments.

More information

Spoil and Water. Irish Ports Association Conference Ciaran Callan Dublin Port Company. 26 th September 2008

Spoil and Water. Irish Ports Association Conference Ciaran Callan Dublin Port Company. 26 th September 2008 Spoil and Water Ciaran Callan Dublin Port Company Irish Ports Association Conference 2008 26 th September 2008 Disposal of Dredge Material: Regulation and Process of Application Requirement for disposal

More information

Poole Harbour Channel Deepening and Beneficial Use Review of Physical monitoring in Poole Bay Technical Note 1 WITHOUT PREJUDICE

Poole Harbour Channel Deepening and Beneficial Use Review of Physical monitoring in Poole Bay Technical Note 1 WITHOUT PREJUDICE 1. Introduction Poole Harbour Channel Deepening and Beneficial Use Review of Physical monitoring in Poole Bay Technical Note 1 WITHOUT PREJUDICE This technical note reviews the physical data that was collected

More information

RINGASKIDDY PORT REDEVELOPMENT

RINGASKIDDY PORT REDEVELOPMENT RINGASKIDDY PORT REDEVELOPMENT Further Information in accordance with Section 37F [1] Revisions to ENVIRONMENTAL IMPACT STATEMENT February 2015 The sole responsibility of this publication lies with the

More information

Draft Structure of the Environmental Report for the Spatial Offshore Grid Plan of the German Exclusive Economic Zone (EEZ) in the Baltic Sea 2013

Draft Structure of the Environmental Report for the Spatial Offshore Grid Plan of the German Exclusive Economic Zone (EEZ) in the Baltic Sea 2013 Draft Structure of the Environmental Report for the Spatial Offshore Grid Plan of the German Exclusive Economic Zone (EEZ) in the Baltic Sea 2013 1 Introduction 1.1 Legal Basis and Function of Environmental

More information

Water Quality in Cleveland Bay. Frequently Asked Questions

Water Quality in Cleveland Bay. Frequently Asked Questions Water Quality in Cleveland Bay Frequently Asked Questions 1 NATURAL WATER QUALITY IN CLEVELAND BAY What is turbidity and how does it relate to water quality? Turbidity is caused by particles suspended

More information

Kurnell Wharf Infrastructure Upgrade

Kurnell Wharf Infrastructure Upgrade Kurnell Wharf Infrastructure Upgrade Sediment and Water Quality Monitoring Program CALTEX REFINERIES (NSW) PTY LTD September 2013 Page 1 1 INTRODUCTION Caltex Refineries (NSW) Pty Ltd (Caltex) proposes

More information

Monitoring Plan for Dredging & Disposal Operations for Killybegs Harbour

Monitoring Plan for Dredging & Disposal Operations for Killybegs Harbour Monitoring Plan for for Killybegs Harbour Produced by AQUAFACT International Services Ltd On behalf of AQUAFACT INTERNATIONAL SERVICES LTD., 12 KILKERRIN PARK, GALWAY. www.aquafact.ie info@aquafact.ie

More information

WFD-compliant dredging and Article 4(7) A practical methodology with lessons for other sectors

WFD-compliant dredging and Article 4(7) A practical methodology with lessons for other sectors WFD-compliant dredging and Article 4(7) A practical methodology with lessons for other sectors Presentation by Jan Brooke*, Environmental Consultant 13 th June 2013 Prepared with Greg Whitfield, Environment

More information

Prepared by the National Parks & Wildlife Service of the Department of Arts, Heritage & the Gaeltacht

Prepared by the National Parks & Wildlife Service of the Department of Arts, Heritage & the Gaeltacht MARINE NATURA IMPACT STATEMENTS IN IRISH SPECIAL AREAS OF CONSERVATION A WORKING DOCUMENT APRIL 2012 Prepared by the National Parks & Wildlife Service of the Department of Arts, Heritage & the Gaeltacht

More information

ABP Southampton: Water Framework Directive Assessment Maintenance Dredging

ABP Southampton: Water Framework Directive Assessment Maintenance Dredging ABP Southampton ABP Southampton: Water Framework Directive Assessment Maintenance Dredging Report R.2264 August 2014 Page intentionally left blank 2 ABP Southampton ABP Southampton: Date: August 2014 Project

More information

Sand extraction Maasvlakte 2 Project: License, Environmental Impact Assessment and Monitoring.

Sand extraction Maasvlakte 2 Project: License, Environmental Impact Assessment and Monitoring. Sand extraction Maasvlakte 2 Project: License, Environmental Impact Assessment and Monitoring. Ad Stolk and Chris Dijkshoorn Ministry of Transport, Public Works and Water Management Rijkswaterstaat North

More information

Kurnell Wharf Infrastructure Upgrade

Kurnell Wharf Infrastructure Upgrade Kurnell Wharf Infrastructure Upgrade Sediment and Water Quality Management Plan 301015-03067 301015-03067-EN-REP-011 1 October 2013 Infrastructure & Environment Level 12, 141 Walker Street, North Sydney

More information

Appendix M. Criteria, Measures and Indicators for Effects Assessment

Appendix M. Criteria, Measures and Indicators for Effects Assessment Appendix M Criteria, Measures and Indicators for Effects Assessment Appendix M. Criteria, Measures and Indicators for Effects Assessment Objective 1: Naturalization Changes to Aquatic Habitat Disruption,

More information

Berth 9 Quay Extension Environmental Statement Non-Technical Summary

Berth 9 Quay Extension Environmental Statement Non-Technical Summary Berth 9 Quay Extension Hutchison Ports UK Ltd July 2013 Final Report 9Y0150 CONTENTS Page 1 PROJECT BACKGROUND 1 2 NEED FOR THE PROPOSED SCHEME 4 3 DESCRIPTION OF THE CONSTRUCTION PHASE 4 4 DESCRIPTION

More information

Conservation and Management of the Waddensea

Conservation and Management of the Waddensea Conservation and Management of the Waddensea Fred van der Vegte Europarc, Sept. 12, 2009 1 Kust - en Zeebescherming 2 4 IUCN WORLD HERITAGE NOMINATION THE WADDEN SEA (GERMANY/THE NETHERLANDS) Criterion

More information

Name Assessor or Approver Date

Name Assessor or Approver Date T: +44 (0)1224 295579 F: +44 (0)1224 295524 E: ms.majorprojects@gov.scot MARINE SCOTLAND LICENSING OPERATIONS TEAM S (MS-LOT) ASSESSMENT OF THE PROJECT S IMPLICATIONS FOR A DESIGNATED NATURE CONSERVATION

More information

Public Notice U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT

Public Notice U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT Public Notice U.S. Army Corps Permit Application No: SWG-2013-00147 Of Engineers Date Issued: 23 May 2017 Galveston District Comments Due: 23 June 2017 U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT

More information

Environmental Assessment Appendix H: Section 404(b)(1) Guidelines Evaluation. U.S. Army Corps of Engineers New York District

Environmental Assessment Appendix H: Section 404(b)(1) Guidelines Evaluation. U.S. Army Corps of Engineers New York District Environmental Assessment Appendix H: Section 404(b)(1) Guidelines Evaluation U.S. Army Corps of Engineers New York District January 2004 APPENDIX H SECTION 404(b)(1) GUIDELINES EVALUATION SECTION 404(b)(1)

More information

MAASVLAKTE 2. Tiedo Vellinga. Monitoring and Evaluation

MAASVLAKTE 2. Tiedo Vellinga. Monitoring and Evaluation EUDA WORKSHOP ON GREEN INNOVATIONS KEEP THE EUROPEAN DREDGERS AT GLOBAL LEADING EDGE WEDNESDAY 3RD NOVEMBER 2010, BRUSSELS MAASVLAKTE 2 Monitoring and Evaluation Tiedo Vellinga Director Environmental Monitoring

More information

PROPOSED WHARF AND DREDGING PROJECT RESOURCE CONSENT APPLICATIONS AND DESCRIPTION AND ASSESSMENT OF EFFECTS ON THE ENVIRONMENT: VOLUME 1

PROPOSED WHARF AND DREDGING PROJECT RESOURCE CONSENT APPLICATIONS AND DESCRIPTION AND ASSESSMENT OF EFFECTS ON THE ENVIRONMENT: VOLUME 1 PROPOSED WHARF AND DREDGING PROJECT RESOURCE CONSENT APPLICATIONS AND DESCRIPTION AND ASSESSMENT OF EFFECTS ON THE ENVIRONMENT: VOLUME 1 PREPARED FOR PORT OF NAPIER LTD NOVEMBER 2017 PROPOSED WHARF AND

More information

Maintenance Dredging 2015 Environmental Monitoring Report

Maintenance Dredging 2015 Environmental Monitoring Report Maintenance Dredging 2015 Environmental Monitoring Report 1208_001/1_Rev0 July 2015 P:\SouthernPorts\1208_PortAlbanyMaintDredging\001_OriginalScope\Reports\ReportFolder_EnvironmentalMonitoring\AlbanyPorts20

More information

Yes: Y No: N (a) (b) (c) (d) (a) (a) (b) (c) (d) (e)

Yes: Y No: N (a) (b) (c) (d) (a) (a) (b) (c) (d) (e) Checklist: 3. Hydropower Stations, Dams and Reservoirs (1) 1 Permits and Explanation 2 Pollution Control (1) EIA and Permits (2) Explanation to the Local Stakeholders Main Check s Have EIA reports been

More information

ENVIRONMENTAL ASSESSMENT REGISTRATION

ENVIRONMENTAL ASSESSMENT REGISTRATION ENVIRONMENTAL ASSESSMENT REGISTRATION PORT HARMON CHANNEL AND HARBOUR DREDGING Submitted to: Department of Environment Environmental Assessment Division May 2004 ENVIRONMENTAL ASSESSMENT REGISTRATION PORT

More information

PROJECT SUMMARY (6.)

PROJECT SUMMARY (6.) BUDAPEST UNIVERSITY OF TECHNOLOGY AND ECONOMICS DEPARTMENT OF HYDRAULIC AND WATER RESOURCES ENGINEERING PROJECT SUMMARY (6.) Institutional development of the hydromorphological monitoring of surface waters

More information

APPENDIX A SECTION 404(B)(1) EVALUATION TYBEE ISLAND, GEORGIA SHORE PROTECTION PROJECT RENOURISHMENT

APPENDIX A SECTION 404(B)(1) EVALUATION TYBEE ISLAND, GEORGIA SHORE PROTECTION PROJECT RENOURISHMENT APPENDIX A SECTION 404(B)(1) EVALUATION TYBEE ISLAND, GEORGIA SHORE PROTECTION PROJECT 2014-2015 RENOURISHMENT U.S. ARMY CORPS OF ENGINEERS SAVANNAH DISTRICT JUNE 2014 This page intentionally blank. SECTION

More information

APPENDIX R NAPIER PORT DRAFT WATER QUALITY MANAGEMENT PLAN

APPENDIX R NAPIER PORT DRAFT WATER QUALITY MANAGEMENT PLAN APPENDIX R NAPIER PORT DRAFT WATER QUALITY MANAGEMENT PLAN DRAFT Water Quality Management Plan Proposed Wharf and Dredging Project November 2017 Revision History Version Description Date Prepared By Approved

More information

Falmouth Marina Dredging - Environmental Impact Assessment

Falmouth Marina Dredging - Environmental Impact Assessment Falmouth Marina Dredging - Environmental Impact Assessment Environmental Statement Non-Technical Summary Hyder Consulting (UK) Limited 2212959 Firecrest Court Centre Park Warrington WA1 1RG United Kingdom

More information

European Sediments 1

European Sediments 1 European Sediments 1 SEDNET Network Editors: Wim Salomons, Ulrich Förstner, Jos Brils Contact: Jos Brils (SEDNET coordinator): Brils@mep.tno.nl Contents 1. Introduction: Scope...1 2. European policies

More information

Water Quality Implication of a severn Barrage

Water Quality Implication of a severn Barrage Water Quality Implication of a severn Barrage by Reza Ahmadian, Bettina Bockelmann-Evans and Roger A. Falconer Hydro-environmental Research Centre School of Engineering, Cardiff University 1 General Challenges

More information

Trans-Tasman Resources Ltd consent application: Ecological monitoring

Trans-Tasman Resources Ltd consent application: Ecological monitoring Trans-Tasman Resources Ltd consent application: Ecological monitoring M.R. James 1, A. MacDiarmid 2 Prepared for Trans-Tasman Resources ltd January 2016 1 Aquatic Environmental Sciences Ltd PO Box 328

More information

FUNDY TIDAL ENERGY DEMONSTRATION PROJECT Environmental Effects Monitoring Report. APPENDIX A Environmental Impact Predictions

FUNDY TIDAL ENERGY DEMONSTRATION PROJECT Environmental Effects Monitoring Report. APPENDIX A Environmental Impact Predictions FUNDY TIDAL ENERGY DEMONSTRATION PROJECT Environmental Effects Monitoring Report APPENDIX A Environmental Impact Predictions 1 Environmental Impact Predictions - Fundy Tidal Energy Demonstration Project

More information

Part III will be filled out by all applicants applying for a permit to perform dredging.

Part III will be filled out by all applicants applying for a permit to perform dredging. INTRODUCTION AND INSTRUCTIONS ENVIRONMENTAL QUESTIONNAIRE FOR CORPS OF ENGINEERS PERMIT APPLICATIONS Philadelphia District, Corps of Engineers Philadelphia, Pennsylvania 19107 CENAP-OP-R The District Engineer

More information

Background Information Document

Background Information Document Environmental Impact Assessment (EIA) of the Proposed Development of Phosphate Deposits off the Coast of Namibia Background Information Document Note 1. This BID addresses the proposed activities within

More information

Estuaries, Sediments and Dredging

Estuaries, Sediments and Dredging Estuaries, Sediments and Dredging Professor Mike Elliott Mike.Elliott@hull.ac.uk Institute of Estuarine & Coastal Studies, University of Hull http://www.hull.ac.uk/iecs Antony et al., 2009, Ecol. & Society

More information

Appendix D 404(b) Analysis

Appendix D 404(b) Analysis Appendix D 404(b) Analysis Appendix D - Evaluation of Section 404(b)(1) Guidelines I. Project Description A. Location: Delaware Bay and bayshore communities (Pickering Beach, Kitts Hummock, Bowers Beach,

More information

ATTACHMENT E.2 EMISSIONS TO SURFACE WATERS SITE SERVICES LAYOUT SHEET 1 OF 2 (IE DR-0021)

ATTACHMENT E.2 EMISSIONS TO SURFACE WATERS SITE SERVICES LAYOUT SHEET 1 OF 2 (IE DR-0021) ATTACHMENT E.2 EMISSIONS TO SURFACE WATERS SITE SERVICES LAYOUT SHEET 1 OF 2 (IE0310818-30-DR-0021) SITE SERVICES LAYOUT SHEET 2 OF 2 (IE0310818-30-DR-0022) LOCATION OF EMISSION TO SURFACE WATER (IE0310818-22-DR-

More information

MARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT

MARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT MARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT The health of the world s oceans and marine life is degrading rapidly as a result of excess human activities.

More information

Notes for NEPA for Generic Terms of Reference

Notes for NEPA for Generic Terms of Reference TERMS OF REFERENCE IIRRIIGATIION AND WATER MANAGEMENT Notes for NEPA for Generic Terms of Reference This generic Terms of Reference (TOR) is applicable to the construction and/or the development of Irrigation

More information

European sediment regulations: Gaps and bridges

European sediment regulations: Gaps and bridges Sednet Conference, Venice 2004 European sediment regulations: Gaps and bridges Helge Bergmann Federal Institute of Hydrology Koblenz (Germany) Sednet 2004 Folie 1 Professional background contaminants in

More information

IN THE MATTER of the Resource Management Act 1991

IN THE MATTER of the Resource Management Act 1991 BEFORE THE NORTHLAND REGIONAL COUNCIL IN THE MATTER of the Resource Management Act 1991 AND IN THE MATTER APPLICATION of a resource consent application by The New Zealand Refining Company Limited under

More information

Project Review Application Form

Project Review Application Form Project Review Application Form Information supplied in this application may be made public during consultation with adjacent municipalities, First Nations groups and other interested parties, as well

More information

4.2 Take of Longfin Smelt

4.2 Take of Longfin Smelt 4.2 Take of Longfin Smelt Take estimation is based upon the likelihood of physical injury or mortality to individuals of longfin smelt. It is not possible to predict the number of individuals that would

More information

Appendix 6: Physical Oceanography. (Envirosphere 2009b)

Appendix 6: Physical Oceanography. (Envirosphere 2009b) Appendix 6: Physical Oceanography (Envirosphere 2009b) Oceanographic Survey, Oceanographic Measurements Salinity, Temperature & Turbidity, Minas Passage Study Site August 2008 March 2009 Submitted to:

More information

19. Summary of Impacts and Mitigation

19. Summary of Impacts and Mitigation 19. Summary of Impacts and Mitigation 19.1 The philosophy of the proposed Berth 201/202 works has been to meet the commercial need by avoiding and/or minimising environmental impacts where possible. For

More information

Cork County Development Plan Volume Three: SEA Statement and Natura Impact Report

Cork County Development Plan Volume Three: SEA Statement and Natura Impact Report Cork County Development Plan 2014 Volume Three: SEA Statement and Natura Impact Report 3 Volume 3: SEA Statement and Natura Impact Report Cork County Development Plan 2014 Contents Section 1 Strategic

More information

The TIDE Project: An overview. - Kirsten Wolfstein, Hamburg Port Authority -

The TIDE Project: An overview. - Kirsten Wolfstein, Hamburg Port Authority - The TIDE Project: An overview - Kirsten Wolfstein, Hamburg Port Authority - The main objective of estuarine management is to maintain and protect the natural ecology while safeguarding the delivery of

More information

Outline for. Protected Areas Management Planning

Outline for. Protected Areas Management Planning Outline for Protected Areas Management Planning Level One: Community-based protected area management organizations and Level Two: Conservation organizations / Non-governmental organizations Outline for

More information

Drainage systems and national plans agro-enviromental production perspective. Ministry of Agriculture Of Latvia

Drainage systems and national plans agro-enviromental production perspective. Ministry of Agriculture Of Latvia Drainage systems and national plans agro-enviromental production perspective Ministry of Agriculture Of Latvia 28.08.2013 Strategic/legal background At the EU level Thematic objectives defined in CSF Regulation

More information

Site Improvement Plan. River Kent SAC. Improvement Programme for England's Natura 2000 Sites (IPENS) Planning for the Future

Site Improvement Plan. River Kent SAC. Improvement Programme for England's Natura 2000 Sites (IPENS) Planning for the Future Improvement Programme for England's Natura 2000 Sites (IPENS) Planning for the Future Site Improvement Plan River Kent Site Improvement Plans (SIPs) have been developed for each Natura 2000 site in England

More information

Management-Planning for the Elbe Estuary

Management-Planning for the Elbe Estuary Natura 2000 Management-Planning for the Elbe Estuary Contents. Natura 2000-Managementplanning for the Elbe Estuary 1. EU Biodiversity Policy and Nature Legislation 2. Natura 2000 in the Elbe Estuary 3.

More information

Good Practice Guidance

Good Practice Guidance Good Practice Guidance Extraction by Dredging of Aggregates from England s Seabed April 2017 Summary Dredging of sand and gravel from the seabed is long established in England to secure material used as

More information

Guidance on the Classification of Ecological Potential for Heavily Modified Water Bodies and Artificial Water Bodies

Guidance on the Classification of Ecological Potential for Heavily Modified Water Bodies and Artificial Water Bodies Guidance on the Classification of Ecological Potential for Heavily Modified Water Bodies and Artificial Water Bodies UKTAG Guidance 31st March 2008 Document title UKTAG Guidance on the Classification of

More information

Sectoral Marine Plan for Wave and Tidal Energy in Scotland s Renewable Energy Zone. Strategic Environmental Assessment Screening and Scoping Report

Sectoral Marine Plan for Wave and Tidal Energy in Scotland s Renewable Energy Zone. Strategic Environmental Assessment Screening and Scoping Report Sectoral Marine Plan for Wave and Tidal Energy in Scotland s Renewable Energy Zone Strategic Environmental Assessment Screening and Scoping Report July 2011 CONTENTS Page 1. INTRODUCTION Background 1 Report

More information

An Introduction to the EU legislation on water. Title

An Introduction to the EU legislation on water. Title An Introduction to the EU legislation on water Subtitle Title Daniel Fernández Gómez Environmental Implementation Unit - E2 DG Environment, European Commission ASSOCIATION OF EUROPEAN ADMINISTRATIVE JUDGES

More information

SECTION 28 Environment Management Strategies

SECTION 28 Environment Management Strategies SECTION 28 Environment Management Strategies 28.0 Environmental Management Strategies 325 28.1 Introduction 325 28.2 Response to Submissions 325 28.2.1 28.2.2 28.2.3 28.2.4 28.2.5 28.2.6 28.2.7 28.2.8

More information

Screening for Appropriate Assessment Proposed residential development at Slievekeale, Waterford City. 13 April 2018

Screening for Appropriate Assessment Proposed residential development at Slievekeale, Waterford City. 13 April 2018 Proposed residential development at City 13 April 2018 NM Ecology Ltd Consultant Ecologists 276 Harold s Grange Road, Dublin 16 Website: www.nmecology.com Email: info@nmecology.com Tel: 087 6839771 Executive

More information

Annex C : Estuarine Classification Scheme for Scotland

Annex C : Estuarine Classification Scheme for Scotland Annex C : Estuarine Classification Scheme for Scotland Class Description Aesthetic Fish Migration Benthic Resident Persistent Water Chemistry Condition Community Fish Substances (Note 15) and/or Bioassay

More information

Scottish MPA Project Management options LOCHS DUICH, LONG AND ALSH POSSIBLE MPA

Scottish MPA Project Management options LOCHS DUICH, LONG AND ALSH POSSIBLE MPA Scottish MPA Project Management options LOCHS DUICH, LONG AND ALSH POSSIBLE MPA This is a working draft that has been produced to support initial discussions with stakeholders about management of activities

More information

Wellington Dock Planning Application, Liverpool. Non-Technical Summary for Environmental Statement

Wellington Dock Planning Application, Liverpool. Non-Technical Summary for Environmental Statement Wellington Dock Planning Application, Liverpool Non-Technical Summary for Environmental Statement INTRODUCTION United Utilities PLC (UU) has applied for planning permission for an extension to Liverpool

More information

Submission on the draft terms of reference for Balaclava Island Coal Export Terminal project

Submission on the draft terms of reference for Balaclava Island Coal Export Terminal project Submission on the draft terms of reference for Balaclava Island Coal Export Terminal project Name: Chantelle James Email: ccc@cqnet.com.au Michael Mc Cabe Organisation (if applicable): Capricorn Conservation

More information

Strategic Environmental Assessment (SEA) Scoping Report. May 2015

Strategic Environmental Assessment (SEA) Scoping Report. May 2015 Strategic Environmental Assessment (SEA) Scoping Report May 2015 TABLE OF CONTENTS 1 INTRODUCTION... 1 1.1 STRATEGIC ENVIRONMENTAL ASSESSMENT... 1 2 DESCRIPTION OF THE PROPOSED NWSMP... 2 2.1 RESPONSIBILITY

More information

1-52 WRANGELL NARROWS, ALASKA (CWIS NOS & 65015) Condition of Improvement 30 September 2008

1-52 WRANGELL NARROWS, ALASKA (CWIS NOS & 65015) Condition of Improvement 30 September 2008 WRANGELL NARROWS 1-52 WRANGELL NARROWS, ALASKA (CWIS NOS. 72852 & 65015) Condition of Improvement 30 September 2008 AUTHORIZATION: (1) Rivers and Harbors Act, 3 March 1925 (House Doc. 179, 67th Congress,

More information

1E OF CLIMATE, LICENSING & RESOURCE USE

1E OF CLIMATE, LICENSING & RESOURCE USE This report has been cleared for submission to the Director by Senior Inspector Dr Karen Creed. 1E OF CLIMATE, LICENSING & RESOURCE USE INSPECTORS REPORT ON A DUMPING AT SEA PERMIT APPLICATION I Application

More information

PHYSICAL ENVIRONMENT MONITORING P LAN DRAFT

PHYSICAL ENVIRONMENT MONITORING P LAN DRAFT Aquatic Effects Monitoring Plan PHYSICAL ENVIRONMENT MONITORING P LAN DRAFT October 2012 POINTE DU BOIS SPILLWAY REPLACEMENT PROJECT Physical Environment Monitoring Plan DRAFT Report Prepared for October

More information

Natura 2000 and Hydropower. Hydropower and Fish Workshop Brussels 29 May, 2017

Natura 2000 and Hydropower. Hydropower and Fish Workshop Brussels 29 May, 2017 Natura 2000 and Hydropower Hydropower and Fish Workshop Brussels 29 May, 2017 Christina Pantazi European Commission DG Environment, Nature Protection Unit (D3) Hydropower and Natura 2000 Hydropower one

More information

LETTER F. City of Del Mar

LETTER F. City of Del Mar LETTER F City of Del Mar F-1 The comment provides introductory statements and does not raise a specific issue related to the adequacy of the EIR. Therefore, no specific response is provided. F-2 The assumption

More information

Implementation of Article 13 Marine Strategy Framework Directive For public consultation: 1 April 30 September 2015

Implementation of Article 13 Marine Strategy Framework Directive For public consultation: 1 April 30 September 2015 English Summary DRAFT Programme of Measures for the Marine Protection of the German Parts of the North Sea and the Baltic Sea Report according to section 45h(1) of the German Federal Water Act Implementation

More information

Impacts of Dredging and Reclamation to Benthic Primary Producer Habitat (BPPH)

Impacts of Dredging and Reclamation to Benthic Primary Producer Habitat (BPPH) Section 9.2 Impacts of Dredging and Reclamation to Benthic Primary Producer Habitat (BPPH) Section 9.2.1 The management goals for BPPH are to: Management Goals for BPPH Maintain the abundance, diversity,

More information

Policy, science, economics and culture at a crossroads: restoring the Deschutes River estuary

Policy, science, economics and culture at a crossroads: restoring the Deschutes River estuary Western Washington University Western CEDAR Salish Sea Ecosystem Conference 2018 Salish Sea Ecosystem Conference (Seattle, Wash.) Apr 4th, 2:15 PM - 2:30 PM Policy, science, economics and culture at a

More information

Conversion of Kurnell refinery to a fuel import terminal

Conversion of Kurnell refinery to a fuel import terminal Conversion of Kurnell refinery to a fuel import terminal Dr Jos Kusters 1 May 2014 AGENDA Background Kurnell site conversion Management of environmental and community impacts Operation as a terminal 2

More information

AMRUN Project Draft Maintenance Dredging Management Plan Port Independent Peer Review

AMRUN Project Draft Maintenance Dredging Management Plan Port Independent Peer Review AMRUN Project Draft Maintenance Dredging Management Plan Port Independent Peer Review Document Reviewed: Maintenance Dredge Management Plan - Port, Draft for Independent Review, 16 November 2017. Independent

More information

Water Quality and Pollution

Water Quality and Pollution Chapter 6 Water Quality and Pollution Guiding Principles: Chapter 4 details all the guiding principles relevant to the overall management of the Harbour. Whilst all should be given some consideration the

More information

This report has been cleared for submission to Director/Board by Patrick Byrne. Eve O'Sullivan, 22/09/ :27

This report has been cleared for submission to Director/Board by Patrick Byrne. Eve O'Sullivan, 22/09/ :27 This report has been cleared for submission to Director/Board by Patrick Byrne. Eve O'Sullivan, 22/09/2014 16:27 OFFICE OF CLIMATE, LICENSING & RESOURCE USE. INSPECTORS REPORT ON A WASTE WATER DISCHARGE

More information

19. INTERACTION OF IMPACTS

19. INTERACTION OF IMPACTS 19. INTERACTION OF IMPACTS 19.1 INTRODUCTION In addition to the requirement to describe the likely significant effects of the proposed development on the different elements of the environment, it is also

More information

6 SUMMARY OF CUMULATIVE AND INDIRECT EFFECTS 6.1 INTRODUCTION

6 SUMMARY OF CUMULATIVE AND INDIRECT EFFECTS 6.1 INTRODUCTION 6 SUMMARY OF CUMULATIVE AND INDIRECT EFFECTS 6.1 INTRODUCTION Cumulative and indirect effects result from the combined impacts of multiple projects / plans. Their consideration is important as the impacts

More information

ENVIRONMENTAL IMPACT ASSESSMENT (EIA) AND THE ENVIRONMENTAL IMPACT STATEMENT (EIS) 2.0 Developments requiring preparation of an EIS

ENVIRONMENTAL IMPACT ASSESSMENT (EIA) AND THE ENVIRONMENTAL IMPACT STATEMENT (EIS) 2.0 Developments requiring preparation of an EIS ENVIRONMENTAL IMPACT ASSESSMENT (EIA) AND THE ENVIRONMENTAL IMPACT STATEMENT (EIS) 1.0 Background 2.0 Developments requiring preparation of an EIS 3.0 The contents of an EIS 4.0 Exemption from the requirement

More information

Bonsall Creek Watershed Management Plan Gap Analysis

Bonsall Creek Watershed Management Plan Gap Analysis Bonsall Creek Watershed Management Plan Gap Analysis March 2015 Prepared by Gap Analysis Introduction The Bonsall Creek Watershed Management Plan provides a vision for water use in the watershed, including

More information

Environmental Performance Report Guideline EPB 453

Environmental Performance Report Guideline EPB 453 Environmental Performance Report Guideline September 2013 EPB 453 Ministry of Environment TABLE OF CONTENTS 1 DEFINITIONS 3 2 INTRODUCTION 5 2.1 Purpose 5 2.2 Legislation 5 2.2.1 Environmental Assessment

More information

International Association for Danube Research

International Association for Danube Research Cristina Sandu IAD, Romania, sanducri@yahoo.com Harald Kutzenberger IAD GS, Austria, kutzenberger@iad.gs Jürg Bloesch IAD, Switzerland, bloesch@eawag.ch International Association for Danube Research www.iad.gs

More information

Understanding Measures of Water Quality: Choosing the Appropriate Method for Permit Compliance

Understanding Measures of Water Quality: Choosing the Appropriate Method for Permit Compliance Understanding Measures of Water Quality: Choosing the Appropriate Method for Permit Compliance Shelly Anghera, Ph.D., Steve Cappellino and Andrew Martin September 7, 2012 WEDA Pacific Why does WEDA membership

More information

Dr. Claudette Spiteri

Dr. Claudette Spiteri Dr. Claudette Spiteri 1. General context Indicators MSFD & indicators 2. Indicator development Process Pan European Regional Seas National Content Descriptors Criteria Indicators Monitoring parameters

More information

Impact of marine traffic and dredging activities on resuspension and release of contaminants from sediments in the port of Antwerp

Impact of marine traffic and dredging activities on resuspension and release of contaminants from sediments in the port of Antwerp Impact of marine traffic and dredging activities on resuspension and release of contaminants from sediments in the port of Antwerp Hanne Hetjens 1, Johannes Teuchies 1, Ronny Blust 1, Agnes Heylen 2 1

More information

Issues in measuring and managing changes to the ecological character of the Western Port Ramsar Site as a result of climate change

Issues in measuring and managing changes to the ecological character of the Western Port Ramsar Site as a result of climate change presenter: Shelley Heron Issues in measuring and managing changes to the ecological character of the Western Port Ramsar Site as a result of climate change Western Port Bay Where is it? Ecological character

More information

Monitoring the River Crane Water Quality and Ecology 2016

Monitoring the River Crane Water Quality and Ecology 2016 Monitoring the River Crane Water Quality and Ecology 2016 Heathrow Airport uses specialist accredited consultants to monitor water quality and biological indicators in the River Crane, a tributary of the

More information

Section 404(b)(1) Evaluation

Section 404(b)(1) Evaluation Appendix B: Section 404(b)(1) Evaluation Lower Pool 2 Channel Management Study: Boulanger Bend to Lock and Dam No. 2 I. Project Description A. Location The proposed fill activities would occur between

More information

Objectives Implications / comments

Objectives Implications / comments Appendix 1: Environmental Protection Objectives Biodiversity UN Convention on Biological Diversity (1992) Bern Convention on the Conservation of European Wildlife and Natural Habitats (1979) Bonn Convention

More information

Water Framework Directive and EIA: our experience. Jo Murphy, MIEMA CEnv MCIM National Environmental Assessment Service (NEAS) 31 May 2012

Water Framework Directive and EIA: our experience. Jo Murphy, MIEMA CEnv MCIM National Environmental Assessment Service (NEAS) 31 May 2012 Water Framework Directive and EIA: our experience Jo Murphy, MIEMA CEnv MCIM National Environmental Assessment Service (NEAS) 31 May 2012 The plan Me: Aims & objectives of the Water Framework Directive

More information

Confirmation of Necessity of Environmental and Social Considerations Study

Confirmation of Necessity of Environmental and Social Considerations Study Confirmation of Necessity of Environmental and Social Considerations Study 1. Title of the Cooperation Project The Study on the Improvement of Pohnpei International Airport in the Federated States of Micronesia

More information

17 Activities in the Coastal Marine Area (CMA)

17 Activities in the Coastal Marine Area (CMA) 17 Activities in the Coastal Marine Area (CMA) Important note: For the purposes of the Resource Management Act 1991 (RMA), the Regional Coastal Plan comprises the general objective and policies of Chapter

More information

Immersed Tunnels in the Natural Environment

Immersed Tunnels in the Natural Environment Immersed Tunnels in the Natural Environment An information paper produced by the International Tunnelling and Underground Space Association Working Group 11 for Immersed and Floating Tunnels 00000-ITA-DOC-8P.indd

More information

determine the effect of the Proposed Development together with the other planned changes within defined areas of influence;

determine the effect of the Proposed Development together with the other planned changes within defined areas of influence; 14 SUMMARY OF CUMULATIVE AND INDIRECT EFFECTS 14.1 INTRODUCTION Cumulative and indirect effects result from the combined impacts of multiple projects / plans. Their consideration is important as the impacts

More information

A Risk Assessment Framework for Fisheries in Natura 2000 sites in Ireland. December 2013 Version 1.3

A Risk Assessment Framework for Fisheries in Natura 2000 sites in Ireland. December 2013 Version 1.3 A Risk Assessment Framework for Fisheries in Natura 2000 sites in Ireland December 2013 Version 1.3 1 Contents Introduction... 3 DPSIR Framework (Drivers, Pressures, States, Impacts, Responses)... 3 Components

More information

Fig. 1. Map for location

Fig. 1. Map for location The Asian Journal of Biology Education (2002) Number 1 3 Faculty of Education, Shiga University 2--1 Hiratsu, Otsu, 20-0862. Japan. Introduction Lake Biwa (Fig. 1) is the largest lake in Japan and one

More information

The following comment in the Scoping report for the marine component is quoted out of context and/or misinterpreted: Appendix 2A page 12 of 37:

The following comment in the Scoping report for the marine component is quoted out of context and/or misinterpreted: Appendix 2A page 12 of 37: Namibian Marine Phosphate (Pty) Ltd Page 1 of 8 Comments and Response Trail All the comments made on the Marine Scoping Report, are presented in the table below, along with responses indicating where and

More information

Monitoring, modelling and management of Irish Sea mussel stocks

Monitoring, modelling and management of Irish Sea mussel stocks Monitoring, modelling and management of Irish Sea mussel stocks Gavin Burnell Aquaculture and Fisheries Development Centre University College Cork Ireland The Shellfish Association of Great Britain, Annual

More information

Chatham Rock Phosphate. Chatham Islands. April 2013

Chatham Rock Phosphate. Chatham Islands. April 2013 Chatham Rock Phosphate Chatham Islands April 03 Who we are Chatham Rock Phosphate Golden Bay co started by us 006 Chris Castle - CEO Linda Sanders Comms director Toko Kapea and Adrian Wilson stakeholder

More information

MEMORANDUM PERTAINING TO THE PUBLIC CONSULTATION PROCESS FOR THE NORDSTREAM EXTENSION PROJECT

MEMORANDUM PERTAINING TO THE PUBLIC CONSULTATION PROCESS FOR THE NORDSTREAM EXTENSION PROJECT Stockholm, 5 June 2017 To: Naturvårdsverket, registrator@naturvardsverket.se Diarienummer NV-03441-13 Regarding: Nord Stream 2 MEMORANDUM PERTAINING TO THE PUBLIC CONSULTATION PROCESS FOR THE NORDSTREAM

More information

Chapter 6 Objective: Protect and Enhance the Environment

Chapter 6 Objective: Protect and Enhance the Environment Chapter 6 Objective: Protect and Enhance the Environment 55 Irish Water Water Services Strategic Plan - October 2015 Our Strategic Aims Ensure that Irish Water services are delivered in a sustainable manner

More information