Review of Xcel Energy's Metropolitan Emission Reduction Alternative Project

Size: px
Start display at page:

Download "Review of Xcel Energy's Metropolitan Emission Reduction Alternative Project"

Transcription

1 Review of Xcel Energy's Metropolitan Emission Reduction Alternative Project April 28, 2003

2 1.0 Introduction The Minnesota Public Utilities Commission (PUC) has begun its consideration of Xcel Energy s Metropolitan Emissions Reduction Project (MERP). During its March 27, 2003 meeting, the PUC asked for additional information about the Alternative project included in Xcel s July 2002 filing. In this report, the Minnesota Pollution Control Agency (MPCA) provides its analysis of Xcel s Alternative project. The Alternative project described by Xcel includes: Allen S. King, Bayport: Installation of new pollution control equipment to control sulfur dioxide, nitrogen oxides and particulate matter, boiler rehabilitation and life extension of generating equipment, with a modest increase in generation capacity of 12 percent. This project is identical in both Xcel s Proposal and in the Alternative. High Bridge, St. Paul: Installation of new pollution control equipment to control sulfur dioxide and particulate matter, and boiler modifications to lower nitrogen oxide emissions on Units 5 and 6, leaving Units 3 and 4 untouched. There is no increase in generating capacity. Riverside, Minneapolis: Installation of new pollution control equipment to control sulfur dioxide and particulate matter from Unit 8, along with a modification of the boiler to lower nitrogen oxide emissions. Rehabilitate the existing scrubber and fabric filter on Units 6 and 7 to reinstate sulfur dioxide and particulate control capabilities, and conduct boiler modifications to lower nitrogen oxide emissions. There is no increase in generating capacity. Minn. Stat. 216B.1692, Subd. 4. asks the MPCA to: Verify that the emission reductions project qualifies under Minn. Stat. 216B.1692, Subd. 1; Describe the projected environmental benefits of the proposed project; and Assess the appropriateness of the project. In addition to answering the above questions in this report, the MPCA is also to provide the PUC with answers to two questions posed under Minn. Stat. 216B.1692 Subd.5(c): Whether the project is needed to comply with new state or federal air quality standards; and Whether the emission reduction project is required as a corrective action as part of any state or federal enforcement action. In this assessment, Alternative refers to the set of alternative projects Xcel included in its filing. Proposal refers to Xcel s preferred project, the subject of the MPCA s December 2002 report. Analyses, definition of terms and concepts remains the same as previously described in the MPCA s December 2002 report. 1

3 2.0 Summary 2.1 Qualifying Projects The MPCA is unable to conclude whether the Alternative project, as presented in the July 2002 filing, qualifies under Minn. Stat. 216B The Alternative meets neither applicable new source review standards (best available control technology (BACT)), nor does the project result in emissions substantially lower than allowed by the new source performance standards for new coal-fired generating units, the first two conditions of Minn. Stat. 216B.1692, subd. (1)(3). Further, the MPCA is unable to conclude whether the Alternative meets the third condition of Minn. Stat. 216B.1692, subd. (1)(3) to qualify a project: that the project reduces emissions from current levels at a unit to the lowest cost-effective level when, due to the age or condition of generating unit, it would not be cost-effective to reduce the emissions to the levels required by new source review or new source performance standards. The MPCA is unable to make this conclusion because Xcel has not demonstrated that the Alternative reduces emissions to the lowest cost-effective level and has not provided any discussion or consideration of the age or condition of the plants. The MPCA has reviewed the Alternative project, and concludes that it is not needed to comply with new state or federal air quality standards, nor is the project required as a corrective action as part of a state or federal enforcement action. 2.2 Project Costs Because project costs are compared to the benefits of the Alternative project, project costs were reviewed to determine if they were in a reasonable range. The MPCA previously determined that the construction costs for the A.S. King rehabilitation project fall within a reasonable range as defined by similar projects conducted nationally. Additionally, the MPCA believes that the estimated cost for installing air pollution control equipment at High Bridge and Riverside are reasonable estimates for installing acid gas/fabric filters and making boiler modifications to reduce NOx emissions. However, the MPCA is concerned that the project costs of the Alternative may actually underestimate the total cost of retrofitting High Bridge and Riverside with air pollution control equipment. The cost estimates do not include plant rehabilitation, an activity the MPCA expects to be necessary to ensure the entire return on investment in air pollution control equipment is realized. In addition, the Alternative, if implemented, should also remedy the current coal management systems in place at the plants to minimize fugitive dust releases and improve the aesthetics. Project costs at these two plants do not include this activity. 2

4 2.3 Projected Environmental Benefits. The MPCA must describe the environmental benefits that result from the implementation of this project [Minn. Stat. 216B.1692, Subd 4 (2)]. These three plants emit significant amounts of pollution in the Twin Cities and Minnesota. The Alternative would reduce sulfur dioxide (SO 2 ) nearly as much as the Proposal. While the Alternative would substantially reduce nitrogen oxides (NOx) and particulate matter (PM10) emissions, the reductions are not nearly as large as the reductions of these pollutants in the Proposal. Instead of reducing carbon dioxide, carbon monoxide and lead as the Proposal does, the Alternative increases emissions of these pollutants. Finally, the Alternative makes no reductions in mercury emissions, unlike the significant reductions that would be achieved by the Proposal. The MPCA has examined the potential economic value of these emission changes by using the PUC s environmental externality values with adjustments for the likely length of time these plants are expected to be in service after the proposed upgrades and using a more appropriate discount rate. The resulting benefits are between $95 and $182 million net present value over a 30 year time period. This benefit estimate does not fully address health issues associated with power plant emissions, namely fine particles. It also does not consider the reduction in regional haze, acid rain, or ground level ozone. Xcel has not provided an estimate of the avoided costs related to the additional generating capacity and rehabilitation at the King plant in the Alternative. Using data presented relative to avoided costs of the Proposal, the MPCA estimates that the avoided cost of the Alternative project are approximately $110 million for the new capacity and $183 million for the refurbishment of King. 2.4 Appropriateness of the Project It is difficult to address the question of the appropriateness of the project since it is not possible at this time to determine whether the Alternative qualifies under Minn. Stat. 216B The MPCA has addressed its concern about the impact of emissions from old pwer plants extensively in its December 2002 submittal. It is a good and appropriate thing that the Alternative would apply emission controls at three old power plants. There will be significant health and environmental benefits. However, the MPCA has some concerns about the Alternative. First, the control technology proposed at High Bridge and Riverside does not represent state-of-the-art controls. It would seem appropriate, if new controls are to be applied, to use the best technology available. Second, the Alternative does not include plant rehabilitation at High Bridge and Riverside. 3

5 When comparing the Alternative to the Proposal, the MPCA concludes that the Proposal is the superior project. The Proposal has greater reductions of more pollutants, provides more local benefits, more new generating capacity, and more refurbished existing generating capacity. In addition, the Proposal appears to be more cost-effective than the Alternative. Another way to assess the costs and benefits of the Proposal and Alternative is to look at the costs per ton of pollutant reduced. This is an approach that is often used by EPA and states to analyze various control technology options for cost-effectiveness. The MPCA has conducted a preliminary assessment of the Proposal and Alternative to determine the cost per ton of pollutant removed for each option, included in Attachment 1. When comparing these two proposals in this manner, taking avoided costs into account, the Proposal shows a lower cost per ton of pollutant reduced than the Alternative proposal. This suggests the Proposal is more cost-effective than the Alternative. 4

6 3.0 Qualifying Projects Xcel has described an alternative project to its Proposal in Attachments 5, 6 and 7 of its July 26, 2002 filing. The project is described as follows: A. S. King The Alternative includes the identical work to A.S. King as the Proposal. A rehabilitation of the A.S. King plant in Bayport would add controls to significantly reduce emissions of SO 2, NO X and PM 10 while increasing the plant s capacity from 504 MW to 564 MW (a 60 MW increase in capacity). The King plant would continue to burn coal. The repowered plant would be functional in High Bridge At the High Bridge plant in St. Paul, located near the Mississippi River in downtown, Xcel s alternative is to continue operating all four existing coal-fired units, adding new air pollution control equipment to the electricity power generating units (Units 5 and 6) and leaving units 3 and 4 untouched. The new air pollution control equipment includes modifications to the combustion chamber to install low NOx burners, and the additional of spray drying to control acid gas emissions, followed by fabric filters to control particulate matter. Riverside In northeast Minneapolis, Xcel proposes to install air pollution control equipment on the existing boilers. The control equipment consists of rehabilitating the existing spray dryer absorber common to Units 6 and 7 (currently not used) to control SO2 emissions, as well as refurbishing the existing fabric filter to better control particulate matter. Boilers on Units 6 and 7 would have low-nox burners and/or over-fire air and boiler optimization software installed to control NOx emissions. Retrofitting Unit 8 at Riverside consists of installing a new spray dryer and fabric filter to control SO2 and particulate matter, keeping existing electrostatic precipitators (ESPs) inplace. NOx control consists of modifying the combustion air system to include over-fire air ports in this cyclone boiler. The MPCA is charged with determining whether proposals qualify for the cost recovery that is allowed under Minn. Stat. 216B This section evaluates each plant proposal to determine if it is a qualifying project. 3.1 Minn. Stat. 216B.1692 Subd. 1. Qualifying Projects. As discussed previously, projects that may be approved for the emissions reduction rate rider under this section must: 1) be installed on existing large electric generating power plants as defined under Minn. Stat. 216B.2421 subd. 2(1), that are located in the state and not subject to emission limitations for new power plants under the federal Clean Air Act; 5

7 The definition of a large power plant under Minn. Stat. 216B includes the following: Large energy facility means any electric power generating plant or combination of plants at a single site with a combined capacity of 50,000 kilowatts (50 MW) or more and transmission lines directly associated with the plant that are necessary to interconnect the plant to the transmission system; 2) not increase capacity by more than 10 percent or 100 megawatts, whichever is greater; This is a straightforward calculation of increased generating capacity over current facility generating capacity. 3) result in the existing power plant either: i) complying with applicable new source review standards under the federal Clean Air Act ; ii) emitting air contaminants at levels substantially lower than allowed for new facilities by the applicable new source performance standards under the federal Clean Air Act; or, iii) reducing emissions from current levels at a unit to the lowest cost-effective level when, due to the age or condition of the generating unit, the public utility demonstrates that it would not be cost effective to reduce emissions to the levels in item (i) or (ii). Clause (i) above, new source review (NSR), is a determination of whether a proposal meets the test of best available control technology (BACT). The requirement of clause (ii) requires the MPCA to determine whether a proposal meets New Source Performance Standards (NSPS) for new facilities. In proposing projects that meet neither of these requirements, clause (iii) requires a proposer to demonstrate that it is not cost-effective to meet clauses (i) or (ii). 3.2 Do the Projects Qualify Under Minn. Stat. 216B.1692 Subd 1? A.S. King The A.S. King plant is located in Bayport, Minnesota on the St. Croix River and has a net generating capacity of 504 MW. The MPCA determined in its original analysis of this project that it qualifies under Minnesota statute. Because the Alternative project and the original Proposal are identical for this plant, the project for A.S. King Alternative qualifies. 6

8 3.2.2 High Bridge Is it an existing large electric generating power plant as defined under Minn. Stat. 216B.2421 subd. 2 that is located in the state and not subject to emission limitations for new power plants under the federal Clean Air Act? The High Bridge plant is located between Shepard Road and the Mississippi River in downtown St. Paul. It has four boiler units, two dedicated to producing steam for a manufacturer and two for generating electricity. The electricity generating units, units 5 and 6, were brought online in 1956 and 1959 respectively. Unit 5 has the electricity generating capacity of 85 MW and Unit 6 has a capacity of 158 MW, for a total generating capacity of 243 MW. Because the facility is greater than 50 MW, it is a large generating station. The project meets this requirement of the statute. Does it increase capacity by more than 10 percent or more than 100 MW? There is no increased in electricity generation with the alternative. There is in fact a slight decrease in available electricity due to the parasitic load of the air pollution control equipment. Does the project propose best available control technology? Table 1 shows the current emission rates at the High Bridge plant and the emission rates that would result from Xcel s Alternative project with BACT determinations for similar plants and the NSPS for new coal-fired power boilers. 7

9 Table 1. Comparison of emission data, including New Source Performance Standards, recent New Source Review limits, existing and proposed emission rates for Xcel High Bridge for the Alternative. Capacity NO x SO 2 PM 10 MW mmbtu/hr Lb/mmBtu Lb/mmBtu Lb/mmBtu High Bridge 5 and 6, coal New Source lb/mwh Performance Standards Recent Best Available Control Technology determinations for coal-fired generating units 3 Range of Recent BACT determinations Median of BACT determinations Emission rate, High Bridge 5 and 6 Alternative Project lb/mmbtu 2.69 lb/mwh Table 1 shows the Alternative project emission rates for SO2 and PM at the High Bridge plant reflect BACT-like control levels. Emission rates for NOx do not meet BACT levels. The Alternative project at High Bridge does not meet BACT. Does the Alternative meet NSPS? Because the Alternative does not meet emission rates that would be established through a BACT analysis for NOx, the MPCA must determine whether the Alternative project for this facility meets the emission rates as set forth in the NSPS for a new coal fired facility. The new source performance standard for new coal-fired facilities expresses NOx limits in terms of the amount of NOx released for the electricity generated (lb/mwh), not in terms of the heat input (lb/mmbtu). The MPCA has calculated the resulting NOx 1 New Source Performance Standards in 40 CFR 60 Subpart Da (40 CFR 60.40b-60.49b). 2 The NSPS restricts emissions of PM (not PM 10 ) from coal-fired boilers. The NSPS also requires a reduction of 99% of particulate matter from coal-fired boilers. 3 These BACT determinations were made for units burning coal. Modifications recorded in the RACT/BACT/LAER Clearinghouse from 1997 to 2002 were included in the analysis. Values for NOx were based on coal-fired boilers, while the values for SO2 and PM10 were based on boilers using subbituminous coal. 4 Emissions rates identified in Xcel Response to MPCA Request No.1, dated August 23, 2002, and the Xcel Response to MPCA Request No. 2, dated September 5,

10 emissions rate for High Bridge as 2.69 lb/mwh, which does not meet NSPS, let alone result in emissions substantially lower than NSPS as required by the statute. Does the project reduce emissions to the lowest cost-effective level, given the age or condition of the generating unit? An assessment has not been provided by Xcel to determine whether the Alternative project at High Bridge reduces emissions to the lowest cost-effective level. The MPCA is currently unable to conclude whether the Alternative meets this requirement of the statute, but has requested information from Xcel to help make this determination. Summary The High Bridge Alternative project does not satisfy the conditions of Minn. Stat. 216B.1692, subd. 1 (i) or (ii). The MPCA is unable to conclude whether the Alternative project at High Bridge qualifies for the rate recovery treatment under Minn. Stat. 216B.1619, subd. 1(iii) at this time Riverside Is it an existing large electric generating power plant as defined under Minn. Stat. 216B.2421 subd. 2 that is located in the state and not subject to emission limitations for new power plants under the federal Clean Air Act? The Riverside Plant is located on the east bank of the Mississippi River north of downtown Minneapolis. It has three power boilers. Units 6 and 7 were initially constructed in 1946 and 1948 respectively. Together, these two boilers generate steam for one steam turbine for a generating capacity of 134 MW. Boiler 8, first installed in 1961, has a separate steam turbine with a generating capacity of 226 MW. Due to the dates of construction, these units were not initially subject to either NSPS or NSR regulations because they were built before the Clean Air Act was passed. The plant s capacity exceeds 50 MW so it is an existing large electricity generating plant. Does it increase capacity by more than 10 percent or more than 100 MW? The proposal does not increase the generating capacity of this plant. In fact, there is a very slight decrease in generating capacity due to the parasitic load of the air pollution control equipment and other operating constraints associated with the control equipment. Does the project propose best available control technology? 9

11 Table 2 shows the current emission rates at the Riverside plant and the emission rates that would result from Xcel s Alternative project with NSPS and BACT determinations for similar plants. Table 2. Comparison of Emission Data, including New Source Performance Standards, recent New Source Review Limits, existing and proposed emission rates for Xcel Riverside for the Alternative project. Capacity NO x SO 2 PM 10 MW mmbtu/hr Lb/mmBtu Lb/mmBtu Lb/mmBtu Riverside 6/ , Riverside , New Source Performance lb/mwh Standards Recent Best Available Control Technology determinations for coal-fired generating units 6 Range of Recent BACT determinations, pulverized coal Median of BACT determinations Emissions, Riverside 6/ Range of Recent BACT determinations, cyclone boilers Median of BACT determinations Emissions, Riverside lb/mmbtu 3.89 lb/mwh lb/mmbtu 4.93 lb/mwh Table 3 shows the Alternative project emission rates for SO2 and PM at the Riverside plant meets BACT-like level of controls. The emission rate for NOx does not meet BACT levels for either Units 6/7 or Unit 8. The Alternative project at Riverside does not meet BACT. 5 New Source Performance Standards in 40 CFR 60 Subpart Da (40 CFR 60.40b-60.49b). 6 These BACT determinations were made for units burning coal. Modifications recorded in the RACT/BACT/LAER Clearinghouse from 1999 to 2002 were included in the analysis. Values for NOx from Riverside Units 6/7 were based on units firing coal. Values for NOx from Riverside Unit 8 were based on coal-fired cyclone boilers. The values for SO2 and PM10 were based on boilers using subbituminous coal. 7 Emissions rates identified in Xcel Response to MPCA Request No.1, dated August 23, 2002, and the Xcel Response to MPCA Request No. 2, dated September 5,

12 Does the Alternative project meet NSPS? Because the Alternative does not reflect emission rates that would be established through a BACT analysis for NOx, the MPCA must determine whether the Alternative project at Riverside meets the emission rates as set forth in the NSPS for a new coal-fired unit. The NSPS for new coal-fired facilities expresses NOx limits in terms of the amount of NOx released for the electricity generated (lb/mwh), not in terms of the heat input (lb/mmbtu). The MPCA has calculated the resulting NOx emissions from Riverside units 6/7 and 8. The emission of NOx from these units is substantially higher than that required by NSPS for NOx. The Alternative does not meet NSPS. Does the project reduce emissions to the lowest cost-effective level, given the age or condition of the generating unit? An assessment has not been provided by Xcel to determine whether the Alternative project at Riverside reduces emissions to the lowest cost-effective level. The MPCA is currently unable to conclude whether the Alternative meets this requirement of the statute, but has requested more information from Xcel to help make this determination. Summary The Riverside Alternative project does not satisfy the conditions of Minn. Stat. 216B.1692, subd. 1 (i) or (ii). The MPCA is unable to conclude whether the Alternative project at Riverside qualifies for the rate recovery treatment under Minn. Stat. 216B.1692, subd. 1(iii) at this time. 11

13 4.0 Other Questions the PUC Must Consider Minn. Stat. 216B.1692, Subd. 5 requires the PUC to evaluate whether: 1. the emission reduction project is needed to comply with new state or federal air quality standards; or 2. the emission reduction project is required as a corrective action as part of any state or federal enforcement action. The MPCA has evaluated both of these questions as they relate to the Alternative project and continues to conclude, for the reasons explained in its December 2002 Report on the Proposal that: 1. None of the projects are currently needed to meet any new state or federal air quality standards, and 2. None of the projects are currently required as a corrective action as part of any state or federal enforcement action. 12

14 5.0 Estimated Capital Cost of the Alternative Project The MPCA reviewed the cost of the alternative project to determine whether the estimated costs are reasonable because they end up being compared to the estimated benefits of the project. Reviewing costs also is important because the cost-effectiveness of this Alternative project is now under consideration. 5.1 Method of Analysis The MPCA used the same data source and cost generating tools as it used for its assessment of the control equipment proposed at the A.S. King plant in the December 2002 report. National cost estimates were gathered from capital costs developed by EPA and U.S. Department of Energy s Energy Information Agency as a general estimate of installing air pollution control equipment (EIA) (EPA 1998, EPA 1999a, EIA, 2000). This type of estimate provides an approximate cost, and does not take into account regional differences between labor, material, or transportation costs. EPA s air pollution control cost workbook CUECost (Keeth) was used to estimate construction costs on a more site-specific basis, recognizing that it too does not account for all site-specific factors. For example, based on Xcel s previous reply 8, the MPCA adjusted CUECost when assessing the Alternative projects at High Bridge and Riverside to account for higher labor rates in this area than the default rates in CueCost. However, other factors, such as specific plant design values, were not adjusted from the default due to the MPCA not having this information, or its relative small effect on estimating construction costs. 5.2 Assessment of A.S. King Cost Estimates Because the air pollution control and boiler/generator upgrades in the Alternative for this plant are identical to the original Proposal, no further assessment of cost estimates for the A.S. King plant were undertaken. Total construction costs are estimated at $363 million ($2001). In December 2002, the MPCA concluded that for this plant, Xcel s capital costs estimates for the air pollution control equipment are within an expected reasonable range of cost, and are consistent with the costs experienced by the industry for this type of project. 5.3 Assessment of High Bridge Cost Estimates The Alternative involves the installation of low-nox burners, over-fire air systems, and boiler optimization software on the boiler of Units 5 and 6. Post-combustion air pollution control would be installed downstream, consisting of adding spray drying/fabric filter. The units currently each have electrostatic precipitators (ESPs) for PM control. A single spray drying absorber unit would be installed after the ESPs, which is followed by a single pulse-jet fabric filter, finally exiting through the plant s single stack. 8 Xcel Response to MPCA Request No. 20, December 9,

15 These types of air pollution control devices are common in the industry due to continued NOx and SO2 reduction requirements under EPA s NOx SIP call and Title IV of the Clean Air Act. Table 3. Comparison of Capital Costs for High Bridge Alternative. Size (MW) 2001 Total Construction Costs (in millions) Installed Cost per kw generating capacity ($/kw) Xcel s Estimate High Bridge Units 5 and EIA/EPA 9 Total cost of air pollution control retrofit (sum of 308 individual estimates below) NOx (LNB/OFA) Acid gas (LSD) Particulate (FF) EPA CUECost 11 Total cost of air pollution control retrofit (sum individual estimates below) NOx (LNB/OFA) Acid Gas (LSD) Particulate (FF) Based on these comparisons as shown in Table 3, Xcel s estimate of total capital cost of installation of air pollution control equipment at High Bridge is almost exactly what national cost estimates would predict as installation costs on a per kilowatt basis. Xcel does not provide a breakdown of costs of the project between NOx, acid gas or particulate control equipment. To obtain the full benefit of retrofitting the air pollution control equipment, Xcel states in its filing that additional rehabilitation work must be performed at the High Bridge plant to ensure its long-term reliability 12. This is a reasonable expectation, as Units 5 and 6 are now nearing 50 years old each. Without rehabilitation, these units will continue to age, becoming less and less reliable as generating stations. 9 Energy Information Agency 2001/EPA 1999a/EPA LNB/OFA= low NOx burners, overfire air; LSD= lime spray drying; FF= pulse jet fabric filter 11 Because a single acid gas and particulate matter device is proposed downstream of both boilers, CUEcost was used to determine the cost of these two controls based on 243 MW of generation. The control of NOx was run separately for a 85 MW boiler (HB 5) and for a 154 MW boiler (HB 6). The NOx control capital cost reflects the sum of these two runs. 12 Xcel Emissions Reduction Proposal, July 26, 2002, Attachment 5.A. 14

16 The MPCA believes that in order for the installation of air pollution control equipment on this plant to be considered a reasonable investment, Xcel would have to commit to overall plant rehabilitation, the extent, timing and cost of which are not described in the filing. Further, the MPCA believes that part of rehabilitating High Bridge must address reconfiguring current coal storage. Because of the ongoing interest in controlling fugitive emissions and the beautification of the Mississippi River, enclosed coal storage and handling facilities should be a part of any facility rehabilitation. Cost estimates for this activity should be included in the cost of overall plant rehabilitation. While the estimated cost of installing the pollution control equipment is reasonable, the Alternative fails to include projected costs for other necessary work that should also take place at the site. 5.3 Assessment of Riverside Capital Costs The coal-fired combustion and generating units at Riverside are very different from one another, which affects the applicability of traditional boiler modifications used to control NOx. Units 6 and 7 are conventional wall-fired pulverized coal boilers. Unit 8 is a cyclone boiler, which burns pulverized coal in a different manner from conventional pulverized coal boilers. The cyclone boiler generates a great deal of NOx, and burner/boiler modifications are technologically limited. Units 6 and 7 already have spray drying and fabric filters in place but have not been in use 13. The Alternative project for Units 6 and 7 includes rehabilitating this control equipment and adding new chemical injection equipment. Riverside 8 includes installing a new spray dryer and fabric filter downstream of the existing ESP. Additionally, overfire air modifications would be made to the boiler to lower NOx emissions from this cyclone boiler. Because of the differing conditions at Unit 6 and 7 and Unit 8, the retrofitting of Riverside should be viewed as two individual projects with different scope and technology options. Unit 6 and 7 The cost estimating tools available to the MPCA do not provide the means of estimating the cost of rehabilitating existing air pollution control equipment. Traditionally the cost of such activities includes first an assessment of the condition of the existing equipment, then a determination of equipments cost of replacement and/or repair. This type of work relies on expert engineering judgment, rather than cost predicting tools. 13 The spray dryer/fabric filter system was installed as a pilot project in the early 1980 s to evaluate appropriate air pollution control technologies for use at Sherco Unit 3. The control equipment is not needed to meet any regulatory requirements because the Riverside plant is grandfathered from various Clean Air Act control requirements that would require use of the spray dryer/fabric filter. 15

17 Costs for NOx control retrofits are fairly well-understood. Assuming that the cost estimating tools have reasonably predicted the cost of NOx control at Unit 6/7 (which for these units has turned out to be very small), the bulk of the cost of improving air pollution control at Unit 6/7 is related to rehabilitating the SD/FF. The $26 million estimated for rehabilitating this plant is only 5 percent of the total capital cost of the Alternative, making the cost of this upgrade minimal relative to the cost of the entire project. The MPCA therefore believes that for the scope of the air pollution control Alternative project described in the filing, the capital cost estimate for Riverside Units 6/7 is reasonable. Table 4. Comparison of Capital Costs for Riverside Unit 8 Alternative Project. Size (MW) 2001 Total Construction Cost (Millions) Installed Cost per kw generating Capacity ($/kw) Xcel Estimate Riverside EIA/EPA Total cost of air pollution control retrofit (sum of individual estimates below) 367 Adding NOx Control (Coal Reburning) 82.7 Adding Acid Gas Control (LSD) 215 Adding Particulate Control (FF) 69 EPA CUECost Workbook Total cost of air pollution control retrofit (sum of individual estimates below) Unit 8 Adding NOx Control (LNB/OFA) Adding Acid Gas Control (LSD) Adding Particulate Control (FF) In its assessment of the cost of NOx control techniques for cyclone burners, EPA assumes the method of choice is a combustion control technique called coal reburning. This method reduces NOx emissions by staging combustion, and EPA assumes it will reduce NOx emissions by about 50%. It is a moderate capital cost method of NOx control over the use of over-fire air modifications, the method proposed for Unit 8 in the Alternative. Xcel estimates that over-fire air will achieve NOx reductions on the order of about 50% (along with the use of boiler optimization software) at Unit 8. Over-fire air modifications represent a low capital cost technology. Because EPA only provided estimates for the more capital-intensive NOx control method for cyclone boilers, the resulting EIA/EPA estimate shown in Table 4 of the Alternative for Unit 8 on a $/kw basis is higher than the Alternative capital cost estimated by Xcel. 16

18 A more site-specific total project cost estimate is provided by CUECost, which predicts an even higher capital cost for the project than the EIA/EPA data, again shown in Table 4. As discussed in the MPCA s December 2002 report, spray drying and fabric filters are fully mature technologies within the past 7 years. This means that since the time that these data sources were generated, advances in scrubbing equipment technology have significantly reduced the size of spray dryers 14, which reduces the cost of materials and installation of such equipment. Further, the control equipment industry itself has consolidated, meaning that a single company can now supply both a spray dryer and fabric filter, offering additional savings by eliminating coordination and tie-in between different suppliers during design and fabrication of the components. The MPCA concludes that the cost estimate for the Alternative project at Riverside Unit 8 appears to be in a reasonable range. Other Issues Like High Bridge, Xcel states that additional rehabilitation work will be necessary at Riverside to ensure that the full benefits of the air pollution control installation are realized 15. The nature, scope and cost of such rehabilitation was not provided in Xcel s filing, thus the total cost of the project at Riverside has not been stated. Because plant rehabilitation would likely significantly further extend the life of the current plant, continuing the ongoing use of coal, the MPCA believes that the scope of plant rehabilitation should include addressing fugitive dust emissions from the transfer of coal and ash at Riverside. This is of considerable consequence to the neighborhood around the Riverside plant, and would be in keeping with the overall goal of improving air quality from operating electricity generating stations, as well as address local interests in improving the aesthetics of the Mississippi River corridor. While the estimated cost of installing the pollution control equipment is reasonable, the Alternative fails to include projected costs for other necessary work that should also take place at the site. 5.4 Summary Construction costs of the Alternative project at all three metropolitan plants appear to be reasonable based on comparisons with national data bases and cost estimating tools. The total Alternative project costs for High Bridge and Riverside are likely underestimated. Rehabilitation of the remaining plant has been noted in Xcel s filing, but has not been accounted for in the project cost estimates. Rehabilitation of the plants should also include redesigning coal management to minimize fugitive dust, which ahs not been included in the Alternative. 14 Xcel Response to MPCA Request No. 20, December 9, Xcel July 29, 2002 Filing, Attachment 6.A. 17

19 The total Alternative project costs are therefore likely expected to be higher than currently described in Xcel s filing. The MPCA is unable at this time to estimate the likely increase. The MPCA recommends that should there be continued interest in the Alternative, Xcel should provide costs related to both plant rehabilitation and coal management. 18

20 6.0 Assessment of the Benefits of the Alternative Project 6.1 Emission estimates of the Alternative Table 5 below shows the MPCA s calculations of emissions expected after implementation of the Alternative project. The capacity factor was provided by Xcel 16. Table 5. MPCA s estimated annual emissions for the Alternative project at Xcel generating stations, tons per year (tpy). Capacity factor SO 2 (tpy) NO X (tpy) PM 10 (tpy) CO 2 (tpy) CO (tpy) Pb (pounds) Mercury (pounds) A.S. King ,298 1, ,810, High Bridge , High Bridge , Riverside 6/ , , Riverside , ,362, Three plants, Total 4,215 8, ,681,857 1, Table 6. Comparison of annual overall emissions for the three plants with the MERP Alternative project. SO 2 NO X PM 10 CO 2 CO Lead Mercury Current annual emissions from the MERP plants (tpy) Emissions change (tpy) 34,178 24, ,545, ,963-16, , Percent change The emission reductions calculated by the MPCA in Table 6 are reported as annual emissions. Xcel reported emission changes over a period of 10 years in its filing. Increases in PM 10, CO 2, and CO result from increased facility use. 16 Xcel Response to MPCA Request No. 1. August 23, Reported for emissions from all units at the facility (High Bridge 5+6, Riverside 6/7 + 8). 18 Lead and mercury emissions are reported in pounds per year. 19

21 6.2 Xcel Energy s Estimates of Environmental Benefits of the Alternative Xcel Energy uses the PUC s high environmental externality values and estimates that the net present value of the MERP Alternative s environmental benefits will be $78 million over ten years 19. This calculation was made using the same assumptions Xcel used to estimate the environmental benefits of the Proposal. 6.3 MPCA's Estimate of Environmental Benefits for the Alternative The MPCA believes that Xcel s estimate of the benefits associated with the Alternative underestimates the benefits for the same reasons the MPCA believed the Xcel Proposal calculation underestimated benefits. Adjusting the benefits estimation to account for a longer time period as well as for a different discount rate (the rational for these adjustments are outlined in the MPCA s original report starting on page 38) changes the benefits estimate to $182 million dollars over a 30 year time period. Figure 1 shows this estimate. Using the PUC s low externality value in the calculation produces a benefits estimate of $95 million. 19 Xcel July 26, 2002 filing, Attachment 7.B. An addition error occurred when summing the total benefits related to NOx. The correct total benefits is $78.48 million, not $60.4 million. 20

22 Figure 1. Estimate of Alternative project benefits to year $ millions, net present value $200.0 $180.0 $160.0 $140.0 $120.0 $100.0 $80.0 $60.0 $40.0 $20.0 $- Xcel original estimate of MERP alternative MPCA: 2040 end date, discount = 3% Low externality value High externality value 6.4 Avoided Costs Xcel s Alternative proposal results in an increase in generation capacity of about 60 MW at the King plant. Xcel has not estimated the value of avoided costs associated with this capacity increase. However, they did estimate the avoided cost associated with the Proposal 21. Using that estimate and scaling down to reflect the amount of additional capacity that would result from the Alternative, the MPCA estimates that the net present value of direct avoided costs for the Alternative to be about $110 million. There are also benefits associated with refurbishing plants to provide a longer useful life. At the time MPCA filed its initial report on the Proposal, there was no estimate available for this. However the MPCA speculated that this value must be worth several hundred million dollars. Xcel has since provided a figure for this benefit for the Proposal as $400 million 22. Scaling this amount to reflect the fact that in the Alternative proposal only the King plant refurbishment results in an increase in generating capacity, the MPCA estimates this net present value benefit to be $183 million. Since this calculation of avoided costs for refurbishing existing capacity of the Alternative proposal is scaled based on MW, it should only be considered as illustrative of the relative magnitude of the actual values, rather than a specific estimate based on the conditions present at the Riverside and High Bridge plants. 20 While an externality value is provided for lead emissions, its contribution to this calculation is so small that the MPCA has chosen not to include it in these discussions. 21 Xcel Response to MPCA Request No. 17, November 18, Xcel Response to Department of Commerce Request No. 31, January 31,

23 6.5 Other Benefits The previous analysis of benefits does not include any benefits relating to a number of important environmental and health issues. These are carefully outlined in the MPCA s original report on pages and pages The most important of these unaccounted benefits include the direct health impacts of fine particulates (PM 2.5 ). It is important to note that with the Alternative as with the Proposal, the MPCA believes that the benefits calculations greatly underestimate the actual benefits, primarily due to the fine particulate issue. Also, because the Alternative does not substitute natural gas for coal at the Riverside and High Bridge plants, the benefits associated with removing coal delivery, storage and ash management would not apply to the Alternative. 6.6 Comparison of the Proposal to the Alternative The following tables summarize the most significant differences between the Proposal and the Alternative. Table 7 compares the difference in the emissions for each project. Table 9 describes important features of each project that should be included in making comparisons between the Proposal and the Alternative. Table 7. Emission Changes of the MERP Proposal and Alternative projects. Proposal Emissions change (tpy) SO 2 NO X PM 10 CO 2 CO Lead Mercury -31,880-22, , Percentage change Alternative Emissions change (tpy) -29,963-16, , Percentage change Lead and mercury are reported in pounds/year. 22

24 Table 8. Comparison of the MERP Proposal and Alternative projects. Cost (net present value) Proposal Alternative $1600 million $664 million Avoided Costs due to new capacity $700 million $110 million Avoided Costs to refurbish the plants $400 million $183 million Health and Environmental Benefits based on $ million $ million externality values Emission Reductions -Greater reductions of SO 2 -Significantly greater reduction of NOx -Significantly greater reduction in PM 10 -Significant reduction in mercury -Significant reduction of SO 2 -Significant reduction in NOx -Sizable reduction in PM 10 -No predicted reductions in mercury -Increase in CO 2, CO and lead -Decrease in CO 2, CO and lead Refurbished Power 1100 MW of refurbished power 504 MW of refurbished power New Capacity Local Benefits 384 MW of new capacity 60 MW of new capacity Greater local benefits due to the emission reduction and elimination of coal handling at 2 plants No benefit from the elimination of coal handling The information in the table clearly shows that while the Proposal has a significantly higher cost than the Alternative, it also has significantly greater benefits. The costs of the Proposal ($1,600 million) roughly equal the benefits ( $500 million in environmental and health benefits + $400 million in avoided costs to refurbish existing capacity + $700 million in avoided costs associated with new capacity = $1,600 million.) For the Alternative, the total costs ($644 million) exceed the estimated benefits ( $182 million in environmental and health benefits + $183 million in avoided costs to refurbish existing capacity + $110 million in avoided costs associated with new capacity = $475 million.) However, it is important to remember that the environmental and health benefits in both calculations do not take some benefits into account because they were calculated using the Commission's externality values. The latest scientific understanding of fine particulates (PM 2.5 ) indicates that the value for PM should be significantly higher. Likewise, environmental scientists now find damages associated with mercury deposition, sulfur dioxide emissions, acid rain and a number of other factors that are excluded from the Commission's externality values. From this analysis, the Proposal is superior. 23

25 Another way to assess the costs and benefits of the Proposal and Alternative is to look at the costs per ton of pollutant reduced. This is an approach that is often used by EPA and states to analyze various control technology options for cost-effectiveness. The MPCA has conducted a preliminary assessment of the Proposal and Alternative to determine the cost per ton of pollutant removed for each option, included in Attachment 1. When comparing these two proposals in this manner, taking avoided costs into account, the Proposal shows a lower cost per ton of pollutant reduced than the Alternative proposal. This suggests the Proposal is more cost-effective than the Alternative. 24

26 7.0 Appropriateness of the Alternative Project The three plants addressed in Xcel s Alternative are old power plants that were exempt from having to upgrade pollution control equipment by the 1970 federal Clean Air Act. Nationally, the need to reduce emissions from power plants, especially the older grandfathered plants has been recognized in all circles. Huge environmental and health benefits will result from reducing power plant emissions. The debate has moved from whether to reduce, to how much and by when. Because the MPCA is currently unable to determine whether the proposed changes at the High Bridge and Riverside plants qualify under the statute, it is difficult to address the appropriateness of the Alternative. It would seem, if pollution control equipment upgrades are to be made at High Bridge and Riverside, state-of-the-art control technology would be more appropriate than lesser technology. Especially, considering that, with this investment in equipment and the refurbishments Xcel refers to but does not include in the Alternative, these plants are likely to continue operating for years to come. 7.1 Cost and Benefits While it has not been possible to provide a detailed qualitative cost-benefit analysis of the Alternative, the MPCA has reviewed both the projected capitol costs and the estimated benefits. The MPCA has concluded that the cost of the Alternative is approximately $664 million net present value, when assuming a plant life beyond After subtracting the avoided costs associated with the benefits of the additional generation capacity and the rehabilitation of the King plant, the cost of the Alternative is closer to $371 million. Using a more realistic timeframe for benefit accrual and using a more appropriate discount rate, the benefits are estimated at between $95 million and $182 million when using the PUC s externality values. Unfortunately, these benefits estimates do not fully and qualitatively assess all the benefits associated with the Alternative. 7.2 Comparison of the Alternative to the Proposal. The MPCA has also compared the Alternative to the Proposal. While the Alternative costs less than the Proposal, the Proposal provides substantially greater benefits. The Alternative would reduce sulfur dioxide (SO 2 ) nearly as much as the Proposal. While the Alternative would substantially reduce nitrogen oxides (NOx) and particulate matter (PM10) emissions, the reductions are not nearly as large as the reductions of these pollutants in the Proposal. Instead of reducing carbon dioxide, carbon monoxide and lead as the Proposal does, the Alternative increases emissions of these pollutants. Finally, the Alternative makes no reductions in mercury emissions, unlike the significant reductions that would be achieved by the Proposal. In addition, the Proposal provides substantial local benefits that the Alternative does not due to the switch from coal to natural gas at High Bridge and Riverside. The costs and benefits that are quantifiable from the Proposal are at least equal, while costs substantially exceed benefits for the Alternative. In both cases, however, the most 25

27 substantial unquantified benefit, reduction in fine particles, is not accounted for in these calculations. Because of the greater emission reductions from the Proposal as well as the greater avoided costs, the MPCA has calculated that the Proposal is more cost effective on a dollars-per-ton-reduced than the Alternative. As a result, the MPCA believes that the Proposal is a more superior project than the Alternative. 26

Review of Minnesota Power s Arrowhead Regional Emission Abatement (AREA) Project January 17, 2006

Review of Minnesota Power s Arrowhead Regional Emission Abatement (AREA) Project January 17, 2006 Review of Minnesota Power s Arrowhead Regional Emission Abatement (AREA) Project January 17, 2006 g-16-01 For More Information Contact the following MPCA staff members for more information about the preparation

More information

Michigan Department of Environmental Quality - Air Quality Division ADDITIONAL TECHNICAL INFORMATION FOR BOILERS

Michigan Department of Environmental Quality - Air Quality Division ADDITIONAL TECHNICAL INFORMATION FOR BOILERS Michigan Department of Environmental Quality - Air Quality Division ADDITIONAL TECHNICAL INFORMATION FOR BOILERS The following information will be used for the technical review of a permit to install application

More information

Naughton Power Plant. Chapter 6, Section 2 Construction Permit Application. Submitted to the Wyoming Air Quality Division And Prepared by

Naughton Power Plant. Chapter 6, Section 2 Construction Permit Application. Submitted to the Wyoming Air Quality Division And Prepared by Naughton Power Plant Chapter 6, Section 2 Construction Permit Application Submitted to the Wyoming Air Quality Division And Prepared by 1407 West North Temple Salt Lake City, Utah 84116 March 2008 1.0

More information

Comparison of Nitrogen Oxides, Sulfur Dioxide, Particulate Matter, Mercury and Carbon Dioxide Emissions for IGCC and Other Electricity Generation.

Comparison of Nitrogen Oxides, Sulfur Dioxide, Particulate Matter, Mercury and Carbon Dioxide Emissions for IGCC and Other Electricity Generation. Comparison of Nitrogen Oxides, Sulfur Dioxide, Particulate Matter, Mercury and Carbon Dioxide Emissions for IGCC and Other Electricity Generation. The Minnesota Pollution Control Agency (MPCA) has been

More information

Air Emissions Permitting Considerations for an Integrated Gasification Combined Cycle (IGCC) Unit Potentially Located in the State of Delaware

Air Emissions Permitting Considerations for an Integrated Gasification Combined Cycle (IGCC) Unit Potentially Located in the State of Delaware Air Emissions Permitting Considerations for an Integrated Gasification Combined Cycle (IGCC) Unit Potentially Located in the State of Delaware Center for the Inland Bays Scientific & Technical Advisory

More information

Wyodak Power Plant. Chapter 6, Section 2 Construction Permit Application. Submitted to the Wyoming Air Quality Division And Prepared by

Wyodak Power Plant. Chapter 6, Section 2 Construction Permit Application. Submitted to the Wyoming Air Quality Division And Prepared by Wyodak Power Plant Chapter 6, Section 2 Construction Permit Application Submitted to the Wyoming Air Quality Division And Prepared by 1407 West North Temple Salt Lake City, Utah 84116 March 2008 1.0 Introduction

More information

Draft Technical Support Document For Air Emission Permit No

Draft Technical Support Document For Air Emission Permit No Draft Technical Support Document For Air Emission Permit No. 13700028-101 This technical support document (TSD) is intended for all parties interested in the draft permit and to meet the requirements that

More information

AIR EMISSION PERMIT NO Major Amendment IS ISSUED TO. Northern States Power Company dba Xcel Energy

AIR EMISSION PERMIT NO Major Amendment IS ISSUED TO. Northern States Power Company dba Xcel Energy AIR EMISSION PERMIT NO. 05300015-005 Major Amendment IS ISSUED TO Northern States Power Company dba Xcel Energy Xcel Energy - Riverside Generating Plant 3100 Marshall Street Northeast Minneapolis, Hennepin

More information

Arkansas Department of pollution Control and Ecology Division of Air Pollution Control. Summary Report Relative to Permit Application

Arkansas Department of pollution Control and Ecology Division of Air Pollution Control. Summary Report Relative to Permit Application ----- Vr%/tXJ Arkansas Department of pollution Control and Ecology Division of Air Pollution Control Summary Report Relative to Permit Application Submitted By: Nekoosa Papers, Inc. Ashdown, Arkansas (Little

More information

PERMITTEE Seminole Electric Cooperative, Inc North Dale Mabry Highway Tampa, FL 33618

PERMITTEE Seminole Electric Cooperative, Inc North Dale Mabry Highway Tampa, FL 33618 PERMITTEE 16313 North Dale Mabry Highway Tampa, FL 33618 Authorized Representative: James R. Frauen, Project Director Air Permit No. 1070025-004-AC Units 1-2 Pollution Controls Upgrade Facility ID No.

More information

Customized Solutions for Environmental Compliance. Combining proven experience, technology and reliable performance for our customers

Customized Solutions for Environmental Compliance. Combining proven experience, technology and reliable performance for our customers Customized Solutions for Environmental Compliance Combining proven experience, technology and reliable performance for our customers Recognize these acronyms? MATS CSAPR CAIR CAVR NSPS NAAQS CAA UMACT

More information

Environmental Regulatory Update. Entergy Arkansas, Inc. Integrated Resource Plan Stakeholder Committee Meeting

Environmental Regulatory Update. Entergy Arkansas, Inc. Integrated Resource Plan Stakeholder Committee Meeting Environmental Regulatory Update Entergy Arkansas, Inc. Integrated Resource Plan Stakeholder Committee Meeting Myra Glover, Entergy Services Inc. July 31, 2012 1 I. EAI s Environmental Stewardship II. Overview

More information

FINE PARTICULATE COLLECTION USING DRY ELECTROSTATIC PRECIPITATORS

FINE PARTICULATE COLLECTION USING DRY ELECTROSTATIC PRECIPITATORS FINE PARTICULATE COLLECTION USING DRY ELECTROSTATIC PRECIPITATORS Robert A. Mastropietro Lodge-Cottrell Inc. 2319 Timerloch Place, Suite E The Woodlands, TX 77380 INTRODUCTION Potential legislation concerning

More information

[Including Revisions to Affected Portions of the Interstate Transport SIP for the hour Ozone and 1997 PM 2.5 NAAQS]

[Including Revisions to Affected Portions of the Interstate Transport SIP for the hour Ozone and 1997 PM 2.5 NAAQS] [Including Revisions to Affected Portions of the Interstate Transport SIP for the 1997 8-hour Ozone and 1997 PM 2.5 NAAQS] Department of Environmental Quality March 20, 2013 Table of Contents List of Tables...

More information

GOVERNMENT of PUERTO RICO OFFICE OF THE GOVERNOR ENVIRONMENTAL QUALITY BOARD

GOVERNMENT of PUERTO RICO OFFICE OF THE GOVERNOR ENVIRONMENTAL QUALITY BOARD GOVERNMENT of PUERTO RICO OFFICE OF THE GOVERNOR ENVIRONMENTAL QUALITY BOARD Air Quality Area STATEMENT OF BASIS Title V Initial Permit The Puerto Rico Environmental Quality Board (EQB) is issuing a draft

More information

Minnesota Pollution Control Agency. Review of Xcel Energy s Sherco Units 1 and 2 Mercury Reduction Plan

Minnesota Pollution Control Agency. Review of Xcel Energy s Sherco Units 1 and 2 Mercury Reduction Plan Minnesota Pollution Control Agency Review of Xcel Energy s Sherco Units 1 and 2 Mercury Reduction Plan Minnesota Pollution Control Agency 520 Lafayette Road North St. Paul, MN 55155-4194 http://www.pca.state.mn.us

More information

NSPS for Dc Boilers Burning Residual Oil

NSPS for Dc Boilers Burning Residual Oil Minnesota Pollution Control Agency AQ Doc. # 8.07 February 1998 Facts about NSPS for Dc Boilers Burning Residual Oil In an effort to regulate new sources of air pollution and ensure that those sources

More information

Excerpt of Thermal Power Guidelines for New Plants

Excerpt of Thermal Power Guidelines for New Plants Excerpt of Thermal Power Guidelines for New Plants The following is an excerpt of the Thermal Power guidelines for New Plants, a complete version of which is found in the Pollution Prevention and Abatement

More information

Coal s Strategic Position in the U.S. for the Next 10 Years. Gerald A. Hollinden, Ph.D. URS Corporation Pittsburgh Coal Conference September 24, 2002

Coal s Strategic Position in the U.S. for the Next 10 Years. Gerald A. Hollinden, Ph.D. URS Corporation Pittsburgh Coal Conference September 24, 2002 Coal s Strategic Position in the U.S. for the Next 10 Years Gerald A. Hollinden, Ph.D. URS Corporation Pittsburgh Coal Conference September 24, 2002 Topics Coal production and use over last 100 years Projections

More information

MPCA Citizens Board. Michael Sandusky Director Environment Analysis and Outcomes Division

MPCA Citizens Board. Michael Sandusky Director Environment Analysis and Outcomes Division DEPARTMENT : POLLUTION CONTROL AGENCY DATE : September 17, 2010 SF-00006-05(4/86) STATE OF MINNESOTA Office Memorandum TO : FROM : MPCA Citizens Board Michael Sandusky Director Environment Analysis and

More information

ABSTRACT LEGISLATIVE AND REGULATORY BACKGROUND

ABSTRACT LEGISLATIVE AND REGULATORY BACKGROUND Title: Summary of Determinations for Coal-Fired Authors: Carl V. Weilert, Katherine Zack and Novi Leigh, Burns & McDonnell Engineering Presented at: Power-Gen Renewable Energy & Fuels Conference Date:

More information

ASA Bloomingburg, LLC. Air permit-to-install (PTI) number Public Hearing Date April 18, 2006 Comment Period End Date April 25, 2006

ASA Bloomingburg, LLC. Air permit-to-install (PTI) number Public Hearing Date April 18, 2006 Comment Period End Date April 25, 2006 ASA Bloomingburg, LLC Air permit-to-install (PTI) number 01-01306 Public Hearing Date April 18, 2006 Comment Period End Date April 25, 2006 Summary of Comments and Ohio EPA Responses August 2006 Introduction

More information

TECHNICAL SUPPORT DOCUMENT For DRAFT/PROPOSED AIR EMISSION PERMIT NO

TECHNICAL SUPPORT DOCUMENT For DRAFT/PROPOSED AIR EMISSION PERMIT NO TECHNICAL SUPPORT DOCUMENT For DRAFT/PROPOSED AIR EMISSION PERMIT NO. 10900011 005 This technical support document (TSD) is intended for all parties interested in the draft/proposed permit and to meet

More information

DRAFT AIR EMISSION PERMIT NO Major Amendment IS ISSUED TO. Miller Milling Co LLC

DRAFT AIR EMISSION PERMIT NO Major Amendment IS ISSUED TO. Miller Milling Co LLC DRAFT AIR EMISSION PERMIT NO. 07900006 004 Major Amendment IS ISSUED TO Miller Milling Co LLC Miller Milling Co LLC 100 2nd Avenue Southwest New Prague, Le Sueur County, MN 56071 The emission units, control

More information

RELEASE POINT TYPE Enter or select one of the following stack/emission point release orientation: downward

RELEASE POINT TYPE Enter or select one of the following stack/emission point release orientation: downward EMISSION SOURCE (Internal Combustion Engines) Instructions for Form B2-G Form B2-G should be completed for all generators. Make as many copies of the form as necessary. Attach all calculations and assumptions

More information

FINAL DETERMINATION. To Grant a. Temporary Permit/Non-Attainment New Source Review Permit. For. Concord Steam Corporation.

FINAL DETERMINATION. To Grant a. Temporary Permit/Non-Attainment New Source Review Permit. For. Concord Steam Corporation. FINAL DETERMINATION To Grant a Temporary Permit/Non-Attainment New Source Review Permit For Concord Steam Corporation To Construct a 305 MMBtu/hr Biomass Boiler (Wood & Natural Gas), 2 Auxiliary Boilers

More information

BART SIP Development: Example from Colorado WRAP IWG Meeting, Denver, CO August 29, 2007 Presented by: Ray Mohr and Curt Taipale

BART SIP Development: Example from Colorado WRAP IWG Meeting, Denver, CO August 29, 2007 Presented by: Ray Mohr and Curt Taipale BART SIP Development: Example from Colorado WRAP IWG Meeting, Denver, CO August 29, 2007 Presented by: Ray Mohr and Curt Taipale Rocky Mountain National Park Presentation Topics Background Colorado s state-only

More information

United States Environmental Protection Agency, Region 9. Air Division. Technical Support Document. for. EPA s Notice of Proposed Rulemaking.

United States Environmental Protection Agency, Region 9. Air Division. Technical Support Document. for. EPA s Notice of Proposed Rulemaking. United States Environmental Protection Agency, Region 9 Air Division Technical Support Document for EPA s Notice of Proposed Rulemaking for the California State Implementation Plan San Joaquin Valley Unified

More information

A REVIEW OF THE EXPECTED AIR EMISSIONS FOR THE PROPOSED FIBROSHORE 40-MW POWER PLANT TO BE FUELED WITH POULTRY LITTER AND WOOD

A REVIEW OF THE EXPECTED AIR EMISSIONS FOR THE PROPOSED FIBROSHORE 40-MW POWER PLANT TO BE FUELED WITH POULTRY LITTER AND WOOD A REVIEW OF THE EXPECTED AIR EMISSIONS FOR THE PROPOSED FIBROSHORE 40-MW POWER PLANT TO BE FUELED WITH POULTRY LITTER AND WOOD Prepared for MARYLAND ENVIRONMENTAL SERVICE STATE OF MARYLAND ANNAPOLIS, MARYLAND

More information

COMAR Amendments and Regulation.12 Standards for Biomass Fuel-Burning Equipment Equal to or Greater Than 350,000 Btu/hr

COMAR Amendments and Regulation.12 Standards for Biomass Fuel-Burning Equipment Equal to or Greater Than 350,000 Btu/hr Department of the Environment COMAR 26.11.09 Amendments and Regulation.12 Standards for Biomass Fuel-Burning Equipment Equal to or Greater Than 350,000 Btu/hr October 30, 2013 Topics Covered Standards,

More information

Ray Chalmers - EPA Region III

Ray Chalmers - EPA Region III Ray Chalmers - EPA Region III On December 16, 2011 EPA finalized the Mercury and Air Toxics Standards, the first national standards to reduce emissions of mercury and other toxic air pollutants from new

More information

The following sections discuss each of our thermal facilities and then describe changes that we have planned for certain facilities.

The following sections discuss each of our thermal facilities and then describe changes that we have planned for certain facilities. Chapter 6. Thermal Generation s thermal generation system is comprised of a combination of nuclear, coal, biomass, hydro, gas and oil fueled generating facilities. These facilities serve as the backbone

More information

AIR EMISSION PERMIT NO IS ISSUED TO. Northern States Power Company

AIR EMISSION PERMIT NO IS ISSUED TO. Northern States Power Company AIR EMISSION PERMIT NO. 14100004-001 IS ISSUED TO Northern States Power Company NSP - Sherburne County 13999 Industrial Boulevard Becker, Sherburne County, Minnesota 55308 The emission units, control equipment

More information

State of New Hampshire Department of Environmental Services Air Resources Division. Temporary Permit

State of New Hampshire Department of Environmental Services Air Resources Division. Temporary Permit State of New Hampshire Department of Environmental Services Air Resources Division Temporary Permit Permit No: TP-0120 Date Issued: December 26, 2012 This certifies that: Northeast Utilities Public Service

More information

AIR EMISSION PERMIT NO [AMENDMENT TO AIR EMISSION PERMIT NO ] IS ISSUED TO

AIR EMISSION PERMIT NO [AMENDMENT TO AIR EMISSION PERMIT NO ] IS ISSUED TO AIR EMISSION PERMIT NO. 05301050-021 [AMENDMENT TO AIR EMISSION PERMIT NO. 05301050-011] IS ISSUED TO THE UNIVERSITY OF MINNESOTA AND FOSTER WHEELER TWIN CITIES, INC. FOR THE UNIVERSITY OF MINNESOTA TWIN

More information

1. ESPs for Electric Utilities

1. ESPs for Electric Utilities Depending on the test method required for permitting, the solid particulate (rocks) can make up all or only a part of the measured particulate. Often-times people refer to the front half catch as the filterable

More information

Update on ICI Boiler MACT

Update on ICI Boiler MACT Update on ICI Boiler MACT Bruce Hedman March 5, 2013 Clean Air Acts Standards for Boilers and Incinerators On December 20, 2012, EPA finalized a specific set of adjustments to March 2011 Clean Air Act

More information

Technology Advancement and Standards for Biomass Fuel to Energy Conversion. Topics Covered

Technology Advancement and Standards for Biomass Fuel to Energy Conversion. Topics Covered Department of the Environment Technology Advancement and Standards for Biomass Fuel to Energy Conversion Husain Waheed Ph.D., Ad.Tech February 18, 2015 For discussion only Topics Covered Standards, Technology,

More information

Blue Ridge Environmental Defense League PO Box 88 Glendale Springs, North Carolina

Blue Ridge Environmental Defense League   PO Box 88 Glendale Springs, North Carolina Blue Ridge Environmental Defense League www.bredl.org PO Box 88 Glendale Springs, North Carolina 28629 BREDL@skybest.com (336) 982-2691 Electric Power from Poultry Waste is Not Green In 2006 Fibrowatt

More information

Greenhouse Gas Regulation (new Federal)

Greenhouse Gas Regulation (new Federal) Mercury & Air Toxics (MATS) Interstate Transport (CAIR/CSAPR) Regional Haze/Visibility Portland Cement NESHAP Greenhouse Gas Regulation (new Federal) Mercury & Air Toxics (MATS) Finalized December 2011

More information

AIR EMISSION PERMIT NO Major Amendment IS ISSUED TO. American Crystal Sugar Company

AIR EMISSION PERMIT NO Major Amendment IS ISSUED TO. American Crystal Sugar Company AIR EMISSION PERMIT NO. 02700001-011 Major Amendment IS ISSUED TO American Crystal Sugar Company AMERICAN CRYSTAL SUGAR - MOORHEAD 2500 11th Street North Moorhead, Clay County, MN 56560 The emission units,

More information

AIR EMISSION PERMIT NO Administrative Amendment IS ISSUED TO. ConAgra Food Ingredients Co

AIR EMISSION PERMIT NO Administrative Amendment IS ISSUED TO. ConAgra Food Ingredients Co AIR EMISSION PERMIT NO. 03700020-003 Administrative Amendment IS ISSUED TO ConAgra Food Ingredients Co CONAGRA FLOUR MILL - HASTINGS 2005 South Vermillion Street Hastings, Dakota County, MN 55033 The emission

More information

TITLE V OPERATING PERMIT STATEMENT OF BASIS

TITLE V OPERATING PERMIT STATEMENT OF BASIS TITLE V OPERATING PERMIT STATEMENT OF BASIS Facility Name: El Cajon Energy, LLC Title V Application Number: APCD2011-APP-001657 Facility ID: Equipment Address: APCD2009-SITE-06554 222 N. Johnson Ave. Facility

More information

AIR EMISSION PERMIT NO ADMINISTRATIVE AMENDMENT IS ISSUED TO. Northern States Power Company

AIR EMISSION PERMIT NO ADMINISTRATIVE AMENDMENT IS ISSUED TO. Northern States Power Company AIR EMISSION PERMIT NO. 05300015-002 ADMINISTRATIVE AMENDMENT IS ISSUED TO Northern States Power Company NSP - RIVERSIDE 3100 Marshall Street Northeast Minneapolis, Hennepin County, MN 554181826 The emission

More information

PART C - POLICY AND PROCEDURES FOR NON-MAJOR POLLUTING FACILITIES

PART C - POLICY AND PROCEDURES FOR NON-MAJOR POLLUTING FACILITIES PART C - POLICY AND PROCEDURES FOR NON-MAJOR POLLUTING FACILITIES BACT GUIDELINES PART C 30 DECEMBER 2016 Chapter 1 - How Is MSBACT Determined for Minor Polluting Facilities? This chapter explains the

More information

Minntac BART Report September 8, 2006

Minntac BART Report September 8, 2006 Minntac BART Report September 8, 2006 Minntac BART Report September 8, 2006 Table of Contents 1. Executive Summary...iv 2. Introduction...1 2.A BART Eligibility...3 2.B BART Determinations...3 3. Streamlined

More information

Boiler Tune-up Guide

Boiler Tune-up Guide Boiler Tune-up Guide National Emission Standards for Hazardous Air Pollutants for Area Sources: Industrial, Commercial, and Institutional Boilers What is a boiler tune-up? 40 CFR Part 63 Subpart JJJJJJ

More information

The Projected Impacts of the Clean Air Interstate Rule on Electricity Prices in Indiana

The Projected Impacts of the Clean Air Interstate Rule on Electricity Prices in Indiana The Projected Impacts of the Clean Air Interstate Rule on Electricity Prices in Indiana State Utility Forecasting Group, Purdue University 1. Introduction This paper examines the impact of various nitrogen

More information

SUNY Westchester Community College Air Emissions Permit Program Latest Revision Date January 2, 2016 Previous Revision Date June 12, 2015.

SUNY Westchester Community College Air Emissions Permit Program Latest Revision Date January 2, 2016 Previous Revision Date June 12, 2015. SUNY Westchester Community College Air Emissions Permit Program Latest Revision Date January 2, 2016 Previous Revision Date June 12, 2015 Air Emissions Permit Program Contents I. Air Permitting Introduction

More information

Emission Control Technology Review for NorthMet Project Processing Plant RS58A

Emission Control Technology Review for NorthMet Project Processing Plant RS58A Emission Control Technology Review for NorthMet Project Processing Plant RS58A PolyMet Mining Inc. October 2007 Emission Control Technology Review for NorthMet Project Processing Plant RS58A PolyMet Mining

More information

TITLE V OPERATING PERMIT STATEMENT OF BASIS

TITLE V OPERATING PERMIT STATEMENT OF BASIS Facility Name: Title V Permit No.: Permit Application Nos.: Site ID: Equipment Address: Goal Line, L.P. APCD2016-TVP-00043 APCD2016-APP-004597 APCD1992-SITE-08447 555 North Tulip Street Escondido, CA 92025

More information

Air Individual Permit Part 70 Reissuance Ever-Green Energy, Inc. Environmental Wood Supply, LLC

Air Individual Permit Part 70 Reissuance Ever-Green Energy, Inc. Environmental Wood Supply, LLC Air Individual Permit Part 70 Reissuance 12300063-004 Permittee: Co-permittee name: District Energy St Paul Inc-Hans O Nyman St Paul Cogeneration Ever-Green Energy, Inc. Environmental Wood Supply, LLC

More information

ADVICE FOR OBTAINING PERMIT EXEMPT APPLICABILITY DETERMINATIONS

ADVICE FOR OBTAINING PERMIT EXEMPT APPLICABILITY DETERMINATIONS ADVICE FOR OBTAINING PERMIT EXEMPT APPLICABILITY DETERMINATIONS It is the intent of this document to guide applicants into preparing Applicability Determination requests which include only the information

More information

BEST AVAILABLE CONTROL TECHNOLOGY & TOXIC BEST AVAILABLE CONTROL TECHNOLOGY DETERMINATION

BEST AVAILABLE CONTROL TECHNOLOGY & TOXIC BEST AVAILABLE CONTROL TECHNOLOGY DETERMINATION 777 12 th Street, Third Floor Sacramento, CA 95814 BEST AVAILABLE CONTROL TECHNOLOGY & TOXIC BEST AVAILABLE CONTROL TECHNOLOGY DETERMINATION DETERMINATION NO.: 145 Category/General Equip Description: Equipment

More information

09/30/2010 Waterside Power Redline Version: Matt Lydon Formatted: Font: Bold, Italic Formatted: Font: Bold, Italic Draft Model Rule Control of Natural

09/30/2010 Waterside Power Redline Version: Matt Lydon Formatted: Font: Bold, Italic Formatted: Font: Bold, Italic Draft Model Rule Control of Natural 09/30/2010 Waterside Power Redline Version: Matt Lydon Formatted: Font: Bold, Italic Formatted: Font: Bold, Italic Draft Model Rule Control of Natural Gas and Distillate Oil Fired HEDD Combustion Turbine

More information

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY p-bp15-01-02b ATTACHMENT 1 STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY IN THE MATTER OF THE DECISION ON THE NEED FOR AN ENVIRONMENTAL IMPACT STATEMENT FOR THE PROPOSED UNIVERSITY OF MINNESOTA

More information

Reducing CO2 Emissions from Fossil Fueled Power Plants

Reducing CO2 Emissions from Fossil Fueled Power Plants Reducing CO2 Emissions from Fossil Fueled Power Plants James E. Staudt, Ph.D For questions: staudt@andovertechnology.com West Virginia University College of Law February 24, 2014 Spectrum of Approximate

More information

State of the Art (SOTA) Manual for Stationary Gas Turbines

State of the Art (SOTA) Manual for Stationary Gas Turbines State of the Art (SOTA) Manual for Stationary Gas Turbines Original Date: July 1997 Revision Date: November 1999 State of New Jersey Department of Environmental Protection Air Quality Permitting Program

More information

APPENDIX A: RESOURCE PLANNING ANALYSIS

APPENDIX A: RESOURCE PLANNING ANALYSIS PUBLIC DOCUMENT TRADE SECRET DATA EXCISED APPENDIX A: RESOURCE PLANNING ANALYSIS Minnesota Power has studied many options for meeting environmental regulations on Boswell Energy Center Unit 4 ( BEC4 )

More information

An Overview on GHG PSD Permitting

An Overview on GHG PSD Permitting An Overview on GHG PSD Permitting Extended Abstract # 64 Melissa Hillman, Trinity Consultants, 1990 California Avenue, 8 th Floor, Walnut Creek, CA 94596 INTRODUCTION As of January 2, 2011, new and modified

More information

Guide to Low-Emission Boiler and Combustion Equipment Selection

Guide to Low-Emission Boiler and Combustion Equipment Selection ORNL/TM-2002/19 Guide to Low-Emission Boiler and Combustion Equipment Selection C. B. Oland ORNL/TM-2002/19 GUIDE TO LOW-EMISSION BOILER AND COMBUSTION EQUIPMENT SELECTION C. B. Oland Date Published: April

More information

AIR QUALITY PERMIT Issued under 401 KAR 52: Wolohan Drive, Suite 1 Ashland

AIR QUALITY PERMIT Issued under 401 KAR 52: Wolohan Drive, Suite 1 Ashland Commonwealth of Kentucky Environmental and Public Protection Cabinet Department for Environmental Protection Division for Air Quality 803 Schenkel Lane Frankfort, Kentucky 40601 (502) 573-3382 AIR QUALITY

More information

AIR EMISSION PERMIT NO IS ISSUED TO. ConAgra Flour Milling Company P.O. Box 3500 Omaha, NE For

AIR EMISSION PERMIT NO IS ISSUED TO. ConAgra Flour Milling Company P.O. Box 3500 Omaha, NE For AIR EMISSION PERMIT NO. 03700020-002 IS ISSUED TO ConAgra Flour Milling Company P.O. Box 3500 Omaha, NE 68103-0500 For CONAGRA FLOUR MILLING COMPANY HASTINGS 2005 South Vermilion Street Hastings, Dakota

More information

PRIMARY OR ALTERNATIVE OPERATING SCENARIO

PRIMARY OR ALTERNATIVE OPERATING SCENARIO EMISSION SOURCE (Fuel Combustion Source) Instructions for Form B2 Form B2 should be completed for all fuel combustion emission sources (e.g., generators, boilers, burn-off ovens, bakeon ovens, bakery ovens,

More information

Wellington Development WVDT, LLC Greene Energy Resource Recovery Project 3. GENERAL CONDITIONS

Wellington Development WVDT, LLC Greene Energy Resource Recovery Project 3. GENERAL CONDITIONS 3. GENERAL CONDITIONS 2 a) This Plan Approval authorizes the construction of two waste coal-fired, circulating fluidized bed (CFB) boilers and a steam generator capable of producing 580 gross megawatts

More information

AIR EMISSION PERMIT NO Total Facility Operating Permit - Reissuance IS ISSUED TO. The City of Chaska AND

AIR EMISSION PERMIT NO Total Facility Operating Permit - Reissuance IS ISSUED TO. The City of Chaska AND AIR EMISSION PERMIT NO. 01900059-003 Total Facility Operating Permit - Reissuance IS ISSUED TO The City of Chaska AND Minnesota Municipal Power Agency MMPA - Minnesota River Station 1040 Dahlen Lane Chaska,

More information

The Supreme Court and EPA Carbon Rules. Michael B. Gerrard Environmental and Energy Study Institute briefing March 6, 2014

The Supreme Court and EPA Carbon Rules. Michael B. Gerrard Environmental and Energy Study Institute briefing March 6, 2014 The Supreme Court and EPA Carbon Rules Michael B. Gerrard Environmental and Energy Study Institute briefing March 6, 2014 Clean Air Act Title II Mobile Sources CAA Section 202 Emission standards for new

More information

Table of Contents. (a) APPLICABILITY... 1 (b) EXEMPTIONS... 1 (c) DEFINITIONS... 1 (d) STANDARDS... 2

Table of Contents. (a) APPLICABILITY... 1 (b) EXEMPTIONS... 1 (c) DEFINITIONS... 1 (d) STANDARDS... 2 RULE 20.4 NEW SOURCE REVIEW PORTABLE EMISSION UNITS (ADOPTED AND EFFECTIVE 5/17/94) (REV. ADOPTED AND EFFECTIVE 12/17/97) (REV. ADOPTED 11/4/98; EFFECTIVE 12/17/98) (REV. ADOPTED AND EFFECTIVE 4/27/16)

More information

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY IN THE MATTER OF A REQUEST FOR A CONTESTED CASE HEARING

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY IN THE MATTER OF A REQUEST FOR A CONTESTED CASE HEARING ATTACHMENT 1 STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY IN THE MATTER OF A REQUEST FOR A CONTESTED CASE HEARING ON AND THE PROPOSED ISSUANCE OF AIR EMISSION PERMIT NO.13700063-004 FOR UNITED

More information

High Bridge Combined Cycle Plant

High Bridge Combined Cycle Plant High Bridge Combined Cycle Plant Location: Down town St. Paul, on the Mississippi River Plant Description: High Bridge is a combined cycle generating facility. A combined cycle plant produces electricity

More information

STATEMENT OF BASIS Mannington Mills, Inc. dba Mannington Wood Floors Epes, Sumter County, Alabama Facility/Permit No

STATEMENT OF BASIS Mannington Mills, Inc. dba Mannington Wood Floors Epes, Sumter County, Alabama Facility/Permit No STATEMENT OF BASIS Mannington Mills, Inc. dba Mannington Wood Floors Epes, Sumter County, Alabama Facility/Permit No. 412-0011 This draft initial Title V Major Source Operating Permit (MSOP) is issued

More information

CAM does have exemptions for certain emission units as follows: Page 1 of 8

CAM does have exemptions for certain emission units as follows: Page 1 of 8 Title: Authors: PM CEMS: The Current Reality of Monitoring Particulate Matter Ms. Robynn Andracsek, Burns & McDonnell Ms. Mary Hauner, Burns & McDonnell Mr. Craig Clapsaddle, MSI/Mechanical Systems, Inc.

More information

"De Minimis" air contaminant source exemption. (A) For purposes of this rule, the following definitions apply:

De Minimis air contaminant source exemption. (A) For purposes of this rule, the following definitions apply: 3745-15-05 "De Minimis" air contaminant source exemption. [Comment: For dates and availability of non-regulatory government publications, publications of recognized organizations and associations, federal

More information

AIR EMISSION PERMIT NO ADMINISTRATIVE AMENDMENT IS ISSUED TO. Northern States Power Company

AIR EMISSION PERMIT NO ADMINISTRATIVE AMENDMENT IS ISSUED TO. Northern States Power Company AIR EMISSION PERMIT NO. 16300005-003 ADMINISTRATIVE AMENDMENT IS ISSUED TO Northern States Power Company NSP - ALLEN S KING GENERATING PLANT 1103 King Plant Road Bayport, Washington County, MN 55003 The

More information

AIR EMISSION PERMIT NO IS ISSUED TO. ConAgra Flour Milling Company P.O. Box 3500 Omaha, NE For

AIR EMISSION PERMIT NO IS ISSUED TO. ConAgra Flour Milling Company P.O. Box 3500 Omaha, NE For AIR EMISSION PERMIT NO. 03700020-001 IS ISSUED TO ConAgra Flour Milling Company P.O. Box 3500 Omaha, NE 68103-0500 For CONAGRA FLOUR MILLING COMPANY - HASTINGS 2005 South Vermillion Street Hastings, Dakota

More information

IMPLEMENTATION OF EMISSION GUIDELINES FOR LARGE MWCS THE STATUS OF EMISSIONS REDUCTION

IMPLEMENTATION OF EMISSION GUIDELINES FOR LARGE MWCS THE STATUS OF EMISSIONS REDUCTION IMPLEMENTATION OF EMISSION GUIDELINES FOR LARGE MWCS THE STATUS OF EMISSIONS REDUCTION Joseph F. Puzio HDR Engineering Inc. ABSTRACT Since the promulgation of the Federal Emission Guidelines for large

More information

ESP and Fabric Filter Considerations for Meeting Environmental Regulations: IED, LCP and WI BREF

ESP and Fabric Filter Considerations for Meeting Environmental Regulations: IED, LCP and WI BREF ESP and Fabric Filter Considerations for Meeting Environmental Regulations: IED, LCP and WI BREF Session T4S7 Presented at the POWER-GEN Europe June 21 23, 2016 Milan, Italy Jeffrey Shellenberger, Aaron

More information

4.0 Emissions Inventory

4.0 Emissions Inventory 4.0 Emissions Inventory Potential emissions during normal, startup, and shutdown operations were estimated for the proposed project. Emission estimates are based on AP-42 emission factors, vendor data,

More information

Longview Power- An Advanced Supercritical Coal Plant

Longview Power- An Advanced Supercritical Coal Plant Longview Power- An Advanced Supercritical Coal Plant prepared for the West Virginia Governor s 2012 Energy Summit December 10, 2012 Longview Power Overview 769 MW gross (695 MW net) Advanced supercritical

More information

Boiler MACT & Related Rules. Western Regional Boiler Association 45 th Annual Meeting Portland, Oregon March 14, 2013

Boiler MACT & Related Rules. Western Regional Boiler Association 45 th Annual Meeting Portland, Oregon March 14, 2013 Boiler MACT & Related Rules Western Regional Boiler Association 45 th Annual Meeting Portland, Oregon March 14, 2013 Clean Air Act Rules Recently Finalized National Emissions Standard for Hazardous Air

More information

CHAPTER Committee Substitute for Committee Substitute for Senate Bill No. 1300

CHAPTER Committee Substitute for Committee Substitute for Senate Bill No. 1300 CHAPTER 2003-144 Committee Substitute for Committee Substitute for Senate Bill No. 1300 An act relating to citrus; amending s. 403.08725, F.S.; redefining the terms new sources and existing sources ; amending

More information

Oklahoma Department of Environmental Quality Air Quality Division

Oklahoma Department of Environmental Quality Air Quality Division Oklahoma Department of Environmental Quality Air Quality Division BART Application Analysis January 19, 2010 COMPANY: FACILITY: FACILITY LOCATION: TYPE OF OPERATION: Units REVIEWER: AEP- Public Service

More information

2. How can the University have an expansion of the Cogeneration Facility without an increase in the amount of coal used?

2. How can the University have an expansion of the Cogeneration Facility without an increase in the amount of coal used? Responses to Questions Raised at the November 9, 2005 Public Hearing on the University of North Carolina at Chapel Hill s Special Use Permit Modification Request 1. What is the nature of the surveying

More information

STATEMENT OF BASIS for NEWARK BAY COGENERATION PARTNERSHIP L.P.

STATEMENT OF BASIS for NEWARK BAY COGENERATION PARTNERSHIP L.P. I. FACILITY INFORMATION Newark Bay Cogeneration Partnership L.P. is located at 414-514 Avenue P, Newark, New Jersey, Essex County and consists of a 120-megawatt cogeneration plant. The facility is owned

More information

Energy Production Systems Engineering

Energy Production Systems Engineering Welcome to Energy Production Systems Engineering USF Polytechnic Engineering tom@thomasblairpe.com Session 10: Environmental Controls Spring 2012 Plant Environmental Control Systems Power plant Environmental

More information

New 2015 Ozone Standard and Implications. July 2016

New 2015 Ozone Standard and Implications. July 2016 New 2015 Ozone Standard and Implications July 2016 What is Ozone? Ground level ozone is formed from the mixture of sunlight, NOx and VOC. 2 Effects of Ground Level Ozone 3 Effects of Ground Level Ozone

More information

Table of Contents. (a) APPLICABILITY... 1 (b) EXEMPTIONS... 1 (c) DEFINITIONS... 1 (d) STANDARDS... 2

Table of Contents. (a) APPLICABILITY... 1 (b) EXEMPTIONS... 1 (c) DEFINITIONS... 1 (d) STANDARDS... 2 RULE 20.4 NEW SOURCE REVIEW PORTABLE EMISSION UNITS (ADOPTED AND EFFECTIVE 5/17/94) (REV. ADOPTED AND EFFECTIVE 12/17/97) (REV. ADOPTED 11/4/98; EFFECTIVE 12/17/98) (REV. ADOPTED AND EFFECTIVE 4/27/16)

More information

WOOD PELLETS- A GROWING MARKETPLACE

WOOD PELLETS- A GROWING MARKETPLACE WOOD PELLETS- A GROWING MARKETPLACE The present drive for carbon neutral energy sources has given rise to increasing focus on biomass for energy. A big component of the world s biomass energy resource

More information

Environmental Compliance and Impacts. June 2011

Environmental Compliance and Impacts. June 2011 Environmental Compliance and Impacts June 2011 1 AEP s environmental stewardship AEP is an environmentally responsible company. It supports regulations that achieve long-term environmental benefits while

More information

Local Impacts of Mercury from Coal-Fired Power Plants

Local Impacts of Mercury from Coal-Fired Power Plants Local Impacts of Mercury from Coal-Fired Power Plants Prepared by Clean Air Task Force, March 2003 Effects of Coal Type and Air Pollution Control Device on Mercury Emissions, Atmospheric Transport and

More information

Clean Air Act Emission Limits

Clean Air Act Emission Limits 1 Clean Air Act Emission Limits CAA Emission Limits Authority for and Origin of Limits Federally promulgated regulations (e.g. NSPS, NESHAP, or MACT) SIP requirements PSD and N/A NSR permits 2 NSPS 3 New

More information

Oklahoma Gas & Electric

Oklahoma Gas & Electric Oklahoma Gas & Electric Sooner Generating Station Best Available Retrofit Control Technology Evaluation Prepared by: Sargent & Lundy LLC Chicago, Illinois Trinity Consultants Oklahoma City, Oklahoma May

More information

STATEMENT OF BASIS. Cheney Lime & Cement Company Landmark Plant Alabaster, Alabama Shelby County Facility No

STATEMENT OF BASIS. Cheney Lime & Cement Company Landmark Plant Alabaster, Alabama Shelby County Facility No STATEMENT OF BASIS Cheney Lime & Cement Company Landmark Plant Alabaster, Alabama Shelby County Facility No. 411-0019 This proposed Title V Major Source Operating Permit (MSOP) renewal is issued under

More information

PERMITTING PROCESS FOR THE COLUMBUS RESOURCE RECOVERY PLANT

PERMITTING PROCESS FOR THE COLUMBUS RESOURCE RECOVERY PLANT PERMITTING PROCESS FOR THE COLUMBUS RESOURCE RECOVERY PLANT STUART R. HERLAN and JOHN D. HUMMEL Alden E. Stilson & Associates Columbus, Ohio HENRY A. BELL Division of Electricity Columbus, Ohio ABSTRACT

More information

Oklahoma Department of Environmental Quality Air Quality Division

Oklahoma Department of Environmental Quality Air Quality Division Oklahoma Department of Environmental Quality Air Quality Division BART Application Analysis January 15, 2010 COMPANY: FACILITY: FACILITY LOCATION: TYPE OF OPERATION: REVIEWERS: Oklahoma Gas and Electric

More information

RULE Prevention of Significant Deterioration Adopted 9/24/84, Amended 11/18/85, 9/2/99, Amended 1/12/12 (Effective 2/8/13)

RULE Prevention of Significant Deterioration Adopted 9/24/84, Amended 11/18/85, 9/2/99, Amended 1/12/12 (Effective 2/8/13) RULE 210.4 Prevention of Significant Deterioration Adopted 9/24/84, Amended 11/18/85, 9/2/99, Amended 1/12/12 (Effective 2/8/13) I. Purpose The purpose of this Rule is to include the federal Prevention

More information

Benefits of Combined Heat and Power Systems for Reducing Pollutant Emissions in MANE-VU States. MANE-VU Technical Support Committee 3/9/2016

Benefits of Combined Heat and Power Systems for Reducing Pollutant Emissions in MANE-VU States. MANE-VU Technical Support Committee 3/9/2016 Benefits of Combined Heat and Power Systems for Reducing Pollutant Emissions in MANE-VU States MANE-VU Technical Support Committee 3/9/2016 Benefits of Combined Heat and Power Systems for Reducing Pollutant

More information

RULE 36 - NEW SOURCE REVIEW - HAZARDOUS AIR POLLUTANTS (Adopted 10/6/98)

RULE 36 - NEW SOURCE REVIEW - HAZARDOUS AIR POLLUTANTS (Adopted 10/6/98) VENTURA COUNTY AIR POLLUTION CONTROL DISTRICT RULE 36 - NEW SOURCE REVIEW - HAZARDOUS AIR POLLUTANTS (Adopted 10/6/98) A. Applicability The requirements of this Rule apply to any owner or operator who

More information

PRISM 2.0: THE VALUE OF INNOVATION IN ENVIRONMENTAL CONTROLS

PRISM 2.0: THE VALUE OF INNOVATION IN ENVIRONMENTAL CONTROLS PRISM 2.0: THE VALUE OF INNOVATION IN ENVIRONMENTAL CONTROLS INTRODUCTION This public brief provides a summary of a recent EPRI analysis of current and pending environmental controls on the U.S. electric

More information

Evaporative Gas Cooling and Emissions Control Solutions

Evaporative Gas Cooling and Emissions Control Solutions Evaporative Gas Cooling and Emissions Control Solutions for the Iron and Steel Industry MEGTEC ENERGY ENVIRONMENTAL B&W MEGTEC Solutions for the Iron & Steel Industry Our Pedigree Babcock & Wilcox MEGTEC

More information