LHC and post-lhc accelerators Engineering challenges Frédérick Bordry 10 th October 2014

Size: px
Start display at page:

Download "LHC and post-lhc accelerators Engineering challenges Frédérick Bordry 10 th October 2014"

Transcription

1 Engineering challenges 10 th October 2014

2 Outline - A brief look at history Importance of Energy - LHC machine - From design to operation - Main LHC challenges - Last results and future - Post-LHC machine - Conclusion 2 2

3 Lord Rutherford, in his inaugural presidential address to the Royal Society in London in 1928, said: I have long hoped for a source of positive particles more energetic than those emitted from natural radioactive substances. This was the start of a long quest for the production of high energy beams of particles in a very controlled way Energy gain 1 ev is the energy that an elementary charge gains when it is accelerated through a potential difference of 1 Volt 1 ev = J 3

4 High energy physics Schematic of Cockcroft and Walton s voltage multiplier. Opening and closing the switches S transfers charge from capacitor K3 through the capacitors X up to K1. 4

5 Van de Graaff's very large accelerator built at MIT's Round Hill Experiment Station in the early 1930s. Under normal operation, because the electrodes were very smooth and almost perfect spheres, Van de Graaff generators did not normally spark. However, the installation at Round Hill was in an open-air hanger, frequented by pigeons, and here we see the effect of pigeon droppings. Engineering challenges and problems 5

6 The Importance of Energy New discoveries often follow the opening of a new energy regime: Discovery of the electron Discovery of the nucleus Discovery of pion and muon Discovery of the kaon Discovery of the proton substructure Discovery of the top quark Discovery of the BEH (Higgs) boson 1 ev 5 MeV 100 MeV 500 MeV 20 GeV 2 TeV 8 TeV Dark Matter (Supersymmetry, ) Extra dimensions, Matter-antimatter asymmetry TeV? towards 100 TeV? 6

7 Lorentz force Challenge B and E Implicit in relativistic formulation of Maxwell s equations Describes the force on a charged particle moving in an em field f = q( E+ v B) Transverse Beam Dynamics Longitudinal Beam Dynamics 7

8 sustained exponential development for more than 80 years progress achieved through repeated jumps from saturating to emerging technologies superconductivity, key technology of high-energy machines since the 1980s 8

9 LHC (Large Hadron Collider) 14 TeV proton-proton accelerator-collider built in the LEP tunnel Lead-Lead (Lead-proton) collisions 1983 : First studies for the LHC project 1988 : First magnet model (feasibility) 1994 : Approval of the LHC by the CERN Council : Series production industrialisation 1998 : Declaration of Public Utility & Start of civil engineering : Placement of the main production contracts 2004 : Start of the LHC installation : Magnets Installation in the tunnel : Hardware commissioning : Beam commissioning and repair : Physics exploitation A 27 km circumference collider 9

10 Overall layout of LHC Four large experiments 10

11 Civil Engineering challenges CMS cavern 53m long, 27m wide by 25m high 30 New buildings 28,000 m 2 11

12 LHC: technological challenges The specifications of many systems were over the state of the art. Long R&D programs with many institutes and industries worldwide. The highest field accelerator magnets: 8.3 T (1232 dipole magnets of 15 m) The largest superconducting magnet system (~ magnets) The largest 1.9 K cryogenics installation (superfluid helium, 150 tons of LHe to cool down tons) Ultra-high cryogenic vacuum for the particle beams (10-13 atm, ten times lower than on the Moon) The highest currents controlled with high precision (up to 13 ka) The highest precision ever demanded from the power converters (ppm level) A sophisticated and ultra-reliable magnet quench protection system (Energy stored in the magnet system: ~10 Gjoule, in the beams > 700 MJ) 12

13 Energy management challenges Energy stored in the magnet system: 10 GJoule 10 GJoule flying 700 km/h Energy stored in the two beams: 720 MJ [ protons (1 ng of H+) at 7 TeV ] 700 MJ melt one ton of copper 700 MJoule dissipated in 88 µs / TW World Electrical Installed Capacity 3.8 TW 90 kg of TNT per beam 13

14 Superconducting Dipoles from Recent Machines 14

15 June 1994 first full scale prototype dipole June 2007 First sector cold ECFA-CERN workshop April 2008 Last dipole down 9T- 1m single bore 1994 project approved by council (1-in-2) 25 years Main contracts signed Decision for Nb-Ti 9T -10 m prototype 2002 String 2 November delivered September 10, 2008 First beams around 15 1

16 Conception, simulation et intégration 3D 16 16

17 Conception, simulation et intégration 3D The 10 metre long prototype bending magnet for LHC, which has reached a field of 8,73 Tesla on 14 April

18 String test : December 1998 Four years after its start-up, the first test string of the LHC comes to the end of its operation. Composed of prototypes, it made it possible to test and validate the various components and systems of the LHC. one complete cell (100m ) 18

19 The LHC Magnet Zoo Accelerators like LHC can also have: Quadrupole magnets to focus a beam Skew Quadrupoles Linear coupling Sextupoles Energy dependence of focusing Chromatic aberration Octupoles Amplitude dependence of focusing Decapoles Higher order correction ROXIE : Routine for the Optimization of magnet X-sections Inverse field computation and coil End design 19 19

20 Final assembly of cryomagnets at CERN One main dipole magnet : 35 tons, 15m 108 mh 1232 main dipoles 400 main quadrupoles 20

21 Systematic tests :100% of the magnets Systematic tests :100% of the magnets 1232 dipoles and 400 quadrupoles Cold magnetic performance measured on 20% of the magnets (correlation between warm and cold measurements) 21

22 Descent Descent of the of the last last magnet magnet km underground at 2 km/h! Installed in the tunnel : t 22

23 Cryomagnet interconnects challenge Total inter-magnet connections 1,695 Total number of High- Current Splices 10, helium-tight in situ welds Soldering and welding in difficult conditions but very high quality needed 250,000 welds in the tunnel environment 23

24 Why 1.9 K? (superfluid helium) 3 Tesla With Nb-Ti as technical superconductor, to get sufficient current density above 9 T, cooling below 2 K is required Trade-off between magnet and cryogenic complexity Very High Specific heat capacity and thermal conductivity, very low viscosity But producing 130 tonnes of He II is a considerable challenge! 24

25 Cryogenics A Huge System: Covering the Magnets, RF system and the detectors (CMS & ATLAS), Reliability is key since any minor stop of the system can lead to a significant stop of the accelerator 25

26 LHC : 1232 SC Main Dipole magnets Magnet inductance : L = 108 mh L total =1232 * = 133 H Ultimate current = 13kA Stored Energy = 11.3 GJ 26

27 One Sector (1/8) of the LHC Machine Cryostat containing 154 Main Dipoles 13kA Total inductance = 16.6H. Total stored energy = 1.2GJ Current source Power Converter 13kA, 10V flat top, ± 180V boost Time Constant = seconds (6 hours 23 minutes) 2x Energy extraction systems. Maximum rate of discharge = 120A/sec. 27

28 28

29 Massive use of HTS in LHC current leads 29

30 LHC magnetic cycle beam dump dipole current (A) Physic run energy ramp (10 to 12h) (30mn) coast injection phase start of the ramp 7 TeV 8.36 T GeV T time from start of injection (s) 30

31 x 10 LHC magnetic 4 cycle 1.3 beam dump dipole current (A) Current offset in Milliamps Physic run energy ramp 1.3 (10 to 12h) (30mn) coast Reference 450 GeV Measured T I 0 = Amps Time in Seconds 3 ppm 4 injection 3 phase 2 start of the ramp Current offset in ppm of 20 ka time from start of injection (s) 7 TeV 8.36 T 31

32 Beam Dump beam absorber (graphite) about 8 m concrete shielding 32

33 Beam Dump beam absorber (graphite) 30kV switch assembly (16kA/µs; 32kA; 6 µs ½ sine wave) about 8 m concrete shielding up to C Temperature of beam dump block at 80 cm 33

34 Operational margin of LHC superconducting magnet Applied Magnetic Field [T] Bc critical field Bc Applied field [T] 8.3 T 0.54 T quench with fast local loss of ~ protons Superconducting state quench with fast local loss of ~ protons Normal state QUENCH Tc critical temperature 1.9 K Temperature [K] Temperature [K] 9 K 34 34

35 Machine Protection Beam 362 MJ Requires: Collimation system to protect the cold surfaces by removing the tails of the beam 56 mm SC Coil: quench limit mj/cm 3 Aim: Minimize the chances of a beam induced quench, or worse, damage 35

36 Collimation System 1.2 m Even a small fraction of the LHC beam impacting on a collimator jaw will cause significant damage Simulation of 8 LHC bunches at 5 TeV impacting a Tungsten Jaw of a Collimator beam Total = 108 collimators About 500 degrees of freedom. All need aligning very precisely (10µm) to the beam 36

37 Collimator Settings Very close to the Beam 2.2 mm Requires very precise control of the beam and fill to fill reproducibility 37

38 Radio Frequency Acceleration System Typical LLRF Board: Several Hundred Control Cards Installed LHC 400MHz SC cavities All major power systems underground: 16, 300kW Klystrons and associated controls Timing and Synchronization systems in a Faraday cage on the surface LHC 400MHz Klystron Installation 38

39 LHC : a rich harvest of collisions Σ 30 fb collisions BEH boson announce 2010: 0.04 fb -1 7 TeV CoM Commissioning 2011: 6.1 fb -1 7 TeV CoM exploring limits 2012: 23.3 fb -1 8 TeV CoM production 7 TeV and 8 TeV in

40 Operation : availability There are a lot of things that can go wrong it s always a battle Cryogenics availability in 2012: 94.7% Courtesy Mike Lamont 40

41 Long Shutdown 1 LS1 starts as the shutdown to repair the magnet interconnects to allow nominal current in the dipole and lattice quadrupole circuits of the LHC. It became a major shutdown which, in addition, includes other repairs, maintenance, consolidation, upgrades and cabling across the whole accelerator complex and the associated experimental facilities. All this in the shadow of the repair of the magnet interconnects. 41

42 LS 1 from 16th Feb to Dec th Oct F M A M J J A S O N D J F M A M J J A S O N D J F M A beam to beam available for works Physics Beam commissioning Shutdown Powering tests 42

43 Opening:100% 100 % done 100 % done 100 % done 100 % done 100 % done Closure: 100% % done 100 % done Done Done 100 % done 100 % done 43

44 LHC schedule V4.1 Safety First, Quality Second, Schedule Third July August September October December November January February March April P1 12 P2 23 P3 34 P4 45 P5 56 P6 67 P7 78 P8 81 NC Cool-down CSCM ELQA PT Φ 1 PT Φ 2 Flushing, nqps, ELQA NC Cool-down CSCM ELQA PT Φ 1 PT Φ 2 Pressure test ELQA Flushing, nqps, ELQA NC Cool-down CSCM ELQA PT Φ 1 PT Φ 2 ELQA Flushing, nqps, ELQA NC Cool-down CSCM ELQA PT Φ Pressure test PT Φ 2 ELQA Flushing, nqps, ELQA NC Cool-down CSCM ELQA PT Φ 1 PT Φ 2 Machine Check-out Beam Commissioning CV maintenanc e CSCM Cool-down ELQA PT Φ 1 PT Φ 2 Pressure test ELQA Flushing, nqps, ELQA NC Cool-down CSCM ELQA PT Φ 1 PT Φ 2 CV maintenanc e Cool-down CSCM ELQA PT Φ 1 PT Φ 2 April March February January December November October September August July 1 st beam on week 11 (starting 9 th March 2015) Courtesy of Katy Foraz 44

45 LHC schedule: Run2 LS3 and Run 3 LS2 starting in 2018 (July) => 18 months + 3 months BC LS3 LHC: starting in 2023 => 30 months + 3 months BC Injectors: in 2024 => 13 months + 3 months BC Physics Shutdown Beam commissioning Technical stop (Extended) Year End Technical Stop: (E)YETS 30 fb -1 LHC b Injectors o LHC o Injectors o Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 EYETS Run Run 2 LS 2 2 LS 2 Run Run 3 YETS YETS YETS b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o PHASE Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 YETS o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o oyets o o o o o o o o o o o o o o o o o LS 3 LS 3 Run 4 Run 4 o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o t 300 fb -1 LS 4 Run 5 LS 5 LS 4 Run 5 LS 5 LS3 : HL-LHC installation 45

46 The European Strategy for Particle Physics Update 2013 Europe s top priority should be the exploitation of the full potential of the LHC, including the high-luminosity upgrade of the machine and detectors with a view to collecting ten times more data than in the initial design, by around This upgrade programme will also provide further exciting opportunities for the study of flavour physics and the quark-gluon plasma. HL-LHC from a study to a PROJECT 300 fb fb -1 including LHC injectors upgrade LIU (Linac 4, Booster 2GeV, PS and SPS upgrade) 46

47 The HL-LHC Project New IR-quads Nb 3 Sn (inner triplets) New 11 T Nb 3 Sn (short) dipoles Collimation upgrade Cryogenics upgrade Crab Cavities Cold powering Machine protection Major intervention on more than 1.2 km of the LHC 47

48 Setting up International collaboration A GLOBAL PROJECT Baseline layout of HL-LHC IR region Q1 Q2a Q2b Q3 D1 Q1-3: 140 T/m MCBX: 2.2 T 2.5/4.5 T m D1: 5.6 T 35 T m D2: 3.5 T 35 T m Q4: 120 T/m D2 Q distance to IP (m) with national laboratories but also involving industrial firms 48

49 LHC roadmap: schedule beyond LS1 LS2 starting in 2018 (July) => 18 months + 3 months BC LS3 LHC: starting in 2023 => 30 months + 3 months BC Injectors: in 2024 => 13 months + 3 months BC (Extended) Year End Technical Stop: (E)YETS 30 fb -1 LHC b Injectors o LHC o Injectors o LHC b Injectors b EYETS Run Run 2 LS 2 2 LS 2 Run Run 3 YETS o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o oyets o o o o o o o o o o o o o o o o o LS 3 LS 3 Run 4 Run 4 o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o LS 4 Run 5 LS 5 LS 4 Run 5 LS 5 Physics Shutdown Beam commissioning Technical stop Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 YETS YETS YETS b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o 300 fb -1 PHASE Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o b b b b b b b b b b b b o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o o t PHASE fb -1 49

50 to propose an ambitious post-lhc accelerator project at CERN by the time of the next Strategy update CERN d) CERN should should undertake undertake design design studies for accelerator projects in in a global a global context, context, with emphasis on proton-proton and electron-positron high-energy frontier machines. These design studies should be coupled to a vigorous accelerator R&D programme, including high-field magnets and high-gradient accelerating structures, in collaboration with national institutes, laboratories and universities worldwide. HFM - FCC HGA - CLIC 50

51 CERN should undertake design studies for accelerator projects in a global context, with emphasis on proton-proton and electron- positron highenergy frontier machines. Highest possible energy e + e - with CLIC (CDR 2012) Multi-lateral collaboration 51

52 to propose an ambitious post-lhc accelerator project at CERN by the time of the next Strategy update CERN d) CERN should should undertake design studies for accelerator projects in a in global a global context, context, with emphasis on proton-proton and electron-positron high-energy frontier machines. These design studies should be coupled to a vigorous accelerator R&D programme, including high-field magnets and high-gradient accelerating structures, in collaboration with national institutes, laboratories and universities worldwide. HFM FCC-hh HGA - CLIC 52

53 Malta Workshop: 33 TeV c.o.m October 2010 Material N. turns Coil fraction Peak field J overall (A/mm 2 ) Nb-Ti 41 27% Nb3Sn (high Jc) 55 37% Nb3Sn (Low Jc) 30 20% HTS 24 16% y (mm) HTS HTS Nb 3 Sn low j Nb 3 Sn low j Nb 3 Sn low j Nb 3 Sn high j Nb 3 Sn high j Nb 3 Sn high j Nb 3 Sn high j Nb-Ti Nb-Ti x (mm) Magnet design (20 T): very challenging but not impossible. 300 mm inter-beam Multiple powering in the same magnet (and more sectioning for energy) Work for 4 years to assess HTS for 2X20T to open the way to 16.5 T/beam. Otherwise limit field to 15.5 T for 2x13 TeV Higher INJ energy is desirable (2xSPS) The synchrotron light is not a stopper by operating the beam screen at 60 K. The beam stability looks «easier» than LHC thanks to dumping time. Collimation is possibly not more difficult than HL-LHC. Reaching 2x10 34 appears reasonable. The big challenge, after main magnet technology, is beam handling for INJ & beam dump: new kicker technology is needed since we cannot make twice more room for LHC kickers. 53

54 "High Energy LHC" First studies on a new 80 km tunnel in the Geneva area HE-LHC :33 TeV with 20T magnets 42 TeV with 8.3 T using present LHC dipoles 80 TeV with 16 T based on Nb 3 Sn dipoles 100 TeV with 20 T based on HTS dipoles 54

55 Future Circular Collider Study - SCOPE CDR and cost review for the next ESU (2018) Forming an international collaboration to study: pp-collider (FCC-hh) defining infrastructure requirements ~16 T 100 TeV pp in 100 km ~20 T 100 TeV pp in 80 km e + e - collider (FCC-ee) as potential intermediate step p-e (FCC-he) option FCC: km infrastructure in Geneva area 55

56 LHC experience The LHC is its own prototype! Limit in all technologies: field 9T, 1.9K, 1 ppm precision demanded from the power converters, high vacuum, protection, energy storage,... It has pushed the boundaries of many technologies and involved the transfer of this technology to industry on a large scale Complexity of the project. The components are all in series (chain of accelerators) Experience in the field of accelerators and large projects. Continuity of projects since 1954 (PS, SPS, ISR, LEP, LHC). Project based on the competence of specialists (design, construction, operation, maintenance) Systematization of prototypes and when possible sub-systems (String 1 and String 2) Individual component tests, e.g. electrical testing of 100% cold magnets and magnetic measurements of 20% (after verification of the measurement transfer between warm to cold conditions). Long Hardware Commissioning of equipments (debugging) 56

57 LHC experience (cont d) LHC QAP: introduction of EDMS (data available on-line worldwide, functional specification, technical specification, Engineering Change Request,...) Complete integration (3D) EVM (Earned Value Management) Competitive production contracts, when possible n+1 strategy LHC Technical committee involving every group leader of the systems Many international collaborations: universities, institutes, Reviews: systematic, independent, international for every system Machine Advisory Committee (global approach) 57

58 Final Design Quality - Cost ( M +P) Planning - Pressure In a project as large and innovative as LHC it is not realistic to expect that everything goes smooth without problems. The incident in Sept.2008 is one of the problems that we had, there were others with similar consequences, but less noticed by the public. Large projects of the size of the LHC are never riskless. Excluding any risk would be out of reach (P+M) Risks are to be evaluated and accepted Problems are not to be hidden. Create a structure allowing problems to surface (open atmosphere), especially under heavy pressure. Q.A. IS VITAL but it takes time! Tests are to be performed by independent teams (especially if outsourcing) 58 58

59 Particle accelerators The first motivation was from Ernest Rutherford who desired to produce nuclear reactions with accelerated nucleons. For many decades the motivation was to get to ever higher beam energies. At the same time, and especially when colliding beams became important, there was a desire to get to ever higher beam current. In the last three decades there has been motivation from the many applications of accelerators, such as producing X-ray beams, medical needs, ion implantation, spallation sources, and on and on. 59

60 List of Technologies needed for building and exploiting Accelerators Civil engineering Survey Electrical distribution Cooling and Ventilation Cryogenics Electrical engineering Electronics Mechanical engineering Beam-materials science Large scale simulations Magnets, room temperature and superconducting Power converters Ultra High Vacuum Radio Frequency, room temperature and superconducting Beam Instrumentation Controls and Databases Beam feedback Injection, extraction fast powerful kicker magnets Targets, dumps and collimators 60

61 May the Energy be with you! The greatest economic benefits of scientific research have always resulted from advances in fundamental knowledge rather than the search for specific applications. Margaret Thatcher

Status Report on the LHC machine Lyndon Evans

Status Report on the LHC machine Lyndon Evans Status Report on the LHC machine Lyndon Evans Third International Symposium on LHC Physics and Detectors Chia, Sardinia, 25th October 2001 Contents Injectors Magnets Cryogenics Vacuum Accelerating system

More information

1. CERN Accelerator Complex 2. Decay Ring Magnets 3. Costing

1. CERN Accelerator Complex 2. Decay Ring Magnets 3. Costing 1. CERN Accelerator Complex 2. Decay Ring Magnets 3. Costing Elena Wildner 2/25/2010 EUROnu WP4 Paris 19 Feb 2010 1 Layout of talk The Intensity Dilemma The News on CERN Machines Production calculations

More information

Energy consumption and savings potential of CLIC

Energy consumption and savings potential of CLIC Energy consumption and savings potential of CLIC Philippe Lebrun CERN, Geneva, Switzerland 55th ICFA Advanced Beam Dynamics Workshop on High Luminosity Circular e + e - Colliders Higgs Factory Beijing,

More information

Session 5 Shutdown schedule 2008/9 and Future shutdowns

Session 5 Shutdown schedule 2008/9 and Future shutdowns Where are we with the current shutdown? LHC Performance rm Workshop 2009 Session 5 Shutdown schedule 2008/9 and Future shutdowns EN/MEF/LPC J.Coupard & K.Foraz LHC Performance 04th Feb. 2009 1 Key drivers

More information

2008 JINST 3 S Cryogenic system. Chapter Overview

2008 JINST 3 S Cryogenic system. Chapter Overview Chapter 7 Cryogenic system 7.1 Overview The LHC is unique among superconducting synchrotrons, because its operating temperature is below 2 K to maximise the field strength of the superconducting magnets

More information

Report from the GDE director. Barry Barish Snowmass 14-Aug-05

Report from the GDE director. Barry Barish Snowmass 14-Aug-05 Report from the GDE director Barry Barish Snowmass 14-Aug-05 Global Design Effort The Mission of the GDE Produce a design for the ILC that includes a detailed design concept, performance assessments, reliable

More information

Guy Crockford, BE/OP/LHC, CERN

Guy Crockford, BE/OP/LHC, CERN Automation in the SPS and LHC and its effect on operator skills The past 20 years have seen great advances in the CERN accelerator control systems. Low level operation skills have been largely replaced

More information

EUROPEAN LABORATORY FOR PARTICLE PHYSICS LABORATOIRE EUROPEEN POUR LA PHYSIQUE DES PARTICULES

EUROPEAN LABORATORY FOR PARTICLE PHYSICS LABORATOIRE EUROPEEN POUR LA PHYSIQUE DES PARTICULES EUROPEAN LABORATORY FOR PARTICLE PHYSICS LABORATOIRE EUROPEEN POUR LA PHYSIQUE DES PARTICULES CERN-ST-99-030 February, 1999 COOLING AND VENTILATION FOR THE LHC STATUS REPORT M. Wilhelmsson Abstract For

More information

ON 19 September 2008, during powering tests of the main

ON 19 September 2008, during powering tests of the main IEEE TRANSACTIONS ON APPLIED SUPERCONDUCTIVITY, VOL. 20, NO. 3, JUNE 2010 2155 Thermal Runaway of the 13 ka Busbar Joints in the LHC Arjan P. Verweij Abstract Triggered by the incident in the LHC in September

More information

ST IMPLICATIONS IN THE CNGS PROJECT

ST IMPLICATIONS IN THE CNGS PROJECT EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH ORGANISATION EUROPÉENNE POUR LA RECHERCHE NUCLÉAIRE CERN - ST Division CERN-ST-2000-012 February, 2000 ST IMPLICATIONS IN THE CNGS PROJECT M. Wilhelmsson Abstract

More information

EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics CERN TS DEPARTMENT

EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics CERN TS DEPARTMENT EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics CERN TS DEPARTMENT EDMS Nr. 480988 CERN-TS-2004-017 (IC) Scheduling the installation of the LHC injection lines L. Lari,

More information

CRYOGENICS AND LHC BEAM COMMISSIONING

CRYOGENICS AND LHC BEAM COMMISSIONING CRYOGENICS AND LHC BEAM COMMISSIONING L. Tavian, CERN, Geneva, Switzerland Abstract During the LHC beam commissioning, the cryogenic system must fulfil its requirements and give maximum availability to

More information

EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH CERN - ACCELERATORS AND TECHNOLOGY SECTOR

EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH CERN - ACCELERATORS AND TECHNOLOGY SECTOR EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH CERN - ACCELERATORS AND TECHNOLOGY SECTOR CERN-ATS-2012-040 13 ka Superconducting Busbars Manufacturing Process R. Principe, P. Fessia, E. Fornasiere CERN, Geneva,

More information

CHAPTER 20 THE INTERNAL BEAM DUMPING SYSTEM

CHAPTER 20 THE INTERNAL BEAM DUMPING SYSTEM CHAPTER 20 THE INTERNAL BEAM DUMPING SYSTEM 20.1 SYSTEM DESCRIPTION There are three main ways in which the SPS internal beam dump will act: Firstly, the internal beam dumping system is automatically triggered

More information

Wir schaffen Wissen heute für morgen

Wir schaffen Wissen heute für morgen Wir schaffen Wissen heute für morgen Paul Scherrer Institute Alexander Gerbershagen Advantages and challenges of superconducting magnets in gantry design 18 September 2015 Motivation: reduce facility s

More information

THE CRYOGENIC SYSTEM FOR THE LHC TEST STRING 2: DESIGN, COMMISSIONING AND OPERATION

THE CRYOGENIC SYSTEM FOR THE LHC TEST STRING 2: DESIGN, COMMISSIONING AND OPERATION EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics Large Hadron Collider Project LHC Project Report 614 THE CRYOGENIC SYSTEM FOR THE LHC TEST STRING 2: DESIGN, COMMISSIONING

More information

Experience with Cryogenic Operations During the Fermilab Collider Program

Experience with Cryogenic Operations During the Fermilab Collider Program Experience with Cryogenic Operations During the Fermilab Collider Program The Fermi National Accelerator Laboratory is a U.S. Department of Energy (DOE) research laboratory, operated under DOE contract

More information

CHARACTERISATION OF MAGNETIC SHIELDING MATERIAL FOR HL-LHC CRAB CAVITIES

CHARACTERISATION OF MAGNETIC SHIELDING MATERIAL FOR HL-LHC CRAB CAVITIES 18th International Conference on RF Superconductivity SRF2017, Lanzhou, China JACoW Publishing doi:10.18429/jacow-srf2017- CHARACTERISATION OF MAGNETIC SHIELDING MATERIAL FOR HL-LHC CRAB CAVITIES Abstract

More information

Review of Cryogenics for Large Superconducting Systems

Review of Cryogenics for Large Superconducting Systems Review of Cryogenics for Large Superconducting Systems Laurent Tavian CERN, Accelerator Technology Department, CERN-AT, Geneva 23, CH 1211, Switzerland phone: +41 22 767 6959; e-mail: laurent.tavian@cern.ch

More information

ILC ASIAN DRAFT SCHEDULE

ILC ASIAN DRAFT SCHEDULE ILC ASIAN DRAFT SCHEDULE K Foraz, M Gastal & J Osborne Many thanks to all contributors Objectives and scope To provide a target baseline construction schedule for the 2 Asian sample sites Address remarks

More information

CEBAF Overview May 29, 2013

CEBAF Overview May 29, 2013 EF Overview May 29, 2013 Paul Vasilauskis Group Leader ccelerator Operations EF Timeline Machine Overview Injector Linear ccelerators Recirculation rcs Extraction Systems eam Specifications eam Operations

More information

Design and Manufacture of the Superconducting Bus-Bars for the LHC Main Magnets

Design and Manufacture of the Superconducting Bus-Bars for the LHC Main Magnets IEEE TRANSACTIONS ON APPLIED SUPERCONDUCTIVITY, VOL. 12, NO. 1, MARCH 2002 1305 Design and Manufacture of the Superconducting Bus-Bars for the LHC Main Magnets L. Belova, M. Genet, J.-L. Perinet-Marquet,

More information

ILC Report. Barry Barish Caltech / GDE. 1-Dec-06. RDR Design Freeze. Global Design Effort 1. 1-Dec-06. HEPAP Univ. Subpanel

ILC Report. Barry Barish Caltech / GDE. 1-Dec-06. RDR Design Freeze. Global Design Effort 1. 1-Dec-06. HEPAP Univ. Subpanel ILC Report RDR Design Freeze Barry Barish Caltech / GDE Global Design Effort 1 Progress toward RDR Global Design Effort 2 Baseline to a RDR 2006 Jan July Dec Frascati Bangalore Vancouver Valencia Freeze

More information

CERN experience and strategy for the maintenance of cryogenic plants and distribution systems

CERN experience and strategy for the maintenance of cryogenic plants and distribution systems IOP Conference Series: Materials Science and Engineering PAPER OPEN ACCESS CERN experience and strategy for the maintenance of cryogenic plants and distribution systems Related content - Management of

More information

CRYOGENIC HEAT LOAD AND REFRIGERATION CAPACITY MANAGEMENT AT THE LARGE HADRON COLLIDER (LHC)

CRYOGENIC HEAT LOAD AND REFRIGERATION CAPACITY MANAGEMENT AT THE LARGE HADRON COLLIDER (LHC) EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics Large Hadron Collider Project LHC Project Report 1171 CRYOGENIC HEAT LOAD AND REFRIGERATION CAPACITY MANAGEMENT AT THE

More information

Surface treatments for vacuum applications at CERN

Surface treatments for vacuum applications at CERN Surface treatments for vacuum applications at CERN Paolo Chiggiato Technology Department Vacuum, Surfaces & Coatings JRC-CERN collaboration workshop, CERN, January 27 th, 2014 2 Outlook 1 2 3 Vacuum materials

More information

Experience with MPS during the 2010 run

Experience with MPS during the 2010 run Experience with MPS during the 2010 run J. Wenninger BE-OP-LHC Acknowledgments: M. Zerlauth (statistics!), R. Schmidt, MPP(r) colleagues and UFO crews. 1 Outline Commissioning and intensity increase Reviews

More information

2008 JINST 3 S The interface to the LHC machine. Chapter Beampipe Layout

2008 JINST 3 S The interface to the LHC machine. Chapter Beampipe Layout Chapter 3 The interface to the LHC machine 3.1 Beampipe The beampipe design is particularly delicate since the LHCb experiment is focussed on the high rapidity region, where the particle density is high.

More information

Quench Protection of Very Large, 50 GJ Class and High-temperature Superconductor Based Detector Magnets

Quench Protection of Very Large, 50 GJ Class and High-temperature Superconductor Based Detector Magnets Quench Protection of Very Large, 50 GJ Class and High-temperature Superconductor Based Detector Magnets Matthias Mentink, Alexey Dudarev, Tim Mulder, Jeroen Van Nugteren, and Herman ten Kate Magnet Technology

More information

Market Survey. Technical Description. Supply of Long Austenitic Steel Shells for D2 Dipole Cold Masses

Market Survey. Technical Description. Supply of Long Austenitic Steel Shells for D2 Dipole Cold Masses EDMS No.: 1813586 Document Ref.: LHC-LBRD-CS-0001 Group Code : TE-MSC The HL-LHC Project Market Survey Technical Description Supply of Long Austenitic Steel Shells for D2 Dipole Cold Masses Abstract This

More information

CERN experience on accelerator magnets based on permanent magnets

CERN experience on accelerator magnets based on permanent magnets CERN experience on accelerator magnets based on permanent magnets for Future Linear and Circular Colliders Geneva 26 th -28 th November 2014 Which types of magnets are used at CERN? Resistive magnets:

More information

CLIC Civil Engineering, Infrastructure and Siting Working Group, (CEIS) John Osborne Matthew Stuart CERN SMB-SE-FAS

CLIC Civil Engineering, Infrastructure and Siting Working Group, (CEIS) John Osborne Matthew Stuart CERN SMB-SE-FAS CLIC Civil Engineering, Infrastructure and Siting Working Group, (CEIS) John Osborne Matthew Stuart CERN SMB-SE-FAS 1 CEIS Working Group Civil Engineering, Infrastructure and Siting Core Disciplines: Civil

More information

Cryogenic heat load and refrigeration capacity management at the Large Hadron Collider (LHC)

Cryogenic heat load and refrigeration capacity management at the Large Hadron Collider (LHC) Proceedings of ICEC 22-ICMC 28, edited by Ho-Myung CHANG et al. c 29 The Korea Institute of Applied Superconductivity and Cryogenics 978-89-957138-2-2 Cryogenic heat load and refrigeration capacity management

More information

Superconducting. magnets. The heart of NMR

Superconducting. magnets. The heart of NMR MARTIN TOWNSEND OXFORD INSTRUMENTS SUPERCONDUCTIVITY Superconducting The achievements of Oxford Instruments Superconductivity as a world leader in the research and development of superconducting magnets

More information

Quench Protection Study of a 11 T Nb 3 Sn Model Dipole for the High Luminosity LHC

Quench Protection Study of a 11 T Nb 3 Sn Model Dipole for the High Luminosity LHC 3LPo2E-05 [L44] 1 Quench Protection Study of a 11 T Nb 3 Sn Model Dipole for the High Luminosity LHC Susana Izquierdo Bermudez, Franco Mangiarotti, Gerard Willering, Marta Bajko, Luca Bottura, Jose Ferradas

More information

Calculation of Water Activity in Point 7

Calculation of Water Activity in Point 7 Calculation of Water Activity in Point 7 SC/RP, M. Brugger, S. Roesler joachim.vollaire@cern.ch Calculation of Water Activity in Point 7 Production of radioactive nuclei in water Production on Oxygen atom

More information

METHODS FOR THE EVALUATION OF QUENCH TEMPERATURE PROFILES AND THEIR APPLICATION FOR LHC SUPERCONDUCTING SHORT DIPOLE MAGNETS

METHODS FOR THE EVALUATION OF QUENCH TEMPERATURE PROFILES AND THEIR APPLICATION FOR LHC SUPERCONDUCTING SHORT DIPOLE MAGNETS EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics Large Hadron Collider Project LHC Project Report 459 METHODS FOR THE EVALUATION OF QUENCH TEMPERATURE PROFILES AND THEIR

More information

CERN Conductor and Cable Development for the 11T Dipole

CERN Conductor and Cable Development for the 11T Dipole FNAL CERN Conductor and Cable Development for the 11T Dipole B. Bordini, A. Ballarino, L. Oberli, D. Richter Collaboration meeting on DS 11T Dipole grounds Outline Wire Specifications and Procurement Ø

More information

Risk and Machine Protection for Stored Magnetic and Beam Energies

Risk and Machine Protection for Stored Magnetic and Beam Energies Published by CERN in the Proceedings of the CAS-CERN Accelerator School: Power Converters, Baden, Switzerland, 7 14 May 2014, edited by R. Bailey, CERN-2015-003 (CERN, Geneva, 2015) Risk and Machine Protection

More information

A POSITRON SOURCE USING CHANNELING IN CRYSTALS FOR LINEAR COLLIDERS

A POSITRON SOURCE USING CHANNELING IN CRYSTALS FOR LINEAR COLLIDERS A POSITRON SOURCE USING CHANNELING IN CRYSTALS FOR LINEAR COLLIDERS R.CHEHAB, X.ARTRU, M.CHEVALLIER, IPNL/ IN2P3/CNRS, UNIVERSITE LYON 1 V.M.STRAKHOVENKO, BINP-NOVOSIBIRSK A.VARIOLA, A.VIVOLI, LAL/IN2P3/CNRS,

More information

llilliiiillllllllilllllllllllllllllllllllil CERN AT, (CR, 94'36

llilliiiillllllllilllllllllllllllllllllllil CERN AT, (CR, 94'36 EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH CERN LIBRARIES, GENEVA llilliiiillllllllilllllllllllllllllllllllil CERN AT, (CR, 94'36 QERN-AT-94-36 ;.t W4?. Four 12 kw/4.5 K Cryoplants at CERN S. Claudet,

More information

CLIC MEETING. 1 - ILC Frascati workshop 2 - Conventional Facilities & Siting. CFS Group of GDE J.L. Baldy

CLIC MEETING. 1 - ILC Frascati workshop 2 - Conventional Facilities & Siting. CFS Group of GDE J.L. Baldy CLIC MEETING 1 - ILC Frascati workshop 2 - Conventional Facilities & Siting CFS Group of GDE J.L. Baldy 13 January 2006 SUMMARY Organization overview / Activity of the CFS Group since

More information

Reliability Analysis of the 11T Dipole Quench Protection System

Reliability Analysis of the 11T Dipole Quench Protection System Reliability Analysis of the 11T Dipole Quench Protection System Daniel Sollich TE-MPE-MI 4 th October 2018 Many thanks to Andrea Apollonio, Miriam Blumenschein, Fernando Menendez Camara, David Carrillo,

More information

Critical Current versus Transverse Stress and Thermal Stability of a RRP Nb 3 Sn Rutherford Cable.

Critical Current versus Transverse Stress and Thermal Stability of a RRP Nb 3 Sn Rutherford Cable. Critical Current versus Transverse Stress and Thermal Stability of a RRP Nb 3 Sn Rutherford Cable. Master assignment report within the MSc. Program Applied Physics carried out within the research chair

More information

Crystal Channeling in Accelerators

Crystal Channeling in Accelerators Crystal Channeling in Accelerators Valery M. Biryukov Institute for High Energy Physics Protvino, Russia EPAC, Edinburgh 27 June 2006 EPAC 2006 V. Biryukov: Crystal Channeling 1 Crystal lattice can trap

More information

ISIS Pulsed Neutron and Muon Source

ISIS Pulsed Neutron and Muon Source ISIS Pulsed Neutron and Muon Source David Findlay Accelerator Division ISIS Department Rutherford Appleton Laboratory PAC-07 June 2007 Albuquerque People: D J Adams, G M Allen, M A Arnold, C J Barton,

More information

Doing business with CERN

Doing business with CERN Doing business with CERN Anders Unnervik Bratislava 24 March 2015 Legal framework CERN, an Intergovernmental Organization, was established in July 1953, by the Convention for the establishment of a European

More information

Energy efficiency of particle accelerators a network in the European program EUCARD-2 M.Seidel, PSI

Energy efficiency of particle accelerators a network in the European program EUCARD-2 M.Seidel, PSI Energy efficiency of particle accelerators a network in the European program EUCARD-2 M.Seidel, PSI 2nd EuCARD-2 Annual Meeting, Barcelona, April 22, 2015 EuCARD-2 is co-funded by the partners and the

More information

Comparison of Carbon and Hi-Z Primary Collimators for Phase 2

Comparison of Carbon and Hi-Z Primary Collimators for Phase 2 Comparison of Carbon and Hi-Z Primary Collimators for Phase 2 Motivation: L. Keller, J. Smith, Th. Weiler 1. Reduce the number of single-diffractive protons lost in the dispersion suppressor. 2. Reduce

More information

Abstract. 1 Introduction. Rachel Bass Grinnell College Mentor: Jim Crittenden Cornell University, CLASSE. August 10, CBETA machine note #021

Abstract. 1 Introduction. Rachel Bass Grinnell College Mentor: Jim Crittenden Cornell University, CLASSE. August 10, CBETA machine note #021 CBETA machine note #021 Comprehensive Tracking Study for the H-Dipoles and Common Magnets in the Splitter Sections of the Cornell/Brookhaven Energy-Recovery-Linac Test Accelerator Rachel Bass Grinnell

More information

The Role of Quench-back in the Passive Quench Protection of Uncoupled Solenoids in Series with and without Coil Sub-division

The Role of Quench-back in the Passive Quench Protection of Uncoupled Solenoids in Series with and without Coil Sub-division MICE Note 322 1 The Role of Quench-back in the Passive Quench Protection of Uncoupled Solenoids in Series with and without Coil Sub-division X. L. Guo, M. A. Green, L. Wang, H. Wu, and H. Pan Abstract

More information

ISOLDE AND N_TOF CONSOLIDATION

ISOLDE AND N_TOF CONSOLIDATION ISOLDE AND N_TOF CONSOLIDATION R. Catherall, CERN, Geneva, Switzerland Abstract The ISOLDE Facility [1] resumed operation in July 2014 providing low energy radioactive ion beams (RIB) to a physics community

More information

RECENT EXPERIMENTAL RESULTS ON AMORPHOUS CARBON COATINGS FOR ELECTRON CLOUD MITIGATION

RECENT EXPERIMENTAL RESULTS ON AMORPHOUS CARBON COATINGS FOR ELECTRON CLOUD MITIGATION OPR02 Proceedings of ECLOUD10, Ithaca, New York, USA RECENT EXPERIMENTAL RESULTS ON AMORPHOUS CARBON COATINGS FOR ELECTRON CLOUD MITIGATION C. Yin Vallgren, S. Calatroni, P. Chiggiato, P. Costa Pinto,

More information

Precise Thermometry for Next Generation LHC Superconducting Magnets

Precise Thermometry for Next Generation LHC Superconducting Magnets 1PoAP-01 1 Precise Thermometry for Next Generation LHC Superconducting Magnets V. Datskov 1, G. Kirby 1, L. Bottura 1, J.C. Perez 1, F. Borgnolutti 1, B. Jenninger 1, P. Ryan 2 Abstract The next generation

More information

Mechanical behavior of a 16 T FCC dipole magnet during a quench

Mechanical behavior of a 16 T FCC dipole magnet during a quench Tampere University of Technology Mechanical behavior of a 16 T FCC dipole magnet during a quench Citation Zhao, J., Stenvall, A., Salmi, T., Gao, Y., & Lorin, C. (2017). Mechanical behavior of a 16 T FCC

More information

TESLA TEST FACILITY (TTF) CRYOSTAT DESIGN AND DEVELOPMENT

TESLA TEST FACILITY (TTF) CRYOSTAT DESIGN AND DEVELOPMENT TESLA TEST FACILITY (TTF) CRYOSTAT DESIGN AND DEVELOPMENT Carlo Pagani, Paolo Pierini, Danilo Barni INFN Milano - LASA, Via Fratelli Cervi 201, 20090 Segrate (Milano), Italy Abstract We present here the

More information

TESLA TEST FACILITY (TTF) CRYOSTAT DESIGN AND DEVELOPMENT

TESLA TEST FACILITY (TTF) CRYOSTAT DESIGN AND DEVELOPMENT TESLA TEST FACILITY (TTF) CRYOSTAT DESIGN AND DEVELOPMENT Carlo Pagani, Paolo Pierini, Danilo Barni INFN Milano - LASA, Via Fratelli Cervi 201, 20090 Segrate (Milano), Italy Abstract We present here the

More information

The DAΦNE Cryogenic System

The DAΦNE Cryogenic System LABORATORI NAZIONALI DI FRASCATI SIS Pubblicazioni LNF 97/046 (IR) 19 Dicembre 1997 The DAΦNE Cryogenic System M. Modena INFN - Laboratori Nazionali di Frascati, P. O. Box 13, I-00044 Frascati (Roma),

More information

ESS CRYOMODULE FOR ELLIPTICAL CAVITIES

ESS CRYOMODULE FOR ELLIPTICAL CAVITIES ESS CRYOMODULE FOR ELLIPTICAL CAVITIES BREAKDOWN OF CRYOGENIC COOLING CIRCUITS Auteur OLIVIER Gilles Date : 03/03/2015 Date : 03/03/2015 Vérifié par BOSLAND Pierre Signature Signature VERSIONS Date 03/03/2015

More information

Cryostats and Cryomodules: Design Choices and Implications

Cryostats and Cryomodules: Design Choices and Implications SPL Meeting CERN July 20 2005 : Design Choices and Implications Paolo Pierini INFN Sezione di Milano LASA Paolo.Pierini@mi.infn.it Outline Cryomodule design, is it starting to be a hot topic? of course

More information

Experiences from First Top-Off Injection At The Stanford Synchrotron Radiation Lightsource

Experiences from First Top-Off Injection At The Stanford Synchrotron Radiation Lightsource SLAC-PUB-13825 October 2009 Experiences from First Top-Off Injection At The Stanford Synchrotron Radiation Lightsource J.M. Bauer *, J.C. Liu, A.A. Prinz, and S.H. Rokni Radiation Protection Department,

More information

An Approach to Reliability Assessment of Complex Systems at CERN

An Approach to Reliability Assessment of Complex Systems at CERN An Approach to Reliability Assessment of Complex Systems at CERN Miriam Blumenschein, CERN Jelena Spasic, PhD., CERN Jens Steckert, CERN Jan Uythoven, PhD., CERN Key Words: Reliability requirements, risk

More information

Disruptions in ITER: Major Catastrophe or Minor Annoyance? Sarah Angelini April 21, 2011

Disruptions in ITER: Major Catastrophe or Minor Annoyance? Sarah Angelini April 21, 2011 Disruptions in ITER: Major Catastrophe or Minor Annoyance? Sarah Angelini April 21, 2011 Disruptions Types of Disruptions Time Scales from the IDDB Thermal Quench Current Quench DINA Simulation Results

More information

Energy Efficiency. 1 Introduction. E. Jensen CERN, Geneva, Switzerland

Energy Efficiency. 1 Introduction. E. Jensen CERN, Geneva, Switzerland Proceedings of the CAS CERN Accelerator School: Free Electron Lasers and Energy Recovery Linacs, Hamburg, Germany, 31 May 10 June 2016, edited by R. Bailey, CERN Yellow Reports: School Proceedings, Vol.

More information

HIGHLY CUSTOMIZED INDUSTRIALIZED LINACS FOR APPLICATIONS IN SCIENTIFIC RESEARCH

HIGHLY CUSTOMIZED INDUSTRIALIZED LINACS FOR APPLICATIONS IN SCIENTIFIC RESEARCH HIGHLY CUSTOMIZED INDUSTRIALIZED LINACS FOR APPLICATIONS IN SCIENTIFIC RESEARCH Christian Piel ACCEL Instruments GmbH, Bergisch Gladbach, Germany Abstract Industrial capabilities and experience in linac

More information

Radiation Environment and Shielding Design Optimization at MEIC

Radiation Environment and Shielding Design Optimization at MEIC Radiation Environment and Shielding Design Optimization at MEIC Pavel Degtiarenko Radiation Physics Group Radiation Control Department, JLab October, 2015 Contents Brief review of MEIC Radiation Protection

More information

Energy efficiency and saving potential analysis of the high intensity proton accelerator HIPA at PSI

Energy efficiency and saving potential analysis of the high intensity proton accelerator HIPA at PSI Journal of Physics: Conference Series PAPER OPEN ACCESS Energy efficiency and saving potential analysis of the high intensity proton accelerator HIPA at PSI To cite this article: A Kovach et al 2017 J.

More information

Design, Material Selection and Operational Feedback for the New Design of the High Energy Beam Dump in the CERN SPS AccApp 17 Quebec, Canada

Design, Material Selection and Operational Feedback for the New Design of the High Energy Beam Dump in the CERN SPS AccApp 17 Quebec, Canada Design, Material Selection and Operational Feedback for the New Design of the High Energy Beam Dump in the CERN SPS AccApp 17 Quebec, Canada P. Rios-Rodriguez, A. Perillo-Marcone, M. Calviani Sources,

More information

Detector Solenoid and Iron Structure

Detector Solenoid and Iron Structure Chapter 11 Detector Solenoid and Iron Structure 11.1 Iron Yoke TheironstructureoftheBelledetector servesasthereturnpathofmagneticfluxandanabsorber material for KLM. It also provides the overall support

More information

CONCEPTUAL SPECIFICATION TCTPH/TCTPV LHC TERTIARY COLLIMATORS WITH BPM WP5

CONCEPTUAL SPECIFICATION TCTPH/TCTPV LHC TERTIARY COLLIMATORS WITH BPM WP5 REV. 0.2 VALIDITY DRAFT REFERENCE : LHC- TCTP- ES- 0001 EDMS NO. xxx CONCEPTUAL SPECIFICATION TCTPH/TCTPV LHC TERTIARY COLLIMATORS WITH BPM WP5 Equipment/system description Tungsten- based tertiary collimators

More information

48 th MEETING OF THE LNF SCIENTIFIC COMMITTEE

48 th MEETING OF THE LNF SCIENTIFIC COMMITTEE 48 th MEETING OF THE LNF SCIENTIFIC COMMITTEE 1. DAΦNE, KLOE and SIDDHARTA... 2 1.1 DAΦNE... 2 1.2 KLOE... 2 1.3 SIDDHARTA... 3 1.4 Recommendations... 3 2. Research Division Activities... 3 2.1 Recommendations...

More information

Overview of Advanced Surface Science activities at CERN. S.Calatroni, M.Taborelli TE-VSC-SCC

Overview of Advanced Surface Science activities at CERN. S.Calatroni, M.Taborelli TE-VSC-SCC Overview of Advanced Surface Science activities at CERN S.Calatroni, M.Taborelli TE-VSC-SCC Basic components of particle accelerators Technology Department 10 October 2014 S. Calatroni & M. Taborelli 2

More information

Soil, Groundwater and Cooling Water

Soil, Groundwater and Cooling Water Laboratory Note DESY D3-114 March 2001 Soil, Groundwater and Cooling Water Activation at the TESLA Beam Dump N. Tesch Deutsches Elektronen-Synchrotron DESY Abstract The main dump system of the linear collider

More information

BEAM PARTICLE SOURCES RESEARCH AT UNIVERSIDAD AUTÓNOMA DE SINALOA

BEAM PARTICLE SOURCES RESEARCH AT UNIVERSIDAD AUTÓNOMA DE SINALOA BEAM PARTICLE SOURCES RESEARCH AT UNIVERSIDAD AUTÓNOMA DE SINALOA XXXI Reunión Anual de la División de Partículas y Campos de la SMF 24/5/2017 Cristhian Valerio Lizarraga,Carlos Duarte, Ildefonso Leon,

More information

Industrialization of Superconducting Accelerator Module Production

Industrialization of Superconducting Accelerator Module Production Technology Transfer and Relations with Industry Industrialization of Superconducting Accelerator Module Production Bernd Petersen DESY MKS acting for the European -Project Cold Linac Accelerator Consortium

More information

Recent progress in multivariate methods for particle physics

Recent progress in multivariate methods for particle physics Recent progress in multivariate methods for particle physics 17 January, 2010 Glen Cowan Physics Department Royal Holloway, University of London g.cowan@rhul.ac.uk www.pp.rhul.ac.uk/~cowan G. Cowan Weizmann

More information

S L H C - PP M I L E S T O N E R E P O R T EU MILESTONE: 7.1. End of Month 14 (May 2009) 29/5/2009

S L H C - PP M I L E S T O N E R E P O R T EU MILESTONE: 7.1. End of Month 14 (May 2009) 29/5/2009 S L H C - PP M I L E S T O N E R E P O R T EU MILESTONE: 7.1 Document identifier: Contractual Date of Delivery to the EC: Actual Date of Delivery to the EC: End of Month 14 (May 2009) 29/5/2009 Document

More information

ESS Target Facility Design. John Haines for the ESS Target Project Team

ESS Target Facility Design. John Haines for the ESS Target Project Team ESS Target Facility Design John Haines for the ESS Target Project Team www.europeanspallationsource.se May 7, 2015 Outline Background Status of technical systems Project status and plans 2 ESS will be

More information

Superconducting Super Collider Laboratory

Superconducting Super Collider Laboratory 5SCL-Preprint-431 May 1993 Distribution Category: 400 SSC String Test Facility for Superconducting Magnets: Testing Capabilities and Program for Collider Magnets P. Kraushaar W. Burgett T. Dombeck A. McInturff

More information

Prospects of MgB 2 Superconductor in Energy and Magnet Applications

Prospects of MgB 2 Superconductor in Energy and Magnet Applications Prospects of MgB 2 Superconductor in Energy and Magnet Applications S. Berta, S. Brisigotti, V. Cubeda, M. Palombo, D. Pietranera, L. Rostila, A. Tumino, and G. Grasso November 4 th, 2010 Outline Considerations

More information

Study on the International Linear Collider Beam Dump by plasma-wakefield deceleration

Study on the International Linear Collider Beam Dump by plasma-wakefield deceleration Study on the International Linear Collider Beam Dump by plasma-wakefield deceleration T. Saeki, J. Fujimoto, H. Hayano, K. Yokoya (KEK/Sokendai) T. Tajima, D. Farinella, X. Zhang (University of California

More information

High performance radio frequency generator technology for the Thermo Scientific icap 7000 Plus Series ICP-OES

High performance radio frequency generator technology for the Thermo Scientific icap 7000 Plus Series ICP-OES TECHNICAL NOTE 43334 High performance radio frequency generator technology for the Thermo Scientific icap 7000 Plus Series ICP-OES Keywords Free-running, Plasma, RF generator, Solid-state Using inductively

More information

Recent Developments in IBA Carbon Accelerator

Recent Developments in IBA Carbon Accelerator Recent Developments in IBA Carbon Accelerator Damien BERTRAND Domain Expert Hadrontherapy Erice Workshop on Hadrontherapy May 20-27, 2011 Clinical basis of Hadrontherapy NIRS (Chiba, Japan) Synchrotron

More information

Current Status of the KSTAR TF Superconducting Magnet Development

Current Status of the KSTAR TF Superconducting Magnet Development Journal of the Korean Physical Society, Vol. 49, December 2006, pp. S240 S244 Current Status of the KSTAR TF Superconducting Magnet Development B. S. Lim, J. Y. Choi, S. Lee, C. S. Kim, I. S. Woo, D. J.

More information

Doing business with CERN Czech Republic and CERN. Anders Unnervik 23 October 2012

Doing business with CERN Czech Republic and CERN. Anders Unnervik 23 October 2012 Doing business with CERN Czech Republic and CERN Anders Unnervik 23 October 2012 Legal framework CERN, an Intergovernmental Organization, was established in July 1953, by the Convention for the establishment

More information

Asynchronous Beam Dump

Asynchronous Beam Dump L. Keller, SLAC Phase 2 Specification and Implementation Meeting, 28 November, 28 Asynchronous Beam Dump Impact Secondary Collimator 6R7 @ 7 TeV Estimate Energy Deposition and Instantaneous Temperature

More information

Interface LINAC ID 25 Risk Assessments ID 26, ID 27, ID 28 Mitigation of Risks

Interface LINAC ID 25 Risk Assessments ID 26, ID 27, ID 28 Mitigation of Risks Interface LINAC ID 25 Risk Assessments ID 26, ID 27, ID 28 Mitigation of Risks European Spallation Source ESS AB Visiting address: Stora Algatan 4 P.O. Box 176 SE-221 00 Lund SWEDEN www.esss.se SUMMARY

More information

PROGRESS ON THE SECTOR MAGNETS FOR THE RIKEN SRC

PROGRESS ON THE SECTOR MAGNETS FOR THE RIKEN SRC PROGRESS ON THE SECTOR MAGNETS FOR THE RIKEN SRC A. Goto, H. Okuno, J. Ohnishi, N. Fukunishi, T. Mitsumoto, S. Fujishima, T. Tominaka, K. Ikegami, Y. Miyazawa, and Y. Yano, RIKEN, Wako, Saitama 351-0198,

More information

Civil Construction: Buildings and Supply Systems

Civil Construction: Buildings and Supply Systems Civil Construction: Buildings and Supply Systems The following is a description of the building complex for the new facility. It reflects the current status of the planning activities. The arrangement

More information

J PARC neutrino Cryogenics system

J PARC neutrino Cryogenics system J PARC neutrino Cryogenics system 1. Purpose of T2K experiment J-PARC (Japan Proton Accelerator Research Complex) Material and Life Science Facility Hadron Experimental Facility Transmutation Experimental

More information

Use Of Plasma Window For Enhanced Ion Beam Transmission From Vacuum To Air

Use Of Plasma Window For Enhanced Ion Beam Transmission From Vacuum To Air Use Of Plasma Window For Enhanced Ion Beam Transmission From Vacuum To Air K. Govender, C.B. Franklyn Radiation Utilisation Department, Nuclear Technology Group, Necsa, South Africa E-mail address of main

More information

A. Hershcovitch, M. Blaskiewicz, J.M. Brennan, W. Fischer, C-J Liaw, W. Meng, R. Todd Brookhaven National Laboratory, Upton, New York 11973, U.S.A A.

A. Hershcovitch, M. Blaskiewicz, J.M. Brennan, W. Fischer, C-J Liaw, W. Meng, R. Todd Brookhaven National Laboratory, Upton, New York 11973, U.S.A A. Novel Device for In-Situ Thick Coatings of Long, Small Diameter Accelerator Vacuum Tubes A. Hershcovitch, M. Blaskiewicz, J.M. Brennan, W. Fischer, C-J Liaw, W. Meng, R. Todd Brookhaven National Laboratory,

More information

RF Breakdown Studies in Tungsten and Copper Structures

RF Breakdown Studies in Tungsten and Copper Structures SLAC-PUB-12050 August 2006 RF Breakdown Studies in Tungsten and Copper Structures 1 L. Laurent, 1 C. Adolphsen, 1 S. Beebe, 3 S. Döbert, 2 N.C. Luhmann, Jr., 1 C. Pearson, 3 J.A. Rodriguez, 1 G. Scheitrum,

More information

3 Month Look Ahead & Long Shutdown Schedule Status. 13 September 2012 Dianne Napier Pat Collins/C. Fragapane

3 Month Look Ahead & Long Shutdown Schedule Status. 13 September 2012 Dianne Napier Pat Collins/C. Fragapane 3 Month Look Ahead & Long Shutdown Schedule Status 13 September 2012 Dianne Napier Pat Collins/C. Fragapane 3 Month Look Ahead Baseline, Progress & Files Change Request List 3 Month Look Ahead (Sept, Oct,

More information

GREEN. Energy for Innovation and Innovation in Energy. CLIC SCHEMATIC (not to scale) LAPP/IN2P3-KEK

GREEN. Energy for Innovation and Innovation in Energy. CLIC SCHEMATIC (not to scale) LAPP/IN2P3-KEK 100m INJECTION TUNNEL LHC Energy for Innovation and Innovation in Energy GREEN e+ INJECTION DESCENT TUNNEL e- INJECTION DESCENT TUNNEL COMBINER RINGS DRIVE BEAM INJECTOR BYPASS TUNNEL DRIVE BEAM LOOPS

More information

CONDUCTION-COOLED 60 A RESISTIVE CURRENT LEADS FOR LHC DIPOLE CORRECTORS

CONDUCTION-COOLED 60 A RESISTIVE CURRENT LEADS FOR LHC DIPOLE CORRECTORS EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics Large Hadron Collider Project LHC Project Report 691 CONDUCTION-COOLED 60 A RESISTIVE CURRENT LEADS FOR LHC DIPOLE CORRECTORS

More information

Measurement Probe Brochures

Measurement Probe Brochures Measurement Probe Brochures Papers Cryogenic News March 2012 World s first 18 Tesla Cryogen Free VSM Measurement system with sample rotating He-3 insert Cryocooled Cryostat For Use With Ccc/Josephson Array

More information

A VARIABLE-ENERGY CW COMPACT ACCELERATOR FOR ION CANCER THERAPY

A VARIABLE-ENERGY CW COMPACT ACCELERATOR FOR ION CANCER THERAPY FERMILAB-CONF-16-077-AD Accepted A VARIABLE-ENERGY CW COMPACT ACCELERATOR FOR ION CANCER THERAPY ABSTRACT C. Johnstone Fermi National Accelerator Laboratory Fermi National Accelerator Lab, Batavia, IL

More information

EXPERIENCE WITH PERMANENT MAGNETS IN THE FERMILAB 8 GeV LINE AND RECYCLER RING

EXPERIENCE WITH PERMANENT MAGNETS IN THE FERMILAB 8 GeV LINE AND RECYCLER RING EXPERIENCE WITH PERMANENT MAGNETS IN THE FERMILAB 8 GeV LINE AND RECYCLER RING G.W. Foster rmi National Accelerator Laboratory [1], MS 345, P.O. Box 5, Batavia, IL 51 USA Abstract rmilab is in the midst

More information

Operation of the Levitated Dipole Experiment Floating Coil

Operation of the Levitated Dipole Experiment Floating Coil > THA11P002 < 1 Operation of the Levitated Dipole Experiment Floating Coil A. Zhukovsky, D. Garnier Abstract The Levitated Dipole Experiment (LDX) is an innovative facility to study plasma confinement

More information