REEVALUATIONS OF NEPA DOCUMENTS

Size: px
Start display at page:

Download "REEVALUATIONS OF NEPA DOCUMENTS"

Transcription

1 REEVALUATIONS OF NEPA DOCUMENTS Requested by: American Association of State Highway and Transportation Officials (AASHTO) Standing Committee on Environment Prepared by: ICF Consulting Fairfax, VA March 2008 The information contained in this report was prepared as part of NCHRP Project 25-25, Task 28, National Cooperative Highway Research Program, Transportation Research Board.

2

3 Acknowledgements This study was requested by the American Association of State Highway and Transportation Officials (AASHTO), and conducted as part of National Cooperative Highway Research Program (NCHRP) Project The NCHRP is supported by annual voluntary contributions from the state Departments of Transportation. Project is intended to fund quick response studies on behalf of the AASHTO Standing Committee on Environment. The report was prepared by ICF International. The study Principal Investigators were Matthew Barkley and John Hansel of ICF International. The work was guided by a task group chaired by Alfredo Acoff (Alabama DOT), Jonathon Cox (Georgia DOT), Keith Hall (Connecticut DOT), John Mettille (Kentucky DOT), Steve Reed (New Mexico DOT), Andrea Stevenson (Ohio DOT), Lamar Smith (U.S. DOT), and Danna Powell (NCHRP). The project was managed by Christopher Hedges, NCHRP Senior Program Officer. Disclaimer The opinions and conclusions expressed or implied are those of the research agency that performed the research and are not necessarily those of the Transportation Research Board or its sponsors. This report has not been reviewed or accepted by the Transportation Research Board s Executive Committee or the Governing Board of the National Research Council.

4

5 CONTENTS EXECUTIVE SUMMARY 1 1 INTRODUCTION Overview and Purpose Research Methodology Report Organization 4 2 REEVALUATION REGULATORY FRAMEWORK AND LEGAL CONSIDERATIONS Summary of Reevaluation Regulations, Policy, and Guidance Reevaluation Case Law 7 3 STATUS OF THE REEVALUATION PROCESS Summary of State DOT Survey Responses Best Practices Challenges and Areas for Improvement 14 4 RECOMMENDED GUIDANCE AND PROCESSES FOR CONDUCTING REEVALUATIONS Projects With Categorical Exclusion Designations Projects With Completed Environmental Assessments Projects With Completed Environmental Impact Statements 17 5 CONCLUSIONS 20 APPENDIX A: COURT CASE SUMMARIES 21 APPENDIX B: SURVEY QUESTIONS FOR STATE DOTS 35 APPENDIX C: SAMPLE REEVALUATION FORMS 36 APPENDIX D: SAMPLE REEVALUATION OF A FINAL ENVIRONMENTAL IMPACT STATEMENT 60 REFERENCES 77 NCHRP Project 25-25, Task 28

6 NCHRP Project 25-25, Task 28

7 EXECUTIVE SUMMARY Since the enactment of the National Environmental Policy Act (NEPA), federal agencies have consistently been encouraged to complete environmental impact analyses as early as possible in their project planning processes. FHWA has clearly tried to follow this mandate, but because its project development process can frequently span several years and contain multiple decision points, the initial NEPA document can become outdated or stale in its ability to support subsequent decisions. For example, changes can occur over time in the design of the project, the environmental requirements applicable to the project, or within the environment in which the project will be located. Consequently, FHWA and the state transportation agencies (hereafter state DOTs) who partner with FHWA in the preparation of NEPA documents must frequently check to see if an aging NEPA document remains current in light of a pending project development decisions. FHWA refers to these checks as reevaluations. Although FHWA has established a requirement to reevaluate its NEPA documents, it has provided little guidance to its field offices or the state DOTs on how to satisfy this requirement. Accordingly, questions have arisen on how well this decentralized approach to reevaluations is working across the states. This study was designed to review current performance, identify problems as well as best practices, and provide any process recommendations, if applicable. The study found that most of the twenty-seven state DOTs that responded to the survey are not experiencing significant problems in conducting reevaluations. Where problems have existed, several state DOTs worked closely with their FHWA Division Offices to develop solutions. These solutions have frequently included agreed upon forms and formats for conducting and documenting reevaluations as well as the establishment of maximum timeframes, such as one year, after which a new reevaluation would be necessary. Several examples of these best practices are provided in this study and most are readily available on state DOT websites. Consequently, any state DOT or FHWA office that continues to experience reevaluation problems can find a variety of successful approaches. Most importantly, close coordination and consultation between a state DOT and its FHWA Division Office coupled with staff training on conducting reevaluations appear to be the key ingredients to effectively streamlining and completing the reevaluation process. One very important reason for getting reevaluations right, especially written reevaluations, is that they can save FHWA and state DOTs time and money, as demonstrated by recent federal court decisions. The courts continue to view revaluations for environmental impact statements (EIS) as an effective tool for determining and documenting why an existing NEPA document remains valid and does not need to undergo potentially costly and time consuming supplementation. The federal courts, however, have also been clear in reminding federal agencies that reevaluations are not NEPA documents, but rather decision documents on whether or not an EIS requires supplementation. Consequently, an agency can neither use a reevaluation in an attempt to remedy any gaps in the impact analysis that should have been addressed in the original NEPA document, nor offer to do a reevaluation as a defense to postponing a challenge to a completed NEPA document, such as a final EIS. NCHRP Project 08-36, Task 35 1

8 1 INTRODUCTION 1.1 Overview and Purpose A reevaluation is an analysis of the changes in a project or existing environment at specified times in the Project Development Process (PDP). 1 The PDP includes multiple decision points such as final design, right-of-way acquisition, and bid letting. Each of these decision points requires the state DOTs and FHWA to reevaluate the NEPA document, NEPA decision, and potentially any related environmental studies. Reevaluations need to be performed when and anytime there has been little activity on a project or prior to requesting FHWA to take an action. 2 Reevaluations can serve as an efficient and effective means for evaluating design changes or addressing circumstances that develop after a NEPA decision is rendered. However, if the requirements and intent of the reevaluation process are not properly understood and managed, reevaluations also can create challenges for state DOTs as they strive to deliver projects on budget and on schedule. In an effort to prevent delays, many state DOTs initiate the NEPA process and corresponding environmental studies as early as possible during the planning stage of project development. The NEPA process, environmental studies, and an initial design are often completed long before the project will go to construction. As time passes, changes in land use, threatened and endangered species, historic properties, environmental laws and regulations, and other resource areas can occur. The public s perception of environmental issues, industry standards, and methods for conducting environmental analyses can also change. A reevaluation can be an effective means for evaluating such changes and can assist state DOTs in determining if additional NEPA documentation and environmental studies are required. Typically, the NEPA process for a transportation project relies on conceptual level design and engineering data. Once environmental studies are complete and a NEPA decision is rendered, detailed final design and engineering data are developed. Differences often occur between the conceptual design evaluated in the environmental studies and NEPA process and the post-nepa process final design and engineering phase of a project. A reevaluation provides an effective means for evaluating the design changes relative to previous environmental analyses conducted pursuant to NEPA. Aside from design changes, other changes can lead to reevaluations of NEPA documents and supporting studies. For example, NEPA documents and corresponding environmental studies are required to address the full length and scope of a proposed action, which often require years to fund and construct. 3 During this time, changes can occur in terms of land use, project design, or even in the funding mechanism itself. For example, a project may be developed and the initial segment constructed through a traditional funding mechanism and the standard design-bid-build process. However, tolling and use of a design-build process may provide a means to accelerate construction of other segments of the project. Use of tolling can result in the need for additional analyses of impacts associated with environmental justice, light, air quality or noise depending on the specific project location and means for collecting tolls. 1 Draft: Reevaluation of Environmental Documents: FHWA Office of NEPA Facilitation in conjunction with an unknown FHWA Division Office. Posted on the RE: NEPA website on August 5, 2002 as a reply to the Reevaluation Process 23 CFR thread. 2 Lamar Smith s August 30, 2006 reply to the FONSI Reevaluation thread included under NEPA Process and Evaluation heading on the RE: NEPA website ( Retrieved on October 26, CFR (f)(1-3) NCHRP Project 08-36, Task 35 2

9 In addition to tolling and other innovative financing options, many state DOTs are using the design-build method of project delivery to reduce project costs and to complete projects faster. The design-build project delivery method can result in substantial deviations from the design concepts analyzed in the NEPA/environmental process. Reevaluations provide a means for addressing these types of changes and ensuring environmental compliance. Many factors influence the level of detail and types of analyses required for a reevaluation. Likewise, different state DOTs and FHWA Divisions employ different policies, procedures, and processes for completing reevaluations. The purpose of this study is to identify and expand upon state DOT and FHWA Division Best Practices, and recommend guidance to more universally establish and apply more systematic and standardized reevaluation processes. Standardized processes and guidelines can reduce uncertainty and inter-agency review times while minimizing disagreements over content. 1.2 Research Methodology This research was conducted in four steps: a literature review, a review of current case law, an survey of state DOTs, and interviews with state DOT and FHWA staff. These research steps were conducted in sequential order, with overlap between some steps Literature Review We reviewed federal policies, regulations, and available guidance related to NEPA reevaluations and the reevaluation process. Materials reviewed included: Council on Environmental Quality Executive Office of the President (CEQ) Regulations for Implementing the Procedural Provisions of the National Environmental Policy Act, 40 CFR CEQ Memorandum, Forty Most Asked Questions Concerning CEQ s NEPA Regulations (1992) FHWA Environmental Impact and Related Procedures, 23 CFR 771 FHWA Technical Advisory T A (1987) FHWA Guidance Memo, Project Development and Documentation Overview (1992) FHWA Draft Guidance Document, Reevaluation of Environmental Documents (2002) SAFETEA-LU Environmental Review Process, Final Guidance, FHWA (2006) FHWA Re: NEPA Website: Questions/Comments and Responses related to NPEA Reevaluations ( ) Recent Case Law Review In conjunction with the literature review described above, we also conducted a review of recent case law related to reevaluations. We used the Lexis service offered by LexisNexis to search state and federal cases decided between January 2000 and October Using different combinations of specific reevaluation terms and by varying the search criteria, we identified twenty different cases that were potentially relevant to reevaluations. We reviewed these twenty cases and identified twelve of them in which a reevaluation was either a substantive issue or affected the outcome. Appendix A of this study contains a summary of each of these twelve cases. NCHRP Project 08-36, Task 35 3

10 1.2.3 Survey of State DOTs A survey request was ed to all DOTs in early September 2007 with a due date of two weeks from receipt. The state DOT contacts with primary NEPA responsibility were identified from a directory on the website for the AASHTO Center for Environmental Excellence. A follow up request was sent to the non-responding states with a due date of October 1, By the conclusion of the survey period, responses were received from twenty-seven states. Appendix B of this study contains a list of the survey questions Follow-up Activities with State DOT and FHWA Staff After reviewing the responses to the survey, telephone interviews were conducted with twelve of the responding state DOTs. The twelve were selected on the basis of survey responses that contained information on relevant subjects such as problems being experienced, unique approaches to conducting reevaluations, or possible best practices. Following the telephone interviews with state DOTs, environmental staff in six FHWA Division Offices were interviewed. The six were selected based upon their close involvement with and expertise on reevaluations, as recommended by the interviewed state DOTs. An additional interview was subsequently conducted with an FHWA Headquarters expert on reevaluations. 1.3 Report Organization The remainder of this report is organized in four sections. Sections 2 establishes the reevaluation regulatory framework and legal considerations; Section 3 describes the current state of the reevaluation process including challenges and best practices; and Section 4 recommends reevaluation guidance and processes for conducting reevaluations. Section 5 is a discussion of general conclusions. The appendices contain summaries of recent federal court cases involving reevaluations, the survey questions, samples of reevaluation forms and formats used by several state DOTs, and pertinent reference materials on reevaluations. NCHRP Project 08-36, Task 35 4

11 2 REEVALUATION REGULATORY FRAMEWORK AND LEGAL CONSIDERATIONS 2.1 Summary of Reevaluation Regulations, Policy, and Guidance The National Environmental Policy Act (NEPA) established the nation s policy on environmental protection and created the Council on Environmental Quality (CEQ). The NEPA process is intended to help federal officials make decisions that are based on an understanding of environmental consequences, and take actions that protect, restore, and enhance the environment [40 CFR (c)]. CEQ issued Regulations for Implementing the Procedural Provisions of the National Environmental Policy Act (40 Code of Federal Regulations [CFR] ) pursuant to NEPA. CEQ s regulations provide the direction to achieve the purpose of NEPA [40 CFR (c)] CEQ s NEPA Regulations From a broad perspective, CEQ s NEPA-implementing regulations instruct federal agencies on how to comply with NEPA primarily for those actions that require an environmental impact statement. The regulations also require federal agencies to adopt their own procedures to supplement the NEPA regulations, as necessary. At a more detailed level, CEQ s regulations define timelines, establish content requirements, and describe specific types of actions and the associated levels of environmental reviews. In terms of reevaluations, the CEQ regulations do not specifically reference this practice. Rather, CEQ s regulations define when an agency shall supplement an Environmental Impact Statement (EIS). The requirement for supplementing an EIS, as presented in CEQ s NEPA regulations, establishes a management need for the concept and practice of NEPA reevaluations and, therefore, this CEQ prescription provides valuable insight into the purpose behind conducting a reevaluation. Section of CEQ s regulations discusses draft, final, and supplemental [environment impact] statements. The following language prescribes when an agency must supplement an EIS: (c) Agencies: (1) Shall prepare supplements to either draft or final environmental impact statements if: (i) (ii) The agency makes substantial changes in the proposed action that are relevant to environmental concerns; or There are significant new circumstances or information relevant to environmental concerns and bearing on the proposed action and its impacts. Through this language, CEQ established two situations that require a federal agency to add to its environmental analysis: 1) when substantial changes are made to the proposed action causing new or different environmental impacts; or 2) when new environmental data or circumstances arise and are related to impacts associated with the proposed action. Although not explicitly stated in the above CEQ provision, in order for federal agencies to meet its intent, they must have in place a management process or tool that periodically reassess the impacts of a proposed action and the environment in which the action would occur. This management need establishes the basis for the FHWA reevaluation process. NCHRP Project 08-36, Task 35 5

12 2.1.2 FHWA Regulations (23 CFR 771) In response to CEQ s NEPA regulations, FHWA established its own agency-specific NEPA procedures in FHWA s regulations, titled Environmental Impact and Related Procedures apply to FHWA and the Federal Transit Administration (FTA). Unlike CEQ s regulations, FHWA s regulations use the term reevaluation and describe reevaluations as follows : Reevaluations (a) A written evaluation of the draft EIS shall be prepared by the applicant in cooperation with the Administration if an acceptable final EIS is not submitted to the Administration within 3 years from the date of the draft EIS circulation. The purpose of this evaluation is to determine whether or not a supplement to the draft EIS or a new draft EIS is needed. (b) A written evaluation of the final EIS will be required before further approvals may be granted if major steps to advance the action (e.g., authority to undertake final design, authority to acquire a significant portion of the right-of-way, or approval of the plans, specifications and estimates) have not occurred within three years after the approval of the final EIS, final EIS supplement, or the last major Administration approval or grant. (c) After approval of the EIS, FONSI, or CE designation, the applicant shall consult with the Administration prior to requesting any major approvals or grants to establish whether or not the approved environmental document or CE designation remains valid for the requested Administration action. These consultations will be documented when determined necessary by the Administration. Consistent with CEQ regulations, FHWA s procedures discuss specific procedures for reevaluating draft and final EISs. FHWA s procedures also address when a supplemental EIS is or is not required. However, Categorical Exclusion (CE) and Finding of No Significant Impact (FONSI) designations apply to the vast majority of state DOT transportation improvement projects. The procedures for reevaluating the applicability of CE and FONSI designations are less straightforward lacking specific time frames and definition. As described in subparagraph (c) above, the applicant (state DOT) shall consult with FHWA prior to requesting any major approvals to determine if the previously approved environmental document remains valid. According to the regulations, FHWA must decide when such consultation should be documented. In the Federal Register of August 7, 2007 and on page 44039, FHWA and FTA published proposed changes to their NEPA procedures. A minor change was proposed to the above section on reevaluations and this change would reorder the paragraphs so that the current last paragraph (c) would be moved to the first paragraph of the section. The purpose for this re-ordering is to place a stronger emphasis on the need to perform timely reevaluations of all NEPA documents and to differentiate when consultation with FHWA is required from the need for a written reevaluation FHWA Technical Advisory T A In October 1987, FHWA published a Technical Advisory (TA) document T A. The TA provides guidance to FHWA personnel and applicants on the preparation and processing of environmental (e.g. NEPA) and Section 4(f) documents. Although focused on reevaluations for Draft and Final EISs, FHWA s TA does provide guidance in terms of reevaluation content which can be applied to a reevaluation of any type of NEPA document. The TA indicates that a reevaluation should, focus on the changes in the project, its surroundings and impacts, and any new issues identified since the draft EIS [or other environmental decision such as a CE designation or FONSI determination]. FHWA s TA also NCHRP Project 08-36, Task 35 6

13 suggests that field reviews, additional studies (as necessary), and coordination (as appropriate) with other agencies should be undertaken and the results included in the written evaluation. However, the TA does not prescribe a specific format for reevaluations and leaves room for interpretation on important reevaluation issues such as level of detail, agency consultation requirements, and public involvement. However, this lack of specificity also allows considerable flexibility for the state DOTs to work with FHWA to satisfy the requirements on a case-by-case basis considering the context of each situation FHWA Project Development and Documentation Overview In 1992, FHWA published a document titled, Project Development and Documentation Overview. In this document, FHWA defined reevaluation as an assessment of any changes which may have occurred in either the project's concept or the affected environment, and a determination of what effects these changes might have on the validity of the environmental documentation. Consistent with (c), this document also reiterated that reevaluation requirements apply to all levels of NEPA documentation not just EISs. However, like FHWA s TA, this document does not provide additional guidance on how to conduct reevaluations, content requirements, or roles and responsibilities. The References section at the end of this study contains additional information on the FHWA regulations, policies, and guidance related to reevaluations. 2.2 Reevaluation Case Law A summary of each of the twelve most relevant cases is included in Appendix A of this study. Ten of these cases involved litigation over federal highway projects; one involved a U. S. Forest Service timber sale; and the other was filed against the U. S. Army Corps of Engineers over a dredging project. The six cases in which the federal government prevailed are presented first in Appendix A and in chronological order from the most recent to the oldest. The six cases in which the federal government did not prevail follow and are presented in a similar chronological sequence. We noted several common themes from this case law review: Although reevaluations are not a component of the CEQ regulations, the courts continue to view a reevaluation as a legitimate tool for determining whether or not an existing NEPA document needs to be supplemented. Consequently, a properly completed reevaluation serves an important role in an agency s administrative record by documenting the reconsideration of environmental impacts and changed circumstances. Unlike an environmental impact statement, an environmental assessment, or a categorical exclusion designation, a reevaluation is not a NEPA document. Consequently, a reevaluation cannot be a substitute for a NEPA document and present information and analysis that should have been in the original or a supplemental NEPA document. For a reevaluation to be viewed as acceptable by a court, it must have been completed in accordance with the federal agency s procedures for completing reevaluations. A reevaluation must take a hard look at any changed circumstances or new information before reaching its conclusion. A reevaluation must be completed prior to a project decision being made and not subsequent to that decision and in anticipation of litigation. NCHRP Project 08-36, Task 35 7

14 The government cannot successfully postpone a challenge to the adequacy of an existing NEPA document on the basis that the document will be the subject of a reevaluation because the judicial review of the reevaluation is limited to the actions taken in reevaluating the existing document. A supplemental EIS is required when new circumstances present a seriously different picture of the environmental impact of the proposed project from what was previously envisioned. Plaintiff s burden is to demonstrate how a revised design would result in substantial changes in environmental impacts. The FHWA regulations do not require that an EIS be supplemented every three years but that a reevaluation of the EIS must be conducted every three years. NCHRP Project 08-36, Task 35 8

15 3 STATUS OF THE REEVALUATION PROCESS 3.1 Summary of State DOT Survey Responses As was indicated above in the description of the research methodology, twenty-seven state DOTs responded to the survey. Following is a summary of the states responses to each survey question. Do you have a formal process in place for conducting reevaluations of NEPA documents? Eleven states said they do not have a process in place and rely on the FHWA regulatory provisions. Sixteen states replied that they do have a process in place. The majority of these sixteen states post their process on their agency s websites and as part of their NEPA implementation guidance and training manuals. Do you have guidance and/or do you conduct training on reevaluating NEPA documents and the reevaluation process? Twenty states do not conduct training on reevaluations and seven said that they do. When training is provided on conducting reevaluations, this training is normally a small component of a state DOT s comprehensive NEPA implementation training. Who is responsible for identifying the need for a reevaluation? With the exception of CA, all of the state DOTs responded that any decision reached is done in consultation with FHWA. CA independently makes this decision based on a delegation from FHWA. CA senior environmental planners perform this function. Ten states responded that they rely on district or regional offices to formulate the recommendation to FHWA, and fifteen states specifically involve environmental staff in a lead role. What criteria are used to determine whether a reevaluation is needed? Almost all of the responding states rely solely on the FHWA criteria contained in 23 CFR However, three state DOTs reevaluate after a one year period expires between major project phases, and one state DOT uses a six month period. When a reevaluation occurs, who determines the need for any additional environmental studies, inter-agency coordination and/or public involvement? Again, with the exception of CA, all of the other states responded that these determinations are made in consultation with FHWA and with FHWA having the deciding role. CA now independently makes these determinations based on a delegation from FHWA. CA senior environmental planners perform this function. Unlike the decentralized responsibility for determining the need for a reevaluation, these additional analyses determinations are more frequently centralized at the state DOT s headquarters office. Also, although environmental staffs are consulted, they are not as frequently in the lead role. In nine states, NCHRP Project 08-36, Task 35 9

16 environmental staffs play a lead role, but in the majority of the state DOTs, project engineers and other supervisory staff are the key decision makers for such determinations. What environmental resources or other factors typically require additional studies, coordination, or public involvement? The most commonly stated factor was a change in alignment. Regulatory changes were the second most frequently mentioned factor. In terms of environmental resources that typically require additional studies, cultural resources were the most frequently mentioned; they were mentioned by ten states. New endangered species listings were next with eight states so responding. Wetlands determinations ranked third with four states listing them. The need to further study these types of site specific resources logically follows from alignment changes. No state DOTs indicated that completing additional public involvement was a common occurrence in its reevaluation process. States tend to review on a case by case basis the status of any public concerns as part of a reevaluation but rarely initiate additional public involvement for NEPA implementation purposes. Rather, state DOTs inform the public of the results of a reevaluation through any remaining public involvement processes that they normally conduct as part of right of way acquisition or final design. Approximately what percentage of your projects requires reevaluation? Of those projects reevaluated, approximately what percentages are for projects where the NEPA document being reevaluated is: (a) a categorical exclusion, (b) an environmental assessment, or (c) an environmental impact statement? Four states were not able to provide data. Of the twenty-three state DOTs that did provide some data or estimates, four indicated that less than one percent of their projects require a reevaluation while another four states said one hundred percent of their projects do. Another two states were at the ninety-five percentile. Thirteen of the twenty-three reporting states were below the twenty-five percentile. For those states with the highest percentages of projects requiring reevaluations, the reason given for these high numbers during the follow up interviews was the occurrence of substantial project delays due to lack of funding. Smaller projects can move up and down the priority list from budget year to budget year until a budget fit is found. Larger more costly projects are broken into logical phases and funded in stages over many years. The NEPA document cited most frequently as needing reevaluation was the categorical exclusion. Seven states so reported. This follow s from the year to year budget juggling that a smaller project may undergo. Another six states stated that there was no percentage difference between categorical exclusions, EAs, or EISs. Four states indicated that EISs were their most frequently reevaluated NEPA document. How is a completed reevaluation documented? What is the typical level or amount of documentation, i.e., a one-pager, a less than 10 page analysis, or a more lengthy analysis? The NEPA document that is most likely to be reevaluated with a one pager is a categorical exclusion. As expected, the number of pages necessary to reevaluate an EA or an EIS can vary considerably based upon the magnitude of the changes. EA reevaluations were generally noted to be less than ten pages and EIS reevaluations were over ten pages. Seven State DOTs indicated that they have developed standard forms or formats for documenting their reevaluations. NCHRP Project 08-36, Task 35 10

17 Do you track your revaluations in a management system and, if so, how is this done? There was almost an even split between the states. Fourteen states tracked reevaluations in a management system and thirteen did not. What role do reevaluations play in tracking environmental commitments? Five states indicated that reevaluations did not play any role in tracking environmental commitments. The most frequent response was that reevaluations serve as a cross check on the status of commitments which are primarily tracked in more comprehensive project management databases. In addition to updating a project s NEPA compliance status, have you experienced any other project management or implementation benefits from your agency s reevaluation process? If so, please describe them. Sixteen states responded that they had not experienced any other benefits. Of the states reporting benefits, these benefits included: keeping the public up to date on the project; keeping the agency up to date on public opinion; prompting intra-departmental coordination on commitment status; assisting in permit compliance; identifying inefficiencies in the original NEPA analyses; and allowing mitigation measures and design features to be more specifically tailored to a better understanding of a project s impacts. Has your agency encountered any problems in conducting reevaluations? If so, please describe them. Two thirds of the responding states or eighteen said that they were not encountering any problems. From those states reporting problems, the cited problems included: inconsistent practices between state-level district office staff and FHWA personnel; inability to readily reach agreement with FHWA on the need for a reevaluation and its content; rapidly changing guidance and regulations; determining the optimum point in the design phase to initiate a reevaluation, e.g., 30% design completion; different requirements between CEQ and FHWA on when to supplement an EIS; reevaluation review times causing project delays; project changes being made late in project development or not timely communicating changes to the environmental review team. Has your agency been able to develop any practices or procedures that overcome encountered problems? If so, please describe them in detail so that they may be considered for inclusion as best practices. Twelve states did not offer any practices or procedures and these states were generally the ones reporting no problems in conducting reevaluations. A discussion of the reported best practices follows immediately below is section Best Practices Best practices were identified from a review of the state DOT survey responses, a review of the NEPA guidance posted on state DOT websites, and interviews with state DOT and FHWA staff. The resulting groupings of best practices address problems with the timely initiation of reevaluations by state DOT s, inconsistent approaches between a state DOT s regions or districts, project delays due to lengthy review times, and disagreements between state DOTs and FHWA on the need for and content of written reevaluations. NCHRP Project 08-36, Task 35 11

18 3.2.1 Timeliness In terms of the timely initiation of reevaluations, several states use computer based scheduling software to remind project managers when a reevaluation deadline is approaching. Reevaluation completion dates are also entered and automatically shared with other project management and budgeting systems. Additionally, to provide as much lead time as possible for completing either a complex reevaluation or a supplemental NEPA document, a few states have established a one year reevaluation requirement as opposed to the FHWA s three year period. (One state DOT employs a six-month standard.) This one year review is applied to all NEPA documents and not just EISs, Unlike a calendar date standard, the timely initiation of reevaluations caused by project changes can be more difficult to address in that project changes do not lend themselves to an automated approach. Rather, project changes must be communicated as soon as possible by the design and engineering staffs to the state DOT staff responsible for completing reevaluations. Staff training that emphasizes early communication is one approach that some states have taken. The NEPA once and done mentality is specifically countered. One interviewed state promotes early intra-office coordination and communication of project changes by emphasizing the time savings and workload benefits of properly completed reevaluations. That is, a concise revaluation is a proven tool that can reasonably eliminate the much larger investment of time and work involved in the alternative approach, i.e., supplementing the existing NEPA document Consistency The problem of inconsistent preparation of reevaluations between a state DOT s district offices is being addressed in a variety of ways. The most common approach is through training and written guidance on how to document a reevaluation. The former is normally conducted as part of a state DOT s staff NEPA training and the latter is posted on NEPA websites. A few of the responding states have gone farther and developed standard formats and forms for documenting reevaluations. Several examples are contained in Appendix C of this study. Interviewed state staff consistently cited the development of these types of reporting formats as their most successful approach in achieving consistent and high quality reevaluations. An important and additional benefit of achieving consistency in the preparation of reevaluations is that the subsequent review and comment periods, especially at the FHWA Division level, can be minimized. The most standardized reevaluation process that was identified from the responding states is an almost paperless one that uses standard forms and formats. To the maximum extent possible, all communications and reevaluation documents are exchanged electronically both between the state DOT s offices and with the FHWA Division Office. This paperless approach has been operating successfully now for several years Streamlining Several approaches were identified that result in either reducing the amount of paperwork required for a reevaluation or eliminating FHWA s review of the reevaluation. For example, the exchange and review of reevaluation paperwork between FHWA and a state DOT has been reduced by regularly including project reevaluations on the agenda of quarterly or other regularly scheduled meetings between the state and its FHWA Division Office. The state DOT prepares a list of the projects to be addressed at the meeting; the project changes are detailed; and the state recommends its position on whether or not a written reevaluation should be submitted to FHWA or a supplemental NEPA document initiated. For NCHRP Project 08-36, Task 35 12

19 those project changes that FHWA concurs do not need a written revaluation, the minutes of the quarterly meeting reflect this along with the state s rationale. The minutes are provided to the FHWA Division Office and serve as the state s documentation of the completed consultation. Two different methods have been used to eliminate FHWA review of reevaluations of projects that have categorical exclusion designations. One is through the preparation of a programmatic categorical exclusion by the state DOT and FHWA. As long as any project change continues to meet the established criteria for the programmatic exclusion, the project change need not be reviewed by FHWA. Rather, the state DOT documents that the programmatic exclusion still applies. The second method is the development of an inter-agency agreement between the state DOT and the FHWA which contains specific delegations for reevaluations. These agreements have also been limited to projects with categorical exclusion designations and allow a state DOT to reevaluate them without consulting FHWA. Under both types of delegations, the FHWA Division Office conducts process reviews to determine whether the delegations are being appropriately implemented by the state DOT. Interviewed Division Office staff indicated that these process reviews have found satisfactory implementation. Perhaps because of this satisfactory implementation, SAFETEA-LU in Section 6004 codified a state DOT s ability to assume responsibility for categorical exclusions after entering into a memorandum of understanding with FHWA and with FHWA in a programmatic monitoring role. Consequently, for those state DOTs that reported that a high percentage of their categorical exclusion projects require reevaluations, pursuing this new delegation authority could be a time saving benefit to them. A final streamlining practice is to streamline the content and size of reevaluation documents. Standard forms can help in this regard. But for valid reasons, these forms work best for the reevaluation of projects with categorical exclusion designations and EAs. As expected, the state DOTs indicated that the reevaluation of final EISs result in the most lengthy reevaluations. Additionally, extensive revaluation documentation may solely by its appearance raise the question of whether this new documentation should be included in a supplemental NEPA document as opposed to a FHWA reevaluation. One responding state DOT indicated that it has placed a major effort on reducing the size of its EIS reevaluations and especially through the use of reader friendly tables and matrices that can more clearly demonstrate the absence of both new impacts as well as any major increased impacts between the original project and the reevaluated project. A standard outline is used for the reevaluation and it is designed to accommodate the addition of future reevaluations, if needed. See Appendix D of this study for an example Interagency Disagreements Although the occurrence of disagreements between a state DOT and its FHWA Division Office over the need for or the content of reevaluations was not frequently raised in the state DOTs survey responses, it did surface in a few of the phone interviews. The complaints focused on allegations that FHWA either was consistently asking for more documentation for submitted reevaluations or was being unpredictable in terms of what documents would suffice. However, these types of disagreements were not a problem in most responding state DOTs and because several practices have been developed to avoid them. These practices all evolve around promoting effective interagency communication and coordination. For example, some state DOTs requested their FHWA Division Office staff to review and comment on their draft reevaluation guidance and forms before issuance. In at least one instance, the guidance was jointly issued. Similarly, some joint training has been held on reevaluations. NCHRP Project 08-36, Task 35 13

20 3.3 Challenges and Areas for Improvement State DOTs identified the lack of funding as the largest cause of delays in moving projects forward to construction. Consequently, as compared to projects on which project development work is ongoing, these delayed projects can become subject to more expansive reevaluations when eventually submitted to FHWA for each major approval. At a minimum, a consultation is required for these non-eis projects and occurs between the state DOT and FHWA Division as part of the state DOT s request for a major approval. The purpose of the consultation is to establish whether or not the approved environmental document or categorical exclusion designation remains valid. Documentation of this reevaluation may be required by FHWA on a case by case basis. It does not follow, however, that when a state DOT is advised by FHWA that the state need not send in documentation, that the state DOT need not document its project files in some manner. The court decisions are clear that an administrative record must exist as to what factors and impacts were reevaluated and include a decision rationale. A resulting challenge for state DOTs is to ensure that it has adequate, internal, reevaluation documentation for those projects on which FHWA has advised that a consultation is sufficient. It follows then that more state DOTs should consider, through the development of forms or formats, standardizing their documentation requirements for all reevaluations, regardless of FHWA s consultation provision. Compared to delayed projects with categorical exclusion designations, the reevaluation of delayed projects that are the subject of completed final EISs is clearly a much more time consuming and complex task from an analytical perspective. EIS projects are normally a state DOT s largest construction projects and, therefore, can be greatly affected by budget constraints. Consequently, state DOTs frequently request funds for these projects in logical phases as funding becomes available. At the same time, because of the larger size of these EIS projects, changes in alignments or design can have much greater ripple affects in terms of conducting both new impact analysis and comparative impact analysis, i.e., comparing the old project s impacts to either the revised project s impacts or changes that have occurred in the affected environment. Additionally, because of their larger study areas, resource changes within the study area are much more likely over time. Keeping track of these changing components can be a challenge let alone analyzing their impact implications. Consequently, state DOTs need to have management and intra-office communication tools in place that keep track of changing components on a timely basis and alert all appropriate staff of the changes. This is especially true for project areas experiencing rapid economic and population growth. State DOTs should not simply fall back on the three year revaluation standard that applies to inactive EIS projects as their management benchmark. That standard, as a worst case standard, only requires more thorough FHWA documentation, i.e., a written reevaluation, because the probability of project or environmental changes is much higher after such a long period of project inactivity. The purpose of the revaluation remains the same, to establish whether the approved EIS remains valid for the current project and project area, but the requirement dictates a written reevaluation. Accordingly, more frequent reviews of inactive EIS projects should be considered by all state DOTS, such as the one-year review conducted by a few state DOTs. This one-year review can provide more lead time in the event the need for either additional field studies or a supplemental EIS is identified. Additionally, if project development work on the project is expected to remain on hold, the reevaluation need not be extensive at this point. It can just keep track of changes and postpone further study of those changes in a manner that better fits the project development schedule. Just as the courts recognize reevaluations as a legitimate tool in deciding whether or not an existing NEPA document requires supplementation, they similarly recognize that a reevaluation is not a NEPA document. A revaluation, no matter how through its analysis, cannot take the place of a supplemental EIS when one is required. Consequently, state DOTs and FHWA staff can face very difficult calls in NCHRP Project 08-36, Task 35 14

21 determining when an extensive reevaluation with a variety of new studies should be converted into a supplement. This difficulty can be minimized the more lead time that exists in that the option of supplementing is more doable. There appear to be at least two governing principles to date. First, FHWA regulations state that if the reevaluated impacts are less than those previously analyzed, a supplement is not required. Second, the courts have stated that if the revaluation addresses a significant impact(s) that should have been addressed in the original NEPA document, then a supplement is required to fill that gap(s). The results of the telephone interviews in particular showed that a NEPA once and done mentality still exists among some state DOT staff. The surveys showed that approximately one-half of the responding state DOT s have neither supplemented the FHWA guidance on reevaluations nor provided training on completing reevaluations. This is true even though a few of these states indicated that their FHWA Division offices were either asking for more documentation or raising concerns about inconsistent implementation between state staff. Given the progress that some state DOTs have made, other states could easily borrow from these approaches, especially in terms of the available reporting formats. A final challenge relates to state DOTs allocating the sufficient time and resources necessary to efficiently conduct reevaluations. For example, twenty of the twenty-seven responding states DOTs indicated that they had not conducted staff training on conducting reevaluations. Also, although projects with categorical exclusion designations appear to be the project type most frequently subject to revaluation, procedures for reducing FHWA s review and its review time of the more complex categorical exclusions known as (d) list categorical exclusions, 4 such as through programmatic categorical exclusions and interagency agreements, have not been fully taken advantage of by state DOTs CFR 117(d) NCHRP Project 08-36, Task 35 15

22 4 RECOMMENDED GUIDANCE AND PROCESSES FOR CONDUCTING REEVALUATIONS The following guidance primarily addresses recommended processes and decision criteria or factors to be applied in the completion of reevaluations. The guidance does not discuss the content of reevaluations in terms of their scope or identifying the need for new studies because our research did not find any major misunderstandings or implementation problems with these aspects of reevaluations. This result is not surprising since changes in project concepts, environmental resource data, and applicable regulations are not unique to reevaluations, but can and do occur during the initial preparation of a NEPA document and especially a lengthy environmental impact statement. NEPA practitioners, therefore, have become accustomed to responding to these changing circumstances at all points in the NEPA process. 4.1 Projects With Categorical Exclusion Designations State DOTs should consider creating a distinct process for projects with categorical exclusion designations. This is recommended because this class of projects appears to be subject to the greatest number of reevaluations; their reevaluations are the least complex; they require the least amount of lead time; and established and time saving procedures exist that can eliminate FHWA s review times by delegating approval authority to state DOTs. A project with a categorical exclusion designation needs to be reevaluated prior to requesting a major approval from FHWA to address the changes made to the project or that occur within the project s affected environment. These reevaluations should be coordinated and managed around the two most relevant project events that are within the state DOT s control, i.e., initiating project changes and submitting approval requests to FHWA. Consequently, whenever a design or alignment change is made to a project with an initially completed categorical exclusion, this new project information needs to be communicated by the design/engineering staff to the environmental staff along with a request to coordinate the preparation of a reevaluation. A short, standard form should be used to document the scope and results of the reevaluation. (See Appendix C for examples.) Not only should the project change be addressed in the reevaluation at this time but also any known changes to the project s affected environment. For projects that are in line to be the subject of a major approval request, the state DOT should establish with its FHWA Division a cut off date for an acceptable categorical exclusion or its most recent reevaluation. For example, at the time of submitting the request, the agencies may establish as a standard policy that the exclusion or its reevaluation may not be more than six to twelve months old. The shorter time frame would be applicable to project areas or counties experiencing rapid growth and frequent changes to the affected environment. Whereas the longer period would apply in relatively stable areas or counties, such as remote rural areas Consequently, as approval requests are scheduled for preparation at the state DOT, environmental staff would be informed well in advance of the planned submittal date and would check on the date of the last reevaluation or initial categorical exclusion, as applicable. For projects that need a current reevaluation but have never been reevaluated because they have not been changed, the focus of the reevaluation would be any possible changes in the resource status of the affected environment. In order to eliminate any FHWA review time currently involved in these categorical exclusion reevaluations, state DOTs should consider incorporating into their NEPA procedures one or more of the following streamlining approaches. As some state DOTs have done, a programmatic categorical exclusion could be prepared with the assistance and concurrence of FHWA. As long as any changes to NCHRP Project 08-36, Task 35 16

23 the project or its affected environment stay within the bounds or criteria established for the programmatic exclusion, the project would retain its exclusion status under the programmatic exclusion. Normally FHWA Division Offices do not require to be consulted on projects changes under this programmatic approach, but the state DOT remains responsible for documenting its rationale for the exclusion s remaining applicability. A second approach is for a state DOT to negotiate a memorandum of agreement with FHWA for the purpose of being delegated the authority for determining and reevaluating, as necessary, its (d) list categorical exclusion designations. Thirdly, state DOTs may want to discuss with FHWA the pros and cons of entering into a memorandum of understanding (MOU) with FHWA under the authority of Section 6004 of SAFETEA-LU. This is a relatively new authority under which a state DOT can accept the legal responsibility for categorical exclusion designations. Whether such a MOU would provide net benefits to a state DOT would depend upon its volume of projects with categorical exclusion designations; how often they require reevaluation; and FHWA s remaining role in these projects reevaluations. 4.2 Projects With Completed Environmental Assessments As in the reevaluation of any project, the reevaluation of a project that was the subject of an EA and a Finding of No Significant Impact (FONSI) must initially focus on any changes that may have occurred to the project, its affected environment, and the regulations applicable to the project s development. Identified changes should then be listed and analyzed in terms of whether or not a significant impact may now exist. Red flags that the FONSI may no longer be applicable would include the identification of increased adverse impacts to one or more resources covered in the original EA, especially Section 4(f) resources, or the identification of an entirely new and major, adverse impact, e.g., a previously adversely affected species is now listed as endangered or wetlands are now extensively and adversely impacted when none were previously. It is recommended that the second focus of an EA reevaluation process address the question of whether or not the EA needs to be amended, even though a finding of no significant may still be applicable in the view of the state DOT and FHWA. The purpose of or possible need for an amendment is to inform other agencies and the public of the changed impacts and provide them the opportunity to review and comment on these changes as well as the pending FHWA FONSI determination. Red flags or factors that state DOTs should consider as especially relevant to a decision to amend include the identification of a newly affected public; a new or lingering controversy; a different mix or picture of the adverse environmental impacts; or new project mitigation whose effectiveness is unproven 4.3 Projects With Completed Environmental Impact Statements The amount of time and effort required to complete the reevaluation of a project with a completed EIS can vary substantially. The determining factor appears to be whether or not, after the completion of the EIS, the project development process continues to move forward with the ongoing project work and analyses providing a readily available and current source of project status information that accommodates the documentation of a concise reevaluation. This is true even in the case where the three-year requirement is triggered for a written revaluation. Based on the above factor, a three-year, required written revaluation report on a draft EIS can often be relatively easy to prepare because the project development process is normally ongoing between the draft and final EIS stages. Furthermore, any resulting project or impact changes can be identified and analyzed in the development of the final EIS, which is a full disclosure document. NCHRP Project 08-36, Task 35 17

24 Should the results of the revaluation of a draft EIS cause a state DOT to seriously consider the need for a supplemental draft EIS, the applicable provisions of the CEQ and FHWA regulations that address when a draft EIS should be supplemented must be initially reviewed. These provisions are contained in the References section of this study with the CEQ provision on page 73 followed by the FHWA provision on page 74. It is also recommended that in deciding whether or not to prepare a supplemental draft EIS, consideration be given to the guidance used by Environmental Protection Agency (EPA) reviewers when commenting on and rating other agencies draft EISs. EPA states in its guidance to its reviewers that a draft EIS should be supplemented when it receives EPA s lowest numerical rating which is a 3. This rating applies when the reviewed draft EIS does not adequately assess the potentially significant environmental impacts of the proposal, or the reviewer has identified new, reasonably available, alternatives, that are outside of the spectrum of alternatives analyzed in the draft EIS, which should be analyzed in order to reduce the potentially significant environmental impacts. The identified additional information, data, analyses, or discussions are of such a magnitude that they should have full public review at a draft stage. This rating indicates EPA s belief that the draft EIS does not meet the purpose of NEPA and/or the Section 309 review, and thus should be formally revised and made available for public comment in a supplemental or revised draft EIS. 5 For final EISs, the completion of a required, three-year written revaluation can necessitate the longest lead time in order to adequately complete any new studies or, more importantly, to supplement the existing EIS, whenever the reevaluation determines that need. Again, this depends on whether the project development process has been actively progressing or stalled. It is recommended that reevaluation processes for final EISs be conducted more frequently than those for other NEPA documents, since the potential costs, measured in both time and money, of overlooking or missing a project change or a new impact are much greater. As for all projects, state DOT final EIS reevaluation processes should include the same early internal communication and coordination systems for alerting appropriate staff to project changes but should be expanded to include automatic re-look periods, such as the one year period used by several states. This one year re-look need not meet the requirements of a full written reevaluation either in terms of its content or the need for FHWA concurrence. For example, it could initially avoid field studies and start with an office review of all project changes; recent global regulatory changes that might affect the adequacy of the existing data or analyses; the past year s new listings for resources such as cultural resources, endangered species, and various state resource inventories; the age of any wetland determinations; and the project s permitting status. If this office review does not identify any reevaluation concerns and the project is not predicted to move forward for a major approval or grant request within the next twelve months, this re-look could conclude with either a decision for no immediate action or, if applicable, a to do list of items to be addressed in the next re-look or reevaluation. On the other hand, if there are reevaluation concerns or a supplemental NEPA document is clearly needed, the required additional studies and analysis can be then be scheduled to coincide with the project s remaining funding and development schedule. However, as an exception to a limited re-look approach, if a one year review is being conducted on a final EIS that is also at one of its three year 5 U.S. Environmental Protection Agency s Environmental Impact Statement Rating System Criteria. Posted on the following website:epa Home, Compliance and Enforcement, National Environmental Policy Act (NEPA), EPA Comments on Environmental Impact Statements ( Retrieved on December 30, NCHRP Project 08-36, Task 35 18

25 anniversary intervals, a written revaluation and not a shortened re-look would be required, per the FHWA NEPA procedures. When a reevaluation is conducted, it must be done so within its legitimate bounds. The review of the court decisions on reevaluations indicates that reevaluations can neither be used to fill gaps in the existing NEPA document nor can they serve as the supplemental document for new information. A reevaluation is not a NEPA document but only an agency decision document on whether or not a new or supplemental NEPA document is needed. The reevaluation decision for a final EIS in terms of whether a supplemental EIS is needed should consider the CEQ and FHWA regulatory provisions referenced above. Additionally, it is recommended that the following three standards be given great weight when making this decision. The first and most straight forward is the possible selection of a project alternative that was not analyzed in the FEIS. The second is the identification of a significant impact not previously analyzed in the FEIS, whether a new impact or an omitted one. Third, just as a revaluation finding of decreased, adverse impacts can be the basis for not supplementing, a finding of increased adverse impacts can be the basis for supplementing. This third standard is clearly more subjective than the first two but it is relevant in light of both court decisions that have concluded that a supplemental EIS is required when new circumstances present a seriously different picture of the environmental impacts of a proposed project from what were previously envisioned; and the major emphasis within the CEQ regulations on the need for public involvement and inter-agency review of potentially significant environmental impacts. NCHRP Project 08-36, Task 35 19

26 5 CONCLUSIONS The courts continue to recognize that when a federal agency timely conducts a reevaluation and in accordance with its established procedures, a reevaluation is a legitimate process for determining whether a supplemental NEPA document is required. Accordingly, a reevaluation is a significant time and cost saving tool when compared to moving directly into the preparation of a supplemental environmental impact statement or amended environmental assessment. The courts have also recognized that a revaluation is not a NEPA document. Consequently, an agency cannot use a reevaluation in an attempt to remedy any gaps in impact analysis that should have been addressed in the original NEPA document, or offer to do a reevaluation as a defense for postponing a challenge to the original NEPA document. Although existing FHWA requirements and guidance on conducting reevaluations are very limited, approximately two-thirds of the state DOTs that responded to this study s survey indicated that they were not experiencing any problems conducting reevaluations. This result appears to occur either because these states have comparatively smaller reevaluation workloads, or over time have developed, in consultation with their FHWA Division Offices, effective practices for overcoming any reoccurring problems. These established practices are available and are worthy of consideration and tailored implementation by those state DOTs and FHWA Divisions that may currently experience problems with the volume, timing, or scope of their reevaluations. NCHRP Project 08-36, Task 35 20

27 APPENDIX A: COURT CASE SUMMARIES A summary of each of the twelve most relevant cases that we found is included below. We used the Lexis service offered by LexisNexis to search state and federal cases decided between January 2000 and October Each case summary focuses on the aspects of the case that relate to NEPA reevaluations, and the summary does not address in any detail other environmental laws or claims that may also have been litigated. Ten of these cases involved litigation over federal highway projects; one involved a U. S. Forest Service timber sale; and the other was filed against the U. S. Army Corps of Engineers over a dredging project. The six cases in which the federal government prevailed are presented first and in chronological order from the most recent to the oldest. The six cases in which the federal government did not prevail follow and are presented in a similar chronological sequence.. NCHRP Project 08-36, Task 35 21

28 CASES IN WHICH THE FEDERAL GOVERNMENT PREVAILED William Ware and Carol Caul, Plaintiffs, v. United States Federal Highway Administration, et al., Defendants United States District Court for the Southern District of Texas, Houston Division 2006 U.S. Dist. LEXIS Decided: March 15, 2006 The plaintiffs filed this suit over a highway construction project located near their home. After the construction of the IH-610 Rehabilitation Project began, the plaintiffs sued state and federal highway agencies alleging that the revised and higher elevation of reconfigured lanes and connectors would greatly increase noise levels at nearby homes and parks. In 1992, FHWA approved the IH-610 project as a Categorical Exclusion (CE) under NEPA. In 2001, TXDOT issued a Reevaluation for the project and concluded that although the project had changed, a CE still applied and no additional environmental studies were needed. Both the 1992 CE and the 2001 Reevaluation included a noise-impact study. In 2004, TXDOT submitted another Reevaluation after notifying FHWA of a miscalculation in the earlier noise impact studies done for the project. The new study found that while noise levels would be higher than originally projected, they would not cause a significant environmental impact with adequate mitigation. The plaintiffs challenged this no significant environmental impact finding and argued that the project should not have been approved as a CE and thus violates NEPA and the Administrative Procedures Act. The 2001 Reevaluation compared the current project to the 1992 CE report and found that the project changes did not result in significant environmental impacts. This Reevaluation included a noise analysis which concluded that the predicted impacts would require noise abatement measures. TXDOT concluded from the 2001 Reevaluation that the CE remained valid and FHWA agreed. The 2004 Reevaluation refers to the 2001 Reevaluation in all areas except for the section on noise. In the 2004 Reevaluation, the noise impacts were determined to be above the levels predicted in the original CE and 2001 Reevaluation. TXDOT evaluated noise abatement measures and concluded that a noise-barrier wall remained the only feasible and reasonable alternative. This 2004 Reevaluation concluded that revisions to the 1992 CE were not necessary and FHWA agreed. At issue in this case was whether a CE was the appropriate NEPA documentation. Although the newly projected increase in noise levels varied from four to nine decibels at fourteen receivers tested in the project area, the District Court concluded that FHWA s CE decision is entitled to substantial deference, and that plaintiffs failed to offer evidence that the increased noise levels constituted a significant environmental impact that would require different treatment under NEPA. The 2001 and 2004 Reevaluations served an important role in the administrative record of the case by documenting the reconsideration of environmental impacts in light of changes to the project over approximately 12 years. The court denied the plaintiffs motion for a preliminary injunction. NCHRP Project 08-36, Task 35 22

29 Florida Keys Citizens Coalition, Inc.; Sierra Club, Inc.; and Friends of the Everglades, Plaintiffs, v. United States Army Corps of Engineers; United State Department of Transportation; Federal Highway Administration; United States Environmental Protection Agency; United States Fish and Wildlife Service; National Oceanic and Atmospheric Administration, Defendants, and Florida Department of Transportation, Defendant Intervenor. United States District Court for the Southern District of Florida, Miami Division 374 F. Supp. 2d 1116; U.S. Dist. LEXIS 16837; 18 Fla. L. Weekly Fed D 759 Decided: April 8, 2005 In March of 1992, FHWA issued a FEIS for improvements along a 20.6 mile stretch of highway US-1, running from its southern terminus on Key Largo in Monroe County, Florida to a northern terminus just south of Florida City in Miami-Dade County. The FEIS preferred alternative consisted of a four-lane divided roadway with associated improvements. In December of 2003 and over some nine years of a difficult permitting process, FDOT downsized the project to a two-lane configuration to reduce wetland impacts but included a northbound shoulder with the capability of serving as an extra lane during emergencies. FHWA and FDOT considered the revised, two-lane project as consisting of mainly safety improvements and prepared a categorical exclusion for these revisions. FHWA and FDOT also completed a Reevaluation that eliminated the accommodation of growth as one of the project s purposes and concluded that a smaller project within the same approved footprint and with less environmental impact did not require SEIS. Plaintiffs filed for an emergency injunction and argued that the revised project required a second EIS or at least a supplement to the first. The District Court agreed with FHWA indicating that FWWA s actions were consistent with its NEPA regulations both with respect to the categorical exclusion provision for highway safety improvements and the provision for reevaluations. Moreover and specific to the Reevaluation, the court noted that other courts have specifically approved the use of reevaluations and that in this case, FHWA carefully and adequately considered the Reevaluation, including all new pertinent information and studies regarding the redesigned project. Although plaintiffs had demonstrated the existence of new information, they had not met their burden of demonstrating how the new design would result in substantial changes in environmental impacts. The District Court found FHWA s position compelling, i.e., simple reductions in project size do not warrant the time and expenditure necessary to prepare a SEIS. NCHRP Project 08-36, Task 35 23

30 West Alabama Quality of Life Coalition, Plaintiff, v. United States Federal Highway Administration, et al., Defendants United States District Court for the Southern District of Texas, Houston Division 302 F. Supp. 2d 672; 2004 U.S. Dist. LEXIS 1752 Decided: February 9, 2004 The West Alabama Quality of Life Coalition filed a motion for a preliminary injunction to halt a construction project on US 59/Spur 527 that was scheduled to begin on February 13, The plaintiff contended that FHWA and TXDOT failed to comply with NEPA, the National Historic Preservation Act, and the Administrative Procedures Act by failing to analyze all impacts of a revised traffic plan and failing to complete public involvement on a new construction plan. The Defendants contended that they were in full compliance and submitted a partial administrative record which included the 1985 FEIS, July 1991 EA, 1997 revised EA, 1998 FONSI, 2002 Reevaluation, and January 2004 Supplemental Report. The Spur 527 project is a component of the Southwest Freeway Project to reconstruct US 59. This reconstruction project was approved in October 1985 based on an EIS completed earlier the same year. This EIS provided no specific plans regarding the reconstruction of Spur 527 at US 59. In 1991, TXDOT prepared an EA for the specific plans in this area. The project received considerable comments in opposition to proposed elevated HOV lanes. As a result, TXDOT prepared a revised EA in September 1997 identifying HOV lanes at the same grade as Spur 527 and requiring reconstruction of this area. The EA stated the construction would not detour a significant amount of traffic onto neighborhood streets and provided a letter from the Texas State Historic Preservation Officer that the project would not have an adverse impact on historic properties in the area. On February 25, 1998, FHWA approved the design with a finding of no significant impact. The project was to be completed in three phases. In 2002, TXDOT submitted to FHWA a Reevaluation of the EA to address further design considerations for Phase 2. FHWA agreed with TXDOT that no further environmental documentation or public involvement was required due to the design modifications. In 2004, after further modifications to the traffic control plan, TXDOT prepared a Supplemental Report concluding that the revised traffic control plan was still consistent with a finding of no significant impact. FHWA argued that the traffic control plan is part of final design activities and is specifically mitigation for potential harmful effects. FHWA cited 23 CFR (a) which states that final design activities shall not proceed until NEPA is completed. The court agreed that FHWA was not required to analyze the final traffic control plan in an EA or an EIS, i.e., traffic control plans fall within final design activities and are not required to be analyzed in an EA or EIS. Therefore, the District Court concluded that the Agency s decision cannot be arbitrary, capricious, or an abuse of discretion. NCHRP Project 08-36, Task 35 24

31 Highway J Citizens Group, Plaintiff-Appellant, v. United States Department of Transportation; Federal Highway Administration; Wisconsin Department of Transportation, Defendants-Appellees United States Court of Appeals for the Seventh Circuit 349 F.3d 938; 2003 U.S. App. LEXIS Decided: November 5, 2003 After the U.S. District Court for the Eastern District of Wisconsin denied plaintiff s motion to enjoin defendants from proceeding with the Ackerville Bridge Project, the Citizens Group appealed and asked the Circuit Court among other things for a permanent injunction to prevent the opening of the bridge and require FHWA to complete an EIS for it. The Citizens Group claimed an EIS was required for the Bridge because the Bridge s construction could affect groundwater contaminated by a nearby former landfill and thereby jeopardize uncontaminated private water supply wells. WDOT and FHWA had prepared a draft EA in 1999 and it did not address the leaching landfill because groundwater had been identified at depths of 30 feet which was well below the expected excavation for the bridge pilings. After a resident submitted comments and expressed concern about the groundwater contamination from the landfill at a public meeting on the draft EA, FHWA responded to these comments in the final EA and specifically addressed whether this concern warranted the preparation of an EIS. FHWA concluded an EIS was not necessary based on the fact that the contamination was well below the excavation limits and the project had no potential to encounter the contaminated groundwater. FHWA signed the FONSI on April 25, Approximately nine months later, in February 2001, WDOT s design consultant issued a report officially stating that the pilings would extend below the groundwater level. Over the course of the next year and a half, WDOT, Wisconsin Department of Natural Resources, Wisconsin Department of Health and Family Services, and USEPA all provided documented analysis and discussion that the pilings would not affect the contaminated groundwater in a way that would harm currently uncontaminated private water supply wells. In the review of the administrative record, the Circuit Court determined that FHWA fulfilled the requirement of taking a hard look at the environmental consequences and through consultations with expert agencies demonstrated that the project did not have significant effects that would require an EIS. The court further pointed out that a WDOT reevaluation memo was timely, occurring both before construction was allowed to start and some eighteen months before FHWA knew it was being sued. The court also noted that FHWA regulation 23 CFR (c) requires that any major changes made after approval of the FONSI be evaluated to determine if the approved environmental document remains valid. If not, a supplement is required. In this case, FHWA re-evaluated the effects of the piling depth and determined that the approved EA/FONSI remained valid. NCHRP Project 08-36, Task 35 25

32 William Norton, Plaintiff, v. Federal Highway Administration and New York State Department of Transportation, Defendants United States District Court for the Western District of New York 2006 U.S. Dist. LEXIS Decided: August 8, 2002 The plaintiff contended that FHWA and NYDOT violated NEPA by preparing a Supplement EIS (SEIS) without first issuing a Notice of Intent (NOI). The affected project was the proposed expansion and upgrade of U.S. Route 219 between Springville, NY and Salamanca, NY. The plaintiff asked for a declaration of the violation and an order to require the filing of a NOI and the preparation of SEIS. FHWA had prepared a DEIS and the Notice of Availability appeared in the Federal Register on June 5, Mr. Norton filed comments that the DEIS incorrectly discussed the eligibility of the Ira Norton Farmstead for listing on the National Register of Historic Places. Approximately three years later, in August 8, 2001, NYDOT notified the plaintiff that technical studies of alternatives to avoid the Ira Norton Farmstead were still underway. The District Court cited the FHWA regulations found at 23 CFR that requires a reevaluation to be conducted to determine if a SEIS is required when three years pass after the DEIS is prepared and the FEIS has not been completed. The District Court determined that the regulations do not require that a SEIS be filed within three years of the DEIS, but only a written evaluation prepared to determine whether a SEIS or a new DEIS is required. The defendants were still incorporating the information regarding the Ira Norton Homestead into the administrative process and had no duty under the regulation to publish a NOI or prepare a SEIS at the time of the case. The District Court, therefore, dismissed the case stating that the action was not yet ripe for judicial review. NCHRP Project 08-36, Task 35 26

33 Route 9 Opposition Legal Fund, et al., Plaintiffs, v. U.S. Department of Transportation, et al., Defendants United States District Court for the Northern District of West Virginia, Martinsburg Division 213 F. Supp. 2d 637; 2002 U.S. Dist. LEXIS 14261; 33 ELR Decided: August 2, 2002 In December 1993, FHWA and WVDOT issued a DEIS for the construction of a new 4.6 mile dual lane section of WV 9, originating at the Charles Town, West Virginia Bypass and terminating at the West Virginia-Virginia state line. Approximately seven years later, in October 2000, the FEIS was released. During that period, two Reevaluations were conducted for the DEIS and both concluded that there was no need to supplement the DEIS. Plaintiffs challenged both the adequacy of the FEIS and FHWA s failure to supplement the DEIS. The District Court dismissed both complaints. Regarding the need for a supplemental DEIS, the Court indicated that the standard in the Fourth Circuit is that a supplemental EIS is required only when new circumstances present a seriously different picture of the environmental impact of the proposed project from what was previously envisioned. The court noted that FHWA had completed two Reevaluations of the DEIS in accordance with its regulations and found that there was no new information requiring a supplemental. Three of the four pieces of new information alleged by the plaintiffs had been reviewed by FHWA as part of its Reevaluations and reasonably determined by it to be either inapplicable to the project or already adequately covered in the DEIS. The fourth piece of alleged new information, a referenced article, had not been provided by the plaintiff to FHWA and the District Court agreed with FHWA s position that FHWA could not do a supplemental EIS based on information not brought to its attention before its decision. NCHRP Project 08-36, Task 35 27

34 CASES IN WHICH THE FEDERAL GOVERNMENT DID NOT PREVAIL South Carolina Wildlife Federation; South Carolina Coastal Conservation League and Audubon South Carolina, Plaintiffs, vs. South Carolina Department of Transportation; Tony L. Chapman, Acting Executive Director, South Carolina Department of Transportation; Federal Highway Administration; and Robert L. Lee, Division Administrator, Federal Highway Administration, Defendants. United States District Court For the District Of South Carolina, Charleston Division 485 F. Supp. 2d 661; 2007 U.S. Dist. LEXIS Decided : April 16, 2007 The lawsuit arose over the planned construction of the Briggs-DeLaine-Pearson Connector which would connect the towns of Rimini and Lone Star, South Carolina. The length of the proposed connector was approximately ten miles with a three mile-long bridge through the Upper Santee Swamp. The DEIS for the project was issued in October 2001 and the FEIS in December The ROD followed in June The plaintiffs included among its claims that the FEIS was not adequate. Defendants argued that this claim was premature and not ripe for review because the defendants still had to conduct a reevaluation of the FEIS. The District Court did not accept defendants position noting that any judicial review after a reevaluation would be limited to the actions taken in reevaluating the FEIS. The District Court explained that the FHWA regulations on reevaluations do not require defendants to develop a new EIS but only to consider the environmental impacts caused by any changes to the project that have occurred since the FEIS was issued. Because the plaintiffs claim addressed the adequacy of the full scope of the completed FEIS, it was ripe for the court s review. NCHRP Project 08-36, Task 35 28

35 Natural Resources Defense Council, Inc.; Raritan Baykeeper, Inc.; Andrew Willner; and Greenfaith, Plaintiffs v. United States Army Corps of Engineers, New York District, Defendant U.S. District Court for the Southern District of New York 399 F. Supp. 2d 386; 2005 U.S. Dist. LEXIS Decided: August 5, 2005 In February 2004, EPA added Newark Bay to the Diamond Alkali Superfund Site and ordered a Remedial Investigation/Feasibility Study (RI/FS) to determine the nature and extent of contamination in the Bay and evaluate possible cleanup options. Shortly thereafter, the U.S. Army Corps of Engineers (COE) proceeded with a project to deepen shipping channels in the New York-New Jersey Harbor through dredging and blasting the Harbor floor and without supplementing its EIS for this project. The plaintiffs maintained that the COE did not give adequate consideration to how the dredging would affect and be coordinated with the RI/FS and that a SEIS was necessary. The District Court indicated that the plaintiff s burden is to establish that there is a substantial possibility that the action may have significant new impacts and not that it clearly will have such impacts. The COE, on the other hand, must demonstrate that it gave a sufficiently hard look at the significance of the new circumstances created by the RI/FS before it approved dredging without a SEIS. The District Court employed the following two standards for determining if an agency s decision not to supplement an EIS is arbitrary and capricious: Did the agency take a hard look at the possible effects of the proposed action? If the court is satisfied that the agency took a hard look, was its decision based on a searching and careful inquiry and did it consider all relevant factors and evaluate the significance or lack of significance of the new information? The COE defended its decision not to supplement on the basis that EPA had stated during a meeting that the dredging project would not delay or prevent an effective cleanup. The District Court, however, concluded that simple, conclusory statements of no impact are not enough to fulfill an agency s duty under NEPA, even if they come from another agency with expertise. The COE further maintained that the designation of Newark Bay as a Study Area under CERCLA is a change in legal status of the Bay, which is not recognized as triggering the need for a SEIS. Since the legal status of the Bay is a policy determination and not a scientific or empirical one, the COE argued that its brief dismissal of the issue was sufficient to constitute a hard look. The District Court did not accept this argument and stated that the presence of sampling activities in the Bay for the RI/FS is a real, physical change. The COE did not take this change into consideration before awarding the dredging contract even though there may be significant new environmental consequences, which could be considered indirect or cumulative effects. The court s decision was that the COE failed to take a hard look at the significance of the new circumstances created by the RI/FS before it approved dredging without a SEIS. The new circumstances were described as the potential impacts of dredging on the RI/FS and methods of coordination with EPA that might reduce those impacts, if any. The District Court held that it was arbitrary and capricious for the COE to decide that it was not required to prepare a SEIS. The District Court did not conclude, however, that the change required a SEIS but emphasized it is possible that after the COE does take a hard look, it may be justified in finding that no SEIS is required. In explaining its decision, the District Court clarified that an agency does not have to supplement an EIS every time there is new information. Rather, if the new information provides a seriously different picture NCHRP Project 08-36, Task 35 29

36 of the environmental landscape, then another hard look is necessary. If the new information is patently insignificant, an agency can meet its obligations under NEPA with only the most cursory look at the significance of the new information. If it is simply irrelevant, the agency can give no consideration. In all cases, the assessment of the significance of new information must be considered prior to the agency s decision and not as part of a litigation response. NCHRP Project 08-36, Task 35 30

37 Wayne Senville; Donald Horenstein; Vermont Public Interest Research Group, Inc.; Friends of the Earth, Inc.; Sierra Club, Inc.; and Conservation Law Foundation, Plaintiffs, v. Mary E. Peters in her official capacity as Administrator of the Federal Highway Administration (FHWA), and Patricia A. McDonald in her official capacity as Secretary of the Vermont Agency of Transportation (VTrans), Defendants. United States District Court for the District of Vermont 327 F. Supp. 2d 335; 2004 U.S. Dist. LEXIS 8312; 58 ERC (BNA) 2129 Decided: May 10, 2004 This case examines Segments A-B of the Chittenden County Circumferential Highway (CCCH) project located in northwest Vermont, a four-lane limited access highway. The project was designated as a demonstration project under Section 131(f) of the Surface Transportation Assistance Act of 1982 which delegated responsibility for environmental documentation to the state of Vermont. The Vermont Agency of Transportation (VTrans), with assistance from FHWA, prepared a DEIS that was published in August, 1985, a FEIS was published the following year, and the ROD was issued on November 5, In September, 1991, FHWA authorized construction for Segments C-F. In late 1998, VTrans began a reevaluation of Segments A-B in preparation for construction of those segments, and in 1999, VTrans concluded that the 1986 FEIS remained adequate and a SEIS was not required. With a new authorization of federal funding needed, a federal EIS had to be in place. In 2001, FHWA determined that they could not use the 1986 FEIS and ROD for future phases of the project, because they did not approve those documents. FHWA adopted the 1986 FEIS in July 2002 under the provisions of 40 C.F.R It also decided to reevaluate Segments A-F and issued a reevaluation EA in August 2002 with a final revised reevaluation (FREA) issued May 9, The FREA concluded that changes to the project and the environment since the 1986 FEIS did not result in any additional or new significant environmental impacts. A ROD was issued on August 22, 2003 that adopted the 1986 FEIS. Plaintiffs claims included that the 1986 FEIS was not adequate and that a supplemental EIS was needed. The District Court agreed that the 1986 FEIS was inadequate; the FEIS did not discuss cumulative impacts; its examination of secondary impacts was cursory; and it did not provide adequate justification for use of Section 4(f) properties. The District Court then indicated that the FREA s analysis of induced growth was dismissive and its conclusion that relocated growth would have an insignificant impact on inner cities and outlying towns not supported. A hard look at the impacts of induced growth had not been undertaken and particularly when the issue was not part of the original EIS which at the time of this case was over seventeen years old. The Court also found that FHWA violated NEPA by preparing an EA to determine whether an SEIS was necessary without analyzing alternatives to the project. The FREA s alternatives analysis only discussed the changes to the selected alternative; it dismissed the other alternatives discussed in the 1986 FEIS as not meeting the purpose and need for the project. The Court noted that the EPA, in urging FHWA to issue a supplemental EIS, stated that alternative modes of transportation appear to be available that were not in This new information was not evaluated by FHWA. The Court found that FHWA violated NEPA, CEQ, and FHWA regulations in approving Segments A-B of the CCCH and enjoined defendants from construction until they complied with NEPA. NCHRP Project 08-36, Task 35 31

38 The Piedmont Environmental Council and Sierra Club, Plaintiffs v. United States Department of Transportation, et al., Defendants United States District Court for the Western District of Virginia, Charlottesville Division 159 F. Supp. 2d 260; 2001 U.S. Dist. LEXIS Decided: August 21, 2001 The plaintiffs brought nine counts against the defendants alleging various violations of NEPA and Section 4(f), including reevaluation as a post-hoc rationalization, failure to supplement the environmental impact statement (EIS) after substantial changes in the project, and deficiencies in the final environmental assessment (EA) and EIS. In 1991, the Virginia Department of Transportation (VDOT) submitted a final EA to the FHWA who issued a FONSI for widening Route 29 around the City of Charlottesville. However, Albemarle County recommended that a comprehensive study of the corridor be completed before proceeding with the widening project. A DEIS was approved by FHWA in In 1993, FHWA approved the FEIS and issued a ROD. In 1995, a FONSI was issued for changes to the bypass termini after an EA determined that modifications to the bypass termini did not present significant environmental impacts. In 1995 and 1996, several changes to the design of the bypass were proposed, and VDOT and FHWA determined that they needed to reevaluate the previous environmental documents. In 2000, FHWA signed and approved a Reevaluation that determined that an SEIS was not needed. The Court initially found that the Reevaluation and revised ROD were not post hoc justifications, but were a proper means of addressing the significance of changes made to the project. The Reevaluation (which was begun in 1996 and completed in 2000) assessed various changes to the bypass design that occurred after the FEIS was filed in 1993 and found that none of the changes met the threshold for requiring new or supplemental filings under NEPA. The Reevaluation explained the review process undertaken prior to the final decision and was conducted prior to that decision. Therefore, it was not a post-hoc rationalization, as the plaintiff argued. The Court noted that not every new circumstance that arises during the course of a project requires the completion of a SEIS. A SEIS is only required for significant changes that were not previously evaluated in the EIS. The new circumstance must present a seriously different picture of the environmental impact of the proposed project from what was previously envisioned. NEPA also requires an EA or other environmental study if the significance of a change or new information is uncertain. In order to make the initial determination about whether a change or new information meets the threshold of significance or uncertainty, an agency may use non-nepa documents such as the Reevaluation. The Court determined that the bypass impact on the South Fork Rivanna Reservoir was the only issue that neither the FEIS nor the EA considered adequately. Although the Reevaluation discussed the bypass project s effects on the Reservoir and the mitigation efforts in place to address those impacts more fully than did the FEIS and EA, the District Court found that the defendants use of the Reevaluation to address issues that should have been included in its original NEPA documents was an improper post hoc justification. Therefore, the Court enjoined the defendants from taking further action on the bypass project until a supplemental EIS is completed. NCHRP Project 08-36, Task 35 32

39 North Carolina Alliance for Transportation Reform, Inc. and Friends of Forsyth County, Plaintiffs, v. U.S. Department of Transportation; Federal Highway Administration; North Carolina Department of Transportation, Defendants 151 F. Supp. 2d 661; 2001 U.S. Dist. LEXIS United States District Court for the Middle District of North Carolina Decided: June 4, 2001 Plaintiffs alleged that the construction of the Western Section of the Winston-Salem Northern Beltway in Winston-Salem, North Carolina violated NEPA because defendants failed to supplement the FEIS after the May 8, 1996 announcement that Forsyth County s Transportation Improvement Program (TIP) had fallen out of conformity with the Clean Air Act (CAA). On June 24, 1992, NCDOT published a DEIS for the Western Section project. On March 29, 1996, NCDOT published the FEIS, and only one day later, on May 7, 1996, FHWA issued the ROD. The following day, FHWA announced that the TIP for the Winston-Salem metropolitan area no longer conformed to the requirements of the CAA. However, funding for the Western Section was allowed to continue because the NEPA process had been completed with the issuance of the ROD. After the lawsuit was filed and in response to it, FHWA decided to reopen the NEPA process to consider whether new or supplemental analysis and documentation were warranted. Consequently, plaintiffs action to enjoin construction of the project became moot. Plaintiffs responded, however, with a request for an award of attorney s fees and expenses. The District Court noted that the Fourth Circuit has developed a two-part test for determining whether an agency must prepare a supplemental EIS: 1) the courts must determine whether the agency took a hard look at the new information and 2) if they agency did take a hard look, they must determine whether the agency s decision not to prepare a supplemental EIS was arbitrary or capricious. The Court concluded that defendants had not taken a hard look since defendants offered no explanation for the failure to supplement the FEIS after the announcement of non-conformity in May Given the criticism the analysis received from EPA for using outdated computer modeling, the Court found that the need for a supplemental analysis should have been readily apparent to FHWA following the nonconformity announcement. The Court, consequently, awarded the plaintiffs their attorney s fees and expenses NCHRP Project 08-36, Task 35 33

40 Idaho Sporting Congress Inc., and The Ecology Center, Plaintiffs, v. United States Forest Service, Defendant, and Intermountain Forest Industry Association, Boise Cascade Corporation, and Evergreen Forest Products, Inc. Intervenors United States Court of Appeals for the Ninth Circuit 222 F.3d 562; 2000 U.S. App. LEXIS 20690; 51 ERC (BNA) 1728 Decided: June 5, 2000 The Idaho Sporting Congress (ISC) appealed the District Court s denial of its motion for preliminary injunction to prevent the U.S. Forest Service (FS) from proceeding with several timber sales and associated commercial logging in the Payette National Forest. ISC included among its claims that the EAs and EISs prepared by the FS did not comply with NEPA. The FS had initially settled with ISC by agreeing to write supplemental information reports (SIRs) that would examine whether further environmental review and documentation were required. FS completed the SIRs and concluded that the original EAs and EISs were adequate and that there was no need to revise its decision. The District Court had held that the FS is permitted under NEPA to use a process such as a SIR, instead of a supplemental EA or EIS. The Circuit Court disagreed with this interpretation and found two problems with the FS use of a SIR. First, the issue in dispute was not the presence of new information but the adequacy of the initial EAs and EISs. Because these documents had been found to be inadequate, a SIR cannot be used to present information and analysis that was required in the original NEPA documents. Second, if a reevaluation determines that a supplement is required, it has to be done prior to a decision, not as a justification for the completed decision and certainly not after an agency has proceeded with its action. In this case, the FS completed the SIRS in response to the litigation and without reopening either its decision making or its administrative appeal processes. The Circuit Court noted that because NEPA and the CEQ regulations are silent on the issue of how agencies are to determine the significance of new information, SIRs and other forms of reevaluations have been recognized and used by several federal agencies for the purpose of determining whether new information or changed circumstances require the preparation of a supplemental EA or EIS. Revaluations are not NEPA documents, and, therefore, they cannot substitute for the information required in one or be used to correct deficiencies in the original EA or EIS. Once an agency determines that new information is significant, it must prepare a supplemental EA or EIS. The Circuit Court remanded the case to the District Court with instructions to grant a preliminary injunction pending a final determination of the merits of ISC s claims. NCHRP Project 08-36, Task 35 34

41 APPENDIX B: SURVEY QUESTIONS FOR STATE DOTS Below is a list of the survey questions that were sent to all of the State DOT contacts via Do you have a formal process in place for conducting reevaluations of NEPA documents? If so, please describe it or indicate how we can access or obtain it. 2. Do you have guidance and/or do you conduct training on reevaluating NEPA documents and the reevaluation process? If so, please describe or indicate how we can access or obtain the information. 3. Who is responsible for identifying the need for a reevaluation? 4. What criteria are used to determine whether a reevaluation is needed? 5. When a reevaluation occurs, who determines the need for any additional environmental studies, interagency coordination and/or public involvement? 6. What environmental resources or other factors typically require additional studies, coordination, or public involvement? 7. Approximately what percentage of your projects requires reevaluation? Of those projects reevaluated, approximately what percentages are for projects where the NEPA document being reevaluated is: (a) a categorical exclusion, (b) an environmental assessment, or (c) an environmental impact statement? 8. How is a completed reevaluation documented? What is the typical level or amount of documentation, i.e., a one-pager, a less than 10 page analysis, or a more lengthy analysis? 9. Do you track your revaluations in a management system and, if so, how is this done? 10. What role do reevaluations play in tracking environmental commitments? 11. In addition to updating a project s NEPA compliance status, have you experienced any other project management or implementation benefits from your agency s reevaluation process? If so, please describe them. 12. Has your agency encountered any problems in conducting reevaluations? If so, please describe them. 13. Has your agency been able to develop any practices or procedures that overcome encountered problems? If so, please describe them in detail so that they may be considered for inclusion as best practices. NCHRP Project 08-36, Task 35 35

42 APPENDIX C: SAMPLE REEVALUATION FORMS NCHRP Project 08-36, Task 35 36

43 State of Alaska Department of Transportation & Public Facilities Statewide Design and Engineering Services Environmental Re-Evaluation Checklist NCHRP Project 08-36, Task 35 37

44 State of Alaska Department of Transportation & Public Facilities Statewide Design & Engineering Services ENVIRONMENTAL RE-EVALUATION CHECKLIST Project Name: Project Number (State/Federal): Date: Document Type and Approval Date: Re-Evaluation Number: Date of Last Re-Evaluation: The purpose of this re-evaluation is to ensure the conclusions of the original environmental document or subsequent re-evaluation remain valid. I. Proposed Action 1. Have changes occurred in the project scope since approval of the original environmental document or subsequent environmental re-evaluation? 2. Has there been a change in the project design parameters since the original environmental document or subsequent environmental document was approved? 3. Describe changes: N/A YES NO II. Purpose and Need 4. Has there been a change in the project purpose and need from that described in the approved environmental document or subsequent environmental document? 5. Describe changes. N/A YES NO III. Environmental Consequences Identify (yes or no) if there have been any changes in project impacts from those identified in the original environmental document or subsequent re-evaluations. For each yes, describe the magnitude of the change and potential for significant impact. 1. Has there been a change in the affected environment within or adjacent to the project area that could affect any of the impact categories (i.e. new legislation, transportation infrastructure, or protected resources)? 2. Describe changes. N/A YES NO A. Right-of-Way Impacts 1. Have the right-of-way requirements changed? 2. Have the project s effects on minorities or disadvantaged persons or those disproportionately affected changed? (E.O ) 3. Describe changes. N/A YES NO Environmental Re-Evaluation Checklist 1 Checklist Revised 10/15/04

45 Project Name: Date: B. Social Impacts 1. Would there be any changes in the neighborhoods or community cohesion for the various social groups as a result of the proposed action? 2. Are there any changes in travel patterns and accessibility (such as vehicular, commuter, bicycle, or pedestrian)? 3. Are there any changes to the impacts on school districts, recreation areas, churches, businesses, police and fire protection, etc.? Include the direct impacts and the indirect impacts that may result from the displacement of households and businesses. 4. Are there any changes to the effects of the project on the elderly, handicapped, nondrivers, transit-dependent, minority and ethnic groups, or the economically disadvantaged? 5. Describe changes. N/A YES NO C. Economic Impacts 1. Are there any changes in the economic impacts of the action on the regional and/or local economy, such as the effects of the project on development, tax revenues and public expenditures, employment opportunities, accessibility, and retail sales? 2. Are there any changes in the potential impacts of the proposed action on established businesses or business districts, or changes in any opportunities to minimize or reduce such impacts by the public and/or private sectors? 3. Describe changes. N/A YES NO D. Local Land Use and Transportation Plan 1. Have there been changes in the local land use or transportation plan? 2. If yes, is the project consistent with the changes to the local transportation land use plan? 3. Would project changes induce adverse secondary and cumulative effects? 4. Describe changes. N/A YES NO E. Cultural Resources Impacts 1. Are there changes in the project s effect on cultural resources? 2. Has there been a change in the status of National Register-listed eligible, or potentially eligible, sites in the project area? 3. Describe changes. N/A YES NO Environmental Re-Evaluation Checklist 2 Checklist Revised 10/15/04

46 Project Name: Date: F. Wetlands Impacts (If yes, resource coordination required) 1. Are there changes in project scope or design that affect the wetland impacts? 2. Acres (original/proposed): 3. Fill quantities (original/proposed: 4. Dredge quantities (original/proposed): 5. Describe any changes from the original environmental document and subsequent environmental re-evaluations. N/A YES NO G. Fish and Wildlife Impacts 1. Are there changes in the effects on fish and wildlife resources? 2. Do project changes require consultation with NMFS per Essential Fish Habitat (EFH) regulations? 3. Has there been a change in the effects on wildlife resources? 4. Does the project affect bald eagles or golden eagles? 5. Describe changes. N/A YES NO H. Threatened and Endangered Species (T&E) Impacts 1. Has there been a change in status of listed T&E species directly or indirectly affected by the project? 2. Describe changes. N/A YES NO I. Water Body Involvement 1. Have there been any changes in the project s effects on water bodies? If yes, complete 2-4 and describe in Does the project affect a navigable water body (as listed by USCG)? 3. Does the project affect navigable waters of the U.S. (as defined by the Corps)? 4. Does the project affect a Catalogued Anadromous Fish Stream ( )? 5. Describe changes. N/A YES NO J. Alaska Coastal Management Program (ACMP) 1. Are there changes that affect the standards of the ACMP? 2. Are there changes to a local coastal management district that affect the consistency finding? 3. If yes to #2, is the project consistent with local coastal management policies? 4. Describe changes. N/A YES NO Environmental Re-Evaluation Checklist 3 Checklist Revised 10/15/04

47 Project Name: Date: K. Hazardous Waste 1. Have there been any changes in the status of known or potentially contaminated sites along the corridor? 2. If buildings or residences are relocated, have they been evaluated for hazardous waste, such as asbestos? 3. Describe changes. N/A YES NO L. Air Quality Conformity 1. Does the project as proposed affect a nonattainment area, which will require a revised conformity determination? 2. Describe changes. N/A YES NO M. Floodplains Impacts 1. Have there been changes in the project effects on a regulatory floodway? 2. Does the project remain consistent with local flood protection standards and E.O ? 3. Have there been changes in the status of local flood hazard ordinances? 4. Describe changes. N/A YES NO N. Noise Impacts 1. Has there been a change in noise sensitive receivers/land uses adjacent to the proposed project? 2. Has there been a substantial change in vertical or horizontal alignment? 3. Has the number of through lanes or the project itself created a noise impact? 4. Has a noise analysis demonstrated potential noise impacts? 5. Are there feasible and reasonable measures that can reduce impacts? 6. Do changes in the project require a local noise permit? 7. Describe changes. N/A YES NO O. Water Quality Impacts 1. Does the project now involve a public or private drinking water source? 2. Would project changes affect the potential discharge of storm water into Waters of the U.S.? 3. Does the project affect a designated impaired water body? (If yes, complete a.) N/A YES NO Environmental Re-Evaluation Checklist 4 Checklist Revised 10/15/04

48 Project Name: Date: O. Water Quality Impacts a. List names and locations. N/A YES NO 4. Will the project now involve a municipal separate storm sewer system (MS4) NPDES permit, or will runoff be mixed with discharges from an NPDES permitted industrial facility? 5. Describe changes. P. Permits and Authorizations 1. Are there any changes in the status of the following permits and authorizations? a. Corps, Section 404/10 b. Coast Guard, Section 9 c. Department of Natural Resources (DNR), Title 41 d. Flood Hazard e. ADEC 401 f. ADEC Storm Water Plan g. DNR, ACMP h. Other. If yes, list. N/A YES NO 2. Describe changes. IV. Construction Impacts Have the following potential construction effects changed: 1. Construction timing commitments? 2. Temporary degradation of water quality? 3. Temporary stream diversion? 4. Temporary degradation of air quality? 5. Temporary delays and detours of traffic? 6. Temporary impacts on businesses? 7. Other construction impacts, including noise? 8. Describe changes. N/A YES NO Environmental Re-Evaluation Checklist 5 Checklist Revised 10/15/04

49 Project Name: Date: V. Section 4(f)/6(f) 1. Has there been a change in status of Section 4(f) properties affected by the proposed action? N/A YES NO 2. Would the project use property from Section 4(f) properties? 3. Has there been a change in status in Section 6(f) properties affected by the proposed action? 4. Is the use of 6(f) property a conversion of use per Section 6(f) of the LWCFA? If yes to any of the above, attach appropriate Section 4(f) and Section 6(f) documentation. VI. Comments and Coordination Conducted for the Re-Evaluation 1. Has public/agency coordination occurred since the environmental document was approved or since the last re-evaluation? N/A YES NO 2. Describe comments and coordination efforts taken for this project since approval of the environmental document or re-evaluation. Discuss pertinent issues raised by the public and government agencies. Attach applicable correspondence and responses. VII. Changes in Environmental Commitments or Mitigation Measures 1. Have there been any changes in the environmental commitments or mitigation? N/A YES NO 2. Describe changes. VIII. Environmental Re-Evaluation 1. The conclusions and commitments of the original environmental document approval or subsequent re-evaluation remain valid. If no, go to #2. N/A YES NO 2. The changes in the project scope, environmental consequences, or public controversy require a new, supplemental environmental document or EIS. No. 2 requires prior consultation with the FHWA area liaison and environmental specialist. Environmental Re-Evaluation Checklist 6 Checklist Revised 10/15/04

50 Project Name: Date: Prepared by: Environmental Analyst or Team Leader Approved by: Regional Environmental Coordinator Approved by: FHWA Area Liaison Date: Date: Date: Copy: Design Manager Environmental Re-Evaluation Checklist 7 Checklist Revised 10/15/04

51 State of California NEPA/CEQA Re-Validation Form NCHRP Project 08-36, Task 35 45

52 NEPA/CEQA RE-VALIDATION FORM DIST./CO./RTE. PM/PM E.A. or Fed-Aid Project No. Other Project No. (specify) PROJECT TITLE ENVIRONMENTAL APPROVAL TYPE DATE APPROVED REASON FOR CONSULTATION (23 CFR ) DESCRIPTION OF CHANGED CONDITIONS Enter District, County & Route (State projects) or the County & Route (Local projects) here. Enter the beginning and ending postmiles here (State projects). Enter the Expenditure Authorization (State projects) or Federal Aid Project # (Local projects) here. Enter any other project number here, and specify the type. Enter project title here. Enter type of original environmental document/ce Determination here. Enter date that environmental document/ce Determination was originally approved here. Check reason for consultation: Project proceeding to next major federal approval Change in scope, setting, effects, mitigation measures, requirements 3-year timeline (EIS only) Briefly describe the changed conditions or new information on page 2. Append continuation sheet(s) as necessary. Include a revised Environmental Commitments Record (ECR) when applicable. NEPA CONCLUSION - VALIDITY Based on an examination of the changed conditions and supporting information: [Check ONE of the two statements below, regarding the validity of the original document/determination (23 CFR ). If document is no longer valid, indicate whether additional public review is warranted and whether the type of environmental document will be elevated.] The original environmental document or CE remains valid. No further documentation will be prepared. The original document or CE is no longer valid; further documentation has been or will be prepared and is included on the continuation sheets or will be attached. (Yes/No) Additional public review is warranted (23 CFR (h)(3)) (Yes/No) Supplemental environmental document is needed. (Yes/No) New environmental document is needed. (If Yes, specify type: ) CONCURRENCE WITH NEPA CONCLUSION I concur with the NEPA conclusion above. Signature: Environmental Branch Chief Date Signature: Project Manager/DLAE Date CEQA CONCLUSION : (Only mandated for projects on the State Highway System.) Based on an examination of the changed conditions and supporting information, the following conclusion has been reached regarding appropriate CEQA documentation: (Check ONE of the four statements below, indicating whether any additional documentation will be prepared, and if so, what kind. If additional documentation is prepared, attach a copy of this signed form and any continuation sheets.) Original document remains valid. No further documentation is necessary. Only minor technical changes or additions to the previous document are necessary. An addendum has been or will be prepared and is included on the continuation sheets or will be attached. It need not be circulated for public review. (CEQA Guidelines, 15164) Changes are substantial, but only minor additions or changes are necessary to make the previous document adequate. A Supplemental environmental document will be prepared, and it will be circulated for public review. (CEQA Guidelines, 15163) Changes are substantial, and major revisions to the current document are necessary. A Subsequent environmental document will be prepared, and it will be circulated for public review. (CEQA Guidelines, 15162) (Specify type of subsequent document, e.g., Subsequent FEIR:) CONCURRENCE WITH CEQA CONCLUSION I concur with the CEQA conclusion above. Signature: Environmental Branch Chief Date Signature: Project Manager Date Page 1 of Revised 06/13/07

53 NEPA/CEQA RE-VALIDATION FORM CONTINUATION SHEET(S) Address only substantial changes or substantial new information since approval of the original document and only those areas that are applicable. Use the list below as section headings as they apply to the project change(s). Use as much or as little space as needed to adequately address the project change(s) and the associated impacts, minimization, avoidance and/or mitigation measures, if any. Changes in project design, e.g., substantial scope change; a new alternative; change in project alignment. Changes in environmental setting, e.g., new development affecting traffic or air quality; Changes in environmental circumstances, e.g., a new law or regulation; change in the status of a listed species. Changes to environmental impacts of the project, e.g., a new type of impact, or a change in the magnitude of an existing impact. Changes to avoidance, minimization, and/or mitigation measures since the environmental document was approved. Changes to environmental commitments since the environmental document was approved, e.g., the addition of new conditions in permits or approvals. When this applies, append a revised Environmental Commitments Record (ECR) as one of the Continuation Sheets. Page 2 of Revised 06/13/07

54 New Jersey Department of Transportation Environmental Reevaluation NCHRP Project 08-36, Task 35 48

55 NEW JERSEY DEPARTMENT OF TRANSPORTATION ENVIRONMENTAL REEVALUATION Route & Sec.: Local Rd. Name: Municipality: Fed. Project. No.: NJDOT Job No.: County: Environmental Document Type & Approval Date: Section 4(f): Date of Previous Reevaluation: NJDOT Project Manager: Type of Authorization Requested: A. Changes to the project since approval of the environmental document: Has there been a change in: No Yes Has there been a change in: No Yes 1. Design / Scope 2. Right-of-Way a. Project Limits 3. Public Opinion b. Roadway Work 4. Regulations, Rules, Laws c. Structure Work 5. Land Use d. Pavement Width 6. Section 4(f) e. Alignment 7. Other (Permits, Section 106, etc.) f. Drainage Type g. Access h. Other Project Features Describe any items checked YES above and comment on current public reaction. March 21, 2008 C:\DOCUMENTS AND SETTINGS\15744.ICF-HQ\LOCAL SETTINGS\TEMPORARY INTERNET FILES\OLK189\NJENVIROMENTAL REEVALUATION FORM DOC

56 B. Environmental Documentation: (Indicate response with a yes, no or N/A) 1. NEPA document still valid without additional documentation. 2. NEPA document still valid, supplemental documentation completed. 3. New NEPA document required. 4. Project subject to Army Corps of Engineers Nationwide Permit # 23. FHWA concurrence with this reevaluation required. 5. Project complies with E.O Floodplain. (For construction only) 6. Project complies with E.O Wetlands. (For construction only) Comments: C. FHWA Consultation: Consultation required if any items in Table A are marked YES unless project still meets a Certified CED definition. Use in determining need for FHWA concurrence of Environmental Reevaluation FHWA person consulted: Date D. FHWA Concurrence of Environmental Reevaluation is required because (Yes No) Items 2, 3, or 4 in Part B were checked YES Consultation in Part C requires it On the basis of this reevaluation, there are no significant changes in the proposed project s scope, right of way, affected environment or anticipated impacts since approval of the environmental document. March 21, 2008 C:\DOCUMENTS AND SETTINGS\15744.ICF-HQ\LOCAL SETTINGS\TEMPORARY INTERNET FILES\OLK189\NJENVIROMENTAL REEVALUATION FORM DOC

57 E. Submitted for Approval: Project Manager, Division of Project Management Date Environmental Team Leader, Bureau of Environmental Project Support Date F. Approved by: Manager, Bureau of Environmental Project Support Date G. Concurrence: Not required for certified CED s (FOR) - Division Administrator, Federal Highway Administration Date March 21, 2008 C:\DOCUMENTS AND SETTINGS\15744.ICF-HQ\LOCAL SETTINGS\TEMPORARY INTERNET FILES\OLK189\NJENVIROMENTAL REEVALUATION FORM DOC

58 Washington State Department of Transportation/Federal Highway Administration Environmental Reevaluation/Consultation Form NCHRP Project 08-36, Task 35 52

59 Environmental Reevaluation/Consultation Form 23 CFR Washington State Department of Transportation/Federal Highway Administration REGION/MODE SR PROJECT PROGRAM# FEDERAL AID # PROJECT# PROJECT TITLE, ENVIRONMENTAL DOCUMENT TYPE & DATE APPROVED: REASON FOR CONSULTATION: DESCRIPTION OF CHANGED CONDITIONS: HAVE ANY NEW OR REVISED LAWS OR REGULATIONS BEEN ISSUED SINCE APPROVAL OF THE LAST ENVIRONMENTAL DOCUMENT THAT AFFECTS THIS PROJECTS? YES ( ) NO ( ) (If yes explain, use additional sheets if necessary) WILL THE CHANGED CONDITIONS AFFECT THE FOLLOWING DIFFERENTLY THAT DESCRIBED IN THE ORIGINAL ENVIRONMENTAL DOCUMENT. (If yes, attach a detailed summary addressing the impacts and mitigation) YES NO YES NO 1) THREATENED or ENDANGERED SPECIES ( ) ( ) 5) HAZARDOUS WASTE SITES ( ) ( ) 2) PRIME and UNIIQUE FARMLAND ( ) ( ) 6) HISTORIC or ARCHAEOLOGICAL SITES ( ) ( ) 3) WETLANDS ( ) ( ) 7) 4 (f) LANDS ( ) ( ) 4) FLOODPLAINS ( ) ( ) 8) 6 (f) LANDS ( ) ( ) WILL THESE CHANGES RESULT IN ANY CONTROVERSY? YES ( ) NO ( ) (If yes explain) Environmental Procedures Manual M Exhibit 411-8, Page 1 of 2 April 2007

60 WILL THESE CHANGES CAUSE ADVERSE IMPACTS IN THE FOLLOWING AREAS: (If yes address comments below) YES NO YES NO 1) AIR QUALITY ( ) ( ) 7) WATER QUALITY ( ) ( ) 2) NOISE ( ) ( ) 8) VISUAL QUALITY ( ) ( ) 3) LAND USE ( ) ( ) 9) NATURAL RESOURCES and ENERGY ( ) ( ) 4) TRAFFIC or TRANSPORTATION ( ) ( ) 10) PUBLIC SERVICES and UTILITIES ( ) ( ) 5) DISPLACEMENT (business or residence) ( ) ( ) 11) VEGETATION and WILDLIFE ( ) ( ) 6) ECONOMIC GROWTH and DEVELOPMENT ( ) ( ) 12) RECREATION ( ) ( ) 13) SOCIAL IMPACTS ( ) ( ) COMMENTS: CONCLUSIONS and/ or RECOMMENDATIONS: I concur with the conclusions and recommendations above Region / Mode Official FHWA Official Date Date Environmental Procedures Manual M Exhibit 411-8, Page 2 of 2 April 2007

61 Florida Department of Transportation Project Reevaluation NCHRP Project 08-36, Task 35 55

62 SAMPLE Florida Department of Transportation PROJECT REEVALUATION I. GENERAL INFORMATION (originally approved document) a. Reevaluation Phase : b. Document Type and Date of Approval : c. Project Numbers : ETDM Federal Aid Financial Project ID d. Project Local Name, Location and Limits : e. Segments of Highway Being Advanced : f. Name of Analyst(s) : II. CONCLUSION AND RECOMMENDATION The above environmental document has been reevaluated as required by 23 CFR 771 or the Project Development and Environment Manual of FDOT, and it was determined that no substantial changes have occurred in the social, economic, or environmental effects of the proposed action that would significantly impact the quality of the human environment. Therefore, the original Administration Action remains valid. It is recommended that the project identified herein be advanced to the next phase of project development. REVIEWER SIGNATURE BLOCK District Environmental Management Office Engineer / / Date On (date) consultation between (FHWA or lead agency representative s name and the District representative s name) took place. This resulted in a determination that no major changes have taken place on this project since the last major approval and that the project may move forward. Note: This is a sample text and is to be used only to document consultation results when the written reevaluation has not been requested by the appropriate lead agency. If a formal submittal is requested, use the CONCURRENCE BLOCK shown below. III. FHWA (or lead federal agency) CONCURRENCE BLOCK (if required) Federal Highway Administration, Division Administrator / / Date FIGURE 13.3 Suggested Project Reevaluation Format PART 1, CHAPTER

63 IV. CHANGES IN IMPACT STATUS OR DOCUMENT COMPLIANCE A. NATURAL ENVIRONMENT YES / NO COMMENTS 1. Air Quality [ ] [ ] 2. Coastal and Marine [ ] [ ] 3. Contamination Sites [ ] [ ] 4. Farmlands [ ] [ ] 5. Floodplains [ ] [ ] 6. Infrastructure [ ] [ ] 7. Navigation [ ] [ ] 8. Special Designations [ ] [ ] 9. Water Quality/Quantity [ ] [ ] 10. Wetlands [ ] [ ] 11. Wildlife and Habitat [ ] [ ] B. CULTURAL IMPACTS 1. Historic/Archaeological [ ] [ ] 2. Recreation Areas [ ] [ ] 3. Section 4(f) Potential [ ] [ ] C. COMMUNITY IMPACTS 1. Aesthetics [ ] [ ] 2. Economics [ ] [ ] 3. Land Use [ ] [ ] 4. Mobility [ ] [ ] 5. Relocation [ ] [ ] 6. Social [ ] [ ] D. OTHER IMPACTS 1. Noise [ ] [ ] 2. Construction [ ] [ ] FIGURE 13.3 Suggested Project Reevaluation Format (continued) PART 1, CHAPTER

64 V. EVALUATION OF MAJOR DESIGN CHANGES AND REVISED DESIGN CRITERIA (e.g., Typical Section Changes, Alignment Shifts, Right of Way Changes, Bridge to Box Culvert, Drainage Requirements, revised design standards). VI. MITIGATION STATUS AND COMMITMENT COMPLIANCE VII. PERMITS STATUS FIGURE 13.3 Suggested Project Reevaluation Format (concluded) PART 1, CHAPTER

65 Exhibit 20-D Status of Environmental Certification STATUS OF ENVIRONMENTAL CERTIFICATION Financial Project ID Proposal/Contract ID Federal Aid No. Project Description This project is a Categorical Exclusion under 23 C.F.R : This project is a Type 1 Categorical Exclusion under (23 CFR (c)) effective November 27, 1987 as determined on, and the determination remains valid. This project is a Programmatic Categorical Exclusion per FHWA, FTA, and FDOT Agency Operating Agreement executed on January 15, 2003 as determined on, and the determination remains valid. The environmental document for this project was a (check one): A Type 2 Categorical Exclusion under 23 C.F.R (d) approved on, A Finding of No Significant Impact under 23 C.F.R approved on, or A Final Environmental Impact Statement under 23 C.F.R approved on. A reevaluation in accordance with 23 C.F.R was (check one): Approved on Not required. Signature: Environmental Administrator Date: Exhibit 20-D from Plans Preparation Manual, Volume I, Chapter 20, Plans Processing and Revisions FIGURE 13.4 Status of Environmental Certification PART 1, CHAPTER

66 APPENDIX D: SAMPLE REEVALUATION OF A FINAL ENVIRONMENTAL IMPACT STATEMENT NCHRP Project 08-36, Task 35 60

67 U. S. DEPARTMENT 228 Walnut Street, Room 508 OF TRANSPORTATION Pennsylvania Division Harrisburg, PA Federal Highway January 20, 2006 In reply refer to: Administration HEV-PA.1 Bucks County, Pennsylvania and Burlington County, New Jersey Pennsylvania Turnpike/Interstate 95 Interchange Project NEPA Reevaluation Mr. M. G. Patel, P.E. Chief Engineer for Highway Administration Pennsylvania Department of Transportation Harrisburg, Pennsylvania Dear Mr. Patel: The FHWA has reviewed the written reevaluation of the final Environmental Impact Statement prepared for the referenced project. This reevaluation (enclosed) was written consistent with FHWA regulation 23 CFR (c). The reevaluation is a good example of a concise NEPA document and may be considered a best practice. Upon review and consideration of the documentation included within and referenced, the FHWA finds that a supplemental EIS is not warranted to address any modifications in impacts due to final design or regulatory changes. Please proceed with final design and right-of-way. Sincerely yours, /s/ David W. Cough Enclosures James A. Cheatham Division Administrator cc: Al Jansen, P.E., Pennsylvania Turnpike Commission

68 approved FEIS Re-eval No Figure 1 - FEIS Elements.pdf Figure 2A - Design Sec..pdf Figure 2B - Design Sec..pdf PTC-I95 Interchange NEPA Reevaluation lt ec: Brian Hare, P.E., PennDOT, BOD Jeff Davis, P.E., PTC S:\FY2006\Jan\PTC-I95 NEPA Reeval.dss.doc

Docket No. CEQ August 20, the Council on Environmental Quality s (CEQ) advance notice of proposed rulemaking (ANPR)

Docket No. CEQ August 20, the Council on Environmental Quality s (CEQ) advance notice of proposed rulemaking (ANPR) Page 1 COMMENTS OF THE EDISON ELECTRIC INSTITUTE ON UPDATE TO THE REGULATIONS FOR IMPLEMENTING THE PROCEDURAL PROVISIONS OF THE NATIONAL ENVIRONMENTAL POLICY ACT Docket No. CEQ-2018-0001 The Edison Electric

More information

Guidance for Managing Legal Risks in the NEPA Process

Guidance for Managing Legal Risks in the NEPA Process Guidance for Managing Legal Risks in the NEPA Process This guidance is intended to assist federal and state transportation agencies in managing legal risks in the environmental review process for transportation

More information

Questions and Answers about the Final NEPA Procedures

Questions and Answers about the Final NEPA Procedures Questions and Answers about the Final NEPA Procedures What is the purpose of the NEPA procedures final rule? The Forest Service NEPA procedures rule places Forest Service procedures for implementing NEPA

More information

Determining Whether a Proposal is Subject to the National Environmental Policy Act (NEPA) Section 102 Updated March

Determining Whether a Proposal is Subject to the National Environmental Policy Act (NEPA) Section 102 Updated March Determining Whether a Proposal is Subject to the National Environmental Policy Act (NEPA) Section 102 Updated March 2005 1 This paper presents some key thresholds to consider when determining whether a

More information

Improving the U.S. Coast Guard s Scoping & Public Involvement Processes

Improving the U.S. Coast Guard s Scoping & Public Involvement Processes Improving the U.S. Coast Guard s Scoping & Public Involvement Processes By Hector L. Schmidt United States Coast Guard Civil Engineering Unit Miami Miami, Florida September 2012 Capstone paper submitted

More information

CHAPTER 7. Statewide Implementation Agreement

CHAPTER 7. Statewide Implementation Agreement CHAPTER 7 Statewide Implementation Agreement National Environmental Policy Act and Clean Water Act Section 404 Concurrent NEPA/404 Processes for Highway Projects in Iowa Note: This process is managed by

More information

Opportunities for Accelerating FTA Project Development Post MAP-21

Opportunities for Accelerating FTA Project Development Post MAP-21 Opportunities for Accelerating FTA Project Development Post MAP-21 October 20, 2013 Diana C. Mendes, AICP AECOM Overview Framework for FTA approach to environmental review during project development Provisions

More information

Texas Department of Transportation Page 1 of 59 Environmental Review of Transportation Projects

Texas Department of Transportation Page 1 of 59 Environmental Review of Transportation Projects Texas Department of Transportation Page of 0 Proposed Preamble The Texas Department of Transportation (department) proposes the repeal of TAC Chapter, Subchapter A,.-.0, Environmental Review and Public

More information

COUNTYWIDE RISK ASSESSMENT AND AUDIT PLAN SUMMIT COUNTY, OHIO

COUNTYWIDE RISK ASSESSMENT AND AUDIT PLAN SUMMIT COUNTY, OHIO COUNTYWIDE RISK ASSESSMENT AND AUDIT PLAN CONTENTS Page Independent Accountants Report on Applying Agreed-Upon Procedures 1 I. Introduction 2 II. Principles for the Risk Assessment and Audit Plan Development

More information

STAFF QUESTIONS AND ANSWERS

STAFF QUESTIONS AND ANSWERS 1666 K Street, N.W. Washington, DC 20006 Telephone: (202) 207-9100 Facsimile: (202) 862-8430 www.pcaobus.org STAFF QUESTIONS AND ANSWERS AUDITING INTERNAL CONTROL OVER FINANCIAL REPORTING Summary: Staff

More information

Preparing a Reevaluation Using the Documented Reevaluation Checklist (DRC)

Preparing a Reevaluation Using the Documented Reevaluation Checklist (DRC) Guidance Preparing a Reevaluation Using the Documented This guidance outlines the TxDOT process for preparing a documented reevaluation as required by 43 TAC 2.85 and 23 CFR 771.129. TxDOT Environmental

More information

INTERNATIONAL STANDARD ON AUDITING 701 COMMUNICATING KEY AUDIT MATTERS IN THE INDEPENDENT AUDITOR S REPORT

INTERNATIONAL STANDARD ON AUDITING 701 COMMUNICATING KEY AUDIT MATTERS IN THE INDEPENDENT AUDITOR S REPORT INTERNATIONAL STANDARD ON AUDITING 701 COMMUNICATING KEY AUDIT MATTERS IN THE INDEPENDENT AUDITOR S REPORT (Effective for audits of financial statements for periods ending on or after December 15, 2016)

More information

of a physical Permitting Council office. With initial Cross-Agency Priority (CAP) Goal funding, the Office of the Executive Director, in cooperation

of a physical Permitting Council office. With initial Cross-Agency Priority (CAP) Goal funding, the Office of the Executive Director, in cooperation Janet Pfleeger Acting Executive Director Federal Permitting Improvement Steering Council Testimony before Senate Committee on Energy and Natural Resources December 12, 2017 Good morning Chairman Murkowski,

More information

Internal Audit Charter

Internal Audit Charter Internal Audit Charter 1. Purpose The purpose of this Charter is to state clearly the objectives and scope of esure Group s (esure) Internal Audit function. It also serves to outline the function s position

More information

EXECUTIVE STRATEGIES FOR RISK MANAGEMENT BY STATE DEPARTMENTS OF TRANSPORTATION EXECUTIVE SUMMARY

EXECUTIVE STRATEGIES FOR RISK MANAGEMENT BY STATE DEPARTMENTS OF TRANSPORTATION EXECUTIVE SUMMARY EXECUTIVE STRATEGIES FOR RISK MANAGEMENT BY STATE DEPARTMENTS OF TRANSPORTATION EXECUTIVE SUMMARY Prepared for: NCHRP 20-24 Administration of Highway and Transportation Agencies Prepared by: Janet D Ignazio

More information

An Overview and Comparison of the Tennessee Department of Transportation s Environmental Evaluation Process

An Overview and Comparison of the Tennessee Department of Transportation s Environmental Evaluation Process Introduction This document provides a brief overview of the policy and procedures that govern the environmental evaluation process that the Tennessee Department of Transportation (TDOT) must follow for

More information

18 June 2017 PRACTITIONER S HANDBOOK AASHTO ADDRESSING AIR QUALITY ISSUES IN THE NEPA PROCESS FOR HIGHWAY PROJECTS

18 June 2017 PRACTITIONER S HANDBOOK AASHTO ADDRESSING AIR QUALITY ISSUES IN THE NEPA PROCESS FOR HIGHWAY PROJECTS AASHTO PRACTITIONER S HANDBOOK 18 June 2017 ADDRESSING AIR QUALITY ISSUES IN THE NEPA PROCESS FOR HIGHWAY PROJECTS This handbook is intended to assist practitioners in addressing air quality issues, including

More information

Speed Up the Delivery of Transportation Projects

Speed Up the Delivery of Transportation Projects Speed Up the Delivery of Transportation Projects A Better Outcome in Half the Time through Integrated and Programmatic Approaches A typical highway project can take from 10 to 15 years to complete up to

More information

Follow-up Audit of the CNSC Performance Measurement and Reporting Frameworks, November 2011

Follow-up Audit of the CNSC Performance Measurement and Reporting Frameworks, November 2011 Audit of Mobile Telecommunication Devices June 21, 2012 Follow-up Audit of the CNSC Performance Measurement and Reporting Frameworks, November 2011 Presented to the Audit Committee on November 21, 2016

More information

Internal Audit Charter

Internal Audit Charter Internal Audit Charter 1. Purpose The purpose of this Charter is to state clearly the objectives and scope of esure Group Plc s (esure) Internal Audit function. It also serves to outline the function s

More information

IAASB CAG Public Session (March 2016) Agenda Item. Initial Discussion on the IAASB s Future Project Related to ISA 315 (Revised) 1

IAASB CAG Public Session (March 2016) Agenda Item. Initial Discussion on the IAASB s Future Project Related to ISA 315 (Revised) 1 Agenda Item C.1 Initial Discussion on the IAASB s Future Project Related to ISA 315 (Revised) 1 Objectives of the IAASB CAG Discussion The objective of this agenda item are to: (a) Present initial background

More information

Standard on Auditing (SA) 701, Communicating Key Audit Matters in the Independent Auditor s Report Contents Paragraph(s) Introduction Scope of this SA

Standard on Auditing (SA) 701, Communicating Key Audit Matters in the Independent Auditor s Report Contents Paragraph(s) Introduction Scope of this SA Standard on Auditing (SA) 701, Communicating Key Audit Matters in the Independent Auditor s Report Contents Paragraph(s) Introduction Scope of this SA... 1 5 Effective Date... 6 Objectives... 7 Definition...

More information

Appendix L: Consideration of Woodmont Commons East Aquatic Resource Impacts and Mitigation for NEPA and Section 404 Permitting

Appendix L: Consideration of Woodmont Commons East Aquatic Resource Impacts and Mitigation for NEPA and Section 404 Permitting Appendix L: Consideration of Woodmont Commons East Aquatic Resource Impacts and Mitigation for NEPA and Section 404 Permitting Memorandum DATE: August 22, 2018 TO: FROM: Project File Louis Berger SUBJECT:

More information

PROGRAMMATIC AGREEMENT A CONCURRENCE PROCESS FOR TRANSPORTATION PROJECTS REQUIRING COMPENSATORY MITIGATION. By Agreement Among

PROGRAMMATIC AGREEMENT A CONCURRENCE PROCESS FOR TRANSPORTATION PROJECTS REQUIRING COMPENSATORY MITIGATION. By Agreement Among PROGRAMMATIC AGREEMENT A CONCURRENCE PROCESS FOR TRANSPORTATION PROJECTS REQUIRING COMPENSATORY MITIGATION By Agreement Among IOWA DEPARTMENT OF TRANSPORTATION FEDERAL HIGHWAY ADMINISTRATION And U. S.

More information

IAASB Main Agenda (March 2016) Agenda Item. Initial Discussion on the IAASB s Future Project Related to ISA 315 (Revised) 1

IAASB Main Agenda (March 2016) Agenda Item. Initial Discussion on the IAASB s Future Project Related to ISA 315 (Revised) 1 Agenda Item 3-A Initial Discussion on the IAASB s Future Project Related to ISA 315 (Revised) 1 Objectives of the IAASB Discussion The objective of this agenda item are to: (a) Present initial background

More information

H. R (a) IN GENERAL. Subchapter I of chapter 1 of title 23, United States Code, is amended by inserting after section 138 the following:

H. R (a) IN GENERAL. Subchapter I of chapter 1 of title 23, United States Code, is amended by inserting after section 138 the following: H. R. 3 714 (7) PLANNING FINDING. A finding shall be made by the Secretary at least every 4 years that the transportation planning process through which statewide transportation plans and programs are

More information

PHASE TWO FOLLOW-UP REPORT ON THE AUDIT OF CONTRACTS (2008)

PHASE TWO FOLLOW-UP REPORT ON THE AUDIT OF CONTRACTS (2008) PHASE TWO FOLLOW-UP REPORT ON THE AUDIT OF CONTRACTS (2008) PREPARED BY: Government Audit Services Branch Government of Yukon APPROVED BY: Audit Committee Table of Contents Page PREFACE 3 EXECUTIVE SUMMARY

More information

EPA and the Corps agree that the proposed discharge can reasonably be expected to result in environmental gain or insignificant losses.

EPA and the Corps agree that the proposed discharge can reasonably be expected to result in environmental gain or insignificant losses. MEMORANDUM OF AGREEMENT BETWEEN THE ENVIRONMENTAL PROTECTION AGENCY AND THE DEPARTMENT OF THE ARMY CONCERNING THE DETERMINATION OF MITIGATION UNDER THE CLEAN WATER ACT SECTION 404(b)(1) GUIDELINES February

More information

National Environmental Policy Act (NEPA)

National Environmental Policy Act (NEPA) National Environmental Policy Act (NEPA) Jeff Wade Center for Governmental Responsibility University of Florida Levin College of Law The National Environmental Policy Act of 1969 (NEPA) first significant,

More information

FOREST SERVICE HANDBOOK NATIONAL HEADQUARTERS (WO) WASHINGTON, DC

FOREST SERVICE HANDBOOK NATIONAL HEADQUARTERS (WO) WASHINGTON, DC Page 1 of 47 FOREST SERVICE HANDBOOK NATIONAL HEADQUARTERS (WO) WASHINGTON, DC Amendment No.: 1909.15-2012-3 Effective Date: June 25, 2012 Duration: This amendment is effective until superseded or removed.

More information

ES&H DIVISION SLAC-I-750-0A16C-001 R001. SLAC National Environmental Policy Act (NEPA) Implementation Procedure

ES&H DIVISION SLAC-I-750-0A16C-001 R001. SLAC National Environmental Policy Act (NEPA) Implementation Procedure ES&H DIVISION SLAC-I-750-0A16C-001 R001 SLAC National Environmental Policy Act (NEPA) Implementation Procedure August 15, 2017 Purpose The objectives of the National Environmental Policy Act (NEPA) are

More information

February 23-24, 2009 Robert D. Thornton, Partner

February 23-24, 2009 Robert D. Thornton, Partner National Environmental Policy Act: A Primer February 23-24, 2009 Robert D. Thornton, Partner NEPA Fundamentals What is NEPA? Statement of Environmental Policy Environmental Review Process Institutional

More information

FOREST SERVICE HANDBOOK NATIONAL HEADQUARTERS (WO) WASHINGTON, DC

FOREST SERVICE HANDBOOK NATIONAL HEADQUARTERS (WO) WASHINGTON, DC Page 1 of 47 FOREST SERVICE HANDBOOK NATIONAL HEADQUARTERS (WO) WASHINGTON, DC Amendment No.: 1909.15-2011-1 Effective Date: April 1, 2011 Duration: This amendment is effective until superseded or removed.

More information

RECLAIMING NEPA. Lucinda Low Swartz, Esq. 1 Environmental Consultant Kensington, Maryland

RECLAIMING NEPA. Lucinda Low Swartz, Esq. 1 Environmental Consultant Kensington, Maryland RECLAIMING NEPA Lucinda Low Swartz, Esq. 1 Environmental Consultant Kensington, Maryland ABSTRACT Streamlining NEPA has been a mantra for years, most recently in the context of the need to spend economic

More information

Lack of coordination among federal, state

Lack of coordination among federal, state 5 INTERAGENCY COORDINATION Lack of coordination among federal, state and local agencies can delay transportation projects and cause unnecessary loss or degradation of wildlife habitat. Indeed, the transportation,

More information

NEPA 101. Minnesota DOT. Dave Gamble FHWA Resource Center Technical Service Team. Environmental Stewardship & Streamlining Workshop March 31, 2009

NEPA 101. Minnesota DOT. Dave Gamble FHWA Resource Center Technical Service Team. Environmental Stewardship & Streamlining Workshop March 31, 2009 NEPA 101 Minnesota DOT Environmental Stewardship & Streamlining Workshop March 31, 2009 Dave Gamble FHWA Resource Center Technical Service Team Environment NEPA 101 Objectives Background and Basics of

More information

CITY OF CHELAN GROWTH MANAGEMENT ACT PUBLIC PARTICIPATION PLAN. Introduction

CITY OF CHELAN GROWTH MANAGEMENT ACT PUBLIC PARTICIPATION PLAN. Introduction CITY OF CHELAN GROWTH MANAGEMENT ACT PUBLIC PARTICIPATION PLAN March 10, 2016 Introduction One cornerstone for the success of the Growth Management Act (GMA) is citizen participation. That concept is first

More information

National Environmental Policy Act Implementing Procedures and Categorical Exclusions

National Environmental Policy Act Implementing Procedures and Categorical Exclusions This document is scheduled to be published in the Federal Register on 01/16/2015 and available online at http://federalregister.gov/a/2015-00681, and on FDsys.gov Billing Code: 6560-58 GULF COAST ECOSYSTEM

More information

INTEGRATING NATIONAL ENVIRONMENTAL POLICY ACT COMPLIANCE REAUTHORIZED MAGNUSON-STEVENS ACT

INTEGRATING NATIONAL ENVIRONMENTAL POLICY ACT COMPLIANCE REAUTHORIZED MAGNUSON-STEVENS ACT INTEGRATING NATIONAL ENVIRONMENTAL POLICY ACT COMPLIANCE INTO A REAUTHORIZED MAGNUSON-STEVENS ACT A Council Coordination Committee Concept White Paper May 2014 1 Introduction Fishery management involves

More information

COST-BENEFIT ANALYSIS. Categorical Exclusions for Oil and Gas Exploration and Development Activities. USDA Forest Service

COST-BENEFIT ANALYSIS. Categorical Exclusions for Oil and Gas Exploration and Development Activities. USDA Forest Service December 7, 2005 COST-BENEFIT ANALYSIS Categorical Exclusions for Oil and Gas Exploration and Development Activities USDA Forest Service COST-BENEFIT ANALYSIS Categorical Exclusions for Oil and Gas Exploration

More information

Kammy Horne, AICP URS Corporation Multimodal Transportation Manager Phoenix, Arizona

Kammy Horne, AICP URS Corporation Multimodal Transportation Manager Phoenix, Arizona Categorical Exclusions for Federally Funded Transit Projects: Due Diligence in Compliance with Environmental Regulations Kammy Horne, AICP URS Corporation Multimodal Transportation Manager Phoenix, Arizona

More information

Departmental Manual Part 516

Departmental Manual Part 516 Departmental Manual Part 516 Page 1 of 1 U.S. DEPARTMENT OF THE INTERIOR BUREAU OF LAND MANAGEMENT Search BLM National Go What We Do Visit Us Information Center Get Involved Our Offices/Centers Contact

More information

United States Forest Service National Environmental Policy Act Process Fact Sheet. Colorado Cattlemen s Association Colorado Public Lands Council

United States Forest Service National Environmental Policy Act Process Fact Sheet. Colorado Cattlemen s Association Colorado Public Lands Council United States Forest Service National Environmental Policy Act Process Fact Sheet Colorado Cattlemen s Association Compiled by Robbie Baird LeValley with special assistance from the Rocky Mountain Region

More information

INTEGRATING NATIONAL ENVIRONMENTAL POLICY ACT COMPLIANCE REAUTHORIZED MAGNUSON-STEVENS ACT

INTEGRATING NATIONAL ENVIRONMENTAL POLICY ACT COMPLIANCE REAUTHORIZED MAGNUSON-STEVENS ACT INTEGRATING NATIONAL ENVIRONMENTAL POLICY ACT COMPLIANCE INTO A REAUTHORIZED MAGNUSON-STEVENS ACT A Council Coordination Committee Concept White Paper February 2015 1 Introduction Fishery management involves

More information

Job Evaluation Guide for TMG. October 2016

Job Evaluation Guide for TMG. October 2016 Job Evaluation Guide for TMG October 2016 Contents Introduction... 1 Job Evaluation: Determining the Value of Each Job... 1 The Hay Group Guide Chart-Profile Method SM of Job Evaluation... 1 Jobs Included

More information

Compilation Engagements

Compilation Engagements Basis for Conclusions March 2012 International Standard on Related Services ISRS 4410 (Revised), Compilation Engagements This document was prepared by the Staff of the International Auditing and Assurance

More information

FSH NATIONAL ENVIRONMENTAL POLICY ACT HANDBOOK CHAPTER - ZERO CODE. Table of Contents

FSH NATIONAL ENVIRONMENTAL POLICY ACT HANDBOOK CHAPTER - ZERO CODE. Table of Contents Page 1 of 19 Table of Contents 01 - PROPOSED ACTIONS SUBJECT TO THE NATIONAL ENVIRONMENTAL POLICY ACT (NEPA) REQUIREMENTS (42 U.S.C. 4321 ET SEQ.)... 2 02 - OBJECTIVE... 6 05 - DEFINITIONS... 6 06 - SCHEDULE

More information

INTERNAL AUDIT DIVISION AUDIT REPORT 2013/102

INTERNAL AUDIT DIVISION AUDIT REPORT 2013/102 INTERNAL AUDIT DIVISION AUDIT REPORT 2013/102 Audit of the United Nations Conference on Trade and Development arrangements for initiation, review and clearance of technical cooperation projects Overall

More information

APPENDIX A. NEPA Assessment Checklist

APPENDIX A. NEPA Assessment Checklist APPENDI A NEPA Assessment Checklist NEPA CHECKLIST DATE: January 12, 2009 PREPARER: Frederick Wells, RLA PIN and Project Title: Surplus Property Request Wilder Balter Partners Marketplace Town of Newburgh,

More information

TIER II STANDARD FOR TECHNICAL COOPERATION ADMINISTRATORS INTRODUCTION

TIER II STANDARD FOR TECHNICAL COOPERATION ADMINISTRATORS INTRODUCTION Job Classification Manual Page 1 of 49 TIER II STANDARD FOR TECHNICAL COOPERATION ADMINISTRATORS INTRODUCTION 1. This grade level standard illustrates the application of the ICSC Master Standard (Tier

More information

Docket ID CEQ Implementation of Procedural Provisions of National Environmental Policy Act

Docket ID CEQ Implementation of Procedural Provisions of National Environmental Policy Act Docket ID CEQ-2018-0001 Implementation of Procedural Provisions of National Environmental Policy Act Comments submitted by National Association of Forest Service Retirees (NAFSR) and The Public Lands Foundation

More information

Arizona Association of County Engineers New Rules for Categorical Exclusions for FHWA Projects

Arizona Association of County Engineers New Rules for Categorical Exclusions for FHWA Projects Arizona Association of County Engineers New Rules for Categorical Exclusions for FHWA Projects Paul O Brien Manager, ADOT Environmental Planning Group June 19, 201 4 MAP-21 What are the new rules for Categorical

More information

INDIRECT AND CUMULATIVE IMPACT ANALYSIS

INDIRECT AND CUMULATIVE IMPACT ANALYSIS INDIRECT AND CUMULATIVE IMPACT ANALYSIS A review and synthesis of the requirements for indirect and cumulative impact analysis and mitigation under major environmental laws and regulations. Requested by:

More information

Agenda Item 1B (marked) Proposed SAS, Communicating Key Audit Matters in the Independent Auditor s Report (AU-C 701)

Agenda Item 1B (marked) Proposed SAS, Communicating Key Audit Matters in the Independent Auditor s Report (AU-C 701) ASB Meeting July 17-20, 2017 Agenda Item 1B (marked) Proposed SAS, Communicating Key Audit Matters in the Independent Auditor s Report (AU-C 701) Requirements Application Material Introduction Scope of

More information

House Committee on Transportation and Infrastructure, Subcommittee on Highways and Transit Attention: Andrew Okuyiga From: Subject:

House Committee on Transportation and Infrastructure, Subcommittee on Highways and Transit Attention: Andrew Okuyiga From: Subject: MEMORANDUM June 7, 2017 To: House Committee on Transportation and Infrastructure, Subcommittee on Highways and Transit Attention: Andrew Okuyiga From: Subject: Questions regarding the report Two Years

More information

National Environmental Policy Act & Habitat Conservation Plans

National Environmental Policy Act & Habitat Conservation Plans National Environmental Policy Act & Habitat Conservation Plans IPAA Strategic Planning Conference Ellen Miille, Principal ICF February 14, 2017 Key Points Why is NEPA required? How is the NEPA public review

More information

Procedures for Implementing the National Environmental Policy Act. SUMMARY: The Tennessee Valley Authority (TVA) is proposing to amend its

Procedures for Implementing the National Environmental Policy Act. SUMMARY: The Tennessee Valley Authority (TVA) is proposing to amend its This document is scheduled to be published in the Federal Register on 06/08/2017 and available online at https://federalregister.gov/d/2017-11784, and on FDsys.gov 8120-08-P TENNESSEE VALLEY AUTHORITY

More information

Supporting DOE EM 4.31, Office of Regulatory Compliance

Supporting DOE EM 4.31, Office of Regulatory Compliance SUMMER INTERNSHIP TECHNICAL REPORT Supporting DOE EM 4.31, Office of Regulatory Compliance DOE-FIU SCIENCE & TECHNOLOGY WORKFORCE DEVELOPMENT PROGRAM Date submitted: October 13, 2017 Principal Investigators:

More information

Using the Transportation Planning Process to Support the NEPA Process

Using the Transportation Planning Process to Support the NEPA Process AASHTO Practitioner s handbook 14 June 2011 Applying the Section 404(b)(1) Guidelines in Transportation Project Decision-Making This Handbook is intended to assist practitioners in applying the Section

More information

AMF Position Compliance function requirements

AMF Position Compliance function requirements AMF Position 2012-17 Compliance function requirements Reference texts: Articles 313-1 to 313-3, 313-5 to 313-7, 313-54, 313-75 of the AMF General Regulation The Autorité des Marchés Financiers applies

More information

ADMINISTRATIVE INTERNAL AUDIT Board of Trustees Approval: 03/10/2004 CHAPTER 1 Date of Last Cabinet Review: 04/07/2017 POLICY 3.

ADMINISTRATIVE INTERNAL AUDIT Board of Trustees Approval: 03/10/2004 CHAPTER 1 Date of Last Cabinet Review: 04/07/2017 POLICY 3. INTERNAL AUDIT Board of Trustees Approval: 03/10/2004 POLICY 3.01 Page 1 of 14 I. POLICY The Internal Audit Department assists Salt Lake Community College in accomplishing its objectives by providing an

More information

CENTRAL BANK OF CYPRUS

CENTRAL BANK OF CYPRUS GUIDELINES TO BANKS ON THE APPROVAL PROCESS OF THE INTERNAL RATINGS BASED (IRB) AND THE ADVANCED MEASUREMENT (AMA) APPROACHES FOR THE CALCULATION OF CAPITAL REQUIREMENTS APRIL 2007 TABLE OF CONTENTS 1.

More information

Transportation Conformity Guidance for Qualitative Hot-spot Analyses in PM 2.5 and PM 10 Nonattainment and Maintenance Areas

Transportation Conformity Guidance for Qualitative Hot-spot Analyses in PM 2.5 and PM 10 Nonattainment and Maintenance Areas Transportation Conformity Guidance for Qualitative Hot-spot Analyses in PM 2.5 and PM 10 Nonattainment and Maintenance Areas United States Environmental Protection Agency Federal Highway Administration

More information

ISO INTERNATIONAL STANDARD. Risk management Principles and guidelines. Management du risque Principes et lignes directrices

ISO INTERNATIONAL STANDARD. Risk management Principles and guidelines. Management du risque Principes et lignes directrices INTERNATIONAL STANDARD ISO 31000 First edition 2009-11-15 Risk management Principles and guidelines Management du risque Principes et lignes directrices http://mahdi.hashemitabar.com Reference number ISO

More information

Regulatory Guidance Letter 93-02

Regulatory Guidance Letter 93-02 Regulatory Guidance Letter 93-02 SUBJECT: Guidance on Flexibility of the 404(b)(1) Guidelines and Mitigation Banking DATE: August 23, 1993 EXPIRES: December 31, 1998 1. Enclosed are two guidance documents

More information

PRACTITIONER S HANDBOOK

PRACTITIONER S HANDBOOK AASHTO PRACTITIONER S HANDBOOK 03 August 2016 MANAGING THE NEPA PROCESS FOR TOLL LANES AND TOLL ROADS This Handbook provides recommendations for conducting National Environmental Policy Act (NEPA) studies

More information

(Effective for audits of financial statements for periods ending on or after December 15, 2013) CONTENTS

(Effective for audits of financial statements for periods ending on or after December 15, 2013) CONTENTS INTERNATIONAL STANDARD ON AUDITING 315 (REVISED) IDENTIFYING AND ASSESSING THE RISKS OF MATERIAL MISSTATEMENT THROUGH UNDERSTANDING THE ENTITY AND ITS ENVIRONMENT Introduction (Effective for audits of

More information

ISA 701, Communicating Key Audit Matters in the Independent Auditor s Report

ISA 701, Communicating Key Audit Matters in the Independent Auditor s Report ISA 701 April 2015 International Standard on Auditing ISA 701, Communicating Key Audit Matters in the Independent Auditor s Report Explanatory Foreword INTERNATIONAL STANDARD ON AUDITING 701 Communicating

More information

03 July 2006 PRACTITIONER S HANDBOOK AASHTO MANAGING THE NEPA PROCESS FOR TOLL LANES AND TOLL ROADS. AASHTO Center for Environmental Excellence

03 July 2006 PRACTITIONER S HANDBOOK AASHTO MANAGING THE NEPA PROCESS FOR TOLL LANES AND TOLL ROADS. AASHTO Center for Environmental Excellence AASHTO PRACTITIONER S HANDBOOK 03 July 2006 MANAGING THE NEPA PROCESS FOR TOLL LANES AND TOLL ROADS Conducting National Environmental Policy Act (NEPA) studies projects involving toll lanes and toll roads

More information

National Environmental Policy Act ( NEPA ) 2013 Environmental Law Workshop Loyola Law School/Sierra Club Angeles Chapter

National Environmental Policy Act ( NEPA ) 2013 Environmental Law Workshop Loyola Law School/Sierra Club Angeles Chapter National Environmental Policy Act ( NEPA ) 2013 Environmental Law Workshop Loyola Law School/Sierra Club Angeles Chapter NEPA 1. OVERVIEW OF NEPA STATUTE 2. COMPARISONS TO CEQA 3. RECENT DEVELOPMENTS NEPA

More information

o62. Honeywell m Additional RACT Requirements for June 27, 2014

o62. Honeywell m Additional RACT Requirements for June 27, 2014 o62. Honeywell Honeywell 101 Columbia Rd. Morristown, NJ 07962 June 27, 2014 Via Electronic and Overnight Mail Environmental Quality Board Rachel Carson State Office Building 16th Floor 400 Market Street

More information

ISRS 4410 (Revised), Compilation Engagements

ISRS 4410 (Revised), Compilation Engagements International Auditing and Assurance Standards Board Exposure Draft October 2010 Comments requested by March 31, 2011 Proposed International Standard on Related Services ISRS 4410 (Revised), Compilation

More information

Compilation and analysis of available information on the scope, effectiveness and functioning of the flexibility mechanisms under the Kyoto Protocol

Compilation and analysis of available information on the scope, effectiveness and functioning of the flexibility mechanisms under the Kyoto Protocol UNITED NATIONS Distr. GENERAL 16 October 2008 ENGLISH ONLY CONFERENCE OF THE PARTIES SERVING AS THE MEETING OF THE PARTIES TO THE KYOTO PROTOCOL Fourth session Poznan, 1 12 December 2008 Item 13 of the

More information

REGISTERED CANDIDATE AUDITOR (RCA) TECHNICAL COMPETENCE REQUIREMENTS

REGISTERED CANDIDATE AUDITOR (RCA) TECHNICAL COMPETENCE REQUIREMENTS REGISTERED CANDIDATE AUDITOR (RCA) TECHNICAL COMPETENCE REQUIREMENTS 1. Context After completion of the recognised training contract, a period of specialisation is required, appropriate to the level required

More information

SRI LANKA AUDITING STANDARD 315 (REVISED)

SRI LANKA AUDITING STANDARD 315 (REVISED) SRI LANKA AUDITING STANDARD 315 (REVISED) IDENTIFYING AND ASSESSING THE RISKS OF MATERIAL MISSTATEMENT THROUGH UNDERSTANDING THE ENTITY AND ITS ENVIRONMENT (Effective for audits of financial statements

More information

ISA 230, Audit Documentation

ISA 230, Audit Documentation International Auditing and Assurance Standards Board Exposure Draft December 2006 Comments are requested by March 31, 2007 Proposed Redrafted International Standard on Auditing ISA 230, Audit Documentation

More information

IAASB Main Agenda Page Agenda Item

IAASB Main Agenda Page Agenda Item IAASB Main Agenda Page 2003 773 Agenda Item 2-A Revision of ISA 230 Documentation Issues Paper Introduction OBJECTIVES 1. The objectives of this project are to revise and update ISA 230 taking into account

More information

Models for Evaluation and Performance Measurement for Small Agencies. Summary Report

Models for Evaluation and Performance Measurement for Small Agencies. Summary Report Models for Evaluation and Performance Measurement for Small Agencies Summary Report Table of Contents Acknowledgements i Executive Summary ii 1.0 Introduction 1 2.0 Overview of Approach 2 3.0 Findings

More information

Guidance Note: Corporate Governance - Audit Committee. January Ce document est aussi disponible en français.

Guidance Note: Corporate Governance - Audit Committee. January Ce document est aussi disponible en français. Guidance Note: Corporate Governance - Audit Committee January 2018 Ce document est aussi disponible en français. Applicability The Guidance Note: Corporate Governance Audit Committee (the Guidance Note

More information

The National Environmental Policy Act: Streamlining NEPA

The National Environmental Policy Act: Streamlining NEPA Order Code RL33267 The National Environmental Policy Act: Streamlining NEPA Updated January 9, 2007 Linda Luther Analyst in Environmental Policy Resources, Science, and Industry Division The National Environmental

More information

A Proven Path for Improving Government Debt Collection

A Proven Path for Improving Government Debt Collection ISSUE PAPER Experience the commitment A Proven Path for Improving Government Debt Collection This issue paper describes a proven path to maximizing revenue collection using modern tools and techniques,

More information

OMB A What Are The Goals Of The Government In Using Voluntary Consensus Standards?

OMB A What Are The Goals Of The Government In Using Voluntary Consensus Standards? Sally Katzen, Administrator, Office of Information and Regulatory Affairs. EXECUTIVE OFFICE OF THE PRESIDENT Office of Management and Budget Washington, D.C. 20503 February 10, 1998. Circular No. A 119

More information

DRAFT FOR PUBLIC COMMENT Guidance Note for ESS10 Stakeholder Engagement and Information Disclosure

DRAFT FOR PUBLIC COMMENT Guidance Note for ESS10 Stakeholder Engagement and Information Disclosure The Guidance Notes provide guidance for the Borrower on the application of the Environmental and Social Standards (ESSs), which form part of the World Bank s 2016 Environmental and Social Framework. The

More information

Comments to be received by 31 January 2008

Comments to be received by 31 January 2008 29 October 2007 To: Members of the Hong Kong Institute of CPAs All other interested parties HKICPA DISCUSSION PAPER EXPOSURE DRAFT ASSISTANCE OPTIONS TO NEW APPLICANTS AND SPONSORS IN CONNECTION WITH INTERNAL

More information

Economic Stimulus and NEPA Compliance

Economic Stimulus and NEPA Compliance Economic Stimulus and NEPA Compliance Streamlining the Environmental Review Process Authors: Ron Bass, ICF Jones & Stokes Alan Summerville, ICF International Ken Bogdan, ICF Jones & Stokes Michael Smith,

More information

Army DCIPS Performance Evaluation Administrative Reconsideration Guide

Army DCIPS Performance Evaluation Administrative Reconsideration Guide Army DCIPS Performance Evaluation Administrative Reconsideration Guide Reference DoD Instruction 1400.25-V2011, 14 DCIPS Performance Management, 7 May 16), http://www.dtic.mil/whs/directives/corres/pdf/1400.25-v2011.pdf.

More information

Chapter 2 Table of Contents 2.1 PROJECT DEVELOPMENT PROCESS

Chapter 2 Table of Contents 2.1 PROJECT DEVELOPMENT PROCESS Chapter 2 Table of Contents Section Page 2.1 PROJECT DEVELOPMENT PROCESS... 2.2 Activity No. 1: Planning... 2.2 Activity No. 2: Identification of Appropriate Level of NEPA Compliance....2.2 Activity No.

More information

Request for Proposals (RFP) Information Technology Independent Verification and Validation RFP No IVV-B ADDENDUM NO.

Request for Proposals (RFP) Information Technology Independent Verification and Validation RFP No IVV-B ADDENDUM NO. Request for Proposals (RFP) Information Technology Independent Verification and Validation ADDENDUM NO. 2 Questions and Answers RFP Amendments September 2015 Contained herein are the responses to the questions

More information

AUDIT UNDP GLOBAL SHARED SERVICE CENTRE MALAYSIA. Report No Issue Date: 21 March 2014

AUDIT UNDP GLOBAL SHARED SERVICE CENTRE MALAYSIA. Report No Issue Date: 21 March 2014 UNITED NATIONS DEVELOPMENT PROGRAMME AUDIT OF UNDP GLOBAL SHARED SERVICE CENTRE IN MALAYSIA Report No. 1242 Issue Date: 21 March 2014 Table of Contents Executive Summary i I. About the Centre 1 II. Audit

More information

IAASB Main Agenda (December 2008) Page Agenda Item

IAASB Main Agenda (December 2008) Page Agenda Item IAASB Main Agenda (December 2008) Page 2008 2669 Agenda Item 2-C PROPOSED INTERNATIONAL STANDARD ON AUDITING 265 COMMUNICATING DEFICIENCIES IN INTERNAL CONTROL (Effective for audits of financial statements

More information

Quality Control Review of Air Force Audit Agency s Special Access Program Audits (Report No. D )

Quality Control Review of Air Force Audit Agency s Special Access Program Audits (Report No. D ) August 26, 2005 Oversight Review Quality Control Review of Air Force Audit Agency s Special Access Program Audits (Report No. D-2005-6-009) Department of Defense Office of the Inspector General Quality

More information

September 5, 2005 Operating Procedures for The Relicensing of the Saluda Hydroelectric Project FERC Projects 516

September 5, 2005 Operating Procedures for The Relicensing of the Saluda Hydroelectric Project FERC Projects 516 September 5, 2005 Operating Procedures for The Relicensing of the Saluda Hydroelectric Project FERC Projects 516 The following Team Operating Procedures (OPs) are intended to facilitate communications

More information

STEVEN HALL & PARTNERS

STEVEN HALL & PARTNERS STEVEN HALL & PARTNERS E X E C U T I V E C O M P E N S A T I O N C O N S U L T A N T S 212-488-5400 www.shallpartners.com shp@shallpartners.com ABOUT US Steven Hall & Partners ( SH&P ) is an independent

More information

Responding to RFPs. Slide 1 Responding to RFIs and RFPs Welcome this module on responding to RFIs and RFPs.

Responding to RFPs. Slide 1 Responding to RFIs and RFPs Welcome this module on responding to RFIs and RFPs. Slide 1 Responding to RFIs and RFPs Welcome this module on responding to RFIs and RFPs. Slide 2 In this module Companies today are spending more time planning and conducting a comprehensive screening process

More information

AUDIT UNDP COUNTRY OFFICE JAMAICA. Report No Issue Date: 24 April 2015

AUDIT UNDP COUNTRY OFFICE JAMAICA. Report No Issue Date: 24 April 2015 UNITED NATIONS DEVELOPMENT PROGRAMME AUDIT OF UNDP COUNTRY OFFICE IN JAMAICA Report No. 1430 Issue Date: 24 April 2015 Table of Contents Executive Summary i I. About the Office 1 II. Good practices 1 III.

More information

INTERNAL AUDIT DIVISION REPORT 2017/134

INTERNAL AUDIT DIVISION REPORT 2017/134 INTERNAL AUDIT DIVISION REPORT 2017/134 Audit of the management of the Junior Professional Officers programme in the Department of Economic and Social Affairs The mandate of the Junior Professional Officers

More information

Audit of Procurement Practices

Audit of Procurement Practices Unclassified Internal Audit Services Branch Audit of Procurement Practices February 2014 SP-608-03-14E You can download this publication by going online: http://www12.hrsdc.gc.ca This document is available

More information

SRI LANKA AUDITING STANDARD 300 PLANNING AN AUDIT OF FINANCIAL STATEMENTS CONTENTS

SRI LANKA AUDITING STANDARD 300 PLANNING AN AUDIT OF FINANCIAL STATEMENTS CONTENTS SRI LANKA AUDITING STANDARD 300 PLANNING AN AUDIT OF FINANCIAL STATEMENTS (Effective for all the audits carried out on or after ) CONTENTS Paragraph Introduction 1-5 Preliminary Engagement Activities 6-7

More information

Guidance Note: Corporate Governance - Audit Committee. March Ce document est aussi disponible en français.

Guidance Note: Corporate Governance - Audit Committee. March Ce document est aussi disponible en français. Guidance Note: Corporate Governance - Audit Committee March 2015 Ce document est aussi disponible en français. Applicability The Guidance Note: Corporate Governance Audit Committee (the Guidance Note )

More information

Fundamental Principles for Smoothing the NEPA Process

Fundamental Principles for Smoothing the NEPA Process Fundamental Principles for Smoothing the NEPA Process By Alan Summerville NEPA Background The National Environmental Policy Act (NEPA) was established in 1970 to ensure that federal agencies assess the

More information