Hydrologic and Ecologic Impacts from the CERP Indian River Lagoon South Project

Size: px
Start display at page:

Download "Hydrologic and Ecologic Impacts from the CERP Indian River Lagoon South Project"

Transcription

1 Hydrologic and Ecologic Impacts from the CERP Indian River Lagoon South Project Dr. Gretchen Ehlinger Senior Biologist US Army Corps of Engineers Jacksonville District November 15, 2016 AWRA Conference

2 Presentation Outline Indian River Lagoon South (IRL-S) Purpose and Status Plan Components C-44 Description REstoration, COordination and VERification (RECOVER) System-wide Science Monitoring and Assessment Performance Measures Adaptive Management 2

3 Indian River Lagoon and St. Lucie Estuary Productive Estuaries Home to more than 4,300 species of plants and animals Supports an annual economic contribution of more than $730 million Threatened Estuaries Altered water flow patterns Excessive rains require additional floodwater releases to the estuary from Lake Okeechobee Large volumes of stormwater runoff Altered salinity levels Impacts to the estuarine ecosystem Degraded water quality Stormwater runoff and Lake Okeechobee releases Pollutants enter the estuaries 3

4 St. Lucie Estuary Salinity 4

5 IRL-S Project Purpose Improve habitat quality in estuarine ecosystems Improve functional quality of wetland ecosystems Maintain or improve water supply for urban and agricultural use Maintain a healthy ecosystem that supports recreational and commercial interests Improve water quality Maintain existing level of flood control 5

6 IRL-S Project

7 IRL-S Phases Phase 1 Components C-44 Reservoir and Stormwater Treatment Area C-23/24 North Reservoir C-23/24 South Reservoir C-23/24 Stormwater Treatment Area C-25 Reservoir and Stormwater Treatment Area Phase 2 Components Palmar Complex Natural Storage and Water Quality Area Allapattah Complex Natural Storage and Water Quality Area Cypress Creek / Trail Ridge Complex Natural Storage and Water Quality Area Northfork Natural Floodplain Restoration Muck Removal and Artificial Habitat Average annual habitat units 53,683 - Wetlands and Uplands; 4,053 - Riverine and Estuarine; 2,438 Floodplain 7

8 Four large reservoirs and stormwater treatment areas 130,000 acre-ft of new storage in about 13,000 acres of new reservoirs 35,000 acre-ft of new storage in about 8,800 acres of STAs > 200 metric tons of nutrients load reduction per year Phase 1 Benefits 8

9 Phase 2 Benefits Natural Storage and Treatment Areas 90,000 acres of wetlands 30,000 acre-ft of new water > 400 metric tons of nutrient loads reduction Muck Remediation for Artificial Habitat 7.9 million of cubic yards of muck 1,300 acres restored for oysters and aquatic vegetation to re-colonize Flood Plain Restoration Enhanced Water Management 9

10 C-44 Reservoir & Stormwater Treatment Area (RSTA) 3,400 acre reservoir water depth of 15 feet 50,600 acre-feet of storage 6,300 acre STA with emergent vegetation 1,100 cubic feet per second (cfs) capacity Pump station located four miles north of the C-44 Canal STATUS C-44 Reservoir under construction Construction scheduled to be completed in 2020 Up to two years of operational testing will follow construction completion SFWMD will operate facility for one year 10

11 REstoration, COordination and VERification (RECOVER) Why RECOVER? Science Behind CERP Planning (System-wide) Evaluation Assessment Communicates and coordinates the results of these evaluations and assessments Scientific support for decision-making Science will be the foundation of restoration Programmatic Regulations 11

12 The Science Behind CERP Science Framework The Monitoring and Assessment Plan (MAP) Organized around Conceptual Ecological Models (CEM s) Indicator Species Hypothesis Clusters Performance Measures Adaptive Management Feedback Loop Plan Projects Implement Projects Inform and Adapt 12

13 St. Lucie Key Indicators Flow/Salinity Water Quality Oysters Submerged Aquatic Vegetation Benthic Infauna

14 Oyster Hypothesis Cluster Driver Stressor Ecological Effect Attribute 14

15 Oyster Performance Measure Substrate Suitability Nutrient Reductions Flow/Salinity Envelope Oyster Distribution, Quantity and Health 3.5 IRL-S Implementation Adaptive Management Entry Points Monitoring designed to assess the predictions or success of implementation over time Acres Live Beds Time 15

16 St. Lucie - CERP Program vs. Project Performance Performance Measure Target Current IRL-S CEPP CERP >2000 cfs High Flow 0 months 174 months 157 months 121 months Oysters per acre , , , Months 16

17 CERP Adaptive Management Prioritized Key Questions Related to CERP Implementation AM Strategies to Address Key Questions Management Options Matrices that Link RECOVER Monitoring to Current and Future CERP Projects 17

18 Key Questions and AM Strategies St. Lucie Estuary 1. Understand Water Quantity and Quality (Nutrients and Suspended Solids) effects on oyster larvae transport and recruitment Adaptive Management Strategies Oyster Performance measure Develop Particle Transport Model to inform placement of oyster cultch Monitoring and synthesis to understand water quality synergistic effects with salinity on oyster recruitment 18

19 Oyster Management Option Matrix Stressor/Attribute Metric Target Mgmt Action 1 Salinity 5-30 psu Change operations to meet flow requirements Substrate Water Quality Sedimentation Acres of suitable habitat Decrease TSS If salinity range is met, add concrete rubble Adjust flows to minimize sediment transport Mgmt Action 2 Add oyster cultch Reduce sediments loads from the watershed Mgmt Action 3 Dredge muck 19

20 Questions?

St. Lucie Estuary/ Southern Indian River Lagoon Water Resource Summary

St. Lucie Estuary/ Southern Indian River Lagoon Water Resource Summary St. Lucie Estuary/ Southern Indian River Lagoon Water Resource Summary Kathy LaMartina Regional Representative, Martin/St. Lucie Counties South Florida Water Management District Water Resource Modifications

More information

Prepared by The Florida Senate Committee on Environmental Preservation and Conservation

Prepared by The Florida Senate Committee on Environmental Preservation and Conservation Prepared by The Florida Senate Committee on Environmental Preservation and Conservation What causes algae blooms cyanobacteria or blue-green algae is naturally occurring freshwater algae that can grow

More information

CERP System Status Reports The Evolution from

CERP System Status Reports The Evolution from CERP System Status Reports The Evolution from 2006-2009 Eliza Hines 22 July 2009 Everglades Restoration Comprehensive Everglades Restoration Plan (CERP) 18,000 sq mile ecosystem Everglades & South Florida

More information

Everglades Restoration Update. Melissa Meeker, Executive Director

Everglades Restoration Update. Melissa Meeker, Executive Director Everglades Restoration Update Melissa Meeker, Executive Director Treasure Coast Regional Planning Council September 21, 2012 The Challenge: Reevaluating Water Flows 3 The Solution: Three-Part Strategy

More information

Everglades Restoration Definitions

Everglades Restoration Definitions Everglades Restoration Definitions - CERP - CEPP - C-44, C-43 - EAA - IRL South - Plan 6 - SLE - STA - Water Farming - WCA - WRDA Pre-drainage Flow Present Flow Restored Flow Source: The National Academies

More information

PLANNING PROJECT (CEPP)

PLANNING PROJECT (CEPP) COMPREHENSIVE EVERGLADES RESTORATION PLAN CENTRAL PRESENTATION EVERGLADES TITLE PLANNING PROJECT (CEPP) AWRA Conference 2016 Presented by: Kim Taplin, Program Manager Jacksonville District US Army Corps

More information

W t a er Q l ua it lit y

W t a er Q l ua it lit y Wt Water Quality SKG report content Regulatory related issues Phosphorus criterion Active lawsuits and resulting WQ actions Numerous approaches for studying Surface water chemistry Soil nutrient conditions

More information

Everglades Restoration. Ernie Barnett Assistant Executive Director

Everglades Restoration. Ernie Barnett Assistant Executive Director Everglades Restoration Ernie Barnett Assistant Executive Director Lake Worth Lagoon Symposium 2013 S O U T H F L O R I D A W A T E R M A N A G E M E N T D I S T R I C T Planning Everglades Restoration

More information

LAKE OKEECHOBEE WATERSHED RESTORATION

LAKE OKEECHOBEE WATERSHED RESTORATION LAKE OKEECHOBEE WATERSHED RESTORATION INTEGRATED PROJECT IMPLEMENTATION REPORT & ENVIRONMENTAL IMPACT STATEMENT Initial Array of Alternatives Overview October 25, 2016 Trusted Partners Delivering Value

More information

Stevenson Creek Watershed Plan and Project Implementation

Stevenson Creek Watershed Plan and Project Implementation Stevenson Creek Watershed Plan and Project Implementation 1999-2007 Stevenson Creek Watershed Management Plan (WMP) Project Site The Watershed Management Plan was completed in 2001 with cooperative funding

More information

Roland Ottolini, P.E. Director, Natural Resources Division. Presented to the Lee County Tourist Development Council. May 11, 2017

Roland Ottolini, P.E. Director, Natural Resources Division. Presented to the Lee County Tourist Development Council. May 11, 2017 Roland Ottolini, P.E. Director, Natural Resources Division Presented to the Lee County Tourist Development Council May 11, 2017 1 Presentation Overview Regional Water Management Caloosahatchee Issues Lee

More information

Crisis at the Indian River Lagoon and Everglades Planning An Ongoing Crisis, An Emerging Solution August 28, 2013

Crisis at the Indian River Lagoon and Everglades Planning An Ongoing Crisis, An Emerging Solution August 28, 2013 1 Crisis at the Indian River Lagoon and Everglades Planning An Ongoing Crisis, An Emerging Solution August 28, 2013 Audio Options TO USE YOUR COMPUTER'S AUDIO: When the Webinar begins, you will be connected

More information

Stormwater Treatment Areas & Everglades Restoration. 3 rd University of Florida Water Institute Symposium

Stormwater Treatment Areas & Everglades Restoration. 3 rd University of Florida Water Institute Symposium Stormwater Treatment Areas & Everglades Restoration 3 rd University of Florida Water Institute Symposium February 15, 2012 Jennifer Leeds, PMP Senior Project Manager Office of Everglades Policy and Coordination

More information

Joyce Zhang. Lake Okeechobee Watershed Tributary Nutrient Loading Trends WY2006-WY2015. Principal Engineer Applied Sciences Bureau

Joyce Zhang. Lake Okeechobee Watershed Tributary Nutrient Loading Trends WY2006-WY2015. Principal Engineer Applied Sciences Bureau Lake Okeechobee Watershed Tributary Nutrient Loading Trends WY2006-WY2015 Joyce Zhang Principal Engineer Applied Sciences Bureau 2016 AWRA Annual Conference November 13-17, 2016 Lake Okeechobee Watershed

More information

CENTRAL PROJECT PLANNING. Draft PIR and EIS EVERGLADES CENTRAL EVERGLADES RESTORING THE HEART OF THE EVERGLADES. TSP Project Overview

CENTRAL PROJECT PLANNING. Draft PIR and EIS EVERGLADES CENTRAL EVERGLADES RESTORING THE HEART OF THE EVERGLADES. TSP Project Overview CENTRAL EVERGLADES PLANNING PROJECT Draft PIR and EIS TSP Project Overview PRESENTED BY Kim Taplin Planning and Policy Division U.S. Army Corps of Engineers Jacksonville District September 16-19 & 25,

More information

CITY OF SANIBEL, FLORIDA

CITY OF SANIBEL, FLORIDA CITY OF SANIBEL, FLORIDA 2018 WATER QUALITY PRIORITIES Introduction Ongoing water quality issues associated with freshwater discharges from Lake Okeechobee and stormwater runoff from the Caloosahatchee

More information

Indian River Lagoon Council

Indian River Lagoon Council Indian River Lagoon Council August 2016 Indian River Lagoon Stormwater Capture and Treatment Project Development and Feasibility Study SJRWMD RF #28450 Project Overview Identify and Evaluate Stormwater

More information

Adventures in Ecosystem Restoration Everglades Case Study

Adventures in Ecosystem Restoration Everglades Case Study Adventures in Ecosystem Restoration Everglades Case Study Andrew LoSchiavo U.S. Army Corps of Engineers Background Restoration Problem Nutrient Implications Timeline Solutions, Progress, and Challenges

More information

C-111 Spreader Canal Project: A Unique Example of Public Involvement and Adaptive Management in Everglades Restoration

C-111 Spreader Canal Project: A Unique Example of Public Involvement and Adaptive Management in Everglades Restoration C-111 Spreader Canal Project: A Unique Example of Public Involvement and Adaptive Management in Everglades Restoration INTERCOL 9 June 7, 2012 Kenneth G. Ammon, P.E. Senior Vice President Overview South

More information

SUSTAINABILITY OF LONG-TERM MONITORING FOR LARGE SCALE ECOSYSTEM RESTORATION

SUSTAINABILITY OF LONG-TERM MONITORING FOR LARGE SCALE ECOSYSTEM RESTORATION SUSTAINABILITY OF LONG-TERM MONITORING FOR LARGE SCALE ECOSYSTEM RESTORATION Gretchen Ehlinger, Eliza Hines, Tom St. Clair, and Dave Tipple INTECOL June 6, 2012 Long-term System-wide Monitoring Critical

More information

Options for Reducing Harmful Lake Okeechobee Discharges and Everglades Restoration

Options for Reducing Harmful Lake Okeechobee Discharges and Everglades Restoration Options for Reducing Harmful Lake Okeechobee Discharges and Everglades Restoration The Florida Senate Appropriations Subcommittee on the Environment and Natural Resources January 11, 2017 Gary Goforth,

More information

12 YEARS OF EVERGLADES RESTORATION

12 YEARS OF EVERGLADES RESTORATION 12 YEARS OF EVERGLADES RESTORATION Idealism, Realism, War, Elections, Recession and Reform Where are We Going Now? Presented by Barbara Cintron Planning Division, Jacksonville District U.S. Army Corps

More information

Charlotte Harbor SWIM Plan Update Proposed Quantifiable Objectives and Management Actions, January 2019

Charlotte Harbor SWIM Plan Update Proposed Quantifiable Objectives and Management Actions, January 2019 Management Actions One of the goals of this SWIM plan is to identify strategic initiatives that will address the major issues and drivers and provide management actions that will improve and maintain the

More information

Jessica Weatherby, P.E. Project Manager USACE Jacksonville District. Jason Aberdeen Senior Project Manager Parsons. 02 Aug 11 NCER Baltimore

Jessica Weatherby, P.E. Project Manager USACE Jacksonville District. Jason Aberdeen Senior Project Manager Parsons. 02 Aug 11 NCER Baltimore Challenges of Large Scale Ecosystem Restoration Construction in the Current Economic Climate INTERAGENCY & INTERNATIONAL SERVICES REGULATORY ECOSYSTEM RESTORATION NAVIGATION FLOOD DAMAGE REDUCTION COASTAL

More information

Thank you for your comment. We understand the MOU and will coordinate as required.

Thank you for your comment. We understand the MOU and will coordinate as required. A NEPA scoping letter dated June 28, 2016 was mailed to stakeholders soliciting comments for this action. The scoping letter was used to invite comments from Federal, State, and local agencies, affected

More information

2016 Lake Worth Lagoon CAP 1135 Benthic Macroinvertebrate Study. Preliminary Results

2016 Lake Worth Lagoon CAP 1135 Benthic Macroinvertebrate Study. Preliminary Results 2016 Lake Worth Lagoon CAP 1135 Benthic Macroinvertebrate Study Preliminary Results Study Objectives Section 1135 of the Water Resources Development Act of 1986 - U.S. Army Corps of Engineers may plan,

More information

Stormwater Treatment Areas For Improving Water Quality in the Everglades

Stormwater Treatment Areas For Improving Water Quality in the Everglades Stormwater Treatment Areas For Improving Water Quality in the Everglades David Goldstein and Alan L. Wright, Everglades Research & Education Center, Belle Glade, FL Introduction Water quality in the Everglades

More information

Everglades Restoration. Incremental Analysis and Justification of a Comprehensive Plan

Everglades Restoration. Incremental Analysis and Justification of a Comprehensive Plan Everglades Restoration Incremental Analysis and Justification of a Comprehensive Plan Analytical and Policy Issues Lessons Learned Recommendations Eric Bush, USACE, Jacksonville District Eric.L.Bush@usace.army.mil

More information

Hydrology & Hydraulics Bureau and Interagency Modeling Center

Hydrology & Hydraulics Bureau and Interagency Modeling Center Hydrology & Hydraulics Bureau and Interagency Modeling Center Regional Simulation Model Basins (RSMBN) Lake Okeechobee Watershed Project Future Without Project Baseline (FWOP) Table of Assumptions Climate

More information

River of Grass Saving the Everglades: Management and Restoration

River of Grass Saving the Everglades: Management and Restoration River of Grass Saving the Everglades: Management and Restoration K. R. Reddy and R G. Best Wetland Biogeochemistry Laboratory Soil and Water Science Department University of Florida and U. S. Geological

More information

Ocklawaha River Restoration as Mitigation

Ocklawaha River Restoration as Mitigation Ocklawaha River Restoration as Mitigation Dredging Will Further Harm the St. Johns Salinity = Farther Upstream Impacting Wetlands Damaging Submerged Grasses Further Stressing Trees Altering Dissolved Oxygen

More information

Tampa Port Authority

Tampa Port Authority McKay Bay Restoration (McKay Bay Mitigation Site and McKay Bay Dredge Hole Restoration) Tampa Port Authority 2014 AAPA Environmental Awards Competition June 2014 Contact: Andy Fobes, Director of Public

More information

The State of Everglades Restoration

The State of Everglades Restoration FCE-LTER All Scientist Meeting The State of Everglades Restoration Fred H. Sklar 14 March 2016 Deering Estate Restoration Update Outline 1. Reservoirs, STAs & FEBs 2. Broward WPA s 3. DPM 4. MFL & Seagrass

More information

Gulf of Mexico Oyster Restoration

Gulf of Mexico Oyster Restoration Gulf of Mexico Oyster Restoration Deepwater Horizon Oyster Restoration Strategy- Laurie Rounds, NOAA Oyster Integrated Monitoring and Mapping Program Workshop St. Augustine, Florida February 24, 2017 TOPICS

More information

Roland Ottolini, P.E. Director, Natural Resources Division. Lee County Board of County Commissioners March 15, 2016

Roland Ottolini, P.E. Director, Natural Resources Division. Lee County Board of County Commissioners March 15, 2016 Roland Ottolini, P.E. Director, Natural Resources Division Lee County Board of County Commissioners March 15, 2016 1 Presentation Overview Lee County Water Quality/Storage Initiatives Regional Initiatives

More information

The Honorable Senator Joe Negron, Chairman Select Committee on Indian River Lagoon and Lake Okeechobee Basin

The Honorable Senator Joe Negron, Chairman Select Committee on Indian River Lagoon and Lake Okeechobee Basin June 6, 2014 The Honorable Senator Joe Negron, Chairman Select Committee on Indian River Lagoon and Lake Okeechobee Basin Subject: Near-term Reductions of Destructive Lake Okeechobee Discharges to the

More information

EVALUATION - SECTION 404 OF THE CLEAN WATER ACT DISCHARGE OF SEDIMENTS FROM OR THROUGH A DAM

EVALUATION - SECTION 404 OF THE CLEAN WATER ACT DISCHARGE OF SEDIMENTS FROM OR THROUGH A DAM EVALUATION - SECTION 404 OF THE CLEAN WATER ACT DISCHARGE OF SEDIMENTS FROM OR THROUGH A DAM U.S. ARMY CORPS OF ENGINEERS, NEW ENGLAND DISTRICT CONCORD, MA PROJECT: Northfield Brook Dam, Naugatuck River

More information

Moving Forward Suggestions for Reducing the Destructive Lake Discharges to the Estuaries

Moving Forward Suggestions for Reducing the Destructive Lake Discharges to the Estuaries Moving Forward Suggestions for Reducing the Destructive Lake Discharges to the Estuaries Gary Goforth April 2014 Moving Forward Commend Corps and District for holding Lessons Learned workshops to identify

More information

Repackaging Is Not As Simple As It Seems: Lessons Learned from the C-44 Project. Brooke Ahrens, PE HDR Engineering, Inc.

Repackaging Is Not As Simple As It Seems: Lessons Learned from the C-44 Project. Brooke Ahrens, PE HDR Engineering, Inc. Repackaging Is Not As Simple As It Seems: Lessons Learned from the C-44 Project Brooke Ahrens, PE HDR Engineering, Inc. Overview Background What is C-44 Project? Project Status Repackaging Process Lessons

More information

Water Management Under Severe Storm Conditions in Central and South Florida

Water Management Under Severe Storm Conditions in Central and South Florida Water Management Under Severe Storm Conditions in Central and South Florida Chandra S. S. Pathak, Ph.D., P.E. Severe Storm Prediction and Global Climate Impact in the Gulf Coast Conference October 29 to

More information

Highlights. Environmental Report SOUTH FLORIDA. Pine Lake, Everglades National Park

Highlights. Environmental Report SOUTH FLORIDA. Pine Lake, Everglades National Park S O U T H F L O R I D A 2016 W A T E R M A N A G E M E N T D I S T R I C T SOUTH FLORIDA Environmental Report Highlights Pine Lake, Everglades National Park With Everglades water cleaner than it has been

More information

Progress Report on SFWMD Implementation of Senate Bill 10 (Section Florida Statutes)

Progress Report on SFWMD Implementation of Senate Bill 10 (Section Florida Statutes) Progress Report on SFWMD Implementation of Senate Bill 10 (Section 373.4598 Florida Statutes) INTRODUCTION Senate Bill 10, approved by the Florida Legislature and signed into law by Governor Rick Scott

More information

wise use of water, wetlands, and watersheds : Everglades restoration using large treatment wetlands

wise use of water, wetlands, and watersheds : Everglades restoration using large treatment wetlands wise use of water, wetlands, and watersheds : Everglades restoration using large treatment wetlands Gary Goforth, P.E., Ph.D. Overview Everglades Restoration Background Stormwater Treatment Areas Design

More information

Webinar for the Natural Floodplain Function Alliance 18 November 2013

Webinar for the Natural Floodplain Function Alliance 18 November 2013 Moving toward Floodplain Restoration at Scale on the Illinois River and Upper Mississippi Basin: Valuing Ecosystem Services, Demonstrating Flood Reduction, and Policy Implications Webinar for the Natural

More information

NEW CLIMATE CHANGE INFORMATION FOR ENHANCING EVERGLADES RESTORATION CLIMATE PREPAREDNESS AND RESILIENCE

NEW CLIMATE CHANGE INFORMATION FOR ENHANCING EVERGLADES RESTORATION CLIMATE PREPAREDNESS AND RESILIENCE NEW CLIMATE CHANGE INFORMATION FOR ENHANCING EVERGLADES RESTORATION CLIMATE PREPAREDNESS AND RESILIENCE Glenn B. Landers, P.E. USACE Jacksonville District GEER Conference, Coral Springs, FL April 19, 2017

More information

CESAJ-PM (Cong) March 2016

CESAJ-PM (Cong) March 2016 CESAJ-PM (Cong) March 2016 FACT SHEET SOUTH FLORIDA ECOSYSTEM RESTORATION (SFER) Overview Congressional Districts: 5, 7, 9, 10, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27 1. DESCRIPTION The Central and

More information

Everglades Restoration Update: Water Quality, Central Everglades and Tamiami Trail Next Steps Project

Everglades Restoration Update: Water Quality, Central Everglades and Tamiami Trail Next Steps Project National Park Service - DOI Everglades Restoration Update: Water Quality, Central Everglades and Tamiami Trail Next Steps Project For the Florida Keys Water Quality Protection Program, February 20, 2013

More information

C-111 West Spreader Canal: An Everglades Restoration Success Story

C-111 West Spreader Canal: An Everglades Restoration Success Story C-111 West Spreader Canal: An Everglades Restoration Success Story National Ecosystem Restoration Conference: July 30, 2013 Tom Teets, Federal Policy Chief, South Florida Water Management District The

More information

Progress on South Florida Estuaries Restoration: C-111 Western Spreader Canal and Biscayne Bay Coastal Wetland CERP Project

Progress on South Florida Estuaries Restoration: C-111 Western Spreader Canal and Biscayne Bay Coastal Wetland CERP Project Progress on South Florida Estuaries Restoration: C-111 Western Spreader Canal and Biscayne Bay Coastal Wetland CERP Project American Water Resources Association 2016 ANNUAL WATER RESOURCES CONFERECNCE

More information

EXECUTIVE SUMMARY DES PLAINES RIVER WATERSHED-BASED PLAN WHY A WATERSHED-BASED PLAN? WHAT IS A WATERSHED?

EXECUTIVE SUMMARY DES PLAINES RIVER WATERSHED-BASED PLAN WHY A WATERSHED-BASED PLAN? WHAT IS A WATERSHED? Des Plaines River Watershed-Based Plan EXECUTIVE SUMMARY June 2018 EXECUTIVE SUMMARY DES PLAINES RIVER WATERSHED-BASED PLAN WHY A WATERSHED-BASED PLAN? Water is elemental to our lives. Plants and animals,

More information

COMPREHENSIVE EVERGLADES RESTORATION PLAN LAKE OKEECHOBEE WATERSHED RESTORATION PROJECT DRAFT INTEGRATED PROJECT IMPLEMENTATION REPORT AND

COMPREHENSIVE EVERGLADES RESTORATION PLAN LAKE OKEECHOBEE WATERSHED RESTORATION PROJECT DRAFT INTEGRATED PROJECT IMPLEMENTATION REPORT AND COMPREHENSIVE EVERGLADES RESTORATION PLAN LAKE OKEECHOBEE WATERSHED RESTORATION PROJECT DRAFT INTEGRATED PROJECT IMPLEMENTATION REPORT AND ENVIRONMENTAL IMPACT STATEMENT July 2018 This page intentionally

More information

Watersheds Functions and Management 1

Watersheds Functions and Management 1 Fact Sheet ABE350 Watersheds Functions and Management 1 S. Shukla 2 What Is a Watershed? The term watershed is often used in discussions about water quality or flood prevention, but most people do not

More information

OCTOBER 2, 2013 WASHINGTON, D.C. 16 COUNTIES ONE VOICE. for South Florida s Ecosystem. 1st Annual Lobby Day. Federal Advocacy Briefing

OCTOBER 2, 2013 WASHINGTON, D.C. 16 COUNTIES ONE VOICE. for South Florida s Ecosystem. 1st Annual Lobby Day. Federal Advocacy Briefing OCTOBER 2, 2013 WASHINGTON, D.C. 16 COUNTIES ONE VOICE for South Florida s Ecosystem 1st Annual Lobby Day Federal Advocacy Briefing 16 County Ecosystem Summit Legislative Priorities federal advocacy briefing

More information

Project Delivery Team Meeting

Project Delivery Team Meeting LOXAHATCHEE RIVER WATERSHED RESTORATION PROJECT Project Delivery Team Meeting December 15, 2014 One of the Last Old Growth Cypress Floodplains in the SE Florida Last Large Freshwater Wetland Corridor in

More information

APPENDIX G BENEFIT MODEL

APPENDIX G BENEFIT MODEL APPENDIX G BENEFIT MODEL Appendix G-i This page intentionally left blank Appendix G-ii TABLE OF CONTENTS APPENDIX G... G-i G... G-1 G.1 Model Documentation... G-1 G.1.1 Description of the CEPP Planning

More information

Scoping Level Evaluation of Everglades Water Quality Compliance Using a Central Flow Way Hydrated With Lake Okeechobee Water

Scoping Level Evaluation of Everglades Water Quality Compliance Using a Central Flow Way Hydrated With Lake Okeechobee Water Scoping Level Evaluation of Everglades Water Quality Compliance Using a Central Flow Way Hydrated With Lake Okeechobee Water by Larry E. Fink, M.S. Waterwise Consulting, LLC 04/22/15 W WC Need Introduction

More information

C-111 SPREADER CANAL Western Project and Design Test

C-111 SPREADER CANAL Western Project and Design Test C-111 SPREADER CANAL Western Project and Design Test Integration of Science and Engineering into Innovative Ecosystem Restoration Concepts National Conference on Ecosystem Restoration August 2011 Ray Wimbrough

More information

Economic Analysis of Water Treatments for Phosphorus Removal in Florida 1

Economic Analysis of Water Treatments for Phosphorus Removal in Florida 1 FE576 Economic Analysis of Water Treatments for Phosphorus Removal in Florida 1 Daisuke Sano, Alan Hodges, and Robert Degner 2 Abstract Excessive phosphorus loads in urban and agricultural runoff are identified

More information

4. Present Activities and Roles

4. Present Activities and Roles 4. Present Activities and Roles The present missions, authorities, activities and roles of the various agencies involved with flood protection, floodplain management and flood-damage reduction are identified

More information

A Study to Estimate Current and Future CSOs to Bubbly Creek and Identify Impacts on the Chicago Area Waterways (CAWS)

A Study to Estimate Current and Future CSOs to Bubbly Creek and Identify Impacts on the Chicago Area Waterways (CAWS) A Study to Estimate Current and Future CSOs to Bubbly Creek and Identify Impacts on the Chicago Area Waterways (CAWS) IWEA WATERCON 2012 Springfield, Illinois March 19, 2012 presented by David Kiel, USACE

More information

Performance Measures and Habitat Units

Performance Measures and Habitat Units Performance Measures and Habitat Units Andrew LoSchiavo, U.S. Army Corps of Engineers One of the Last Old Growth Cypress Floodplains in the SE Florida Last Large Freshwater Wetland Corridor in Project

More information

EXECUTIVE SUMMARY. Assessing Pre-CERP Conditions by MAP Module

EXECUTIVE SUMMARY. Assessing Pre-CERP Conditions by MAP Module EXECUTIVE SUMMARY The 2007 Assessment Team (AT) System Status Report (SSR) provides an in-depth assessment of the monitoring data provided by: (1) the Restoration Coordination and Verification (RECOVER)

More information

COTTONWOOD CREEK RECLAMATION PHASE I & II

COTTONWOOD CREEK RECLAMATION PHASE I & II COTTONWOOD CREEK RECLAMATION PHASE I & II COTTONWOOD CREEK RECLAMATION Stream Stabilization Approach to Urban Runoff Quality Cherry Creek Basin Water Quality Authority The Problem The Cherry Creek Reservoir

More information

APPENDIX E SECTION 404 (B) (1) EVALUATION OF DREDGE AND FILL MATERIAL

APPENDIX E SECTION 404 (B) (1) EVALUATION OF DREDGE AND FILL MATERIAL APPENDIX E SECTION 404 (B) (1) EVALUATION OF DREDGE AND FILL MATERIAL SECTION 404 (B) (1) EVALUATION FOR AUGUSTA ROCKY CREEK SECTION 205 FEASIBILITY STUDY, RICHMOND COUNTY, GEORGIA FEBRUARY 2016 TABLE

More information

SHORELINE INVENTORY AND RESTORATION PLANNING

SHORELINE INVENTORY AND RESTORATION PLANNING CHAPTER 3 SHORELINE INVENTORY AND RESTORATION PLANNING A. PURPOSE OF THE SHORELINE INVENTORY AND CHARACTERIZATION A first step in the comprehensive Master Program update process is development of a shoreline

More information

For the Love of Florida: The North Fork of the St. Lucie River

For the Love of Florida: The North Fork of the St. Lucie River For the Love of Florida: The North Fork of the St. Lucie River February 13, 2019 Gary Goforth, P.E., Ph.D. Disclaimer: Disclaimer: Opinions Opinions expressed expressed are are those those of of the the

More information

1999 Base Line Report for the Comprehensive Everglades Restoration Plan. Table of Contents. Introduction... 1

1999 Base Line Report for the Comprehensive Everglades Restoration Plan. Table of Contents. Introduction... 1 Table of Contents Introduction... 1 1. Lake Okeechobee Phosphorus Levels... 4 2. St. Lucie Estuary Oyster Beds... 6 3. St. Lucie Estuary Phosphorus Levels... 8 4. Lake Okeechobee and East Coast Water Supply

More information

APPENDIX I CENTRAL EVERGLADES PLANNING PROCESS ISSUE RESOLUTION

APPENDIX I CENTRAL EVERGLADES PLANNING PROCESS ISSUE RESOLUTION APPENDIX I PLANNING PROCESS ISSUE RESOLUTION This page intentionally left blank Central Everglades Planning Project EAA Formulation Issue Resolution Conference July 20, 2012 MEETING PURPOSE Issue Resolution

More information

Roland Ottolini, PE Director, Lee County Division of Natural Resources 09/11/2018

Roland Ottolini, PE Director, Lee County Division of Natural Resources 09/11/2018 Roland Ottolini, PE Director, Lee County Division of Natural Resources 09/11/2018 1 What is a watershed? What is the State of Lee County s Watersheds? Defined by recent extreme events? Flooding 2017 Harmful

More information

Comprehensive Everglades Restoration Project. U.S. Army Corps of Engineers South Florida Water Management District Other Agencies and NGOs

Comprehensive Everglades Restoration Project. U.S. Army Corps of Engineers South Florida Water Management District Other Agencies and NGOs Comprehensive Everglades Restoration Project U.S. Army Corps of Engineers South Florida Water Management District Other Agencies and NGOs Everglades Restoration Overview Past, Present, and Future South

More information

GROVE LAND UTILITIES, LLC

GROVE LAND UTILITIES, LLC GROVE LAND UTILITIES, LLC Financial Feasibility Study of the Grove Land Reservoir and Stormwater Treatment Area, Phase 2 Study FINAL Report Photo courtesy of the St. Lucie County Media Relations and St.

More information

Ecosystem Restoration and Management in Biscayne National Park

Ecosystem Restoration and Management in Biscayne National Park Ecosystem Restoration and Management in Biscayne National Park Brian Carlstrom, Biscayne National Park, National Park Service Homestead, FL. Greater Everglades Ecosystem Restoration Conference April 21-23,

More information

Ecosystem Management

Ecosystem Management Ecosystem Management General Goals Ecosystem management integrates scientific knowledge of ecological relationships within a complex sociopolitical and values framework toward the general goal of protecting

More information

Natural & Cultural Resources

Natural & Cultural Resources II. Natural & Cultural Resources Hydrology/Water Management The North Thousand Islands is located within the Banana River and within the Indian River Lagoon system. Significant waterbodies within the region

More information

LAKE OKEECHOBEE WATERSHED RESTORATION

LAKE OKEECHOBEE WATERSHED RESTORATION COMPREHENSIVE EVERGLADES RESTORATION PLAN LAKE OKEECHOBEE WATERSHED RESTORATION INTEGRATED PROJECT IMPLEMENTATION REPORT & ENVIRONMENTAL IMPACT STATEMENT 17-May-2017 Trusted Partners Delivering Value Today

More information

TOWN OF JUPITER. David L. Brown, Director of Utilities

TOWN OF JUPITER. David L. Brown, Director of Utilities DATE: October 18, 2016 TOWN OF JUPITER TO: THRU: FROM: Honorable Mayor and Members of the Jupiter Town Council Andy D. Lukasik, Town Manager David L. Brown, Director of Utilities SUBJECT: Resolution No.

More information

Everglades Restoration Using Large-Scale Treatment Wetlands on Former Agricultural Lands

Everglades Restoration Using Large-Scale Treatment Wetlands on Former Agricultural Lands Everglades Restoration Using Large-Scale Treatment Wetlands on Former Agricultural Lands Gary Goforth, P.E., Ph.D. Overview Everglades Restoration Background Stormwater Treatment Areas Land Acquisition

More information

CHAPTER 2 ALTERNATIVES

CHAPTER 2 ALTERNATIVES CHAPTER 2 ALTERNATIVES This page intentionally left blank. 2.0 ALTERNATIVES This chapter outlines the process used to determine the range of reasonable alternatives to the proposed action and presents

More information

Little River Watershed Restoration Project. Mark Powell, Consultant Natural Resources Management

Little River Watershed Restoration Project. Mark Powell, Consultant Natural Resources Management Little River Watershed Restoration Project Mark Powell, Consultant Natural Resources Management Lessons Learned Strong partnerships RC&D, Soil and Water, 2 counties, Albemarle Commission, Universities,

More information

NATIONAL FISH AND WILDLIFE FOUNDATION (NFWF) PHASE II

NATIONAL FISH AND WILDLIFE FOUNDATION (NFWF) PHASE II This suite of projects will reduce sediment and nutrient loading to Bayou Chico, reduce turbidity, increase water clarity, and improve light penetration for photosynthesis to enable expansion of submerged

More information

Meacham Creek Fish Habitat Enhancement: Application of the CTUIR River Vision

Meacham Creek Fish Habitat Enhancement: Application of the CTUIR River Vision Meacham Creek Fish Habitat Enhancement: Application of the CTUIR River Vision Future of Our Salmon A Vision of Restoration in the Columbia River Basin June 1, 2011 James Webster Confederated Tribes of

More information

A multi-tiered monitoring approach to address management-driven research questions

A multi-tiered monitoring approach to address management-driven research questions A multi-tiered monitoring approach to address management-driven research questions Amanda Kahn Dickens, Ph.D. & Christopher Buzzelli, Ph.D. Senior Scientist, Coastal Ecosystem Section Applied Science Bureau

More information

STATE OF WASHINGTON FINAL DECISIONS AND SECTION 401 WATER QUALITY CERTIFICATION CONDITIONS FOR THE CORPS OF ENGINEERS 2017 NATIONWIDE PERMIT PROGRAM

STATE OF WASHINGTON FINAL DECISIONS AND SECTION 401 WATER QUALITY CERTIFICATION CONDITIONS FOR THE CORPS OF ENGINEERS 2017 NATIONWIDE PERMIT PROGRAM STATE OF WASHINGTON FINAL DECISIONS AND SECTION 401 WATER QUALITY CERTIFICATION CONDITIONS FOR THE CORPS OF ENGINEERS 2017 NATIONWIDE PERMIT PROGRAM In addition to all the U.S. Army Corps of Engineers

More information

Calleguas Creek Watershed Wetland Restoration Plan. David L. Magney. David Magney Environmental Consulting

Calleguas Creek Watershed Wetland Restoration Plan. David L. Magney. David Magney Environmental Consulting Calleguas Creek Watershed Wetland Restoration Plan David L. Magney David Magney Environmental Consulting Calleguas Creek Watershed About the Watershed Located in southeastern Ventura County Drains 343

More information

Lake Okeechobee Operations and Blue-Green Algae Update

Lake Okeechobee Operations and Blue-Green Algae Update Lake Okeechobee Operations and Blue-Green Algae Update Lawrence Glenn Section Administrator, Lakes and River Section South Florida Water Management District Palm Beach County WRTF Meeting October 20, 2016

More information

ECOLOGICAL DISTURBANCES IN THE ST. LUCIE ESTUARY AND THE SOUTHERN INDIAN RIVER LAGOON, EASTERN FLORIDA, ELUCIDATED THROUGH MACROBENTHIC MONITORING

ECOLOGICAL DISTURBANCES IN THE ST. LUCIE ESTUARY AND THE SOUTHERN INDIAN RIVER LAGOON, EASTERN FLORIDA, ELUCIDATED THROUGH MACROBENTHIC MONITORING ECOLOGICAL DISTURBANCES IN THE ST. LUCIE ESTUARY AND THE SOUTHERN INDIAN RIVER LAGOON, EASTERN FLORIDA, ELUCIDATED THROUGH MACROBENTHIC MONITORING Bjorn Tunberg Scott Jones, Sherry Reed, Michelle Stephens

More information

the Picayune Strand Restoration Project

the Picayune Strand Restoration Project Picayune Strand Current Status and Future of the Picayune Strand Restoration Project David J. Bauman Biologist Jacksonville District July 14, 2010 Greater Everglades Ecosystem Restoration 2010 US ARMY

More information

Compilation of Benefits and Costs of STA and Reservoir Projects in the South Florida Water Management District

Compilation of Benefits and Costs of STA and Reservoir Projects in the South Florida Water Management District Compilation of Benefits and Costs of STA and Reservoir Projects in the South Florida Water Management District Report Prepared by Hazen and Sawyer For the World Wildlife Fund acting on behalf of the Florida

More information

Everglades Restoration Goals

Everglades Restoration Goals Everglades Restoration Goals Restore natural hydrologic conditions in the remaining 50% of historic Everglades Water quantity, quality, timing and distribution Maintain existing services in developed areas

More information

Municipal Stadium Wetland

Municipal Stadium Wetland W A T E R S H E D F A C T S Total watershed area 140 mi 2 Average annual rainfall 38 in Average annual temperature 58 F Elevation Max 1321 ft Min 899 ft C. J. Brown Reservoir controls flow from 83 mi 2

More information

October 2015 Utilizing a County-Owned Golf Course for Watershed Restoration in Gwinnett County, GA

October 2015 Utilizing a County-Owned Golf Course for Watershed Restoration in Gwinnett County, GA October 2015 Utilizing a County-Owned Golf Course for Watershed Restoration in Gwinnett County, GA Arvind Narayanan, P.E.*, CFM, Water Resources Engineer Overview Project Identification Project Implementation:

More information

DEPARTMENT OF THE ARMY CHIEF OF ENGINEERS 2600 ARMY PENTAGON WASHINGTON, D.C

DEPARTMENT OF THE ARMY CHIEF OF ENGINEERS 2600 ARMY PENTAGON WASHINGTON, D.C DEPARTMENT OF THE ARMY CHIEF OF ENGINEERS 2600 ARMY PENTAGON WASHINGTON, D.C. 20310-2600 DAEN.f 3 DEC 2014 THE SECRETARY OF THE ARMY SUBJECT: Central Everglades Planning Project, Comprehensive Everglades

More information

S.R. 4007, Section 14B PADEP Environmental Assessment Form. Enclosure C Description of Aquatic Habitat

S.R. 4007, Section 14B PADEP Environmental Assessment Form. Enclosure C Description of Aquatic Habitat S.R. 4007, Section 14B PADEP Environmental Assessment Form Description of Aquatic Habitat Cresheim Creek is the only water resource that exists within the project area. No jurisdictional wetlands were

More information

Palm Beach County Board of County Commissioners Workshop October 29, Yongshan Wan, Ph.D. P.E. Section Leader Coastal Ecosystems Section

Palm Beach County Board of County Commissioners Workshop October 29, Yongshan Wan, Ph.D. P.E. Section Leader Coastal Ecosystems Section S O U T H F L O R I D A W A T E R M A N A G E M E N T D I S T R I C T Palm Beach County Board of County Commissioners Workshop October 29, 2013 Yongshan Wan, Ph.D. P.E. Section Leader Coastal Ecosystems

More information

Bill Crowell, PhD, AICP Lindsey Smart, MS. Chesapeake Bay Program Science & Technical Advisory Committee 18 March 2014

Bill Crowell, PhD, AICP Lindsey Smart, MS. Chesapeake Bay Program Science & Technical Advisory Committee 18 March 2014 Bill Crowell, PhD, AICP Lindsey Smart, MS Chesapeake Bay Program Science & Technical Advisory Committee 18 March 2014 1 Albemarle-Pamlico Estuarine System: Nation s Second Largest Estuary Chesapeake Bay

More information

Lake Okeechobee Performance Measure Ecological Indicator Score (Vascular SAV, Chara, panfish, Cyanobacteria, Epiphyton and Epipelon)

Lake Okeechobee Performance Measure Ecological Indicator Score (Vascular SAV, Chara, panfish, Cyanobacteria, Epiphyton and Epipelon) Lake Okeechobee Performance Measure Ecological Indicator Score (Vascular SAV, Chara, panfish, Cyanobacteria, Epiphyton and Epipelon) Last Date Revised: October 20, 2016 Acceptance Status: Accepted 1.0

More information

Land and Water Management Division Programs. Department of Environmental Quality

Land and Water Management Division Programs. Department of Environmental Quality Land and Water Management Division Programs Department of Environmental Quality Land and Water Management Programs Since the mid-1970 s, special resources that exist at the interface between land and water

More information

Water Quality Stewardship Plan (WaQSP)

Water Quality Stewardship Plan (WaQSP) Salt Lake Countywide Water Quality Stewardship Plan (WaQSP) Natalie Rees Salt Lake County Flood Control & Engineering Division 2008 Watershed Symposium COUNTY RESPONSIBILITY AND AUTHORITY Salt Lake County

More information

St. Johns River Water Quality Projects. St. Johns River Water Quality Projects Fiscal Year

St. Johns River Water Quality Projects. St. Johns River Water Quality Projects Fiscal Year St. Johns River Water Quality Projects Fiscal Year 2011 2012 The St. Johns River is an invaluable part of Florida and is central to our quality of life. However, for decades, the river has suffered from

More information

Gulf of Mexico Hydrological Restoration Criteria for Identifying and Prioritizing Projects

Gulf of Mexico Hydrological Restoration Criteria for Identifying and Prioritizing Projects Gulf of Mexico Hydrological Restoration Criteria for Identifying and Prioritizing Projects Definition of hydrological restoration for this Partnership To remove or modify anthropogenic barriers to restore

More information