PRE FEASIBILITY REPORT JOJOBERA CEMENT PLANT

Save this PDF as:
 WORD  PNG  TXT  JPG

Size: px
Start display at page:

Download "PRE FEASIBILITY REPORT JOJOBERA CEMENT PLANT"

Transcription

1 PRE FEASIBILITY REPORT Of JOJOBERA CEMENT PLANT (STAND-ALONE CEMENT GRINDING UNIT) FOR ENVIRONMENTAL CLEARANCE FOR CHANGE IN PRODUCT MIX OF 4.6 MILLION TONNES PER ANNUM CEMENT PRODUCTION (NO INCREASE IN PRODUCTION) AT CEMENT GRINDING UNIT P.O. Rahargora, Jamshedpur (Jharkhand) By 0 Prepared By

2 Table of Contents Executive summary Introduction of the project/ Background information Project Description. Site Analysis Planning Brief. Proposed Infrastructure Rehabilitation and Resettlement (R & R) Plan. Project Schedule & Cost Estimates Analysis of Proposal (Final Recommendations). 1

3 1. EXECUTIVE SUMMARY Lafarge India Limited (LIL) is operating Jojobera Cement Plant (JCP), a State-of-the-art cement grinding unit based on latest and most ecofriendly technology adjacent to Thermal Power plant of Tata Power Station near Jamshedpur. The plant has been set up with the primary objective of utilizing the waste product of Steel manufacturing slag and Fly Ash produced by Tata Power Limited (TPL) which was earlier considered as solid waste. The present production details are; Million Tonnes Per Annum PSC (Max.) Portland Pozzolona (Max.) Cement (PPC)) However the production is limited to 4.6 Million Tonnes per annum The unit is utilizing bulk quantity of Fly Ash generated by Tata Thermal Power Station and the Slag generated from Tata Iron & Steel Co. Ltd. (TISCO) in an eco-friendly manner and thus is instrumental in abating the Pollution in the region in terms of Solid waste utilization approximate 0.35 MTPA of fly-ash and approximate 2.2 MTPA of slag. The required Clinker produced at LIL sister units Sonadih Cement Plant (SCP) and Arasmeta Cement Plant (ACP) is transported to Jamshedpur by Rail, Slag from TISCO, Fly Ash from TPL. The Environmental Clearance for this unit was issued vide letter no J11011/638/2008- IA II (I) on for producing ground cement of 4.6 Million Tonnes per annum(mtpa), with Portland Slag Cement at 3.2 MTPA and Portland Pozzolona Cement (PPC) at 1.4 MTPA. (Annexure-I) Subsequently, to meet the trend in the market, LIL obtained Amendment for Environmental Clearance from Ministry vide letter no. J-11011/638/2008.IA.II(I) dated 16th March, 2016 (Annexure-II ) for the production of Cement mix as given below Million Tonnes Per Annum PSC (Max.) PPC (Max.) However the production is limited to 4.6 Million Tonnes per annum 2

4 Now LIL proposes to produce Composite Cement, which is a blend of ground slag & fly ash cement, in addition to existing product i.e. PPC & PSC, while maintaining the total output at 4.6 Million Tonnes Per Annum. It amounts to increase in cementitious materials consumption with reduction in Clinker consumption. Now, the proposed product mix would be : Million Tonnes Per Annum Present Proposed PSC (Max.) PPC (Max.) Composite Cement (CC) 1.0 (Max.) However the production is limited to 4.6 Million Tonnes per annum Since the overall volume remains same, we don t see any increase in water requirement for the plant, which is about 1050 m3/day. The water is sourced from JUSCO (A subsidiary company of TISCO). There would not be any increase in water consumption. Present contract demand for power requirement is 30 MVA for 4.6 MTPA for PPC and PSC production. No additional power requirement will be there. Hot Air Generators is being used for drying the wet slag in the grinding mill. Presently furnace oil consumption is about 16 KL per day and coal is about 60 MT/per day on yearly average basis, which also remains unchanged. The present strength of manpower is 230. No additional manpower is required. No solid waste generation from the plant. The production and requirements of the project before and after change of product mix are given below: Parameter PSC PPC Present 4.0(Max.) 1.0(Max.) Proposed (change of product mix) 4.0 (Max.) 1.0 (Max.) Remarks No Change No Change 3

5 Parameter Present Proposed (change of product mix) Remarks CC Total, MTPA Clinker, MTPA Gypsum, MTPA Fly Ash, MTPA Slag, MTPA 4.6(Max.) (Max) 4.6(Max) 2.15 Additional No Change No Change No Change Land, Ha Manpower Water, m3/day Acres Acres Increase in consumption Increase in consumption No Change No Change No Change waste waste The present location of the plant is adjacent to premises of TPL. About acres of the area has been leased out to LIL by the TISCO for operating the grinding unit. Green belt in an area of more than 45 Acres has been developed inside the plant boundary as per statutory norms. No additional land is required for change. There is no wild life sanctuary, national park, eco-sensitive area within the 10 km radius of the project site. Existing infrastructure include railway siding and well developed roads, parking area, storm water drains with adequate storage space for clinker and fly ash. All infrastructure facilities such as education, health facilities and other social facilities are available adequately at nearest populated area i.e Jamshedpur. LIL has well-defined CSR policy to Carryout social development and welfare measures in the surrounding villages. Under CSR activity LIL has initiated community development projects, in the fields of health & safety, education and environment infrastructure & employability, in and around the plant. 4

6 2. INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION (I) IDENTIFICATION OF PROJECT AND PROJECT PROPONENT PROJECT Lafarge India Limited is operating Jojobera Cement Plant is a State-ofthe-art cement grinding unit based on latest and most eco-friendly technology adjacent to Tata Thermal Power Station near Jamshedpur. The plant has been set up with the primary objective of utilizing industrial waste of TATA Steel & TATA Power i.e slag & Fly ash resp. and abating the Pollution in the region in terms of Solid waste utilization. The required Clinker produced at LIL sister units Sonadih Cement Plant and Arasmeta Cement Plant is transported to the plant by Rail, Slag from Tata steel by rail & road, Fly ash pneumatically conveyed through closed pipelines and Gypsum by rail, to produce cement. Jojobera Cement Plant is having automated grinding system consists of a ball mills, roller presses and vertical roller mill. PROJECT PROPONENT Lafarge India Limited in its Indian operation is producing cement as well as building materials. Its operation is spread all over the country. By focusing on the development and advancement of building materials, Lafarge places the customer at the core of its strategy and offers the construction industry and the general public innovative solutions that will bring more safety, comfort and beauty to our everyday lives. The Group s expertise in efficient industrial processes generate value, protects the environment, shows respect for societies & cultures and is sparing in its use of natural resources and energy. Lafarge entered the Indian market in 1999, through its cement business, with the acquisition of TISCO s cement business. This acquisition was followed by the purchase of the Raymond Cement facility in Lafarge currently has six cement plants in India: two plants in the state of Chhattisgarh (Sonadih and Arasmeta), One in 5

7 Rajsthan, Grinding Units in Jharkhand (Jojobera) and West Bengal (Mejia) and Blending unit in Jhajjar, Haryana. In recent years, Lafarge has significantly enlarged its operations across its three business divisions - Cement, Aggregates & Concrete. Lafarge s total cement production capacity in the Indian market currently stands at around 11 million tons and Lafarge India has plan to further expand its production capacity in existing operations. In addition to capacity changes at Sonadih and Jojobera, the Company is building on the success of its regional development models and is in the process of starting projects in Karnataka, Meghalaya and Himachal Pradesh. Lafarge has been committed to sustainable development for many years, pursuing a strategy that combines industrial knowhow with performance, value creation, respect for employees and local cultures, environmental protection and the conservation of natural resources and energy. To make advances in building materials, Lafarge places the customer at the heart of its concerns. It offers the construction industry and the general public innovative solutions bringing greater safety, comfort and quality to their everyday surroundings. Safety is the cornerstone of the Company s performance culture and longstanding people-centric tradition. All Lafarge India plants have an innate culture of safety consciousness and assured best-in-class Health & Safety standards. (II) BRIEF DESCRIPTION OF NATURE OF THE PROJECT Presently, Cement production capacity of the plant is 4.6 MTPA with 4.0 Million Ton per Annum, (max) PSC and 1.0 Million Ton per annum (max) of PPC. The required Clinker produced at LIL sister units Sonadih Cement Plant and Arasmeta Cement Plant is transported to Jamshedpur by Rail and Ground along with Slag (after drying) to produce PSC and Fly Ash to produce PPC with addition of gypsum. The proposal is now to produce of about 1.0 MTPA (max) Composite Cement by blending of Ground Slag & blendable PPC keeping the total capacity at the present level of 4.6 MTPA. For making Composite Cement, a blendable PPC bin, weighing scale and blender will be installed and same shall be stored in one of the 6

8 existing cement silos. Ground slag will be used from the existing operation. The details of production capacity with change of product mix is given below S. No in million tons per annum (MTPA) Present capacity Proposed change PSC 3.2 PPC 1.4 Composite Cement Total (Max.) 1.0 (Max.) 1.0(Max) 4.6 (III) NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY AND OR REGION Very purpose of need of project is introduction of new ISS (Indian Standard Specification) for Composite Cement (CC) wherein, Lafarge seeing opportunity for further reduction in CO2 emission & conservation of natural resources by means reducing clinker component which requires Limestone, coal and water thereby reducing Green house gas emission. The most important raw material for these cements are blast furnace slag as a byproduct from the iron making process and fly ash as a byproduct from electricity production in coal fired power plants. These by-products earlier were seen as waste. In the developed technical world, these products were renamed from waste to by-product and are used as raw material in producing the blended cements, namely PSC and PPC. For more utilization of the industrial wastes or by products and also to minimize the Clinker consumption, there by reduction in Power requirement, better utilization of Solid waste, with out compromising on the quality of strength, Bureau of Indian Standards (BIS) has introduced Composite Cement as per IS : 2015 whose mix is about 15% - 35 % Fly ash, 20-50% Slag, more than 35% OPC (Clinker + Gypsum). Overall percentage of Slag and Fly Ash should not exceed 65 % in any case. Based on the concept of waste to by-product, and in view of the demand, LIL now proposes to produce Composite Cement to max. Quantity of 1.0 MTPA in addition to PSC and PPC, keeping total 7

9 production capacity of the plant at 4.6 MTPA for which EC was granted. (IV) DEMAND- SUPPLY GAP Market demand and projections Cement growth is expected to be above the GDP growth of the country, which is expected to be around 8% for the coming years. The Indian cement Industry is poised for a period of significant growth and the demand for cement is expected to match the current availability by the end of the current fiscal. Cement demand has registered a CAGR of about 8.5% over the last decade. In fact, at the current levels of growth, the cement industry may have to add over 90 Million Tons of cement capacity to meet the demand for cement over the next 5 years. Cement companies were operating at levels below capacity in the past but with the demand and supply reaching equilibrium; almost all plants are working at above 90% capacity. The rate of growth in cement demand is growing at a faster pace as compared to the capacity change. This will improve the realizations of the industry in the coming year. (V) IMPORTS Vs INDIGENOUS PRODUCTION India is self sufficient to meet the demands of the market with the GDP projected at 10% in the coming decades and in view of the infrastructure. (VI) EXPORT POSSIBILITY No export is proposed. (VII) DOMESTIC/EXPORT MARKETS The entire production is envisaged for the domestic market. (VIII) EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE PROJECT No additional employment is proposed 8

10 3. PROJECT DESCRIPTION (I) TYPES OF PROJECT INCLUDING INTERLINKED AND INTERDEPENDENT PROJECT IF ANY. Required Clinker produced at LIL sister units Sonadih Cement Plant and Arasmeta Cement Plant are transported to Jamshedpur by Rail. The plant is utilizing bulk quantity of Fly Ash generated by TPL and the slag generated from TISCO. (II) LOCATION (MAP SHOWING GENERAL LOCATION, SPECIFIC LOCATION, AND PROJECT BOUNDARY & PROJECT SITE LAYOUT WITH COORDINATES The Cement Plant is located in the Jojobera area of Jamshedpur Notified Area Committee. Jamshedpur is an industrial centre of repute with industrial giants such as TISCO and TPL. It falls in District East Singbhum of Jharkhand State and is about 250 kms by road from Kolkatta. Jamshedpur city is well connected by Rail, Roads and Air. National highway 33 connects Jamshedpur to Ranchi and Kolkatta. Jamshedpur Chaibsa road and Jamshedpur Gamharia roads also fall in study area which connects Jamshedpur to Chaibasa, Adityapur Industrial Area and Gamharia. The site of Jojobera is well connected by road to all major centers of Jamshedpur city. River Subarnarekha and River Kharkai flow in NE and WNW direction of plant site and they both meet at about 12 kms in NW direction of plant site. Geographically the site is very close to the intersection of latitude N and the longitude E and 129 m above Mean Sea Level The site is well connected with communication facilities like telephone, fax, wireless and telex, railway, airport, highway and as such, no constraints are envisaged in this aspect as the tehsil and district headquarter is near to the site. The environmental setting of the unit is given in table below The location of Jojobera cement plant is shown in Fig-1 and Key Map of the plant site is shown in Fig-2. Salient features of the project site are given in Table-1. 9

11 FIG 1 10

12 FIG 2 11

13 FIG 3 12

14 TABLE-1 SALIENT FEATURES OF THE PROJECT SITE Feature Details Altitude 194 m above MSL Between to E Longitude Between to N Latitude Village, Tehsil, District, State Rahargora Village, Jamshedpur Tehsil & District,, Jharkhand Max. Temp. Min. Temp. Relative Humidity Annual rainfall Topography Soil Type Nearest River Nearest Highway Nearest Railway station & Junction Nearest Industries Nearest Village 46.6oC 5.0.oC 25-78% mm Plain Predominantly clayey River Kharkai km (ENE) River Subarnrekha 7.5 km (W) National Highway (NH-33) connecting Pardih Mohulia 7.2 km - N Tatanagar 8 km - WNW Nearest Town Nearest Air port None within 10 km radius Bari nagar 1.3 km NW Govidpur 0.6 km ENE Parsudi km W Gayatri Nagar 2.5 km NW Jamshedpur 6.5 km - NW Ranchi Nearest Forest No reserve forest in the proximity of 10 kms. Historical places None within 10 km radius *all distances mentioned in the above table are aerial distances 13

15 (III) DETAILS OF ALTERNATE SITES CONSIDERED AND THE BASIS OF SELECTING THE PROPOSED SITE, PARTICULARLY THE ENVIRONMENTAL CONSIDERATIONS GONE INTO SHOULD BE HIGHLIGHTED. No additional land or site is required or examined as the present proposal does not require any additional land except for installation Conveying air slide, bucket elevator, blender, dust collector, storage bin. (IV) SIZE OR MAGNITUDE OF OPERATION Present Cement production capacity is 4.6 MTPA. The proposal is for change of product mix as per the table given below Million Tonnes Per Annum PSC PPC COMPOSITE CEMENT - Present 4.0 (Max.) 1.0 (Max.) 4.6 (Max) Proposed (Max.) (Max.) (Max.) (Max) (V) PROJECT DESCRIPTION WITH PROCESS DETAILS (A SCHEMATIC DIAGRAM/FLOW CHART SHOWING THE PROJECT LAYOUT, COMPONENTS OF THE PROJECT ETC. SHOULD BE GIVEN. PROCESS DESCRIPTION Clinker is received from its SCP situated near Raipur in Chhattisgarh and ACP Situated near Bilaspur in Chhattisgarh. Slag is received from the TISCO, Jamshedpur and Gypsum is received from various sources from within and outside the country. Fly Ash which is an additive for manufacturing PPC is received from TPL situated adjacent to Jojobera Cement Plant. The cement production at the plant involves grinding of clinker, Slag/ash and gypsum: Handling of raw materials clinker, Slag, Fly ash, Gypsum and Coal. Slag drying in hot air generator Slag grinding in roller press grinding circuit. 14

16 4. Clinker is grinding in roller press and ball mill grinding circuit. 5. Mixing of ground clinker and ground slag by paddle mixer 6. Mixing the slag with Pozzolona cement to arrive at Composite Cement. 7. Cement storage (PSC) 8. Cement Storage (PPC) 9. Cement Storage (CC) 10. Packing and dispatch Capacity of main equipment & storage already existing are as mentioned below SL. NO. EQUIPMENT Wagon Tippler Roller Press 3. Clinker Silo CAPACITY Dry Slag Silo Ground Clinker Silo Ground Slag Silo Ball Mill Cement Silo Packer Machine Truck Loading Machine Wagon Loading Machine L D O / F.O Storage Tank L D O / F.O. Day Tank H S D Storage & Dispensing Unit Locomotive 03 Nos. 1X 500 TPH + 1 X 1200 TPH 4 X 75 TPH 2 X TON + 1 X TON 2 X 4500 TON 1X 700 TON + 1 X 3000 TON 1X 700 TON + 1 X 4000 TON 2 X 140 TPH 5 X 7000 EACH 6 X 240 TPH 4 X 90 TPH 16 X 90 TPH 2 X 22 KL + 1 X 44 KL 2 X 5 KL 2 X 20 KL 2 X 350 HP + 1 X 1200 HP Pay Loader 02 Nos. Dozer 01 No. Wet Slag Stock Pile / Storage 2 CUBIC METER 150 HP TON 19. Coal Stock Pile / Storage 4000 TON 20. Truck Tippler 21. Vertical Cement Mill Hoppers 22. Coal Mill 23. Vertical Cement Mill 24. Bulk Loaders 40 TON 350 T (SLAG) T (CLINKER) T (MINERAL GYPSUM) T (CHEMICAL GYPSUM) 15 TPH 230 TPH (SLAG) / 127 TPH (CLINKER) 1 X 230 CFM 25. Paddle Mixer 1 X 425 TPH + 1 X 225 TPH 26. Stacker 1400 TPH 27. Reclaimer 300 TPH 15

17 Additional equipment Installation of Conveying air slide, bucket elevator, blender, dust collector, storage bin. PROJECT LAYOUT The plant is located in an area of Acres. More than 33 % of the plant area is developed under greenbelt. No additional land will be required for change. The plant layout is shown in Fig 3. (VI) RAW MATERIAL REQUIRED ALONG WITH ESTIMATED QUANTITY, LIKELY SOURCE, MARKETING AREA OF FINAL PRODUCTS/S, MODE OF TRANSPORT OF RAW MATERIAL AND FINISHED PRODUCT Raw Material Requirement The total raw material required for producing clinker and total Cement after change of product mix will be: S. No Minerals Clinker Slag Fly Ash Gypsum Furnace Oil Coal RAW MATERIAL REQUIREMENT Quantity in MTPA Source Existing Additional Ultimate Lafarge s Sonadih, Arasmeta Cement Plant TISCO TPL IFFCO, PPL, Vizag Imported, etc HPCL, IOC etc Imported indigenous & 16

18 FLOW DIAGRAM OF RAW MATERIAL FLOW Road / Rail / Pipeline Rail CLINKER LAFARGE SONADIH, ARASMETA CEMENT PLANT 9 km SLAG, FLYASH,,TISCO, JAMSHEDPUR By Ship /Rail km IMPORTED MINERAL GYPSUM, 1900 km 4.6 MTPA PSC /PPC/CC PRODUCTION 8 km Pipe Line Rail WATER JUSCO JAMSHEDPUR CHEMICAL GYPUSM IFFCO, PPL, VIZAG MODE OF TRANSPORTATION Clinker, Gypsum, Coal, wet slag is transported by the railway wagons dry slag by road and Fly-Ash is received through dense phase conveying system from the TPL located adjacent to Jojobera Cement Plant. After packing cement bags of different types are dispatched to several depots by means of Railways and Roadways. Railways The nearest railway station is at Tata Nagar situated at a distance of 8 Km from plant. Lafarge Cement with co-operation of Railway department has extended the railway track upto the cement plant for transportation of essential raw materials and dispatching cement to domestic market. Roadways Jojobera is well connected to Jamshedpur city by road network. The NH- 33, which is connected Jamshedpur city to Ranchi and Kolkata. Katjor- Haludpukhar road, connecting Katjor and Haludpukhar 17

19 through Jamshedpur city. In addition to the main roads, there are several roads connecting Jojobera and Jamshedpur city. Lafarge Cement purchases all the additives from outside parties, and carries them by railways, trucks and trailers on roadways. Roadways are the other option through which Lafarge Cement dispatch cement to the domestic market. (VII) RESOURCES OPTIMIZATION/ RECYCLING AND REUSE ENVISAGED IN THE PROJECT, IF ANY, SHOULD BE BRIEF OUTLINED The concept of waste-minimization, recycle/reuse/recover techniques, Energy conservation, and natural resource conservation have been considered and detailed below. Waste minimization: The plant is presently using about 2.11 MTPA of Slag & 0.34 MTPA of ash of TISCO & TPL respectively which otherwise is treated as waste and needs disposal. In the proposed change - more wet slag will be consumed and more clinker will be saved. Reduction of greenhouse gas emissions - CO2 By introducing composite cement we are expecting about 15% increase in cementitious consumption over PPC. Which will bring down equivalent quantity of clinker consumption there by coal. For 1.00 MTPA of CC, about 15% Clinker is saved and there by reduction of Green house gases by means of reduction in coal consumption at clinker manufacturing unit, which is approx. 30 million Kg of CO2. (VIII) AVAILABILITY OF WATER ITS SOURCES, ENERGY /POWER REQUIREMENT AND SOURCES SHOULD BE GIVEN Utilities and Resource Requirement The major utilities for running of the cement plant are as follows: 18

20 (a) Water Requirement Present water requirement for the plant is about is 1050 KLD) The water is sourced from JUSCO. There would not be any increase in water consumption. (b) Power Requirement Present power requirement is 30 MVA. Total Power requirement after change is 30 MVA. The source of power is Tata Power Company the same will be for change also. (c) Fuel Requirement Hot Air Generators is being used for drying the wet slag in the grinding mill. Presently furnace oil consumption is about 16 KL per day and coal is about 60 Ton per day on year average basis. (d) Manpower Requirement The present strength of manpower is around 230 and no additional manpower requirement. (e) Power: The power demand is met from Tata Steel /JUSCO. (f) Water: Present water consumption is 1050 m3/day. The water is sourced from JUSCO. (IX) QUANTITY OF WASTES TO GENERATED (LIQUID AND SOLID) AND SCHEME FOR THEIR MANAGEMENT/DISPOSAL) No solid waste generation from the plant. Waste water generation is only from domestic use is treated in Sewage treatment Plant. (X) SCHEMATIC REPRESENTATIONS OF THE FEASIBILITY WHICH GIVE INFORMATION OF EIA PURPOSE Not applicable 19

21 4. SITE ANALYSIS (I) CONNECTIVITY Nearest railway line connecting Plant site Jojobera of SER. The site is located at a distance of about 0.3 km from road connecting Salgajhuri to Jojobera. The nearest main railway station is located at Jojobera which is 8 km from the site (II) LAND FORM, LAND USE AND LAND OWNERSHIP The present location of the plant is within the premises of Jojobera thermal power plant. About Acres of the area has been leased out to LIL by the TATA Steel for operating the grinding unit. (III) TOPOGRAPHY (ALONG WITH MAP) The plant is existing and is developed. radius around the plant site Fig 2 shows the 10 km (IV) EXISTING LAND USE PATTERN (AGRICULTURE, NONAGRICULTURE, FOREST, WATER BODIES (INCLUDING AREA UNDER CRZ)), SHORTEST DISTANCES FROM THE PERIPHERY OF THE PROJECT TO PERIPHERY OF THE FORESTS, NATIONAL PARK, WILD LIFE SANCTUARY, ECO SENSITIVE AREAS, WATER BODIES (DISTANCE FORM THE HFL OF THE RIVER), CRZ. IN CASE OF NOTIFIED INDUSTRIAL AREA, A COPY OF THE GAZETTE NOTIFICATION SHOULD BE GIVEN) The present location of the plant is adjacent to Jojobera Tata Power Company. About Acres of the area has been leased out to LIL by the Tata Steel for operating the grinding unit. S.No Details Plant &Machinery Roads Railway Siding Parking Area Greenbelt Vacant Land Total Extent (Acres)

22 There is no wild life sanctuary, national park, eco-sensitive area within the 10 km radius of the project site. (V) EXISTING INFRASTRUCTURE. Existing infrastructure include railway siding and well developed roads, storm water drains with adequate storage space for clinker and fly ash and parking area (VI) SOIL CLASSIFICATION Predominantly clayey soil. (VII) CLIMATIC DATA FROM THE SECONDARY SOURCES. The macro climate of the study area is characterized as dry, except in the monsoon season. The average annual rainfall is about 1300 mm. May is generally the hottest month with mean daily maximum of 46 oc and the mean daily minimum of 20oC. The relative humidity (RH) is high during the monsoon season with maximum value of 82 %. During the south-west monsoon and brief spells of a day or two in the cold season in association with passing western disturbances, heavily clouded or overcast skies prevail. In the rest of the year the skies are mostly clear or slightly clouded. Winds are mostly from the east or west during the period throughout the year. Post-monsoon, winds are light and variable in direction. Wind velocity increases post winter season, highest being in summer. VIII) SOCIAL INFRASTRUCTURE AVAILABLE. All infrastructure facilities such as education, health facilities and other social facilities are adequate at nearby commercial area. 21

23 5. PLANNING BRIEF (I) PLANNING CONCEPT (TYPES OF INDUSTRIES, FACILITIES, TRANSPORTATION ETC) TOWN AND COUNTRY PLANNING/ DEVELOPMENT AUTHORITY CLASSIFICATION The present location of the plant is within the premises of Jojobera thermal power plant. About acres of the area has been leased out to LIL by the TATA steel for operating the grinding unit The site is well connected by Rail, road and air network. (II) POPULATION PROJECTION. No increase in population is anticipated (IV) ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL & SOCIAL) No additional infrastructure is required. No additional employment is required (V) AMENITIES/ FACILITIES All infrastructure facilities such as education, health facilities and other social facilities are adequate at Jamshedpur. 22

24 6. PROPOSED INFRASTRUCTURE (I) INDUSTRIAL AREA (PROCESSING AREA) No Additional processing area requirement (II) RESIDENTIAL AREA (NON PROCESSING AREA) No residential area is existing. (III) GREEN BELT Green belt in an area of more than 45 Acres has been developed inside the plant boundary as per statutory norms. (IV) SOCIAL INFRASTRUCTURE. LIL has well-defined CSR policy to Carryout social development and welfare measures in the surrounding villages. Under CSR activity LIL has initiated community development projects, in the fields of health & safety, education and environment, infrastructure & employability in and around the plant. (V) CONNECTIVITY (TRAFFIC AND TRANSPORTATION ROAD / RAIL/METRO/ WATER WAYS ETC) Adequate facilities with railway siding and roads are existing. No additional connectivity is required (VI) DRINKING WATER MANAGEMENT (SOURCE AND SUPPLY OF WATER) No additional water is required. (VII) SEWERAGE SYSTEM No additional sewerage system is required as there is no additional wastewater generation (VIII) INDUSTRIAL WASTE MANAGEMENT. No industrial wastewater generation from the process at present or in future 23

25 (IX) SOLID WASTE MANAGEMENT Dust collected from air pollution control equipment is 100% recycled in process and there are no solid wastes in cement plant. (X) POWER REQUIREMENT & SUPPLY / SOURCE Power demand remains the same. 24

26 7. REHABILITATION AND RESETTLEMENT (R & R) PLAN (I) POLICY TO BE ADOPTED (CENTRAL/ STATE) IN RESPECT OF THE PROJECT AFFECTED PERSONS INCLUDING HOME OUSTEES, LAND OUSTEES AND LANDLESS LABORERS (A BRIEF OUTLINE TO BE GIVEN). Not applicable, since the project is already existing 25

27 8. PROJECT SCHEDULE & COST ESTIMATES (I) LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATE OF COMPLETION (TIME SCHEDULE FOR THE PROJECT TO BE GIVEN) No major construction activity is required except for installation for installation of an hopper bin, air slide, bucket elevator and blender. (II) ESTIMATED PROJECT COST ALONG WITH ANALYSIS IN TERMS OF ECONOMIC VIABILITY OF THE PROJECT The estimated project cost for change of product mix is about Rs 12.0 crores. 26

28 9. ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS) (I) FINANCIAL AND SOCIAL BENEFITS WITH SPECIAL EMPHASIS ON THE BENEFIT TO THE LOCAL PEOPLE INCLUDING TRIBAL POPULATION, IF ANY IN THE AREA Based on the growing demand in the state, the proximity of the project location to this market is an advantage with respect reduction in freight of cement to these markets. The project is environmental friendly as it is using Steel plant & power plant waste. Considering the above, LIL is planning to go ahead with the project, once it gets all the statutory approvals. 27

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project of MANUFACTURING OF SYNTHETIC ORGANIC DYES (5 f B IND II) By SHREEJI BAPA DYE CHEM PLOT NO 1319 & 1320, PHASE-III, GIDC, VATVA, AHEMADABAD-382445, GUJARAT,

More information

M/s. SAL STEEL LTD Survey no.245/p, Village:-Bharapar, Taluka:- Gandhidham, District:-Kutch, Gujarat.

M/s. SAL STEEL LTD Survey no.245/p, Village:-Bharapar, Taluka:- Gandhidham, District:-Kutch, Gujarat. Pre-Feasibility Study Report For Proposed Fly Ash Co-processing clinker grinding cement Unit of 40,000 MT/month Production capacity within our Existing Premises for M/s. SAL STEEL LTD Survey no.245/p,

More information

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION Jaypee Group is a leading Business House of the country with its presence in Core industries and Service Sectors like Cement, Infrastructure development,

More information

PROJECT FEASIBILITY REPORT

PROJECT FEASIBILITY REPORT PROJECT FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE For PROPOSED CHEMICAL MANUFACTURING UNIT From M/s. MORADIA BROTHERS CHEM PVT LTD LOCATED AT: Block No.: 45, JalBhumi Industrial Estate,

More information

IMS (Integrated Milling System)

IMS (Integrated Milling System) IMS (Integrated Milling System) PORTABLE CEMENT GRINDING PLANT IMSATEC GmbH Grinding Plant IMS (Integrated Milling System) CONCEPT Mini Cement grinding plants with greater efficiency in the cement market.

More information

- 1 S. NO. PARTICULARS DETAILS

- 1 S. NO. PARTICULARS DETAILS 1.0 INTRODUCTION EXECUTIVE SUMMARY M/s. Lafarge India Private Ltd. (LIPL) is a subsidiary of French building materials major Lafarge. Lafarge entered in the Indian market in 1999 with acquisition of cement

More information

PRE-FEASIBILITY REPORT. for

PRE-FEASIBILITY REPORT. for PRE-FEASIBILITY REPORT for PROPOSED COMMON EFFLUENT TREATMETN PLANT (CETP) of M/s. VIKASHTEX ENVIROTECH CETP PVT. LTD. Block No. 523, Village: Hathoda, Taluka: Mangrol, Dist: Surat - 394 405 (Guj.) Prepared

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT VENSUB LABORATORIES PRIVATE LIMITED SY. NO. 29, TUPAKULAGUDEM VILLAGE, TALLAPUDI MANDAL, WEST GODAVARI DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT VENSUB LABORATORIES PRIVATE LIMITED Duplex No. 12,

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For Polyurethane Foam Manufacturing Facility Of M/s. KRISHNA MARUTI LTD. At Plot No-13, SMG JV Park, Block No- 334,335 Vill- Hansalpur, Tal - Mandal Dist.: Ahmedabad, Gujarat INDEX

More information

F. No. J-11011/480/2007-IA II (I) Government of India Ministry of Environment and Forests (I.A Division)

F. No. J-11011/480/2007-IA II (I) Government of India Ministry of Environment and Forests (I.A Division) To, M/s. Madras Cement Ltd. V Floor 98-A, Dr. Radhakrishnan Road Mylapore Chennai 600 004 Tamilnadu F. No. J-11011/480/2007-IA II (I) Government of India Ministry of Environment and Forests (I.A Division)

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. (Change in Technology) at Hindadih Village, Masturi Tehsil Bilaspur District, Chhattisgarh Submitted to

More information

Shri Hari Dyes & Chemicals Plot No.: 439/1,417, Phase No. II, GIDC Estate, Vatva , Ahmedabad

Shri Hari Dyes & Chemicals Plot No.: 439/1,417, Phase No. II, GIDC Estate, Vatva , Ahmedabad Annexure Prefeasibility Report (PFR) File PRE FEASIBILITY REPORT For PROPOSED EXPANSION IN EXISTING MANUFACTURING PLANT Of Shri Hari Dyes & Chemicals Work & Regd. Office: CONTENTS Sr. No. Description 1.

More information

Environmental Clearance Compliance Half Yearly Report

Environmental Clearance Compliance Half Yearly Report Environmental Clearance Compliance Half Yearly Report HALF YEARLY COMPLIANCE REPORT- Oct. 2015 to March 2016 Ref: MOEF, New Delhi Environment Clearance F. No. J-11011/118/2007- IA II (I) dated 25 th August,

More information

PRE- FEASIBILITY REPORT

PRE- FEASIBILITY REPORT PRE- FEASIBILITY REPORT PREPARED FOR SHIV SHANTHI CEMENT PRIVATE LIMITED Sy. Nos. 92, 93 & 94, Tatiguda Village, Garividi Mandal, Vizianagaram District, Andhra Pradesh. PREPARED BY ISO 9001: 2008 Certified

More information

Table 1.1: The Salient Features of the Project. Proposed Quartz Mine Of Sri. Syed Masthan Basha

Table 1.1: The Salient Features of the Project. Proposed Quartz Mine Of Sri. Syed Masthan Basha 1. EXECUTIVE SUMMARY 1.1 Introduction The Eknampuram Quartz mine of 89.80 Acres/ 36.34 ha is located in Sy. No. 60, Eknampuram Village, C.S. Puram Mandal, Prakasam District, Andhra Pradesh has been allotted

More information

D:\My Documents\Legislative\Legislation BS\Consents\Six monthly compliance\cement\june 2017\COMPLIANCE STATUS.docx.docx

D:\My Documents\Legislative\Legislation BS\Consents\Six monthly compliance\cement\june 2017\COMPLIANCE STATUS.docx.docx COMPLIANCE STATUS OF ENVIRONMENT CLEARANCE EC letter no. J-11011/79/2007-IA II (I) Dated 16.04.2009 A. Specific Conditions : SN Condition Compliance 1. Continuous stack monitoring facilities to monitor

More information

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA 1.0 INTRODUCTION M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA dry type of coal washery at Village: Hindadih, Tehsil: Masturi, District: Bilaspur (C.G.) for which

More information

PRE FEASIBILITY REPORT. For EXPANSION OF CEMENT PLANT

PRE FEASIBILITY REPORT. For EXPANSION OF CEMENT PLANT PRE FEASIBILITY REPORT For EXPANSION OF CEMENT PLANT With INCREASE OF PRODUCTION CLINKER: 1.5 to 4.0 Million Tonnes per Annum CEMENT: 2.0 to 4.6 Million Tonnes per Annum & INCREASE OF WASTE HEAT RECOVERY

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT for Proposed Integrated Cement Plant of 4.00 MTPA Cement Plant with Captive Limestone mines, Thermal Power Plant, Desalination Plant and Jetty at Amreli District, Gujarat, India

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. 0.96 MTPA Wet type Coal Washery at Birgahani Village, Baloda Tehsil Janjgir-Champa District, Chhattisgarh

More information

General Information. How to apply:

General Information. How to apply: General Information Adani Power Maharashtra Limited s (APML) Thermal Power Plant of 3300 MW Capacity (5 x 660 MW) is located in the state of Maharashtra at Tirora near Gondia. All units are with Supercritical

More information

M/s JINDAL STEEL & POWER LIMITED

M/s JINDAL STEEL & POWER LIMITED PRE-FEASIBILITY REPORT On PROPOSED 1.1 MTPA ( PSC & GGS ) CEMENT GRINDING UNIT AT VILLAGE- MUKUNDPUR & BHUBANPUR, TESHIL-CHENDIPADA, DISTRICT-ANGUL, ODISHA OF M/s JINDAL STEEL & POWER LIMITED Prepared

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For PRIOR ENVIRONMENTAL CLEARANCE STORAGE CAPACITY ENHANCEMENT OF HPCL, LPG BOTTLING PLANT Capacity: 3 X 500 MT At Plot No.499 Kota-Jhalawar Road (NH-12) Village- Mandana, Tehsil-

More information

Environmental Clearance Compliance Half Yearly Report

Environmental Clearance Compliance Half Yearly Report Environmental Clearance Compliance Half Yearly Report HALF YEARLY COMPLIANCE REPORT- April 2015 to September 2015 Ref: 1. MOEF, New Delhi Environment Clearance F. No. J-11011/119/2007- IA II (I) dated

More information

INNOVATION IN ENERGY CONSUMPTION

INNOVATION IN ENERGY CONSUMPTION INNOVATION IN ENERGY CONSUMPTION SYNOPSIS In the cement industry, during the last few years there has been a steep rise in the cost of production as the cost of energy inputs has increased sharply. Studies

More information

Executive Summary in English

Executive Summary in English for Proposed Cement Plant with a capacity of Clinker 3 MTPA, Cement 7 MTPA (0.70 MTPA OPC, 3.50 MTPA PSC & 2.80 MTPA PPC) at Bhimnagar village, Sedam taluka, Gulbarga district, Karnataka in English Project

More information

For. Coal Washery. Promoter. : Budbud & Kerajharia. Plot No.29, Transport Nagar, Indira Complex, Korba [C.G.] May 2012

For. Coal Washery. Promoter. : Budbud & Kerajharia. Plot No.29, Transport Nagar, Indira Complex, Korba [C.G.] May 2012 Pre-feasibility Report For Coal Washery at Village Tehsil District : Budbud & Kerajharia : Pali : Korba [C.G.] Promoter Plot No.29, Transport Nagar, Indira Complex, Korba [C.G.] May 2012 Contents 1.0 Executive

More information

COAL STOCKPILES IN INDIAN POWER PLANTS. H Ramakrishna TCE Consulting Engineers Limited 73/1, St Marks Road, Bangalore , Karnataka, India

COAL STOCKPILES IN INDIAN POWER PLANTS. H Ramakrishna TCE Consulting Engineers Limited 73/1, St Marks Road, Bangalore , Karnataka, India SUMMARY: Coal will be transported to the power plant by belt conveyors in case of pit head power plants. In case of power plants located far away from the mines, coal will be transported by rail. In some

More information

SUBMITTED TO M.P. POLLUTION CONTROL BOARD BHOPAL (M.P.)

SUBMITTED TO M.P. POLLUTION CONTROL BOARD BHOPAL (M.P.) JAYPEE REWA PLANT (A Unit of Jaiprakash Associates Limited) JAYPEE NAGAR REWA (M.P.) 2012 2013 SUBMITTED TO M.P. POLLUTION CONTROL BOARD BHOPAL (M.P.) Jaypee Rewa Plant (A unit of Jaiprakash Associates

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT By Agrawal Iron & Industries (Unit # 2) [Regularisation of Pellet plant 90,000 MTPA along with Coal Gasifier 5000 Nm3/Hr] at Kh.No.219, 220, 221, P.H.No.54, Village Billory, Tehsil

More information

2 No. Continuous Ambient Air Quality Monitoring System (CAAQMS) installed in downwind & upwind direction and are connected to APPCB server.

2 No. Continuous Ambient Air Quality Monitoring System (CAAQMS) installed in downwind & upwind direction and are connected to APPCB server. Environmental Clearance Point Wise Half Yearly Compliance Report (October 2014 to March 2015) Cement Plant - EC No: F.No. J-11011/450/2007-IA II(I) Dated: 24 th March 2008 A. SPECIFIC CONDITIONS : S.NO.

More information

Mangalam Cement Ltd. (Unit-II) Stack No.

Mangalam Cement Ltd. (Unit-II) Stack No. Mangalam Cement Ltd. (Unit-II) Name of the Project :- Expansion of cement grinding capacity from 1.7 MTPA to 2.3 MTPA Project Code :- Clearance Letter No. : - F NO. J - 11011 /110 /2012 - IA II (I), dtd

More information

PRE FEASIBILITY REPORT (PFR)

PRE FEASIBILITY REPORT (PFR) APPLICANT : M/s PLANTERS AGGREGATES 27 PRE FEASIBILITY REPORT (PFR) APPLICANT : M/s PLANTERS AGGREGATES 28 INDEX S. No. Contents Page No. 1.0 EXECUTIVE SUMMARY 30 2.0 INTRODUCTION OF THE PROJECT / BACKGROUND

More information

Jaypee Lime Stone Mine Jaypee Bela Plant (A Unit of Jaiprakash Associates Limited)

Jaypee Lime Stone Mine Jaypee Bela Plant (A Unit of Jaiprakash Associates Limited) Jaypee Lime Stone Mine Jaypee Bela Plant (A Unit of Jaiprakash Associates Limited) Introduction: Jaypee Group is the 3 rd largest cement producer in the country. The groups cement facilities are located

More information

PRE - FEASIBILITY REPORT

PRE - FEASIBILITY REPORT PRE - FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE For EXISTING MINING ACTIVITY CATEGARY B2 UNDER THE EIA NOTIFICATION 2006 AMENDED ON 31/05/2012 TO PIRABHAI VALABHAI NANDASANIYA LOCATED

More information

Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited

Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited Introduction: Jaypee Group is the 3 rd largest cement producer in the country. The Groups cement facilities are located in

More information

PREFEASIBILITY REPORT OF PROPOSED BUILDING LIMESTONE PROJECT OF

PREFEASIBILITY REPORT OF PROPOSED BUILDING LIMESTONE PROJECT OF PREFEASIBILITY REPORT OF PROPOSED BUILDING LIMESTONE PROJECT OF Indulal C. Vora AT VILLAGE:- Palakhda, TALUKA:- Porbandar, DIST.:-Porbandar 1 (B) CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXECUTIVE SUMMARY

More information

JAYPEE NIGRIE SUPER THERMAL POWER PROJECT

JAYPEE NIGRIE SUPER THERMAL POWER PROJECT JAYPEE NIGRIE SUPER THERMAL POWER PROJECT (A Unit of M/s Jaiprakash Power Ventures Limited) Villages: Nigrie, Tehsil :Sarai District: Singrauli 2014 2015 SUBMITTED M.P. POLLUTION CONTROL BOARD BHOPAL (M.P.)

More information

KL) Proposed capacity of the. No change similar as existing i.e KL (MS KL, HSD KL & SKO KL) Terminal

KL) Proposed capacity of the. No change similar as existing i.e KL (MS KL, HSD KL & SKO KL) Terminal 1.0 EXECUTIVE SUMMARY Hindustan Petroleum Corporation Limited (HPCL) is one of the major Public Sector Navratna Oil Company engaged in refining, marketing and distribution of Petroleum Products in India.

More information

PRE-FEASIBILITY REPORT. M/s. NUVOCO VISTAS CORPORATION LTD. ( Formerly Lafarge India Limited) At-Jojobera, Jamshedpur, Dist East Singhbhum Jharkhand

PRE-FEASIBILITY REPORT. M/s. NUVOCO VISTAS CORPORATION LTD. ( Formerly Lafarge India Limited) At-Jojobera, Jamshedpur, Dist East Singhbhum Jharkhand PRE-FEASIBILITY REPORT On Proposed Installation of 1 X 27 MW Coal Based Captive Power Plant in the Existing 4.6 MTPA Cement Grinding Unit at Jojobera, Dist-East Singhbhum, Jharkhand OF M/s. NUVOCO VISTAS

More information

Mangalam Cement Ltd.(Unit I)

Mangalam Cement Ltd.(Unit I) Mangalam Cement Ltd.(Unit I) Name of the Project :- Expansion of cement Project Code :- grinding capacity from 1.3 MTPA to 1.7 MTPA Clearance Letter No. : - F NO. J - 11011 /119 /2012 - IA II (I), dtd

More information

PART A. M/s Shree Cement Ltd, (Grinding Unit) village - Udepur, Tehsil- Suratgarh, District -Shri Ganganagar, Rajasthan

PART A. M/s Shree Cement Ltd, (Grinding Unit) village - Udepur, Tehsil- Suratgarh, District -Shri Ganganagar, Rajasthan Page 1 of 9 Environmental Statement for Clinker Grinding Unit of M/s Shree Cement Limited, situated at village - Udepur, Tehsil- Suratgarh, District -Shri Ganganagar, Rajasthan for the Period from: 10

More information

ACC Limited CHAIBASA CEMENT WORKS

ACC Limited CHAIBASA CEMENT WORKS ACC Limited CHAIBASA CEMENT WORKS ENVIRONMENTAL STATEMENT (FINANCIAL YEAR ENDING MARCH 31st, 2016) PREPARED BY ACC Limited CHAIBASA CEMENT WORKS P.O. JHINKAPNI -833 215 DIST. WEST SINGHBHUM, JHARKHAND

More information

Capacity Enhancement and Energy Conservation in Cement Plant

Capacity Enhancement and Energy Conservation in Cement Plant Capacity Enhancement and Energy Conservation in Cement Plant V.K. Batra*, P.N. Chhangani**, Dinesh Satija*** and R. B. Garg**** Holtec Consulting Private Limited, Gurgaon ABSTRACT The cement industry continues

More information

Name of Project: J.K. Cement Works (Unit: J.K. Cement Ltd.), Muddapur (Karnataka)

Name of Project: J.K. Cement Works (Unit: J.K. Cement Ltd.), Muddapur (Karnataka) J.K. Cement Works, Village- Muddapur, Taluka- Mudhol, Distt.- Bagalkot, Karnataka MoEF Letter No. F.No. J-11011/263/2009-IA II (I) dated 21-06-2010 Name of Project: J.K. Cement Works (Unit: J.K. Cement

More information

Performance Analysis of Cement manufacturing Industry

Performance Analysis of Cement manufacturing Industry www.ijecs.in International Journal Of Engineering And Computer Science ISSN:2319-7242 Volume 4 Issue 3 March 2015, Page No. 10937-10941 Performance Analysis of Cement manufacturing Industry Neeraj Pandagre

More information

Spillage and Material Handling Systems. By Hugros Inc.

Spillage and Material Handling Systems. By Hugros Inc. Spillage and Material Handling Systems By Hugros Inc. Our Profile is a technology solution provider for industries for all their requirements to keep a safer and green work environment. We offer engineering

More information

North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA)

North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA) SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA) Proposed at: Bonda Industrial

More information

ppt on Ash Management By :J.N. Dave (G.M.-Power) & D.S.Makwana (I/c. G.M.-PP)

ppt on Ash Management By :J.N. Dave (G.M.-Power) & D.S.Makwana (I/c. G.M.-PP) ppt on Ash Management By :J.N. Dave (G.M.-Power) & D.S.Makwana (I/c. G.M.-PP) Salient Features of Lignite Project Panandhro Village Panandhro, Fulra & Khanot Total Meter age of Exploration 10,757 m Total

More information

PRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD

PRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD PRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD PLOT No. F-1,2,3,8,9,10, ADDL. MIDC, PHASE II, AND GUT NO. 46 & 63, VILLAGE DAREGAON, TEHSIL: JALNA DIST: JALNA, MAHARASHTRA 2014-15 1. Executive

More information

RAW MATERIALS

RAW MATERIALS RAW MATERIALS General The major Raw Materials required for production of Pellets by the Grate chain technology are graded Iron Ore fines and Bentonite. Coke/H.S.D./L.D.O. is being used as a Fuel. IRON

More information

MANJULA PULVERIZING. Manjula Pulverizing Cement Grinding & Packing Sedarapet Industrial Estate, Villiayanur Commune, Puducherry

MANJULA PULVERIZING. Manjula Pulverizing Cement Grinding & Packing Sedarapet Industrial Estate, Villiayanur Commune, Puducherry PROJECT PRE FEASIBILITY MANJULA PULVERSING MANJULA PULVERIZING Sedarapet Industrial Estate Villiayanur Commune PUDUCHERRY-605Centre 502 for Environment, Health & Safety CONTENT Chapter No. I. II. III IV

More information

DEVELOPMENT of. LPG Storage & Bottling Plant. Haldia. Project Feasibility Report

DEVELOPMENT of. LPG Storage & Bottling Plant. Haldia. Project Feasibility Report Hindustan Aegis LPG Limited DEVELOPMENT of LPG Storage & Bottling Plant Haldia Project Feasibility Report August 2017 1 Amendment Record: Amendment Inserted by (Name printed) Date Signature Remarks 2 Table

More information

The Ramco Cements Limited RR Nagar. P.M.RAMASUBRAMANIAN GM Process & QC Sr. Manager - Process S.V.Veeraraghavan Asst.

The Ramco Cements Limited RR Nagar. P.M.RAMASUBRAMANIAN GM Process & QC Sr. Manager - Process S.V.Veeraraghavan Asst. The Ramco Cements Limited RR Nagar P.M.RAMASUBRAMANIAN GM Process & QC V.SURESH Sr. Manager - Process S.V.Veeraraghavan Asst.Manager-Electrical Salient Futures of Ramasamy Raja Nagar Unit A flagship company

More information

Details of the proposed project as presented before the committee are tabulated below:

Details of the proposed project as presented before the committee are tabulated below: Shrungal Homes Block No. 141, F.P.No.42, O.P.No.42, T.P.S.No.58 (Bamroli), Choryasi, Surat. Screening & scoping / appraisal. Details of the proposed project as presented before the committee are tabulated

More information

PUBLIC SERVICE COMPANY OF OKLAHOMA (PSO)

PUBLIC SERVICE COMPANY OF OKLAHOMA (PSO) PUBLIC SERVICE COMPANY OF OKLAHOMA (PSO) NORTHEASTERN POWER STATION ANNUAL CCR FUGITIVE DUST CONTROL REPORT Prepared By: Public Service Co. of Oklahoma 7300 East Highway 88 Oologah, OK 74053 and American

More information

F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar.

F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar. 20. Karnavati Premier Living F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar. Screening & scoping / appraisal Details of the proposed project as presented before the committee

More information

RE: Comments on the National Ports Authority Tariff Application 2018/2019

RE: Comments on the National Ports Authority Tariff Application 2018/2019 11 September 2017 The Chairman Ports Regulator Private Bag X54322 Durban 4000 Dear Sir RE: Comments on the National Ports Authority Tariff Application 2018/2019 We are pleased to provide our comments on

More information

IBAU HAMBURG Custom-built Small Terminals

IBAU HAMBURG Custom-built Small Terminals IBAU HAMBURG Your efficient partner for modern and effective bulk material handling I BAU HAMBURG PLANT DESIGN - ENGINEERING - EPC-CONTRACTING CEMENT - THERMAL POWER - MINERALS Central Cone Silos Single

More information

PRE FEASIBILITY REPORT INCREASE IN THE PRODUCTION OF PENTAERYTHRITOL FROM 560 MTM TO 730 MTM & SODIUM FORMATE FROM 336 MTM TO 480 MTM

PRE FEASIBILITY REPORT INCREASE IN THE PRODUCTION OF PENTAERYTHRITOL FROM 560 MTM TO 730 MTM & SODIUM FORMATE FROM 336 MTM TO 480 MTM PRE FEASIBILITY REPORT INCREASE IN THE PRODUCTION OF PENTAERYTHRITOL FROM 560 MTM TO 730 MTM & SODIUM FORMATE FROM 336 MTM TO 480 MTM (PRODUCT IS IN POWDER & SOLUTION FORM) at SIPCOT INDUSTRIAL COMPLEX,

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT TATA CONSULTING ENGINEERS LIMITED PRE FEASIBILITY REPORT FOR 4000 MW COAL BASED ULTRA MEGA POWER PLANT AT HUSAINABAD, DEOGHAR DISTRICT, JHARKHAND, INDIA Project Proponent: Deoghar Mega Power Limited A

More information

QUALITY TREND IN INDIAN CEMENTS - A DECADE APPRAISAL

QUALITY TREND IN INDIAN CEMENTS - A DECADE APPRAISAL QUALITY TREND IN INDIAN CEMENTS - A DECADE APPRAISAL U S Sinha, K Bhatnagar, R Gupta and M M Ali National Council for Cement and Building Materials, India Abstract Cement industry plays a vital role in

More information

Bishunpur Small Hydro Power Project

Bishunpur Small Hydro Power Project 1.0 INTRODUCTION 1.1 General The state of Jharkhand almost comprises hilly terrain mostly of Chhotanagpur plateau and 30% of total area (79,714 sq km) is covered with forest. The normal annual rainfall

More information

BUREAU OF INDIAN STANDARDS. (Southern Regional Office) Our Ref: 60/CM

BUREAU OF INDIAN STANDARDS. (Southern Regional Office) Our Ref: 60/CM (Southern Regional Office) Our Ref: 60/CM 1 10 03 2014 Subject: Preparation & Review of Product Manuals for Product Certification This has reference to CMD-I s circular CMD-1/31 dated 11 Nov 2013 on the

More information

Rapid Environmental Impact Assessment Study for the Proposed Cement Plant at Majhgawan, District Sidhi, Madhya Pradesh

Rapid Environmental Impact Assessment Study for the Proposed Cement Plant at Majhgawan, District Sidhi, Madhya Pradesh 1.0 Project Description 1.1 Background Jaiprakash Associates Limited (JAL) formerly known as Jaypee Cement Limited is the well diversified conglomerate of Jaypee Group. Its cement division has 3 modern,

More information

CONVERTING INDUSTRIAL WASTE INTO ALTERNATE RAW MATERIALS THROUGH BENEFICIAL REUSE AND RECYCLING

CONVERTING INDUSTRIAL WASTE INTO ALTERNATE RAW MATERIALS THROUGH BENEFICIAL REUSE AND RECYCLING CONVERTING INDUSTRIAL WASTE INTO ALTERNATE RAW MATERIALS THROUGH BENEFICIAL REUSE AND RECYCLING Cement Industry... Cementatious concrete is the second most used material in the world next to water. As

More information

PRE-FEASIBILITY REPORT. 5.0 Hectare sand mine under bhu-jal

PRE-FEASIBILITY REPORT. 5.0 Hectare sand mine under bhu-jal 1.0 SUMMARY OF THE PROJECT PRE-FEASIBILITY REPORT Project Name of Company / Mine Location Village Taluka District State Sand mine Gram Panchayat Tarrighat, Sand mine Tarrighat Tarrighat Patan Durg Chhattisgarh

More information

Connecting. markets. you to key

Connecting. markets. you to key Essar Ports Ltd. Essar House, Keshavrao Khadye Marg Mahalaxmi Mumbai - 400 034 Maharashtra, India Telephone: (+9 22) - 50000 / 666000 Fax: (+9 22) - 6660809 Email: eptlbdm@essar.com www.essarports.com

More information

Mangalam Cement Ltd.

Mangalam Cement Ltd. Mangalam Cement Ltd. Name of the Project :- New Cement Plant Unit - III and 17.5 mw CPP-II Project Code :- Raj- 80-600 - 2008 Clearance Letter No. :-F NO. J - 11011 / 30/2006 - IA II (I), dtd 17/07/2007

More information

Custom-built Small Terminals

Custom-built Small Terminals I BAU HAMBURG A MEMBER OF THE HAVER GROUP Information I BAU HAMBURG Custom-built Small Terminals Small terminals from IBAU HAMBURG Custom-built, high flexibility Requirements for small terminals Cement

More information

CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA.

CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA. CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA. A. CONSENT TO ESTABLISH UNDER THE PROVISIONS OF WATER (PREVENTION & CONTROL OF

More information

Scraper Reclaimer Technology. Optimal solutions for Bulk Materials Handling

Scraper Reclaimer Technology. Optimal solutions for Bulk Materials Handling Scraper Reclaimer Technology Optimal solutions for Bulk Materials Handling TENOVA is a worldwide supplier of advanced technologies, products and engineering services for the iron & steel and mining industries.

More information

FORM V (See rule 14) Environmental Statement for the financial year ending 31 st March 2014 PART A

FORM V (See rule 14) Environmental Statement for the financial year ending 31 st March 2014 PART A FORM V (See rule 14) Environmental Statement for the financial year ending 31 st March 2014 i) Name and address of the owner / Occupier ii) Industry category Primary (STC Code) Secondary (SIC Code) PART

More information

Improvements in Material Handling: A Case Study of Cement Manufacturing Plant

Improvements in Material Handling: A Case Study of Cement Manufacturing Plant Vol:5, No:3, 21 Improvements in Handling: A Case Study of Cement Manufacturing Plant A. Pancharya International Science Index, Industrial and Manufacturing Engineering Vol:5, No:3, 21 waset.org/publication/12945

More information

INDUSTRIAL ACCESSORIES COMPANY

INDUSTRIAL ACCESSORIES COMPANY INDUSTRIAL ACCESSORIES COMPANY Industrial Accessories Company is an industrial design/build and original equipment manufacturer of baghouses, flue gas desulfurization, heavy metal mitigating sorbent injection

More information

ENGINEERING SERVICES

ENGINEERING SERVICES ENGINEERING SERVICES www.elb.co.za Bulk Materials Handling ABOUT ELB ENGINEERING SERVICES ELB Engineering Services (ELB) is an internationally recognised technology driven holistic solutions provider to

More information

ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR

ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR 2013-2014 FOR ACC LIMITED SINDRI CEMENT WORKS P.O. : ACC COLONY DIST. : DHANBAD JHARKHAND- 828124 INDEX S.N. PART PARTICULARS 1 INTRODUCTION 2 A GENERAL

More information

Policy Resolution for Promotion of. Petroleum, Chemicals and Petrochemical Investment Regions (PCPIRs)

Policy Resolution for Promotion of. Petroleum, Chemicals and Petrochemical Investment Regions (PCPIRs) Policy Resolution for Promotion of Petroleum, Chemicals and Petrochemical Investment Regions (PCPIRs) POLICY OBJECTIVES 1. The Petroleum, Chemicals and Petrochemical industry in India is well established

More information

HINDUJA NATIONAL POWER CORPORATION LIMITED. HNPCL, (2X520 MW). VIZAG Technical Enquiry Specification for PU Coated Pipe For Ash Water Recovery System

HINDUJA NATIONAL POWER CORPORATION LIMITED. HNPCL, (2X520 MW). VIZAG Technical Enquiry Specification for PU Coated Pipe For Ash Water Recovery System HNPCL, (2X520 MW). VIZAG THERMAL POWER PROJECT TECHNICAL ENQUIRY SPECIFICATION FOR MS ERW 45O NB POLYURETHANE COATED PIPE FOR ASH WATER RECOVERY SYSTEM Prepared By Checked by Approved by Ashok Kumar Ashok

More information

Essar Steel (I) Ltd. Hazira

Essar Steel (I) Ltd. Hazira Essar Steel (I) Ltd. Hazira Presentation on : Technological conjunction of Iron & Steel Making at Essar Steel India Ltd. By : Mr. Hitesh Sheth (Hitesh.Sheth@essar.com) Ms. Neeru Singh (Neeru.Singh@essar.com)

More information

Clearance Letter no. : MoEF Vide Letter no. J-11011/79/2003-IA-II (I) dated April 21, 2004

Clearance Letter no. : MoEF Vide Letter no. J-11011/79/2003-IA-II (I) dated April 21, 2004 Name of the Project: Jaypee Rewa Plant, Unit of M/s Jaiprakash Associates Limited for expansion Of cement production from 2.5 MTPA to 3.5 MTPA at Jaypee Nagar, District Rewa, Madhya Pradesh Project Code:

More information

FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) PART A

FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) PART A (I) FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR 2013-14 M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) Name & Address of the Owner / Occupier of the Industry Operation or Process

More information

MINERAL ADMIXTURES IN CONCRETE

MINERAL ADMIXTURES IN CONCRETE MINERAL ADMIXTURES IN CONCRETE by Dr J D BAPAT Seminar on Admixtures in Concrete 28 June 2011 Institution of Engineers, Shivajinagar Pune, Maharashtra, India FOREWORD THIS PRESENTATION GIVES BRIEF VIEW

More information

RE: Comment on the National Ports Authority Tariff Application 2013/2014

RE: Comment on the National Ports Authority Tariff Application 2013/2014 11 December 2012 The Chairman Ports Regulator Private Bag X54322 Durban 4000 Dear Sir RE: Comment on the National Ports Authority Tariff Application 2013/2014 Background OSHO SA Cement (Pty) Limited is

More information

U-II : 3.5 MTPA Cement Commissioned : Jan U-I : 3 MTPA Cement Commissioned : 1997

U-II : 3.5 MTPA Cement Commissioned : Jan U-I : 3 MTPA Cement Commissioned : 1997 Content Prism Cement at Glance Cement Process Overview What is Fly ash & how it s Benefit for Cement How to evaluate Fly ash for Cement Option of Fly Ash Integration PPC Cement Impact on Concrete Prism

More information

TABLE OF CONTENTS. Title page Table of contents List of tables List of figures Non- technical summary

TABLE OF CONTENTS. Title page Table of contents List of tables List of figures Non- technical summary TABLE OF CONTENTS Title page Table of contents List of tables List of figures Non- technical summary Page i ii vii viii ix CHAPTER 1: INTRODUCTION 1 1.1 Project Background 1 1.2 Aims and Objectives 3 1.3

More information

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra Draft Terms of References (ToR) (Based on the model TOR given in Environmental Impact Assessment Guidance Manual for building construction projects by MoEF & CC) For PROPOSED IT PARK By M/s.Balewadi Tech

More information

ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT

ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT EXECUTIVE SUMMARY NAGERCOIL MUNICIPALITY, KANYAKUMARI DISTRICT TWAD BOARD,SEWERAGE DIVISION,NAGERCOIL

More information

HINAUTI LIMESTONE MINE Mine Lease area ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P)

HINAUTI LIMESTONE MINE Mine Lease area ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P) HINAUTI LIMESTONE MINE Mine Lease area 378.261 ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P) 2012-2013 SUBMITTED TO M.P.POLLUTION CONTROL BOARD BHOPAL (M.P.) Jaypee Sidhi Cement

More information

4. The ambient air quality monitoring stations We are monitoring the ambient air quality

4. The ambient air quality monitoring stations We are monitoring the ambient air quality GLOBAL CALCIUM PRIVATE LTD., 125&126, SIPCOT COMPLEX, HOSUR 635 126 Ref : No. J-11011/411/2006-IA-II(I) dated 1 st August 2007. Compliance Report for the Period ending 31.3.2015 Sl. Specific Conditions

More information

Torpa Small Hydro Power Project

Torpa Small Hydro Power Project 1.0 INTRODUCTION 1.1 General The state of Jharkhand almost comprises hilly terrain mostly of Chhotanagpur plateau and 30% of total area (79,714 sq km) is covered with forest. The normal annual rainfall

More information

Bin Level Indication Applications in Cement Production and Concrete Batching Plants

Bin Level Indication Applications in Cement Production and Concrete Batching Plants Bin Level Indication Applications in Cement Production and Concrete Batching Plants Introduction Concrete is fundamental to our modern day construction and a key part of our global economy. Concrete is

More information

STANDARD OPERATING PROCEDURE

STANDARD OPERATING PROCEDURE STANDARD OPERATING PROCEDURE Consent to Established/Operate Procedural Guidelines Consent to Establish NOC Check List Consent to Operate NOC Check List Renewal to Consent to Operate Check List Time Frame

More information

PRE FEASIBILITY REPORT FOR. Mining of Riverbed Sand. From Darakeswar River. Area : 8.09 Ha ( 20 Acres )

PRE FEASIBILITY REPORT FOR. Mining of Riverbed Sand. From Darakeswar River. Area : 8.09 Ha ( 20 Acres ) PRE FEASIBILITY REPORT FOR Mining of Riverbed Sand From Darakeswar River Area : 8.09 Ha ( 20 Acres ) AT Mouza: Kunjapur, Plot No: 2227 (P), 2269 (P), 2603 (P),JL: 112, Village: Kunjapur, Block : Indus,,

More information

1.1 SALIENT FEATURES OF THE PROJECT Pipeline extension from VVSPL Vijayawada to the proposed Dharmapuri Storage Terminal

1.1 SALIENT FEATURES OF THE PROJECT Pipeline extension from VVSPL Vijayawada to the proposed Dharmapuri Storage Terminal 1.0 EXECUTIVE SUMMARY Hindustan Petroleum Corporation Limited (HPCL) is one of the major Public Sector Navratna Oil Company engaged in refining, marketing and distribution of Petroleum Products in India.

More information

Thethaitangar Small Hydro Power Project

Thethaitangar Small Hydro Power Project 1.0 INTRODUCTION 1.1 General The state of Jharkhand almost comprises hilly terrain mostly of Chhotanagpur plateau and 30% of total area (79,714 sq km) is covered with forest. The normal annual rainfall

More information

CO 2 Emissions Profile of U.S. Cement Industry

CO 2 Emissions Profile of U.S. Cement Industry CO 2 Emissions Profile of U.S. Cement Industry Overview Purpose of study Cement production process Energy consumption GHG emissions State-level analysis Background and Purpose Cement is a key industry

More information

PRE FEASIBILITY REPORT. For EXPANSION OF CEMENT PLANT. With. INCREASE OF PRODUCTION CLINKER: 2.00 to 5.00 MTPA CEMENT: 3.00 to 6.

PRE FEASIBILITY REPORT. For EXPANSION OF CEMENT PLANT. With. INCREASE OF PRODUCTION CLINKER: 2.00 to 5.00 MTPA CEMENT: 3.00 to 6. PRE FEASIBILITY REPORT For EXPANSION OF CEMENT PLANT With INCREASE OF PRODUCTION CLINKER: 2. to 5. MTPA CEMENT: 3. to 6. MTPA By ORIENT CEMENT LIMITED Itagi & Diggaon villages, Chittapur taluk, Kalaburagi

More information

TECHNOLOGICAL ADVANCEMENTS IN THE APPLICATION OF ALTERNATE RAW MATERIALS IN CEMENT MANUFACTURE - NCB'S EXPERIENCE

TECHNOLOGICAL ADVANCEMENTS IN THE APPLICATION OF ALTERNATE RAW MATERIALS IN CEMENT MANUFACTURE - NCB'S EXPERIENCE TECHNOLOGICAL ADVANCEMENTS IN THE APPLICATION OF ALTERNATE RAW MATERIALS IN CEMENT MANUFACTURE NCB'S EXPERIENCE ASHWANI PAHUJA Director General NATIONAL COUNCIL FOR CEMENT AND BUILDING MATERIALS, Sustainability

More information

Cement Manufacturing Page 1 10/12/2005 WP0003

Cement Manufacturing Page 1 10/12/2005 WP0003 Cement Manufacturing Page 1 10/12/2005 WP0003 Is it cement or is it concrete? Does it matter? Cement and concrete might mean the same thing to most of us, but there is a major difference in the two. In

More information