1 \ Monthly Environmental Monitoring Report Name of Operation Name of Licensee Environmental Protection Licence Reporting Period start date Reporting Period end date Version Author Approver Moolarben Coal Complex Moolarben Coal Operations Pty Ltd December December M. Cavanagh G. Chase MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP
2 1 INTRODUCTION Moolarben Coal Operations Pty Ltd (MCO) operates the Moolarben Coal Mine located at 4250 Ulan Road, Ulan, NSW which is approximately 40km north-east of Mudgee, within the Western Coal Field. It is located east of the Ulan Coal Mine and west of the Wilpinjong Coal Mine. The purpose of this report is to provide a monthly update of monitoring data in accordance with the requirements of Environmental Protection Licence (EPL) 12932, section 66(6) of the POEO Act and the MCO Project Approvals 05_0117 and 08_0135. To view MCO EPL in full please refer to the link below. On 26 May 2016 EPL Variation was approved. The variation replaces all previous versions of the licence. 2 MONITORING REQUIREMENTS The Moolarben Environment Protection Licence (EPL) specifically requires the monitoring of: Eight dust gauge sites (dust deposition monitoring); Three Tapered Element Oscillating Microbalance (TEOM) PM 10 sites; One PM 10 High Volume Air Sampler (HVAS); Three water discharge points; Two surface water quality sites; Four effluent discharge sites; Blast monitoring; Noise monitoring; and Meteorological monitoring. Monitoring of sites not required by the EPL are carried out in accordance with MCO Environmental Monitoring Program (EMP) and Project Approval 05_0117 and 08_0135. The MCO EPL12932 Environmental Monitoring Network is shown on Figure 1. MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP Page 1
3 MONTHLY ENVIRONMENTAL MONITORING REPORT Figure 1: EPL MCO Environmental Monitoring Network MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP Page 2
4 3 DUST DEPOSITIONAL GAUGES During December 2016 samples from eleven dust gauges were collected and analysed by a NATA accredited laboratory (Table 1). As at 31 December 2016 no depositional dust gauges had recorded an exceedance of the 12-month rolling average criteria of 4 g/m 2 /month (Figure 2). Sampled: 30 December 2016 Table 1: Dust Deposition Results December 2016 Licensee: Moolarben Coal Operations Pty Ltd Obtained: 13 January 2017 EPL No Published: 23 January 2017 Monitoring frequency: Monthly Location EPA ID no. Pollutant Measurement (g/m2/month) 12 month Rolling Average (g/m2/month) Note: Contaminated results are not included in the 12 month rolling average Monthly results above 4g/m 2 /month are not classed as an exceedance of criteria as the criteria is an annual average of 4g/m 2 /month 100 percentile concentration limit (g/m2/month) DG01 6 Particulates - Deposited Matter DG04 9 Particulates - Deposited Matter DG05 10 Particulates - Deposited Matter DG06 11 Particulates - Deposited Matter DG07 12 Particulates - Deposited Matter DG08 13 Particulates - Deposited Matter DG09 14 Particulates - Deposited Matter DG11 NA Particulates - Deposited Matter DG12 7 Particulates - Deposited Matter DG13 NA Particulates - Deposited Matter DG14 NA Particulates - Deposited Matter MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP Page 3
5 Figure 2: Depositional Dust 12 Month Averages MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP Page 4
6 4 REAL TIME PM10 MONITORING Continuous particulate matter less than 10μm (PM10) monitoring was conducted by four tapered element oscillating microbalance (TEOM) units at Moolarben during December The EPA identification numbers 15, 17 and 27 refer to the TEOMs installed on Ulan-Wollar Road (TEOM06), Ulan Public School (TEOM 1) and Southern Ridge Road (TEOM 5) respectively. In addition, a fourth unit is located on Ulan Road (TEOM 4) with data used for management purposes only. No results were above the daily or annual limit (Table 2). Real time PM10 results for December 2016 are illustrated in Figure 3. Table 2: Explanation of TEOM results above the daily criteria Site Date Result (μg/m 3 ) Weather Comment There were no average results above the daily limit There were no average results above the annual limit Figure 3: Daily Results from TEOMs MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP Page 5
7 TEOM06 EPL 15 TEOM05 EPL27 TEOM04 TEOM01 EPL 17 TEOM06 EPL 15 TEOM05 EPL27 TEOM04 TEOM01 EPL 17 MONTHLY ENVIRONMENTAL MONITORING REPORT Table 3: TEOM Data December 2016 Daily PM10 Monitoring EPL No Obtained 03 January 2017 Licensee: Moolarben Coal Operations Pty Ltd Published 23 January 2017 Sampled 24hr Impact (µg/m 3 ) 12 month Rolling Average (µg/m 3 ) Measurement Criteria Measurement Criteria 1/12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ /12/ MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP Page 6
8 5 HIGH VOLUME AIR SAMPLER (HVAS) PM10 MONITORING Moolarben Coal monitors PM 10 with two high volume air sampler (HVAS) units located on John Street in Ulan Village and on Ridge Road. The Ridge Road HVAS is not required by the EPL. Samples were taken every six days with a 100% data capture rate for the period. The annual rolling average and PM 10 results for December 2016 are presented graphically in Figure 4. Table 4: HVAS (PM 10) RESULTS Obtained: 13 January 2017 EPL No Licensee: Moolarben Coal Operations Pty Ltd Published: 23 January 2017 Monitoring frequency: Every 6 days Sample Date Pollutant Measurement 24hr Impact Assessment Criteria 12 Month Rolling Average Yearly Impact Assessment Criteria Sampling Point: PM01 (EPL Point No. 16) Ulan Village 01-Dec-16 PM µg/m 3 07-Dec-16 PM µg/m 3 13-Dec-16 PM µg/m 3 19-Dec-16 PM µg/m 3 25-Dec-16 PM µg/m 3 31-Dec-16 PM µg/m 3 Sampling Point: PM02 Ridge Rd 01-Dec-16 PM µg/m 3 07-Dec-16 PM µg/m 3 13-Dec-16 PM µg/m 3 19-Dec-16 PM µg/m 3 25-Dec-16 PM µg/m 3 31-Dec-16 PM µg/m 3 Units Table 5: Explanation of HVAS Results Above Criteria Site Date Result (μg/m 3 ) Weather There were no daily results above the daily limit There were no average results above the annual limit Comment MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP Page 7
9 Figure 4: HVAS Results MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP Page 8
10 6 SURFACE WATER Table 6 shows the total suspended solids, electrical conductivity, ph and oil and grease results for the routine monthly monitoring conducted on 9 th December In accordance with conditions M2.3 of EPL 12932, surface water quality is monitored at two locations, SW10 (EPL Point 4) and SW11 (EPL Point 3), along Bora Creek on a monthly basis. Sampled: 09 December 2016 Obtained: 13 January 2017 Published: 23 January 2017 Location SW01 Goulburn River SW02 Goulburn River SW04 Murragamba Creek SW05 Moolarben Creek SW07 Lagoon Creek SW08 Moolarben Creek SW09 Moolarben Creek SW10 Bora Creek SW11 Bora Creek SW12 Goulburn River SW 15 Wilpinjong Creek SW 16 Wilpinjong Creek SW17 Eastern Creek SW18 Wilpinjong Creek SW19 Murragamba Creek EPL Sampling point Table 6: Surface Water Results Licensee: Moolarben Coal Operations Pty Ltd EPL No EPL Monitoring frequency Total Suspended Solids (mg/l) Electrical Conductivity (μs/cm) ph Oil & Grease n/a n/a n/a n/a n/a < n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a 4 Special Frequency 1 1 Dry Dry Dry Dry 3 Special Frequency <5 n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a Dry Dry Dry n/a n/a n/a < n/a SW20 n/a n/a Dry Dry Dry n/a Eastern Creek Note: Total Suspended Solids limit of Analysis = <5mg/L. Sample result below detectable range. 1: Point 3 is required to be sampled monthly in the event of a flow, and daily during periods of discharge from license point 1 and in the event of a flow at Point 3. Point 4 is required to be sampled monthly in the event of a flow. MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP Page 9
11 Figure 5: ph Results Figure 6: EC Results MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP Page 10
12 Figure 7: Total Suspended Solid Results MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP Page 11
13 6.1 Water Discharges Moolarben Coal did not have any licensed discharges during December Effluent System Moolarben Coal operates four effluent discharges to land, which are identified as Point 5, Point 22, Point 23 and Point 48 in Condition P1.3 of EPL Effluent discharge occurs daily and quality sampling occurs on a quarterly basis. MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP Page 12
14 7 GROUNDWATER Figure 8: Groundwater Levels MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP Page 13
15 Figure 9: Groundwater Levels MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP Page 14
16 Figure 10: Groundwater Levels MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP Page 15
17 Figure 11: Groundwater Levels MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP Page 16
18 8 NOISE In accordance with the MCO Noise Management Plan attended noise compliance monitoring is undertaken monthly by a suitably qualified and experienced person. Monthly monitoring was conducted in December 2016 with results obtained on 17 January All monitoring measurements were undertaken during night time, except for monitoring site NA1 (Ulan School) which was monitored during the day. A brief description of the measurements at all sites are shown below and full attended noise monitoring results for December 2016 are shown in Table 7. NA1, Ulan School During the day measurement on 14 December 2016, MCO was inaudible. Birds generated the measured L A1, L A10 and L Aeq. Breeze in foliage generated the measured LA90. Road traffic noise, aircraft, insects and noise from a nearby school were also noted. The wind speed during this measurement was 3.5 m/s with a stability class of A. NA6, Lower Ridge Road During the night measurement on 13 December 2016, MCO was inaudible. Dogs were primarily responsible for generating the measured L A1 and contributed to the measured L A10 and L Aeq. Insects and frogs were primarily responsible for the measured L A10 and L Aeq and generated the measured L A90. Birds, livestock and road traffic noise were also noted. The wind speed during this measurement was 1.1 m/s with a stability class of D. NA12, Winchester Crescent During the night measurement on 13 December 2016, MCO was inaudible. Frogs and insects were primarily responsible for measured levels. Road traffic noise, aircraft, birds, dogs, livestock and owls were also noted. The wind speed during this measurement was 0.9 m/s with a stability class of D. MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP Page 17
19 Table 7: Monthly Attended Noise Monitoring Results MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP Page 18
20 MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP Page 19
21 9 BLASTING Blast monitoring is required by EPL at Ulan School (BM1). Monitoring is also undertaken at Ridge Road (BM5). A total of eight blasts were conducted during December The blast results are shown in Table 8. Table 8: Blast Results BM1 Ulan School BM5 Ridge Rd Date Time Blast Location Ground Vibration (mm/s) Blast Overpressure (dbl) Ground Vibration (mm/s) Blast Overpressure (dbl) 07/12/16 12:17 OC4 S02 B /12/16 12:04 OC2 S13 B /12/16 12:01 OC2 S14 B /12/16 12:11 OC4 S02 B /12/16 12:06 OC4 S02 B /12/16 16:02 OC2 S14 B /12/16 16:00 OC2 S10 B /12/16 16:05 OC4 S02 B MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP Page 20
22 01/12/16 03/12/16 05/12/16 07/12/16 09/12/16 11/12/16 13/12/16 15/12/16 17/12/16 19/12/16 21/12/16 23/12/16 25/12/16 27/12/16 29/12/16 31/12/16 Rainfall (mm) 01/12/16 03/12/16 05/12/16 07/12/16 09/12/16 11/12/16 13/12/16 15/12/16 17/12/16 19/12/16 21/12/16 23/12/16 25/12/16 27/12/16 29/12/16 31/12/16 Degree (Celsius) MONTHLY ENVIRONMENTAL MONITORING REPORT 10 METEOROLOGY Weather data is measured continuously at the Ulan Road Weather Station (Weather Station 3). Temperature (2m) and rainfall data are presented below. In addition to these parameters the weather station also measures wind, temperature (10m), solar radiation, humidity, atmospheric pressure, and sigma theta. All data was captured during December Weather Station 3 Temperature (2m) Maximum Temperature Average Temperature Minimum Temperature Date Figure 12: Temperature Data Weather Station 3 Rainfall Daily Rainfall Cumulative Rainfall 0 Date Figure 13: Rainfall Data MOOLARBEN COAL OPERATIONS PTY LTD PART OF THE YANCOAL AUSTRALIA GROUP Page 21
Monthly Environmental Monitoring Report. March 2018
Report 1 Final Date Rev. Status Page i Table of Contents 1. Introduction... 2 2. Monitoring Requirements... 2 3. Dust Depositional Monitoring... 5 4. Total Suspended Particulates... 7 5. Real Time PM 10
More informationMonthly Environmental Monitoring Report. February 2018
Report 1 Final Date Rev. Status Page i Table of Contents 1. Introduction... 2 2. Monitoring Requirements... 2 3. Dust Depositional Monitoring... 5 4. Total Suspended Particulates... 7 5. Real Time PM 10
More informationWILPINJONG COAL PTY LTD. Environment Protection Licence (EPL) 12425
WILPINJONG COAL PTY LTD Environment Protection Licence (EPL) 12425 Link to Environment Protection Licence EPL12425 LICENCE MONITORING DATA MONTHLY SUMMARY REPORT for 1 March 2018 to 31 March 2018 Air Monitoring
More informationWILPINJONG COAL PTY LTD. Environment Protection Licence (EPL) 12425
WILPINJONG COAL PTY LTD Environment Protection Licence (EPL) 12425 Link to Environment Protection Licence EPL12425 LICENCE MONITORING DATA MONTHLY SUMMARY REPORT for 1 February 2018 to 28 February 2018
More informationWILPINJONG COAL PTY LTD. Environment Protection Licence (EPL) 12425
WILPINJONG COAL PTY LTD Environment Protection Licence (EPL) 12425 Link to Environment Protection Licence EPL12425 LICENCE MONITORING DATA MONTHLY SUMMARY REPORT for 1 July 2018 to 31 July 2018 Air Monitoring
More informationWILPINJONG COAL PTY LTD. Environment Protection Licence (EPL) 12425
+ WILPINJONG COAL PTY LTD Environment Protection Licence (EPL) 12425 Link to Environment Protection Licence EPL12425 LICENCE MONITORING DATA MONTHLY SUMMARY REPORT for 1 August 2018 to 31 August 2018 Air
More informationWILPINJONG COAL PTY LTD. Environment Protection Licence (EPL) 12425
WILPINJONG COAL PTY LTD Environment Protection Licence (EPL) 12425 Link to Environment Protection Licence EPL12425 LICENCE MONITORING DATA MONTHLY SUMMARY REPORT for 1 December 2017 to 31 December 2017
More informationWILPINJONG COAL PTY LTD. Environment Protection Licence (EPL) 12425
WILPINJONG COAL PTY LTD Environment Protection Licence (EPL) 12425 Link to Environment Protection Licence EPL12425 LICENCE MONITORING DATA MONTHLY SUMMARY REPORT for 1 November 2017 to 30 November 2017
More informationWILPINJONG COAL PTY LTD. Environment Protection Licence (EPL) 12425
WILPINJONG COAL PTY LTD Environment Protection Licence (EPL) 12425 Link to Environment Protection Licence EPL12425 LICENCE MONITORING DATA MONTHLY SUMMARY REPORT for 1 September 2017 to 30 September 2017
More informationWILPINJONG COAL PTY LTD. Environment Protection Licence (EPL) 12425
WILPINJONG COAL PTY LTD Environment Protection Licence (EPL) 12425 Link to Environment Protection Licence EPL12425 LICENCE MONITORING DATA MONTHLY SUMMARY REPORT for 1 June 2017 to 30 June 2017 Air Monitoring
More informationWILPINJONG COAL PTY LTD. Environment Protection Licence (EPL) 12425
WILPINJONG COAL PTY LTD Environment Protection Licence (EPL) 12425 Link to Environment Protection Licence EPL12425 LICENCE MONITORING DATA MONTHLY SUMMARY REPORT for 1 February 2014 to 30 April 2014 Air
More informationWILPINJONG COAL PTY LTD. Environment Protection Licence (EPL) 12425
WILPINJONG COAL PTY LTD Environment Protection Licence (EPL) 12425 Link to Environment Protection Licence EPL12425 LICENCE MONITORING DATA MONTHLY SUMMARY REPORT for 1 August 2017 to 31 August 2017 Air
More informationWILPINJONG COAL PTY LTD. Environment Protection Licence (EPL) 12425
WILPINJONG COAL PTY LTD Environment Protection Licence (EPL) 12425 Link to Environment Protection Licence EPL12425 LICENCE MONITORING DATA MONTHLY SUMMARY REPORT for 1 October 2017 to 31 October 2017 Air
More informationWILPINJONG COAL PTY LTD. Environment Protection Licence (EPL) 12425
WILPINJONG COAL PTY LTD Environment Protection Licence (EPL) 12425 Link to Environment Protection Licence EPL12425 LICENCE MONITORING DATA MONTHLY SUMMARY REPORT for 1 August 2013 to 31 August 2013 Air
More informationKaruah East Quarry. Monthly Environmental Monitoring Report
Karuah East Quarry July 2018 Table of Contents 1. INTRODUCTION... 1 2. DUST MONITORING... 1 2.1 Dust Deposition Results... 2 2.2 High Volume Air Sampling Results... 3 2.3 Dust Monitoring Results Summary...
More informationWAMBO COAL PTY LIMITED MONTHLY ENVIRONMENTAL MONITORING REPORT. April 2011
WAMBO COAL PTY LIMITED MONTHLY ENVIRONMENTAL MONITORING REPORT Table of Contents April 2011 1.0 INTRODUCTION... 1 2.0 METEOROLOGICAL DATA... 1 3.0 SURFACE WATER SAMPLING... 1 4.0 GROUND WATER SAMPLING...
More informationAIR, WATER AND METEOROLOGICAL MONITORING JUNE 2018 PINE DALE MINE, BLACKMANS FLAT
AIR, WATER AND METEOROLOGICAL MONITORING JUNE 2018 PINE DALE MINE, BLACKMANS FLAT Prepared for Pine Dale Mine Community Consultative Committee Prepared by RCA Australia RCA ref 6880-1771/0 RCA AUSTRALIA
More informationSURFACE WATER, DEPOSITIONAL DUST, HVAS AND METEOROLOGICAL MONITORING Prepared for Pine Dale Mine Community Consultative Committee Prepared by RCA
SURFACE WATER, DEPOSITIONAL DUST, HVAS AND METEOROLOGICAL MONITORING Prepared for Pine Dale Mine Community Consultative Committee Prepared by RCA Australia RCA ref 6880-1733/0 January 2017 RCA AUSTRALIA
More informationKaruah East Quarry. Monthly Environmental Monitoring Report
Karuah East Quarry June 2018 Table of Contents 1. INTRODUCTION... 1 2. DUST MONITORING... 1 2.1 Dust Deposition Results... 2 2.2 High Volume Air Sampling Results... 3 2.3 Dust Monitoring Results Summary...
More informationAIR, WATER AND METEOROLOGICAL MONITORING AUGUST 2018 PINE DALE MINE, BLACKMANS FLAT
AIR, WATER AND METEOROLOGICAL MONITORING AUGUST 2018 PINE DALE MINE, BLACKMANS FLAT Prepared for Pine Dale Mine Community Consultative Committee Prepared by RCA Australia RCA ref 6880-1775/0 RCA AUSTRALIA
More informationSURFACE WATER, DEPOSITIONAL DUST, HVAS AND METEOROLOGICAL MONITORING Prepared for Pine Dale Mine Community Consultative Committee Prepared by RCA
SURFACE WATER, DEPOSITIONAL DUST, HVAS AND METEOROLOGICAL MONITORING Prepared for Pine Dale Mine Community Consultative Committee Prepared by RCA Australia RCA ref 6880-1757/0 January 2018 RCA AUSTRALIA
More informationAIR, WATER AND METEOROLOGICAL MONITORING MAY 2018 PINE DALE MINE, BLACKMANS FLAT
AIR, WATER AND METEOROLOGICAL MONITORING MAY 2018 PINE DALE MINE, BLACKMANS FLAT Prepared for Pine Dale Mine Community Consultative Committee Prepared by RCA Australia RCA ref 6880-1769/0 RCA AUSTRALIA
More informationSURFACE WATER, DEPOSITIONAL DUST, HVAS AND METEOROLOGICAL MONITORING Prepared for Pine Dale Mine Community Consultative Committee Prepared by RCA
SURFACE WATER, DEPOSITIONAL DUST, HVAS AND METEOROLOGICAL MONITORING Prepared for Pine Dale Mine Community Consultative Committee Prepared by RCA Australia RCA ref 6880-882/0 May 2015 RCA AUSTRALIA ABN
More informationStatus report October 2017 Goulburn River mining precinct. Goulburn River mining precinct
Status report October 2017 The NSW Status Report project is an initiative by the Land and Water Commissioner in response to community concerns on monitoring and impacts from coal mining and CSG projects.
More informationEnvironment Protection Licence 6538 Monthly Monitoring Data Summary
Bengalla Mining Company Pty Limited A.B.N. 32 053 909 470 Bengalla Road, Muswellbrook Locked Mail Bag 5, Muswellbrook NSW 2333 Australia Bengalla Mine Environment Protection Licence 6538 Monthly Monitoring
More informationCentennial Ivanhoe No2 Colliery. Environmental Monitoring Data
Centennial Ivanhoe No2 Colliery Environmental Monitoring Data October 2012 TABLE OF CONTENTS 1. INTRODUCTION... 1 2. RAINFALL... 2 3. AIR QUALITY MONITORING... 2 3.1 Depositional Dust... 2 4. SURFACE WATER
More informationMonthly Environmental Data May 2016
Monthly Environmental Data May 2016 Contents 1 AIR QUALITY... 2 1.1 HIGH VOLUME AIR SAMPLERS... 2 1.2 TAPERED ELEMENT OSCILLATING MICROBALANCE SAMPLING (TEOM)... 7 1.3 DUST DEPOSITION SAMPLING... 11 2
More informationRasp Mine Monthly Environment Monitoring Report INTRODUCTION TABLE OF CONTENTS
Monthly Environmental Monitoring Report January 2018 INTRODUCTION Broken Hill Operations Pty Ltd (BHOP) [a wholly owned subsidiary of CBH Resources Limited (CBH)] owns and operates the Rasp Mine (the Mine),
More informationPollution Monitoring Data January 2013
Cristal Mining Australia Limited Broken Hill Mineral Separation Plant Pinnacles Road Broken Hill NSW 2880 Pollution Monitoring Data January 2013 Licence Details EPA Licence Number: 12314 Hyperlink to Licence:
More informationGROUND WATER DEPOSITIONAL DUST HVAS AND METEOROLOGICAL MONITORING
GROUND WATER DEPOSITIONAL DUST HVAS AND METEOROLOGICAL MONITORING Pine Dale Mine Pine Dale Mine Community Consultative Committee RCA Australia RCA ref 6880-801/0 July 2012 RCA AUSTRALIA ABN 53 063 515
More informationPollution Monitoring Data April 2013
Cristal Mining Australia Limited Broken Hill Mineral Separation Plant Pinnacles Road Broken Hill NSW 2880 Pollution Monitoring Data April 2013 Licence Details EPA Licence Number: 12314 Hyperlink to Licence:
More informationPollution Monitoring Data July 2014
Cristal Mining Australia Limited Broken Hill Mineral Separation Plant Pinnacles Road Broken Hill NSW 2880 Pollution Monitoring Data July 2014 Licence Details EPA Licence Number: 12314 Link to Licence:
More informationLiddell Coal - Monthly Environmental Summary February 2018
Liddell Coal - Monthly Environmental Summary February. Dust Gauges Table : Dust Deposition Results Jan to Feb ( Days) Site Monthly Insoluble Solids (g/m.month) Monthly Ash Residue (g/m.month) Monthly Combustible
More informationMETROPOLITAN COAL ENVIRONMENTAL PROTECTION LICENCE MONITORING SUMMARY
Introduction The Protection of the Environment Operations Act 1997 (POEO Act) requires that holders of an environment protection licence make their pollution monitoring data publicly available in a timely
More informationMETROPOLITAN COAL ENVIRONMENTAL PROTECTION LICENCE MONITORING SUMMARY
Introduction The Protection of the Environment Operations Act 1997 (POEO Act) requires that holders of an environment protection licence make their pollution monitoring data publicly available in a timely
More informationPeak Gold Mines MONTHLY ENVIRONMENTAL MONITORING SUMMARY REPORT. February 2018
Peak Gold Mines MONTHLY ENVIRONMENTAL MONITORING SUMMARY REPORT EPL 3596 Hillston Road, Cobar NSW 2835 February 2018 Contents 1. INTENT... 3 2. SCOPE... 3 3. DEFINITIONS... 3 4. MONITORING RESULTS... 4
More informationTOMINGLEY GOLD PROJECT. Monthly Environmental Monitoring Report
TOMINGLEY GOLD PROJECT Monthly Environmental Monitoring Report April 2016 TOMINGLEY GOLD PROJECT Monthly Environmental Monitoring Report April 2016 Document History DATE VERSION REASON FOR CHANGE AUTHOR
More informationEnvironmental Monitoring Data Monthly Monitoring Results January 2014
Environmental Monitoring Data Monitoring Results January 2014 Newcastle Grain Terminal Page 1 Table of Contents 1.0 Introduction and Background... 3 2.0 Newcastle Grain Terminal Site Information... 3 2.
More informationMonthly Environmental Data January 2014
Monthly Environmental Data January 2014 Contents Monthly Environmental Data January 2014... 0 Air Quality...2 High Volume Sampling...2 Tapered Element Oscillating Microbalance Sampling... 8 Dust Deposition
More informationREPORT. Integra Underground Monthly Environmental Report March 2012 REPORT TITLE PREPARED BY. DATE 11 th May Signature DISTRIBUTION.
TITLE Integra Underground Monthly Environmental Report March 2012 PREPARED BY Dan Byrne DATE 11 th May 2012 Signature DISTRIBUTION 1. Manager, Sustainability 2. Integra Coal Website S:\Enviro\009 S\Monthly
More informationREPORT TITLE 2012 PREPARED BY
TITLE Integra Underground Monthly Environmental Report February 2012 PREPARED BY Dan Byrne DATE 11 th May 2012 Signature DISTRIBUTION 1. Manager, Sustainability 2. Integra Coal Website S:\Enviro\009 S\Monthly
More informationDrayton Management System Standard. Environmental Monitoring Program
Anglo Coal (Drayton Management) Pty Ltd Drayton Management System Standard Author: Name Brooke York Title Environmental Officer Signature Date 10-10-2017 Reviewer: Name Matt Lord Title Environmental Superintendent
More informationRasp Mine Monthly Environment Monitoring Report INTRODUCTION TABLE OF CONTENTS
Monthly Environmental Monitoring Report April 2018 INTRODUCTION Broken Hill Operations Pty Ltd (BHOP) [a wholly owned subsidiary of CBH Resources Limited (CBH)] owns and operates the Rasp Mine (the Mine),
More informationEnvironment Protection Licence
Licence Details Number: Anniversary Date: 12425 08-February Licensee WILPINJONG COAL PTY LTD LOCKED BAG 2005 MUDGEE NSW 2850 Premises WILPINJONG COAL MINE 1434 ULAN-WOLLAR ROAD WILPINJONG NSW 2850 Scheduled
More informationBOUNDARY AIR MONITORING PLAN POT 1881 REVISION 0
POT 1881 REVISION 0 BOUNDARY AIR MONITORING PLAN Port of Townsville Limited, on behalf of Glencore, Northern Stevedoring Services, South 32 and Flinders TBSH Pty Ltd. POT 1881 CONTENTS 1 Introduction...
More informationROOTY HILL REGIONAL DISTRIBUTION CENTRE MONTHLY ENVIRONMENTAL MONITORING REPORT Air Quality, Construction Noise and Meteorology
ROOTY HILL REGIONAL DISTRIBUTION CENTRE MONTHLY ENVIRONMENTAL MONITORING REPORT Aspect Air Quality, and Meteorology Date January 2015 SUMMARY Monitoring period 1 January to 31 January 2015 Parameters monitored
More informationHunter Valley Operations. EPL Monitoring Data. Published 17 October 2017 FOR THE MONTH ENDING 30 September Environment Protection Licence 640
Hunter Valley Operations EPL Monitoring Data Published 17 October 2017 Name of Operation Hunter Valley Operations Environment Protection Licence 640 Licensee Premises EPL Link HV Operations Pty Ltd Hunter
More informationATTACHMENT 2 COMMUNITY INFORMATION
ATTACHMENT 2 COMMUNITY INFORMATION Wilpinjong Coal Wilpinjong s 75W modification November, 2012 The Wilpinjong Coal Mine is located in the developing western coalfields of NSW and produces a high quality
More informationROOTY HILL REGIONAL DISTRIBUTION CENTRE MONTHLY ENVIRONMENTAL MONITORING REPORT Air Quality, Construction Noise and Meteorology
ROOTY HILL REGIONAL DISTRIBUTION CENTRE MONTHLY ENVIRONMENTAL MONITORING REPORT Aspect Air Quality, and Meteorology Date March 2015 SUMMARY Monitoring period 1 March to 31 March 2015 Parameters monitored
More informationBAAL BONE COLLIERY. January to March 2015 Environmental Monitoring Summary. Baal Bone Colliery Q Quarterly Environmental Monitoring Report
BAAL BONE COLLIERY January to March 2015 Environmental Monitoring Summary 1. Introduction In accordance with Schedule 5, Condition 9 of Project Approval 09_0178 this report provides a summary of environmental
More informationBengalla Mine. State Significant Development 5170 Monthly Monitoring Data Summary
Bengalla Mine State Significant Development 5170 Monthly Monitoring Data Summary October 2018 CONTENTS 1. INTRODUCTION... 1 2. AIR QUALITY... 2 3. NOISE... 6 4. BLASTING... 7 TABLES Table 1. PM10 Monitoring
More informationBengalla Mine. State Significant Development 5170 Monthly Monitoring Data Summary
Bengalla Mine State Significant Development 5170 Monthly Monitoring Data Summary November 2018 CONTENTS 1. INTRODUCTION... 1 2. AIR QUALITY... 2 3. NOISE... 6 4. BLASTING... 7 TABLES Table 1. PM10 Monitoring
More informationPEABODY ENERGY AIR QUALITY MANAGEMENT PLAN
PEABODY ENERGY AIR QUALITY MANAGEMENT PLAN Wl-ENV-MNP-0004 June 2018 Document Owner Environmental Advisor Document Approver Environment and Community Manager Version Approval Date Approver Name 4 June
More information1 Introduction. Mine EPL. report. Dear Leonard, J13083L2_24 assessment. operation of. the crusher, RASP Mine. 2015); and
14 January 2016 Leonard Sharp Environment and Community Liaison Officer CBH Resources RASP Mine Broken Hill Operations Pty Ltd 130 Eyre St, Broken Hill, NSW 2880 Level 5, 21 Bolton Street Newcastle NSW
More informationBengalla Mine. State Significant Development 5170 Monthly Monitoring Data Summary
Bengalla Mine State Significant Development 5170 Monthly Monitoring Data Summary April 2018 CONTENTS 1. INTRODUCTION... 1 2. AIR QUALITY... 2 3. NOISE... 6 4. BLASTING... 7 TABLES Table 1. PM10 Monitoring
More informationGROUND WATER DEPOSITIONAL DUST HVAS AND METEOROLOGICAL MONITORING PINE DALE MINE. Prepared for PINE DALE MINE COMMUNITY CONSULTATIVE COMMITTEE
GROUND WATER DEPOSITIONAL DUST HVAS AND METEOROLOGICAL MONITORING PINE DALE MINE Prepared for PINE DALE MINE COMMUNITY CONSULTATIVE COMMITTEE Prepared by RCA AUSTRALIA RCA-LE ref 6880-789/0 February 2012
More informationMonthly Environmental Monitoring Report
MACH Energy Australia Pty. Limited 21-Nov-2016 Monthly Environmental Monitoring Report Project - October 2016 Project - October 2016 Client: MACH Energy Australia Pty. Limited ABN: 34608495441 Prepared
More informationEnvironmental Protection Licence 2688
Perilya Environmental Protection Licence 2688 Licensee Perilya Broken Hill Limited (PBHL) Address Wentworth Rd, Broken Hill, NSW, 2880. Environmental Protection Licence 2688 (Southern Operations) Link
More informationPEAK GOLD MINES MONTHLY ENVIRONMENTAL SUMMARIES. April 2015
PEAK GOLD MINES MONTHLY ENVIRONMENTAL SUMMARIES April 2015 Prepared By Peak Gold Mines Signature Jenna Marett Date 20/04/2015 Distribution New Gold Internet www.newgold.com 1 Table of Contents INTENT:
More informationMonthly Noise Monitoring Assessment
Monthly Noise Monitoring Assessment Tomingley Gold Mine, December 2018 Prepared for: Tomingley Gold Operations Pty Limited December 2018 MAC160270RP28 Document Information Monthly Noise Monitoring Assessment
More informationAPPENDIX 3B AIR QUALITY MONITORING DATA
APPENDIX 3B AIR QUALITY MONITORING DATA 2017 Annual Review Wilpinjong Coal Mine Appendix 3B Air Quality Monitoring Data Summary of Annual Average Dust Deposition EPL 12425 ID No. 3 4-6 - 9 10 11 12 26
More informationEnvironmental Noise Assessment
July to September 2014 Rev 0 (Final) Report Details - July to September 2014 Filename: Job #: J0140003 Folder #: F13130 Revision: 0 (Final) Date: Prepared For Clark Potter, Senior Environmental Advisor
More information2017 Annual Review. Wilpinjong Coal Mine
2017 Annual Review Wilpinjong Coal Mine Table 1 Annual Review Title Block Name of operation Name of operator Development consent/project approval # Name of holder of development consent/project approval
More informationEnvironment Protection Licence
Licence Details Number: Anniversary Date: 20850 24-November Licensee MACH ENERGY AUSTRALIA PTY LTD LEVEL 2, 179 GREY STREET SOUTH BANK QLD 4101 Premises MOUNT PLEASANT OPERATION 1100 WYBONG ROAD MUSWELLBROOK
More informationMonthly Environmental Monitoring Report. Yancoal Hunter Valley Operations April 2018
Monthly Environmental Monitoring Report Yancoal Hunter Valley Operations April 218 1 CONTENTS 1. INTRODUCTION... 4 2. AIR QUALITY... 4 2.1 Meteorological Monitoring... 4 2.1.1 Rainfall... 4 2.1.2 Wind
More informationCulcairn Quarry Environmental Monitoring Report. Culcairn Quarry. Environmental Monitoring Report. October 2017
Environmental Monitoring Report Environmental Monitoring Report October 2017 Published: November 2017 1 Environmental Monitoring Report This monitoring report is to satisfy the requirements of Section
More informationPEAK GOLD MINES MONTHLY ENVIRONMENTAL SUMMARIES APRIL 2012
PEAK GOLD MINES MONTHLY ENVIRONMENTAL SUMMARIES APRIL 2012 Prepared By Peak Gold Mines Signature Sophie Thompson 8/05/2012 Distribution New Gold Internet www.newgold.com Peak Gold Mines Intranet HSE Public
More informationMoolarben Coal Complex Open Cut Optimisation Modification. Environmental Assessment APPENDIX A. Noise Assessment
Environmental Assessment APPENDIX A Yancoal Australia Limited Level 25, 363 George Street SYDNEY NSW 2000 Version: v1.0 Page 2 PREPARED BY: ABN 29 001 584 612 2 Lincoln Street Lane Cove NSW 2066 Australia
More informationMONTHLY ENVIRONMENTAL MONITORING REPORT PORT BOTANY REDEVELOPMENT PATRICK STEVEDORES
MONTHLY ENVIRONMENTAL MONITORING REPORT PORT BOTANY REDEVELOPMENT PATRICK STEVEDORES DECEMBER 2013 www.mcconnelldowell.com MCCONNELL DOWELL CORPORATION PAGE 1 OF 13 McConnell Dowell Constructors (Aust.)
More informationBombo Quarry Environmental Monitoring Report. Bombo Quarry. Environmental Monitoring Report. October 2017
Bombo Quarry Environmental Monitoring Report October 2017 Published: November 2017 This monitoring report is to satisfy the requirements of Section 66 (6) of the Protection of the Environment and Operations
More informationEnvironment Protection Licence
Licence Details Number: Anniversary Date: 656 30-November Licensee MUSWELLBROOK COAL COMPANY LTD PO BOX 123 MUSWELLBROOK NSW 2333 Premises MUSWELLBROOK COLLIERY HOLDING COAL ROAD MUSWELLBROOK NSW 2333
More information2015 Annual Review. Wilpinjong Coal Mine
2015 Annual Review Wilpinjong Coal Mine Table 1 Annual Review Title Block Name of operation Name of operator Wilpinjong Coal Mine Wilpinjong Coal Pty Limited Development consent/project approval # PA 05-0021
More informationMONTHLY ENVIRONMENTAL MONITORING REPORT PORT BOTANY REDEVELOPMENT PATRICK STEVEDORES
MONTHLY ENVIRONMENTAL MONITORING REPORT PORT BOTANY REDEVELOPMENT PATRICK STEVEDORES JANUARY 2014 www.mcconnelldowell.com MCCONNELL DOWELL CORPORATION PAGE 1 OF 13 McConnell Dowell Constructors (Aust.)
More informationAir Quality Monitoring Plan
Air Quality Monitoring Plan 1 OBJECTIVE The monitoring and management of air quality within the Port of Townsville is critical to address a potential risk that has generated considerable public interest
More informationGunlake Quarry. Noise and Blast Management Plan
Gunlake Quarry Noise and Blast Management Plan August 2015 Table of Contents 1. Introduction 3 1.1 Overview 3 1.2 Aims and Objectives 3 2. Noise Criteria 3 2.1 Operational Noise Assessment Criteria 3 2.2
More informationSHELL COVE BOATHARBOUR - STAGE 2 MONTHLY MONITORING SUMMARY December, 2016
SHELL COVE BOATHARBOUR - STAGE 2 MONTHLY MONITORING SUMMARY COASTWIDE CIVIL PTY LTD ADDRESS: 19 CROOME LANE, ALBION PARK, 2527 POSTAL: P.O.BOX 116, KIAMA, 2533 E-MAIL: info@coastwidecivil.com.au ABN: 71
More informationAUSTAR COAL MINE AIR QUALITY MANAGEMENT AND MONITORING PLAN
AUSTAR COAL MINE AIR QUALITY MANAGEMENT AND MONITORING PLAN Issue 1: January 2007 Final Austar Coal Mine Carbon Based Environmental Pty Limited 2006. This document was prepared solely for the original
More informationSHELL COVE BOATHARBOUR - STAGE 2 MONTHLY MONITORING SUMMARY November, 2016
SHELL COVE BOATHARBOUR - STAGE 2 MONTHLY MONITORING SUMMARY COASTWIDE CIVIL PTY LTD ADDRESS: 19 CROOME LANE, ALBION PARK, 2527 POSTAL: P.O.BOX 116, KIAMA, 2533 E-MAIL: info@coastwidecivil.com.au ABN: 71
More informationGunlake Quarry. Air Quality Management Plan
Gunlake Quarry Air Quality Management Plan August 2015 Table of Contents 1. Introduction 3 1.1 Overview 3 1.2 Aims and Objectives 3 2. Air Quality Criteria 3 2.1 Impact Assessment Criteria 4 2.2 Sources
More informationAir Quality and Greenhouse Gas Management Plan
Air Quality and Greenhouse Gas Management Document Page 1 of 53 Table of Contents 1 Commitment and Policy... 5 1.1 Introduction... 5 1.2 Purpose... 5 1.3 Scope... 6 2 ning... 8 2.1 Project Approval Requirements...
More informationLYNWOOD QUARRY AIR QUALITY MANAGEMENT PLAN FINAL
LYNWOOD QUARRY AIR QUALITY MANAGEMENT PLAN FINAL October 2016 LYNWOOD QUARRY AIR QUALITY MANAGEMENT PLAN FINAL Prepared by Umwelt (Australia) Pty Limited on behalf of Holcim (Australia) Pty Limited Project
More informationEnvironmental Monitoring Results Summary
Environmental Monitoring Results Summary Quarter 1 2016 Name of Mine: CSA Mine Environment Protection Licence: EPL 1864 Licensee Name and Operator: Cobar Management Pty Ltd Licensee Address: PO Box 31,
More informationIncorporating an Air Quality Monitoring Protocol
UNDERGROUND OPERATION Incorporating an Air Quality Monitoring Protocol Issue 1: March 2007 Carbon Based Environmental Pty Limited 2007. This document was prepared solely for the original recipient and
More informationBoral Maldon Cement Works POELA Act 2011 Monitoring Data
Boral Maldon Cement Works POELA Act 2011 Monitoring Data Boral Cement Maldon, NSW Environmental Protection Licence No. 212 Explanation of units of measure: mg/m 3 = milligrams per cubic metre g/m2/month
More informationSection 75J of the Environmental Planning and Assessment Act 1979
Project Approval Section 75J of the Environmental Planning and Assessment Act 1979 I, the Minister for Planning, approve the project referred to in schedule 1, subject to the conditions in schedules 2
More informationMoolarben Coal Complex UG1 Optimisation Modification. Environmental Assessment APPENDIX F SURFACE WATER ASSESSMENT REVIEW
Moolarben Coal Complex UG1 Optimisation Modification Environmental Assessment APPENDIX F SURFACE WATER ASSESSMENT REVIEW Moolarben Coal Complex UG1 Optimisation Modification Surface Water Assessment Review
More informationWILPINJONG COAL NOISE MANAGEMENT PLAN
WILPINJONG COAL NOISE MANAGEMENT PLAN WI-ENV-MNP-0011 June 2017 Document Owner Environmental Advisor Document Approver Environment and Community Manager Version Approval Date Approver Name 3 June 2017
More informationSTRATFORD MINING COMPLEX Air Quality and Greenhouse Gas Management Plan
STRATFORD MINING COMPLEX Air Quality and Greenhouse Gas Management Plan STRATFORD MINING COMPLEX AIR QUALITY AND GREENHOUSE GAS MANAGEMENT PLAN Revision Status Register Section/Page/ Annexure Revision
More informationNEWNES KAOLIN PTY LTD
NEWNES KAOLIN PTY LTD Sand quarry & kaolin mine Resource Assessments & Compliance 31st March 2018 NSW Department of Planning & Environment PO Box 5475 WOLLONGONG NSW, 2520 email: Christopher.Schultz@planning.nsw.gov.au
More informationMoolarben Coal Complex Open Cut Optimisation Modification. Environmental Assessment ATTACHMENT 3. Stage 2 Project Approval (08_0135)
Moolarben Coal Complex Open Cut Optimisation Modification Environmental Assessment ATTACHMENT 3 Stage 2 Project Approval (08_0135) Project Approval Section 75J of the Environmental Planning & Assessment
More informationCristal Mining Australia Ltd. MSP Air Quality
Document No: Revision: 1 Department: Tech Services Process: Environment Document Cat: Management Plan Operation: Murray Basin Product: N/A Cristal Mining Australia Ltd MSP Air Quality 27 June 2017 Revision
More informationSHELL COVE BOATHARBOUR - STAGE 2 MONTHLY MONITORING SUMMARY March, 2016
SHELL COVE BOATHARBOUR - STAGE 2 MONTHLY MONITORING SUMMARY COASTWIDE CIVIL PTY LTD ADDRESS: 19 CROOME LANE, ALBION PARK, 2527 POSTAL: P.O.BOX 116, KIAMA, 2533 E-MAIL: info@coastwidecivil.com.au ABN: 71
More informationBOGGABRI COAL MINE PRP U1: MONITORING RESULTS WHEEL GENERATED DUST
Report BOGGABRI COAL MINE PRP U1: MONITORING RESULTS WHEEL GENERATED DUST BOGGABRI COAL PTY LTD Job ID. 08031 8 August 2014 PROJECT NAME: Boggabri Coal Mine PRP U1: Monitoring Results Wheel Generated Dust
More informationBrisbane Motorway Services CLEM7 Ambient Air Quality Monitoring Report December 2017 Ref: DR.1712CLEM Issue Date: 19 January 2018
Brisbane Motorway Services CLEM7 Ambient Air Quality Monitoring Report December 2017 Ref: DR.1712CLEM Issue Date: 19 January 2018 Norditech Pty Ltd Unit 36/70 Holbeche Road Arndell Park NSW 2148 m: +61
More informationASHTON COAL OPERATIONS - UNDERGROUND AND OPEN CUT ENVIRONMENTAL REGULATORY COMPLIANCE AUDIT REPORT
ASHTON COAL OPERATIONS - UNDERGROUND AND OPEN CUT ENVIRONMENTAL REGULATORY COMPLIANCE AUDIT REPORT Audit period: August 2004 August 2007 Audit conducted: 27 & 28 August 2007 Draft report submitted: 24
More informationOrica Kooragang Island. Community Reference Group. Monthly Briefing Paper #3 January 2012 ISSUED FOR CRG MEETING ON 30 JANUARY 2012
Orica Kooragang Island Community Reference Group Monthly Briefing Paper #3 January 2012 ISSUED FOR CRG MEETING ON 30 JANUARY 2012 1. Introduction This Briefing Paper focuses on activity and events during
More informationTransfield Services Limited
Eastlink Ambient Air Quality Monitoring NATA Accreditation No: 14184 Eastlink Ambient Air Quality Monitoring System Report 1 st June 2010 30 th June 2010 Report issue date: 15 th July 2010 Maintenance
More informationQuarry Products (Newcastle) Pty Ltd. Environmental Monitoring Report. Date Report Published: 5th December 2016
Date Report Published: 5th December 2016 Document No: E001 Revision: 0 Date: 30 Nov 2016 Page 1 of 4 CONTENTS 1. INTRODUCTION... 2 2. PURPOSE... 2 3. REFERENCES / SUPPORTING DOCUMENTS... 2 4. DEFINITIONS
More informationWambo Coal Mine Annual Report
Wambo Coal Mine Annual Report Environmental ise Monitoring 1 January to 31 December 2016 Prepared for Wambo Coal Pty Limited Page i Wambo Coal Mine Annual Report Environmental ise Monitoring 1 January
More informationMoolarben Coal Complex Open Cut Optimisation Modification. Environmental Assessment ATTACHMENT 2. Stage 1 Project Approval (05_0117)
Moolarben Coal Complex Open Cut Optimisation Modification Environmental Assessment ATTACHMENT 2 Stage 1 Project Approval (05_0117) Project Approval Section 75J of the Environmental Planning and Assessment
More information