1 Hot Water Management at PT Nusa Halmahera Minerals Toguraci Mine Lawolo, R, Isles, J, Evert, J, Valenza, A, King, Dr S Presentation of: 13th AusIMM Underground Operators' Conference, October 16, 2017
2 Disclaimer Forward Looking Statements This presentation includes forward looking statements. Forward looking statements can generally be identified by the use of words such as may, will, expect, intend, plan, estimate, anticipate, continue, outlook and guidance, or other similar words and may include, without limitation, statements regarding plans, strategies and objectives of management, anticipated production or construction commencement dates and expected costs or production outputs. The Company continues to distinguish between outlook and guidance. Guidance statements relate to the current financial year. Outlook statements relate to years subsequent to the current financial year. Forward looking statements inherently involve known and unknown risks, uncertainties and other factors that may cause the Company s actual results, performance and achievements to differ materially from statements in this presentation. Relevant factors may include, but are not limited to, changes in commodity prices, foreign exchange fluctuations and general economic conditions, increased costs and demand for production inputs, the speculative nature of exploration and project development, including the risks of obtaining necessary licences and permits and diminishing quantities or grades of reserves, political and social risks, changes to the regulatory framework within which the Company operates or may in the future operate, environmental conditions including extreme weather conditions, recruitment and retention of personnel, industrial relations issues and litigation. Forward looking statements are based on the Company s good faith assumptions as to the financial, market, regulatory and other relevant environments that will exist and affect the Company s business and operations in the future. The Company does not give any assurance that the assumptions will prove to be correct. There may be other factors that could cause actual results or events not to be as anticipated, and many events are beyond the reasonable control of the Company. Readers are cautioned not to place undue reliance on forward looking statements. Forward looking statements in these materials speak only at the date of issue. Except as required by applicable laws or regulations, the Company does not undertake any obligation to publicly update or revise any of the forward looking statements or to advise of any change in assumptions on which any such statement is based. Competent Person s Statement The information in this presentation that relates to Newcrest s 31 December 2016 Mineral Resources or Ore Reserves has been extracted from the release titled Annual Mineral Resources and Ore Reserves Statement 31 December 2016 dated 13 February 2017 (the original release). Newcrest confirms that it is not aware of any new information or data that materially affects the information included in the original release and, in the case of Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the original release continue to apply and have not materially changed. Newcrest confirms that the form and context in which the competent person s findings are presented have not been materially modified from the original release. Non-IFRS Financial Information Newcrest results are reported under International Financial Reporting Standards (IFRS) including EBIT and EBITDA. This presentation also includes non-ifrs information including Underlying profit (profit after tax before significant items attributable to owners of the parent company), All-In Sustaining Cost (determined in accordance with the World Gold Council Guidance Note on Non-GAAP Metrics released June 2013), AISC Margin (realised gold price less AISC per ounce sold (where expressed as USD), or realised gold price less AISC per ounce sold divided by realised gold price (where expressed as a %)), Interest Coverage Ratio (EBITDA/Interest payable for the relevant period), Free cash flow (cash flow from operating activities less cash flow related to investing activities), EBITDA margin (EBITDA expressed as a percentage of revenue) and EBIT margin (EBIT expressed as a percentage of revenue). These measures are used internally by Management to assess the performance of the business and make decisions on the allocation of resources and are included in this presentation to provide greater understanding of the underlying performance of Newcrest s operations. The non-ifrs information has not been subject to audit or review by Newcrest s external auditor and should be used in addition to IFRS information. Reliance on Third Party Information The views expressed in this presentation contain information that has been derived from sources that have not been independently verified. No representation or warranty is made as to the accuracy, completeness or reliability of the information. This presentation should not be relied upon as a recommendation or forecast by Newcrest.
3 Background Late stage epithermal gold system Open pit mining commenced 2003 and completed 2006 Hot water flows in excess of 200l/s at between 50 0 C and 80 0 C encountered Underground mining commenced 2011 Early 2014 increasing amounts of hot water in development and stoping areas led to a review of overall dewatering system
4 Effects of Hot Water on Underground Cannot Be Underestimated
5 Safety Necessity Human interaction with 65 0 to 75 0 C water has led to 3 rd degree burns and heat stroke Risk reduced by minimising casual exposure to hot water; Minimise pooling water in working area through correct floor gradients and also reduce the number of sumps per level. (Heat sinks) Sump pump changes reduced by using specialised RNE pumps Bluey seals used as standard during raisebore hole drilling Wheel actuated taps used rather than lever Passive drainage drilling conducted through valve stand pipe Deep diamond drilling conducted through blow out preventers Bore hole pump changouts reduced by using Schlumberger axial oil well pumps suitable for hot water.
6 Toguraci Vein Structure Looking North Yahut Yahut HW Surface trace Damar Apr 17 As Built Midas Toguraci Vein Structure Looking North
7 Percentage in Each Phase of Prgramme Percentage of Holes Drilled Dry and Life Less than 12 Months 80% 70% 60% 50% 40% 30% 20% 10% 0% Phase of Programme Phases 1 and 2 High proportion of drilled dry or low life holes July 2016 strategy changed to target water bearing structures within the orebodies Proportion of drilled dry holes dropped in Phases 3 and 4 Drilled Dry Life less than 12months Success Rate
8 Structural Targeting BH38 Qtz and cataclastic zone zone m coherent above to 415m Coherent no faults between structures Qtz zone tight 411m Coherent no faults between structures Cataclastic 415m TI DC10-DD01-BH38 TND005W Sept 2017 BH38 String Preferred Trajectory FW to zone m
9 Boreholes Drilled to 311mm diameter with Blattner SB 400 raisebore rig. Cased with welded DN250 steel casing, (273mm OD) to three metres above hole bottom. Casing slotted for the bottom six metres. Equipped with predominantly Schlumberger high head axial flow pumps Pump placed six metres from the bottom of the casing and attached to a PWT or PQ steel casing riser (127mm or 102mm ID). Pumps, attached to the risers, are lowered using the same winch and launching gantry configuration used when installing the casing. Vibrating wire piezometers installed three metres above the pump
10 Flow Rate v Number of Operational Pumps End of Phase 5 Total Borehole Flow Rate l/s Jan-15 Mar-15 May-15 Jul-15 Sep-15 Nov-15 Jan-16 Mar-16 May-16 Jul-16 Sep-16 Nov-16 Jan-17 Mar-17 May-17 Jul-17 Sep-17 Nov Start of Structural Targeting Mid Phase Operational Pumps 0 0 Operational Pumps (RHS) Total Borehole Flow Rate l/s (LHS)
11 0 1 to 3 4 to 6 7 to 9 10 to to15 16 to18 19 to to to to 30 Number Current Borehole Life Borehole Life Months Reducing number of drilled dry holes Proportion of longer life stoped out holes increasing as longer term planning improves Proportion of longer life ran dry holes increasing as access gained to deeper drill sites Drilled Dry Ran Dry Mined/Stoped Out Operational
12 Typical Borehole Chamber Headworks Collection manifold Isolation valve Non-return valve Flowmeter Bleed valve Bore recovery lug Head works away from collar Pressure gauge
13 Pump Station, Pipeline and Borehole Schematic
14 Capital Pump Stations Clean Water Pump Station Primary Pump Station
15 Ex Mine Pumping Capacity 570 l/s Capacity to Surface Capital Pump Stations l/s l/s Dirty Water Sumps 14 Bores
16 PumpSim Simulation of Dewatering System
17 Newtrax Monitoring System
18 Use of Thermal Paint Before C After C
19 Thermal Imaging U/G Pump Station Portal pipe work U/G Service water Surface discharge
20 Passive Drainage SOLO drilling through valved standpipe SOLO drilling through valved standpipe Drainage gallery ready for hookup
21 Orebody Water Level Lowering Between September 2014 and October 2017 Yahut Yahut HW Surface trace 5100 mrl Damar Oct 17 As Built 5000 mrl Midas 4900 mrl 4800 mrl Sept 14 Water Level Oct 17 Water Level Toguraci Vein Structure Looking North
22 Where to next? Decline 11 on orebody footwall to access dewatering gallery at 4920mRL Establish Warman (8/6) pump chamber at 4920mRL Diamond drill below 4800mRL Decline in Yahut orebody FW to below 4800mRL Update and calibrate the water model to reflect observed condition
23 Decline 11 Dewatering Gallery (Concept) Midas Damar Yahut HW T-Fault 4930 CWPS rising main Projection of Yahut Splay 9111 Yahut 4930 Dewatering Gallery Nth Concept Dec 11 NORTH 8/6 Warman pump station Steve King Competent Ground Zone Notes: 4945 Gallery = 8 holes for 1,200m HQ 4930 Gallery = 11 holes for 1,900m HQ Rising main = 65 degrees dip The alternative Decline 11 avoids intersecting the projection of the Yahut Splay (9111) Both dewatering galleries are designed in SK competent ground Total of 44 dewatering structural intersections Existing bores =
24 Thank You
Brett Fletcher Executive General Manager PNG & Indonesian Operations
Hidden Valley Brett Fletcher Executive General Manager PNG & Indonesian Operations Disclaimer Forward Looking Statement These materials include forward looking statements. Often, but not always, forward
More informationMarket Release Newcrest Mining 15 February 2016
Market Release Newcrest Mining 15 February 2016 Lihir Pit Optimisation Project to progress to Feasibility Study stage As previously advised, a project is being undertaken to optimise the integrated life
More informationNEWS RELEASE Trading Symbol: TSX: SVM
NEWS RELEASE Trading Symbol: TSX: SVM SILVERCORP REPORTS Q3 FISCAL 2016 FINANCIAL AND OPERATING RESULTS AND FISCAL 2017 GUIDANCE ISSUED VANCOUVER, British Columbia February 5, 2016 Silvercorp Metals Inc.
More informationSILVERCORP REPORTS Q3 FISCAL 2016 FINANCIAL AND OPERATING RESULTS AND FISCAL 2017 GUIDANCE ISSUED
NEWS RELEASE Trading Symbol: TSX: SVM SILVERCORP REPORTS Q3 FISCAL 2016 FINANCIAL AND OPERATING RESULTS AND FISCAL 2017 GUIDANCE ISSUED VANCOUVER, British Columbia February 5, 2016 Silvercorp Metals Inc.
More informationOZ MINERALS THIRD QUARTER REPORT Andrew Michelmore Managing Director & CEO. 21 October 2008
OZ MINERALS THIRD QUARTER REPORT Andrew Michelmore Managing Director & CEO 21 October 2008 IMPORTANT NOTICE 2 This presentation has been prepared by OZ Minerals Limited ( OZ Minerals ) and consists of
More informationOur pursuit of continuous improvement
Western Australia Iron Ore Our pursuit of continuous improvement Mike Henry President HSE, Marketing and Technology 27 October 2014 Disclaimer Forward-looking statements This presentation contains forward-looking
More informationSA Mining and Exploration Conference Adelaide Convention Centre 11 DECEMBER 2015
SA Mining and Exploration Conference Adelaide Convention Centre 11 DECEMBER 2015 Disclaimer This presentation has been prepared by OZ Minerals Limited ( OZ Minerals ) and consists of written materials/slides
More informationSILVERCORP NET INCOME $43.7 MILLION, $0.26 PER SHARE, FOR FISCAL 2017
NEWS RELEASE Trading Symbol: TSX: SVM NYSE MKT: SVM SILVERCORP NET INCOME $43.7 MILLION, $0.26 PER SHARE, FOR FISCAL 2017 VANCOUVER, British Columbia May 25, 2017 Silvercorp Metals Inc. ( Silvercorp or
More informationUnderground Ore Reserve growth at Prominent Hill extends mine life to 2030
12 NOVEMBER 2018 Underground Ore Reserve growth at Prominent Hill extends mine life to 2030 Prominent Hill underground Ore Reserve increased to 40Mt @ 1.7% copper equivalent i with a 50% increase in Proved
More informationSILVERCORP REPORTS Q2 RESULTS: NET INCOME OF $11.1 MILLION, $0.07 PER SHARE
NEWS RELEASE Trading Symbol: TSX: SVM NYSE AMERICAN: SVM SILVERCORP REPORTS Q2 RESULTS: NET INCOME OF $11.1 MILLION, $0.07 PER SHARE VANCOUVER, British Columbia November 8, 2017 Silvercorp Metals Inc.
More informationSILVERCORP REPORTS SILVER PRODUCTION OF 5.0 MILLION OUNCES, CASH FLOWS FROM OPERATIONS OF $31.9 MILLION, OR $0
NEWS RELEASE Trading Symbol: TSX: SVM SILVERCORP REPORTS SILVER PRODUCTION OF 5.0 MILLION OUNCES, CASH FLOWS FROM OPERATIONS OF $31.9 MILLION, OR $0.19 PER SHARE, FOR FISCAL YEAR ENDED MARCH 31, 2016 VANCOUVER,
More informationForward Looking Statement
Olympias Forward Looking Statement Certain of the statements made in this Presentation may contain forward-looking statements or information within the meaning of the United States Private Securities Litigation
More informationSILVERCORP REPORTS Q2 FISCAL 2017 RESULTS: NET INCOME UP 454%, CASH FLOWS FROM OPERATIONS OF $27.0 MILLION ON RECORD SILVER PRODUCTION
NEWS RELEASE Trading Symbol: TSX: SVM SILVERCORP REPORTS Q2 FISCAL 2017 RESULTS: NET INCOME UP 454%, CASH FLOWS FROM OPERATIONS OF $27.0 MILLION ON RECORD SILVER PRODUCTION VANCOUVER, British Columbia
More informationSILVERCORP REPORTS Q3 RESULTS: NET INCOME OF $12.7 MILLION, $0.08 PER SHARE AND PROVIDES FISCAL 2019 PRODUCTION AND CASH COSTS GUIDANCE
NEWS RELEASE Trading Symbol: TSX: SVM NYSE AMERICAN: SVM SILVERCORP REPORTS Q3 RESULTS: NET INCOME OF $12.7 MILLION, $0.08 PER SHARE AND PROVIDES FISCAL 2019 PRODUCTION AND CASH COSTS GUIDANCE VANCOUVER,
More informationNEWS RELEASE New York - AG Toronto FR August 11, 2015 Frankfurt FMV Mexico - AG
FIRST MAJESTIC SILVER CORP. Suite 1805 925 West Georgia Street Vancouver, B.C., Canada V6C 3L2 Telephone: (604) 688-3033 Fax: (604) 639-8873 Toll Free: 1-866-529-2807 Web site: www.firstmajestic.com; E-mail:
More informationNEWS RELEASE New York AG February 25, 2019 Toronto FR Frankfurt FMV. First Majestic Announces Financial Results for Q4 and Year End 2018
FIRST MAJESTIC SILVER CORP. Suite 1800 925 West Georgia Street Vancouver, B.C., Canada V6C 3L2 Telephone: (604) 688-3033 Fax: (604) 639-8873 Toll Free: 1-866-529-2807 Web site: www.firstmajestic.com; E-mail:
More informationFor personal use only
Operations Improving, Continued Exploration Success July 2016 Picture taken from Monkey Hill looking north Disclaimer Forward Looking Statements These materials include forward looking statements. Forward
More informationAMERICAS SILVER CORPORATION PROVIDES THIRD QUARTER PRODUCTION RESULTS AND SAN RAFAEL PROJECT UPDATE
AMERICAS SILVER CORPORATION PROVIDES THIRD QUARTER PRODUCTION RESULTS AND SAN RAFAEL PROJECT UPDATE TORONTO, ONTARIO October 24, 2016 Americas Silver Corporation (TSX:USA) (OTCQX:USAPF) ( Americas Silver
More informationHidden Valley PNG s Newest Mine Briefing for Analysts
Hidden Valley PNG s Newest Mine Briefing for Analysts 30 March 2011 Harmony Gold Disclosure Statement This presentation contains "forward-looking statements" within the meaning of Section 27A of the Securities
More informationConfidence in Carrapateena project grows
7 NOVEMBER 2016 Confidence in Carrapateena project grows Carrapateena Pre-Feasibility Study released - project competitive with, or better than comparable long-life copper assets globally Project metrics
More informationInvestor Update. January 2014 ASX : ENR
Investor Update January 2014 ASX : ENR INVESTMENT SUMMARY Greenfields Copper Discovery - BM7 Large scale Cu system >14km long and growing $20m farm-in with Antofagasta plc (2 tenements) Key ground position
More informationOM HOLDINGS LIMITED Investor Presentation May 2018
1 OM HOLDINGS LIMITED Investor Presentation May 2018 2 DISCLAIMER This presentation has been prepared and issued by OM Holdings Limited ARBN 081 028 337 ( OMH ). This presentation contains summary information
More informationALACER GOLD ANNOUNCES FOURTH QUARTER MINE PRODUCTION AND 2012 GUIDANCE
ALACER GOLD ANNOUNCES FOURTH QUARTER MINE PRODUCTION AND 2012 GUIDANCE Quarterly Gold Production Increases to 113,861 ounces and 421,204 Ounces Achieved for January 24, 2012 Alacer Gold Corp ( Alacer or
More informationAMERICAS SILVER CORPORATION PROVIDES THIRD QUARTER PRODUCTION UPDATE
AMERICAS SILVER CORPORATION PROVIDES THIRD QUARTER PRODUCTION UPDATE TORONTO, ONTARIO October 27, 2015 Americas Silver Corporation (TSX: SPM) (OTCQX: SMNPF) ( Americas Silver or the Company ) today announced
More informationKirkland Lake Gold Produces 130,425 Ounces of Gold in Q Supported by Strong Grade Performance at Macassa and Fosterville Mines
NEWS RELEASE Kirkland Lake Gold Produces 130,425 Ounces of Gold in Q1 2017 Supported by Strong Grade Performance at Macassa and Fosterville Mines 4/12/2017 TORONTO, ONTARIO--(Marketwired - April 12, 2017)
More informationOCEANAGOLD PROVIDES AN UPDATE TO HAILE COMMISSIONING AND REVISED COMPANY GUIDANCE
MEDIA RELEASE 26 June 2017 OCEANAGOLD PROVIDES AN UPDATE TO HAILE COMMISSIONING AND REVISED COMPANY GUIDANCE (All financial figures in US Dollars unless otherwise stated) (MELBOURNE) OceanaGold Corporation
More informationSECOND QUARTER REPORT 15 JULY 2014
SECOND QUARTER REPORT 15 JULY 2014 DISCLAIMER This presentation has been prepared by OZ Minerals Limited ( OZ Minerals ) and consists of written materials/slides for a presentation concerning OZ Minerals.
More informationMacquarie Australia Conference 2018 Warrick Ranson Chief Financial Officer. M a y 2018
Macquarie Australia Conference 2018 Warrick Ranson Chief Financial Officer M a y 2018 Disclaimer Forward looking statements This presentation has been prepared by OZ Minerals Limited (OZ Minerals) and
More informationNevada Copper Hits with 19 Mineralized Holes: Enhances Potential of Open Pit Economics
NEWS RELEASE TSX: NCU Nevada Copper Hits with 19 Mineralized Holes: Enhances Potential of Open Pit Economics September 24, 2018 - Nevada Copper Corp. (TSX: NCU) ("Nevada Copper" or the Company ) is pleased
More informationFor personal use only
28 November 2017 Corporate Details Ordinary Shares: 780,917,069 Market Capitalisation: ~$156 million Cash and bullion at 30 September 2017: ~$20.1 million Debt: NIL ASX Code: MOY Board of Directors Greg
More informationT S X : R M X N Y S E. M K T : R B Y. Rubicon Begins Stockpiling Mill Feed for Projected Production Commencing Mid-2015
T S X : R M X N Y S E. M K T : R B Y News Release D e c e m b e r 1 8, 2014 Rubicon Begins Stockpiling Mill Feed for Projected Production Commencing Mid-2015 TORONTO, Ontario Rubicon Minerals Corporation
More informationNet income of $7.2 million, or $0.04 per share, compared to net loss of $43.2 million, or
NEWS RELEASE Trading Symbol: TSX: SVM NYSE: SVM SILVERCORP FISCAL 2015 Q2 RESULTS: SILVER PRODUCTION UP 32%, NET INCOME OF $7.2 MILLION ($0.04 PER SHARE), CASH FLOW FROM OPERATIONS OF $20.1 MILLION ($0.12
More informationFor personal use only
Rewardle Holdings Limited (ASX:RXH) Company overview and update: November 2015 A marketing and transactional platform designed for a connected world Rewardle Holdings Limited 1 Rewardle is a social network
More informationFor personal use only
Go to View / Master / Slide Master. Insert, position and crop pictures on this Master Slide behind Vision Graphic element. MASTERMYNE GROUP AGM OPERATIONS UPDATE NOVEMBER 2017 www.mastermyne.com.au Overview
More information(TSX: AUQ) (NYSE: AUQ)
AuRico Gold Announces a New Gold-Copper Porphyry Discovery at the Kemess Project; Initial Resource Estimate Expected in Early 2015 Hole KH-14-04 intersects 768 metres of 0.442 g/t Au and 0.392% Cu Toronto:
More informationTrading Symbol: TSX: SVM February 8, 2011 NYSE: SVM
PRESS RELEASE Trading Symbol: TSX: SVM February 8, 2011 NYSE: SVM SILVERCORP REPORTS RECORD SILVER PRODUCTION, SALES AND CASH FLOWS FOR FISCAL 2011 Q3: NET INCOME UP 140% TO $29.7 MILLION OR $0.18 PER
More informationMay 8, 2018 NYSE:HL. Exploration Update. To accompany 05/08/18 news release
May 8, 2018 Update To accompany 05/08/18 news release Cautionary Statements Cautionary Statement Regarding Forward Looking Statements, This presentation contains forward-looking statements within the meaning
More informationCHINA MINING Conference Tianjin October 2014
CHINA MINING Conference Tianjin October 2014 Forward Looking Statements These materials include forward looking statements. Often, but not always, forward looking statements can generally be identified
More informationFY16 AGM Rob Woolley, Chair Laura McBain, CEO 19 October 2016
FY16 AGM Rob Woolley, Chair Laura McBain, CEO 19 October 2016 SHARE PRICE $ 18 16 14 12 10 8 6 4 2 0 05-Aug-14 30-Aug-14 30-Sep-14 31-Oct-14 30-Nov-14 31-Dec-14 31-Jan-15 28-Feb-15 31-Mar-15 30-Apr-15
More informationFor personal use only
ASX ANNOUNCEMENT 09 NOVEMBER 2011 Australian Securities Exchange Code: NST Board of Directors Mr Chris Rowe Non-Executive Chairman Mr Bill Beament Managing Director Mr Michael Fotios Non-Executive Director
More informationKANMANTOO COPPER MINE: STRATEGY AND OPPORTUNITY SA GOVERNMENT COPPER SUMMIT GREG HALL IIIII CEO & MANAGING DIRECTOR 6 MAY 2015
KANMANTOO COPPER MINE: STRATEGY AND OPPORTUNITY SA GOVERNMENT COPPER SUMMIT GREG HALL IIIII CEO & MANAGING DIRECTOR 6 MAY 2015 STRATEGY ENHANCING SHAREHOLDER VALUE THREE PILLARS FOR ENHANCING SHAREHOLDER
More informationQUARTERLY REPORT for the three months ending 31 December 2018
ASX: AMI December 2018 Quarter 22 January 2019 QUARTERLY REPORT for the three months ending 31 December 2018 HIGHLIGHTS Group quarterly gold production of 35,834 oz at an AISC of $732/oz and an AIC of
More informationRambler Reports Fiscal 2016 Q4 and Yearend Production Results 12% Increase in Production over Fiscal 2015
Page 1 of 5 21 September Rambler Reports Fiscal Q4 and Yearend Production Results 12% Increase in Production over Fiscal 2015 London, England & Baie Verte, Newfoundland and Labrador, Canada - Rambler Metals
More informationFebruary 12, 2018 NYSE:HL. Exploration Update. To accompany 02/12/18 news release
February 12, 2018 Exploration Update To accompany 02/12/18 news release Cautionary Statements Cautionary Statement Regarding Forward Looking Statements, This presentation contains forward-looking statements
More informationAuRico Gold Provides Monthly Update on Young-Davidson Ore Processing Underway
AuRico Gold Provides Monthly Update on Young-Davidson Ore Processing Underway Toronto: April 5, 2012: AuRico Gold Inc. (TSX:AUQ) (NYSE:AUQ), ( AuRico, AuRico Gold or the Company ) is pleased to provide
More informationT S X : R M X N Y S E. M K T : R B Y
T S X : R M X N Y S E. M K T : R B Y News Release A p r i l 1 4, 2015 Rubicon s Phoenix Gold Project Commences Mill Commissioning and Remains on Schedule for Mid-2015 Projected Initial Production TORONTO,
More informationCoeur Files Technical Report for Palmarejo Complex
NEWS RELEASE Coeur Files Technical Report for Palmarejo Complex Seven-Year Mine Life with Average Annual Production of Nearly 12 million AgEq Unit Costs 13% Lower than Last Filed Technical Report Chicago,
More informationForward-looking Statements
Forward-looking Statements The information given in this presentation and during Mandalay Resources Corporation s September 12, 2016 Investor Day contain "forwardlooking statements" within the meaning
More informationFor personal use only
BIGTINCAN HOLDINGS LIMITED FULL YEAR RESULTS PRESENTATION AUGUST 2018 1 2017 BIGTINCAN 2018 BIGTINCAN I SEPTEMBER 11, 2017 FY18 Financial Highlights ARR* $15.4m REVENUE $13.1m LOSS ($6.8m) 41% 42% 15%
More informationQUADRA ANNOUNCES THIRD QUARTER 2009 PRODUCTION RESULTS
QUADRA ANNOUNCES THIRD QUARTER 2009 PRODUCTION RESULTS Vancouver, Canada October 13 th, 2009 Quadra Mining Ltd. ( Quadra or the Company ) (QUA:TSX) announces the production results for the third quarter
More informationFor personal use only
4 AUGUST 2017 TROPICANA GOLD MINE UPDATE Independence Group NL ( IGO or the Company ) (ASX: IGO) is pleased to provide a progress report on initiatives to further maximise and optimise the Tropicana Gold
More informationHighlights during the three and nine months ended September 30, 2015, and Outlook
No. 11/2015 News release KATANGA MINING ANNOUNCES THIRD QUARTER 2015 RESULTS BAAR, SWITZERLAND, November 13, 2015 Katanga Mining Limited (TSX: KAT) ("Katanga" or the "Company") today announces its financial
More informationMANGANESE THE NEED FOR A SUSTAINABLE FUTURE
MANGANESE THE NEED FOR A SUSTAINABLE FUTURE GRAHAM KERR CHIEF EXECUTIVE OFFICER FEBRUARY 2016 IMPORTANT NOTICES The purpose of this presentation is to provide general information about South32 Limited.
More informationFor personal use only
September 2013 Quarterly Report 24 October 2013 Highlights Record gold production of 7,733 oz (34% increase on the previous quarter) Average gold price received of A$1,465/oz (US$1,335/oz) Cash costs reduced
More informationZincOx Resources plc. Corporate Overview
ZincOx Resources plc Corporate Overview May 2012 Where there s Muck there s Brass Disclaimer This document is for informational purposes only and must not be used or relied upon for the purposes of making
More informationFor personal use only
Saracen Mineral Holdings Limited Australian Gold Producer ASX:SAR SARACEN MINERAL HOLDINGS LTD Guido Staltari, Executive Chairman Raleigh Finlayson, Chief Operating Officer Denver Gold Forum Denver, CO
More informationSARACEN MINERAL HOLDINGS LTD
Saracen Mineral Holdings Limited Australian Gold Producer ASX:SAR SARACEN MINERAL HOLDINGS LTD Guido Staltari, Executive Chairman Raleigh Finlayson, Chief Operating Officer Denver Gold Forum Denver, CO
More informationNorthern Iron. Investor Update March 2010
Northern Iron Investor Update March 2010 Disclaimer Forward-looking statements This presentation may include forward-looking statements. Forward-looking statements are only predictions and are subject
More informationQ4 & Full Year 2014 Results
The leading high-grade gold producer in Colombia Q4 & Full Year 2014 Results Lombardo Paredes Arenas, CEO Mike Davies, CFO 1 DISCLAIMER Forward-Looking Statements This presentation contains "forward-looking
More informationSantacruz Silver Reports First Quarter 2017 Production and Financial Results
TSX.V: SCZ FSE: 1SZ May 31, 2017 Santacruz Silver Reports First Quarter 2017 Production and Financial Results Vancouver, B.C. Santacruz Silver Mining Ltd. (TSX.V:SCZ) (the Company or Santacruz ) reports
More informationNEWS RELEASE New York AG February 22, 2017 Toronto FR Frankfurt FMV Mexico - AG. First Majestic Announces Financial Results for Q4 and Year End 2016
FIRST MAJESTIC SILVER CORP. Suite 1805 925 West Georgia Street Vancouver, B.C., Canada V6C 3L2 Telephone: (604) 688-3033 Fax: (604) 639-8873 Toll Free: 1-866-529-2807 Web site: www.firstmajestic.com; E-mail:
More informationUpdate on Hammer Mill 3 Commissioning
Update on Hammer Mill 3 Commissioning ASX/Media Release 18 April 2018 Hammer Mill 3 (HM3) production of 131.4 ounces of gold in doré during 7.5-day initial commissioning run-time in March (i.e., average
More informationNon-IFRS performance measure. Refer to the Non-IFRS Performance Measures contained in the Q Management s Discussion and Analysis.
PRESS RELEASE TSX NYSE: RIC Richmont Mines Reports Strong Second Quarter Financial Results Driven by Solid Operational and Record Cost Performance from the Island Gold Mine; Reports Net Free Cash Flow
More informationMalachite Resources AGM. November For personal use only. Malachite Resources Limited
Malachite Resources AGM November 2013 1 Malachite Resources Limited Disclaimer and Competent Person Statement Disclaimer This presentation may contain forward looking statements that are subject to risk
More informationFor personal use only
June 2013 Quarterly Report 30 July 2013 Highlights Total gold production was 5,767 ounces for the quarter. Cash operating profit was A$628,000 for the quarter. Gold production at Lily was 4,641 ounces
More informationFor personal use only
Annual General Meeting 21 May 2013 - Melbourne Western Australia 2013 Boart Longyear. All rights reserved. Important Notice and Disclaimer This presentation has been prepared by Boart Longyear Limited,
More informationFor personal use only
Highlights March 2014 Quarterly Report 30 April 2014 Record tonnes milled of 131,950 tonnes for the quarter. Gold production of 7,786 oz for the quarter. Average gold price received of A$1,447/oz (US$1,300
More informationQ Preliminary Production Results, 2018 Production Guidance and Mineral Reserve and Resource Update
For immediate release 10 January 2018 Centamin plc ("Centamin" or "the Company") (LSE:CEY, TSX:CEE) Q4 2017 Preliminary Production Results, 2018 Production Guidance and Mineral Reserve and Resource Update
More informationThe Model for Tungsten
The Model for Tungsten ASX:TGN www.tungstenmining.com April 2013 Disclaimer This presentation has been prepared by Tungsten Mining NL ( Tungsten Mining ) and consists of slides for a presentation concerning
More informationFor personal use only REGIS RESOURCES LTD JUNE 2016 QUARTERLY REPORT & EXPLORATION UPDATE
1 REGIS RESOURCES LTD JUNE 2016 QUARTERLY REPORT & EXPLORATION UPDATE DISCLAIMER & COMPETENT PERSONS STATEMENT 2 This presentation contains only a brief overview of Regis Resources Limited and its associated
More informationIncreasing Net Present Value by a Third at an Operating Sublevel Cave Mine Using Draw Strategy Optimisation. Presented by Alex Campbell
Increasing Net Present Value by a Third at an Operating Sublevel Cave Mine Using Draw Strategy Optimisation Presented by Alex Campbell Presentation Overview Three year project to optimise the draw strategy
More informationThe Model of Growth for Tungsten
The Model of Growth for Tungsten ASX:TGN www.tungstenmining.com February 2013 Disclaimer This presentation has been prepared by Tungsten Mining NL ( Tungsten Mining ) and consists of slides for a presentation
More informationFebruary 2018 KURUÇAY ZINC PROJECT
February 2018 KURUÇAY ZINC PROJECT Disclaimer: The economic analysis contained in this presentation is based, in part, on inferred resources, and is preliminary in nature for the Kuruçay Zinc Project («Project»)
More informationPROUDLY POSITIONED AS AN AUSTRALIAN MINER ASX:MLX. November 2017 AGM Presentation
PROUDLY POSITIONED AS AN AUSTRALIAN MINER ASX:MLX November 2017 AGM Presentation DISCLAIMER General Disclaimer This presentation has been prepared by Metals X Limited ( Metals X or the Company ) for the
More informationSeptember 2018 Quarterly Report Presentation and Webcast 25 October 2018
September 2018 Quarterly Report Presentation and Webcast 25 October 2018 Access this presentation at: http://webcasting.brrmedia.com/broadcast/5bb2ad1abfd72969440cb5a0 or http://www.sandfire.com.au 1 Important
More informationKANMANTOO PUMPED HYDRO STEVE McCLARE IIIII CEO & MANAGING DIRECTOR PUMPED HYDRO ENERGY STORAGE CONFERENCE SYDNEY MARCH 2018
KANMANTOO PUMPED HYDRO STEVE McCLARE IIIII CEO & MANAGING DIRECTOR PUMPED HYDRO ENERGY STORAGE CONFERENCE SYDNEY MARCH 2018 STATEMENT No representation or warranty is or will be made by any person (including
More informationMt Carlton. May Arlene Rofe General Manager
Mt Carlton May 2014 Arlene Rofe General Manager Disclaimer This presentation has been prepared by Evolution Mining Limited ( Evolution Mining ) and consists of slides for a presentation concerning the
More informationFor personal use only
ASX Announcement 2 December 2013 Positive scoping study confirms economic viability of Bird-in-Hand Gold Project HIGHLIGHTS Scoping Study confirms technical and economic viability of the Birdin-Hand Gold
More informationAccelerated Exploration
Mandalay Resources Corporation Increases Mineral Resources and Replaces Reserves in Augusta East & West Lodes and Accelerates Drilling at its Costerfield Gold-Antimony Mine, Australia TORONTO, ON, April
More informationThe Model for Tungsten
The Model for Tungsten Presented by: Paul Berndt Tungsten Mining NL Managing Director October 17 th 2012 29/10/2012 1 Disclaimer This presentation has been prepared by Tungsten Mining NL ( Tungsten Mining
More informationCarbine Tungsten Limited Mt Carbine Tungsten Project
Carbine Tungsten Limited Mt Carbine Tungsten Project Jim Morgan CEO & Managing Director Mt Carbine Tungsten Mine - Location Mt Carbine Tungsten Project Mt Carbine Mining Leases cover ~367 hectares. Historical
More informationNEWS RELEASE GREAT PANTHER SILVER ACHIEVES SEVERAL PRODUCTION RECORDS IN THIRD QUARTER 2013
October 0, 203 For Immediate Release TSX: GPR NYSE MKT: GPL NEWS RELEASE GREAT PANTHER SILVER ACHIEVES SEVERAL PRODUCTION RECORDS IN THIRD QUARTER 203 GREAT PANTHER SILVER LIMITED (TSX: GPR; NYSE MKT:
More informationOZ Minerals Update. Geoff Deans, Group Manager Social Performance. A modern mining company 29 AUGUST 2018
OZ Minerals Update Geoff Deans, Group Manager Social Performance 29 AUGUST 2018 A modern mining company Disclaimer This presentation has been prepared by OZ Minerals Limited (OZ Minerals) and consists
More informationTHIRD QUARTER REPORT 14 OCTOBER 2014
THIRD QUARTER REPORT 14 OCTOBER 2014 DISCLAIMER This presentation has been prepared by OZ Minerals Limited ( OZ Minerals ) and consists of written materials/slides for a presentation concerning OZ Minerals.
More informationFor personal use only
Bulletin Resources is the 100% owner of the Nicolson s Gold Project located near Halls Creek in the Kimberley region of Western Australia. The project has a combined open pit and underground Mineral Resource
More informationSILVERCORP REPORTS FINANCIAL AND OPERATING RESULTS FOR THE FISCAL YEAR AND FOURTH QUARTER ENDED MARCH
NEWS RELEASE Trading Symbol: TSX: SVM NYSE: SVM SILVERCORP REPORTS FINANCIAL AND OPERATING RESULTS FOR THE FISCAL YEAR AND FOURTH QUARTER ENDED MARCH 31, 2015 VANCOUVER, British Columbia May 21, 2015 Silvercorp
More informationPositive Lerokis Copper Recovery Testwork
For ASX Market Release: 20 November 2017 Positive Lerokis Copper Recovery Testwork HIGHLIGHTS Positive copper recovery results have been received from diamond drill core samples from Lerokis, the next
More informationSmarTone Telecommunications Holdings Limited
SmarTone Telecommunications Holdings Limited FY18 Interim Results Presentation For the six months ended 31 December 2017 13 February 2018 1 Disclaimer It is not the intention to provide, and no reliance
More informationMORANBAH NORTH MINE. Analyst & Investor Site Visit Australia 28 October 2011
MORANBAH NORTH MINE Analyst & Investor Site Visit Australia 28 October 2011 DISCLAIMER Disclaimer: This presentation has been prepared by Anglo American plc ( Anglo American ) and comprises the written
More informationChampion Bear Announces Drilling Results from Plomp Farm West Gold project
Champion Bear Announces Drilling Results from Plomp Farm West Gold project Drill Hole PF18-98 records multiple intersections including 1.0 m at 3.65 Au, combined 6.0 m equal to or greater than 1.0 Au,
More informationSyrah Resources Annual General Meeting. Shaun Verner, Managing Director and CEO 17 May 2018
Syrah Resources Annual General Meeting Shaun Verner, Managing Director and CEO 17 May 2018 1 Disclaimer This presentation is for information purposes only. Neither this presentation nor the information
More informationASX ANNOUNCEMENT. CMP to Purchase Additional Stake in Productora for US$1.5 Million. Sprott Loan to be Reduced and Extended by 12 Months
ASX ANNOUNCEMENT Wednesday 18 th May 2016 CMP to Purchase Additional Stake in Productora for US$1.5 Million Sprott Loan to be Reduced and Extended by 12 Months Hot Chili Limited (ASX Code: HCH) is pleased
More informationNew Zealand Energy Corp.
New Zealand Energy Corp. Investor Business Update November 2016 CAUTIONARY NOTES FORWARD-LOOKING INFORMATION This document contains certain forward-looking information and forward-looking statements within
More informationAdelaide Brighton Ltd Macquarie Australia Conference 2 May 2012
Adelaide Brighton Ltd Macquarie Australia Conference 2 May 2012 Adelaide Brighton Ltd Disclaimer The following presentation has been prepared by Adelaide Brighton Limited ACN 007 596 018 for information
More information2017 annual general meeting. 27 October 2017
2017 annual general meeting 27 October 2017 Andrew Reitzer Chairman 2 Board of directors Julian Ogrin Maria Martin 3 Board of directors Jodie Sangster Thorsten Kraemer 4 Board of directors Rolf Hansen
More informationRichmont Mines Provides a Status Update on an Expansion Case Preliminary Economic Assessment for the Island Gold Mine
NEWS RELEASE Richmont Mines Provides a Status Update on an Expansion Case Preliminary Economic Assessment for the Island Gold Mine 11/1/2016 Potential for Increased Production to 1,100 Tonnes per Day with
More information121 MINING INVESTMENT CONFERENCE HONG KONG
ASX / MEDIA RELEASE 23 April 2018 121 MINING INVESTMENT CONFERENCE HONG KONG St George Mining Limited (ASX: SGQ) ( St George or the Company ) is participating at the 121 Mining Investment Conference in
More informationN E W S R E L E A S E
ASM: TSX/NYSE American Avino Silver & Gold Mines Ltd. T (604) 682 3701 Suite 900-570 Granville Street F (604) 682 3600 Vancouver, BC V6C 3P1 www.avino.com N E W S R E L E A S E April 17, AVINO ANNOUNCES
More informationSierra Metals Exploration Update Call
Sierra Metals Exploration Update Call October 5, 2017 TSX SMT NYSE AMERICAN: SMTS BVL SMT Forward Looking Statements Disclaimer Certain statements in this presentation constitute forward-looking information
More information