1 Environmental and social impacts of smallscale hydropower: Issues and Challenges Glenn Morgan (LCSEN) World Bank Water Week February 18, 2009

2 Presentation objectives Review the nature and scale of environmental and social impacts associated with small-scale hydropower Identify emerging issues with regard to small scale hydro especially for run-of-river and IPP projects Recommend good practices when preparing, appraising and supervising such projects

3 Why focus on small-scale hydro? Small-scale hydro may be a desirable and growth segment of the energy generation among some Bank clients (e.g. Honduras) Projects are assumed to represent *green* or *low-impact* energy alternatives Lower or more acceptable environmental and social costs than alternative fossil-fuel burning projects Environmental and social benefits outweigh the environmental and social costs Scale of works increases potential sustainability by reducing or eliminating risks normally associated with large scale hydro Projects can be brought on-line more rapidly and expect to benefit from a streamlined review and processing requirements

4 What is small scale? Definitions are somewhat arbitrary but generally considered to be up to 30 MW but may be as high as high as 50 MW Projects do not trigger the ICOLD criteria for large dams (15 m. / 1 million cum. storage etc.) Intended to supplement the existing grid and do not involve long incremental transmission lines They are typically run-of-river design and do not require reservoir storage capacity Typically do not involve large or complex resettlement or land acquisition

5 What is run-of-river? Typical configuration of a run-of-river project

6 Observations about small hydro In general, these projects function well and can provide electricity with low impacts when properly designed and managed However, there are some systemic issues which may occur even in the smallest hydro projects These issues - if not addressed - could create risks for the sustainability of the project as well as reputational or other political risks Companies are carrying out their responsibilities but face risks with respect to capacity and resources especially in dealing with host communities

7 Social and environmental impacts in small scale projects At and above the dams or barriers Below the dam especially in the diversion / dewatered river reaches From associated infrastructure access roads, borrow pits and transmission lines Operational impacts affecting timing and volumes of river flow Cumulative impacts with multiple dams and other projects in the same watershed Land acquisition or physical resettlement Land and resource tenure including access to water resources Community development, livelihood support or expectations of sharing in benefits

8 La Esperanza - Project Description 13.5 MW IPP developed in three phases Phase 1A 500 KW; Phase 1B 1 MW; Phase 2 12 MW Project involves construction of 4 small dams; 3 retention ponds; powerhouse; underground penstock; access roads; work camp site; project offices. Project has been operational (Phase 1A) since 2003 Now considering a fourth phase further downstream

9 La Esperanza - Project Context Located within the Intibuca River basin near towns of Intibuca and La Esperanza, Honduras Area of influence is sparsely settled with important existing environmental values. Populated by Lenca people Host communities experience high incidence of poverty Project situated on privately owned company lands Environmental license and ERPA specifies E&S requirements but government capacity to monitor or enforce is limited

10

11

12

13 La Esperanza - Project E&S Issues Works undertaken in remote but sensitive location 10 km of the Intibuca river s upper catchment dewatered at various times of the year Mitigation plan heavily oriented to provision of community services and reforestation Limited characterization of construction impacts

14 La Esperanza - Project E&S Issues Project received environmental license and was required to develop EMP as part of ERPA but specific commitments are not well understood by the community at large NGO community is generally favorable towards the project but feel company lacks transparency Monitoring of management plans by local authorities is weak Riparian flows and water quality are not monitored Water use rights on tributary streams could become an important issue

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32 Summary Need to consider all impacts, especially construction related impacts of ancillary works such as roads Need for stakeholder involvement and improved communications. Specific requirements of EMP and CDP may not be well understood in the community at large Need to support capacity building of supporting agencies. Need to consider beyond the project counterpart. Local government units are often left to carry out monitoring and compliance tasks. Need for better coordination and dialogue. Project often require inter-agency coordination

33 Summary Need to limit project E&S liabilities. Importance of developing clear agreements with specific annual work plans, budget resources and monitorable outcomes specified. Need to clarify the process requirements. Companies are often unclear as to what is required due to lack of legal framework, regulations, clarity of institutional roles and responsibilities Desire for efficient review process. Project developers desire more rapid and efficient licensing procedures

34 Summary Project proponents, often small IPP, may not have sufficient experience or resources to successfully implement programs Construction and operational delays may threaten a company s financial viability and ability to meet E&S commitments Even small projects may face adverse local attitudes regarding transparency, communications, community development support. Managing community expectations can be difficult and challenging

35 Summary Social and environmental context of any project is important. No two small hydro projects are alike Installed capacity is generally a poor indicator of a project s potential impacts Small-scale and run-of-river does not necessarily mean *no* or even *low* impact Projects, though small to us, can be locally important and can raise controversies which need to be managed

National Policy on Environmental and Social Sustainability of the Hydropower Sector in Lao PDR

National Policy on Environmental and Social Sustainability of the Hydropower Sector in Lao PDR National Policy on Environmental and Social Sustainability of the Hydropower Sector in Lao PDR By Xaypaseuth PHOMSOUPHA Deputy Director General Department of Energy Promotion and Development Ministry of

More information

GEIDCO Summit 22 February Designing collaborative and adaptive approaches to river basin development

GEIDCO Summit 22 February Designing collaborative and adaptive approaches to river basin development GEIDCO Summit 22 February 2017 60 50 40 30 20 10 0 Designing collaborative and adaptive approaches to river basin development International Hydropower Association Origin Created in 1995, under the auspices

More information

COMPLIANCE APPRAISAL: SUMMARY OF RESULTS

COMPLIANCE APPRAISAL: SUMMARY OF RESULTS May 16, 2016 Office of the Compliance Advisor Ombudsman (CAO) COMPLIANCE APPRAISAL: SUMMARY OF RESULTS Enso Albania (IFC Project #30979) Albania On September 28, 2011, IFC approved an early stage equity

More information

A CITIZEN S GUIDE. Awareness Raising on Hydropower Project Development and EIA for Citizens (part I)

A CITIZEN S GUIDE. Awareness Raising on Hydropower Project Development and EIA for Citizens (part I) A CITIZEN S GUIDE Awareness Raising on Hydropower Project Development and EIA for Citizens (part I) Prepared by Lasha Gurgenidze and Tamar Mtvarelidze with Dr. Shivcharn S. Dhillion May, 2014 Content of

More information

UNRAVELING THE MYRAID OF STANDARDS AND TOOLS

UNRAVELING THE MYRAID OF STANDARDS AND TOOLS UNRAVELING THE MYRAID OF STANDARDS AND TOOLS HYDRO POWER DEVELOPMENT IN MEKONG REGION: CYCLING THROUGH FROM POLICY TO IMPLEMENTATION WORKSHOP SEPTEMBER 12-13, 2013 Basin Wide National regulations Project

More information

Vishnugad Pipalkoti Hydropower Project Tehri Hydro Development Corporation Uttarakhand, India

Vishnugad Pipalkoti Hydropower Project Tehri Hydro Development Corporation Uttarakhand, India Vishnugad Pipalkoti Hydropower Project Tehri Hydro Development Corporation Uttarakhand, India World Bank Water Week February 17, 2009 Pyush Dogra (Environmental Specialists) & Daryl Fields (Senior Water

More information

Some aspects of the sediment transit on the Mekong river in relation with hydropower development

Some aspects of the sediment transit on the Mekong river in relation with hydropower development Some aspects of the sediment transit on the Mekong river in relation with hydropower development Daniel Loudière Société Hydrotechnique de France A presentation in three parts - the situation when starting

More information

SUMMARY 2013 EDITION

SUMMARY 2013 EDITION SUMMARY 2013 EDITION RSAT Joint Initiative on Rapid Basin-wide Hydropower Sustainability Assessment Tool PART 1: OVERVIEW OF THE RSAT The RSAT is designed as an integrative tool to assess hydropower development

More information

Environmental and Social Impact Assessment for Rogun Hydro Power Plant

Environmental and Social Impact Assessment for Rogun Hydro Power Plant Environmental and Social Impact Assessment for Rogun Hydro Power Plant Environmental and Social Impacts July 14-19, 2014 Content Project History Purpose and Scope The Project Area The Project The Project

More information

Nam Theun 2. TNC workshop April 2014

Nam Theun 2. TNC workshop April 2014 Nam Theun 2 1 TNC workshop April 2014 The Hydropower Project Build, Operate, Transfer 25 year concession for Nam Theun Power Co. US$1.3 Billion cost, financed by 27 parties (1/3 Equity; 2/3 debt) Generating

More information

Programme of Activities (PoA) for Sustainable Renewable Energy Power in Papua New Guinea (PNG)

Programme of Activities (PoA) for Sustainable Renewable Energy Power in Papua New Guinea (PNG) Programme of Activities (PoA) for Sustainable Renewable Energy Power in Papua New Guinea (PNG) The RE CDM PoA in PNG Programme of Activities (PoA) for Sustainable RE Power in Papua New Guinea (PNG) envisages

More information

Safeguard Requirements And the Framework Process

Safeguard Requirements And the Framework Process Safeguard Requirements And the Framework Process The World Bank Europe & Central Asia Region Biskek,Tblisi March/April 2008 1 Role of Bank and Borrower Bank Screens and Sets EA Category Advises Borrower

More information

ENVIRONMENT ASSESSMENT TOOLS FOR IMPROVING THE SUSTAINABILITY OF DEVELOPMENT IN THE MEKONG REGION

ENVIRONMENT ASSESSMENT TOOLS FOR IMPROVING THE SUSTAINABILITY OF DEVELOPMENT IN THE MEKONG REGION ENVIRONMENT ASSESSMENT TOOLS FOR IMPROVING THE SUSTAINABILITY OF DEVELOPMENT IN THE MEKONG REGION INTRODUCTION This brief introduces the main environmental assessment tools now used in the Mekong region

More information

Hydropower & Dams Services

Hydropower & Dams Services Hydropower & Dams Services We represent a world-class concentration of hydropower and dam expertise. Since 1920, we have designed hundreds of new hydropower and dams globally, producing clean reliable

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE. Rural Electrification and Transmission Interconnection Project (RETP) Region

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE. Rural Electrification and Transmission Interconnection Project (RETP) Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.:47622 Project Name Rural

More information

Case Presentation: Law for Benefit sharing on hydropower projects in Viet Nam - & - Linking national benefit sharing to Transboundary benefit sharing

Case Presentation: Law for Benefit sharing on hydropower projects in Viet Nam - & - Linking national benefit sharing to Transboundary benefit sharing Case Presentation: Law for Benefit sharing on hydropower projects in Viet Nam - & - Linking national benefit sharing to Transboundary benefit sharing Transboundary Cooperation Workshop Vientiane 20-22

More information

SUSTAINABLE HYDROPOWER DEVELOPMENT A NORWEGIAN-GEORGIAN COOPERATION PROGRAM. A Citizen s Guide. Communication and Hydropower EIA

SUSTAINABLE HYDROPOWER DEVELOPMENT A NORWEGIAN-GEORGIAN COOPERATION PROGRAM. A Citizen s Guide. Communication and Hydropower EIA Communication and Hydropower EIA September, 2014 Dhillion, S.S. and Bakhtadze, M. 2014. A Citizen s Awareness Guide: Communication and Hydropower EIA. Sustainable Hydropower Development in Georgia. Report

More information

Pumped Storage Profile

Pumped Storage Profile Pumped Storage Profile Table of Contents Brookfield Asset Management Introduction Brookfield Renewable Power Introduction Pumped Storage Profile Brookfield Pumped Storage Projects Conclusion 2 Brookfield

More information

Meeting in Yichang China 25 Oct 2008 By Lawrence Haas Independent Consultant, UK

Meeting in Yichang China 25 Oct 2008 By Lawrence Haas Independent Consultant, UK HSAF Briefing On Benefit Sharing / Additional Benefits Meeting in Yichang China 25 Oct 2008 By Lawrence Haas Independent Consultant, UK Key Points 1. Larger issue - financing is key to long-term environment

More information

COMPLIANCE REPORT ASSESSING APPLICATION OF ARTICLE 11 b (6) OF EMISSIONS TRADING DIRECTIVE TO HYDROELECTRIC PROJECT ACTIVITIES EXCEEDING 20 MW

COMPLIANCE REPORT ASSESSING APPLICATION OF ARTICLE 11 b (6) OF EMISSIONS TRADING DIRECTIVE TO HYDROELECTRIC PROJECT ACTIVITIES EXCEEDING 20 MW COMPLIANCE REPORT ASSESSING APPLICATION OF ARTICLE 11 b (6) OF EMISSIONS TRADING DIRECTIVE TO HYDROELECTRIC PROJECT ACTIVITIES EXCEEDING 20 MW Section 1: Description of the project (Final Version of 17

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE. Rural Electrification and Transmission Interconnection Project (RETP) Region

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE. Rural Electrification and Transmission Interconnection Project (RETP) Region PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.:45460 Project Name Rural Electrification and Transmission Interconnection Project (RETP) Region EAST ASIA AND PACIFIC Sector Energy Project ID

More information

Project Name PROJECT INFORMATION DOCUMENT (PID) Nepal Village Micro Hydro Carbon Offset Project. South Asia SASSD P095978

Project Name PROJECT INFORMATION DOCUMENT (PID) Nepal Village Micro Hydro Carbon Offset Project. South Asia SASSD P095978 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name Region Sector Project ID Borrower(s) Implementing Agency PROJECT INFORMATION

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE. Kabeli A Hydroelectric Project. Component 2: Ministry of Energy

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE. Kabeli A Hydroelectric Project. Component 2: Ministry of Energy Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Kabeli A Hydroelectric

More information

Glenfarg Hydropower Development. Hydro-potential in the Glenfarg area

Glenfarg Hydropower Development. Hydro-potential in the Glenfarg area Client: Glenfarg Renewable Energy Association Contract Start Date: May 2014 Report Reference: Contributors: Checked by: MNV/GF001/2011 Dr R C Johnson Rita Day Document Revisions: Status Version Date Final

More information

Integrity issues in Hydropower Development: Hydropower Development in Sikkim. Neena Rao, PhD. June 6th 2013

Integrity issues in Hydropower Development: Hydropower Development in Sikkim. Neena Rao, PhD. June 6th 2013 Integrity issues in Hydropower Development: Hydropower Development in Sikkim Neena Rao, PhD June 6th 2013 Neena@saciwaters.org Mountainous regions population engaged in subsistence farming & scarce land

More information

Social and Environmental Standards for Large Dams

Social and Environmental Standards for Large Dams Social and Environmental Standards for Large Dams Comparing the Strategic Priorities and Policy Principles of the World Commission on Dams, the Sustainability Guidelines and Sustainability Assessment Protocol

More information

IWRM And Water Planning in Gurara River Basin Engr. Abdul-Qadir D. Aliyu

IWRM And Water Planning in Gurara River Basin Engr. Abdul-Qadir D. Aliyu IWRM And Water Planning in Gurara River Basin Engr. Abdul-Qadir D. Aliyu National Water Resources Institute, Kaduna Nigeria. Outline Introduction IWRM Water Planning and Allocation Background Study Area

More information

Outline. Hydro potential in CDM Issues in new hydro projects Case studies Next step? Short brief on EcoSecurities

Outline. Hydro potential in CDM Issues in new hydro projects Case studies Next step? Short brief on EcoSecurities The Clean Development Mechanism: Emission down, profit up Paul Butarbutar Senior Project Manager EcoSecurities Indonesia EcoSecurities Group plc Outline Hydro potential in CDM Issues in new hydro projects

More information

The First Mekong River Commission Summit 2010

The First Mekong River Commission Summit 2010 15th Anniversary 5 April 1995 5 April 2010 The First Mekong River Commission Summit 2010 The Mekong Basin as a source of economic prosperity The water resources of the 795,000 square kilometer Mekong Basin

More information

Meeting Vietnam s Energy Demands in a Sustainable Way

Meeting Vietnam s Energy Demands in a Sustainable Way TRUNG SON HYDROPOWER PROJECT Meeting Vietnam s Energy Demands in a Sustainable Way Photo by: World Bank 1 Photo by: Mai Ky/World Bank, 2012 OVERVIEW Trung Son Hydropower Project (TSHPP) is a US$411.57

More information

Glimpse of Hydro Projects Development in Nepal

Glimpse of Hydro Projects Development in Nepal Glimpse of Hydro Projects Development in Nepal Total theoretical hydroelectricity potential of the country : 83,000 MW Economically feasible : 42,000 MW (ADB and ICIMOD, 2006) Of the total installed 829

More information

Energy Industry Resources Society Economy Environment Health & Safety Risk Compliance Sustainability The world s leading sustainability consultancy

Energy Industry Resources Society Economy Environment Health & Safety Risk Compliance Sustainability The world s leading sustainability consultancy Energy Industry Resources Society Economy Environment Health & Safety Risk Compliance Sustainability Managing Environmental and Social Risks of Large Hydro Power Projects: The Business Case and Keys for

More information

AN OVERVIEW OF TANAHU HYDROPOWER PROJECT. Presented by: Achyut Ghimire TANAHU HYDROPOWER PROJECT TRADE TOWER, THAPATHALI, KATHMANDU

AN OVERVIEW OF TANAHU HYDROPOWER PROJECT. Presented by: Achyut Ghimire TANAHU HYDROPOWER PROJECT TRADE TOWER, THAPATHALI, KATHMANDU AN OVERVIEW OF TANAHU HYDROPOWER PROJECT Presented by: Achyut Ghimire TANAHU HYDROPOWER PROJECT TRADE TOWER, THAPATHALI, KATHMANDU Date: June 1, 2016 OUT LINE OF THE PRESENTATION INTRODUCTION OBJECTIVE

More information

TECHNICAL ASSISTANCE DESCRIPTION, COST ESTIMATES AND OUTLINE TERMS OF REFERENCE

TECHNICAL ASSISTANCE DESCRIPTION, COST ESTIMATES AND OUTLINE TERMS OF REFERENCE Greater Mekong Subregion Nam Ngum 3 Hydropower Project (RRP LAO 41385) Supplementary Appendix 5 TECHNICAL ASSISTANCE DESCRIPTION, COST ESTIMATES AND OUTLINE TERMS OF REFERENCE Strengthening Biodiversity

More information

Aquatic habitat offset to address cumulative impacts in the context of hydropower development

Aquatic habitat offset to address cumulative impacts in the context of hydropower development Aquatic habitat offset to address cumulative impacts in the context of hydropower development Special IAIA Symposium on Biodiversity & Ecosystem Services in Impact Assessment Aquatic Biodiversity and Ecological

More information

Concept of WSM Country Status on Watershed Management Planning Institution and Legislation relevant to WSM in Laos Application of Watershed Management

Concept of WSM Country Status on Watershed Management Planning Institution and Legislation relevant to WSM in Laos Application of Watershed Management Watershed Management in the Lao PDR Dr. Khamla Phanvilay Assoc. Prof. Dr. Sithong Thongmanivong Faculty of Forestry National University of Laos 1 Outlines of Presentation Concept of WSM Country Status

More information

Defining the boundaries of a project: Where does Bank accountability stop? Lessons from Panel cases and beyond

Defining the boundaries of a project: Where does Bank accountability stop? Lessons from Panel cases and beyond The Inspection Panel Defining the boundaries of a project: Where does Bank accountability stop? Lessons from Panel cases and beyond Alf Jerve, Chairperson Presentation at the World Bank Spring Meetings,

More information

Svarychiv small hydropower plant project non-technical summary

Svarychiv small hydropower plant project non-technical summary Svarychiv small hydropower plant project non-technical summary 1 Introduction 01 Dec 2015 This document provides a non-technical overview of the proposed development plans of private company Hydropower

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC5832. Date ISDS Prepared/Updated: 12/22/2010 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC5832. Date ISDS Prepared/Updated: 12/22/2010 I. BASIC INFORMATION. A. Basic Project Data Date ISDS Prepared/Updated: 12/22/2010 I. BASIC INFORMATION A. Basic Project Data INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC5832 Country: Uruguay Project ID: P110965 Project Name: Sustainable

More information

WEBINAR 3 AGENDA ITEM 5 HIGH PROFILE AND CROSS- CUTTING ISSUES

WEBINAR 3 AGENDA ITEM 5 HIGH PROFILE AND CROSS- CUTTING ISSUES WEBINAR 3 AGENDA ITEM 5 HIGH PROFILE AND CROSS- CUTTING ISSUES TEXT FROM DRAFT PROTOCOL: High Profile and Cross Cutting Issues Table 13 lists some high profile and cross-cutting issues that are not apparent

More information

JCM Power. The Environmental and Social Governance (ESG) Policy

JCM Power. The Environmental and Social Governance (ESG) Policy JCM Power The Environmental and Social Governance (ESG) Policy 21 St. Clair Avenue East Suite 500 Toronto, Ontario, Canada M4T 1L9 1-647-447-1662 info@jcmpower.ca Contents 1. Our Corporate Vision and Mission...

More information

Surface Water Management Strategy

Surface Water Management Strategy Interim Report for the Surface Water Management Strategy WHAT WE HEARD SUMMARY November 2012 INTRODUCTION The surface water management strategy will outline a strategic plan to improve the management of

More information

Hydropower Development, Mitigation and Best Practices in Ontario

Hydropower Development, Mitigation and Best Practices in Ontario April 2014 Hydropower Development, Mitigation and Best Practices in Ontario Imagine the result Contents Introduction 3 Construction Mitigation 5 Some General Lessons 7 Integration of EIA and Construction

More information

Research on Prospect and Problem for Hydropower Development of China

Research on Prospect and Problem for Hydropower Development of China Available online at www.sciencedirect.com Procedia Engineering 28 (2012) 677 682 2012 International Conference on Modern Hydraulic Engineering Research on Prospect and Problem for Hydropower Development

More information

British Hydropower Association

British Hydropower Association British Hydropower Association The leading trade membership association that solely represents the interests of the UK hydropower industry (from micro to large scale) Operates in the UK and overseas Has

More information

Downstream Flow Regimes

Downstream Flow Regimes This guideline expands on the criteria statements in the Hydropower Sustainability Assessment Protocol for the topic, relating to Assessment, Management, Stakeholder Engagement, Conformance/ Compliance

More information

SEMINAR ON CUMULATIVE IMPACT ASSESSMENT & MANAGEMENT

SEMINAR ON CUMULATIVE IMPACT ASSESSMENT & MANAGEMENT SEMINAR ON CUMULATIVE IMPACT ASSESSMENT & MANAGEMENT 29 February 2016 Seminar Agenda Time Item 09.00 Agenda/objectives 09.05 Impact Assessment Toolbox: Situating the CIA 09.15 What is Cumulative Impact

More information

Aquanova Nyzhniy Bystryi small hydropower plant project non-technical summary

Aquanova Nyzhniy Bystryi small hydropower plant project non-technical summary Aquanova Nyzhniy Bystryi small hydropower plant project non-technical summary 1 Introduction This document provides a non-technical overview of Aquanova Development Nyzhniy Bystryi Hydropower Plant project

More information

THE FIRST MEKONG RIVER COMMISSION SUMMIT Hua Hin, Thailand

THE FIRST MEKONG RIVER COMMISSION SUMMIT Hua Hin, Thailand THE FIRST MEKONG RIVER COMMISSION SUMMIT Hua Hin, Thailand Excellencies, Ladies and Gentlemen, Development Partners Group Statement 5 April 2010 The Development Partners congratulate the Heads of the Governments

More information

Report No.: ISDSA14479

Report No.: ISDSA14479 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized 0 o O Date ISDS Prepared/Updated: 16-Nov-2015 INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL

More information

ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK. for the. Partial Risk Guarantees Project for Independent Power Producers in Kenya DRAFT

ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK. for the. Partial Risk Guarantees Project for Independent Power Producers in Kenya DRAFT ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK for the Partial Risk Guarantees Project for Independent Power Producers in Kenya DRAFT May 2011 INTRODUCTION The World Bank, through IDA funding, is proposing

More information

Tri An Hydropower Plant in the South Vietnam, 400 MW power capacity, 2.7 km 3 water storage reservoir

Tri An Hydropower Plant in the South Vietnam, 400 MW power capacity, 2.7 km 3 water storage reservoir Tri An Hydropower Plant in the South Vietnam, 400 MW power capacity, 2.7 km 3 water storage reservoir The ICOLD Committee on Dams for Hydroelectric Energy - Some topics discussed at the Committee Meeting

More information

Our Social License to Operate: The SN Aboitiz Power Experience Philippines. Mike Hosillos Presentation to ICH

Our Social License to Operate: The SN Aboitiz Power Experience Philippines. Mike Hosillos Presentation to ICH Our Social License to Operate: The SN Aboitiz Power Experience Philippines Mike Hosillos Presentation to ICH Overview The Philippines Energy Situation About SN Aboitiz Power Group Our Social License to

More information

UNRAVELING THE MYRAID OF STANDARDS AND TOOLS

UNRAVELING THE MYRAID OF STANDARDS AND TOOLS UNRAVELING THE MYRAID OF STANDARDS AND TOOLS February 29, 2016 STANDARDS & TOOLS OVERVIEW Standard Tool Project level Basin Wide National regulations IFC Performance Standards Equator Principles Safeguard

More information

BURUNDI, RWANDA, TANZANIA

BURUNDI, RWANDA, TANZANIA Financing water for growth in Africa Rusumo Falls: water for power generation and multipurpose use, Burundi, Rwanda, Tanzania Summary The Regional Rusumo Falls Hydroelectric and Multipurpose Project is

More information

Bob Gundersen, PSNH Hydro Manager

Bob Gundersen, PSNH Hydro Manager PSNH s Renewable Hydro Power Fleet Bob Gundersen, PSNH Hydro Manager 1 PSNH is a Regulated Public Utility serving ~480,000 customers in New Hampshire. Its generation capacity plays a small but important

More information

1. Background Provisioning Regulating: Cultural:

1. Background Provisioning Regulating: Cultural: IN PARTNERSHIP WITH EXECUTIVE SUMMARY The Myanmar hydropower sector, in the early stages of development, has the opportunity to develop sustainably by balancing electricity generation with environmental

More information

Power Summit Presentation

Power Summit Presentation Government Of Nepal Ministry of Energy Power Summit Presentation 1st June 2016 Presented by: Moti Bahadur Kunwar Executive Director Web: www.nhpdc.gov.np Email: info@nhpdc.gov.np GON has Constituted Nalsing

More information

STAKEHOLDERS, PARTICIPATION AND BENEFIT SHARING: APPROACH TO MIDDLE YEYWA

STAKEHOLDERS, PARTICIPATION AND BENEFIT SHARING: APPROACH TO MIDDLE YEYWA STAKEHOLDERS, PARTICIPATION AND BENEFIT SHARING: APPROACH TO MIDDLE YEYWA ADVANCING SUSTAINABILITY IN RENEWABLE ENERGY Yangon, October 2018 Dr. Stephen Sparkes Vice President, International Power 1 CONTENTS

More information

Developing Albania s Hydroelectric Potential towards the Networks of the Future

Developing Albania s Hydroelectric Potential towards the Networks of the Future Developing Albania s Hydroelectric Potential towards the Networks of the Future John Chadjivassiliadis Secretary General, IENE 1 Good prospects for hydro and electricity sector in Albania The development

More information

Inter-office memo. Bear Creek Reservoir. Elliot Headpond. Jordan Generating Tailrace. Diversion Reservoir. Maximum Normal Elevation (m) Minimum Normal

Inter-office memo. Bear Creek Reservoir. Elliot Headpond. Jordan Generating Tailrace. Diversion Reservoir. Maximum Normal Elevation (m) Minimum Normal Inter-office memo TO: File DATE: 8 November 2007 FROM: Engineering FILE: GENMIS08 NRGPLN SUBJECT: Jordan River Pumped Storage 1.0 Introduction The British Columbia Utility Commission has directed BC Hydro

More information

Rapid Hydropower Assessment Model Identify Hydroelectric Sites Using Geographic Information Systems

Rapid Hydropower Assessment Model Identify Hydroelectric Sites Using Geographic Information Systems ABSTRACT Rapid Hydropower Assessment Model Identify Hydroelectric Sites Using Geographic Information Systems By Ron Monk, M.Eng., P.Eng.; Stefan Joyce, P.Eng.; and Mike Homenuke, P.Eng. Kerr Wood Leidal

More information

Impact of the Controlled Activities Regulations on Dam Construction, Maintenance and Operation in Scotland

Impact of the Controlled Activities Regulations on Dam Construction, Maintenance and Operation in Scotland Impact of the Controlled Activities Regulations on Dam Construction, Maintenance and Operation in Scotland C. W. BERRY, GHD Pty, Australia (formerly of W A Fairhurst and Partners) K. M. H. BARR, W. A.

More information

Review and Update of the World Bank s Environmental and Social Safeguard Policies Phase 3 Feedback Summary

Review and Update of the World Bank s Environmental and Social Safeguard Policies Phase 3 Feedback Summary Review and Update of the World Bank s Environmental and Social Safeguard Policies Phase 3 Feedback Summary Date: January 28, 2016 Location (City, Country): Jakarta, Indonesia Audience: Civil Society Organizations

More information

Trung Son Hydropower. Project Overview and Description

Trung Son Hydropower. Project Overview and Description Trung Son Hydropower Project Overview and Description (As of February 2011) Overview and Objective The Trung Son is a $ 411.57 million medium-sized hydropower and development project located in the Hoa

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE ELECTRICTY TRANSMISSION

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE ELECTRICTY TRANSMISSION Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE ELECTRICTY TRANSMISSION

More information

Hydropower Sustainability Assessment Protocol Section III Trail ESKOM. Ingula Pumped Storage Scheme. November 2009

Hydropower Sustainability Assessment Protocol Section III Trail ESKOM. Ingula Pumped Storage Scheme. November 2009 Hydropower Sustainability Assessment Protocol Section III Trail ESKOM Ingula Pumped Storage Scheme November 2009 Assessor: Rob Griffin Date: 2009-11-25 Table of Contents 1 Introductory Information... 3

More information

ESIAs for Large Scale Infrastructure: Energy

ESIAs for Large Scale Infrastructure: Energy ESIAs for Large Scale Infrastructure: Energy GEMS Environmental Compliance- ESDM Training Series Kabul July / August 2016 8/1/2016 1 SESSION OBJECTIVES: Understand importance of construction activities

More information

Low Impact Hydropower Institute 34 Providence Street Portland, ME Tel. (207) Fax (206)

Low Impact Hydropower Institute 34 Providence Street Portland, ME Tel. (207) Fax (206) Low Impact Hydropower Institute 34 Providence Street Portland, ME 04103 Tel. (207) 773-8190 Fax (206) 984-3086 www.lowimpacthydro.org LOW IMPACT HYDROPOWER QUESTIONNAIRE E. LOW IMPACT HYDROPOWER QUESTIONNAIRE

More information

Trishuli River Case Study

Trishuli River Case Study Moving from a Project-level to River Basin-level CIA: Trishuli River Case Study January 2018 Insert then choose Picture select your picture. Right click your picture and Send to back. Trishuli River Basin

More information

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized o Date ISDS Prepared/Updated: 19-Jan-2016 INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan 1.Name of the Project Country: The Republic of Indonesia Project: Upper Citarum Basin Flood Management Sector Loan Loan Agreement: March 28,

More information

Environmental Safeguards Framework (ESF)

Environmental Safeguards Framework (ESF) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Vietnam RENEWABLE ENERGY DEVELOPMENT PROJECT Environmental Safeguards Framework (ESF)

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY

SECTOR ASSESSMENT (SUMMARY): ENERGY SECTOR ASSESSMENT (SUMMARY): ENERGY Country Partnership Strategy: Nepal, 2013-2017 A. Overview 1. Nepal has long recognized the development of its large hydropower potential as an important cornerstone

More information

Appendix C: Flow Estimation and Measurement Techniques of the Scenic Rivers Monitoring Program. Ungaged Stream Flow Estimation

Appendix C: Flow Estimation and Measurement Techniques of the Scenic Rivers Monitoring Program. Ungaged Stream Flow Estimation Appendix C: Flow Estimation and Measurement Techniques of the Scenic Rivers Monitoring Program Eric Wentz and Robert Limbeck Ungaged Stream Flow Estimation Two USGS computer applications were used by DRBC

More information

Guiding Principles on Sustainable Hydropower Development in the Danube River Basin

Guiding Principles on Sustainable Hydropower Development in the Danube River Basin Guiding Principles on Sustainable Hydropower Development in the Danube River Basin Lead Countries : Austria, Romania, Slovenia in the frame of the International Commission for the Danube River Protection

More information

Setting Standards for Sustainable Development. Update and Review of the World Bank s Safeguard Policies

Setting Standards for Sustainable Development. Update and Review of the World Bank s Safeguard Policies Setting Standards for Sustainable Development Update and Review of the World Bank s Safeguard Policies Why the Review? World Bank Group Commitment The World Bank Group is committed to supporting countries

More information

EXECUTIVE SUMMARY. Consultative Committee Report Jordan River Water Use Plan

EXECUTIVE SUMMARY. Consultative Committee Report Jordan River Water Use Plan EXECUTIVE SUMMARY The consultative process was initiated in April 2000 and completed in November 2001. The consultative process follows the steps outlined in the 1996 provincial government Water Use Plan

More information

Zambezi River Basin Challenges and Issues

Zambezi River Basin Challenges and Issues Zambezi River Basin Challenges and Issues GEO-UNESCO Joint Workshop on Earth Observation and Capacity Development for IWRM at River Basins in Africa : 12-14 January 2012, Nairobi, Kenya. Zvikomborero MANYANGADZE

More information

Water and Environment in Tanzania: A Case of Pangani River Basin

Water and Environment in Tanzania: A Case of Pangani River Basin Water and Environment in Tanzania: A Case of Pangani River Basin Andrew Ngereza Mikocheni Agricultural Research Institute P.O. Box 6226 Dar es Salaam Tanzania E-mail: jngereza@yahoo.com Abstract The Pangani

More information

Importance of Small Hydro-Power in Developing Mountainous Country: A Case Study of Nepal Ram Hari Dhakal Civil / Hydropower Engineer, Vidhyut Utpadan

Importance of Small Hydro-Power in Developing Mountainous Country: A Case Study of Nepal Ram Hari Dhakal Civil / Hydropower Engineer, Vidhyut Utpadan Importance of Small Hydro-Power in Developing Mountainous Country: A Case Study of Nepal Ram Hari Dhakal Civil / Hydropower Engineer, Vidhyut Utpadan Company Limited (VUCL) Phone: 977-9851000936, Email:

More information

Small Hydropower Development and Legal Limitations in Thailand

Small Hydropower Development and Legal Limitations in Thailand Small Hydropower Development and Legal Limitations in Thailand Thanaporn Supriyasilp 1,*, Kobkiat Pongput 2, Challenge Robkob 3 1 Department of Civil Engineering, Faculty of Engineering, Chiang Mai University.

More information

1 A.3. Project Description

1 A.3. Project Description Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized ntegrated Safeguards Data Sheet (SDS) Section - Basic nformation Date SDS Preparempdated:

More information

MRC's role in relation to planning and implementation of mainstream dams and its strategic assessment framework

MRC's role in relation to planning and implementation of mainstream dams and its strategic assessment framework MRC's role in relation to planning and implementation of mainstream dams and its strategic assessment framework Jeremy Bird, Chief Executive Officer MRC Secretariat 1 Average flow in Kratie 1960-2004 Flow

More information

Session: For more information:

Session: For more information: Session: For more information: www.hydropower.org/congress Added Value ---- Managing Non- Technical Sustainability Risks Insert then choose Picture select your picture. Right click your picture and Send

More information

Implementation Plan and FAQs for the Guide to Water Act Authorizations Required for Dugouts, Borrow Pits and other types of Pits/Excavations

Implementation Plan and FAQs for the Guide to Water Act Authorizations Required for Dugouts, Borrow Pits and other types of Pits/Excavations Title: Implementation Plan and FAQs for the Guide to Water Act Authorizations Number: Program Name: Approvals Effective Date: June 30, 2016 This document was updated on: ISBN No. 978-1-4601-3034-6 (PDF)

More information

Site 7: Abbeystead Weir, Abbeystead

Site 7: Abbeystead Weir, Abbeystead Site 7: Abbeystead Weir, Abbeystead Site Assessment Report Title Figure 1 Map showing general layout Abbeystead Reservoir is contained by an attractive curved overflow weir, thought to have been built

More information

220 KV TRANSMISSION LINE AKHALTSIKHE-BATUMI

220 KV TRANSMISSION LINE AKHALTSIKHE-BATUMI 220 KV TRANSMISSION LINE AKHALTSIKHE-BATUMI ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT TERMS OF REFERENCE Transmission line Akhalsikhe-Batumi Georgia Terms of Reference for Tender docs and ESIA 2 1 PROJECT

More information

PROJECT IDENTIFICATION FORM (PIF) PROJECT TYPE: Full-sized project THE GEF TRUST FUND

PROJECT IDENTIFICATION FORM (PIF) PROJECT TYPE: Full-sized project THE GEF TRUST FUND PROJECT IDENTIFICATION FORM (PIF) PROJECT TYPE: Full-sized project THE GEF TRUST FUND Re-submission Date: 27 November 2009 PART I: PROJECT IDENTIFICATION INDICATIVE CALENDAR GEF PROJECT ID: 4004 PROJECT

More information

DRAINAGE. Actions for Tomorrow. Drainage. Actions Today

DRAINAGE. Actions for Tomorrow. Drainage. Actions Today DRAINAGE The objective of Manitoba s water drainage policies is to enhance the economic viability of Manitoba s agricultural community through the provision of comprehensively planned drainage infrastructure.

More information

Grafton Hydro, LLC. 55 Union Street, 4 th Floor Boston, MA, USA Tel: Fax: October 9, 2015

Grafton Hydro, LLC. 55 Union Street, 4 th Floor Boston, MA, USA Tel: Fax: October 9, 2015 Grafton Hydro, LLC 55 Union Street, 4 th Floor Boston, MA, 02108-2400 USA Tel: +617-710-1114 Fax: +617-367-3796 October 9, 2015 Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First

More information

Small Hydro based energy generation

Small Hydro based energy generation Workshop on Capacity Development Program for Afghan Women (Clean Energy Access) Small Hydro based energy generation G Anil Head Small Hydro Power Dn., Energy Management Centre, Trivandrum 695017, Kerala,

More information

Yale Hydroelectric Project FERC Project No APPLICATION FOR NEW LICENSE FOR MAJOR PROJECT Volume I

Yale Hydroelectric Project FERC Project No APPLICATION FOR NEW LICENSE FOR MAJOR PROJECT Volume I APPLICATION FOR NEW LICENSE FOR MAJOR PROJECT Volume I Executive Summary Initial Statement Exhibit A - Description of the Project Exhibit B - Project Operation and Resource Utilization Exhibit C - Construction

More information

mtegratedsafeguardsdatasheet APPRAISAL STAGE

mtegratedsafeguardsdatasheet APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared: I. BASIC INFORMATION l. Basic Project Data mtegratedsafeguardsdatasheet

More information

Assessment Report. Complaint filed to the CAO regarding the Uganda Bujagali Hydropower Project

Assessment Report. Complaint filed to the CAO regarding the Uganda Bujagali Hydropower Project Assessment Report Complaint filed to the CAO regarding the Uganda Bujagali Hydropower Project September 2001 Office of the Compliance Advisor/Ombudsman of the International Finance Corporation and the

More information

Albanian Power Exchange - Novelties and Impact

Albanian Power Exchange - Novelties and Impact Albanian Power Exchange - Novelties and Impact Abstract Melisa Panariti University of Durres Gloria Çeno University of Durres This article provides an overview related to the establishment of the Albanian

More information

AC431. Integrated Safeguards Data Sheet (Updated)

AC431. Integrated Safeguards Data Sheet (Updated) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Integrated Safeguards Data Sheet (Updated) Section I - Basic Information Date Prepared/Updated:

More information

Subject Waterpower New Site Release and Development Review

Subject Waterpower New Site Release and Development Review Ontario Ministry of Natural Resources Subject Waterpower New Site Release and Development Review Compiled by Lands and Waters Section Water Resources Policy Draft-March 28, 2004 Date Issued New Replaces

More information

Environmental and Social Impact Assessment and Strategic Environmental and Social Assessment at the World Bank

Environmental and Social Impact Assessment and Strategic Environmental and Social Assessment at the World Bank Environmental and Social Impact Assessment and Strategic Environmental and Social Assessment at the World Bank Agi Kiss Regional Safeguards Advisor, Europe and Central Asia Region The World Bank Economic

More information