C&B Alberta Solar Development ULC

Size: px
Start display at page:

Download "C&B Alberta Solar Development ULC"

Transcription

1 Decision D Newell Solar Power Plant November 15, 2017

2 Alberta Utilities Commission Decision D Newell Solar Power Plant Proceeding Application A001 November 15, 2017 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary, Alberta T2P 3L8 Telephone: Fax: Website:

3 Alberta Utilities Commission Calgary, Alberta Decision D Proceeding Newell Solar Power Plant Application A001 1 Decision summary 1. In this decision, the Alberta Utilities Commission must decide whether to approve an application from to construct and operate a power plant designated as the Newell Solar Project. After considering the record of the proceeding, and for the reasons outlined in this decision, the Commission finds that approval of the project is in the public interest having regard to the social, economic, and other effects of the project, including its effect on the environment. 2 Introduction 2. (CBA) filed an application with the AUC for approval to construct and operate a 13.2-megawatt (MW) power plant, designated as the Newell Solar Project, pursuant to Section 11 of the Hydro and Electric Energy Act. The Newell Solar Project would be located approximately 800 metres south of the city of Brooks in Newell County in the southwest quarter of Section 20, Township 18, Range 14, west of the Fourth Meridian on land owned by the County of Newell. The application was registered on July 4, 2017, as Application A On August 2, 2017, the Commission issued a notice of application for Proceeding The notice was sent directly to potentially affected stakeholders within 2,000 metres of the project. The notice was also published in the Brooks Bulletin on August 15, 2017, posted on the AUC website and notification was automatically ed to efiling System users who had chosen to be notified of notices of application issued by the Commission. 4. In response to the notice, the Commission received a submission from the County of Newell on September 7, The County stated that the parcel of land where the proposed project would be located was not zoned for alternative energy, and that the parcel would require rezoning to a land use district that could accommodate the development. In addition, the County indicated that CBA would have to obtain development and construction permits prior to the commencement of construction. 5. On October 2, 2017, the Commission requested that the County clarify any outstanding concern or objection it has with respect to the proposed solar project. 6. On October 16, 2017, the County responded that CBA had submitted an application to rezone the site to accommodate the solar facility and that after the land had been rezoned, CBA could apply for a development permit approval for the proposed project. The County of Newell did not request standing in the proceeding. Decision D (November 15, 2017) 1

4 3 Discussion 7. The proposed project consists of approximately 51,000 solar modules and six inverter and transformer stations within a fenced area covering approximately 28.7 hectares of land. A collector system would also be installed. 8. The proposed project would be located on land that is entirely native prairie. There are two temporary flooded graminoid marsh wetlands and an ephemeral water body located nearby, but avoided by the project footprint. 9. Siting a project on native prairie increases the risk to wildlife and is inconsistent with Alberta Environment and Parks (AEP) Wildlife Management policy and recommendations as outlined in the AEP Wildlife Guidelines for Alberta Solar Energy Projects. However, in this specific situation AEP has ranked the risk as low due to existing disturbances, proximity to the town limits of Brooks, and alternative mitigation outlined by CBA The AEP wildlife biologist reviewed the wildlife assessment and the post-construction monitoring plan. In the referral report dated May 31, 2017, AEP concluded that the proposed project would pose a low risk to wildlife and wildlife habitat due to residential, recreational, and industrial development, as well as road infrastructure surrounding the proposed project area. 11. CBA committed to working with AEP to ensure potential wildlife traps are removed and all overhead collector lines are properly marked to reduce bird collisions. Post-construction monitoring would be conducted in the first year and CBA would work with AEP to develop and implement mitigation if a high level of bird mortality were observed. If initial mitigation does not sufficiently reduce mortality, further mitigation and post-construction monitoring surveys would be required as prescribed by the AEP wildlife biologist. If mortality rates are low during the first year of monitoring, as determined in consultation with AEP, options for a second year of post-construction monitoring would be discussed. 12. CBA submitted it had received confirmation from AEP that an approval or registration under the Alberta Environmental Protection and Enhancement Act is not required because the proposed solar project is not a designated activity pursuant to the Activities Designation Regulation. Consequently, an environmental assessment is not required. 13. A Statement of Justification was submitted on March 22, 2017 to Alberta Culture and Tourism seeking clearance under the Historical Resources Act. Alberta Culture and Tourism provided a response requiring a pre-construction Historic Resources Impact Assessment for archaeological resources. The subsequent field assessment concluded that there were no recordable finds other than one lithic shatter. The archaeologists recommended no further work. 14. CBA retained Scott Land & Lease Ltd. to develop and conduct a project-specific participant involvement program that complies with Rule 007: Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments. Personal consultation was conducted with stakeholders located within 800 metres of the proposed project, and stakeholders within 2,000 metres of the proposed project were notified. An open house was held on April 5, CBA also met with municipal and provincial agencies. 1 Exhibit X0005, Attach 4 Newell AEP Referral Report, PDF Page 6. 2 Decision D (November 15, 2017)

5 15. CBA stated that one landowner expressed concerns with the proposed project due to visual impact, interference with cell towers, historical resources impacts, native prairie and environmental impacts, increase in gravelled land, property value, community benefits, reclamation, and temperature impact on cattle. 16. CBA submitted a noise impact assessment for the proposed project. There are no dwellings within 1,500 metres of the proposed project footprint. CBA identified four potential noise sensitive receptors along the eastern boundary of the land parcels with potential for future development. At the most impacted potential future dwelling location, 25 metres from the proposed project boundary, the sound level contribution from the project alone is predicted to be 28.6 dba L eq. The existing sound level, which includes the assumed ambient sound level plus energy-related facilities in the project area, is 40.2 dba L eq nighttime. The resultant cumulative sound level is 40.5 dba, resulting in net increase of 0.3 dba. The results of the noise impact assessment indicate that the proposed project would result in no net increase to the baseline sound level and be in compliance with Rule 012: Noise Control. 17. The project would connect to the FortisAlberta Inc. distribution system at 25 kilovolts. A system access service request form was submitted to the Alberta Electric System Operator by FortisAlberta Inc. regarding the proposed project. CBA stated it would apply for a connection order pursuant to Section 18 of the Hydro and Electric Act after FortisAlberta Inc. confirms the facilities it would require to connect the proposed project. 18. CBA stated that the proposed project is subject to the outcome of Alberta s initiatives to procure solar power for its government operations and install renewable generation under the Renewable Electricity Program. Construction could commence in the spring of 2018 or later, and could be completed by the spring of Findings 19. The Commission has reviewed the application and finds that the information filed with respect to the technical, siting, emissions, environmental and noise aspects of the power plant complies with the requirements prescribed in Rule CBA is in the process of obtaining development permits from the County of Newell. The Commission notes that no parties objected to the application and no other responses were received in response to the notice of application and finds that the participant involvement program undertaken by CBA meets the requirements of Rule The proposed project poses a potential low risk to wildlife and wildlife habitat. The Commission accepts that in consultation with AEP, CBA will keep the project s wildlife data current (e.g., less than two years old) until the project is commissioned by updating the wildlife field surveys if necessary. CBA will also implement any additional mitigation measures recommended by AEP should any new wildlife features or issues be identified during completion of the updated wildlife surveys. 22. The Commission accepts CBA s post construction monitoring plan and commitment to work with AEP to implement mitigation measures if a high level of bird mortalities were to occur. Decision D (November 15, 2017) 3

6 23. The Commission considers CBA s commitment to abide by any requirements laid out in AEP s May 31, 2017 Referral Report for the project to be reasonable. As necessary, CBA will continue to consult with AEP throughout construction and operation of the project; for example, consultation should occur if habitat features of sensitive wildlife species (e.g., raptor nests, sensitive breeding bird nests, sharp-tailed grouse leks, snake hibernacula) are discovered during future wildlife field surveys. 24. The Commission accepts CBA s assessment that the noise from the solar project will comply with Rule 012 permissible sound levels. 25. The Commission expects the applicant to comply with all applicable requirements for conservation and reclamation of the project site under the Environmental Protection and Enhancement Act at the end of the project s life, including the requirement to obtain a reclamation certificate. However, if for any reason, at the time of decommissioning, there are no statutory reclamation requirements in place for solar electric power generating facilities, the applicant will be required to submit a reclamation plan to the Commission for its review and approval. 26. The Commission notes that a connection order was not applied for at this time. CBA must apply for a connection order from the Commission prior to connecting the power plant to the FortisAlberta Inc. distribution network. 27. Based on the foregoing, the Commission considers the project to be in the public interest in accordance with Section 17 of the Alberta Utilities Commission Act. 5 Decision 28. Pursuant to Section 11 of the Hydro and Electric Energy Act, the Commission approves the application and grants CBA the approval set out in Appendix 1 Power Plant Approval D November 15, 2017 (Appendix 1 will be distributed separately), subject to the following conditions: (1) CBA shall keep the project s wildlife data current (less than two years old) until the project is commissioned by updating the wildlife field surveys. (2) CBA shall implement all additional mitigation measures recommended by AEP if any new wildlife features or issues are identified during completion of the updated wildlife surveys. (3) CBA shall abide by all requirements laid out in AEP s May 31, 2017 Referral Report for the project. (4) CBA shall continue to consult with AEP throughout construction and operation of the project. Consultation with AEP must occur if habitat features of sensitive wildlife species (e.g., raptor nests, sensitive breeding bird nests, sharp-tailed grouse leks, snake hibernacula) are discovered during future wildlife field surveys. 4 Decision D (November 15, 2017)

7 (5) Should AEP require post-construction mitigation measures as a result of bird mortalities, CBA will advise the Commission of those measures, in writing, as soon as practical. Dated on November 15, Alberta Utilities Commission (original signed by) Anne Michaud Commission Member Decision D (November 15, 2017) 5

SunEEarth Alberta Solar Development Inc.

SunEEarth Alberta Solar Development Inc. Decision 22422-D01-2017 Yellow Lake Solar Project September 26, 2017 Alberta Utilities Commission Decision 22422-D01-2017 Yellow Lake Solar Project Proceeding 22422 Application 22422-A001 September 26,

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22499-D01-2017 June 7, 2017 Decision 22499-D01-2017 Proceeding 22499 Application 22499-A001 June 7, 2017 Published by the: Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary, Alberta

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22296-D01-2017 Hays Solar Power Plant June 7, 2017 Alberta Utilities Commission Decision 22296-D01-2017 Hays Solar Power Plant Proceeding 22296 Application 22296-A001 June 7, 2017 Published by

More information

Decision GTE Solar Inc. Brooks Solar Power Plant. January 31, 2013

Decision GTE Solar Inc. Brooks Solar Power Plant. January 31, 2013 Decision 2013-027 Brooks Solar Power Plant January 31, 2013 The Alberta Utilities Commission Decision 2013-027: Brooks Solar Power Plant Application No. 1608532 Proceeding ID No. 1938 January 31, 2013

More information

Pteragen Canada Inc.

Pteragen Canada Inc. Decision 2013-171 May 7, 2013 The Alberta Utilities Commission Decision 2013-171: Application No. 1608907 Proceeding ID No. 2181 May 7, 2013 Published by The Alberta Utilities Commission Fifth Avenue Place,

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22447-D01-2017 Vauxhall Solar Power Plant July 4, 2017 Alberta Utilities Commission Decision 22447-D01-2017 Vauxhall Solar Power Plant Proceeding 22447 Application 22447-A001 July 4, 2017 Published

More information

Decision D The City of Calgary. Bonnybrook Cogeneration Expansion Project. May 17, 2018

Decision D The City of Calgary. Bonnybrook Cogeneration Expansion Project. May 17, 2018 Decision 22711-D01-2018 Bonnybrook Cogeneration Expansion Project May 17, 2018 Alberta Utilities Commission Decision 22711-D01-2018 Bonnybrook Cogeneration Expansion Project Proceeding 22711 Application

More information

Burdett Solar GP Corp.

Burdett Solar GP Corp. Decision 23364-D01-2018 Burdett Solar Project Time Extension October 3, 2018 Alberta Utilities Commission Decision 23364-D01-2018 Burdett Solar Project Time Extension Proceeding 23364 Application 23364-A001

More information

Seven Generations Energy Ltd.

Seven Generations Energy Ltd. Decision 22976-D01-2018 Power Plant Exemption at Gold Creek Gas Plant January 17, 2018 Alberta Utilities Commission Decision 22976-D01-2018 Power Plant Exemption at Gold Creek Gas Plant Proceeding 22976

More information

Solar Krafte Utilities Inc.

Solar Krafte Utilities Inc. Decision 23323-D01-2018 August 21, 2018 Alberta Utilities Commission Decision 23323-D01-2018 Proceeding 23323 Application 23323-A001 August 21, 2018 Published by the: Alberta Utilities Commission Eau Claire

More information

Signalta Resources Limited

Signalta Resources Limited Decision 22388-D01-2017 Coaldale 6.4-Megawatt Cogeneration Station June 1, 2017 Alberta Utilities Commission Decision 22388-D01-2017 Coaldale 6.4-Megawatt Cogeneration Station Proceeding 22388 Application

More information

Alberta Electric System Operator Yeo 2015S Substation Needs Identification Document

Alberta Electric System Operator Yeo 2015S Substation Needs Identification Document Decision 3476-D01-2015 Alberta Electric System Operator Yeo 2015S Substation Needs Identification Document ATCO Electric Ltd. Yeo Substation Project Facility Application February 18, 2015 Alberta Utilities

More information

NaturEner Wild Rose 1 Energy Inc.

NaturEner Wild Rose 1 Energy Inc. Decision 2013-348 Amendment to Wild Rose 1 Wind Power Plant September 13, 2013 The Alberta Utilities Commission Decision 2013-348: Amendment to Wild Rose 1 Wind Power Plant Application No. 1609685 Proceeding

More information

Grande Prairie Generation, Inc.

Grande Prairie Generation, Inc. Decision 20292-D01-2015 Northern Prairie Power Plant November 27, 2015 Alberta Utilities Commission Decision 20292-D01-2015 Northern Prairie Power Plant Proceeding 20292 Application 20292-A001 November

More information

Alberta Electric System Operator Needs Identification Document Application

Alberta Electric System Operator Needs Identification Document Application Decision 22618-D01-2017 Alberta Electric System Operator Needs Identification Document Application Facility Applications June 22, 2017 Alberta Utilities Commission Decision 22618-D01-2017: Alberta Electric

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 23468-D01-2018 Margie 1034S Substation May 28, 2018 Alberta Utilities Commission Decision 23468-D01-2018 Margie 1034S Substation Proceeding 23468 Application 23468-A001 May 28, 2018 Published

More information

Pembina NGL Corporation

Pembina NGL Corporation Decision 22928-D01-2018 45-Megawatt Cogeneration Power Plant, Alteration to Scoria 318S Substation and Amendment to the Redwater Industrial System Designation January 9, 2018 Alberta Utilities Commission

More information

NOVA Chemicals Corporation

NOVA Chemicals Corporation Decision 2013-426 NOVA Chemicals Corporation Industrial System Designation Amendment November 29, 2013 The Alberta Utilities Commission Decision 2013-426: NOVA Chemicals Corporation Industrial System Designation

More information

Oldman 2 Wind Farm Limited

Oldman 2 Wind Farm Limited Decision 2010-461 Oldman 2 Wind Farm Project September 24, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-461: Oldman 2 Wind Farm Project Application No. 1605398 Proceeding ID. 293 September 24, 2010

More information

Harvest Operations Corp.

Harvest Operations Corp. Decision 2014-214 Six-MW Power Plant Exemption July 21, 2014 The Alberta Utilities Commission Decision 2014-214: Six-MW Power Plant Exemption Application No. 1610444 Proceeding No. 3153 July 21, 2014 Published

More information

Greengate Power Corporation

Greengate Power Corporation Decision 2011-085 Blackspring Ridge Wind Project March 9, 2011 The Alberta Utilities Commission Decision 2011-085: Blackspring Ridge Wind Project Application No. 1604777 Proceeding ID No. 190 March 9,

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22562-D01-2017 ENMAX No. 31 Substation Alteration May 25, 2017 Alberta Utilities Commission Decision 22562-D01-2017 ENMAX No. 31 Substation Alteration Proceeding 22562 Application 22562-A001 May

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 22229-D01-2016 Victoria E511S Substation Breaker Additions December 19, 2016 Alberta Utilities Commission Decision 22229-D01-2016 Victoria E511S Substation Breaker Additions Proceeding 22229 Application

More information

Aquatera Utilities Inc.

Aquatera Utilities Inc. Decision 2014-194 Aquatera Utilities Inc. 2.85-MW Power Plant June 26, 2014 The Alberta Utilities Commission Decision 2014-194: Aquatera Utilities Inc. 2.85-MW Power Plant Application No. 1610366 Proceeding

More information

Decision D ATCO Electric Ltd. Swan Hills F.P.L. 744S Substation Decommission and Salvage. November 8, 2018

Decision D ATCO Electric Ltd. Swan Hills F.P.L. 744S Substation Decommission and Salvage. November 8, 2018 Decision 23890-D01-2018 Swan Hills F.P.L. 744S Substation Decommission and Salvage November 8, 2018 Alberta Utilities Commission Decision 23890-D01-2018 Swan Hills F.P.L. 744S Substation Decommission and

More information

Decision B. St. Pierre kW Photovoltaic Micro-Generation System. May 15, 2013

Decision B. St. Pierre kW Photovoltaic Micro-Generation System. May 15, 2013 Decision 2013-180 13.05-kW Photovoltaic Micro-Generation System May 15, 2013 The Alberta Utilities Commission Decision 2013-180: 13.05-kW Photovoltaic Micro-Generation System Application No. 1609500 Proceeding

More information

Alberta Power (2000) Ltd.

Alberta Power (2000) Ltd. Decision 23558-D01-2018 Battle River Power Plant Alterations August 27, 2018 Alberta Utilities Commission Decision 23558-D01-2018 Battle River Power Plant Alterations Proceeding 23558 Application 23558-A001

More information

TransAlta Corporation

TransAlta Corporation Decision 23808-D01-2018 Coal-to-Gas Conversion of Keephills Power Plant Units 1 and 2 December 21, 2018 Alberta Utilities Commission Decision 23808-D01-2018 Coal-to-Gas Conversion of Keephills Power Plant

More information

The City of Red Deer

The City of Red Deer Decision 2010-148 The City of Red Deer 15-kW Solar Power Plant for City of Red Deer Civic Yards Building April 5, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-148: The City of Red Deer 15-kW Solar Power

More information

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments This rule as amended was approved by the Alberta Utilities Commission on March

More information

OPEN HOUSE PROJECT OVERVIEW OPEN HOUSE NOVEMBER 16, :00-8:00 PM FALL 2017

OPEN HOUSE PROJECT OVERVIEW OPEN HOUSE NOVEMBER 16, :00-8:00 PM FALL 2017 FALL 2017 PROJECT OVERVIEW EDF EN Canada is proposing to develop, construct, and operate the Cypress Wind Power Project with 243.6 megawatts (MW) of generating capacity. The Project is south of Dunmore,

More information

Suncor Energy Inc. Errata to Decision Firebag Substations and Power Plant Expansion and Industrial System Designation Amendment

Suncor Energy Inc. Errata to Decision Firebag Substations and Power Plant Expansion and Industrial System Designation Amendment Decision 2011-523 (Errata) Errata to Decision 2011-523 Firebag Substations and Power Plant Expansion and Industrial System Designation Amendment January 10, 2012 The Alberta Utilities Commission Decision

More information

Connacher Oil and Gas Limited

Connacher Oil and Gas Limited Decision 2010-094 Cogeneration Plant and Industrial System Designation March 2, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-094: Cogeneration Plant and Industrial System Designation Application No.

More information

Decision Cenovus FCCL Ltd.

Decision Cenovus FCCL Ltd. Decision 2012-196 Construct and Operate a 95-MW Cogeneration Power Plant, Construct and Operate Sunday Creek 539S Substation, Industrial System Designation and Interconnection of the Christina Lake Industrial

More information

Renewable Energy Services Ltd.

Renewable Energy Services Ltd. Decision 1976-D01-2018 McLaughlin Wind Power Plant and Substation February 23, 2018 Alberta Utilities Commission Decision 1976-D01-2018 McLaughlin Wind Power Plant and Substation Proceeding 1976 Applications

More information

Decision MEG Energy Corp. Amend Christina Lake Industrial System Designation. December 15, 2011

Decision MEG Energy Corp. Amend Christina Lake Industrial System Designation. December 15, 2011 Decision 2011-496 December 15, 2011 The Alberta Utilities Commission Decision 2011-496: Application No. 1607774 Proceeding ID No. 1505 December 15, 2011 Published by The Alberta Utilities Commission Fifth

More information

Grizzly Oil Sands ULC

Grizzly Oil Sands ULC Decision 2013-124 Algar Lake Project Distribution System Exemption March 28, 2013 The Alberta Utilities Commission Decision 2013-124: Algar Lake Project Distribution System Exemption Application No. 1609370

More information

Welcome to our Open House!

Welcome to our Open House! Welcome to our Open House! Please sign in at the front desk and provide your contact information if you would like to receive project updates. We invite you to walk around and look at the displays. If

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23713-D01-2018 August 28, 2018 Alberta Utilities Commission Decision 23713-D01-2018 Proceeding 23713 Application 23713-A001 August 28, 2018 Published by the: Alberta Utilities Commission Eau Claire

More information

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments This rule as amended was approved by the Alberta Utilities Commission on June

More information

Nexen Inc. and CNOOC Canada Inc.

Nexen Inc. and CNOOC Canada Inc. Decision 2012-330 Long Lake Project December 6, 2012 The Alberta Utilities Commission Decision 2012-330: Long Lake Project Application No. 1608729 Proceeding ID No. 2074 December 6, 2012 Published by The

More information

Nexen Inc. OPTI Canada Inc.

Nexen Inc. OPTI Canada Inc. Decision 2010-006 Nexen Inc. OPTI Canada Inc. Long Lake South Phase 1 Cogeneration Power Plant January 15, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-006: Nexen Inc. and OPTI Canada Inc. Long Lake

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23918-D01-2018 Paddle Prairie Compressor Station Installation Mackenzie County October 11, 2018 Alberta Utilities Commission Decision 23918-D01-2018 Paddle Prairie Compressor Station Installation

More information

Pengrowth Energy Corporation

Pengrowth Energy Corporation Decision 2013-308 Lindberg SAGD Industrial System Designation August 20, 2013 The Alberta Utilities Commission Decision 2013-308: Lindberg SAGD Industrial System Designation Application No. 1609200 Proceeding

More information

Oldman 2 Wind Farm Limited

Oldman 2 Wind Farm Limited Decision 22706-D01-2017 Spring 2017 Comprehensive Sound Survey at Receptors R and S August 25, 2017 Alberta Utilities Commission Decision 22706-D01-2017 Proceeding 22706 Application 22706-A001 August 25,

More information

Welcome to Capital Power s Halkirk 2 Project Open House #2

Welcome to Capital Power s Halkirk 2 Project Open House #2 Welcome to Capital Power s Halkirk 2 Project Open House #2 ABOUT US BC AB RESPECTED, RELIABLE, COMPETITIVE ON Capital Power is a growth-oriented North American power producer headquartered in Edmonton,

More information

Project siting. Lanfine. Wind resource assessment. Wind Power Project

Project siting. Lanfine. Wind resource assessment. Wind Power Project Project siting Wind resource assessment This assessment determines how much electrical energy can be extracted from the wind Meteorological towers are installed on site to measure wind speed and direction

More information

Notice of Technical Meeting

Notice of Technical Meeting Notice of Technical Meeting Amendments to three wind energy projects in the Pincher Creek area proposed by Welsch Wind Power Inc., Windy Point Wind Park Ltd. and NextEra Canada Development & Acquisitions,

More information

Decision FortisAlberta Inc. Micro-Generation Determination. December 16, 2008

Decision FortisAlberta Inc. Micro-Generation Determination. December 16, 2008 Decision 2008-132 FortisAlberta Inc. Micro-Generation Determination December 16, 2008 ALBERTA UTILITIES COMMISSION Decision 2008-132: FortisAlberta Inc. Micro-Generation Determination Application No. 1594619

More information

October 30, 2012 Our File:

October 30, 2012 Our File: October 30, 2012 Our File: 5000-510-5120 Minister of Environment and Sustainable Resource Development 204 Legislature Building 10800 97 Avenue Edmonton, AB T5K 2B6 Attention: Honourable Diana McQueen at

More information

EDF EN Canada Development Inc.

EDF EN Canada Development Inc. Decision 21203-D01-2016 Blackspring Ridge Wind Power Plant March 2, 2016 Alberta Utilities Commission Decision 21203-D01-2016 Blackspring Ridge Wind Power Plant Proceeding 21203 Application 21203-A001

More information

WHO ARE WE? Willow Ridge Wind Project

WHO ARE WE? Willow Ridge Wind Project Willow Ridge WELCOME This is the Second Public Open House for the, where project staff are available to answer any questions and recieve input from attendees.this process is being undertaken as part of

More information

Up to 9.5MW AC solar project located near Burdett, Alberta

Up to 9.5MW AC solar project located near Burdett, Alberta PROJECT OVERVIEW Up to 9.5MW AC solar project located near Burdett, Alberta Located on agricultural land within the quarter section NE-21-010-12-W4M near the intersection of Range Road 123 and Township

More information

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments This rule as amended was approved by the Alberta Utilities Commission on December

More information

Willow Ridge Wind Project Frequently Asked Questions. Popular Questions Who is the developer of the proposed project?

Willow Ridge Wind Project Frequently Asked Questions. Popular Questions Who is the developer of the proposed project? Willow Ridge Wind Project Frequently Asked Questions Popular Questions Who is the developer of the proposed project? Algonquin Power Co./ Liberty Power Co. is the company proposing the project and, if

More information

E.L. SMITH SOLAR FARM PROJECT UPDATE

E.L. SMITH SOLAR FARM PROJECT UPDATE E.L. SMITH SOLAR FARM PROJECT UPDATE Artist rendering: Looking northeast from Anthony Henday Drive (located southwest of project site) In June 2017, we sent you information about the E.L. Smith Solar Farm

More information

COMMUNITY FUND AND INVOLVEMENT

COMMUNITY FUND AND INVOLVEMENT ENNER WIND POWER ANUARY 2018 NEWSLETTER INTRODUCTION enner Wind Limited Partnership (WLP), a subsidiary of Potentia Renewables Inc. (PRI), would like to thank you for your continued support and interest

More information

Ellerslie Substation Expansion

Ellerslie Substation Expansion Ellerslie Substation Expansion Volume 2 UV 2 North Saskatchewan River EDMONTON UV 216 UV 14 ") ELLERSLIE 89S Bretona!! Trevithick March 2010 Why are you receiving this newsletter? You are receiving this

More information

D-1. SOUTH PEACE EAST AND WEST SOP PROJECTS PATRICK HENN, DEVELOPMENT MANAGER PRRD Board of Directors Meeting, April

D-1. SOUTH PEACE EAST AND WEST SOP PROJECTS PATRICK HENN, DEVELOPMENT MANAGER PRRD Board of Directors Meeting, April SOUTH PEACE EAST AND WEST SOP PROJECTS PATRICK HENN, DEVELOPMENT MANAGER PRRD Board of Directors Meeting, April 28 2016 Renewable Energy Systems (RES) In Canada for more than 12 years Family-owned company

More information

Wind Power Regulatory Process Review

Wind Power Regulatory Process Review Wind Power Regulatory Process Review Stakeholder Consultation Summary of Discussion September 28, 2012 The Alberta Utilities Commission Wind Power Regulatory Process Review Stakeholder Consultation Summary

More information

AMHERST ISLAND WIND ENERGY PROJECT CONSULTATION REPORT. Appendix C. Project Notices

AMHERST ISLAND WIND ENERGY PROJECT CONSULTATION REPORT. Appendix C. Project Notices AMHERST ISLAND WIND ENERGY PROJECT CONSULTATION REPORT Appendix C Project Notices AMHERST ISLAND WIND ENERGY PROJECT CONSULTATION REPORT Appendix C1 Notice of Proposal to Engage in a Renewable Energy Project

More information

We are here to:

We are here to: Welcome! We are here to: Provide an overview and update of the proposed wind energy project Introduce the Project team Review the wind project development process Answer your questions NextEra Energy Resources

More information

Amherst Island Wind Energy Project - Renewable Energy Approval Amendment Modification Report #4

Amherst Island Wind Energy Project - Renewable Energy Approval Amendment Modification Report #4 Amherst Island Wind Energy Project - Renewable Energy Approval Amendment Modification Report #4 Prepared for: Windlectric Inc. 2845 Bristol Circle Oakville ON L9H 7H7 Prepared by: Stantec Consulting Ltd.

More information

Substation Developments Environmental Guidelines Checklist for Applicants

Substation Developments Environmental Guidelines Checklist for Applicants Substation Developments Environmental Guidelines Checklist for Applicants Effective date: February 1, 2016 These guidelines are intended to be used in conjunction with the flowchart in Figure 1 which conceptually

More information

New York Community Solar Facility Decommissioning Plan

New York Community Solar Facility Decommissioning Plan New York Community Solar Facility Decommissioning Plan July 2017 Prepared For: Town of Dryden, NY Delaware River Solar 33 Irving Place, Suite 1090 New York, NY 10003 Table of Contents Page 1. Introduction

More information

ENVIRONMENTAL SCREENING REPORT

ENVIRONMENTAL SCREENING REPORT ENVIRONMENTAL SCREENING REPORT Pursuant to the Canadian Environmental Assessment Act (CEA Act) SCREENING SUMMARY TransCanada PipeLines Limited (TransCanada) is proposing to conduct a contaminant sampling

More information

Alberta Electric System Operator AltaLink Management Ltd. Alberta-Pacific Forest Industries Inc.

Alberta Electric System Operator AltaLink Management Ltd. Alberta-Pacific Forest Industries Inc. Decision 2010-612 Alberta Electric System Operator AltaLink Management Ltd. Alberta-Pacific Forest Industries Inc. Needs Identification Document, Transmission Line, Substation and Power Plant Al-Pac Pulp

More information

1. Description of and Rationale for Proposed Change

1. Description of and Rationale for Proposed Change Suite 500, 4342 Queen Street Niagara Falls, Ontario, Canada L2E 7J7 Tel. 905 374 5200 Fax: 905 374 1157 www.hatch.ca Nick Colella 2 St. Clair Avenue West Floor 12A Toronto, ON M4V 1L5 Dear Mr. Colella:

More information

December 2, 2016 EAB File #: Transaction #:

December 2, 2016 EAB File #: Transaction #: Ministry of Environment Environmental Assessment and Stewardship Branch 4 th floor, 3211 Albert Street Regina, Saskatchewan S4S 5W6 Phone: (306) 787-6132 Fax: (306) 787-0930 December 2, 2016 EAB File #:

More information

EXECUTIVE SUMMARY 1. INTRODUCTION

EXECUTIVE SUMMARY 1. INTRODUCTION I 1. INTRODUCTION EXECUTIVE SUMMARY Mulilo Renewable Energy (Pty) Ltd (later referred to as Mulilo) has identified two alternative sites for the establishment of a 10MW photovoltaic (PV) power generation

More information

Environmental Assessment Approval

Environmental Assessment Approval Environmental Assessment Approval Approval Date: Original Dated October 1, 2010 Hants County Aggregate Quarry Extension Project Municipal Enterprises Ltd., Proponent Hants County, Nova Scotia The Hants

More information

NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT

NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT Date: September 18, 2017 NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT To: Agencies and Interested Parties Lead Agency: Sacramento Municipal Utility District 6201 S Street, MS H201 Sacramento,

More information

LNG Canada Development Inc.

LNG Canada Development Inc. LNG Canada Development Inc. Shell Centre 32 nd Floor 400 4 th Avenue SW PO Box 100, Station M Calgary AB T2P 2H5 Canada Submitted electronically to: compliance.conformite@ceaa-acee.gc.ca April 20, 2016

More information

THE PROJECT. What is happening? Why is this facility needed? Why did you choose this location?

THE PROJECT. What is happening? Why is this facility needed? Why did you choose this location? THE PROJECT What is happening? - We are proposing to build a new solar farm on our property just south of the existing E.L. Smith Water Treatment Plant (at 3900 E.L. Smith Road). - If approved, the project

More information

State Environmental Quality Review NEGATIVE DECLARATION Notice of Determination of Non-Significance

State Environmental Quality Review NEGATIVE DECLARATION Notice of Determination of Non-Significance State Environmental Quality Review NEGATIVE DECLARATION Notice of Determination of Non-Significance Project: East Hampton Temporary Generation Facility Expansion Date: May 17, 2018 This notice is issued

More information

Welcome. Windy Point. The WIND FARM. Thank you for coming to the Windy Point Wind Farm Open House. AGENDA WIND FARM

Welcome. Windy Point. The WIND FARM. Thank you for coming to the Windy Point Wind Farm Open House. AGENDA WIND FARM The Windy Point WIND FARM Thank you for coming to the Windy Point Wind Farm Open House. AGENDA 7 P.M. Spend time meeting team members or browsing the information provided in poster boards WIND FARM 7:30

More information

Listing of Historic Resources: Instructions for Use

Listing of Historic Resources: Instructions for Use Introduction Listing of Historic Resources: Instructions for Use In accordance with Section 37(2) of the Historical Resources Act (HRA), the Minister of Alberta Culture and Tourism (CT) may require that

More information

Grand Valley Wind Farms Phase 3 Wind Project Wind Turbine Specification Report

Grand Valley Wind Farms Phase 3 Wind Project Wind Turbine Specification Report Grand Valley Wind Farms Phase 3 Wind Project Wind Turbine Specification Report Prepared for: Grand Valley 2 Limited Partnership 222 3rd Avenue Southwest, Suite 900 Livingston Place, South Tower Calgary

More information

County of Wetaskiwin Pigeon Lake Watershed Area Concept Plan February 6, 2014

County of Wetaskiwin Pigeon Lake Watershed Area Concept Plan February 6, 2014 County of Wetaskiwin Pigeon Lake Watershed Area Concept Plan February 6, 2014 1 Introduction 1.1 Background The Pigeon Lake area continues to attract significant attention from landowners wanting to pursue

More information

EAST-WEST TIE TRANSMISSION PROJECT

EAST-WEST TIE TRANSMISSION PROJECT Connecting Ontario s Northwest What s Inside? Answers to On: NextBridge Infrastructure and the East-West Tie Project Electricity in Northern Ontario Land issues Routing Project approval process Health

More information

methods consist of: activities of The physical the Project surveying; stockpiling; grading; piling and turbine delivery; distribution line; operation

methods consist of: activities of The physical the Project surveying; stockpiling; grading; piling and turbine delivery; distribution line; operation 3.0 SCOPE OF THE ASSESSMENT The following section provides the scope of the Project and its assessment as well as the used for the environmental assessment. methods 3.1 Scope of the Project and Assessment

More information

October 2, 2015 EAB File #: Transaction #:

October 2, 2015 EAB File #: Transaction #: Ministry of Environment Environmental Assessment Branch 4 th floor, 3211 Albert Street Regina, Saskatchewan S4S 5W6 Phone: 306.787 5971 Fax: 306 787 0930 October 2, 2015 EAB File #: 2015-013 Transaction

More information

Summary of Proposed Changes to the Technical Guide to Renewable Energy Approvals

Summary of Proposed Changes to the Technical Guide to Renewable Energy Approvals Summary of Proposed Changes to the Technical Guide to Renewable Energy Approvals Purpose The Ministry of the Environment and Climate Change (MOECC) is proposing a number of revisions and updates to the

More information

AMHERST ISLAND WIND ENERGY PROJECT PROPERTY LINE SETBACK ASSESSMENT REPORT. File No April Prepared for:

AMHERST ISLAND WIND ENERGY PROJECT PROPERTY LINE SETBACK ASSESSMENT REPORT. File No April Prepared for: PROPERTY LINE SETBACK ASSESSMENT REPORT File No. 160960595 April 2013 Prepared for: Windlectric Inc. 2845 Bristol Circle Oakville ON L6H 7H7 Prepared by: Stantec Consulting Ltd. Suite 1 70 Southgate Drive

More information

SemCAMS Area Project Description

SemCAMS Area Project Description REGULATORY The Redwillow Pipeline Project involves crossing a provincial boundary, and therefore, approval for it will require the preparation of an application to the NEB. plans to proceed with the regulatory

More information

EAST-WEST TIE TRANSMISSION PROJECT

EAST-WEST TIE TRANSMISSION PROJECT EAST-WEST TIE TRANSMISSION PROJECT Connecting Ontario s Northwest THANK YOU for attending this Open House We want to hear from you www.nextbridge.ca Purpose of the Open House We are here to provide you

More information

E.L. Smith Solar Farm Project Open House. Lower Level

E.L. Smith Solar Farm Project Open House. Lower Level E.L. Smith Solar Farm Project Open House Lower Level We are consulting you to share feedback and perspectives that we will consider in the planning and execution of this project. Who is epcor? Powering

More information

Wind Turbine Zoning for CERTs

Wind Turbine Zoning for CERTs Turbine Northwest Energy Workshop August 3rd, 2006 University of Minnesota Crookston Mark Lindquist The Minnesota Project www.mnproject.org The Model Ordinance Project Collaboration of: The Minnesota Project

More information

SUNDANCE 7 January 2014

SUNDANCE 7 January 2014 Artist rendering of a combined-cycle natural gas power plant. SUNDANCE 7 January 2014 Project Information Booklet Table of Contents Introduction to Sundance 7 1 TransAlta and MidAmerican 1 Project location

More information

Ohio Power Siting Board. Staff Investigation Report and Recommendation

Ohio Power Siting Board. Staff Investigation Report and Recommendation Ohio Power Siting Board Staff Investigation Report and Recommendation Case No.: 11-1995-EL-BGA Project: Amendment to Blue Creek Wind Farm Certificate of Environmental Compatibility and Public Need Applicant:

More information

AREA STRUCTURE PLAN PROCESS

AREA STRUCTURE PLAN PROCESS AREA STRUCTURE PLAN PROCESS Planning & Development Guide County of Grande Prairie No. 1 10001 84 Avenue Clairmont, Alberta, T0H 0W0 Tel: (780) 513-3950 Fax: (780) 539-7686 www.countygp.ab.ca Page 1 TABLE

More information

Decision D Alberta Ltd. (BluEarth) Bull Creek Wind Power Project Noise Complaints

Decision D Alberta Ltd. (BluEarth) Bull Creek Wind Power Project Noise Complaints Decision 22493-D01-2018 1646658 Alberta Ltd. (BluEarth) Bull Creek Wind Power Project Noise Complaints January 17, 2018 Alberta Utilities Commission Decision 22493-D01-2018 1646658 Alberta Ltd. (BluEarth)

More information

BOLAND ENVIRONMENTAL CONSULTANTS CC

BOLAND ENVIRONMENTAL CONSULTANTS CC BOLAND ENVIRONMENTAL CONSULTANTS CC y ENVIRONMENTAL IMPACT ASSESSMENT PROCESS Proposed Photo-Voltaic Solar Power Plant On Farm Nuwerus, No. 450 Portion 6, Worcester DEA REF. NO: 12/12/20/2019 BACKGROUND

More information

Community Update. Draft. North-South 400kV Interconnection Development. Application for Planning Approval to An Bord Pleanála

Community Update. Draft. North-South 400kV Interconnection Development. Application for Planning Approval to An Bord Pleanála North-South 400kV Interconnection Development Draft Community Update Part Funded by the EU-TEN-E Initiative Application for Planning Approval to An Bord Pleanála Project Background The North-South 400kV

More information

Environmental Assessment Approval

Environmental Assessment Approval presented in the Registration Document. dispose of this Approval without the written consent of the Minister. The sale of a controlling interest of a business or a transfer of an approval following conditions

More information

Cassadaga Wind Project Exhibit 6. Wind Power Facilities

Cassadaga Wind Project Exhibit 6. Wind Power Facilities Case No. 14-F-0490 1001.6 Exhibit 6 Wind Power Facilities WIND POWER FACILITIES (a) Factors Considered During Placement of Wind Turbines (Setback Requirements/Recommendations/Fall-Down Distances) The primary

More information

A Guide to the Municipal Planning Process in Saskatchewan

A Guide to the Municipal Planning Process in Saskatchewan A Guide to the Municipal Planning Process in Saskatchewan An overview of the municipal planning, development permit and the subdivision approval processes in Saskatchewan July 2016 Prepared By: Community

More information

Decision Syncrude Canada Ltd. Mildred Lake Power Plant. July 17, 2014

Decision Syncrude Canada Ltd. Mildred Lake Power Plant. July 17, 2014 Decision 2014-212 Syncrude Canada Ltd. Mildred Lake Power Plant July 17, 2014 Decision 2014-212: Syncrude Canada Ltd. Mildred Lake Power Plant Application No. 1610311 Proceeding No. 3068 July 17, 2014

More information

Background. Overview: Rail Yard Expansion. NOVA Chemicals Joffre Site Project Description: Proposed Rail Yard Expansion

Background. Overview: Rail Yard Expansion. NOVA Chemicals Joffre Site Project Description: Proposed Rail Yard Expansion NOVA Chemicals Joffre Site Project Description: Proposed Rail Yard Expansion Accompanying the Application to Lacombe County for Rezoning and a Development Permit January Background In mid-2012, Lacombe

More information

Chapter 750 WIND POWER GENERATION FACILITIES

Chapter 750 WIND POWER GENERATION FACILITIES Chapter 750 WIND POWER GENERATION FACILITIES 750.01 Purpose 750.02 Definitions 750.03 Designated Areas 750.04 Permitted Uses 750.05 Conditional Uses 750.06 Construction Standards 750.07 Application Requirements

More information