PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT

Size: px
Start display at page:

Download "PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT"

Transcription

1 PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT PROJECT DESCRIPTION McFarland-Johnson, Inc. (MJ) has prepared this proposal to perform the Project Scoping Phase in conformance with the Project Development Process of the Regional Planning Commission (CCRPC), which is similar to the Project Development Process of the Vermont Agency of Transportation (VTrans). The purpose of the Project Scoping Phase is to investigate various bridge improvement alternatives to address existing and future structural and functional deficiencies of the bridge crossing. Through a collaborative public participation process, the community and project stakeholders will play an active role in the study and in the selection of a preferred alternative. A comprehensive scoping report will be prepared and submitted. The Main Street Bridge, constructed in 1929, is a significant structure with a length of 360 feet. The bridge carries over 30,000 vehicles per day across the Winooski River. It consists of a three-span riveted steel plate girder superstructure supported on cast-in-place reinforced concrete abutments and piers. The VTrans 2015 Inspection Report lists the bridge deck and superstructure in satisfactory condition and the substructure in good condition. The bridge deck, sidewalks, and concrete parapet are in need of rehabilitation or replacement. The 87-year-old steel superstructure has a limited remaining service life, with many areas in need of steel repair and painting. Available information from recent designs and studies will be considered in the development of the scoping report. These designs and studies provide additional information on the condition of the existing steel, deck, and bridge rail; potential alternatives to carry bike and pedestrian traffic independently of the Main Street Bridge; local traffic demands and possible roadway and intersection improvements; and community input through various public participation efforts in recent studies and plans. SCOPE OF SERVICES 1.0 PROJECT KICKOFF MEETING MJ will attend a project kickoff meeting with the CCRPC, VTrans, and City staff from Burlington and Winooski. This meeting will finalize the project schedule, goals, and deliverables. Regional Planning Commission 1-1 Winooski Burlington, VT

2 2.0 DATA COLLECTION & ANALYSES 2.1 Information Collection MJ and our subconsultants will perform an information search, and review available background information relative to the existing bridge, waterway, and immediate approaches, including but not limited to: as-built bridge plans bridge load rating bike/pedestrian/intersection reports right-of-way information (from tax map) utility information traffic and crash data hydraulic information reports and studies on existing environmental resources information from VTrans, including the DTA 2.2 Site Visit - In addition to the above, MJ will perform a site visit using the VTrans Site Visit Checklist as a guide. Key items to be noted in the field visit will be: Horizontal and vertical sight distances Intersection/driveway sight distance Location of potential historic resources Location and type of utilities Location of potential archeological resources Identification of any special habitats A site visit for historic and archeological resources will be conducted by our subconsultant. They will field check the project area to assess or update known historic survey forms, identify disturbed areas, and to assess the buildings within the project area. Distinguishing features of the project area will be photographed. 2.3 Base Map MJ will use existing survey data and digital aerial orthophoto information that is already available to prepare a base map suitable for use in developing the scoping study. MJ will identify any additional needs for targeted survey data. 2.4 Bridge Inspection MJ will conduct a field review of the bridge noting differences in condition from the VTrans inspection report. These will be noted in the minutes of the field visit, but a formal bridge inspection and report will not be completed. 2.5 Hydraulic Analysis For this study a detailed hydraulic analysis will not be completed. It is assumed that reviewing and understanding the available FEMA mapping will be sufficient to evaluate the probable replacement bridge options. 2.6 Subsurface Investigations No subsurface investigations are required at this time. Existing information will be used for any replacement bridge options. 2.7 Current and Future Traffic Analyses Some recent traffic data within the project area is available from a variety of sources and reports. The MJ team will review all available Regional Planning Commission 1-2 Winooski Burlington, VT

3 data and determine any further data needs. The MJ team will also coordinate closely with recent projects and activities in the area. For instance, a current study is analyzing the Colchester/Riverside/Barrett intersection, south of the bridge. Traffic data and capacity analyses from the intersection scoping study will be available to use in this study. Also, a VISSIM model of the Winooski Circulator is available for use but it will need to be updated and calibrated with more recent traffic data. Please note that VTrans has a 2016 AADT count just north of the bridge. This scope assumes recent counts for the Circulator and Riverside Avenue/Colchester intersection are available and no new traffic counts are required. It also assumes the existing VISSIM and Synchro models of the Circulator and Riverside Avenue/Colchester Avenue intersection are calibrated to the previous existing condition (and will be updated as part of this effort). The MJ team will develop design hour volumes for (design year) Traffic modeling will be conducted for 2 bridge scenarios: Four-lane cross section (existing condition) with two northbound and two southbound lanes. Three-lane cross section with two northbound lanes and one southbound lane. Traffic analyses (LOS, delays, and queues) will be conducted for: A 3-lane and a 4-lane bridge for Alternative 2: Bridge Rehabilitation Only a 4-lane bridge for all other build alternatives. Traffic evaluation will focus on the Winooski Circulator since the Burlington side has been analyzed as part of the Colchester/Riverside/Barrett scoping. MJ will incorporate the design work from the intersection scoping into the plans and provide a layout of possible modifications to the approach to the circulator based on future traffic volumes. The model will include the preferred intersection alternative at the Riverside Avenue/Colchester Avenue intersection. See the attached Detailed Scope prepared by RSG Inc. for additional detail on the above scope of work. The CCRPC will run their Regional Travel Demand Model to determine any regional network impacts of full or partial closure of the bridge. The MJ team will examine these modeling results and include their conclusions in the scoping report. 2.8 Resource Identification Areas of sensitive resources will be identified by the MJ team. At this location, areas of sensitivity may include archeology and historic structures. Potentially historic structures and archeologically sensitive areas will be identified. Documentation will also be completed confirming what, if any, natural resources will be affected. A review of records for the presence of any hazardous materials will also occur. Farmland soils: The project is within an urban area with no active agricultural land, so important farmland or primary agricultural soils are unlikely to occur. The USDA Web Soil Survey will be consulted regarding potential farmland soils. Regional Planning Commission 1-3 Winooski Burlington, VT

4 Wetlands: No wetlands were found in the immediate vicinity of the Main Street bridge during the 2003 scoping report work. The Vermont Natural Resources Atlas will be consulted and the study area will be revisited to determine whether wetlands are present. If wetlands are present, their locations will be sketched on plans. It is assumed no new wetland delineation will be necessary. Waterways: The ordinary high water line will be determined based on existing information, such as survey or topographic mapping. Floodplains and floodways: Existing FEMA mapping and studies will be consulted to determine floodplain and floodway boundaries and elevations. Boundaries will be shown on project base mapping. Hazardous materials sites: Known sites will be identified by consulting the ANR Atlas. Possible indications of hazardous materials will be evaluated during other resource identification site visits. Fish and Wildlife Habitats: Habitats will be identified in the field and described. The Natural Resources Atlas and ECOS Map Viewer will be consulted, and the Vermont fisheries biologist will be contacted for information on fisheries in the Winooski River. The 2003 study reported two significant natural communities, and there is also currently a mapped habitat block in the project vicinity. Threatened and Endangered (T&E) Species: T&E species will be identified based on the Vermont Natural Resources Atlas and correspondence with the Vermont Wildlife Diversity Program. The 2003 study reported three rare species in the area. Historical and Archeological Resources: Historic resources were identified and described by consultant Thomas Arcuti and archeological resources by consultant Hartgen Archeological Associates in 1999 for a different project being studied at this time. Our subconsultant will update this resource information as needed based upon the current project and the alternatives outlined in this scope. The following is a summary for the work to be completed by our subconsultant: An Archeological Resource Assessment Report will be prepared that will include the details on the resources identified as well as an assessment of the archeological sensitivity and potential of the project area and recommendations regarding Phase IB testing. An Architectural Resource Identification Report will be prepared and will contain a background history and context statement for the project Area of Potential Effect (APE) with history maps and photos necessary to support the findings. If applicable, National Register eligibility recommendation for each structure or district will be presented. This work will be closely coordinated with VTrans Historic Preservation and Archeology Officers. Section 4(f) Resources: Public parks or historic resources that may qualify as Section 4(f) resources in the project vicinity will be identified. Regional Planning Commission 1-4 Winooski Burlington, VT

5 Section 6(f) Resources: The State of Vermont coordinator will be contacted to determine whether Section 6(f) resources are present. Socioeconomic Characteristics and Environmental Justice: The socioeconomic characteristics will be identified based on the ECOS database and other readily available information. Air Quality: It is assumed the project will not substantially alter air quality or result in an increase of 10,000 vehicles per day over 10 years. These considerations will be addressed, but no formal analyses are proposed. Noise Sensitive Land Uses: Existing sensitive receptors such as residential land use will be identified. The potential for the project to qualify as a Type 1 federal highway project requiring noise analysis will be addressed. It is assumed no formal noise analysis will be needed for the scoping study. Aesthetics and community character: The aesthetics of the bridge and its surroundings, including views of and from the bridge, will be reviewed in the field from a variety of vantage points, and will be described briefly in the scoping report. Resource information will be presented in a separate Resource Identification Chapter of the Project Scoping Report. Resources will be briefly described, and a resource inventory drawing will be prepared. Impacts to identified resources will be quantified (to the extent possible) for each alternative under consideration. This information will also be summarized in the overall alternative evaluation matrix to be contained in the Scoping Report. Included will be a tabulation of any anticipated permit requirements for each alternative. 3.0 PURPOSE AND NEED Following the Local Concerns meeting, MJ will develop a draft Purpose and Need Statement that defines the problem and associated needs for the Winooski River Bridge. MJ will forward the draft Purpose and Need Statement to the CCRPC, cities of Burlington and Winooski, and designated VTrans staff for their review and comment. The revised draft Purpose and Need Statement will be presented at a public meeting. Any comments received from the public will be used to finalize the Purpose and Need Statement. 4.0 PUBLIC PARTICIPATION PLAN 4.1 Advisory Committee Meetings - MJ will attend four (4) Advisory Committee meetings. The CCRPC will lead the formation of the Advisory Committee. The purpose of the Advisory Committee is to provide general oversight and direction for this project. The committee may include representatives from the following bodies/organizations/agencies: City of Burlington Regional Planning Commission 1-5 Winooski Burlington, VT

6 City of Winooski Vermont Agency of Transportation (VTrans) Regional Planning Commission (CCRPC) Green Mountain Transit (GMT) Ward 1 Neighborhood Planning Assembly UVM Medical Center Local Motion CATMA Others as needed, potentially including City Councilors A total of four (4) Advisory Committee meetings will occur for this Scoping Study to correspond to the following key project milestones: Advisory Committee Meeting #1: Project Kick-Off Advisory Committee Meeting #2: Review of Draft Purpose and Need Statement Advisory Committee Meeting #3: Development of Build Alternatives Advisory Committee Meeting #4: Evaluation of Build Alternatives and Evaluation Matrix (see Task 6.2) Deliverables (for each meeting) Invitation, Agenda, Sign-in Sheet, Meeting Minutes PowerPoint Presentation and relevant graphics (mounted on boards) Assumptions Advisory Committee meetings will be attended by two (2) Consultant staff. CCRPC will secure the location of each of the four (4) meetings. 4.2 Project Web Site - The CCRPC will host and manage a project-specific web page on the existing CCRPC website. Materials developed under other tasks will be provided by MJ for CCRPC posting on the web site. These materials are anticipated to include the following: general project information; project schedule; maps, graphics and other visuals; public meeting notices and meeting notes; web-based survey and results; meeting dates and locations; and study documents. Assumptions: MJ, in collaboration with the CCRPC, will develop publicity materials including press release, informational postcards, calendar listings, and social media releases. The project web site will be used to keep updated project information available to the public. 4.3 Draft Alternatives Workshop / Local Concerns Meeting - MJ will conduct a draft alternatives workshop to solicit public and stakeholder input, and concerns, on the draft alternatives considered. Following the meeting, MJ will prepare a brief Technical Memorandum on the feedback received. Regional Planning Commission 1-6 Winooski Burlington, VT

7 Deliverables Publicity materials (press release, informational postcards, provide CCRPC with information for social media posts) Public Information Meeting PowerPoint Presentation and/or boards. Agenda, Sign-in Sheet, Meeting Minutes Assumptions: MJ will develop publicity materials including press release, informational postcards, and social media posts. Meeting will be attended by three (3) Consultant staff. CCRPC will secure the location of meeting and will be ADA compliant. 5.0 DEVELOPMENT OF ALTERNATIVES The Purpose and Need Statement, evaluation of current and future conditions, as well as inputs from the advisory committee, stakeholders (including via a meeting between VTrans-bridge and MJ) and the public will be used to help guide the development of the alternatives. The development will include preliminary analysis, plans / graphics, construction cost estimates and life cycle cost comparisons. It is currently assumed that the alternatives to be investigated will include the following; the specifics of the build alternatives will be further defined upon completion of the Purpose and Need task: 1. No Build 2. Bridge Rehabilitation 3. Bridge Superstructure Replacement with Substructure Widening 4. Bridge Replacement (a total of two different alternatives) The No-Build, or do nothing, alternative must always be considered in the range of alternatives. The No-Build will serve as a base to compare other alternatives to. For this project, the No-Build alternative would simply result in a continuation of the conditions that already exist. Because the Winooski River Bridge is an extremely important regional facility, it is currently assumed that traffic will be maintained during bridge construction. Accelerated Bridge Construction (ABC) techniques will be considered for the alternatives to shorten the duration of construction and impacts to regional traffic. The Slide-In-Bridge (lateral slide) method will be one of the techniques considered. The Evaluation Matrix will be used to provide a comparison of the alternatives, in general terms, for their suitability to ABC techniques. Construction of the bridge cross section will most likely require staging to maintain a portion of the travel way and sidewalk for traffic. Due to existing constraints at each end of the bridge, it is unlikely that construction of an adjacent temporary bridge would be feasible to carry vehicular traffic during construction. Regional Planning Commission 1-7 Winooski Burlington, VT

8 Bridge Rehabilitation Alternative will be based upon either the three-lane or four-lane traffic scenario, which will be determined subsequent to the findings of the traffic analyses. It is assumed that a three-lane alternative would retain the existing bridge typical section but one lane would be converted to shoulders to carry the bike lanes. A four-lane alternative would require a separate pedestrian bridge, and the superstructure and sidewalks would require modifications to accommodate the bike lanes on the existing bridge. As a minimum, rehabilitation measures are expected to include partial depth replacement of the bridge deck and sidewalks; rehabilitation or replacement of the bridge rail; painting of the structural steel; and isolated repairs to structural steel and concrete substructure at targeted locations in need. Bridge Superstructure Replacement Alternative would consist of the replacement of the existing superstructure and widening of the existing substructure as determined necessary to support the new girder framing system. This alternative will extend the service life of the bridge superstructure and potentially offer options to improve some functional aspects of the crossing. Bridge Replacement Alternatives would consist of the replacement of the existing bridge superstructure and substructure. These alternatives will be of higher initial construction cost than the other alternatives but provide for a greater lifespan and options to improve and add pedestrian and bicycle facilities on the bridge. It is assumed that the two alternatives would consist of a two-span and single-span bridge. The singlespan alternative would consist of a long span signature type structure for this prominent location bridging Burlington and Winooski. Hydraulic Evaluation - Using the previously gathered hydraulic information and data, MJ will consider the suitability of the various alternatives in terms of hydraulic performance. Traffic Control During Construction - Two construction staging alternatives will be evaluated including: Alternating one-way traffic (two-phase construction) Single lane of traffic maintained in each direction (three-phase construction) The concept of a complete closure of the bridge will not be evaluated. Also, potential diversion of traffic during construction will not be evaluated. Each construction staging alternative will be qualitatively evaluated for impacts to vehicular traffic as well as emergency vehicles. No traffic analysis will be performed. Each of these alternatives assumes a single 5 wide sidewalk will be maintained across the bridge during construction and bicyclists will ride with traffic through the work zone or walk their bicycles on the sidewalk. Resource Agency Coordination MJ understands how important it is to engage the resource agencies early and throughout the project to resolve key concerns during the Regional Planning Commission 1-8 Winooski Burlington, VT

9 alternative screening process. alternatives become defined. The following agencies may be consulted as the Vermont Agency of Natural Resources Watershed Management Division Wetlands Program Rivers Program Wildlife Diversity Program Department of Fish and Wildlife VTrans: Environmental Section (Historic Preservation and Archaeology Officers) and other relevant Divisions U.S. Army Corps of Engineers U.S. Fish and Wildlife Service MJ will invite the resource agencies to all public meetings. It is assumed MJ will attend one (1) resource agency meeting at VTrans after conceptual alternatives and resource impacts have been identified. MJ will prepare meeting handouts and visuals (resource mapping, preliminary alternatives, and a preliminary evaluation matrix), and discuss impacts of potential alternatives on key resource constraints. MJ will also coordinate with VTrans, whose staff serves as State Historic Preservation Officers, and have primary responsibility regarding Section ALTERNATIVES EVALUATION 6.1 Evaluation Matrix Each of the alternatives will be developed to comparable levels utilizing the resource constraints identified as a basis for comparing impacts. Plans depicting the alternatives will consist of the alternatives overlaid on the base mapping, and a typical section. Each alternative will be evaluated and compared to the No-Build alternative based on a variety of criteria including costs; engineering features; environmental, cultural, traffic and other impacts; and the degree to which each alternative satisfies the project s Purpose and Need. The Risk Register methodology will be used to assist in evaluating the alternatives for risk. Resource impacts will be identified and described qualitatively. In some cases, an approximate quantity or range of impact, such as square footage of river impact, may be identified. All information will be summarized in the project s Evaluation Matrix. Needed permits will also be identified and included in the evaluation matrix. The alternative development process and evaluation will be documented in the Scoping Report. Regional Planning Commission 1-9 Winooski Burlington, VT

10 6.2 Evaluation Matrix Presentation to the Advisory Committee Upon development of the draft Alternative Evaluation Matrix, MJ will submit copies of the alternative plans and Evaluation Matrix to the CCRPC for initial review and comment. MJ will revise the documents based on CCRPC s input and send them to the Advisory Committee for review and discussion at the fourth and final Advisory Committee Meeting (see Task 4.1). At this meeting the Advisory Committee will review and discuss the Alternatives and draft Evaluation Matrix. If possible, the Advisory Committee will endorse an alternative to recommend to both the Burlington and Winooski City Councils for acceptance. Upon resolution of any committee comments, MJ will work with the CCRPC to develop a web-based survey to solicit public and stakeholder input on the proposed alternatives. MJ will summarize the results and present them at the Alternatives Presentations meetings in Burlington and Winooski (Task 7.0). Deliverables Drawing plan & typical section of each alternative Evaluation matrix Assumptions The web-based survey will be sent to the database of stakeholders, participants, and those who expressed interest in the project. 7.0 BURLINGTON AND WINOOSKI CITY COUNCILS - ALTERNATIVES PRESENTATIONS The consultant, CCRPC and City staff will present the Winooski Main Street Bridge scoping including alternatives development and evaluation, public process, and the Advisory Committee s recommended alternative to the Winooski and Burlington City Councils. The outcome of the meetings should be a locally preferred alternative for the Winooski River Bridge selected by both City Councils. Deliverables (for each meeting) Invitation to Stakeholders (via ) Drawing plan and typical section of each alternative, evaluation matrix, and summary of web-based survey results Summary of the project s public process PowerPoint Presentation and relevant graphics (mounted on boards) Assumptions Alternatives Presentation meetings will be attended by two (2) Consultant staff. There will be one meeting with the Winooski City Council and one meeting with the Burlington City Council. CCRPC will secure the location of the meetings Regional Planning Commission 1-10 Winooski Burlington, VT

11 8.0 DRAFT AND FINAL SCOPING REPORT Upon obtaining consensus relative to a locally preferred alternative, the MJ team will complete a Draft Scoping Report and submit it to the CCRPC for review and comment. MJ will then incorporate any comments into a Final Scoping Report. MJ will prepare 6 hard copies of the final scoping report for the CCRPC, Burlington, Winooski and VTrans. 9.0 PROJECT MANAGEMENT AND COORDINATION MJ will coordinate with the CCRPC Project Manager on a regular basis throughout the duration of this project and with the Cities of Burlington and Winooski as well as VTrans as appropriate. MJ will maintain the project schedule and report progress as part of each invoice and encourage feedback throughout the scoping process. All correspondence will occur through the CCRPC and MJ Project Managers. Regional Planning Commission 1-11 Winooski Burlington, VT

12 TECHNICAL ASSUMPTIONS FOR SCOPING OF THE MAIN STREET BRIDGE OVER THE WINOOSKI RIVER The following is a list of additional assumptions regarding the proposed scope of work: 1. A base plan will be developed from readily available information. No digital terrain model will be developed and no roadway profile or cross sections will be required. 2. The study area for resource identification will be approximately 200 away from the bridge in all directions. 3. Natural resource information is assumed to be available from existing sources except when otherwise noted. 4. One resource agency meeting is assumed to be needed. 5. Although a consulting archeologist and consulting historian previously prepared a resource identification report, this work will be updated by MJ s subconsultant. 6. MJ staff will be responsible for any coordination with the VT Division for Historic Preservation. This scope of work does not include Act 250 involvement or any other environmental permits or approvals. 7. No structural analyses will be required. 8. If evaluation of the four-lane bridge rehabilitation alternative is needed, MJ will not develop plans or costs for the separate pedestrian bridge but will instead incorporate the information from the recent study by others. And such information will be used to help compare the bridge rehabilitation alternative to the other alternatives. 9. Written project materials and notices do not need to be in a language other than English. 10. Newspaper notices will be in the form of a press release. Legal advertisements are not part of the scope of work. 11. Post cards developed to inform the public on the project will be limited to 500 total, printed in black and white. The CCRPC will be responsible for mailing or distributing the post cards. Regional Planning Commission 1-12 Winooski Burlington, VT

Scope of Work. Project Approach and Understanding. Task 1: Study Initiation and Administration

Scope of Work. Project Approach and Understanding. Task 1: Study Initiation and Administration Scope of Work Route 116/Hinesburg Growth Center Corridor Study Town of Hinesburg and CCRPC Project Approach and Understanding Route 116 through Hinesburg had seen substantial changes in the past 15 years,

More information

Exhibit A Mn/DOT Contract No

Exhibit A Mn/DOT Contract No Exhibit A Mn/DOT Contract No. 98142 SCOPE OF WORK AND DELIVERABLES Preliminary Design Red Wing US 63 Bridge and Approach Roadways State Project (SP) 2515-21 SCOPE OVERVIEW... 2 SCHEDULE... 2 PROJECT TASK

More information

CHITTENDEN COUNTY REGIONAL PLANNING COMMISSION Winooski/Burlington, US RTs 2 & 7 Bridge Scoping Study ADVISORY COMMITTEE MEETING NO.

CHITTENDEN COUNTY REGIONAL PLANNING COMMISSION Winooski/Burlington, US RTs 2 & 7 Bridge Scoping Study ADVISORY COMMITTEE MEETING NO. CHITTENDEN COUNTY REGIONAL PLANNING COMMISSION Winooski/Burlington, US RTs 2 & 7 Bridge Scoping Study ADVISORY COMMITTEE MEETING NO. 5 Agenda: 1. Welcome/Introductions 2. Progress & Updates Since Previous

More information

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction Chapter 1 Bridge Design Manual General Design Information Section 1.02 Selection and Geometry Introduction Selection or Rehabilitation Report This section of the design manual provides guidance on the

More information

Conceptual Design Report

Conceptual Design Report Conceptual Design Report I-244/Arkansas River Multimodal Bridge Tulsa, Oklahoma Prepared for the Oklahoma Department of Transportation Prepared by: August 2009 I-244 / ARKANSAS RIVER MULTIMODAL BRIDGE

More information

SAN ANTONIO STREET BRIDGE AT COMAL RIVER. Open House

SAN ANTONIO STREET BRIDGE AT COMAL RIVER. Open House SAN ANTONIO STREET BRIDGE AT COMAL RIVER Open House May 1, 2018 SAN ANTONIO STREET BRIDGE AT COMAL RIVER, NEW BRAUNFELS COMAL COUNTY OPEN HOUSE MAY 1, 2018 5:00 P.M 7:00 P.M. New Braunfels Civic/Convention

More information

REHABILITATION PACKAGE 4-a

REHABILITATION PACKAGE 4-a 4-a WINONA BRIDGE (BRIDGE 5900) REHABILITATION PACKAGE 4-a Rehab option 4-a is a rehabilitation package whereby all spans of the existing steel truss structure would be rehabilitated and strengthened.

More information

Chester Bridge Environmental Assessment (EA) CAG Meeting #2. October 12, 2017

Chester Bridge Environmental Assessment (EA) CAG Meeting #2. October 12, 2017 Chester Bridge Environmental Assessment (EA) CAG Meeting #2 October 12, 2017 Agenda Introductions Purpose & Need review and Merger Approval Review of the Conceptual Alternatives Recap of the Public Meeting

More information

Rehabilitation of West Main Street Culvert and Shirley Street Bridge. Town of Ayer. November 22, 2016

Rehabilitation of West Main Street Culvert and Shirley Street Bridge. Town of Ayer. November 22, 2016 Rehabilitation of West Main Street Culvert and Shirley Street Bridge Town of Ayer November 22, 2016 Agenda Outline Introductions Project Goals and Objectives Existing Conditions Review Design Considerations

More information

Comprehensive Transportation Study for Glencoe, MN

Comprehensive Transportation Study for Glencoe, MN Comprehensive Transportation Study for Glencoe, MN Introduction and Project Information Introduction There have been a number of planning and preliminary engineering studies completed in the Glencoe area

More information

Railyard Enterprise Project (REP) Supplemental Scoping

Railyard Enterprise Project (REP) Supplemental Scoping FINAL SCOPE OF WORK DATE: November 11, 2016 PROJECT: PROJECT DESCRIPTION Railyard Enterprise Project (REP) Supplemental Scoping The City of Burlington and VTrans would like to further evaluate the REP

More information

Appendix. Sample EA/EIS Scope of Work

Appendix. Sample EA/EIS Scope of Work Appendix K Sample EA/EIS Scope of Work EA/EIS Sample Scope of Work The purpose of this Scope of Work (SOW) is to prepare an EA document pursuant to the National Environmental Policy Act (NEPA) to analyze

More information

Clinton Street Bridge over the Maumee River. ODOT Project DEF December 2, 2014 Stakeholder s Meeting

Clinton Street Bridge over the Maumee River. ODOT Project DEF December 2, 2014 Stakeholder s Meeting Clinton Street Bridge over the Maumee River ODOT Project DEF-15-14.77 December 2, 2014 Stakeholder s Meeting Purpose of Stakeholder Meeting Discuss the project and why it s happening Describe the process

More information

MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK

MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK The professional services to be provided by the Consultant under this Agreement shall be as necessary to complete the required analyses, layouts,

More information

Rapid City, SD HDR Project No RE: Replacement of Existing I-190 Twin Bridges at I-190/Silver Street Interchange, Rapid City, SD

Rapid City, SD HDR Project No RE: Replacement of Existing I-190 Twin Bridges at I-190/Silver Street Interchange, Rapid City, SD To: Steve Gramm, SDDOT Memo From: HDR Project: SDDOT I-190 Silver Street Interchange Study Rapid City, SD HDR Project No. 000000000137390 Date: December 27, 2011 RE: Replacement of Existing I-190 Twin

More information

Frequently Asked Questions Connecting Palo Alto

Frequently Asked Questions Connecting Palo Alto Frequently Asked Questions Connecting Palo Alto www.cityofpaloalto.org/connectingpaloalto General Project Questions Q1: What is Connecting Palo Alto? A1: Connecting Palo Alto (formerly the Palo Alto Rail

More information

Request for Proposals. Hillsdale Pedestrian/Bicyclist Bridge Design

Request for Proposals. Hillsdale Pedestrian/Bicyclist Bridge Design Request for Proposals Hillsdale Pedestrian/Bicyclist Bridge Design Public Works Department City of San Mateo 330 West 20th Avenue San Mateo, CA 94403 JUNE 13, 2013 The City of San Mateo (CITY) is accepting

More information

Preliminary Project Assessment

Preliminary Project Assessment DISCLAIMERS: Date: March 14, 2014 Case No.: 2014.0097U Project Address: Third Street Crossing of Islais Creek Block/Lot: Public Right-of-Way Zoning: Not Applicable Area Plan: Not Applicable Project Sponsor:

More information

Table Table 7.2 Potential Environmental Impacts and Mitigation Measures

Table Table 7.2 Potential Environmental Impacts and Mitigation Measures 7.2 Natural Environment/Environmental Planning Executive Summary/Key Points The Environmental Consultation and Mitigation Plan establishes: o A process for consultation with environmental resource agencies

More information

9.0 I-26 & I-526 Interchange Improvements

9.0 I-26 & I-526 Interchange Improvements 9.0 I-26 & I-526 Interchange Improvements The I-26 & I-526 System-to-System interchange currently consists of a combination of directional and loop ramps providing for all movements from one Interstate

More information

Interstate 73 FEIS: I-95 to the Myrtle Beach Region Chapter 4. Public Involvement and Agency Coordination

Interstate 73 FEIS: I-95 to the Myrtle Beach Region Chapter 4. Public Involvement and Agency Coordination 4-65 Interstate 73 FEIS: I-95 to the Myrtle Beach Region 4-66 Comment noted. The use of existing roadways was considered during alternative development (refer to Chapter 2, Section 2.1, page 2-1 and the

More information

I. PROJECT INITIATION

I. PROJECT INITIATION REPLACE BELLE CHASSE TUNNEL AND BRIDGE STAGE 1 - ENVIRONMENTAL ASSESSMENT PLAQUEMINES PARISH, LOUISIANA (State Project No. 700-38-0108) / H.004791 Background This is a scope of services for the preparation

More information

CMNAA. Central Manatee Network Alternatives Analysis Alternatives Public Meeting CMNAA STUDY PROCESS. STUDY AREA 17th St. W

CMNAA. Central Manatee Network Alternatives Analysis Alternatives Public Meeting CMNAA STUDY PROCESS. STUDY AREA 17th St. W District One CMNAA Central Manatee Network Alternatives Analysis December 12, 2017 5:00 pm - 7:00 pm First Baptist Church 1306 Manatee Ave. W, Bradenton, FL 34205 Central Manatee Network Alternatives Analysis

More information

BENNING ROAD & BRIDGES

BENNING ROAD & BRIDGES BENNING ROAD & BRIDGES DRAFT JUNE 2015 TRANSPORTATION IMPROVEMENTS ENVIRONMENTAL ASSESSMENT DRAFT MAY 2016 EXECUTIVE SUMMARY ES-1 This page left intentionally blank This page left intentionally blank

More information

SCOPE OF WORK AND DELIVERABLES

SCOPE OF WORK AND DELIVERABLES 1.0 PROJECT OVERVIEW The State of Minnesota (State) has identified the need for the replacement of Bridge 5308, a railroad bridge that carries the Canadian Pacific Railroad (CP Rail) over Trunk Highway

More information

LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE DRAFT ENVIRONMENTAL IMPACT STATEMENT

LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE DRAFT ENVIRONMENTAL IMPACT STATEMENT LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE DRAFT ENVIRONMENTAL IMPACT STATEMENT Project Name: Project Location: Lead Agency & Contact Person: SEQRA Classification: Project Sponsors:

More information

NJTPA 2014 Local Concept Development Study Hudson & Essex Counties Clay Street Bridge over the Passaic River. Public Information Center

NJTPA 2014 Local Concept Development Study Hudson & Essex Counties Clay Street Bridge over the Passaic River. Public Information Center NJTPA 2014 Local Concept Development Study Hudson & Essex Counties Clay Street Bridge over the Passaic River Public Information Center June 24, 2015 PROJECT STATUS Study Began January 2014 Data collection

More information

St. Francis Drive through the City of Santa Fe Corridor Study

St. Francis Drive through the City of Santa Fe Corridor Study VIII. ENGINEERING AND ENVIRONMENTAL EVALUATION INTERSECTION IMPROVEMENTS SOUTHERN For the southern end of the corridor, traffic volumes are expected to increase over existing levels. The Phase A Report

More information

TH 25 Bituminous Mill, Full Depth Reclamation and Overlay SP &

TH 25 Bituminous Mill, Full Depth Reclamation and Overlay SP & TH 25 Bituminous Mill, Full Depth Reclamation and Overlay SP 4910-29 & 0504-14 Contract No. 1002252 Project Overview is in need of professional and technical assistance to provide detail design for State

More information

Railyard Enterprise Project (REP) Scoping/Planning & Environmental Linkages (PEL) Study Steering Committee #3 Meeting Notes

Railyard Enterprise Project (REP) Scoping/Planning & Environmental Linkages (PEL) Study Steering Committee #3 Meeting Notes 110 West Canal Street, Suite 202 Winooski, Vermont 05404 802.846.4490 www.ccrpcvt.org Railyard Enterprise Project (REP) Scoping/Planning & Environmental Linkages (PEL) Study Steering Committee #3 Meeting

More information

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION AUGUST 2015 Table of Contents 1 Decision... 1 1.1 Project Description... 2 1.2 Basis for the FHWA Decision... 7 1.2.1

More information

Whittier Bridge I-95 Improvement Project Newburyport/Amesbury/Salisbury

Whittier Bridge I-95 Improvement Project Newburyport/Amesbury/Salisbury Whittier Bridge I-95 Improvement Project Newburyport/Amesbury/Salisbury EAE No. 14427 http://whittierbridge.mhd.state.ma.us/ Public Meeting 12.07.11 Whittier Bridge I-95 Improvement Project Newburyport/Amesbury/Salisbury

More information

EXHIBIT A SCOPE OF SERVICES INTERCHANGE JUSTIFICATION REPORT (IJR) FOR INTERSTATE 75 AT OVERPASS ROAD

EXHIBIT A SCOPE OF SERVICES INTERCHANGE JUSTIFICATION REPORT (IJR) FOR INTERSTATE 75 AT OVERPASS ROAD Scope of Services 12/08/2008 EXHIBIT A SCOPE OF SERVICES INTERCHANGE JUSTIFICATION REPORT (IJR) FOR INTERSTATE 75 AT OVERPASS ROAD TABLE OF CONTENTS Section Pace I. 0 PROJECT DESCRIPTION........................,............................................................

More information

Traffic Impact Study Requirements

Traffic Impact Study Requirements [TYPE THE COMPANY NAME] Traffic Impact Study Requirements County of San Mateo Department of Public Works Roadway Services 9/1/2013 I. Introduction The County of San Mateo (County), Department of Public

More information

Reconstruction Project Update

Reconstruction Project Update I-65/I-70 North Split Interchange Reconstruction Project Update September 18, 2017 Agenda Welcome/introductions Project overview Scope and limits Need Environmental Assessment Maintenance of traffic Financial

More information

Austin Avenue Bridges Project Walking Tour Agenda

Austin Avenue Bridges Project Walking Tour Agenda Agenda Event Start End Introductions and Overview 9:00 Environmental Process Section 106 and Consulting Parties Historic Significance of Bridges Project Background Bridge Components Bridge Conditions 9:30

More information

5.0 PRELIMINARY ENVIRONMENTAL REVIEW

5.0 PRELIMINARY ENVIRONMENTAL REVIEW 5.0 PRELIMINARY ENVIRONMENTAL REVIEW 5.1 INTRODUCTION A preliminary environmental review was performed on the proposed freeway improvements that form Concept C, which encompasses the three freeway corridors

More information

I-95/US 322 Interchange Improvement Project. Website Update

I-95/US 322 Interchange Improvement Project. Website Update I-95/US 322 Interchange Improvement Project Website Update The following is an outline of the I-95/US 322 website showing the primary pages and then sub-pages within the primary pages. The outline indicates

More information

TIER 2 EIS SCOPING MEETING WELCOME TO THE FEDERAL AVIATION ADMINISTRATION SCOPING MEETING

TIER 2 EIS SCOPING MEETING WELCOME TO THE FEDERAL AVIATION ADMINISTRATION SCOPING MEETING TIER 2 EIS SCOPING MEETING WELCOME TO THE FEDERAL AVIATION ADMINISTRATION SCOPING MEETING TIER 2 EIS OVERVIEW SOUTH SUBURBAN INAUGURAL AIRPORT ENVIRONMENTAL IMPACT STATEMENT The proposed, (SSA) will require

More information

Procedure for NEPA for County or City Projects

Procedure for NEPA for County or City Projects Procedure for NEPA for County or City Projects I. County or City Projects with any Federal Highway funding or action shall be submitted to Environmental Program Division (EPD) with a request to start studies

More information

GUIDE FOR THE PREPARATION OF TRAFFIC IMPACT STUDIES

GUIDE FOR THE PREPARATION OF TRAFFIC IMPACT STUDIES GUIDE FOR THE PREPARATION OF TRAFFIC IMPACT STUDIES Adopted by Town Council on November 25, 2008 Prepared By: HNTB Engineering Department Planning Department TABLE OF CONTENTS I. INTRODUCTION... 1 II.

More information

Final Design Guideline

Final Design Guideline Final Design Guideline May, 2016 July, 2011 Check the Capital Project Delivery website to ensure this is the current version Table of Contents Purpose... 1 Introduction... 1 FD Support... 1 Roadway and

More information

STRUCTURE AND BRIDGE DIVISION

STRUCTURE AND BRIDGE DIVISION Sheet 1 of 8 VIRGINIA DEPARTMENT OF TRANSPORTATION STRUCTURE AND BRIDGE DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: State of Good Repair Bridge Project Selection and Eligible Work

More information

Article 16 Traffic Impact Analysis

Article 16 Traffic Impact Analysis Article 16 Traffic Impact Analysis Table of Contents... 16-1 Chapter 16.1 Purpose and Intent... 16-2 Chapter 16.2 Applicability... 16-2 Chapter 16.3 Exemptions... 16-2 Chapter 16.4 Trip Generation Data...

More information

VENETIAN CAUSEWAY. (Venetian Way) Project Development & Environment (PD&E) Study FROM NORTH BAYSHORE DRIVE TO PURDY AVENUE. FM No.

VENETIAN CAUSEWAY. (Venetian Way) Project Development & Environment (PD&E) Study FROM NORTH BAYSHORE DRIVE TO PURDY AVENUE. FM No. VENETIAN CAUSEWAY (Venetian Way) Project Development & Environment (PD&E) Study FROM NORTH BAYSHORE DRIVE TO PURDY AVENUE FM No. 422713-2-22-01 Efficient Transportation Decision Making (ETDM): 12756 Project

More information

Central Manatee Network Alternatives Analysis

Central Manatee Network Alternatives Analysis District One CMNAA Central Manatee Network Alternatives Analysis Central Manatee Network Alternatives Analysis The Florida Department of Transportation (FDOT) is conducting the Central Manatee Network

More information

State Route 8 Bridge Replacement Project

State Route 8 Bridge Replacement Project OPEN HOUSE PUBLIC INVOLVEMENT MEETING Celebration Church 688 Dan Street, Akron, Ohio Tuesday, July 14, 2015 5:00 PM to 7:00 PM State Route 8 Bridge Replacement Project Existing Bridge Future Bridges: Steel

More information

6 th STREET VIADUCT SIESMIC IMPROVEMENT PROJECT

6 th STREET VIADUCT SIESMIC IMPROVEMENT PROJECT 6 th STREET VIADUCT SIESMIC IMPROVEMENT PROJECT Project Location The 6 th Street Viaduct (Bridge No. 53C-1880) and Sixth Street Overcrossing (Bridge No. 53-0595) comprise a single structure, which spans

More information

I-91 Viaduct Public Information Briefing

I-91 Viaduct Public Information Briefing I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 10 December 18, 2017 Agenda Welcome Update on Construction Activities (Full Beneficial Use) Next:

More information

Public Meeting for SH-85A Horse Creek Bernice, OK. SH-85A bridge located 3.5 miles east of SH-85, including west and east approaches

Public Meeting for SH-85A Horse Creek Bernice, OK. SH-85A bridge located 3.5 miles east of SH-85, including west and east approaches WELCOME Public Meeting for SH-85A Horse Creek Bernice, OK SH-85A bridge located 3.5 miles east of SH-85, including west and east approaches Randle White, PE ODOT Division VIII Engineer PURPOSE OF THIS

More information

City of Fairfax, Virginia City Council Regular Meeting

City of Fairfax, Virginia City Council Regular Meeting City Council Regular Meeting Agenda Item # 7b City Council Meeting 5/10/2016 TO: FROM: SUBJECT: ISSUE(S): SUMMARY: Honorable Mayor and Members of City Council Robert Sisson, City Manager Consideration

More information

MnDOT Contract Exhibit A - Scope of Services

MnDOT Contract Exhibit A - Scope of Services Project Development for Pavement Rehabilitation and Pedestrian Access -Improvements on TH 22 in Glencoe, MN from US 212 to Cedar Ave. (R.P. 106+00.650 to 108+00.141) -Improvements on TH 71 in Olivia, MN

More information

CHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION

CHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION CHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION SECTION 2B 1 - GROUND SURVEYS Survey Authorization... 2B-1 Interstate... 2B-1 Principal / Minor Arterial... 2B-1 Urban...

More information

The Norwich Street Bridge

The Norwich Street Bridge The Norwich Street Bridge Class Environmental Assessment Open House May 17, 2017 6:30-8 p.m. Guelph City Hall Phase 1 Phase 2 Project File Our Study Process: This study is being undertaken as a Schedule

More information

Summary. Preliminary Alternative Development and Screening. DEIS July 23, 2018

Summary. Preliminary Alternative Development and Screening. DEIS July 23, 2018 What is the Carolina Crossroads Project? The South Carolina Department of Transportation (SCDOT), in cooperation with the Federal Highway Administration (FHWA), is proposing to upgrade and redesign a key

More information

ASCE STRUCTURAL ENGINEERING CONFERENCE. Ames Iowa

ASCE STRUCTURAL ENGINEERING CONFERENCE. Ames Iowa 2014 HDR Architecture, 2014 HDR, Inc., all rights reserved. ASCE STRUCTURAL ENGINEERING CONFERENCE Ames Iowa WHAT DO YOU DO IF YOU HAVE MORE PROJECT THAN BUDGET? DESIGN BUILDER SELECTION METHOD Fixed Price

More information

2.0 Purpose. 3.0 Work Plan. Page 1 of 7

2.0 Purpose. 3.0 Work Plan. Page 1 of 7 2.0 Purpose The purpose of this document is to present the findings of the field investigation and concept design study, as well as recommend appropriate track relocation and bridge modifications to provide

More information

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS, CENTER FOR ENVIRONMENTAL EXCELLENCE, HISTORIC BRIDGES COMMUNITY OF PRACTICE

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS, CENTER FOR ENVIRONMENTAL EXCELLENCE, HISTORIC BRIDGES COMMUNITY OF PRACTICE AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS, CENTER FOR ENVIRONMENTAL EXCELLENCE, HISTORIC BRIDGES COMMUNITY OF PRACTICE HISTORIC BRIDGE REHABILITATION AND MAINTENANCE CASE STUDY

More information

LOCATION AND DESIGN DIVISION

LOCATION AND DESIGN DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Design Exceptions / Waivers SPECIFIC SUBJECT: Design Exception Request Form

More information

EXHIBIT "A" County Road 54 (Wesley Chapel Boulevard) (from North of Magnolia Boulevard to Oakley Boulevard) Work Order No. C-1640.

EXHIBIT A County Road 54 (Wesley Chapel Boulevard) (from North of Magnolia Boulevard to Oakley Boulevard) Work Order No. C-1640. EXHIBIT "A" County Road 54 (Wesley Chapel Boulevard) (from North of Magnolia Boulevard to Oakley Boulevard) Work Order No. C-1640.00 SECTION I PURPOSE This document describes the scope of work and the

More information

Northwest State Route 138 Corridor Improvement Project

Northwest State Route 138 Corridor Improvement Project Northwest State Route 138 Corridor Improvement Project Los Angeles County, CA DISTRICT 7- LA- 138 (PM 0.0/36.8); DISTRICT 7- LA- 05 (PM 79.5/83.1); DISTRICT 7- LA- 14 (PM 73.4/74.4) 265100/ 0700001816

More information

PROPOSED SCOPE OF WORK: REGIONAL ANALYSIS AND LONG-RANGE PLAN FOR EXPANSION OF SUBMARINE SHIPBUILDING

PROPOSED SCOPE OF WORK: REGIONAL ANALYSIS AND LONG-RANGE PLAN FOR EXPANSION OF SUBMARINE SHIPBUILDING PROPOSED SCOPE OF WORK: REGIONAL ANALYSIS AND LONG-RANGE PLAN FOR EXPANSION OF SUBMARINE SHIPBUILDING PHASE 1: PROJECT START-UP 1.1 KICK OFF MEETING Our work will begin with a kick-off meeting with the

More information

Public Information Meeting Information Packet: Childress Drive Bridge over South Utoy Creek June 29, 2016

Public Information Meeting Information Packet: Childress Drive Bridge over South Utoy Creek June 29, 2016 Public Information Meeting Information Packet: Childress Drive Bridge over South Utoy Creek June 29, 2016 Welcome to the Public Information Meeting for the proposed replacement of the Childress Drive Bridge

More information

Red Wing Bridge Alternates

Red Wing Bridge Alternates Alternate 1 Tied Arch Alternate 2 Simple Span Truss Alternate 1 Design Drawing Alternate 2 Design Drawing Similar Bridge Design to Alternate 1 Similar Bridge Design to Alternate 2 Evaluation Matrix for

More information

Canadian Consulting Engineering Awards 2016 CANADIAN NIAGARA POWER FOREBAY BRIDGE RECONSTRUCTION

Canadian Consulting Engineering Awards 2016 CANADIAN NIAGARA POWER FOREBAY BRIDGE RECONSTRUCTION Canadian Consulting Engineering Awards 2016 CANADIAN NIAGARA POWER FOREBAY BRIDGE RECONSTRUCTION April 2016 ELLIS Engineering Inc. 214 Martindale Road, Suite 201 St. Catharines, Ontario L2S 0B2 www.ellis.on.ca

More information

CHAPTER 7. Statewide Implementation Agreement

CHAPTER 7. Statewide Implementation Agreement CHAPTER 7 Statewide Implementation Agreement National Environmental Policy Act and Clean Water Act Section 404 Concurrent NEPA/404 Processes for Highway Projects in Iowa Note: This process is managed by

More information

WELCOME. QEW Credit River Bridge Detail Design Assignment from Mississauga Road to Hurontario Street. Public Information Centre Round #1 October 2017

WELCOME. QEW Credit River Bridge Detail Design Assignment from Mississauga Road to Hurontario Street. Public Information Centre Round #1 October 2017 WELCOME QEW Credit River Bridge Detail Design Assignment from Mississauga Road to Hurontario Street Public Information Centre Round #1 October 2017 Please Sign In PURPOSE OF THIS MEETING The Ontario Ministry

More information

LOCATION HYDRAULIC REPORT

LOCATION HYDRAULIC REPORT Draft LOCATION HYDRAULIC REPORT Florida Department of Transportation District One US 41 at Fruitville Road (CR 780) Intersection Improvements - PD&E STUDY Sarasota County, Florida Financial Project ID

More information

TOWN OF MOORESVILLE TRANSPORTATION IMPACT ANALYSIS PROCEDURES MANUAL TOWN OF MOORESVILLE, NORTH CAROLINA

TOWN OF MOORESVILLE TRANSPORTATION IMPACT ANALYSIS PROCEDURES MANUAL TOWN OF MOORESVILLE, NORTH CAROLINA TOWN OF MOORESVILLE TRANSPORTATION IMPACT ANALYSIS PROCEDURES MANUAL TOWN OF MOORESVILLE, NORTH CAROLINA Effective August 1, 2007 Amended March 4, 2013, December 1, 2014, May 1, 2017 TOWN OF MOORESVILLE,

More information

Review of Plans and Specs from a Constructability Perspective

Review of Plans and Specs from a Constructability Perspective Review of Plans and Specs from a Constructability Perspective The Executive Regional Manager and the Project Manager, with approval of the Director of Project Management, may request the Constructability

More information

I535 NB off ramp to I35 SB over I35 and the Burlington Northern Santa Fe (BNSF) Railroad I535 NB off ramp to I35 NB over I35 and the BNSF

I535 NB off ramp to I35 SB over I35 and the Burlington Northern Santa Fe (BNSF) Railroad I535 NB off ramp to I35 NB over I35 and the BNSF Final Bridge Design Twin Ports Interchange Bridges State Project Nos. (SP) 6980-60, 6915-136, 6982-322 Exhibit A Scope of Services PROJECT OVERVIEW State has programmed the construction of the Twin Ports

More information

Draft Environmental Assessment Terminal B/C Redevelopment, Secure National Hall, and Related Improvements

Draft Environmental Assessment Terminal B/C Redevelopment, Secure National Hall, and Related Improvements JUNE 2016 RONALD REAGAN WASHINGTON NATIONAL AIRPORT Draft Environmental Assessment Terminal B/C Redevelopment, Secure National Hall, and Related Improvements PREPARED BY: Ricondo & Associates, Inc. IN

More information

Work Breakdown Structure Element Dictionary Preliminary Engineering

Work Breakdown Structure Element Dictionary Preliminary Engineering Element Name Initiation PE 3.1 Initiation includes the implementation of the project s funding and notification of the consultant or in-house design staff to commence work, the Kickoff Meeting with the

More information

Oklahoma Department of Transportation Environmental Programs Division Office Fax

Oklahoma Department of Transportation Environmental Programs Division Office Fax Oklahoma Department of Transportation Environmental Programs Division Office 521-3050 Fax 522-5193 Documented Categorical Exclusion (DCE) for I-40: Pavement Reconstruction and Added Lanes from the Douglas

More information

Free Bridge Congestion Relief Project: Using FHWA s Eco-Logical Process

Free Bridge Congestion Relief Project: Using FHWA s Eco-Logical Process Free Bridge Congestion Relief Project: Using FHWA s Eco-Logical Process An Ecosystem Approach to Developing Infrastructure Projects June 27, 2014 Charlottesville Albemarle Metropolitan Planning Organization

More information

Cochran Mill Road Bridge over Tuscarora Creek

Cochran Mill Road Bridge over Tuscarora Creek Cochran Mill Road Bridge over Tuscarora Creek July 15, 2014 Brian Morrison, P.E. NOVA District Senior Structural Engineer (703) 259-2606 brian.morrison@vdot.virginia.gov Purpose & Need Purpose Update project

More information

NEPA and Design Public Hearings

NEPA and Design Public Hearings NEPA and Design Public Hearings Monday, December 5, 2016 Washington-Lee High School 1301 N. Stafford Street Arlington, VA 22201 Thursday, December 8, 2016 Mary Ellen Henderson Middle School 7130 Leesburg

More information

PUBLIC INFORMATION MEETING June 24, 2015

PUBLIC INFORMATION MEETING June 24, 2015 Gallows Road (RTE. 650) over Arlington Boulevard (RTE. 50) Fairfax County Bridge Rehabilitation, Preventive Maintenance and Pier Repairs Phase 1 - Project No. 0650-029-235; UPC 106956, Pier Repair Phase

More information

SCCRTC- MP San Lorenzo River Bridge Walkway Widening Feasibility Report

SCCRTC- MP San Lorenzo River Bridge Walkway Widening Feasibility Report SCCRTC- MP 19.43 San Lorenzo River Bridge Walkway Widening Feasibility Report May 19, 2016 INTRODUCTION Jacobs Engineering Group was selected to provide a feasibility report for the Santa Cruz County Regional

More information

Appendix C: Port Jervis Line Capacity Improvements Analysis. Technical Memorandum 2: Passing Siding Alternative

Appendix C: Port Jervis Line Capacity Improvements Analysis. Technical Memorandum 2: Passing Siding Alternative Appendix C: Port Jervis Line Capacity Improvements Analysis Technical Memorandum 2: Passing Siding Alternative January 2018 TABLE OF CONTENTS 1. Introduction... 1 2. Passing Sidings: Locations and Components...

More information

THE COMMONWEALTH OF MASSACHUSETTS NON-NHS BRIDGE R&R POLICY

THE COMMONWEALTH OF MASSACHUSETTS NON-NHS BRIDGE R&R POLICY THE COMMONWEALTH OF MASSACHUSETTS Number: P-92-010 Date: 10-08-92 - ) HIGHWAY DEPARTMENT FROM: NON-NHS BRIDGE R&R POLICY The purpose of this Engineering Directive is to formally notify Department Personnel

More information

Russell Street Design STPU M 8105(8) UPN

Russell Street Design STPU M 8105(8) UPN May 24, 2012 MORRISON MAIERLE,INC. Russell Street Design STPU M 8105(8) UPN 4128000 Missoula, Montana Project Understanding Key Project Elements Major urban arterial 1 of 5 river crossings over the Clark

More information

Downtown Estes Loop Project Frequently Asked Questions

Downtown Estes Loop Project Frequently Asked Questions May 15 th, 2015 Project Status 1) Has Alternative 1 already been selected? Is it a done deal? Response: The NEPA process will proceed with environmental analysis of both the No Action and Alternative 1.

More information

AGENCY MEETING. I-10E Planning & Environmental Linkages Meeting #1 TxDOT Houston District

AGENCY MEETING. I-10E Planning & Environmental Linkages Meeting #1 TxDOT Houston District AGENCY MEETING I-10E Planning & Environmental Linkages Meeting #1 TxDOT Houston District January 25, 2018 WELCOME TxDOT Project Manager: Grant Chim, P.E. Agenda 1 Introductions / Purpose of Meeting 2 What

More information

11 Joint Development Regulatory Context and Methodology

11 Joint Development Regulatory Context and Methodology 11 Joint Development This chapter describes the long-term direct and potential indirect impacts, and short-term direct and potential indirect impacts, of the proposed METRO Blue Line Light Rail Transit

More information

BUSINESS DISTRICT REVITALIZATION FUND $450,000 FOR DMP IMPLEMENTATION

BUSINESS DISTRICT REVITALIZATION FUND $450,000 FOR DMP IMPLEMENTATION BUSINESS DISTRICT REVITALIZATION FUND $450,000 FOR DMP IMPLEMENTATION Perform Master Plan Implementation Consulting: $50,000 Perform Post Office Site Evaluation (if necessary): $50,000 11 Agenda Packet

More information

REQUEST FOR PROPOSALS (RFP)

REQUEST FOR PROPOSALS (RFP) REQUEST FOR PROPOSALS (RFP) Date: December 8, 2016 To: Open Invitation to Professional Design/Engineering Consultants From: Department of Parks, Recreation & Waterfront, Planning Division Re: Professional

More information

NEW JERSEY DEPARTMENT OF TRANSPORTATION MEMORANDUM

NEW JERSEY DEPARTMENT OF TRANSPORTATION MEMORANDUM NEW JERSEY DEPARTMENT OF TRANSPORTATION MEMORANDUM TO: FROM: All Engineering & Support Staff Structural Evaluation James Lane, Manager Structural Evaluation DATE: January 2, 2008 PHONE: 530-3572 SUBJECT:

More information

CROWS LANDING CORRIDOR PLAN

CROWS LANDING CORRIDOR PLAN ATTACHMENT 1: SCOPE OF WORK CROWS LANDING CORRIDOR PLAN INTRODUCTION: StanCOG proposes the Crows Landing Corridor Plan (Plan), which is needed to determine the feasibility of inter-jurisdictional transportation

More information

The Main Street Bridge - Supporting Transportation Systems

The Main Street Bridge - Supporting Transportation Systems The Main Street Bridge - Supporting Transportation Systems October 28, 2015 So what is the Transportation System Project Background BACKGROUND N DOWNTOWN 70 70 SOUTH INNERBELT STUDY Existing Condition

More information

State Environmental Quality Review Act (SEQR) SCOPING DOCUMENT

State Environmental Quality Review Act (SEQR) SCOPING DOCUMENT State Environmental Quality Review Act (SEQR) SCOPING DOCUMENT Debra Lasouska Cluster Subdivision Town of Shawangunk, Ulster County, NY Draft Environmental Impact Statement SEQR CLASSIFICATION: LEAD AGENCY:

More information

APPENDIX B. Public Works and Development Engineering Services Division Guidelines for Traffic Impact Studies

APPENDIX B. Public Works and Development Engineering Services Division Guidelines for Traffic Impact Studies APPENDIX B Public Works and Development Engineering Services Division Guidelines for Traffic Impact Studies Revised December 7, 2010 via Resolution # 100991 Reformatted March 18, 2011 TABLE OF CONTENTS

More information

ENVIRONMENTAL ASSESSMENT

ENVIRONMENTAL ASSESSMENT ENVIRONMENTAL ASSESSMENT Section 408 Request to Alter the Brookville Local Protection Project for State Route 3033 Bridge Replacement in Jefferson County, PA May 16, 2018 Prepared By: Environmental and

More information

Oversight Team Meeting

Oversight Team Meeting Oversight Team Meeting September 18, 2014 INTRODUCTIONS (15 MINUTES) Name and affiliation Review agenda Edits to June s Oversight Team meeting summary Review the policy statements 2 Agenda Introduction

More information

SAFETY ASSESSMENTS FOR LOCAL TRANSPORTATION FACILITIES IN NEW YORK STATE

SAFETY ASSESSMENTS FOR LOCAL TRANSPORTATION FACILITIES IN NEW YORK STATE SAFETY ASSESSMENTS FOR LOCAL TRANSPORTATION FACILITIES IN NEW YORK STATE Quick Reference Guide Safety Assessments can save lives in New York State. They have been proven effective in practice, easy to

More information

ENVIRONMENTAL ASSESSMENT

ENVIRONMENTAL ASSESSMENT ENVIRONMENTAL ASSESSMENT Section 408 Request to Alter the Dubois Local Protection Project for the Beaver Drive sidewalk construction in Clearfield County, PA June 28, 2018 Prepared By: Environmental and

More information

Active Risk Management - Charles River Basin

Active Risk Management - Charles River Basin Protecting, Promoting and Enhancing our Commonwealth: Assisting MassDOT to deliver projects on Time and on Budget Active Risk Management - Charles River Basin September 18, 2013 & Massachusetts Accelerated

More information

Route 7/15 Norwalk Project - Update Winter Route 7/15 Norwalk. Presentation to Silvermine January 30, 2017 CTDOT State Project #

Route 7/15 Norwalk Project - Update Winter Route 7/15 Norwalk. Presentation to Silvermine January 30, 2017 CTDOT State Project # Project - Update Winter 2017 Agenda Introductions Project Goals Update on Work Status Alternative Development Project Schedule Review Next Steps Project Goals Provide for increased mobility and connectivity

More information

Northern Intermodal Transit Facility WHAT IS AN INTERMODAL TRANSIT FACILITY?

Northern Intermodal Transit Facility WHAT IS AN INTERMODAL TRANSIT FACILITY? WHAT IS AN INTERMODAL TRANSIT FACILITY? An intermodal transit facility gathers many modes of transportation together and is strategically located to increase destination alternatives. Intermodal facilities

More information

TRANSPORTATION IMPACT STUDIES

TRANSPORTATION IMPACT STUDIES January 28, 2009 POLICIES AND PROCEDURES FOR TRANSPORTATION IMPACT STUDIES Related to Highway Occupancy Permits Pennsylvania Department of Transportation Bureau of Highway Safety and Traffic Engineering

More information