August 22, 2014 FIRE ISLAND WIND

Size: px
Start display at page:

Download "August 22, 2014 FIRE ISLAND WIND"

Transcription

1 August 22, 2014 FIRE ISLAND WIND

2 Phase 1 Summary: Performance Project Performance: Benefits realized: 93,500 MWh LTD >875,000 MCF of NG burn avoided ~$6.5 MM in NG purchases avoided 55,000 tons of CO2 not emitted Total production 2013: 49,531 MWh vs. 51,180 budget Turbine Availability 98.5% - including planned maintenance outages Need photo here

3 Month MWh 2013 MWh 8,000 Fire Island Phase Production MWh 60,000 7,000 50,000 6,000 5,000 40,000 4,000 30,000 3,000 20,000 2,000 1,000 10,000 0 January February March April May June July August September October November December Actual Budget Cum. Actual Cum. Budget 0 Description Actual Budget Variance Production 49,530 51,180 (3.2)%

4 Actual curtailment vs. Expected CEA Curtailment of 25% 63% less curtailment than CEA anticipated Actual Expected DGE Actual 4,780 MWh 2013 Expected DGE 12,795 MWh

5 Phase 1 Summary: Energy Produced as Expected Integration Successful Curtailment well below expectations Impact on CEA frequency and reliability has been acceptable CEA Q status report to the RCA: "Chugach is not aware of any electrical system operational issues as a result of Chugach receiving energy from the Project. CEA April 2013 Final RCA Report: Chugach's generation and transmission assets have not experienced any negative impacts as a result of energy generated by the Project, and Chugach is not aware of any such impacts on the generation or transmission assets of any interconnected Railbelt utility. Construction and Operation of Phase 1 is a Success

6 Fire Island Wind Project Proposed Phase 2

7 Fire Island Wind, Phase MW project B String flanks the east ridgeline of island 11 General Electric 1.85 MW XLE wind turbines 29.7% Net Capacity Factor (NCF) P50 = 52,900 MWh Simplified transmission interconnection Shovel-ready project All material permits in-hand

8 Combined Production Phase 1 and Phase 2 14,000 12,000 Fire Island Wind Project Monthly Combined Production MWh 6,242 5,740 10,000 4,904 5,142 4,655 4,735 5,359 8,000 4,063 6,000 4,000 5,555 4,746 4,977 3,932 4,506 3,243 3,185 3,139 3,082 2,211 3,423 3,313 4,582 5,187 6,042 2,000 2,140 - Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec MWh P50 - Phase I MWh P50 - Phase II

9 Phase 2 Project Timeline ASAP Oct Dec Negotiate PPA Approval of PPA by RCA Construction RFP TSA contract Construction contract Close Financing NTP for contractors May start construction September completion September commissioning October - COD Time is of the essence! Qualified for 30% ITC worth ~ $40/MWh on Price

10 So, Why Hasn t The Project Moved Forward??? Buyer Needed Economic Hurdle Operational Hurdle Overcoming the Status Quo

11 Advantages of Expansion Overcoming the Economics Reduced capital requirement for Phase 2: Utilizes existing roads Switchgear O & M Facility Project Labor and Equipment Optimize Transmission Assets Much simpler contracting: PPA template previously approved by RCA Revise Interconnection Turbine supply Financing Much Lower Pricing

12 Phase 2 Project Energy Expect 52,900 MWh/year Price Phase 1: $0.0970/kWh for 25 years Phase 2 Price: $.07988/kWh for PPA 25 years $.06270/kWh escalating 25 years Phase 2 price is 18% lower (utilizes significant existing infrastructure)

13 Elements for Phase 2 Success Present Now: Shovel Ready Achievable Schedule Power Off-take: GVEA, CEA, or MEA Pricing is comparable to low depending on buyer Future tax savings uncertain Optimizes state investment in transmission Helps AK comply with EPA Clean Power Plan Moves us closer to State s 50% renewable goal

14 EPA imposes new mandatory rules: : EPA s proposed Clean Power Plan will regulate carbon emissions from existing fossilfueled power plants using the agency s authority under the Clean Air Act Overall goal of power sector - CO2 emission reduction of 30% of 2012 levels by 2030 Draft rules to be finalized in 2015 AKDEC craft approach to cut greenhouse-gas emissions State implementation plans due in RPS, energy efficiency, and/or buy carbon credits

15 FIW Phase 2 Offsets CO2 Emissions - Helps with compliance, EPA rule 111.d CO2 emission offsets will have significant future value one projection is below: Source: The Brattle Group

16 FIW Phase 2 Compares Favorably to Avoided Costs Current average avoided cost along with estimate of incremental avoided power cost in 2016, with and without effect of CO2 offsets. Avoided costs are compared to Phase 2 power plus wheeling.

17 Avg. Cost/MWh Net MWh GVEA Average Cost of Energy by Facility $1, ,000 $1,200 $1, ,000 $1,000 $ ,000 $800 $700 80,000 $600 $500 60,000 $400 $300 40,000 $200 $100 20,000 $0 0 Jun-13 Sep-13 Dec-13 Mar-14 Jun-14 North Pole Net MWh North Pole Exp. Net MWh CEA Net MWh FIW P2 Net MWh Avoided Cost Avg./MWh North Pole Avg. Cost/MWh North Pole Exp. Avg./MWh CEA Avg./MWh FIW P2 Avg./MWh

18 So, Why Doesn t The Project Move Forward??? Buyer Needed Economic Hurdle Operational Hurdle Changing the Status Quo Hurdle

19 Power Integration Typical Electric Utility Daily Load Shape 4 Balancing Areas System Operator: Supply = Demand, At lowest cost Source: U.S. DOE, 20% Wind Energy by 2030 (2008)

20 Megawatts Thermal plus Hydro Plenty of Capacity to Integration of Phase Installed Thermal and Hydro Generation vs. Peak Load by Utility CEA MLP GVEA MEA HEA hydro thermal peak load

21 Megawatts Integration with existing resources: There is capacity available to integrate FIWP Phase 2 2,500 Railbelt Installed Capacity vs. Peak Monthly Load Estimates 2,000 1,500 1,000 1,220 1,110 1, Installed Capacity excludes Units announced for retirement ,030 1,130 1, January February March April May June July August September October November December Railbelt 2016 peak estimate Installed Capacity

22 Integration - CAPACITY Railbelt Generation: Perfect for Integrating Wind 2012: Southcentral Power Plant: 3X1 CC LM : ML&P LM : ML&P Plant 2: 2X1 CC LM GE : MEA: 10 X 17.1 MW Wartsila 18V50DF Bradley Lake Hydro Cooper Lake Eklutna Hydro

23 Wartsila designed for flexibility

24 Source: Wartsila cycling flexibility

25 Integration ENERGY: Railbelt Energy Hydro-electric Natural gas Gas flexibility CINGSA Generous Imbalance allowances with pipelines Wind farm control system parameters Inertia Ramp rate control Curtailment of wind

26 MW wind different from forecast Integration how much gas flex is needed: FIW Phase 2 - MW of Wind Unplanned vs. MMBtu Fuel worst case/24 hour 8,000 HR Short gas imbalance MMBtu/day worst case Long gas imbalance Conservative: assumes no intra-day gas nom changes. Imbalance quantity still acceptable

27 Gas System Flexibility is Proven: Can accommodate unplanned start or shut down of a thermal unit if needed for wind integration Hilcorp tariff provides for significant imbalance Imbalance tolerance will work as the spring to enable unplanned gas burn or storage as needed Will be fully implemented November 1, 2014 Enstar operations 2014: unplanned start or shut down of a Beluga or similar unit is noise would not cause gas system reliability or curtailment issues. Imbalance provision exists today

28 Elements for Phase 2 Success Present Now: Integration Generation Capacity Operational flexibility Future Optimization Expanding Balancing Area Economic dispatch Bi-lateral cross-utility agreements

29 So, Why Doesn t The Project Move Forward??? Buyer Needed Economic Hurdle Operational Hurdle Overcoming the Status Quo

30 Combined Production Fire Island Phase 1 and Phase 2 as compared to Railbelt total sales Where there is a will, there is a way! Phase 2 energy is not a material amount compared to total Railbelt sales. There are ways and means to integrate Phase 2 smoothly. FIW Phase 2 as part of the total Railbelt Railbelt Total Sales FIW Phase 1 FIW Phase 2 Fire Island Wind total phase 1 plus phase 2 is approx. 2% of Railbelt energy. This is a very modest amount of wind compared to other regions of the country. 1% 1% 98%

31 Renewable Integration in Hawaii: Hawaii is an electrically islanded grid, similar to Railbelt. In 2012 renewable energy was 13.7% of statewide total. Source: Hawaii Energy Facts and Figures June 2013 Hawaii State Energy Office

32 Wind Integration in ERCOT: ERCOT is an electrically islanded grid, similar to Railbelt. In 2013 renewable energy was 9.9 % of ERCOT total example day below: Source: ERCOT Grid Operations

33 Wind Integration in ERCOT: ERCOT is a less flexible system than Railbelt no hydro and less natural gas to flex but still able to 10% wind energy. Source: ERCOT Grid Operations May 2014

34 Renewable Integration in BPA: Total wind capacity in BPA system is over 4,500 MW. During last week of July 2014 wind was nearly 1/3 of all generation serving load in BPA. Wind is nearly 30% of load and nearly equal to thermal generation in some periods Source:

35 01/01/14 00:00 01/01/14 04:55 01/01/14 09:50 01/01/14 14:45 01/01/14 19:40 01/02/14 00:35 01/02/14 05:30 01/02/14 10:25 01/02/14 15:20 01/02/14 20:15 01/03/14 01:10 01/03/14 06:05 01/03/14 11:00 01/03/14 15:55 01/03/14 20:50 01/04/14 01:45 01/04/14 06:40 01/04/14 11:35 01/04/14 16:30 01/04/14 21:25 01/05/14 02:20 01/05/14 07:15 01/05/14 12:10 01/05/14 17:05 01/05/14 22:00 01/06/14 02:55 01/06/14 07:50 01/06/14 12:45 01/06/14 17:40 01/06/14 22:35 01/07/14 03:30 01/07/14 08:25 01/07/14 13:20 01/07/14 18:15 01/07/14 23:10 01/08/14 04:05 01/08/14 09:00 01/08/14 13:55 01/08/14 18:50 01/08/14 23:45 01/09/14 04:40 01/09/14 09:35 01/09/14 14:30 01/09/14 19:25 01/10/14 00:20 01/10/14 05:15 01/10/14 10:10 01/10/14 15:05 01/10/14 20:00 Renewable Integration in BPA: Total wind capacity in BPA system is over 4,500 MW. Significant wind integration issues have been dealt with the Railbelt can do this as well! BPA wind generation vs total load January 1 through January 10, 2014 TOTAL WIND GENERATION IN BPA CONTROL AREA (MW) TOTAL BPA CONTROL AREA LOAD (MW) Source:

36 Development Options: Chugach, MEA or GVEA Diversifies supply portfolio Stabilizes prices for consumers Get ahead of the curve on new EPA rules Chugach wheels power in all cases MEA provides regulation to others Lot of daylight between $63 and $115/MWh to pay for integration and wheeling

37 Conclusion & Summary FIW P2 is a small but important project Clean, abundant, and economic Privately funded stimulates the economy Environmental benefits + avoided CO2 emissions penalty Moves toward AK State Energy Goal Much lower price than Phase 1 No significant impediment to successful construction Time to act is now Time is very short ITC value is $40/MWh. PTC is $ 23 $0.00

38 Contact Information Suzanne Gibson Cook Inlet Region, Inc

39 Supporting Information

40

41 System Impacts EPS study results 8/27/10 Assumes larger 33 unit 53 MW project - integration solely by CEA. The addition of the FIWF does not have any effect on the stability of the Railbelt system due to transient disturbances. The transient analysis found no stability issues due to the addition of the FIWF to the Railbelt system. The addition of FIWF capacity to the Railbelt grid did not result in any negative impacts to the Railbelt grid within the scope of this study. Need photo here

42 Wind Farm Power Regulation Final Report 3/4/11 EPS Assumes larger project at 33 units = 53 MW This study was undertaken with the assumption that Chugach would provide all of the regulation required for FIWF in order to meet its control area obligation. Analyzing the wind data indicated that the Chugach thermal generation or its hydro resources have the technical capability of regulating the ramp rates predicted for the wind farm. Although both simple-cycle and combined cycle generation has the capability of providing regulation for the wind resources, the natural gas suppliers and transportation company do not have the ability to deliver resources to match the capability of the generation. No longer true!! Gas system not a constraint

43 Wind Farm Power Regulation Final Report cont d. Conclusions - among other things: The incorporation of the FIWF into the Railbelt system does not present overly difficult technical obstacles or issues. The technical issues can be overcome with revisions to the current utility practice and planning. In the future, the ability to provide accurate, reliable hourly forecasts of wind energy hours in advance could lessen the integration costs and risk associated with the project. The constraining factor does not appear to be the electrical system, but the gas supply and delivery system. No longer true!! Gas system not a constraint

44 Fire Island Wind is Popular with Railbelt Consumers: Over 90% of consumers in Railbelt either support or are indifferent. Over 75% willing to pay more for Fire Island wind power Source: Cracium Research, Inc Fire Island consumer survey update

Wind Update. Renewable Energy Integration Lessons Learned. March 28, 2012

Wind Update. Renewable Energy Integration Lessons Learned. March 28, 2012 Wind Update Renewable Energy Integration Lessons Learned March 28, 212 Contents Summary Review of Historical Wind Growth and Output Impact of Wind on Operations Wind Curtailments Dispatchable Intermittent

More information

California Independent System Operator Corporation. California ISO. Import resource adequacy. Department of Market Monitoring

California Independent System Operator Corporation. California ISO. Import resource adequacy. Department of Market Monitoring k California Independent System Operator Corporation California ISO Import resource adequacy September 10, 2018 Department of Market Monitoring Summary This report provides an update of analysis and trends

More information

PGE s 2013 Integrated Resource Plan

PGE s 2013 Integrated Resource Plan PGE s 2013 Integrated Resource Plan OPUC Public Meeting 2014 Portland General Electric. All rights reserved. Today s topics IRP public process Load-resource balance Assumptions and inputs E3 low-carbon

More information

2011 RFP for All Generation Sources Proposal Conference

2011 RFP for All Generation Sources Proposal Conference 2011 RFP for All Generation Sources Proposal Conference August 16, 2011 Agenda Welcome and introductory remarks Chris Bevil, Manager Resource Acquisition RFP for All Generation Sources ( All Source RFP

More information

4. RAILBELT LOAD FORECASTS

4. RAILBELT LOAD FORECASTS 4. RAILBELT LOAD FORECASTS Much of the generation and transmission infrastructure of the Railbelt region of Alaska is aging and is at or near its time for replacement. The Railbelt is generally defined

More information

Eugene Water & Electric Board. The Future of Utilities in the Pacific Northwest

Eugene Water & Electric Board. The Future of Utilities in the Pacific Northwest Eugene Water & Electric Board The Future of Utilities in the Pacific Northwest 1 Eugene Water & Electric Board The Future of Utilities in the Pacific Northwest Erin Erben Manager, Power & Strategic Planning

More information

Results of California s Renewable Energy Program and Agricultural Biomass to Energy Program (SB704)

Results of California s Renewable Energy Program and Agricultural Biomass to Energy Program (SB704) 2 nd Annual California Biomass Collaborative Forum Results of California s Renewable Energy Program and Agricultural Biomass to Energy Program (SB704) Tony Gonçalves Program Lead Existing Renewable Facilities

More information

The Texas Experience: Implications of 8,000+ MW Wind Generation Resources In ERCOT. David Campbell CEO, Luminant 2009 Summer Seminar August 3, 2009

The Texas Experience: Implications of 8,000+ MW Wind Generation Resources In ERCOT. David Campbell CEO, Luminant 2009 Summer Seminar August 3, 2009 The Texas Experience: Implications of 8,000+ MW Wind Generation Resources In ERCOT David Campbell CEO, Luminant 2009 Summer Seminar August 3, 2009 Growth of Wind Generation in ERCOT MW 12,000 10,000 8,000

More information

A Bulk Energy Storage Resource Case Study with 40% RPS in 2024

A Bulk Energy Storage Resource Case Study with 40% RPS in 2024 A Bulk Energy Storage Resource Case Study with 40% RPS in 2024 Shucheng Liu Principal, Market Development 2015-2016 Transmission Planning Process Stakeholder Meeting February 18, 2016 California ISO Public

More information

Leading Insights into Solar

Leading Insights into Solar Leading Insights into Solar Fong Wan Senior Vice President, Energy Procurement Pacific Gas and Electric Company CalSEIA - SolarTech Summit May 7, 2009 Agenda California s Clean Energy History Renewable

More information

The Implications of Lower Natural Gas Prices for the Electric Generation Mix in the Southeast 1

The Implications of Lower Natural Gas Prices for the Electric Generation Mix in the Southeast 1 Highlights May 2009 Short Term Energy Outlook Supplement: The Implications of Lower Natural Gas Prices for the Electric Generation Mix in the Southeast 1 This supplement to the Energy Information Administration

More information

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid Greening the Grid Andhra Pradesh Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid State-specific results from Volume II, which includes all of India. The full reports

More information

ERCOT Public LTRA Probabilistic Reliability Assessment. Final Report

ERCOT Public LTRA Probabilistic Reliability Assessment. Final Report ERCOT Public 2016 LTRA Probabilistic Reliability Assessment Final Report November 21, 2016 Contents Summary... 1 Software Model Description... 3 Demand Modeling... 3 Controllable Capacity Demand Response

More information

21,363 MW 22,774 MW ONTARIO ENERGY REPORT Q JULY SEPT 2014 ELECTRICITY. Electricity Highlights Third Quarter Ontario s Power Grid

21,363 MW 22,774 MW ONTARIO ENERGY REPORT Q JULY SEPT 2014 ELECTRICITY. Electricity Highlights Third Quarter Ontario s Power Grid ONTARIO ENERGY REPORT Q3 Y T ELECTRICITY Electricity Highlights Third Quarter Electricity Generation Output by Fuel Type (Q3) Nuclear Ontario Peak Demand (Q3) 21,363 MW 25.0 TWh 65.7% Hydro 8.8 TWh 23.1%

More information

PJM ENERGY PRICES 2005 Response to Howard M. Spinner Paper

PJM ENERGY PRICES 2005 Response to Howard M. Spinner Paper PJM ENERGY PRICES 2005 Response to Howard M. Spinner Paper Joseph Bowring PJM Market Monitor Response to Howard M. Spinner Paper Re: PJM Energy Prices 2005 A March 13, 2006 paper ( Spinner paper ) by Howard

More information

General Session. Four Decades of Pursuing a Diversified Energy Portfolio at MIKE KOTARA. Senior Vice President

General Session. Four Decades of Pursuing a Diversified Energy Portfolio at MIKE KOTARA. Senior Vice President General Session Four Decades of Pursuing a Diversified Energy Portfolio at CPS Energy SPEAKER MIKE KOTARA Senior Vice President CPS Energy CPS Energy Background Electric & Gas utility serving the greater

More information

California ISO. Q Report on Market Issues and Performance. February 10, Prepared by: Department of Market Monitoring

California ISO. Q Report on Market Issues and Performance. February 10, Prepared by: Department of Market Monitoring California Independent System Operator Corporation California ISO Q4 2013 Report on Market Issues and Performance February 10, 2014 Prepared by: Department of Market Monitoring Department of Market Monitoring

More information

Renewable energy - the future is now

Renewable energy - the future is now University of Nevada, Las Vegas Digital Scholarship@UNLV UNLV Renewable Energy Symposium 2007 UNLV Energy Symposium Aug 15th, 9:00 AM - Jul 15th, 10:00 AM Renewable energy - the future is now Thomas Fair

More information

For Bandon Utilities Commission

For Bandon Utilities Commission For Bandon Utilities Commission July 12, 2017 Profile BPA, a component of the U.S. Department of Energy, is a non-profit and self-funded power marketing administration in the Pacific Northwest. Congress

More information

Integrated Resource Planning at Tacoma Power. Ahlmahz Negash EE 500E Energy & Environment Seminar University of Washington

Integrated Resource Planning at Tacoma Power. Ahlmahz Negash EE 500E Energy & Environment Seminar University of Washington Integrated Resource Planning at Tacoma Power Ahlmahz Negash EE 500E Energy & Environment Seminar University of Washington 11-8-2018 About Tacoma Public Utilities Public, cost-of-service organization; we

More information

PORTFOLIO OPTIMIZATION MODEL FOR ELECTRICITY PURCHASE IN LIBERALIZED ENERGY MARKETS

PORTFOLIO OPTIMIZATION MODEL FOR ELECTRICITY PURCHASE IN LIBERALIZED ENERGY MARKETS PORTFOLIO OPTIMIZATION MODEL FOR ELECTRICITY PURCHASE IN LIBERALIZED ENERGY MARKETS Edwin Castro CNEE Guatemala Viena, september 2009 What is the reason to develop this model? In our own electricity market

More information

The Optimal Approach to Firming Windpower

The Optimal Approach to Firming Windpower 5735 Hollister Avenue, Suite B Goleta, California 93117 T 805.683.9659 F 805.683.9671 www.gravitypower.net The Optimal Approach to Firming Windpower Summary As many regions of the world are staging massive

More information

Wind Workshop. Technical Characterization: Dependable Capacity & Firm Energy 10:00-10:30am

Wind Workshop. Technical Characterization: Dependable Capacity & Firm Energy 10:00-10:30am Wind Workshop Technical Characterization: Dependable Capacity & Firm Energy 10:00-10:30am Objective of this session: Understand BC Hydro s definitions and calculation methodology of dependable capacity

More information

Bidding Strategy I Day-Ahead Market 8 th February 2017 I New Delhi

Bidding Strategy I Day-Ahead Market 8 th February 2017 I New Delhi Bidding Strategy I Day-Ahead Market 8 th February 2017 I New Delhi Rajesh K Mediratta Business Development +91-9654125157 I rajesh.mediratta@iexindia.com 1 For office use In this presentation Type of Market

More information

Wind Generation and Grid Operations: Experience & Perspective

Wind Generation and Grid Operations: Experience & Perspective Wind Generation and Grid Operations: Experience & Perspective Yuri Makarov and David Hawkins California Independent Corporation Folsom, California, USA Participating Intermittent Resources Workshop March

More information

TransCanada Power Market Update January 2018

TransCanada Power Market Update January 2018 Forward Prices Table TransCanada Flat 7x24 ($/MWh) AB - 6x16 On Peak ($/MWh) AB - Off-Peak ($/MWh) AECO Gas ($/GJ) Heat Rate BOM $42. $49.56 $32.76 $1.78 23.6 February $39.75 $46.51 $31.1 $1.69 23.5 218

More information

CCA Pilot Project Update

CCA Pilot Project Update CCA Pilot Project Update Santa Barbara, California July 13, 2007 Topics Project Overview Renewable Energy Supply: Highlighting Marin County s Current CCA Initiative Process & Timeline for CCA Implementation

More information

CHAPTER 6 - Load Forecast & Resource Plan

CHAPTER 6 - Load Forecast & Resource Plan CHAPTER 6 - Load Forecast & Resource Plan Introduction This Chapter describes the electric resource portfolio that may be acquired to meet the energy requirements of MBCP customers. The following overarching

More information

CCA Pilot Project Update

CCA Pilot Project Update CCA Pilot Project Update Petaluma, California October 10, 2007 Topics Project Overview Renewable Energy Supply: Highlighting Marin County s Current CCA Initiative Process & Timeline for CCA Implementation

More information

Hetch Hetchy Integrated Resource Plan Commission Meeting May 23, 2017

Hetch Hetchy Integrated Resource Plan Commission Meeting May 23, 2017 Hetch Hetchy Integrated Resource Plan Commission Meeting May 23, 2017 Today s Presentation 1. Introduction to IRP 2. IRP Applied to Hetch Hetchy Program 3. IRP Approach 4. IRP Results 5. Discussion SFPUC

More information

Agenda. Natural gas and power markets overview. Generation retirements and in developments. Future resource mix including large hydro

Agenda. Natural gas and power markets overview. Generation retirements and in developments. Future resource mix including large hydro Agenda Natural gas and power markets overview Generation retirements and in developments Future resource mix including large hydro Balancing environmental, reliability and cost impacts 1 Northeast Utilities

More information

Renewables Curtailment in China is there light at the end of the tunnel? Liutong Zhang

Renewables Curtailment in China is there light at the end of the tunnel? Liutong Zhang Renewables Curtailment in China is there light at the end of the tunnel? Liutong Zhang Renewable curtailment in China All ready to generate but no place to go RE curtailment in China TWh 100 90 80 70 60

More information

Renewables Review. Operations Committee December 9, 2015

Renewables Review. Operations Committee December 9, 2015 Renewables Review Operations Committee December 9, 2015 1 Presentation Intro to resource planning Decades review (1990s, 2000s, 2010s) Resource planning Historical perspective Evaluations, engineering

More information

CO2, SO2 and NOX Emission Rates. March 15, 2018

CO2, SO2 and NOX Emission Rates. March 15, 2018 March 15, 2018 This page is intentionally left blank. PJM 2018 www.pjm.com 1 P age Introduction To support the efforts of regulators, stakeholders, and other interested parties as they work towards achieving

More information

Self-Schedules Bid Cost Recovery Allocation and Lower Bid Floor

Self-Schedules Bid Cost Recovery Allocation and Lower Bid Floor Summary Self-Schedules Bid Cost Recovery Allocation and Lower Bid Floor Draft Final Proposal Comments by Department of Market Monitoring August 23, 2016 The ISO proposal to lower the energy bid floor from

More information

Flexible Resource Adequacy Criteria and Must-Offer Obligation

Flexible Resource Adequacy Criteria and Must-Offer Obligation Flexible Resource Adequacy Criteria and Must-Offer Obligation February 13, 2014 Karl Meeusen, Ph.D. Market Design and Regulatory Policy Lead Stakeholder Meeting Agenda 2/13/14 Time Topic Presenter 12:30

More information

On the Path to SunShot: Emerging Issues and Challenges in Integrating High Levels of Solar into the Electrical Generation and Transmission System

On the Path to SunShot: Emerging Issues and Challenges in Integrating High Levels of Solar into the Electrical Generation and Transmission System On the Path to SunShot: Emerging Issues and Challenges in Integrating High Levels of Solar into the Electrical Generation and Transmission System Paul Denholm, Kara Clark, and Matt O Connell National Renewable

More information

AEP Ohio. Combined Heat and Power (CHP) May 24 th, 2017 Steve Giles Vice President Alternative Energy Hull & Associates, Inc.

AEP Ohio. Combined Heat and Power (CHP) May 24 th, 2017 Steve Giles Vice President Alternative Energy Hull & Associates, Inc. AEP Ohio Combined Heat and Power (CHP) May 24 th, 2017 Steve Giles Vice President Alternative Energy Hull & Associates, Inc. OUR MARKET AREAS Shale Oil & Gas Waste Management PROJECT DEVELOPMENT AND ASSET

More information

PJM Wind Integration Initiatives

PJM Wind Integration Initiatives PJM Wind Integration Initiatives West Virginia Wind Forum Davis, WV September 25, 2012 Ken Schuyler Renewable Services PJM Interconnection 1 26% of generation in Eastern Interconnection 28% of load in

More information

ELECTRICITY TRADE AGREEMENT. An Assessment of the Ontario-Quebec Electricity Trade Agreement

ELECTRICITY TRADE AGREEMENT. An Assessment of the Ontario-Quebec Electricity Trade Agreement ELECTRICITY TRADE AGREEMENT An Assessment of the Ontario-Quebec Electricity Trade Agreement Spring 2018 About this Document Established by the Financial Accountability Officer Act, 2013, the Financial

More information

Ten Years After Gas & Power in Perspective

Ten Years After Gas & Power in Perspective Regional Market Trends Forum Ten Years After Gas & Power in Perspective Richard Levitan, rll@levitan.com May 1, 2014 Agenda 2014 Polar Vortex v. 2004 Cold Snap Northeast Gas & Power 10 Years After Gas

More information

Solar, Wind and Market Power in the New Zealand Electricity Market (and hydro lake dynamics) Mina Bahrami Gholami and Stephen Poletti

Solar, Wind and Market Power in the New Zealand Electricity Market (and hydro lake dynamics) Mina Bahrami Gholami and Stephen Poletti Solar, Wind and Market Power in the New Zealand Electricity Market (and hydro lake dynamics) Mina Bahrami Gholami and Stephen Poletti University of Auckland Economic Paradox Energy Only Markets. Low-carbon

More information

Solving Climate: The Need for Zero Carbon On-Demand Power

Solving Climate: The Need for Zero Carbon On-Demand Power Solving Climate: The Need for Zero Carbon On-Demand Power Armond Cohen, Executive Director Clean Air Task Force National Coal Council 2016 Annual Spring Meeting April 20, 2016 STABILIZING CLIMATE MEANS

More information

Keeyask Generation Project. Public Involvement. Supporting Volume. Environmental Impact Statement

Keeyask Generation Project. Public Involvement. Supporting Volume. Environmental Impact Statement Keeyask Generation Project Environmental Impact Statement Supporting Volume Public Involvement June 212 The Manitoba Hydro System and its Operation Harold Surminski Power Supply December 15, 21 Broad Overview

More information

FERC/RTO Training Session Institute for Policy Integrity New York University School of Law June 15, 2011

FERC/RTO Training Session Institute for Policy Integrity New York University School of Law June 15, 2011 FERC/RTO Training Session Institute for Policy Integrity New York University School of Law June 15, 2011 N. Jonathan Peress Conservation Law Foundation Clean Energy and Climate Change Program 1 It is change,

More information

Load Shift Working Group. https://gridworks.org/initiatives/load-shift-working-group/

Load Shift Working Group. https://gridworks.org/initiatives/load-shift-working-group/ Load Shift Working Group APRIL 18 10AM 2PM PST CPUC GOLDEN GATE ROOM https://gridworks.org/initiatives/load-shift-working-group/ Agenda 10:00 10:20am: Intro and Purpose (Gridworks) 10:20 12:00pm: Grid

More information

Pacific Northwest Low Carbon Scenario Analysis

Pacific Northwest Low Carbon Scenario Analysis Pacific Northwest Low Carbon Scenario Analysis Achieving Least-Cost Carbon Emissions Reductions in the Electricity Sector November 8, 2017 Arne Olson, Partner Nick Schlag, Sr. Managing Consultant Jasmine

More information

Substantial Changes Ahead for MISO North Michigan Impacts 2018 MMEA Fall Conference

Substantial Changes Ahead for MISO North Michigan Impacts 2018 MMEA Fall Conference Substantial Changes Ahead for MISO North Michigan Impacts 2018 MMEA Fall Conference Mike Zenker, Managing Director of Market Analysis NextEra Energy Resources September 13, 2018 2 3 The Following Information

More information

2001 Annual Report on the New York Electricity Markets

2001 Annual Report on the New York Electricity Markets 2001 Annual Report on the New York Electricity Markets Presented to: New York ISO Management Committee David B. Patton, Ph.D. Independent Market Advisor April 16, 2002 Conclusions and Recommendations The

More information

Renewable Integration The California Experience

Renewable Integration The California Experience Renewable Integration The California Experience Mark Rothleder Vice President, Market Quality and Renewable Integration New England Power Pool 2017 NEPOOL Participants Committee Summer Meeting June 28,

More information

Wild Horse Solar Photovoltaic Project

Wild Horse Solar Photovoltaic Project Wild Horse Solar Photovoltaic Project Steven J. St.Clair Manager Renewable Assets Phone: 425-462-3057 Email: steven.stclair@pse.com November 19, 2009 Agenda Introduction PSE Renewable Energy Facilities

More information

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid Greening the Grid Rajasthan Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid State-specific results from Volume II, which includes all of India. The full reports include

More information

Utility Perspectives on Bioenergy for California

Utility Perspectives on Bioenergy for California California Biomass Collaborative Climate Change, Carbon Policies, Renewable Energy and the Role of Biomass Utility Perspectives on Bioenergy for California March 27, 2007 PG&E s 2005 Electric Delivery

More information

Portland General Electric 2016 Integrated Resource Plan. OPUC Public Meeting December 20, 2016

Portland General Electric 2016 Integrated Resource Plan. OPUC Public Meeting December 20, 2016 Portland General Electric 2016 Integrated Resource Plan OPUC Public Meeting December 20, 2016 Agenda Process and Compliance Approach and Summary Analysis Action Plan Next steps 2 2013 IRP Order Resource

More information

TransCanada Power Market Update February 2018

TransCanada Power Market Update February 2018 Forward Prices Table TransCanada Flat 7x24 ($/MWh) AB - 6x16 On Peak ($/MWh) AB - Off-Peak ($/MWh) AECO Gas ($/GJ) Heat Rate BOM $37.5 $44.25 $29.25 $1.85 2.3 March $38. $44.46 $29.64 $1.45 26.2 BOY $6.3

More information

The consumer and societal benefits of wind energy in Texas

The consumer and societal benefits of wind energy in Texas The consumer and societal benefits of wind energy in Texas November 2014 Introduction Texas wind energy provides the state with $3.3 billion in societal benefits per year. These benefits include reducing

More information

Electric Forward Market Report

Electric Forward Market Report Mar-01 Mar-02 Jun-02 Sep-02 Dec-02 Mar-03 Jun-03 Sep-03 Dec-03 Mar-04 Jun-04 Sep-04 Dec-04 Mar-05 May-05 Aug-05 Nov-05 Feb-06 Jun-06 Sep-06 Dec-06 Mar-07 Jun-07 Sep-07 Dec-07 Apr-08 Jun-08 Sep-08 Dec-08

More information

Valuing Energy Storage as a Flexible Resource. Final Phase 1 Report for Consideration in CPUC A

Valuing Energy Storage as a Flexible Resource. Final Phase 1 Report for Consideration in CPUC A Valuing Energy Storage as a Flexible Resource Final Phase 1 Report for Consideration in CPUC A. 14-02-006 June 19, 2014 Valuing Energy Storage as a Flexible Resource Final Phase 1 Report for Consideration

More information

Zero Net Carbon Portfolio Analysis

Zero Net Carbon Portfolio Analysis Zero Net Carbon Portfolio Analysis Prepared for: Platte River Power Authority December 12, 2017 www.paceglobal.com Agenda Background Methodology Assumptions Cases Findings and Recommendations Page 2 Background

More information

Resource Adequacy Enhancements Straw Proposal - Part 1. Stakeholder Call January 23, 2019

Resource Adequacy Enhancements Straw Proposal - Part 1. Stakeholder Call January 23, 2019 Resource Adequacy Enhancements Straw Proposal - Part 1 Stakeholder Call January 23, 2019 Agenda Time Topic Presenter 1:00 1:10PM Welcome and introduction Jody Cross 1:10 1:40PM Rules for Import RA Chris

More information

Section 3 Characteristics of Credits Types of units. Economic Noneconomic Generation.

Section 3 Characteristics of Credits Types of units. Economic Noneconomic Generation. Section 3 Operating Reserve Operating Reserve Day-ahead and real-time operating reserve credits are paid to market participants under specified conditions in order to ensure that resources are not required

More information

California ISO. Q Report on Market Issues and Performance. November 1, Department of Market Monitoring

California ISO. Q Report on Market Issues and Performance. November 1, Department of Market Monitoring California Independent System Operator Corporation California ISO Q3 2018 Report on Market Issues and Performance November 1, 2018 Department of Market Monitoring TABLE OF CONTENTS Executive summary...

More information

Executive summary. Value of Smart Power Generation for utilities in Australia. A white paper by Wärtsilä and Roam Consulting

Executive summary. Value of Smart Power Generation for utilities in Australia. A white paper by Wärtsilä and Roam Consulting Value of Smart Power Generation for utilities in Australia A white paper by Wärtsilä and Roam Consulting Executive summary This study analyses the potential of Smart Power Generation () power plants in

More information

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Transmission Expansion Advisory Committee EPA's Clean Power Plan PJM Modeling Approach and Deliverables PJM Interconnection December 3, 2015 www.pjm.com Clean Power Plan Analysis Overview What is it? US

More information

PWP 2015 IRP Update Energy Roadmap Event

PWP 2015 IRP Update Energy Roadmap Event PWP 2015 IRP Update Energy Roadmap Event May 13, 2015 Can You Name These PWP Power Sources? 2 PWP Power Supplies 4 Energy Integrated Resource Plan (IRP) The IRP is a 20 year plan for meeting forecasted

More information

PUBLIC DOCUMENT NOT PUBLIC DATA

PUBLIC DOCUMENT NOT PUBLIC DATA Appendix F: Strategist Modeling Assumptions PUBLIC DOCUMENT NOT PUBLIC DATA HAS BEEN EXCISED Appendix F: Strategist Modeling Assumptions PUBLIC DOCUMENT NOT PUBLIC DATA HAS BEEN EXCISED Table of Contents

More information

Schedule 2 TECHNICAL INFORMATION

Schedule 2 TECHNICAL INFORMATION Schedule 2 TECHNICAL INFORMATION This document is intended to provide context to the Haida Gwaii Request for Expressions of Interest (RFEOI) for the potential electricity supply opportunity for clean electricity

More information

CO2, SO2 and NOX Emission Rates. August 21, 2015

CO2, SO2 and NOX Emission Rates. August 21, 2015 August 21, 2015 This page is intentionally left blank. PJM 2015 www.pjm.com 1 P age Introduction In recent years, federal and state environmental regulations have applied or will apply more stringent restrictions

More information

Wyoming Pipeline Authority Happy Jack Wind Farm

Wyoming Pipeline Authority Happy Jack Wind Farm December 10, 2009 Wyoming Pipeline Authority Happy Jack Wind Farm 1 Black Hills Corporation An integrated and diversified energy company Utilities Gas Utilities Colorado Natural Gas Iowa Natural Gas Kansas

More information

Appendix 13. Renewable Energy Market Potential

Appendix 13. Renewable Energy Market Potential Appendix 13. Renewable Energy Market Potential Briefing Paper for the SageCon Partners Estimates of Oregon Renewable Development through 2025 Phil Carver, Oregon Dept. of Energy January 22, 2014 Summary

More information

Elliot Mainzer, BPA. NW Wind Integration Forum SC Meeting June 6, 2011

Elliot Mainzer, BPA. NW Wind Integration Forum SC Meeting June 6, 2011 Elliot Mainzer, BPA Ken Dragoon, g NWPCC NW Wind Integration Forum SC Meeting June 6, 2011 1. Review the fundamentals concerning our current wind fleet and the regulatory demand for renewables by 2020.

More information

Outline of Talk. Dynamic vs. Time-of-use pricing. Dynamic vs. Time-of-use pricing

Outline of Talk. Dynamic vs. Time-of-use pricing. Dynamic vs. Time-of-use pricing Symmetric Treatment of Load and Generation: A Necessary Condition for Demand Response to Benefit Wholesale Market Efficiency and Manage Intermittency Frank A. Wolak Director, Program on Energy Sustainable

More information

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid Greening the Grid Tamil Nadu Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid State-specific results from Volume II, which includes all of India. The full reports include

More information

Operations Report. Stephanie Monzon Manager, Markets Coordination Operating Committee July 10, PJM 2018

Operations Report. Stephanie Monzon Manager, Markets Coordination Operating Committee July 10, PJM 2018 Operations Report Stephanie Monzon Manager, Markets Coordination Operating Committee July 10, 2018 Forecast Error (Absolute %) Load Forecasting Error (Achieved 80% of the Time) 5.0 4.5 4.0 On-Peak Average

More information

Preliminary Assumptions for On-Shore Wind Technologies. Gillian Charles GRAC October 2, 2014

Preliminary Assumptions for On-Shore Wind Technologies. Gillian Charles GRAC October 2, 2014 Preliminary Assumptions for On-Shore Wind Technologies Gillian Charles GRAC October 2, 2014 At the last meeting Discussed current status of wind development in PNW Reviewed recent trends in development

More information

Operations Report. Stephanie Monzon Manager, Markets Coordination MC Webinar January 22, PJM 2018

Operations Report. Stephanie Monzon Manager, Markets Coordination MC Webinar January 22, PJM 2018 Operations Report Stephanie Monzon Manager, Markets Coordination MC Webinar January 22, 2019 Forecast Error (Absolute %) Load Forecasting Error (Achieved 80% of the Time) 4.0 3.5 On-Peak Average Off-Peak

More information

Managing Risk and Volatility in Gas-Fired Generation

Managing Risk and Volatility in Gas-Fired Generation Managing Risk and Volatility in Gas-Fired Generation The Institute for Regulatory Policy Studies May 1, 2008 Jay Dibble Director of Gas Regulatory Calpine Corporation TABLE OF CONTENTS CALPINE OVERVIEW

More information

System Needs: An Energy Planning Perspective. Randy Reimann

System Needs: An Energy Planning Perspective. Randy Reimann System Needs: An Energy Planning Perspective Randy Reimann TOPICS BCUC 2006 IEP/LTAP Decision 2008 LTAP Workplan Resource Options Update System Planning and Criteria 2 BCUC IEP/LTAP DECISION Key findings:

More information

FLEXIBILITY HOW TO CONTRIBUTE TO THE STABILITY OF THE GRID THANKS TO THE FLEXIBILITY OF YOUR PRODUCTION PROCESSES?

FLEXIBILITY HOW TO CONTRIBUTE TO THE STABILITY OF THE GRID THANKS TO THE FLEXIBILITY OF YOUR PRODUCTION PROCESSES? FLEXIBILITY HOW TO CONTRIBUTE TO THE STABILITY OF THE GRID THANKS TO THE FLEXIBILITY OF YOUR PRODUCTION PROCESSES? 1 The energy transition: decentralized power generation Past situation Current situation

More information

Flexible Resource Adequacy Criteria and Must Offer Obligation Working Group Meeting

Flexible Resource Adequacy Criteria and Must Offer Obligation Working Group Meeting Flexible Resource Adequacy Criteria and Must Offer Obligation Working Group Meeting Karl Meeusen, Ph.D. September 26, 2017 2017 CAISO - Public Page 1 FRACMOO 2 Working Group Meeting Agenda 9/26/2017 Time

More information

Briefing Paper for the SageCon Partners Estimates of Oregon Renewable Development through 2025

Briefing Paper for the SageCon Partners Estimates of Oregon Renewable Development through 2025 Briefing Paper for the SageCon Partners Estimates of Oregon Renewable Development through 2025 Phil Carver, Oregon Dept. of Energy January 23, 2014 Revisons based in PacifiCorp comments as of January 22

More information

Western Energy Imbalance Market

Western Energy Imbalance Market Western Energy Imbalance Market Monday, May 23, 2016 Peter Colussy, External Affairs Manager - Regional Copyright 2016 California ISO Energy Imbalance Market is an easily-scalable extension of real-time

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION California Independent System ) Docket Nos. ER12-1630 Operator Corporation ) ER14-971 Informational Report of the California Independent System

More information

Operations Report. Hong Chen Senior Lead Engineer, Markets Coordination Members Committee October 22, PJM 2018

Operations Report. Hong Chen Senior Lead Engineer, Markets Coordination Members Committee October 22, PJM 2018 Operations Report Hong Chen Senior Lead Engineer, Markets Coordination Members Committee October 22, 2018 Forecast Error (Absolute %) Load Forecasting Error (Achieved 80% of the Time) 4.0 3.5 On-Peak Average

More information

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid Greening the Grid Gujarat Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid State-specific results from Volume II, which includes all of India. The full reports include

More information

Selected Findings from Scenario and Sensitivity Analysis Conducted To Date. August 6, 2015

Selected Findings from Scenario and Sensitivity Analysis Conducted To Date. August 6, 2015 Selected Findings from Scenario and Sensitivity Analysis Conducted To Date August 6, 2015 Progress Since The July Council Meeting: All Planned Scenario Analysis Completed! RPM Systems 2 Progress Since

More information

Electric Analysis PSE Integrated Resource Plan. Contents. Chapter 6: Electric Analysis

Electric Analysis PSE Integrated Resource Plan. Contents. Chapter 6: Electric Analysis 6 2017 PSE Integrated Resource Plan Electric Analysis This chapter presents the results of the electric analysis. Contents 1. ANALYSIS OVERVIEW 6-3 2. RESOURCE NEED 6-5 Components of Physical (Peak) Need

More information

Q2/2016 Quarterly Report

Q2/2016 Quarterly Report April June 2016 July 29, 2016 Taking action to promote effective competition and a culture of compliance and accountability in Albertaʹs electricity and retail natural gas markets www.albertamsa.ca Table

More information

Ancillary Service Markets

Ancillary Service Markets Section 9 Ancillary Services Ancillary Service Markets The United States Federal Energy Regulatory Commission (FERC) defined six ancillary services in Order No. 888: 1) scheduling, system control and dispatch;

More information

MISO Energy Storage Study DRAFT Scope

MISO Energy Storage Study DRAFT Scope MISO Energy Storage Study DRAFT Scope MISO Energy Storage Study DRAFT Scope July 19, 2011 MISO Page 1 Table of Contents 1. Introduction... 3 2. Study Objectives... 3 3. Study Drivers... 4 4. Study Description...

More information

MARKET MATTERS HVDC UTILISATION REPORT OCTOBER 2018

MARKET MATTERS HVDC UTILISATION REPORT OCTOBER 2018 HVDC Utilisation In late 2016 we published a report covering what restricts HVDC north transfer 1. We are now publishing monthly updates on the market aspects that restricted HVDC north transfer, and some

More information

Annual Renewable Energy Constraint and Curtailment Report 2016

Annual Renewable Energy Constraint and Curtailment Report 2016 Annual Renewable Energy Constraint and Curtailment Report 2016 07/04/2017 Contents Executive Summary... 3 1 Introduction... 5 1.1 Context... 5 1.2 Reasons for Dispatch-Down... 5 1.3 Reporting Methodology...

More information

The Confluence Model. Presentation to Modeling and Forecasting Working Group January 21, 2015

The Confluence Model. Presentation to Modeling and Forecasting Working Group January 21, 2015 The Confluence Model Presentation to Modeling and Forecasting Working Group January 21, 2015 Introductions Presenter: Gary Fiske Working Group Water Department staff Objective: Penetrate the Black Box

More information

Hedging Coal Price Risk in a Deregulated Power Market

Hedging Coal Price Risk in a Deregulated Power Market Hedging Coal Price Risk in a Deregulated Power Market Ginny Farrow Manager Rail Car Fleet NCCI Spring Conference Greensboro, NC April 12, 2007 Safe Harbor Statement This Presentation contains forward-looking

More information

OVERVIEW OF DESERT SOUTHWEST POWER MARKET AND ECONOMIC ASSESSMENT OF THE NAVAJO GENERATING STATION

OVERVIEW OF DESERT SOUTHWEST POWER MARKET AND ECONOMIC ASSESSMENT OF THE NAVAJO GENERATING STATION OVERVIEW OF DESERT SOUTHWEST POWER MARKET AND ECONOMIC ASSESSMENT OF THE NAVAJO GENERATING STATION ARIZONA CORPORATION COMMISSION APRIL 6, 2017 DALE PROBASCO MANAGING DIRECTOR ROGER SCHIFFMAN DIRECTOR

More information

Draft 2011 Long-term Transmission Plan. Stakeholder Session June 20, 2011

Draft 2011 Long-term Transmission Plan. Stakeholder Session June 20, 2011 Draft 2011 Long-term Transmission Plan Stakeholder Session June 20, 2011 Agenda Highlights of draft 2011 Long-term Transmission Plan Discussion of project costs and rate impact Impact of transmission constraints

More information

Western Energy Imbalance Market and Regional Initiatives

Western Energy Imbalance Market and Regional Initiatives Western Energy Imbalance Market and Regional Initiatives Presentation to mid-c Seminar Don Fuller Director Strategic Alliances July 27, 2016 Today s topics Renewable portfolio continues to grow Energy

More information

Determining water allocations in the regulated Murrumbidgee Valley

Determining water allocations in the regulated Murrumbidgee Valley Determining water allocations in the regulated Murrumbidgee Valley September 2013 Introduction The NSW Office of Water (NOW) is responsible for sharing water between consumptive users and the environment

More information

Briefing on the duck curve and current system conditions

Briefing on the duck curve and current system conditions Briefing on the duck curve and current system conditions Clyde Loutan, Senior Advisor Market Surveillance Committee Meeting General Session July 15, 215 Original estimate of net-load as more renewables

More information

Renewable Portfolio Standards

Renewable Portfolio Standards Renewable Portfolio Standards Lisa Schwartz Presentation to Oregon State University Energy Economics Class Feb. 22, 2010 The Regulatory Assistance Project China EU India United States About the Regulatory

More information