1 2018 Proposed Budget PRESENTED TO UTILITIES COMMISSION OCTOBER 2 ND 2017

2 Proposed Budget Reflects Council s Goals Overview

3 FY2018 Budget at a glance Overview General Fund Open Lake Nighthorse General Fund Capital Improvement Program Only 3 projects Water & Sewer Enterprise Funds 3% Rate increase each Transportation Enterprise Fund Service cuts necessary to achieve fiscal sustainability Solid Waste Enterprise Fund Better transparency, 6% Rate increase Airport Fund Addressing Capital Projects Library New Circulation Services Supervisor From 2017 adopted to 2018 proposed operating expenditures, the overall change is a decrease of 2.9%.

4 All Operating Fund Expenditures: Where it goes Overview Solid Waste Enterprise Fund 3% Airport Enterprise Fund 5% Sewer Enterprise Fund 10% Transportation Services Fund Transporati 5% on Services General Fund 48% Water Enterprise Special Revenue Funds 8% Internal Service Funds 12% Proposed FY2018 Budget Figures

5 Dr. Martín Carcasson Deliberative Process: Tame & Wicked Problems Director of the Center for Public Deliberation Professor, Department of Communication Studies at CSU DurangoGov.org/WickedProblems Thanks to Dr. Carcasson for suggesting new ideas for our budget process!

6 Typical public process in Durango Deliberative Process: Tame & Wicked Problems Engagement occurs too late in the process Often framed as yes/no issues Primarily provides opportunities for individual expression Caters to entrenched and organized voices Little to no effective interaction or learning/refinement of opinion Methods used for public input: Social media political engagement Town halls Interest groups and lobbyists Chamber of Commerce Eggs and Issues Citizen comment and public hearings Expert panels Letters to the editors s and campaigns to policymakers

7 What we need public process to do: Deliberative Process: Tame & Wicked Problems Build capacity for wisdom, collaborative action and co-creation Spark collaborative learning and the refinement (not just expression) of opinion Help differentiate strong and weak arguments Build mutual understanding and development of respect Support listening and genuine interaction Provide opportunities for voice and public input

8 Tame and Wicked Problems Deliberative Process: Tame & Wicked Problems Tame Problems Problems that are essentially technical in nature and can be solved by experts through scientific means. Can be divided into manageable parts, and efforts to solve them are primarily judged in terms of efficiency. Wicked Problems Inherently involve competing underlying values, paradoxes, and tradeoffs that cannot be resolved by science. Call for high quality communication, creativity, and broad collaborative action to manage well.

9 Solving Wicked Problems Deliberative Process: Tame & Wicked Problems Presume wicked problems not wicked people Focus on improving the conversation not winning the argument Put civic energy toward identifying and finding better ways to negotiate inherent tensions Emphasize the ongoing conversation and a creative learning process

10 Utilities Department The Utilities Department treats and distributes an average of 3.19 million gallons of drinking water per day (based on 2016 values), reclaims approximately 1.53 million gallons of waste water per day, and in 2017 our crews have actively worked on approximately 20 Capital Improvement Projects. All of these efforts repairing and replacing old systems, improving monitoring and remote visibility, and maintaining the systems in place have been to improve the City of Durango s ability and capacity to provide clean water to customers, the Animas River, and the Colorado River Basin. Providing clean water for the people of the City of Durango, the health of Animas River, and downstream users.

11 Fund Highlights: Overview Water Enterprise Fund Revenues: Total revenues decrease 7.9% ( $710,000) Residential and commercial rate increase 3% Expenditures: Operating expenditures decrease by 0.7% ($26,814) Staffing changes: New Project Manager position to expedite backlog of capital projects (50% from Water Fund) Elimination of Utilities Management Analyst (50% from Water Fund) Capital: Transfer to Capital Projects fund decrease of $600,000 from previous year.

12 Fund Highlights: Sewer Enterprise Fund Overview Revenues: Total Revenues increase 2.6% ($207,875) Residential and commercial rate increase 3% Expenditures: Proposed operating expenditures increase 11.5% ($730,448) Staffing: New Project Manager position to expedite backlog of capital projects (50% from Sewer Fund) New SRWRF Operator position Elimination of Utilities Management Analyst(50% from Sewer Fund) Capital: Transfer to Capital Projects fund decrease by $1,530,000 Debt service payments for SRWRF ($3,396,785)

13 Utility Rates Increases Fiscal Sustainability

14 Water & Sewer Enterprise Funds Fiscal Sustainability Water Fund Title 2018 Ridges Basin WTP Water Main Extension $ 920, Meter Replacement Program $ 600, Property Acquisition $ 500, Florida River Rainbow Ranch $ 300, Pumping Station- PRV's, Pumps, Motors $ 210, Valve Replacements $ 100, Site Pipe/Valve Replacement $ 80, CMWTP Coagulant Pumps $ 75, WTP Process Piping Rehab $ 50, TOTAL 2018 CIPs $ 2,835, Sewer Fund Title 2018 In Situ Sewer Project $ 200, Lift Station Generator Replacements $ 175, Collection System Flow Monitoring and Control Syst $ 100, Fiber Upgrade and Expansion $ 50, Sewer Inflow Study $ 50, TOTAL 2018 CIPs $ 575, Ongoing Sewer CIPs: $70,384,521 Ongoing Water CIPs: $11,795,138

15 Why do we need a project Fiscal Sustainability manager? To address and manage the Water and Sewer Capital Improvements Projects Largest project in City s history, Santa Rita Water Reclamation Facility, is underway and requires significant staff effort 64 ongoing capital projects (47 water projects and 17 sewer projects) Constraints of current staffing level lead to the request for more capacity via the proposed project manager

16 Water Enterprise Funds Ongoing CIPs Currently there are 47 Water CIP Projects in process, ranging from Tank Chlorine Tablet Feeders for $38,856 to a New 3MG Tank for $2,158,930. Some projects will be complete by 2017 Year End. Many projects have engineering lead time which makes them multi year projects. All of these projects are being managed with current Water Plant and Distribution Staff. Title 2017 Waterline Replacements $ 776, Water System Telemetry $ 281, Land Acquisition WTP $ 94, WTP Process Revisions $ 140, WTP Office Expansion $ 336, Water Conservation Audits $ 111, La Posta Waterline Bridge To Airpark $ 81, WTP HVAC Insulation Upgrades and New Roof $ 73, ALP SCADA Outfall Improvements $ 250, Terminal Reservoir Improvements $ 94, WTP Reclaim/Sludge Management $ 369, Filter Effluent to Waste System $ 335, T1 Floculator VFD Replacement $ 133, WTP Electrical Upgrade $ 480, New 3 MG Tank $ 2,158, Valve Replacements $ 88, HWy 160 W Water Main Capacity Assurance $ 49, Meter Replacement Program $ 91, Florida River Rainbow Ranch $ 452, Santa Rita Pump Station Pump Replacement $ 109, WTP Process Piping Rehab $ 68, Storage Tank Cleaning Refurbishing $ 196, Fiber Expansion 29th Street Pipeline $ 60, Terminal Reservoir Dam Repair $ 247, Animas River Repair Work $ 107, Compressed Air System upgrades $ 50, Fencing at WTP $ 50, Site Pipe/Valve Replacement $ 85, Upgrade/New Sewer Mains Facility Miox System $ 150, Concrete Sidewalks and Aprons $ 50, Pumping Station- PRV's, Pumps, Motors $ 81, Santa Rita Variable Frequency Drives MCC $ 698, Grandview Pump Control Panels $ 44, Ball Lane Pump Station Upgrades $ 228, River Crossings Replacements Water Mains $ 499, Tank Chlorine Tablet Feeders $ 38, Storage Tank Painting Exterior $ 230, Storage Tanks Control Panel Systems $ 131, Drought Plan $ 50, AMR Upgrades $ 659, Florida Raw Water Line Replacement $ 500, Terminal Reservoir Expansion $ 80, SMWTP Site Pipe/Valve Replacement $ 80, Grandview Pump Station Building Site Improvements $ 100, College Drive Waterline Upsize $ 100, New RBWTP 14.0 MGD WTP $ 400, Storage Tank Cleaning/Refurbishing $ 300, TOTAL $11,795, Fiscal Sustainability

17 Sewer Enterprise Funds Fiscal Sustainability Ongoing CIPs Currently there are 17 Sewer CIP Projects in process, ranging from a floodplain study for $50,000 to Liftstation Replacement for $1,537,446. Some projects will be complete by 2017 Year End. Many projects have engineering lead time which makes them multi year projects. All of these projects are being managed with current Water Reclamation Plant and Collections Staff. Title 2017 In Situ Sewer Project $ 518, Lift Station Replacement $ 1,537, Lift Station Generator Replacements $ 336, Process Revisions/Expansion Nutrient Regs $ 80, SRWWTP Rehab Digester Outer Walls $ 180, West Sewer Line Capacity Assurance $ 600, Fiber Upgrade and Expansion $ 100, Collection System Flow Monitoring and Control Syst $ 196, Sewer Inflow Study $ 150, Primary Clarifier II $ 450, Limited Storage Liftstation/Emergency Vaults $ 800, SRWWTP Flood Plain Study $ 50, River Crossing Replacements $ 450, Purchase of Silver Peaks Condo $ - EIAF 7738 Waste Water Treatment Plant Design $ 333, State Revolving Loan Fund (SRF - EPA) $64,200, Chamber of Commerce Relocation $ 400, TOTAL $70,384,521.00

18 Santa Rita Water Reclamation Facility Fiscal Sustainability Largest infrastructure project in City s history

19 Next Steps What s left? Council Sets Goals (July 18 & August 1) Public Workshop (July 26) Cities and Towns Week (September 11-17) CM Proposed Budget Presentation to Council (Today) Council/BOCC Study Session on Joint Sales Tax (Library & Senior Center) and Airport October 3 All Day Council Budget Workshop October 5 Study Session: Review CIP October 10 Community Support (Discretionary), DATO, BID October 24 Public Hearing on the Budget November 6 Budget Reconciliation November 14 Budget Adoption December 5

Section 1 - Introduction...7. Section 2 - Raw Water Supply Section 3 - Water Treatment Section 4 - Water Distribution System...

Section 1 - Introduction...7. Section 2 - Raw Water Supply Section 3 - Water Treatment Section 4 - Water Distribution System... Table of Contents Section 1 - Introduction...7 1.1 Population Growth...7 1.1.1 Service Area...7 1.1.2 Past Population...7 1.1.3 Projected Population Growth...9 1.2 Water Demands...9 1.2.1 Past Water Demands...9

More information

Long-Term Capital Improvement Funding Plan. March 18, 2014 City Council Study Session

Long-Term Capital Improvement Funding Plan. March 18, 2014 City Council Study Session Long-Term Capital Improvement Funding Plan March 18, 2014 City Council Study Session Overview Long-term 10 year view to know what s planned Project Overview Focus on FY 2014-15 and FY 2015-16 Funding Plan

More information

Report on Feasibility Assessment and Proposed Consolidation Agreement Maumelle Water Management September 22, 2015

Report on Feasibility Assessment and Proposed Consolidation Agreement Maumelle Water Management September 22, 2015 Report on Feasibility Assessment and Proposed Consolidation Agreement Maumelle Water Management September 22, 2015 Monthly Utility Bill in $ 100 Combined Average Utility Bill for 2015-2020 5/8 Meter with

More information

Ann Arbor Wastewater Treatment Plant Facilities Renovations Project October 2017

Ann Arbor Wastewater Treatment Plant Facilities Renovations Project October 2017 Ann Arbor Wastewater Treatment Plant Facilities Renovations Project October 2017 The Facilities Master Plan was completed in 2004 and identified the need for improvements to the City of Ann Arbor s Wastewater

More information

CHAPTER 8 CAPITAL IMPROVEMENT PLAN

CHAPTER 8 CAPITAL IMPROVEMENT PLAN INTRODUCTION CHAPTER 8 CAPITAL IMPROVEMENT PLAN This chapter presents 6-, 10-, and 20-year Capital Improvement Plans (CIPs) in accordance with the requirements of WAC 26-290. Water system capital improvements

More information

AGENDA LOVELAND CITY COUNCIL STUDY SESSION TUESDAY, JULY 14, 2015 CITY COUNCIL CHAMBERS 500 EAST THIRD STREET LOVELAND, COLORADO

AGENDA LOVELAND CITY COUNCIL STUDY SESSION TUESDAY, JULY 14, 2015 CITY COUNCIL CHAMBERS 500 EAST THIRD STREET LOVELAND, COLORADO AGENDA LOVELAND CITY COUNCIL STUDY SESSION TUESDAY, JULY 14, 2015 CITY COUNCIL CHAMBERS 500 EAST THIRD STREET LOVELAND, COLORADO The City of Loveland is committed to providing an equal opportunity for

More information

Public Utilities Director. Public Utilities Assistant Director. Administrative Analyst. Laboratory. Laboratory Manager. Sr. Utilities.

Public Utilities Director. Public Utilities Assistant Director. Administrative Analyst. Laboratory. Laboratory Manager. Sr. Utilities. Director Administrative Support Manager Assistant Director Controller Senior Staff Assistant Personnel/ Payroll Technician (2) Administrative Analyst Accountant Storeskeeper Accounting Tech Infrastructure

More information

Calendar Year capital improvement. Program

Calendar Year capital improvement. Program Calendar Year 2010 capital improvement Program Important Notice: The information found in this file concerning the 2010 Capital Improvements Program, has been extracted from the San Antonio Water System

More information

Citizens Advisory Committee. Process Kick-Off July 12, 2017

Citizens Advisory Committee. Process Kick-Off July 12, 2017 Citizens Advisory Committee Process Kick-Off July 12, 2017 MEETING AGENDA Introductions: Facilitator, committee and key staff Committee Process Overview and Ground Rules BBWD Overview Facility Tour FACILITATOR:

More information

Study Session Wastewater Enterprise, Proposed Improvement Projects and Projected Funding Needs Update

Study Session Wastewater Enterprise, Proposed Improvement Projects and Projected Funding Needs Update Study Session Wastewater Enterprise, Proposed Improvement Projects and Projected Funding Needs Update February 24, 2015 Overview Wastewater Collection System Customer Base 16,276 SFR 1,968 MFR 1,364 COM/IND

More information

Volume 1 Executive Summary

Volume 1 Executive Summary 2013 Cheyenne Water and Wastewater Master Plans Final November 27, 2013 Prepared for: City of Cheyenne Board of Public Utilities 2416 Snyder Ave. Cheyenne, WY 82001 Prepared by: HDR Engineering AMEC Earth

More information

ckly STAFF REPORT Trish Rhay, Assistant Director of Public Works Caitlin Sims, Senior Management Analyst

ckly STAFF REPORT Trish Rhay, Assistant Director of Public Works Caitlin Sims, Senior Management Analyst Subject: Distribution of Water Rates Public Notice Phase 1: Five-Year Rate Review and Adjustment to Address Revenue Phase 2: WEP Unit Capital Charge and Cost of Service Study. With that direction, staff

More information

Quonset Business Park Infrastructure Assets Water / Wastewater May 17, 2016

Quonset Business Park Infrastructure Assets Water / Wastewater May 17, 2016 Quonset Business Park Infrastructure Assets Water / Wastewater May 17, 2016 Quonset Development Corporation As the management and development entity of the Quonset Business Park, QDC maintained Capital

More information

Overview of Local Facilities. Integrated Resource Planning Advisory Committee

Overview of Local Facilities. Integrated Resource Planning Advisory Committee Overview of Local Facilities Integrated Resource Planning Advisory Committee City of Henderson Utility Services System Overview 2 CITY OF HENDERSON Department of Utility Services The Department of Utility

More information

Energy Reduction / Alternative Energy Strategies Palm Beach County Board of County Commissioners Water Utilities Department March 26, 2013 Bevin A. Beaudet, PE Utilities Director Utility Background Operations

More information

Horizon 2020 Steering Committee Water and Wastewater Master Plan Overview

Horizon 2020 Steering Committee Water and Wastewater Master Plan Overview Horizon 2020 Steering Committee Water and Wastewater Master Plan Overview August 11, 2014 Let s Look at the Numbers Water System 2 - Raw Water Sources Clinton Reservoir Kansas River 2 - Water Treatment

More information

Water and Wastewater Capital Improvement Plan Options and Revenue Requirements

Water and Wastewater Capital Improvement Plan Options and Revenue Requirements Water and Wastewater Capital Improvement Plan Options and Revenue Requirements The Master Plan s objectives are to assess our needs and recommend Capital Improvement Plans that address the following: Infrastructure

More information

City of Moline Water Infrastructure Overview

City of Moline Water Infrastructure Overview City of Moline Water Infrastructure Overview January 2012 Moline s Water Supply System Delivers: Public Health Protection Fire Protection Support for the Local Economy Quality of Life Moline s Water Supply

More information

Capital Investment Plan (CIP) Quarterly Report for the period ending December 2013

Capital Investment Plan (CIP) Quarterly Report for the period ending December 2013 Report Engineering Services Group Capital Investment Plan (CIP) Quarterly Report for the period ending December 2013 Summary This report provides a summary of fiscal year accomplishments, capital expenditures

More information

Long Beach Water Department Fiscal Year 2018 Annual Budget Summary

Long Beach Water Department Fiscal Year 2018 Annual Budget Summary Long Beach Water Department Fiscal Year 2018 Annual Summary I. Overview For over 100 years, the Long Beach Water Department has provided Long Beach residents and businesses with a reliable, cost-effective

More information

Capital Investment Plan (CIP) Quarterly report for period ending September 2015

Capital Investment Plan (CIP) Quarterly report for period ending September 2015 Report Group Capital Investment Plan (CIP) Quarterly report for period ending September 2015 Summary This report provides a summary of fiscal year accomplishments, capital expenditures to date, and updates

More information

ORANGE WATER AND SEWER AUTHORITY Quality Service Since 1977

ORANGE WATER AND SEWER AUTHORITY Quality Service Since 1977 ORANGE WATER AND SEWER AUTHORITY Quality Service Since 1977 Mayor Kevin Foy Town of Chapel Hill 306 North Columbia Street Chapel Hill, NC 27516 Chairman Barry Jacobs Orange County Board of Commissioners

More information

Capital Improvement Plan Update:

Capital Improvement Plan Update: Board of Supervisors Meeting Carson City Public Works Department Capital Improvement Plan Update: Wastewater Collection, Treatment and Reuse March 14, 2013 Topics of Discussion Regionalization Existing

More information

Engaging Our Team Investing in Our Infrastructure Employing Best Technology Exceptional Customer Service

Engaging Our Team Investing in Our Infrastructure Employing Best Technology Exceptional Customer Service Engaging Our Team Investing in Our Infrastructure Employing Best Technology Exceptional Customer Service 1 Our Mission We ensure safe and reliable services of water, wastewater and electricity, at an affordable

More information

Healthy Environment. Expenditure and Funding Source Summary Solid Waste Disposal:

Healthy Environment. Expenditure and Funding Source Summary Solid Waste Disposal: Healthy Environment Expenditure and Funding Source Summary... 53 Solid Waste Disposal: Hanes Mill Road Landfill Development and Upgrades... 54 Hanes Mill Road Landfill EVO Property Development... 55 Hanes

More information

UTILITY SYSTEM OVERVIEW. Water Source Water Distribution Wastewater Collection Wastewater Treatment

UTILITY SYSTEM OVERVIEW. Water Source Water Distribution Wastewater Collection Wastewater Treatment 1 UTILITY SYSTEM OVERVIEW Water Source Water Distribution Wastewater Collection Wastewater Treatment 2 AGENDA Overview of the Utility System (building on the Council tours) ARWA Petersburg SCWWA Infrastructure

More information

CHAPTER 1 - WASTEWATER SYSTEM DESCRIPTION

CHAPTER 1 - WASTEWATER SYSTEM DESCRIPTION CHAPTER 1 - WASTEWATER SYSTEM DESCRIPTION 1.1 Introduction The GWA provides wastewater services for Guam s general population and for Andersen Air Force Base. The wastewater system is made up of seven

More information

CITY OF YUBA CITY STAFF REPORT. Honorable Mayor & Members of the City Council. Diana Langley, Public Works Director. Water and Wastewater Rate Study

CITY OF YUBA CITY STAFF REPORT. Honorable Mayor & Members of the City Council. Diana Langley, Public Works Director. Water and Wastewater Rate Study CITY OF YUBA CITY STAFF REPORT Agenda Item 5 Date: March 1, 2016 To: From: Presentation by: Honorable Mayor & Members of the City Council Public Works Department Diana Langley, Public Works Director Summary

More information

Modified FY ,100, ,329,791

Modified FY ,100, ,329,791 Retail/North Andrews Gardens Neighborhood Improvement Program Expenses Through FY 4 Modified FY 5 Budget FY 26-21 North Andrews Gardens Neighborhood Improvement Project 21,524,34 22,75,757 --- 6,1, 6 ---

More information

ALBEMARLE COUNTY SERVICE AUTHORITY

ALBEMARLE COUNTY SERVICE AUTHORITY AGENDA TITLE: Rivanna Water & Sewer Authority (RWSA) Monthly Update STAFF CONTACT(S)/PREPARER: Gary O Connell, Executive Director AGENDA DATE: February 16, 2017 CONSENT AGENDA: Informational ATTACHMENTS:

More information

Capital Investment Plan Quarterly Report for period ending September 2017

Capital Investment Plan Quarterly Report for period ending September 2017 Report Engineering Services Group Capital Investment Plan Quarterly Report for period ending September 2017 Summary This report provides a summary of accomplishments to date on the Capital Investment Plan

More information

Pittsburgh Water Treatment Plant Projects. by Jay R. Lucas, P.E. Senior Project Manager

Pittsburgh Water Treatment Plant Projects. by Jay R. Lucas, P.E. Senior Project Manager Pittsburgh Water Treatment Plant Projects by Jay R. Lucas, P.E. Senior Project Manager Who Is American Water We are the largest publicly traded water and wastewater utility in the United States Broad national

More information

This is the title of the proposed project. A CIP contract or project number will be assigned to the projects as funding is established.

This is the title of the proposed project. A CIP contract or project number will be assigned to the projects as funding is established. WATER PROJECTS PROJECT DESCRIPTIONS The CIP includes a general list of projects scheduled during each of the five years of the program, followed by detailed project sheets arranged by project category,

More information

EXEMPLIFYING SHARED COMMITMENT TO THE PEE DEE: A PROACTIVE SOLUTION BY THE CITY

EXEMPLIFYING SHARED COMMITMENT TO THE PEE DEE: A PROACTIVE SOLUTION BY THE CITY EXEMPLIFYING SHARED COMMITMENT TO THE PEE DEE: A PROACTIVE SOLUTION BY THE CITY OF FLORENCE AND TOWN OF TIMMONSVILLE Josh Norton, PE CDM Smith Michael Hemingway City of Florence, SC 2014 NC AWWA/WEA 94TH

More information

AECOM Amendment 2. Thien Ng Interim Public Works Director. December 13, 2017

AECOM Amendment 2. Thien Ng Interim Public Works Director. December 13, 2017 AECOM Amendment 2 Thien Ng Interim Public Works Director December 13, 2017 AECOM Agreements to be Combined Public Works Department On-Call Engineering Services $250,000 Increase $250,000 Existing Water

More information

Public Utilities Department April 13, 2017 Delaware Citizens Academy Brad Stanton, Director

Public Utilities Department April 13, 2017 Delaware Citizens Academy Brad Stanton, Director Public Utilities Department April 13, 2017 Delaware Citizens Academy Brad Stanton, Director Utility Fast Facts Average household uses 107,000 gallons of water each year. 1,851 gallons of water to refine

More information

Utilities Extension Project (UEP) North 2 Update

Utilities Extension Project (UEP) North 2 Update Utilities Extension Project (UEP) North 2 Update Committee of the Whole Meeting February 8, 2016 1 North 2 Service Area Approx. 5.0 Sq. Miles Approx. 8,800 Parcels Construction Complete 2017 North 1 Service

More information

City Council Public Input Session Water / Sewer Rate Study. March 19, 2014

City Council Public Input Session Water / Sewer Rate Study. March 19, 2014 City Council Public Input Session Water / Sewer Rate Study March 19, 2014 Overview of Meeting Introduction of the Study Overview of Water and Sewer Systems FY14 Rate Study Work Accomplished and Presentations

More information

Boynton Beach Utilities

Boynton Beach Utilities Boynton Beach Utilities Budget Highlights Total Budget for 2018 19 $48,708,104 Increase from prior year $2,164,311 (4.7%) The following major changes include: General Fund direct overhead $2,850,000 General

More information

WILDERNESS MOUNTAIN WATER SERVICE 2014 ANNUAL REPORT OCTOBER 5, 2015

WILDERNESS MOUNTAIN WATER SERVICE 2014 ANNUAL REPORT OCTOBER 5, 2015 WILDERNESS MOUNTAIN WATER SERVICE 2014 ANNUAL REPORT OCTOBER 5, 2015 Purpose of the Annual General Meeting The agenda for the Annual General Meeting (AGM) is approved by the members of the Commission.

More information

DC WATER CAPITAL IMPROVEMENT PROGRAM (CIP)

DC WATER CAPITAL IMPROVEMENT PROGRAM (CIP) DC WATER CAPITAL IMPROVEMENT PROGRAM (CIP) District of Columbia Water and Sewer Authority of Maryland Thursday, April 7, 2016 George S. Hawkins, General Manager Presented by: Liliana Maldonado, Director,

More information

Polk City MAY SUMMARY

Polk City MAY SUMMARY Polk City Commissioners MAY 2013 UTILITY OPERATIONS SUMMARY TABLE OF CONTENTS SECTION PAGE NO. Executive Summary... ES-1 1. OPERATIONS AND MAINTENANCE ACTIVITIES... 1-1 1.1 Miscellaneous Job Order Completions...

More information

Metropolitan Water District

Metropolitan Water District 1 Metropolitan Water District Regional Water Wholesaler 6 counties 5,200 Square Miles 18 million people Growing 220,000 people/yr. 26 Member Agencies Support a $600+ Billion Regional economy Meets about

More information

Capital Improvement Summary by Fund

Capital Improvement Summary by Fund Capital Improvement Summary by Fund Central Services Fund Desciption F Y 2017 F Y 2018 F Y 2019 F Y 2020 F Y 2021 Total 2017-2021 Cost Revenues: Pay as you Go 1,000,000 1,000,000 Vehicle Leases - 1,250,000

More information

McDuff WTP High Service Pump Replacement

McDuff WTP High Service Pump Replacement T E C H N I C A L M E M O R A N D U M 642-03 MCDUFF WTP HIGH SERVICE PUMP REPLACEMENT 642-03 McDuff WTP High Service Pump Replacement PREPARED FOR: PREPARED BY: Capital Budget Planning Craig Jones DATE:

More information

Table 1 Population Projections Year Population 2,320 2,325 2,330 Percent Increase 0.22% 0.43%

Table 1 Population Projections Year Population 2,320 2,325 2,330 Percent Increase 0.22% 0.43% EXEMPLFYING SHARED COMMITMENT IN SOUTH CAROLINA: A PROACTIVE SOLUTION FOR A TOWN UNDER A FEDERAL CONSENT DECREE Olivia O. Flynn, PE Senior Project Manager, CDM Smith, Inc. ABSTRACT Few things are worse

More information

VILLAGE OF ALGONQUIN 2014 WASTEWATER FACILITY PLAN UPDATE EXECUTIVE SUMMARY

VILLAGE OF ALGONQUIN 2014 WASTEWATER FACILITY PLAN UPDATE EXECUTIVE SUMMARY EXECUTIVE SUMMARY EXECUTIVE SUMMARY INTRODUCTION AND BACKGROUND The Village of Algonquin, located along the Fox River in McHenry County, provides wastewater collection and treatment services to the entire

More information

LADWP WATER INFRASTRUCTURE PLAN

LADWP WATER INFRASTRUCTURE PLAN LADWP 2017-18 WATER INFRASTRUCTURE PLAN Introduction All major components of the Water System infrastructure are evaluated as part of the ongoing Asset Management (AM) Program. The goal of AM is to systematically

More information

All Facilities - Security Systems Improvement 15295

All Facilities - Security Systems Improvement 15295 All Facilities - Security Systems Improvement 15295 Total Program $13,743,000 Total ed Through June 30, 2016 $12,707,900 Appropriated Amount $19,600,000 Percent Complete 92% Biennial $275,900 Date 2018

More information

Terry Leeds, Director KC Water. February 21, 2017

Terry Leeds, Director KC Water. February 21, 2017 Terry Leeds, Director KC Water February 21, 2017 Capital Improvement Plan (CIP) FY 2018 CIP () Category s Investment Water 43 $71,340,000 Wastewater 64 $78,577,510 TOTAL: 107 $149,917,510 3 Water CIP ()

More information

City of Benicia Water and Sewer Rate Questions and Answers September 5, 2017

City of Benicia Water and Sewer Rate Questions and Answers September 5, 2017 City of Benicia Water and Sewer Rate Questions and Answers The following are a list of questions that were asked at the August 15, 2017 City Council meeting and the answers. 1. Why were the water meters

More information

Massachusetts Water Resources Authority Update on 2018 Water and Wastewater Master Plan

Massachusetts Water Resources Authority Update on 2018 Water and Wastewater Master Plan Massachusetts Water Resources Authority Update on 2018 Water and Wastewater Master Plan February 12, 2019 Background 33 Years of MWRA Capital Investment FY86 18 $8.3 Billion Capital Spending 70% on Wastewater

More information

City of Deerfield Beach. Environmental Services

City of Deerfield Beach. Environmental Services City of Deerfield Beach Environmental Services Areas of Responsibility Engineering and Administration Responsible for the coordination, budget, and quality control of all department functions. Review and

More information

WATER SUPPLY SERVICES

WATER SUPPLY SERVICES PRACTICE MANUAL FOR WATER SUPPLY SERVICES IN KENYA PART A WATER SUPPLY A 1 LIST OF CONTENTS PART A - WATER SUPPLY Page: A1 1. INTRODUCTION A16 1.1 Background A16 1.2 Purpose A17 1.3 Water Supply Administration

More information

Condition of Improvements 30 December 2014 Snettisham, Alaska (CWIS No )

Condition of Improvements 30 December 2014 Snettisham, Alaska (CWIS No ) Snettisham Condition of Improvements 30 December 2014 Snettisham, Alaska (CWIS No. 017020) Authorization Flood Control Act, 23 October 1962 (House Doc. 40, 87th Congress, 1st Session) as adopted, provides

More information

St. John the Baptist Parish

St. John the Baptist Parish St. John the Baptist Parish Conceptual Engineering of Mississippi River Water Source for LaPlace March 26, 2015 digital engineering 1 Major Water System Components Conceputalized Laplace Water System New

More information

City of Ames. Water Pollution Control. Long Range Facility Plan

City of Ames. Water Pollution Control. Long Range Facility Plan City of Ames Water Pollution Control Long Range Facility Plan Introduction Over 25 years ago, the City of Ames last completed a Wastewater Facility Plan. That Facility Plan prompted design and construction

More information

NELSONVILLE WATER TREATMENT PLANT IMPROVEMENTS

NELSONVILLE WATER TREATMENT PLANT IMPROVEMENTS Location City of Nelsonville, Ohio Environmental Engineering, Design and Bidding, Construction Administration and Observation, Start-up Services Cost $4.25 million Size 1,000 gallon per minute Professional

More information

REGULAR MEETING OF THE MUNICIPAL SERVICES COMMITTEE Tuesday, March 22, 2011, 4:00 P.M. 100 North Garfield Avenue, Pasadena, Council Chambers AGENDA

REGULAR MEETING OF THE MUNICIPAL SERVICES COMMITTEE Tuesday, March 22, 2011, 4:00 P.M. 100 North Garfield Avenue, Pasadena, Council Chambers AGENDA REGULAR MEETING OF THE MUNICIPAL SERVICES COMMITTEE Tuesday, March 22, 2011, 4:00 P.M. 100 North Garfield Avenue, Pasadena, Council Chambers AGENDA 1. CALL TO ORDER/ROLL CALL 2. PUBLIC COMMENTS ON MATTERS

More information

144

144 REVENUES Intergovernmental Grants $1,455,000 239,324 851,345 1,090,669 Investment Earnings 470,412 448,376 72,711 521,087 Wake County Reimbursement 131,760 131,760 --- 131,760 Developer Reimbursements

More information

Water Treatment Plant and Water Supply Study CITY OF SNOHOMISH, WASHINGTON

Water Treatment Plant and Water Supply Study CITY OF SNOHOMISH, WASHINGTON Water Treatment Plant and Water Supply Study CITY OF SNOHOMISH, WASHINGTON May 2009 TABLE OF CONTENTS EXECUTIVE SUMMARY Page Purpose and Background... ES-1 Existing Water System... ES-1 Water Demands...

More information

Matt Jordan, General Manager Charles H. Carden, Chief Operating Officer Energy Management Program - Status Report

Matt Jordan, General Manager Charles H. Carden, Chief Operating Officer Energy Management Program - Status Report AGENDA ITEM C4 DATE: June 1, 2015 TO: FROM: SUBJECT: SUMMARY: Matt Jordan, General Manager Charles H. Carden, Chief Operating Officer Energy Management Program - Status Report A programmatic approach to

More information

CAPITAL IMPROVEMENT PROGRAM WATER

CAPITAL IMPROVEMENT PROGRAM WATER CAPITAL IMPROVEMENT PROGRAM 246 247 FUNDS (711-715) Access Road Improvements c709840 Minor road repair and pipeline clearance work to gain access to water facilities and equipment. Project Cost Estimate

More information

HOW TO SAVE COSTS AND IMPROVE SUSTAINABILITY WHILE REDUCING EFFLUENT NITROGEN

HOW TO SAVE COSTS AND IMPROVE SUSTAINABILITY WHILE REDUCING EFFLUENT NITROGEN HOW TO SAVE COSTS AND IMPROVE SUSTAINABILITY WHILE REDUCING EFFLUENT NITROGEN Introduction Donna Kaluzniak, CEP, Utility Director, City of Atlantic Beach, Florida John E. Collins, Jr., P.E., J. Collins

More information

Cypress Waters: TIF Plan and MOU Amendments, Related Service Plan/Development Agreements and Boundary Adjustments

Cypress Waters: TIF Plan and MOU Amendments, Related Service Plan/Development Agreements and Boundary Adjustments Cypress Waters: TIF Plan and MOU Amendments, Related Service Plan/Development Agreements and Boundary Adjustments Economic Development Committee June 1, 2015 Purpose Update status of Cypress Waters project

More information

Water / Wastewater Fund

Water / Wastewater Fund WATER/WASTEWATER FUND The Water/Wastewater Fund is used to account for the provision of water and wastewater services to residents of the City. All activities necessary to provide water/ wastewater services

More information

This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library.

This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library. This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library. For additional information about this document and the document conversion process, please contact

More information

Public Utilities - Sewer

Public Utilities - Sewer County of Henrico, Virginia Capital Improvement Program FY 2017-18 through FY 2021-22 Fund 51 Enterprise Fund - W&S Request Request Request Request Request Project/Work Phase Priority FY 17-18 FY18-19

More information

Louisville & Jefferson County Metropolitan Sewer District Infrastructure Upgrades Overview. Wet Weather Team Stakeholder Group Meeting July 20, 2006

Louisville & Jefferson County Metropolitan Sewer District Infrastructure Upgrades Overview. Wet Weather Team Stakeholder Group Meeting July 20, 2006 Louisville & Jefferson County Metropolitan Sewer District Infrastructure Upgrades Overview Wet Weather Team Stakeholder Group Meeting July 20, 2006 AGENDA MSD Capital Spending Trends Capital Project Accomplishments

More information

The Future of Ventura s Water Supply

The Future of Ventura s Water Supply The Future of Ventura s Water Supply Daniel Cormode East Ventura Community Council Planning & Development Committee 2016 02 25 02/28/2016 11 We re running short of water? 02/28/2016 2 1/1/2025 Allocation

More information

Marina Coast Water District: A California Special District ORD COMMUNITY WATER AUGMENTATION

Marina Coast Water District: A California Special District ORD COMMUNITY WATER AUGMENTATION Marina Coast Water District: A California Special District ORD COMMUNITY WATER AUGMENTATION DIRECTORS Dr. THOMAS P. MOORE President JAN SHRINER Vice President HOWARD GUSTAFSON WILLIAM Y. LEE PETER LE Interim

More information

BOARD OF COUNTY COMMISSIONERS OKALOOSA COUNTY, FLORIDA DEPARTMENT/PROGRAM: WATER & SEWER ENTERPRISE FUND/WATER OPERATIONS

BOARD OF COUNTY COMMISSIONERS OKALOOSA COUNTY, FLORIDA DEPARTMENT/PROGRAM: WATER & SEWER ENTERPRISE FUND/WATER OPERATIONS Water & Sewer SERVICE AREA: PHYSICAL ENVIRONMENT BOARD OF COUNTY COMMISSIONERS OKALOOSA COUNTY, FLORIDA DEPARTMENT/PROGRAM: WATER & SEWER ENTERPRISE FUND/WATER OPERATIONS PROGRAM DESCRIPTION: This program

More information

2018 Water and Wastewater Budget Summary

2018 Water and Wastewater Budget Summary 2018 Water and Wastewater Budget Summary Each day, clean, safe water travels through the City s watermains for use by residents and businesses. Similarly, wastewater flows through the City s sewer system

More information

WATER AND SEWER INFRASTRUCTURE PROGRAMS

WATER AND SEWER INFRASTRUCTURE PROGRAMS Arlington County, Virginia WATER AND SEWER INFRASTRUCTURE PROGRAMS Program Description This program provides and maintains water delivery, sanitary sewer collection, and wastewater treatment systems that

More information

Thermal and Hydro Power Plant Maintenance Deer Island Treatment Plant

Thermal and Hydro Power Plant Maintenance Deer Island Treatment Plant Massachusetts Water Resources Authority Presentation to MWRA Board of Directors Thermal and Hydro Power Plant Maintenance Deer Island Treatment Plant March 12, 2014 On-Site Thermal/Power Plant Built in

More information

BOARD CORPORATE ALLOCATION POLICY

BOARD CORPORATE ALLOCATION POLICY BOARD CORPORATE ALLOCATION POLICY 1 2018 CENTRALIZED SUPPORT BOARD POLICY Approved July 2017 Updated previously based on 2010 operating costs Adjusted annually Methodology for allocation to MV entities

More information

City Council Liaisons: Mayor Galbraith and Councilmember Mary Koberstein

City Council Liaisons: Mayor Galbraith and Councilmember Mary Koberstein City of St. Helena Ad Hoc Committee Special Meeting Vintage Hall Board Room - Second Floor, 465 Main Street., St. Helena, CA 94574 Monday, May 8, 2017 @ 6:00 PM 1. CALL TO ORDER 2. ROLL CALL Ad Hoc Utility

More information

Rehoboth Beach Commissioners Meeting Ocean Outfall & Treatment Plant Project Update July 26, Jeff Sturdevant Principal Kelvin George Principal

Rehoboth Beach Commissioners Meeting Ocean Outfall & Treatment Plant Project Update July 26, Jeff Sturdevant Principal Kelvin George Principal Rehoboth Beach Commissioners Meeting Ocean Outfall & Treatment Plant Project Update July 26, 2017 Jeff Sturdevant Principal Kelvin George Principal Rehoboth Beach Ocean Outfall/CIP Project(s) Update Agenda

More information

Capital Improvement Plan. Fiscal Years

Capital Improvement Plan. Fiscal Years Fiscal Years 2019 2024 June 2018 Table of Contents Summary of Uses and Sources of Funds 1 Use of Funds 2 Source of Funds 3 Capital Acquisitions, Improvements & Replacement Needs: Fiscal Year 2019 4-6 Fiscal

More information

ALBEMARLE COUNTY SERVICE AUTHORITY

ALBEMARLE COUNTY SERVICE AUTHORITY AGENDA TITLE: Rivanna Water & Sewer Authority (RWSA) Monthly Update STAFF CONTACT(S)/PREPARER: Gary O Connell, Executive Director AGENDA DATE: May 18, 2017 CONSENT AGENDA: Informational ATTACHMENTS: None

More information

Section 5: Infrastructure and Utilities

Section 5: Infrastructure and Utilities 5.0 Infrastructure and Utilities 5.1 Introduction The Town of Holly Springs rapid growth provides for challenges with respect to funding, environmental permitting, and installation of infrastructure utilities

More information

CHARLES RIVER POLLUTION CONTROL DISTRICT Capital Improvement Plan

CHARLES RIVER POLLUTION CONTROL DISTRICT Capital Improvement Plan CHARLES RIVER POLLUTION CONTROL DISTRICT Capital Improvement Plan Cheri Cousens, P.E. Executive Director, CRPCD Jane Madden, P.E. Senior Vice President, CDM November 21, 2011 Agenda Introduction Proposed

More information

Summary Report of MWRA Demand Management Program Fiscal Year 2015

Summary Report of MWRA Demand Management Program Fiscal Year 2015 Summary Report of MWRA Demand Management Program Fiscal Year 2015 This report is organized into four sections, as follows: 1. Summary 2. Background and Long Range Water Supply Program 3. Ongoing Demand

More information

DISTRICT COURT, WATER DIVISION 7, COLORADO WATER RESUME

DISTRICT COURT, WATER DIVISION 7, COLORADO WATER RESUME DISTRICT COURT, WATER DIVISION 7, COLORADO WATER RESUME TO: ALL PERSONS INTERESTED IN WATER APPLICATIONS IN SAID WATER DIVISION NO. 7 Pursuant to C.R.S. 37-92-302, you are notified that the following is

More information

Water Treatment Plant Phase 1 Upgrades CMAR Selection Pre-Submittal Meeting

Water Treatment Plant Phase 1 Upgrades CMAR Selection Pre-Submittal Meeting Water Treatment Plant Phase 1 Upgrades CMAR Selection Pre-Submittal Meeting October 12, 2017 Water Treatment Plant Phase 1 Upgrades 22 mgd WTP Expand capacity to 32 mgd Upgrades to most processes Only

More information

Report. Engineering Services Group. Capital Investment Plan (CIP) Quarterly Report for the period ending September Summary.

Report. Engineering Services Group. Capital Investment Plan (CIP) Quarterly Report for the period ending September Summary. Report Engineering Services Group Capital Investment Plan (CIP) Quarterly Report for the period ending September 2012 Summary This report provides a summary of fiscal year accomplishments, capital expenditures

More information

Charlotte County Utilities

Charlotte County Utilities Charlotte County Utilities Past, Present, and Future Board Workshop - April 16, 2013 Past CHARLOTTE COUNTY UTILITIES ESTABLISHED 1991 CCU Beginnings General Development Utilities (GDU) A Florida Corporation

More information

Building a Water System for Our Future

Building a Water System for Our Future Water Department Prop. 218 Notice Proposed Rates July 2016 Building a Water System for Our Future The mission of the City of Santa Cruz Water Department is to provide a safe, clean and continuous supply

More information

Water Development Commission 6920 YELLOWTAIL ROAD TELEPHONE: (307) CHEYENNE, WY 82002

Water Development Commission 6920 YELLOWTAIL ROAD TELEPHONE: (307) CHEYENNE, WY 82002 THE STATE OF WYOMING Water Development Commission 6920 YELLOWTAIL ROAD TELEPHONE: (307) 777-7626 CHEYENNE, WY 82002 WATER DEVELOPMENT PROGRAM APPLICATION MUNICIPAL/JOINT POWERS WATER BOARD WATER SYSTEMS

More information

TUOLUMNE UTILITIES DISTRICT FY 18 CAPITAL IMPROVEMENT PROGRAM STATUS-AT-A-GLANCE AS OF OCTOBER 24, 2017

TUOLUMNE UTILITIES DISTRICT FY 18 CAPITAL IMPROVEMENT PROGRAM STATUS-AT-A-GLANCE AS OF OCTOBER 24, 2017 FY 18 CAPITAL IMPROVEMENT PRORAM STATUS-AT-A-LANCE AS OF OCTOBER 24, 2017 Water Sewer Phoenix Dam Improvements-Phase 1 1 Scope of work for improvements to Phoenix Lake Dam in accordance with annual Division

More information

City of Naples. Utilities Department Operation and Maintenance Budgets Fiscal Year Water & Sewer Solid Waste Equipment Services

City of Naples. Utilities Department Operation and Maintenance Budgets Fiscal Year Water & Sewer Solid Waste Equipment Services City of Naples Water & Sewer Solid Waste Equipment Services Utilities Department Operation and Maintenance Budgets Fiscal Year 2016-17 August 15, 2016 Water and Sewer Fund Total department expenses $21,859,133

More information

GREEN PROJECT RESERVE BUSINESS CASE CITY OF BROKEN ARROW WATER SUPPLY IMPROVEMENTS PROJECT

GREEN PROJECT RESERVE BUSINESS CASE CITY OF BROKEN ARROW WATER SUPPLY IMPROVEMENTS PROJECT GREEN PROJECT RESERVE BUSINESS CASE CITY OF BROKEN ARROW WATER SUPPLY IMPROVEMENTS PROJECT July, 2011 The Oklahoma Water Resources Board (OWRB) requires a Business Case be made for projects or certain

More information

Storm Water Utility Improvements

Storm Water Utility Improvements Storm Water Utility Improvements Overview: The Storm Water Utility includes culverts, intakes, and subsurface piping designed to convey storm water from the City during wet weather events. Status of Storm

More information

Water / Wastewater Fund

Water / Wastewater Fund WATER/WASTEWATER FUND The Water/Wastewater Fund is used to account for the provision of water and wastewater services to residents of the City. All activities necessary to provide water/ wastewater services

More information

EnTech, Inc. Consulting Engineers Sheridan, Wyoming

EnTech, Inc. Consulting Engineers Sheridan, Wyoming TOWNS OF DAYTON AND RANCHESTER WATER SUPPLY PROJECTS UPDATE PRESENTED BY: EnTech, Inc. Consulting Engineers Sheridan, Wyoming TOWN OF DAYTON PROBLEM AREAS WITH CURRENT WATER SYSTEM EXISTING 10 ASBESTOS

More information

GENERAL ASSEMBLY OF NORTH CAROLINA SESSION 2011 SESSION LAW HOUSE BILL 609

GENERAL ASSEMBLY OF NORTH CAROLINA SESSION 2011 SESSION LAW HOUSE BILL 609 GENERAL ASSEMBLY OF NORTH CAROLINA SESSION 2011 SESSION LAW 2011-374 HOUSE BILL 609 AN ACT TO PROMOTE THE DEVELOPMENT OF WATER SUPPLY RESERVOIRS AND OTHER WATER SUPPLY RESOURCES, TO PROVIDE THAT FUNDS

More information

Management of Aging Wastewater Infrastructure -- Challenges and Strategies --

Management of Aging Wastewater Infrastructure -- Challenges and Strategies -- Management of Aging Wastewater Infrastructure -- Challenges and Strategies -- Jerry N. Johnson, General Manager District of Columbia Water and Sewer Authority Washington, D.C. Overview of the Aging Situation

More information

Director of Utilities City of Amarillo. Panhandle-High Plains Water Conservation Symposium. Amarillo Civic Center Amarillo, TX February 12, 2014

Director of Utilities City of Amarillo. Panhandle-High Plains Water Conservation Symposium. Amarillo Civic Center Amarillo, TX February 12, 2014 Presented by: To: At: Emmett A. Autrey Director of Utilities City of Amarillo Panhandle-High Plains Water Conservation Symposium Amarillo Civic Center Amarillo, TX February 12, 2014 Water Use Categories

More information

Providing Infrastructure Redundancy at the Rocky River WWTP. Timothy McCann AECOM Keith Bovard Rocky River WWTP

Providing Infrastructure Redundancy at the Rocky River WWTP. Timothy McCann AECOM Keith Bovard Rocky River WWTP Timothy McCann AECOM Keith Bovard Rocky River WWTP WWTP Infrastructure Redundancy Redundancy As NASA Would Say: A Backup Plan for the Backup Plan Nuclear Power Plant Wastewater Treatment Plant Page 3 Infrastructure

More information

City of Modesto - North Valley Regional Recycled Water Program (NVRRWP) William Wong Engineering Division Manager Utilities Department

City of Modesto - North Valley Regional Recycled Water Program (NVRRWP) William Wong Engineering Division Manager Utilities Department City of Modesto - North Valley Regional Recycled Water Program (NVRRWP) William Wong Engineering Division Manager Utilities Department City of Modesto Wastewater System Provides sewer service for Modesto,

More information