National Environmental Policy Act (NEPA) Process and Federal Agency Compliance

Size: px
Start display at page:

Download "National Environmental Policy Act (NEPA) Process and Federal Agency Compliance"

Transcription

1 National Environmental Policy Act (NEPA) Process and Federal Agency Compliance Prepared for Northwest/Tribal Transportation Program Training/Conference April 1, /2/2014 1

2 Course Objectives Provide a brief overview of the NEPA procedures with respect to federal actions NEPA s relationship to other federal and regulatory requirements Schedule 4/2/2014 2

3 Authorities National Environmental Policy Act 1969 (NEPA) Section 102 (2) of NEPA establishes procedures which are binding on all Federal agencies. Council on Environmental Quality (CEQ) NEPA established the Council on Environmental Quality (CEQ) in the Office of the President. CEQ has promulgated regulations for implementing the procedural provisions of NEPA (40 CFR Parts ) 4/2/2014 3

4 59 IAM 3-H BIA s NEPA Handbook Provides advisory guidance for compliance with the NEPA process as regulated by CEQ. Provides guidance to BIA and tribal officials. Provides a step-by-step approach of explaining each phase of the NEPA process. 4/2/2014 4

5 516 DM 10 Department of the Interior Manual for Managing the NEPA Process-Bureau of Indian Affairs Provides supplementary requirements for implementing provisions of 156 DM 1 through 6 within the Department s Bureau of Indian Affairs Defines NEPA responsibilities within the agency Provides guidance to Tribal Governments 4/2/ and/or other Applicants.

6 When is NEPA triggered? If the action uses Federal funding, requires Federal licensing or is carried out by a Federal agency, then NEPA is triggered. 4/2/2014 6

7 NEPA Compliance Was there adequate environmental analysis and identification of the environmental impacts of the proposed federal action sufficiently covered in an earlier environmental document? Is the proposed federal action a listed Categorical Exclusion? 4/2/2014 7

8 Types of NEPA Documents Categorical Exclusions (CATEX) Exception Checklist for BIA Categorical Exclusions Environmental Assessment (EA) Finding Of No Significant Impact (FONSI) Environmental Impact Statement (EIS) Record of Decision (ROD) Finding 4/2/2014 8

9 Categorical Exclusions Actions which have been listed in 516 DM 2, Appendix 1 and 516 DM 10.5, have been determined not to individually or cumulatively affect the quality of the human environment and, therefore, they do not normally require an EA or EIS. 4/2/2014 9

10 Roads and Transportation CATXs 516 DM 10.5L Eleven Exemption Categories Approval of utility installations along or across a transportation facility located in whole within the limits of the roadway rights-of-way. Construction of bicycle and pedestrian lanes and paths adjacent to existing highways and within the existing rights-of-way. 4/2/

11 Roads and Transportation CATXs Activities included in a highway safety plan under 23 CFR 402. Installation of fencing, signs, pavement markings, small passenger shelters, traffic signals, and railroad warning devices where no substantial land acquisition or traffic disruption will occur. Emergency repairs under 23 U.S.V /2/

12 Roads and Transportation CATXs Acquisition of scenic easements Alterations to facilities to make them accessible for the elderly or handicapped. Resurfacing a highway without adding to the existing width. Rehabilitation, reconstruction, or replacement of an existing bridge structure on essentially the same alignment or location. 4/2/

13 Roads and Transportation CATXs Approvals for changes in access control within the existing rights-of-way. Road construction within an existing right-ofway which has already been acquired for a HUD housing project and for which earlier NEPA analysis has already been prepared. 4/2/

14 Other Exclusion Categories. 516 DM 10.5A Operation, Maintenance and Replacement of Existing Facilities. Examples are normal renovation of buildings, road maintenance, and limited rehabilitation of irrigation structures. 516 DM 10.5F Rights-of-Way e.g. renewals, amendments, ROW within ROW, service line agreements 4/2/

15 Environmental Assessment The main purpose of an EA is to determine whether or not an EIS is required. If an EA supports a Finding of No Significant Impact (FONSI), then an EIS is not required. 4/2/

16 Environmental Impact Statement The primary requirement of NEPA is that an EIS be prepared for every Federal action that will or may significantly affect the quality of the human environment. There are three ways of reaching the conclusion that an EIS is required. 4/2/

17 Environmental Impact Statement EIS is normally required when: The actions are listed in 516 DM 6, Appendix 4.3. If an EA does not support a FONSI. If, based on the judgment of the responsible BIA official(s), an EA is not likely to support a FONSI, then unnecessary delay can be avoided by preparing an EIS rather than an EA. 4/2/

18 EA Procedures Notice of Availability of Draft EA 30 day Public Comment Period Responses to Comments/Revisions to Draft EA FONSI or FONSI/Final EA Notice of Availability of FONSI 30 day waiting period prior to action implementation 4/2/

19 EIS Procedures Notice of Intent (NOI), publish in Federal Register Scoping Phase, public hearing, issues and alternatives Scoping Report Cooperating Agency invitations Administrative Draft EIS 4/2/

20 EIS Procedures continued Notice of Availability of DEIS, publish in Federal Register 60 day Public Comment Period Public Hearing Responses to Comments NOA of FEIS, publish in Federal Register Record of Decision 4/2/

21 Other Federal Statutes Section 106 of the National Historic Preservation Act Endangered Species Act Clean Water Act Safe Drinking Water Act Clean Air Act Coastal Zone Management Act 4/2/

22 For additional information on the NEPA process B J Howerton, Regional Environmental Protection Specialist: (503) or b.howerton@bia.gov For a copy of this Power Point presentation Dan Hall, Regional Archeologist PRO/Acting Regional Archeologist NWRO: (916) harold.hall@bia.gov 4/2/

TRANSMITTAL LETTER. Design Manual Part 1B Post-TIP NEPA Procedures November 2015 Edition

TRANSMITTAL LETTER. Design Manual Part 1B Post-TIP NEPA Procedures November 2015 Edition OS-299 (7-08) TRANSMITTAL LETTER PUBLICATION: Publication 10B November DATE: November 9, 2015 SUBJECT: Design Manual Part 1B Post-TIP NEPA Procedures November INFORMATION AND SPECIAL INSTRUCTIONS: Publication

More information

Updates on FAA Order F. Agenda. Communicate FAA Order Updates. Educate attendees on the changes to FAA Order

Updates on FAA Order F. Agenda. Communicate FAA Order Updates. Educate attendees on the changes to FAA Order Updates on FAA Order 1050.1F Rhonda Solomon March 3, 2015 Airports Conference 2015 Agenda Communicate FAA Order 1050.1 Updates Educate attendees on the changes to FAA Order 1050.1 1 1 Overview of NEPA

More information

ARP SOP No SOP for CATEX Determinations Effective Date: Oct. 01, Federal Aviation Administration

ARP SOP No SOP for CATEX Determinations Effective Date: Oct. 01, Federal Aviation Administration ARP SOP No. 5.00 SOP for CATEX Determinations Effective Date: Oct. 01, 2014 February 2016 Important Points to Note: FAA recently established Standard Operating Procedures (SOP) for CatEx Determinations

More information

NYSDOT Project Development Manual (PDM)

NYSDOT Project Development Manual (PDM) Company LOGO NYSDOT Project Development Manual (PDM) Overview of NYSDOT Project Development Process January 24, 2006 Farhan F. Haddad, P.E. Design Quality Assurance Bureau Project Development Manual

More information

CEQA BASICS. The California Environmental Quality Act. Prepared for: Orange County Department of Education. Prepared by:

CEQA BASICS. The California Environmental Quality Act. Prepared for: Orange County Department of Education. Prepared by: The California Environmental Quality Act CEQA BASICS Prepared for: Orange County Department of Education Prepared by: Contact: DWAYNE MEARS, AICP Principal 714.966.9220 dmears@planningcenter.com The Beginning

More information

THE COMMONWEALTH OF MASSACHUSETTS NON-NHS BRIDGE R&R POLICY

THE COMMONWEALTH OF MASSACHUSETTS NON-NHS BRIDGE R&R POLICY THE COMMONWEALTH OF MASSACHUSETTS Number: P-92-010 Date: 10-08-92 - ) HIGHWAY DEPARTMENT FROM: NON-NHS BRIDGE R&R POLICY The purpose of this Engineering Directive is to formally notify Department Personnel

More information

ALTERNATIVE PROJECT DELIVERY DIVISION

ALTERNATIVE PROJECT DELIVERY DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION ALTERNATIVE PROJECT DELIVERY DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Design-Build Requirements for Advertisement SPECIFIC SUBJECT: APPROVED:

More information

NEPA OVERVIEW & ANALYSIS Environmental Law Workshop Loyola Law School/Sierra Club Angeles Chapter

NEPA OVERVIEW & ANALYSIS Environmental Law Workshop Loyola Law School/Sierra Club Angeles Chapter NEPA OVERVIEW & ANALYSIS 2010 Environmental Law Workshop Loyola Law School/Sierra Club Angeles Chapter Summary 1. OVERVIEW OF STATUTE 2. COMPARISONS TO CEQA 3. DISCUSSION OF NEPA AND GHG s CASE LAW RECENT

More information

PROGRAM NAME: Northfield Owner-Occupied Home Rehabilitation 2015

PROGRAM NAME: Northfield Owner-Occupied Home Rehabilitation 2015 NEW YORK STATE HOUSING TRUST FUND HOME PROGRAM PROGRAMMATIC ENVIRONMENTAL REVIEW RECORD FOR LOCAL PROGRAM ADMINISTRATOR (LPA) PROGRAMS PROGRAM NAME: Northfield Owner-Occupied Home Rehabilitation 2015 SHARS

More information

National Environmental Policy Act (NEPA)

National Environmental Policy Act (NEPA) National Environmental Policy Act (NEPA) Jeff Wade Center for Governmental Responsibility University of Florida Levin College of Law The National Environmental Policy Act of 1969 (NEPA) first significant,

More information

Project Purpose. Federal Railroad Administration

Project Purpose. Federal Railroad Administration Project Purpose To preserve the current functionality of Amtrak s Northeast Corridor service and NJ TRANSIT s commuter rail service between New Jersey and Penn Station New York by repairing the deteriorating

More information

FEDERAL BOULEVARD (5 TH AVENUE TO HOWARD PLACE) PLANNING ENVIRONMENTAL LINKAGE STUDY TRAFFIC NOISE IMPACT ANALYSIS

FEDERAL BOULEVARD (5 TH AVENUE TO HOWARD PLACE) PLANNING ENVIRONMENTAL LINKAGE STUDY TRAFFIC NOISE IMPACT ANALYSIS FEDERAL BOULEVARD (5 TH AVENUE TO HOWARD PLACE) PLANNING ENVIRONMENTAL LINKAGE STUDY TRAFFIC NOISE IMPACT ANALYSIS Prepared for: City and County of Denver 201 West Colfax Avenue, Department 509 Denver,

More information

Transportation Decision-making Principles of Project Evaluation and Programming. Chapter 1. Introductory Concepts in Transportation Decision Making

Transportation Decision-making Principles of Project Evaluation and Programming. Chapter 1. Introductory Concepts in Transportation Decision Making Transportation Decision-making Principles of Project Evaluation and Programming Chapter 1 Introductory Concepts in Transportation Decision Making K. C. Sinha and S. Labi Purdue University School of Civil

More information

TAPPAN ZEE HUDSON RIVER CROSSING PROJECT

TAPPAN ZEE HUDSON RIVER CROSSING PROJECT TAPPAN ZEE HUDSON RIVER CROSSING PROJECT Joint Record of Decision and State Environmental Quality Review Act Findings Statement Rockland and Westchester Counties, New York Federal Lead Agency: Federal

More information

New Jersey Department of Transportation. Local Freight Impact Fund Handbook. Procedures and Criteria for Local Freight Impact Fund Grant Program

New Jersey Department of Transportation. Local Freight Impact Fund Handbook. Procedures and Criteria for Local Freight Impact Fund Grant Program New Jersey Department of Transportation Local Freight Impact Fund Handbook Procedures and Criteria for Local Freight Impact Fund Grant Program Page 1 of 10 Overview The New Jersey Department of Transportation

More information

MISSILE DEFENSE AGENCY RECORD OF ENVIRONMENTAL CONSIDERATION

MISSILE DEFENSE AGENCY RECORD OF ENVIRONMENTAL CONSIDERATION MISSILE DEFENSE AGENCY RECORD OF ENVIRONMENTAL CONSIDERATION Project Title: AN/TPY-2 Radar Deployment at the Ted Stevens Marine Research Institute (TSMRI) on the National Oceanic and Atmospheric Administration

More information

MAP-21 DIVISION A FEDERAL-AID HIGHWAYS AND HIGHWAY SAFETY CONSTRUCTION PROGRAMS

MAP-21 DIVISION A FEDERAL-AID HIGHWAYS AND HIGHWAY SAFETY CONSTRUCTION PROGRAMS MAP-21 DIVISION A FEDERAL-AID HIGHWAYS AND HIGHWAY SAFETY CONSTRUCTION PROGRAMS Section Program/Topic Funding Major Changes from SAFETEA-LU Implications for Minnesota Authorizations and Programs 1101 Authorization

More information

GEOMETRIC DESIGN CRITERIA for Non-freeway Resurfacing, Restoration, and Rehabilitation Projects

GEOMETRIC DESIGN CRITERIA for Non-freeway Resurfacing, Restoration, and Rehabilitation Projects GEOMETRIC DESIGN CRITERIA for Non-freeway Resurfacing, Restoration, and Rehabilitation Projects SEPTEMBER 1989 Arkansas State Highway and Transportation Department GEOMETRIC DESIGN CRITERIA for Non-freeway

More information

Overview of the Project Development Process. Brian Blanchard, PE Assistant Secretary for Engineering and Operations

Overview of the Project Development Process. Brian Blanchard, PE Assistant Secretary for Engineering and Operations Overview of the Project Development Process Brian Blanchard, PE Assistant Secretary for Engineering and Operations Overall Project Development Process The time it takes to produce a project varies significantly

More information

Defense Logistics Agency REGULATION

Defense Logistics Agency REGULATION Defense Logistics Agency REGULATION DLAR 1000.22 Effective December 2, 2011 ENVIRONMENTAL CONSIDERATIONS IN DEFENSE LOGISTICS AGENCY ACTIONS Subpart A - Introduction Section 1 Purpose. a. This part implements

More information

Long Bridge Project. Environmental Impact Statement (EIS) Revised Purpose and Need

Long Bridge Project. Environmental Impact Statement (EIS) Revised Purpose and Need Environmental Impact Statement (EIS) Revised Purpose and Need June 23, 2017 1.0 What is the Proposed Action? The consists of potential improvements to the Long Bridge and related railroad infrastructure

More information

U.S. DEPARTMENT OF TRANSPORTATION Federal Highway Administration. RECORD OF DECISION June 2014

U.S. DEPARTMENT OF TRANSPORTATION Federal Highway Administration. RECORD OF DECISION June 2014 U.S. DEPARTMENT OF TRANSPORTATION Federal Highway Administration RECORD OF DECISION June 2014 Grand Parkway (State Highway 99) Segments H and I-1 From United States Highway (US) 59 North/Interstate Highway

More information

Technical Memorandum MULTIMODAL NEEDS. Prepared for: Oklahoma Department of Transportation. Prepared by:

Technical Memorandum MULTIMODAL NEEDS. Prepared for: Oklahoma Department of Transportation. Prepared by: Technical Memorandum MULTIMODAL NEEDS Prepared for: Oklahoma Department of Transportation Prepared by: May 2015 Technical Memorandum The Technical Memos were written to document early research for the

More information

The ET Rover Pipeline Processes and Pitfalls of Pipeline Development

The ET Rover Pipeline Processes and Pitfalls of Pipeline Development The ET Rover Pipeline Processes and Pitfalls of Pipeline Development Presented by: James J. Lanham J. Benjamin Fraifogl Critchfield, Critchfield& Johnston, Ltd. 225 N. Market Street Wooster, Ohio 44691

More information

AREAWIDE BRIDGE REPLACEMENT AND REHABILITATION

AREAWIDE BRIDGE REPLACEMENT AND REHABILITATION CECIL COUNTY 2018 TRANSPORTATION IMPROVEMENT PROGRAM AREAWIDE BRIDGE REPLACEMENT AND REHABILITATION DESCRIPTION: On-going program to provide major upgrades to state owned bridges that are structurally

More information

CODE CONSOLIDATION PHASE II SUMMARY OF CHANGES Effective February 1, 2011, Ordinance s

CODE CONSOLIDATION PHASE II SUMMARY OF CHANGES Effective February 1, 2011, Ordinance s CODE CONSOLIDATION PHASE II SUMMARY OF CHANGES Effective February 1, 2011, Ordinance 2010-70s Revisions to Title 2 Administration 2.45 Land Use Advisory Commissions. Twelve individual LUAC chapters were

More information

CEQA Categorical Exemption Determination

CEQA Categorical Exemption Determination CEQA Categorical Exemption Determination PROPERTY INFORMATION/PROJECT DESCRIPTION Project Address Block/Lot(s) Case No. Permit No. Plans Dated Addition/ Demolition Alteration (requires HRER if over 45

More information

All Aboard Florida Project Status Update TREASURE COAST REGIONAL PLANNING COUNCIL

All Aboard Florida Project Status Update TREASURE COAST REGIONAL PLANNING COUNCIL All Aboard Florida Project Status Update TREASURE COAST REGIONAL PLANNING COUNCIL APRIL 2014 Southeast Florida Rail Network & Proposed All Aboard Florida Route To Jacksonville Tampa Orlando Everglades

More information

2.1 Project Definition/Classification/Initial Study Project Definition

2.1 Project Definition/Classification/Initial Study Project Definition 2.1 Project Definition/Classification/Initial Study 2.1.1 Project Definition The correct and complete definition of all reasonably foreseeable elements of a proposed project is the single most important

More information

TCATS October 12-Michigan Works 5:30-7pm. NATS October 19-Niles District Library 6-7:30pm

TCATS October 12-Michigan Works 5:30-7pm. NATS October 19-Niles District Library 6-7:30pm Goal Development Workshop TCATS October 12- Works 5:30-7pm NATS October 19-Niles District Library 6-7:30pm SAFETEA-LU Goals 2035 TwinCATS Goals 2030 TwinCATS Goals 1. Support the economic vitality of the

More information

Introduction to the Proposed Statewide Transportation Improvement Program (STIP) Transportation Planning and Programming

Introduction to the Proposed Statewide Transportation Improvement Program (STIP) Transportation Planning and Programming Introduction to the Proposed 2015-2018 Statewide Transportation Improvement Program (STIP) Transportation Planning and Programming Public Hearing August 19 th, 2014 TABLE OF CONTENTS Introduction... 1

More information

The Policies section will also provide guidance and short range policies in order to accomplish the goals and objectives.

The Policies section will also provide guidance and short range policies in order to accomplish the goals and objectives. 4 Goals & Objectives INTRODUCTION The 2015-2040 MTP preserves and promotes the quality of life and economic prosperity of the MAB by providing a transportation system consistent with the regional goals.

More information

SH 35 Public Meeting

SH 35 Public Meeting SH 35 Public Meeting Major Corridor Feasibility Study Environmental Impact Statement March 27 and 28, 2007 Good evening and welcome to the State Highway 35 Public Meeting. This meeting is being conducted

More information

SRF 101 SRF Cross Cutters: Understanding the Environmental

SRF 101 SRF Cross Cutters: Understanding the Environmental SRF 101 SRF Cross Cutters: Understanding the Environmental and Cultural Reviews EPA s Perspective CIFA Conference Workshop Seattle, Washington Monday, November 2, 2009 Philip C. Metzger Attorney, US EPA

More information

PRACTITIONER S HANDBOOK

PRACTITIONER S HANDBOOK AASHTO PRACTITIONER S HANDBOOK 03 August 2016 MANAGING THE NEPA PROCESS FOR TOLL LANES AND TOLL ROADS This Handbook provides recommendations for conducting National Environmental Policy Act (NEPA) studies

More information

TRANSPORTATION IMPACT ANALYSIS GUIDELINES

TRANSPORTATION IMPACT ANALYSIS GUIDELINES TRANSPORTATION IMPACT ANALYSIS GUIDELINES SANTA CLARA COUNTY TRANSPORTATION AUTHORITY CONGESTION MANAGEMENT PROGRAM ADOPTED MARCH 2009 TABLE OF CONTENTS PART I - STATUTE AND AUTHORITY...1 CHAPTER 1. CMP

More information

How to Prepare Your Categorical Exclusion (CATEX) Information and Prepare a Brief Environmental Assessment

How to Prepare Your Categorical Exclusion (CATEX) Information and Prepare a Brief Environmental Assessment How to Prepare Your Categorical Exclusion (CATEX) Information and Prepare a Brief Environmental Assessment Presented to: By: Peter F. Ciesla, Environmental Protection Specialist Date: CATEX Presentation

More information

Water Quality Analyses for NEPA Documents: Selecting Appropriate Methodologies. Prepared for: Prepared by: July 2008

Water Quality Analyses for NEPA Documents: Selecting Appropriate Methodologies. Prepared for: Prepared by: July 2008 Water Quality Analyses for NEPA Documents: Selecting Appropriate Methodologies Prepared for: American Association of State Highway and Transportation Officials (AASHTO) Standing Committee on the Environment

More information

Durham-Orange Light Rail Transit Project

Durham-Orange Light Rail Transit Project Durham-Orange Light Rail Transit Project Scoping Information Booklet WHAT S INSIDE What is Scoping? p. 3 How was the LPA determined? p. 3 Project development process p. 4 Project Purpose & Need p. 5 Alternatives

More information

MDOT SHA s NEPA/MEPA, Agency and Public Involvement Processes. Presentation to BRTB s Technical Committee August 1, 2017

MDOT SHA s NEPA/MEPA, Agency and Public Involvement Processes. Presentation to BRTB s Technical Committee August 1, 2017 MDOT SHA s NEPA/MEPA, Agency and Public Involvement Processes Presentation to BRTB s Technical Committee August 1, 2017 Agenda Introductions MDOT SHA Overview and NEPA Evaluation Process Section 4(f) TERP

More information

Environmental Review Standards for OHTF Funded Projects

Environmental Review Standards for OHTF Funded Projects Environmental Review Standards for OHTF Funded Projects Updated May 1, 2017 ENVIRONMENTAL REVIEW STANDARDS FOR OHTF FUNDED PROJECTS Contents Environmental Review Standards... 1 OHTF Funded Projects...

More information

Sustainable Transportation

Sustainable Transportation Sustainable Transportation Stephanie Hickman 5 April 2011 What I ll talk about Definitions Principles Programs and Initiatives References Sustainability Providing an acceptable quality of life for today

More information

TEMPORARILY SUSPENDED

TEMPORARILY SUSPENDED DESIGN BULLETIN #83/2014 0. (REVISED May 26, 2014) Project Identification Sign for Capital and Rehabilitation Construction Projects May 26, 2014 Amendment to Design Bulletin #83/2014 This amendment is

More information

CHAPTER 12 THE NATIONAL ENVIRONMENTAL POLICY ACT (NEPA) SECTION 1: INTRODUCTION PURPOSE APPLICABILITY

CHAPTER 12 THE NATIONAL ENVIRONMENTAL POLICY ACT (NEPA) SECTION 1: INTRODUCTION PURPOSE APPLICABILITY CHAPTER 12 THE NATIONAL ENVIRONMENTAL POLICY ACT (NEPA) PARAGRAPH PAGE SECTION 1: INTRODUCTION PURPOSE... 12100 12-2 APPLICABILITY... 12101 12-2 BACKGROUND... 12102 12-2 FEDERAL STATUTES... 12103 12-2

More information

Determining Whether a Proposal is Subject to the National Environmental Policy Act (NEPA) Section 102 Updated March

Determining Whether a Proposal is Subject to the National Environmental Policy Act (NEPA) Section 102 Updated March Determining Whether a Proposal is Subject to the National Environmental Policy Act (NEPA) Section 102 Updated March 2005 1 This paper presents some key thresholds to consider when determining whether a

More information

APPROVAL TO SUBMIT COMMENTS ON I-45 AND MORE DRAFT ENVIRONMENTAL IMPACT STATEMENT

APPROVAL TO SUBMIT COMMENTS ON I-45 AND MORE DRAFT ENVIRONMENTAL IMPACT STATEMENT TAC Agenda Item 09 Mailout 7/12/17 APPROVAL TO SUBMIT COMMENTS ON I-45 AND MORE DRAFT ENVIRONMENTAL IMPACT STATEMENT Background The Texas Department of Transportation, in cooperation with the Federal Highway

More information

LOCATION AND DESIGN DIVISION

LOCATION AND DESIGN DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Design Exceptions / Waivers SPECIFIC SUBJECT: Design Exception Request Form

More information

Coulter Transportation Consulting, LLC 1524 Paula Avenue Wheaton, IL Ph:

Coulter Transportation Consulting, LLC 1524 Paula Avenue Wheaton, IL Ph: MEMO To: Tri-Cities Impact Fee Review Group From: Brent Coulter, PE, PTOE Date: November 8, 2006 Subject: General Review of the Preliminary Kane County CRIP Kane County requested in recent (late October

More information

Holyoke Station Feasibility Study and Site Analysis

Holyoke Station Feasibility Study and Site Analysis Holyoke Station Feasibility Study and Site Analysis APRIL 2011 TABLE OF CONTENTS List of Figures List of Tables v vii Executive Summary 1 Report Chapters 1 Introduction 15 Project Purpose and Background

More information

Thank You to our Sponsors. Instructors 9/25/2013 AEP CENTRAL CHAPTER EASTERN SLOPE CONFERENCE MAMMOTH LAKES, CA

Thank You to our Sponsors. Instructors 9/25/2013 AEP CENTRAL CHAPTER EASTERN SLOPE CONFERENCE MAMMOTH LAKES, CA AEP CENTRAL CHAPTER EASTERN SLOPE CONFERENCE MAMMOTH LAKES, CA NEPA Workshop Friday September 27, 2013 Instructors Sean Bechta Ascent Environmental Steve Nelson BLM Roger Turner Turner & Associates Thank

More information

COST-BENEFIT ANALYSIS. Categorical Exclusions for Oil and Gas Exploration and Development Activities. USDA Forest Service

COST-BENEFIT ANALYSIS. Categorical Exclusions for Oil and Gas Exploration and Development Activities. USDA Forest Service December 7, 2005 COST-BENEFIT ANALYSIS Categorical Exclusions for Oil and Gas Exploration and Development Activities USDA Forest Service COST-BENEFIT ANALYSIS Categorical Exclusions for Oil and Gas Exploration

More information

State Route 8 Bridge Replacement Project

State Route 8 Bridge Replacement Project OPEN HOUSE PUBLIC INVOLVEMENT MEETING Celebration Church 688 Dan Street, Akron, Ohio Tuesday, July 14, 2015 5:00 PM to 7:00 PM State Route 8 Bridge Replacement Project Existing Bridge Future Bridges: Steel

More information

Public Notice. Applicant: City of Dallas Project No.: SWF Date: April 18, Name: Chandler Peter Phone Number:

Public Notice. Applicant: City of Dallas Project No.: SWF Date: April 18, Name: Chandler Peter Phone Number: Public Notice Applicant: City of Dallas Project No.: SWF- 2014-00151 Date: April 18, 2014 The purpose of this public notice is to inform you of a proposal for work in which you might be interested. It

More information

PLAN CATEGORICAL EXCLUSION QUESTIONS AND ANSWERS

PLAN CATEGORICAL EXCLUSION QUESTIONS AND ANSWERS PLAN CATEGORICAL EXCLUSION QUESTIONS AND ANSWERS What is a Categorical Exclusion? Categorical exclusions are an essential part of NEPA that provide a categorical determination, based on agency experience,

More information

Geometric Design: Past, Present, and Future

Geometric Design: Past, Present, and Future A2A02: Committee on Geometric Design Chairman: Daniel B. Fambro Geometric Design: Past, Present, and Future DANIEL B. FAMBRO, Texas A&M University JOHN C. COLLINGS, Delcan Corporation ROBERT DELLA VEDOVA,

More information

Standard Performance Attributes for Transportation Projects

Standard Performance Attributes for Transportation Projects Standard s for Transportation Projects Mainline Operations Local Operations Maintainability Construction Impacts Environmental Impacts Project Schedule An assessment of traffic operations and safety on

More information

Notice of Availability of the Final Environmental Impact Statement for the Monument

Notice of Availability of the Final Environmental Impact Statement for the Monument This document is scheduled to be published in the Federal Register on 06/24/2016 and available online at http://federalregister.gov/a/2016-15023, and on FDsys.gov 4310-DQ-P DEPARTMENT OF THE INTERIOR Bureau

More information

History of the Environmental Movement

History of the Environmental Movement History of the Environmental Movement Political cartoon, "A Big Job," Times Union (Jacksonville), January 14, 1905. Napoleon Bonaparte Broward, governor of Florida, prepares to drain the Everglades Major

More information

PUBLIC HEARING April 24, 2017

PUBLIC HEARING April 24, 2017 PUBLIC HEARING April 24, 2017 1 Agenda SDEIS Public Review Environmental Process Overview Project Highlights Comments to Stenographer 2 3 SDEIS Public Review Public Hearing Schedule Monday, April 24, 2017

More information

FOREST SERVICE HANDBOOK NATIONAL HEADQUARTERS (WO) WASHINGTON, DC

FOREST SERVICE HANDBOOK NATIONAL HEADQUARTERS (WO) WASHINGTON, DC Page 1 of 19 FOREST SERVICE HANDBOOK NATIONAL HEADQUARTERS (WO) WASHINGTON, DC FSH 7709.55 TRAVEL PLANNING HANDBOOK Amendment No.: Effective Date: Duration: This amendment is effective until superseded

More information

Conclusions & Lessons Learned

Conclusions & Lessons Learned What is a DDI Recommended Practices Traffic Operations Analysis Geometric Design FHWA Review Conclusions & Lessons Learned It s not about you, it s about the public Developed by Access Utah County

More information

Environmental Review and

Environmental Review and Environmental Review and the HOME Program Training Environmental Review Training Training offered under HUD s CPD Institute Local HUD officials present Who are we? ICF International trainers: Kelly Price

More information

5.D.1 HISTORIC, ARCHITECTURAL, ARCHEOLOGICAL, AND CULTURAL RESOURCES

5.D.1 HISTORIC, ARCHITECTURAL, ARCHEOLOGICAL, AND CULTURAL RESOURCES 5.D.1 HISTORIC, ARCHITECTURAL, ARCHEOLOGICAL, AND CULTURAL RESOURCES Section 106 of the National Historic Preservation Act (NHPA) of 1966, as amended (16 U.S.C. Section 470(f)) protects properties that

More information

TRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM

TRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM VIRGINIA DEPARTMENT OF TRANSPORTATION TRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Americans with Disabilities Act Requirements of Maintenance and Operational

More information

Wind Energy Development Specialist Report

Wind Energy Development Specialist Report United States Department of Agriculture Forest Service Southwestern Region Cibola National Forest and National Grasslands Wind Energy Development Specialist Report Kiowa, Rita Blanca, Black Kettle and

More information

Notice of Preparation For Link Union Station (Link US) Project. Joint Environmental Impact Statement and Environmental Impact Report

Notice of Preparation For Link Union Station (Link US) Project. Joint Environmental Impact Statement and Environmental Impact Report Notice of Preparation For Link Union Station (Link US) Project Joint Environmental Impact Statement and Environmental Impact Report Date: May 27, 2016 To: Subject: Project Title: From: All Interested Agencies,

More information

Cost Estimating Guideline February, 2017

Cost Estimating Guideline February, 2017 Cost Estimating Guideline February, 2017 Procedures are subject to change without notice. Check the Capital Project Delivery website to ensure this is the current version. Table of Contents Section 1 -

More information

Economic Stimulus and NEPA Compliance

Economic Stimulus and NEPA Compliance Economic Stimulus and NEPA Compliance Streamlining the Environmental Review Process Authors: Ron Bass, ICF Jones & Stokes Alan Summerville, ICF International Ken Bogdan, ICF Jones & Stokes Michael Smith,

More information

California Environmental Quality Act Part 1: CEQA Basics

California Environmental Quality Act Part 1: CEQA Basics California Environmental Quality Act Part 1: CEQA Basics California Preservation Foundation Webinar June 10, 2014 Presented by Chris McMorris Partner / Architectural Historian Overview of CEQA California

More information

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017 WELCOME IL 47 Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017 MEETING PURPOSE MEETING AGENDA 1. Welcome/Introduction 2. Review Previous Public Involvement 3. Process/Schedule

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions) FY 2018-2027 WIDE TRANSPORTATION IMPROVEMENT PROGRAM NY Susquehanna and Western Rail Line Bicycle/Pedestrian Path DBNUM: NS9803 / UPC: 058018 The 4.8 mile New York, Susquehanna, and Western Railway (NYS&W)

More information

Draft Environmental Assessment for Phoenix Sky Harbor International Airport Sky Train Stage 2

Draft Environmental Assessment for Phoenix Sky Harbor International Airport Sky Train Stage 2 Draft Environmental Assessment for Phoenix Sky Harbor International Airport Sky Train Stage 2 Prepared for: City of Phoenix Aviation Department and U.S. Department of Transportation Federal Aviation Administration

More information

Highway Traffic Noise: Analysis and Abatement Guidance

Highway Traffic Noise: Analysis and Abatement Guidance Highway Traffic Noise: Analysis and Abatement Guidance 1 TABLE OF CONTENTS TABLE OF CONTENTS... 2 THREE-PART APPROACH TO HIGHWAY TRAFFIC NOISE ABATEMENT... 6 Noise Compatible Planning... 6 Source Control...

More information

SAN LUIS VALLEY PUBLIC LANDS CENTER

SAN LUIS VALLEY PUBLIC LANDS CENTER Decision Notice And Finding of No Significant Impact Watershed and Fisheries Conservation Treatments SAN LUIS VALLEY PUBLIC LANDS CENTER USDA Forest Service Rocky Mountain Region Public Lands Center Rio

More information

United States Department of the Interior

United States Department of the Interior United States Department of the Interior I:'( RE P! Y RE ~ER TO BUREAU OF INDIAN AFFAIRS Pacific Regional Office 2800 Cottage Way Sacramento, California 95825 Honorable Leonard Masten Chairman. Hoopa Valley

More information

Selecting Projects for Accelerated Bridge Construction

Selecting Projects for Accelerated Bridge Construction Selecting Projects for Accelerated Bridge Construction In January of 2017, the Engineering Services and Operations Division Directors issued a memo instructing Districts to consider accelerated bridge

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions) Route 3, Route 46, Valley Road and Notch/Rifle Camp Road Interchange, Contract B DBNUM: 059B / UPC: 123020 From Notch/Rifle Camp Road to just east of the Valley Road Intersection, Route 46 will be widened

More information

3 INTERSTATES. The Carolina Crossroads Project Team Welcomes You

3 INTERSTATES. The Carolina Crossroads Project Team Welcomes You The Carolina Crossroads Project Team Welcomes You 3 INTERSTATES + 12 = KEY INTERCHANGES We re here to: Discuss the Carolina Crossroads I-20/26/126 Corridor Project Gather your input on study issues We

More information

I-91 Viaduct Public Information Briefing

I-91 Viaduct Public Information Briefing I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 10 December 18, 2017 Agenda Welcome Update on Construction Activities (Full Beneficial Use) Next:

More information

CEQA and its Role in Historic Preservation. Darcy Kremin, AICP Bay Area Environmental Practice Leader Michael Baker International, Oakland, CA

CEQA and its Role in Historic Preservation. Darcy Kremin, AICP Bay Area Environmental Practice Leader Michael Baker International, Oakland, CA CEQA and its Role in Historic Preservation Darcy Kremin, AICP Bay Area Environmental Practice Leader Michael Baker International, Oakland, CA General CEQA Requirements and Limitations Mitigation Measures

More information

TABLES OF CONTENTS APPENDIX C

TABLES OF CONTENTS APPENDIX C TABLES OF CONTENTS APPENDIX C SECTION C-1 DESIGN FEATURES On-Street Parking... C-1 Park-And-Ride Lots... C-6 Bus Turnout (Bus Stop) Design: Location, Type and Dimensions... C-15 Bus (Transit) Stops, Shelters

More information

FINAL SUPPLEMENTAL FINAL ENVIRONMENTAL IMPACT STATEMENT

FINAL SUPPLEMENTAL FINAL ENVIRONMENTAL IMPACT STATEMENT Date FINAL SUPPLEMENTAL FINAL ENVIRONMENTAL IMPACT STATEMENT For Trunk Highway 60 St. James to Windom Prepared by: Minnesota Department of Transportation and Federal Highway Administration Minnesota Division

More information

Regional Transportation Studies Regional Council

Regional Transportation Studies Regional Council Pima Association of Governments 1 E. Broadway, Tucson, Arizona Santa Rita Conference Room Regional Transportation Studies Regional Council September 28, 2017 I-11 Tier 1 Environmental Impact Statement

More information

CHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION

CHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION CHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION SECTION 2B 1 - GROUND SURVEYS Survey Authorization... 2B-1 Interstate... 2B-1 Principal / Minor Arterial... 2B-1 Urban...

More information

St. Helens Urban Renewal Plan. Prepared for: The St. Helens City Council

St. Helens Urban Renewal Plan. Prepared for: The St. Helens City Council St. Helens Urban Renewal Plan Prepared for: The St. Helens City Council September, 2008 ST. HELENS URBAN RENEWAL PLAN ACKNOWLEDGEMENTS The St. Helens City Council appointed a citizen advisory body to direct

More information

MPO Glossary & Acronyms

MPO Glossary & Acronyms MPO Glossary & Acronyms 2016 Jonesboro Metropolitan Planning Organization (MPO) Terms Continuing, Cooperative, and Comprehensive American Association of State Highway and Transportation Officials American

More information

Blanche Park Reservoir Decision Notice and Finding of No Significant Impact

Blanche Park Reservoir Decision Notice and Finding of No Significant Impact Blanche Park Reservoir Decision Notice and Finding of No Significant Impact U.S. Forest Service Grand Mesa, Uncompahgre, and Gunnison National Forests Delta County, Colorado INTRODUCTION The Grand Mesa

More information

National Housing Trust Fund Environmental Review and Funding Requirements

National Housing Trust Fund Environmental Review and Funding Requirements National Housing Trust Fund Environmental Review and Funding Requirements National Housing Trust Fund grants come with their own environmental review requirements that differ slightly from the Part 58

More information

CHAPTER 21: COMMITMENT OF RESOURCES

CHAPTER 21: COMMITMENT OF RESOURCES CHAPTER 21: COMMITMENT OF RESOURCES 21.1 INTRODUCTION In accordance with the National Environmental Policy Act (NEPA) and the Council on Environmental Quality s implementing procedures under Title 40,

More information

Scope of Work. Project Approach and Understanding. Task 1: Study Initiation and Administration

Scope of Work. Project Approach and Understanding. Task 1: Study Initiation and Administration Scope of Work Route 116/Hinesburg Growth Center Corridor Study Town of Hinesburg and CCRPC Project Approach and Understanding Route 116 through Hinesburg had seen substantial changes in the past 15 years,

More information

U.S. Department of Housing and Urban Development Community Planning and Development

U.S. Department of Housing and Urban Development Community Planning and Development U.S. Department of Housing and Urban Development Community Planning and Development Special Attention of: Notice: CPD-16-02 Regional Directors Field Office Directors Issued: February 8, 2016 CPD Division

More information

TRANSPORTATION TRANSPORTATION 9-1

TRANSPORTATION TRANSPORTATION 9-1 TRANSPORTATION Community Vision 2028 Because we place such high value on our natural surroundings, we responsibly plan for, manage, and mitigate the impacts of growth on those surroundings. Kezziah Watkins

More information

Performance Based Practical Design. An FHWA Perspective

Performance Based Practical Design. An FHWA Perspective Performance Based Practical Design An FHWA Perspective Early Adopters Research on PBPD and Background Materials http://www.fhwa.dot.gov/design/pbpd/ FAST Act Changes that Encourage PBPD On the NHS, design

More information

Executive Summary October 2017

Executive Summary October 2017 Executive Summary The King of Prussia Rail Draft Environmental Impact Statement/Draft Section 4(f) Evaluation (DEIS) describes and summarizes the transportation and environmental benefits and impacts of

More information

U.S. DEPARTMENT OF TRANSPORTATION Federal Highway Administration. RECORD OF DECISION March 2013

U.S. DEPARTMENT OF TRANSPORTATION Federal Highway Administration. RECORD OF DECISION March 2013 U.S. DEPARTMENT OF TRANSPORTATION Federal Highway Administration RECORD OF DECISION March 2013 Grand Parkway (State Highway 99) Segment C From United States Highway 59 (US 59) To State Highway 288 (SH

More information

NEPA and CEQA Documentation

NEPA and CEQA Documentation NEPA and CEQA Documentation National Environmental Policy Act (NEPA) Review and Compliance California Environmental Quality Act (CEQA) Review and Compliance Environmental Justice Bilingual Outreach Visual

More information

3-13 Other Required Findings and Regulatory Compliance

3-13 Other Required Findings and Regulatory Compliance Affected Environment and Environmental Consequences 3-13 Other Required Findings and Regulatory Compliance 3-13.1 Short-term Uses and Long-term Productivity NEPA requires consideration of the relationship

More information

DECISION MEMO. West Fork Blacktail Deer Creek Hardened Crossing

DECISION MEMO. West Fork Blacktail Deer Creek Hardened Crossing Page 1 of 6 Background DECISION MEMO USDA Forest Service Madison Ranger District Madison County T12S, R4W, Section 30 The project is in the Gravelly Landscape, Snowcrest Recommended Wilderness Management

More information

Alberta Transportation Gas Tax Fund and Public Transit Fund Outcomes Report December 2009

Alberta Transportation Gas Tax Fund and Public Transit Fund Outcomes Report December 2009 Alberta Transportation Gas Tax Fund and Public Transit Fund Outcomes Report December 2009 FINAL 1 Table of Contents Slide Number Executive Summary 3 Understanding the Outcomes Report 5 Measuring results

More information

TRANSPORTATION IMPACT STUDIES

TRANSPORTATION IMPACT STUDIES January 28, 2009 POLICIES AND PROCEDURES FOR TRANSPORTATION IMPACT STUDIES Related to Highway Occupancy Permits Pennsylvania Department of Transportation Bureau of Highway Safety and Traffic Engineering

More information