From Wasteland to Green Parkland The West Melbourne Gasworks
|
|
- Felicia Bond
- 6 years ago
- Views:
Transcription
1 MGP 2006 International Conference Reading UK 2-4 April 2006 From Wasteland to Green Parkland The West Melbourne Gasworks Ken Mival - Senior Principal - URS Australia (Presenter) Warren Pump Senior Principal URS Australia Glenn Dixon Projects Coordinator - VicUrban Melbourne Docklands The Vision 1
2 Gas production started 1st Jan
3 1920s Significant expansion and reconfiguration in 1920s 3
4 West Melbourne Gasworks Site in 2000 Regulatory Progress EPA - Clean up Notice Issued Audit Starts & Risk Based Criteria Established Clean-up Contract Let by Docklands Statements of Environmental Audit Issued Clean-up Notice Lifted - GQRUZ Declared 2002 to Groundwater Monitoring Continues 4
5 Development of Risk Based Criteria Tier 1 Soil Criteria - Gas Industry Association & NEPM HRA for Residential; Open Space; and Roads Ecological Risks - Back Analysis from Yarra River Attenuation in Groundwater - Bioscreen Estimated Max Allowable Soil Source Concentrations Moderated by HRA; Odour; and Union Concerns Fate & Transport Modeling and HRA for NAPLs Acceptance Criteria for Clean-up Contract Units mg/kg 5
6 Clean-up Process : Methods Considered Cap and Contain with: Bentonite Slurry Walls» Limitations: Obstructions Long term integrity NAPL sources remain on site In-situ Deep Soil Mixing Barriers» Limitations: as above Clean-up Process : Methods Cont. Excavation, Separation of Inert Solids, then Potential Treatment of Fines by: Low Temperature Thermal Desorption [cost & time] Bioremediation [time and effectiveness] Incineration for Energy Recovery [trial proposed] Chemical Treatment [many attempts] Stabilisation and Landfill [last resort & low cost] 6
7 Clean-up Process First Contract Excavated & Treated about 300,000m to 8 metres depth Power-screen separates coarse material; Concrete and Brick crushed & re-used Fines treated to reduce/stabilize contaminants About 15% processed material returned to excavation Clean-up Process contd. Remove tarry liquids and shallow groundwater Separation in Interceptors Hydrocyclones to remove silt and some NAPLs Backfill Soils from large CBD excavations Re-used soil from other Docklands sites 7
8 The Theory The Reality large areas under management simultaneously 8
9 Clean-up Process contd Contractor Proposed Treatment Options: Energy recovery for tars and oily wastes [unavailable due to constraints at power station] Containment of source areas by capping & deep cut-off» [Obstructions uneconomic - did not proceed] Permanganate treatment of PAH soils [Attempted but unsuccessful] Fenton s Reagent (Peroxide) to treat PAHs [Also failed] Clean-up Process contd Lime Treatment of PAH in Soils Reduces by about 30%» [partly successful some re-use on site] Excavation and Dump Approx 350,000 tonnes to landfill 150kL of liquid tarry wastes removed off site 9
10 Exothermic Reactions up to 100 o C and up to 30% Lime in some stockpiles! 10
11 Pug Mill for Fenton s Reagent Trial Clean-up Process contd GRS Remediation Excavation and Treatment within Tent Reterra Machine to Crush and Mix Soils Enhanced Bioremediation Odour management Tent; Daily cover; Deodorisers 11
12 Clean-up Process contd Results Partial Success with Naphthalene and TPH BaP largely unchanged Attributed to project timing in winter Approx 50,000 tonnes of hydrocarbon contaminated wastes disposed to landfill GRS under wraps to control odour 12
13 Excavations up to 9.5m deep Addition of materials to control odour when outside the tented area 13
14 Worst Case Scenario - Post Clean-up Modeled Potential Extent of Vapour Risk from NAPLs in Worst Case Scenario Benzene 14
15 Groundwater Monitoring 2002 to 2005 TRHs Area A Fill - TRH (C10-C36) (140m g/l trigger) mg/l TRH C May-02 Aug-02 Nov-02 Feb-03 May-03 Aug-03 Date Nov-03 Feb-04 May-04 Aug-04 MW27A MW28A MW29A MW 18A Benzene Area A Fill - Benzene (0.5m g/l trigger) mg/l Benzene May-02 Aug-02 Nov-02 Feb-03 May-03 Aug-03 Nov-03 Date Feb-04 May-04 Aug-04 MW27A MW28A MW29A MW18A 15
16 Total PAH Area A Fill - Total PAH (1mg/L trigger) mg/l PAH May-02 Aug-02 Nov-02 Feb-03 May-03 Aug-03 Date Nov-03 Feb-04 May-04 Aug-04 MW27A MW28A MW29A MW 18A Phenols Area A Fill - Phenols (5m g/l trigger) 2.5 MW27A mg/l Phenol May-02 Aug-02 Nov-02 Feb-03 May-03 Aug-03 Date Nov-03 Feb-04 May-04 Aug-04 MW28A MW29A MW18A 16
17 Metals - Manganese Area A Fill - Manganese (10m g/l trigger) MW27A mg/l Mn May-02 Aug-02 Nov-02 Feb-03 May-03 Aug-03 Date Nov-03 Feb-04 May-04 Aug-04 MW28A MW29A MW18A Metals - Nickel Area A Fill - Nickel (2mg/L trigger) mg/l Ni MW27A MW28A MW29A* 0 May-02 Aug-02 Nov-02 Feb-03 May-03 Aug-03 Date Nov-03 Feb-04 May-04 Aug-04 17
18 Cyanide - Area A Area A Fill - Cyanide 20 MW27A MW28A 15 MW29A mg/l CN May-02 Aug-02 Nov-02 Feb-03 May-03 Aug-03 date Nov-03 Feb-04 May-04 Aug-04 MW19A trigger ph MW18A Cyanide Area B (Source Zones) Area B Fill - Cyanide MW24A* 60 MW23A 50 MW13A mg/l CN MW14A MW15A MW21A 10 0 Aug-01 Dec-01 Apr-02 Aug-02 Dec-02 Apr-03 date Aug-03 Dec-03 Apr-04 Aug-04 MW26A ph trigger * Indicates x 10 Employee Presentation p 36 18
19 Conclusions The Risk Management approach allowed development whilst contamination remains Major sources of groundwater pollution have been removed to the extent practicable Metals and Hydrocarbons in groundwater have reduced or remain at acceptable concentrations Cyanide mobilised by high ph in groundwater is short term Assumptions in Risk Assessments and Modeling were appropriate Contingency groundwater management plans are not required to be implemented Wetlands Recycle Stormwater For Irrigating Parkland 19
20 Award Winning Park on Area B 20
21 Innovative large mobile sculpture in children s play area A walk from south to north through the park 21
22 22
23 23
24 Acknowledgements Mr John Tabart Retiring CEO - VicUrban Mr Glenn Dixon Projects Coordinator VicUrban and Co-Author Mr Warren Pump URS Site Superintendent and Co-Author Mr Colin White GHD - Project Manager West Melbourne Gasworks Clean-up 24
Remediation of the Former Gasworks, High Wycombe, UK
Remediation of the Former Gasworks, High Wycombe, UK Apr-4-06 MGP Symposium, Reading UK, April 2006 Presented By Stuart Arch Apr-4-06 4/4/06 WPREpresentation1.ppt 1 Site Setting Contents of Presentation
More informationDo Australian Clean Up Projects Currently Accord with the Concept of Sustainable Remediation?
Do Australian Clean Up Projects Currently Accord with the Concept of Sustainable Remediation? Peter Nadebaum Australasian Land and Groundwater Association SuRF Australia, CRC CARE, GHD Pty Ltd Clean Up
More informationTighes Hill Remediation Project Update
3 September 2015 Tighes Hill Remediation Project Update This presentation includes forward-looking statements. Actual future conditions (including economic conditions, energy demand, and energy supply)
More informationETHICALCHEM BACKGROUND
A division of Ethical Solutions LLC Successfully Integrating Surfactants Into Chemox Technologies Dan Socci, CEO, EthicalChem Green Chemical Solutions for Environmental Remediation ETHICALCHEM BACKGROUND
More informationUsing Mass Balance to Assist in Determining Remedial Options. Stephen Thomson URS New Zealand Limited
Using Mass Balance to Assist in Determining Remedial Options Stephen Thomson URS New Zealand Limited Presentation Outline Introduction. Example Site. Mass Balance. Calculations. Outcomes. Introduction
More informationSydney Olympic Park Sustainability Planning and Policy. Pakinee Chaikaew ID No
Sydney Olympic Park Sustainability Planning and Policy Pakinee Chaikaew ID No. 4837979 Contents Introduction History of Sydndy Olympic Park Contamination of the site Homebush Bay remediation Risk Assessment
More informationWASTE ACCEPTANCE CRITERIA AND DEVELOPMENT OF SOIL TRIGGER VALUES FOR EPA-LICENSED SOIL RECOVERY FACILITIES
WASTE ACCEPTANCE CRITERIA AND DEVELOPMENT OF SOIL TRIGGER VALUES FOR EPA-LICENSED SOIL RECOVERY FACILITIES 1. Introduction This guidance document applies to soil recovery facilities which exceed the operational
More informationManaging a MGP Site Containing 121,000 Tons of Soils Containing Highly Impacted and Multiple Contaminates Of Concern (COC) Clinton, Iowa
Managing a MGP Site Containing 121,000 Tons of Soils Containing Highly Impacted and Multiple Contaminates Of Concern (COC) Clinton, Iowa Dean Hargens, Alliant Energy Frank Kellogg, DCI Environmental. Inc.
More informationRemScan. Real-Time Measurement of TPH in Soil
RemScan Real-Time Measurement of TPH in Soil Presentation Outline Real-Time Data What is RemScan? Application Benefits Case Studies Demand for Real-Time Data More data, increased confidence Real-time,
More informationCLOSURE AND POST-CLOSURE OF LANDFILLS IN MALAYSIA CASE STUDIES
CLOSURE AND POST-CLOSURE OF LANDFILLS IN MALAYSIA CASE STUDIES Fauziah S.H., Noorazamimah Aiza A. and Agamuthu, P. Institute of Biological Sciences, Faculty of Science, University of Malaya 50603 Kuala
More informationKirkstallForge -Paving the Way for a new urban regeneration project in Leeds
KirkstallForge -Paving the Way for a new urban regeneration project in Leeds 0 Project Team Commercial Estates Group Ltd (CEG) - Client WYG - Environmental and Engineering Consultant Rebecca Reynolds Geotechnical
More informationMill Street Corridor Assessment/Cleanup Overview
Mill Street Corridor Assessment/Cleanup Overview Former S. Bent Mill Site Site History Overview Circa 1867 to 1992 - S. Bent Mill Company (furniture manufacturing) Circa early 1900s - expansion of the
More informationRecycling Christchurch. Gareth James General Manager Transpacific Waste Management South Island 5 October 2011
Recycling Christchurch Gareth James General Manager Transpacific Waste Management South Island 5 October 2011 The scene 22 February earthquake destroyed most of the CBD and much of Christchurch eastern
More informationRemediation, treatment and recovery of waste generated by up- and downstream oil industries Wouter De Weirdt
Remediation, treatment and recovery of waste generated by up- and downstream oil industries Wouter De Weirdt 1 General Introduction 2 HISTORY 1938 - Jan De Nul - contractor of civil works 1951 - First
More information2013 IPEC Conference San Antonio
2013 IPEC Conference San Antonio CLIQUEZ ET MODIFIEZ LE TITRE IN-SITU THERMAL REMEDIATION BENEATH A HISTORIC HOME AUTHORS: GRANT GECKELER, WALTER MULICA (GLOBAL TECHNOLOGIES), HATEM SAADAOUI, PHILIPPE
More informationContent of the presentation
Content of the presentation Status of and policy on contaminated sites in Finland Anna-Maija Pajukallio 20.9.2006 Nordrocs, Malmö Contaminated sites in Finland Inventories Authorities Remediations Some
More information7.0 EVALUATION OF REMEDIAL ALTERNATIVES
7.0 EVALUATION OF REMEDIAL ALTERNATIVES This section provides a description of the developed remedial alternatives based on viable remedial technologies and process options, as identified in Section 4.0,
More informationWaste Management, a Role for Surveyors - Linking the Environment and Planning
Waste Management, a Role for Surveyors - Linking the Environment and Planning John R PARKER, Australia Key words: Waste management, environment, planning, extractive industry, recycling, landfill SUMMARY
More informationLarge scale Bioremediation of hydrocarbon contaminated sites in desert environment
Large scale Bioremediation of hydrocarbon contaminated sites in desert environment 23 d International Petroleum & Environmental Conference New Orleans, LA 8-10 th Nov, 2016 Krishna Vangala Senior Environment
More informationRegulations to deal with the reuse of excvated (polluted) soil in Germany
Regulations to deal with the reuse of excvated (polluted) soil in Germany Andreas Bieber Federal Ministry for the Environment Ad Hoc Int. WG on Contaminated Land, Paris, Sept. 30, 05 Soil: Definition Material
More informationASCE Geotechnical Division Specialty Conference Grouting, Soil Improvement and Geosynthetics New Orleans, Louisiana February 25-28, 1992
ASCE Geotechnical Division Specialty Conference Grouting, Soil Improvement and Geosynthetics New Orleans, Louisiana February 25-28, 1992 IN-SITU STABILIZATION AND FIXATION OF CONTAMINATED SOILS BY SOIL
More informationThermal Remediation Services, Inc.
Thermal Remediation Services, Inc. Electrical Resistance Heating for In-Situ Remediation of Soil & Groundwater December 10, 2002 Greg Beyke (770) 794-1168 gbeyke@thermalrs.com www.thermalrs.com 1 1 2 2
More informationContaminated Media Management Plan. DEQ UST Site # Del Oeste Veterinary Clinic Prairie Road Eugene, Oregon
Contaminated Media Management Plan DEQ UST Site #20-97-7034 Del Oeste Veterinary Clinic 90238 Prairie Road Eugene, Oregon March 2014 This page left intentionally blank. 2 Overview This Contaminated Media
More informationBotany Groundwater Cleanup Project Progress Update
Botany Groundwater Cleanup Project Progress Update B Dewhurst & L Archer (Orica) 18/03/2014 Progress Since Last CLC Meeting Groundwater containment was achieved at all three containment lines (SCA, PCA
More informationGreen Remediation at. LUST Technical Workshop Stephen G. Reuter New Mexico Environment Department
Green Remediation at Tank Sites LUST Technical Workshop Stephen G. Reuter New Mexico Environment Department stephen.reuter@state.nm.us 505-222-9577 1 Green Remediation of LUST Sites Best management practices
More informationKurnell Refinery Conversion Project
Kurnell Refinery Conversion Project Contamination Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site
More informationBeyond Dig and Haul: A survey of Remedial Technologies. NYS Department of Environmental Conservation
Beyond Dig and Haul: A survey of Remedial Technologies Agenda (20 Minutes) Excavations Bioremediation ISCO SVE Thermal treatment Remedy Selection Do not select the remedy before you investigate the site
More informationTreatment System Locations. Treatment System Sampling Activities and Analytical Results. June 15, 2011
June 15, 2011 Mr. David Anderson Oregon Department of Environmental Quality Eastern Region 475 NE Bellevue Drive, Suite 110 Bend, Oregon 97701-7415 Re: Status Report: May 2011 Keno Area Wide Groundwater
More informationManufactured Gas Plant Site Management - Program 50
Manufactured Gas Plant Site Management - Program 50 Program Description Program Overview Most former manufactured gas plants (MGPs) ceased operation by the 1960s, but by-products and wastes, often disposed
More informationEnvironmental Management Division. David Amidei NASA HQ
NASA s Remediation Challenges David Amidei NASA HQ Environmental Management Division i i NASA Facilities Environmental Management Division Previous Practices Environmental Management Division and more
More informationSustainable Landfill Design by Monitoring and Managing Cap Infiltration
Sustainable Landfill Design by Monitoring and Managing Cap Infiltration CONTACT Stephen Hancock,Senior Principal/Director URS Australia Pty Ltd Brian Fox-Lane, National Manager, Boral Landfill & Waste
More informationThermal Remediation Services, Inc.
Thermal Remediation Services, Inc. Electrical Resistance Heating for Rapid Remediation of DNAPL April 2003 David Fleming 425-396-4266 dfleming@thermalrs.com www.thermalrs.com What is Electrical Resistance
More informationNovember Contaminated Land Assessment in NSW
November 2015 Contaminated Land Assessment in NSW Contaminated Site Assessment and Management Process Prompts for assessing site contamination: Acquisition or divestment of property Site rezoning or DA
More informationPlume Stability Analysis
Groundwater Contaminant Plume Stability Analysis Joe A. Ricker, P.E. A member of the Earth Consulting Group, Inc. family of companies Ricker Plume Stability Analysis Background Ricker Plume Stability Analysis
More informationISO Monitoring and Measurement Nonconformance and Corrective and Preventative Action
ISO 14001 4.5.1 Monitoring and Measurement 4.5.2 Nonconformance and Corrective and Preventative Action 4.5.1 Monitoring and Measurement The organization shall establish and maintain documented procedures
More informationSelf-Sustaining Treatment for Active Remediation (STAR): Overview and Applications of the Technology
Self-Sustaining Treatment for Active Remediation (STAR): Overview and Applications of the Technology Shanna Thompson, P.E. Gavin Grant, Ph.D., P.Eng. In Partnership with: siremlab.com/star Overview The
More informationESS EcoCell Ecological Tank Systems
Modular eo-void Systems Total Water Management ESS EcoCell Ecological Tank Systems ENVIRONMENTAL SUSTAINABLE SOLUTIONS LTD Environmental Sustainable Solutions Welcome to Environmental Sustainable Solutions;
More informationSkim Pit Closure Report for the Hickert No. 1A Lease Washington County, Colorado COGCC Remediation # 9065
Skim Pit Closure Report for the Hickert No. 1A Lease Washington County, Colorado COGCC Remediation # 9065 Prepared for: Mr. Terry Pape HRM Resources, LLC 410 17 th Street, Suite 1100 Denver, CO 80202 Nicholson
More informationAdvancing the Science of In Situ Groundwater Remediation Petroleum Hydrocarbon Remediation Technologies
Advancing the Science of In Situ Groundwater Remediation Petroleum Hydrocarbon Remediation Technologies RemBind Vadose Zone Treatment Tersus is the exclusive North American distributor for RemBind (US
More informationThis report was prepared by Stanley Abraham, Bioremediation of Hydrocarbon-Contaminated Soil
This report was prepared by Stanley Abraham, Vice President, Industrial Systems Corp. LLC, PO Box 61, Postal Code 134, Shattia, Muscat, Sultanate of Oman, Oman. Bioremediation of Hydrocarbon-Contaminated
More informationInventaire Report Information Report ID: Report Year: 2008 Programs Included:npri. Facility Information.
https://blrscr3.egs-seg.gc.ca/ec/owners/edrs/protected/6a43731b4840478a3b51594c233b... Page 1 of 19 Inventaire 2008 Report Information Report ID: 20090428-37323934383132 Report Year: 2008 Programs Included:npri
More informationTHERMAL REMEDIATION OF A CLOSED GASOLINE SERVICE STATION PRESENTATION AND DISCUSSION LED BY: GLEN VALLANCE PROJECT MANAGER, CGRS
THERMAL REMEDIATION OF A CLOSED GASOLINE SERVICE STATION IPEC 13 November 2013 CLIQUEZ ET MODIFIEZ LE TITRE PRESENTATION AND DISCUSSION LED BY: GLEN VALLANCE PROJECT MANAGER, CGRS 1. IN-SITU THERMAL REMEDIATION
More informationSECTION 7: CLIMATE AND AIR QUALITY
SECTION 7: CLIMATE AND AIR QUALITY 7.1 INTRODUCTION This study considers the potential impacts of emissions to atmosphere on air quality including, airborne pollutants and dust emissions during operation
More informationApplications of Waste Tire Products in Civil Engineering
Applications of Waste Tire Products in Civil Engineering Introduction to Civil Engineering Design CSU, Chico Introduction Background Benefits of Using TDA Civil Engineering Applications Lightweight Fill
More informationCity of Olean Water Filtration Plant
1332 River Street Olean, NY 14760 Phone: (716) 376-5699/ 376-5627 Fax: (716) 376-5704 E-Mail: dwalker@cityofolean.org Dale Walker, Senior Operator and Lab Director City of Olean Water Filtration Plant
More informationDoes Water Resources Management in the Snake River Basin Matter for the Lower Columbia River? Or Is the Snake River Part of Another Watershed?
Does Water Resources Management in the Snake River Basin Matter for the Lower Columbia River? Or Is the Snake River Part of Another Watershed? John C. Tracy, Director Idaho Water Resources Research Institute
More informationMoving Towards Sustainable Remediation: Overview and Concepts
Moving Towards Sustainable Remediation: Overview and Concepts Daniel M. Powell, Chief Technology Integration and Information Branch US EPA, Office of Superfund Remediation and Technology Innovation Washington,
More informationIn Situ, Low Temperature Thermal Remediation of LNAPL with Pesticides and Other Recalcitrant Compounds
In Situ, Low Temperature Thermal Remediation of LNAPL with Pesticides and Other Recalcitrant Compounds RemTech 2017, Banff Springs Hotel and Conference Centre October 11, 2017 Presented by - Jay Dablow,
More informationThe State of Contaminated Land in Wales
The State of Contaminated Land in Wales www.naturalresourceswales.gov.uk April 2016 Contents Executive Summary...3 1. Introduction...4 Aim of the report Who is the report for? What the report covers How
More informationCoke Manufacturing. Environmental Guidelines for. Multilateral Investment Guarantee Agency. Industry Description and Practices. Waste Characteristics
Multilateral Investment Guarantee Agency Environmental Guidelines for Coke Manufacturing Industry Description and Practices Coke and coke by-products (including coke oven gas) are produced by the pyrolysis
More informationCITY OF LONDON ENVIRONMENTAL & ENGINEERING SERVICES DEPARTMENT WASTEWATER TREATMENT OPERATIONS GREENWAY POLLUTION CONTROL CENTRE 2013 ANNUAL REPORT
CITY OF LONDON ENVIRONMENTAL & ENGINEERING SERVICES DEPARTMENT WASTEWATER TREATMENT OPERATIONS GREENWAY POLLUTION CONTROL CENTRE 2013 ANNUAL REPORT FEBRUARY 2014 SUMMARY This annual report is in response
More informationRemActiv Concentrate: Bioremediation Enhancer
RemActiv Product Overview RemActiv Concentrate: Bioremediation Enhancer Z100-03 08/15 RemScan RemActiv Contents Features and Benefits... 3 Specifications... 4 Case Study RemActiv Trials successful for
More informationA Clean, Green Remediation
A Clean, Green Remediation How Green Remediation can make hazardous waste cleanup more eco-friendly, from beginning to end and at the same time help the bottom line By Robert J. Young, PG Vice President,
More informationThe year 2005 was one of significant change for
In This Report Letter from the CEO About SUMCO Long-term EHS Goals EHS Policies EHS and Safety Environmental Stewardship / Natural Resource Use Environmental Performance Analysis The year 2005 was one
More informationMATERIALS MANAGEMENT PLAN (MMP)
MATERIALS MANAGEMENT PLAN (MMP) CONTENTS 1. INTRODUCTION...5 1.1 Background...5 1.2 Scope...5 1.3 Conclusions from the Environmental Impact Assessments...6 2. THE USE OF SITE-DERIVED MATERIALS...7 2.2
More informationWaste Synergies and Opportunities Daniels Health Incinerators. Paul Vujic Manager Industrial Waste
Waste Synergies and Opportunities Daniels Health Incinerators Paul Vujic Manager Industrial Waste Safety Share Site visit today at Wiblin Street Watch for uneven surfaces eg concrete footpaths Take time
More informationKilkenny County Council. Sludge Management Plan. for. County Kilkenny
Kilkenny County Council Sludge Management Plan for County Kilkenny February 2003 Draft Sludge Management Plan for County Kilkenny County Manager Director of Services Mr A Walsh (Acting) Mr T Gunning Prepared
More informationUrban Rainwater Harvesting Systems: Promises and Challenges
TheWaterChannel Webinar #5 Urban Rainwater Harvesting Systems: Promises and Challenges By Vishwanath S Zenrainman@gmail.com www.ircsa.org www.rainwaterclub.org Thanks for coming. The webinar will begin
More informationIn Situ Thermal NAPL Remediation at the Northeast Site Pinellas Environmental Restoration Project
ABSTRACT In Situ Thermal NAPL Remediation at the Northeast Site Pinellas Environmental Restoration Project R. Juhlin, M. Butherus S.M. Stoller Corporation 2597 B ¾ Road, Grand Junction, C0 81506 USA The
More informationHydrocarbon Management PROCEDURE
Hydrocarbon Management PROCEDURE Doc No: Approved: PRO-0380 Operations Manager Table of Contents 1. PURPOSE... 3 2. SCOPE... 3 3. REFERENCES... 3 3.1 LEGISLATION/STANDARDS... 3 4. DEFINITIONS... 3 5. HYDROCARBON
More informationPST Rulemaking: Draft Rule Changes
PST Rulemaking: Draft Rule Changes Lonnie Gilley Technical Specialist/Environmental Investigator TCEQ OCE, DFW Region Office 817-588-5841 lonnie.gilley@tceq.texas.gov 1 Texas UST Rulemaking Process Stakeholder
More informationSolar Power Realities
Solar Power Realities Supply-Demand Characteristics, Storage and Capital Costs by Peter Lang Abstract This paper provides a simple analysis of the capital cost of solar power and energy storage sufficient
More informationAmerican Association of State Highway and Transportation Officials (AASHTO) 444 North Capitol Street, N.W., Suite 249 Washington, D.C.
Compost Program Texas Department of Transportation How has this team performed exemplary service, which has furthered the transportation activities of the department and had a positive impact on transportation
More informationESG Roadshow. Pat Risner Group HSE Officer James Upton Head of ESG Policy and Engagement, Group Governance Elisa Morniroli Manager, Investor Relations
ESG Roadshow Pat Risner Group HSE Officer James Upton Head of ESG Policy and Engagement, Group Governance Elisa Morniroli Manager, Investor Relations Safety performance H1 FY2017 On 21 October 2016 a team
More informationEnvironmental Improvement Plan. Sohar Refinery
Environmental Improvement Plan Sohar Refinery Feb 2014 Page 1 of 18 Waste Water Treatment Plant Improvements Background The treatment of the waste water of the Refinery was malfunctioning for a long period.
More informationPermeOx. Plus. Enhanced Aerobic Biodegradation
PermeOx Plus Enhanced Aerobic Biodegradation Introduction Successful bioremediation of petroleum contamination through aerobic microbial respiration depends on a number of factors including the presence
More informationFlorida Fracking Summit November 2, 2016
Florida Fracking Summit November 2, 2016 Presentation on Potential Water Risks - Based on Real World Data By Scott Smith Chief Technology Officer & Investigator Oil Contaminated Flood Waters 2006 We Are
More informationPerformance review of a pipe jacking project in Hong Kong
Geotechnical Aspects of Underground Construction in Soft Ground Ng, Huang & Liu (eds) 2009 Taylor & Francis Group, London, ISBN 978-0-415-48475-6 Performance review of a pipe jacking project in Hong Kong
More informationENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN. Environment Protection Authority, ACT May 2009
ENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN Environment Protection Authority, ACT May 2009 ISBN-13: 978-0-642-60494-1 ISBN-10: 0-642-60494-0 Australian Capital Territory,
More informationIn-pit tailings disposal at Langer Heinrich TSFs in a unique hydrogeological setting
In-pit tailings disposal at Langer Heinrich TSFs in a unique hydrogeological setting Tailings and Mine Waste Management for the 21 st Century 2015 Page number 373 in proceedings Prepared by: Cameron Hore
More informationGENERAL PERMIT WMGR098 BENEFICIAL USE OF WASTE FOUNDRY SAND AND SAND SYSTEM DUSTS
A. Description: The approval herein granted is limited to the beneficial use of waste foundry system sand and sand system dusts (hereinafter referred to as waste foundry sand) generated by ferrous metal
More informationContaminated Land Politics in Switzerland - Tackling the "Sins of Yesterday" under the Principle of Appropriateness
International Seminar on In-Situ Remediation of Contaminated Sites 4./5.11.02 - Sao Paulo, Brazil Contaminated Land Politics in Switzerland - Tackling the "Sins of Yesterday" under the Principle of Appropriateness
More informationMineral Processing by Bioheapleaching at The Talvivaara Nickel Mine in Sotkamo, Finland. Jukka Pitkäjärvi General Manager Talvivaara Exploration Ltd
Mineral Processing by Bioheapleaching at The Talvivaara Nickel Mine in Sotkamo, Finland Jukka Pitkäjärvi General Manager Talvivaara Exploration Ltd DISCLAIMER The following information contains, or may
More informationIronton Russell Bridge Project
Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014
More informationRock Fill Layer Management and Maintenance Plan Former BNSF Site 13 Highway 99 Eugene, Oregon
Rock Fill Layer Management and Maintenance Plan 13 Highway 99 Prepared for: Half Moon LLC P.O. Box 25112 97402 PBS Project No. 51833.000 Rock Fill Layer Management and Maintenance Plan TABLE OF CONTENTS
More informationOn March 6, 2014, 17 shallow soil samples were collected along the proposed trail alignment according to
LAKE EWAUNA TRAIL LEVEL 2 FIELD SAMPLING ASSESSMENT the proposed alignment (Figure 1). The trail will also include the installation of a geothermal snow melt system, allowing for year round use of the
More informationMarc de Croisset FBR CAPITAL MARKETS & CO. Coal-to-Gas Switching: Distilling the Issue
Marc de Croisset. 646.885.5423. mdecroisset@fbr.com FBR CAPITAL MARKETS & CO. Coal-to-Gas Switching: Distilling the Issue September 20, 2012 Disclosures Important disclosures can be found at the end of
More informationWaste Business Monitor The only source of "real time" trend data analysing global waste plant developments
Waste Business Monitor The only source of "real time" trend data analysing global waste plant developments In this month's report The latest waste plant developments in August 2015 ALL DATA CURRENT AT
More informationWallasea Island Wild Coast Project Phase 1
Wallasea Island Wild Coast Project Phase 1 Simon Trickett Environmental Consultant Wallasea Island Location Wallasea Island History How big? The Wallasea Island Wild Coast Project Area of intertidal salt
More information/ 1 2 ANNUAL REPORT BALANCE RECRUITMENT E N V I R O N M E N T A L
BALANCE RECRUITMENT E N V I R O N M E N T A L ANNUAL REPORT 2 0 1 1 / 1 2 Balance Recruitment provides recruitment consultancy services for the placement of professionals in office environments, on both
More informationName That Source. Point and Nonpoint Sources
Name That Source Point and Nonpoint Sources Adapted from: Name That Source in Environmental Resource Guide: Nonpoint Source Pollution Prevention. Air & Waste Management Association, 1992. Grade Level:
More informationDRAFT ANALYSIS OF BROWNFIELDS CLEANUP ALTERNATIVES CITY OF MICHIGAN CITY, INDIANA S BROWNFIELDS CLEANUP PROJECT FOR THE FORMER ERINCRAFT FACILITY TH
DECEMBER 22, 2008 DRAFT ANALYSIS OF BROWNFIELDS CLEANUP ALTERNATIVES CITY OF MICHIGAN CITY, INDIANA S BROWNFIELDS CLEANUP PROJECT FOR THE FORMER ERINCRAFT FACILITY TH 742 EAST 8 STREET MICHIGAN CITY, INDIANA
More informationa subsidiary of EnGlobe Corp. ENVIRONMENTAL REMEDIATION CONTRACTING
a subsidiary of EnGlobe Corp. ENVIRONMENTAL REMEDIATION CONTRACTING a subsidiary of EnGlobe Corp. 02 a subsidiary of EnGlobe Corp. First Street, Manchester - Remediation of a 7.6 acre former inner city
More informationConstruction Waste Measurement Guide
Draft V6 Last updated: February 2013 Construction Waste Measurement Guide A guide to measuring and reporting waste from construction activities 1 Introduction This document provides guidance on how to
More informationMassachusetts Department of Environmental Protection Bureau of Waste Site Cleanup
A. THIS FORM IS BEING USED TO: (check one) 1. Log Date: 10/24/2017 Log Time: 11:18 AM PM 2. Assign a (RTN) to a Release or TOR Report. a. Reportable Release or TOR. b. Release that is Less Than the Reporting
More informationTelephone Lake project
Telephone Lake project Cenovus Energy Inc. is a Canadian oil company. We re committed to applying fresh, progressive thinking to safely and responsibly unlock energy resources the world needs. Our operations
More informationRECENT USES OF IN SITU STABILIZATION, IN SITU CHEMICAL OXIDATION, AND IN SITU CHEMICAL REDUCTION USING SOIL MIXING. RE3 Remediation, Renewal, Results
RECENT USES OF IN SITU STABILIZATION, IN SITU CHEMICAL OXIDATION, AND IN SITU CHEMICAL REDUCTION USING SOIL MIXING Presented by: Ken Andromalos & Daniel Ruffing RE3 Remediation, Renewal, Results Soil Mixing
More informationConnecticut Department of Energy and Environmental Protection and Environmental Professionals Organization of Connecticut, Inc.
Connecticut Department of Energy and Environmental Protection and Environmental Professionals Organization of Connecticut, Inc. 95% UCL Guidance Guidance workgroup formed out of the Remediation Roundtable
More informationDevelopment for further replacement of Fossil Fuel with Alternative Fuels and for use of Alternative Raw Materials
Waste Management Introduction The principal objective of sustainable resource and waste management is to use material and energy resources more efficiently, to reuse, recycle and recover material and reduce
More informationYou may use 1 sheet of notes for the final. Please turn in notes sheet with your exam.
HazW Final p. 1 FINAL EXAM FOR CVEN 4474 - HAZARDOUS WASTE TREATMENT MAY 8 11:30 AM - 2:30 PM TOTAL POINTS: 200 You may use 1 sheet of notes for the final. Please turn in notes sheet with your exam. Multiple
More informationBiological Reductive Dechlorination of Chlorinated Compounds. Barry Molnaa WSW Remediation Practice Manager ARCADIS
Biological Reductive Dechlorination of Chlorinated Compounds Barry Molnaa WSW Remediation Practice Manager ARCADIS 1 Presentation Outline What are we trying to do? How is it supposed to work? What are
More informationAUSTRIA where we stay, what we need in future MÜLLER-GRABHERR / BERGTHALER / ORTMANN
AUSTRIA where we stay, what we need in future MÜLLER-GRABHERR / BERGTHALER / ORTMANN COMMON FORUM, Vienna, 12.04.2017 2 at the heart of Europe holding a sharing on a wide spectrum of natural systems and
More information--- Surfactant Enhanced Aquifer Restoration at a Former Chemical Weapons Manufacturing Site
25/03/2015 Amélioration de la réhabilitation d un aquifère pollué par du chloroforme et du triclorofluorométhane (Freon-11) par usage de surfactant sur un ancien site de fabrication d armes chimiques ---
More informationThe Role of Biodegradable Waste Management in Europe. Dr. Stefanie Siebert, Quality Manager, European Compost Network ECN
The Role of Biodegradable Waste Management in Europe Dr. Stefanie Siebert, Quality Manager, European Compost Network ECN About ECN About the European Compost Network ECN Exchange of Experience Circulation
More informationCopyright 2007 Essex Contaminated Land Consortium All rights reserved. December 2007 v2
Copyright 2007 Essex Contaminated Land Consortium All rights reserved December 2007 v2 CONTENTS 1. Introduction 5 2. Site Characterisation & Risk Assessment 6 Phase 1 Desktop Study 6 Phase 2 Intrusive
More informationProject Photo Tour Updated July 15, Tom Blackman Project Lead. Gary Cambre Senior Communications Manager 1
Soil Remedial Actions Planned at Middle River Complex - 2015 Project Photo Tour Updated July 15, 2015 Tom Blackman Project Lead Gary Cambre Senior Communications Manager 1 This Project is composed of:
More informationRemediation of a Former MGP Site in Norwich New York: a Case Study
Proceedings of the Annual International Conference on Soils, Sediments, Water and Energy Volume 17 Article 9 2012 Remediation of a Former MGP Site in Norwich New York: a Case Study Scott A. Underhill AECOM
More informationNew mill grinds down costs and boosts efficiency at Savage River
1/5 Inside Grange Resources Savage River magnetite concentrator in north-western Tasmania. Upgraded mill to the right of Metso s Steve Searle & John Aran New mill grinds down costs and boosts efficiency
More informationSLURRY WALLS FOR SEEPAGE CUTOFF IN LEVEE APPLICATIONS RECENT EXPERIENCE AND CONSTRUCTION CHALLENGES IN THE NORTHERN CENTRAL VALLEY OF CALIFORNIA
SLURRY WALLS FOR SEEPAGE CUTOFF IN LEVEE APPLICATIONS RECENT EXPERIENCE AND CONSTRUCTION CHALLENGES IN THE NORTHERN CENTRAL VALLEY OF CALIFORNIA Deep Foundation Institute Slurry Wall Committee July 22,
More informationBiochar: One of the solutions for climate change, land restoration and food security
Biochar: One of the solutions for climate change, land restoration and food security Earth Systems June 2016 Authors: Gwendoline Raban Azain Raban (World Vision) Nigel Murphy Adrian Morphett John Sanderson
More information