IN THE MATTER of the Resource Management Act 1991 MERIDIAN ENERGY LIMITED. Appellant SOUTHLAND DISTRICT COUNCIL. Respondent NOTICE OF APPEAL

Size: px
Start display at page:

Download "IN THE MATTER of the Resource Management Act 1991 MERIDIAN ENERGY LIMITED. Appellant SOUTHLAND DISTRICT COUNCIL. Respondent NOTICE OF APPEAL"

Transcription

1 BEFORE THE ENVIRONMENT COURT AT CHRISTCHURCH ENV-2014-CHC- IN THE MATTER of the Resource Management Act 1991 AND IN THE MATTER BETWEEN of an appeal under Clause 14(1), First Schedule of the Act in relation to the Proposed Southland District Plan Decisions MERIDIAN ENERGY LIMITED Appellant AND SOUTHLAND DISTRICT COUNCIL Respondent NOTICE OF APPEAL ANDERSON LLOYD LAWYERS DUNEDIN Solicitor: S W Christensen / R J Brooking Level 10, Otago House Cnr Moray Place & Princes Street, Private Bag 1959, DUNEDIN 9054 DX YX Tel Fax

2 1 TO: The Registrar Environment Court Christchurch 1 Meridian Energy Limited ("Meridian") appeal parts of a decision of Southland District Council on the Proposed Southland District Plan. 2 Meridian made a submission and further submissions on that Plan. 3 Meridian is not a trade competitor for the purposes of section 308D of the Resource Management Act 1991 ("RMA"). 4 Meridian received notice of the decision on or about 13 October The decision was made by Southland District Council. General Reasons 6 Meridian s proposed amendments to the Plan will better achieve the purpose of both the Manapouri Te Anau Development Act 1963 ("MTADA") and the RMA than the provisions as amended by the Decision. The general reason for Meridian's appeal is to protect its assets in Southland District. These assets include the Manapouri Hydro Electric Power Scheme being nationally important infrastructure and the White Hill Wind Farm being regionally significant infrastructure. Meridian is also interested in the potential to further optimise these assets and consider options to develop other future electricity generation resources in the District. In particular it wishes to ensure that existing infrastructure is appropriately recognised. 7 The provisions as amended by the Decision present potential obstacles to the use and development of renewable energy and may be better balanced to assist with assessing the overall merits of such proposals. Greater clarity is required so that the consideration of complex issues and values that occur within the district and regional planning context, and for individual development projects, is assisted by clear policy guidance. 8 The particular decisions that Meridian appeals follow.

3 2 Manapouri Te Anau Development Act Meridian sought recognition and provision for MTADA's role in relation to the operation of the Manapouri Power Station. This included making Manapouri Power Station activities a permitted activity (submission numbers and 184.5). The decision rejected the submissions and this rejection is the subject of this appeal. 10 Meridian and Southland District Council have recently appeared in the High Court to seek a declaration on whether or not MTADA prevails over the RMA. A decision of the High Court has not yet been made. If the High Court declares that MTADA prevails, then an inconsistency with the provisions of the District Plan can be avoided by a clear statement in the District Plan that activities authorised by MTADA are not regulated by the District Plan. In its decision Southland District Council have retained the status quo and did not provide for MTADA. Reasons 11 MTADA gives Meridian full power and authority to construct and operate works in relation to the Manapouri Power Scheme. 1 Meridian sought recognition of this power in the: introductory section; Fiordland / Rakiura Zone; Rural Zone; and Energy, Minerals and Infrastructure section. 12 Activities regulated by MTADA should not be regulated by the District Plan in order to avoid inconsistency between MTADA and the District Plan an RMA instrument. Double regulation is both inefficient and inconsistent with MTADA. 13 If the High Court declaration is that MTADA prevails over the RMA then a statement to this effect should be included in the Plan. If the High Court declares that MTADA does not prevail then the Plan should continue to permit the operation of the Manapouri Power Station and enable future work. Meridian seeks the following relief 14 Appropriate recognition within the Plan confirming that activities authorised by MTADA are not regulated by the Plan. 1 Section 4(1)

4 3 15 Alternative relief is sought in the event of a High Court declaration that MTADA does not prevail over the RMA being that all activities associated with the Manapouri Power Scheme and authorised by MTADA are a permitted activity under the District Plan. 16 In addition to the above, the following relief is also sought: Any additional or alternative relief that achieves the same or similar outcome; Consequential or ancillary changes to the above. Section 2.3 Natural Features and Landscapes 17 Policy NFL.3 relates to adverse effects to landscapes not identified as "Visual Amenity Landscapes" or "Outstanding Natural Features and Landscapes". Meridian submitted that Policy NFL.3 be deleted. The decision amended Policy NFL.3. Reasons 18 The retention of Policy NFL.3 means that landscape effects will need to be assessed in areas that have low values and may create unrealistic expectations as to management. Policy NFL.3 will lead to uncertainty about when landscape issues are relevant and is unnecessary. The deletion of Policy NFL.3 will better achieve the sustainable management purpose of the RMA. Meridian seeks the following relief 19 The deletion of Policy NFL In addition to the above, the following relief is also sought: Any additional or alternative relief that achieves the same or similar outcome; Consequential or ancillary changes to the above. Section 2.4 Coastal Environment 21 Objective CE.1 relates to development in the coastal environment and lists 8 requirements for that development. The appeal relates to the

5 4 wording of the requirements at 1, 2 and 3 and a new requirement at 9. The wording of the requirements at 1, 2 and 3 are absolute and do not include a qualifier for the requirement to only apply to "inappropriate development". The list of requirements do not recognise the locational needs or technical constraints associated with infrastructure. 22 Policy CE.1 is to avoid or mitigate adverse effects on the coastal environment. The term "remedy" is not included in Policy CE.1. The qualifier of "inappropriate development" is also not included in Policy CE.1. Reasons 23 Objective CE.1 and Policy CE.1 should focus on development that is "inappropriate". To apply the restrictions in this objective and policy to all development is unnecessary and does not achieve the sustainable management purpose of the RMA. Development needs to be qualified and understood in the context of the effects that it has on the identified values associated with the resource under consideration. 24 The locational functional and technical needs associated with some infrastructure in close proximity to the coast should be recognised. Providing for infrastructure's locational functional and technical constraints and associated requirements is consistent with the sustainable management purpose of the RMA. 25 Consideration of remedying adverse effects on the coastal environment should be included in Policy CE.1. In some circumstances it will be appropriate to remedy adverse effects on the coastal environment rather than mitigate them. Meridian seeks the following relief 26 Amend Objective CE.1 by inserting the following underlined words and deleting the following strike through words at requirements 1, 2, 3 and 9: "1. Preserves the natural character of the coast coastal environment and protection of it from inappropriate subdivision, use and development." "2. Protects Outstanding Natural Features and Landscapes from inappropriate subdivision, use and development."

6 5 "3. Maintains Visual Amenity Landscapes from inappropriate subdivision, use and development." "9. Recognises that some infrastructure, such as the electricity generation and energy projects have a need to be located within the coastal environment." 27 Amend Policy CE.1 by inserting the following underlined words: "Avoid, remedy or mitigate the adverse effects of inappropriate subdivision, land use and development on the coastal environment." 28 In addition to the above, the following relief is also sought: Any additional or alternative relief that achieves the same or similar outcome; Consequential or ancillary changes to the above. Section 2.9 Energy, Minerals and Infrastructure 29 Objective ENGM.1, as amended by the decision, is "Energy and mineral resources are developed and electricity is generated, in a manner that minimises adverse effects on the environment". Submitters, supported by Meridian's further submission, sought an amendment to reflect that it is not always practical to minimise adverse effects of generation. 30 Policy ENGM.4 (previously Policy ENGM.3) and its explanation recognise that generation can have requirements for being "sited at a particular location". Meridian submitted that the policy should specifically refer to renewable energy. Meridian also submitted that the explanation to this policy should be amended to specifically refer to renewable energy. Reasons 31 Electricity generation is important to the district, regional and national economy and should be encouraged. The Manapouri Power Station generates 12% of the country's energy requirements and is nationally important. The Plan should allow some adverse effects where it is not practical to minimise them.

7 6 32 Renewable energy is a specific consideration in section 7 RMA and the Plan should explicitly provide for renewable energy and relevant locational requirements. Meridian seeks the following relief 33 Amend Objective ENGM.1 by inserting the following underlined words: "Energy and mineral resources are developed and electricity is generated, in a manner that minimises adverse effects on the environment as far as practical." 34 Amend Policy ENGM.4 by inserting the following underlined words: "Recognise that development of energy and mineral resources and the generation of electricity, including renewable energy, can have a functional, technical or operation requirements to be sited at a particular location." 35 Amend the explanation to Policy ENGM.4 to include an explanation of the relationship between the location of the resource and the development of energy facilities. 36 In addition to the above, the following relief is also sought: Any additional or alternative relief that achieves the same or similar outcome; Consequential or ancillary changes to the above. Section 3.1 Rural Zone 37 Meridian sought the inclusion of a new "Rule Rural.1 Permitted Activities (Investigation and Assessment Works for Electricity Generation Projects)". The decision rejected Meridian's submission and there is no new rule. 38 Rule RURAL.1 lists activities that are permitted provided they meet the General Rural Standards. At paragraph 7 earthworks within a riparian margin are permitted up to 25m 3. At paragraph 8 earthworks 20m away from a water body are permitted up to 1000m 3. There are a number of conditions in paragraphs 7 and 8 that apply to earthworks. Paragraph 17 permits "The operation, maintenance, refurbishment,

8 7 enhancement and minor upgrading of any existing electricity generation facilities." 39 The relationship of the earthworks rules (paragraphs 7 and 8) to the upgrading of existing generation facilities (paragraph 17) is not clear. A submitter, supported by Meridian's further submission, sought an amendment to clarify that the requirements (conditions) in paragraphs 7 and 8 do not apply to the upgrading of existing generation facilities (paragraph 17). Reasons 40 A new rule that permits investigation and assessment work for electricity generation works should be included in the Plan. The inclusion of a new rule is consistent with the National Policy Statement for Renewable Electricity Generation 2011 and section 7(j) RMA. 41 Clarification regarding whether or not earthworks relating to the upgrading of existing generation facility is required. Meridian seeks the following relief 42 Insert a new Rule into Rule RURAL.1 paragraph 21 to read: "21. Investigation and Assessment Works for Electricity Generation Projects The following activities undertaken for the identification and assessment of potential sites and energy sources for renewable electricity generation and research-scale investigation into existing and emerging renewable electricity generation technologies and methods are permitted activities that do not have to comply with the RURAL 7 General Rural Standards: (i) The erection of meteorological masts that do not exceed 100 metres in height; (ii) (iii) Digging test pits, drilling boreholes, constructing investigation drives and removing samples to investigate geological conditions; The installation of instruments into drill holes for monitoring groundwater levels and land movement;

9 8 (iv) (v) (vi) Erecting survey monuments and installing instruments to monitor land movement; Installing flumes and weirs to measure water flows; Erecting telemetry stations for the transmission of instrument data; (vii) Installing microseismic stations to measure microseismic activity and ground noise; (viii) Erection of signs or notices giving warning of danger; (ix) Construction and maintenance of access tracks and roads to any investigation and assessment sites and facilities; except: this activity is not undertaken in an area of Outstanding Natural Features and Landscapes the activity does not affect any items listed in the Historic Heritage Schedule 5.2 Providing that: At the end of the investigation or assessment period, any ground disturbed by such activities shall be reinstated to a condition no less than that which existed prior to the commencement of the work No such investigation or assessment period shall exceed five (5) years; (c) All equipment and structures shall be removed at the end of the investigation or assessment period and the site shall be restored and rehabilitated to a condition no less than that which existed prior to the works commencing." 43 Amend rule RURAL.1 paragraphs 7 and 8 by inserting the following proviso: "Provided that this rule does not apply to the ongoing operation, maintenance, enhancement, refurbishment or upgrading within the existing envelope of any lawfully established energy generation facility."

10 9 44 In addition to the above, the following relief is also sought: Any additional or alternative relief that achieves the same or similar outcome; Consequential or ancillary changes to the above. Section 4 Definitions 45 Additional definitions were requested to provide for the enhancement, upgrading or expansion of existing energy facilities. In response there is a new definition of "minor upgrading". The new definition of minor upgrading "means an upgrade to an existing electricity generation facility lawfully established which does not increase the building envelope by more than 100m 2 or 10% whichever is the lesser, within a 5 year period." A related new definition is "existing envelope (for electricity generation facilities): is the floor area / structure footprint that has been consented or otherwise authorised for the activity". Reasons 46 The new definitions of "minor upgrading" and "existing envelope" do not accord with section 10 RMA existing use rights and unnecessarily constrains the rights of electricity generators; particularly the operations of the Manapouri Power Scheme. Meridian seeks the following relief 47 Delete the definition of "minor upgrading" and replace with the following: "Minor upgrading (in relation to existing energy facilities) means modification of an energy facility including structures and associated earthworks and site works where the effects of that utility remain the same or similar in character, and scale. Minor upgrading includes the replacement of a structure in the same location, and replacement of parts of such." 48 Delete the definition of "existing envelope". 49 In addition to the above, the following relief is also sought:

11 10 Any additional or alternative relief that achieves the same or similar outcome; Consequential or ancillary changes to the above. 50 The following documents are attached to this notice: (c) A copy of Meridian's submission and further submissions. A copy of the relevant parts of the decision. A list of names and addresses of persons to be served with this notice. DATED this 24th day of November 2014 S W Christensen / R J Brooking Counsel for Meridian Energy Limited Address for service of Appellant: Anderson Lloyd Lawyers Private Bag 1959 Dunedin 9054 Phone: Fax: Contact person: Stephen Christensen / Rachel Brooking stephen.christensen@andersonlloyd.co.nz / rachel.brooking@andersonlloyd.co.nz

12 11 Advice to recipients of copy of notice of appeal How to become party to proceedings You may be a party to the appeal if you made a submission or a further submission on the matter of this appeal and you lodge a notice of your wish to be a party to the proceedings (in form 33) with the Environment Court within 15 working days after the period for lodging a notice of appeal ends. Your right to be a party to the proceedings in the court may be limited by the trade competition provisions in section 274(1) and Part 11A of the Resource Management Act You may apply to the Environment Court under section 281 of the Resource Management Act 1991 for a waiver of the above timing or service requirements (see form 38). How to obtain copies of documents relating to appeal The copy of this notice served on you does not attach a copy of the appellant's submission, further submissions or parts of the decision appealed. These documents may be obtained, on request, from the appellant. Advice If you have any questions about this notice, contact the Environment Court in Christchurch.

NTW.1 Network Utilities

NTW.1 Network Utilities NTW.1 Network Utilities NOTE: The following provisions apply district wide in addition to any other provisions in this Plan applicable to the same areas or site. Index NTW.1 Network Utilities NTW.1.1 NTW.1.2

More information

Report for Agenda Item: 2

Report for Agenda Item: 2 QLDC Council 28 September 2017 Department: Planning & Development Report for Agenda Item: 2 Stage 2 Proposed District Plan Notification Purpose The purpose of this paper is to present those parts of Stage

More information

Further Submission on Proposed Natural Resources Plan for the Wellington Region

Further Submission on Proposed Natural Resources Plan for the Wellington Region Property Group National Service Centre Alexander Road Private Bag 902 Trentham Upper Hutt 5140, New Zealand Further on Proposed Natural Resources Plan for the Wellington Region Clauses 8 of First Schedule,

More information

STATEMENT OF EVIDENCE OF MARK BULPITT CHRISP

STATEMENT OF EVIDENCE OF MARK BULPITT CHRISP IN THE MATTER of the Resource Management Act 1991 AND IN THE MATTER of submissions by Contact Energy Ltd in relation to Proposed Plan Changes 29 and 33 to the Taupo District Plan STATEMENT OF EVIDENCE

More information

Kaipara District Plan: Proposed Plan Change 2 - Fire Safety Rules SUMMARY

Kaipara District Plan: Proposed Plan Change 2 - Fire Safety Rules SUMMARY Kaipara District Plan: Proposed Plan Change 2 - Fire Safety Rules SUMMARY Kaipara District Council is proposing changes to the Fire Safety Rules in the Kaipara District Plan. Research has been undertaken

More information

13 Section 32 Summary for the Residential Chapter

13 Section 32 Summary for the Residential Chapter 13 Section 32 Summary for the Residential Chapter The purpose of this section is to present a summary of the evaluation of the objectives, policies and methods of the Residential Zone Chapter of the Proposed

More information

RE: Submission on the Proposed National Policy Statement on Urban Development Capacity

RE: Submission on the Proposed National Policy Statement on Urban Development Capacity Fonterra Co-operative Group Limited 165 Broadway Avenue PALMERSTON NORTH 4414 15 July 2016 NPS Urban Development Ministry for the Environment PO Box 106483 AUCKLAND 1143 Dear Sir / Madam RE: Submission

More information

(18 April 2011 to date) MINERAL AND PETROLEUM RESOURCES DEVELOPMENT ACT 28 OF 2002

(18 April 2011 to date) MINERAL AND PETROLEUM RESOURCES DEVELOPMENT ACT 28 OF 2002 (18 April 2011 to date) MINERAL AND PETROLEUM RESOURCES DEVELOPMENT ACT 28 OF 2002 (Gazette No. 23922, Notice No. 1273 dated 10 October 2002. Commencement date: 1 May 2004 [Proc. No. R25, Gazette No. 26264])

More information

Rural-Residential Rural-Residential Explanatory Statement Significant Issues Objectives and Policies...

Rural-Residential Rural-Residential Explanatory Statement Significant Issues Objectives and Policies... Section Contents Rural-Residential... 2 16. Rural-Residential... 2 Explanatory Statement... 2 16.1 Significant Issues... 2 16.2 Objectives and Policies... 3 16.3 Activity Lists... 3 16.4 Activity Performance

More information

POLICY EARTHQUAKE PRONE DANGEROUS & INSANITARY BUILDINGS

POLICY EARTHQUAKE PRONE DANGEROUS & INSANITARY BUILDINGS POLICY EARTHQUAKE PRONE DANGEROUS & INSANITARY BUILDINGS Adopted: Council Meeting 30 June 2011 Review date: before 30 June 2016 Contents 1 Introduction and background... 1 2 Policy approach... 2 2.1 Policy

More information

3 RURAL ENVIRONMENT CONTENTS

3 RURAL ENVIRONMENT CONTENTS 3 RURAL ENVIRONMENT CONTENTS 3.1 ISSUES 4 3.2 OBJECTIVES 5 3.3 POLICIES 7 3.4 RULES RURAL PRODUCTION ZONE 10 3.5 Performance standards 15 3.6 RULES RURAL LIFESTYLE ZONE 18 3.7 Performance standards 19

More information

Climate Change and Renewable Energy Bill 2017*

Climate Change and Renewable Energy Bill 2017* Queensland Climate Change and Renewable Energy Bill 2017* Current DRAFT as at 24 November 2017 *Material in this draft Bill has been excerpted from the Climate Change Act 2017 (Vic) and the Climate Change

More information

Plan Change 85A: Rural Production Environment

Plan Change 85A: Rural Production Environment Plan Change 85A: Rural Production Environment Section 32 Evaluation Report Prior to Notification Part 3 JUNE 2016 1 Contents 1. Introduction... 3 1.1 Overview and background... 3 1.2 The proposed plan

More information

Plan Change 5 to the Canterbury Land and Water Regional Plan

Plan Change 5 to the Canterbury Land and Water Regional Plan Plan Change 5 to the Canterbury Land and Water Regional Plan Table of contents PART 1 (HOW TO READ THIS DOCUMENT)... 1-1 Introduction... 1-2 Information for the Reader... 1-2 How amendments to the Plan

More information

E20 Māori Land. (2) The importance of economic development to support the occupation, development and use of Māori land is recognised.

E20 Māori Land. (2) The importance of economic development to support the occupation, development and use of Māori land is recognised. E20. Māori Land E20.1. Background These Auckland-wide provisions recognise the unique legal and governance framework for Māori Land being subject to Te Ture Whenua Māori Act 1993. They provide for the

More information

Climate Change and Renewable Energy Bill 2017*

Climate Change and Renewable Energy Bill 2017* Queensland Climate Change and Renewable Energy Bill 2017* Current DRAFT as at 22 December 2017 *Material in this draft Bill has been excerpted from the Climate Change Act 2017 (Vic) and the Climate Change

More information

Rural Living Environment

Rural Living Environment 1 RLE.1 Rural Living Environment RLE.1.1 Description & Expectations The Rural Living Environment (RLE) covers rural areas within the District that are either already characterised by lifestyle activities

More information

Understanding the State Planning Policy July 2017 Changes to state interest statements, policies and assessment benchmarks

Understanding the State Planning Policy July 2017 Changes to state interest statements, policies and assessment benchmarks Understanding the State Planning Policy July 2017 Changes to state statements, policies and assessment benchmarks This fact sheet outlines the key policy changes to the state statements, policies and assessment

More information

Last Amended 19 November 2014 Utility Rules Operative 27/07/00

Last Amended 19 November 2014 Utility Rules Operative 27/07/00 23. UTILITY RULES These provisions apply to utility network infrastructure [and the activities of other operators] PC74 dealt with in this chapter throughout all parts of the city. The area based objectives,

More information

QLDC Council 8 November Report for Agenda Item: 1

QLDC Council 8 November Report for Agenda Item: 1 5 QLDC Council 8 November 2017 Department: Planning & Development Report for Agenda Item: 1 Stage 2 Proposed District Plan Notification - Transport Purpose 1 The purpose of this report is to present parts

More information

Contents GR Geothermal Resources... 1

Contents GR Geothermal Resources... 1 Geothermal Resources 14 September 2017 Contents GR Geothermal Resources... 1 Issues... 1 Objectives... 4 Policies... 4 Methods of Implementation... 9 Rules... 14 BAY OF PLENTY REGIONAL COUNCIL TOI MOANA

More information

Manawatu District Plan Proposed Plan Change 55: Chapter 3 District Wide Rules

Manawatu District Plan Proposed Plan Change 55: Chapter 3 District Wide Rules Manawatu District Plan Proposed Plan Change 55: Chapter 3 District Wide Rules Section 32 Report April 2016 Part I District Plan Review 1 Proposed amendments to the District Plan This proposed Plan Change

More information

Earthquake-Prone Buildings Policy

Earthquake-Prone Buildings Policy Earthquake-Prone Buildings Policy Introduction and Purpose The purpose of this Policy is to balance out the need to address earthquake risk and other priorities, taking account of the social, cultural

More information

15B Maori Purposes: Treaty Settlement Land

15B Maori Purposes: Treaty Settlement Land 15B Maori Purposes: Treaty Settlement Land 15B.1 Introduction / Resource Description This Chapter of the District Plan addresses land included as part of the recent Treaty Settlements between: Te Uri o

More information

Contact Energy Limited Proposed Amendments to the National Policy Statement for Freshwater Management 2011

Contact Energy Limited Proposed Amendments to the National Policy Statement for Freshwater Management 2011 Contact Energy Limited Proposed Amendments to the National Policy Statement for Freshwater Management 2011 Proposed Amendments NPS Freshwater Management 1 This submission by Contact Energy Limited (Contact)

More information

Information on the focal point for the Convention. Information on the point of contact for the Convention

Information on the focal point for the Convention. Information on the point of contact for the Convention Questionnaire for the REPORT OF MONTENEGRO ON THE IMPLEMENTATION OF THE CONVENTION ON ENVIRONMENTAL IMPACT ASSESSMENT IN A TRANSBOUNDARY CONTEXT in the period 2006 2009 Information on the focal point for

More information

CON 509: APPLICATION FOR A RESOURCE CONSENT UNDER THE RESOURCE MANAGEMENT ACT 1991

CON 509: APPLICATION FOR A RESOURCE CONSENT UNDER THE RESOURCE MANAGEMENT ACT 1991 APPLICATION TO USE LAND FOR FARMING ACTIVITY PAGE 1 OF 15 August 2016 CON 509: APPLICATION FOR A RESOURCE CONSENT UNDER THE RESOURCE MANAGEMENT ACT 1991 TO USE LAND FOR A FARMING ACTIVITY WITHIN THE SELWYN

More information

Beds of Water Bodies 14 September 2017

Beds of Water Bodies 14 September 2017 Beds of Water Bodies 14 September 2017 Contents Beds of Water Bodies... 1 Activities in the Beds of Water Bodies Issues... 1 Objectives... 4 Policies... 4 Methods of Implementation... 7 Rules... 11 Stock

More information

Date of Request for Comment: April 7, 2017 Period of Comment: April 7, 2017 through May 5, 2017

Date of Request for Comment: April 7, 2017 Period of Comment: April 7, 2017 through May 5, 2017 Market Participant Comments and AESO Replies Matrix Proposed Amended Section 304.3, Wind and Solar Power Ramp Up Management ( amended Section 304.3 ) Date of Request for Comment: April 7, 2017 Period of

More information

Documents submitted in response to Regulation 22 request. Additional documents submitted by Provectus Remediation Ltd

Documents submitted in response to Regulation 22 request. Additional documents submitted by Provectus Remediation Ltd Documents submitted in response to Regulation 22 request The documents recently submitted by Provectus Remediation Ltd in response to the Planning Inspectors request under Regulation 22 add nothing of

More information

Improving resource consent conditions

Improving resource consent conditions Improving resource consent conditions Mike Freeman, Director, Freeman Environmental Ltd. Introduction The management of New Zealand s water, stormwater and wastewater infrastructure is critical to our

More information

11 May Sigma Consultants PO Box 553 ROTORUA Attn: Ann Nicholas. Dear Ann

11 May Sigma Consultants PO Box 553 ROTORUA Attn: Ann Nicholas. Dear Ann 11 May 2017 Sigma Consultants PO Box 553 ROTORUA 3040 72 Lake Terrace, Taupō 3330 Private Bag 2005, Taupo Mail Centre Taupō 3352, New Zealand T 07 376 0899 F 07 378 0118 E general@taupo.govt.nz www.taupo.govt.nz

More information

Cork County Development Plan Volume Three: SEA Statement and Natura Impact Report

Cork County Development Plan Volume Three: SEA Statement and Natura Impact Report Cork County Development Plan 2014 Volume Three: SEA Statement and Natura Impact Report 3 Volume 3: SEA Statement and Natura Impact Report Cork County Development Plan 2014 Contents Section 1 Strategic

More information

H3 Residential Single House Zone

H3 Residential Single House Zone H3. Residential Single House Zone [ENV-2016-AKL-000243: K Vernon] Addition sought [CIV-2016-404-002333: Franco Belgiorno-Nettis]-Note: The properties affected by this appeal are identified on the Auckland

More information

28 JULY 2015 PLANNING COMMITTEE. 5i 14/1315 Reg d: Expires: Ward: OW. of Weeks on Cttee Day:

28 JULY 2015 PLANNING COMMITTEE. 5i 14/1315 Reg d: Expires: Ward: OW. of Weeks on Cttee Day: 5i 14/1315 Reg d: 25.11.2014 Expires: 29.04.15 Ward: OW Nei. Con. Exp: 14.01.15 BVPI Target Minor (13) Number of Weeks on Cttee Day: 21/8 On Target? No LOCATION: PROPOSAL: TYPE: London House, 134 High

More information

by: New Zealand Transport Agency Submitter Opening legal submissions on behalf of the New Zealand Transport Agency

by: New Zealand Transport Agency Submitter Opening legal submissions on behalf of the New Zealand Transport Agency under: the Resource Management Act 1991 in the matter of: a submission by the New Zealand Transport Agency (submitter number 146) on the Proposed Natural Resources Plan for the Wellington Region and in

More information

Monitoring Report for the Quail Rise Special Zone

Monitoring Report for the Quail Rise Special Zone 97 2011 Monitoring Report for the Quail Rise Special Zone Policy and Planning Queenstown Lakes District Council September 2011 1 98 Executive Summary In accordance with section 35 of the Resource Management

More information

EWA ENVIRONMENTAL AFFAIRS

EWA ENVIRONMENTAL AFFAIRS 326 National Environmental Management Act (107/1998): Amendments to the Environmental Impact Assessment Regulations, 2014 40772 STAATSKOERANT, 7 APRIL 2017 No. 40772 211 DEPARTMENT OF ENVIRONMENTAL AFFAIRS

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22781-D01-2017 Newell Solar Power Plant November 15, 2017 Alberta Utilities Commission Decision 22781-D01-2017 Newell Solar Power Plant Proceeding 22781 Application 22781-A001 November 15, 2017

More information

B. Stakeholder Guide: Infrastructure and utility providers

B. Stakeholder Guide: Infrastructure and utility providers B. Stakeholder Guide: Infrastructure and utility providers Why is the Government proposing new legislation? As our population grows, the Government wants to accelerate the building of new communities and

More information

PLAN SUBMISSION, BUFFERING AND SETBACK FROM TRANSMISSION PIPELINES

PLAN SUBMISSION, BUFFERING AND SETBACK FROM TRANSMISSION PIPELINES PLAN SUBMISSION, BUFFERING AND SETBACK FROM TRANSMISSION PIPELINES Note: The sections of this ordinance are intended to be enacted as part of a Township s Subdivision and Land Development Ordinance. AN

More information

8 RURAL ENVIRONMENT CONTEXT 8.1 ISSUES. Chapter 8 - RURAL ENVIRONMENT Section 6 Rural Production Zone

8 RURAL ENVIRONMENT CONTEXT 8.1 ISSUES. Chapter 8 - RURAL ENVIRONMENT Section 6 Rural Production Zone Section 6 Rural Production Zone 8 RURAL ENVIRONMENT CONTEXT The majority of the land in the Far North is, and will remain, rural, where rural production is the main activity but there are distinct differences

More information

H2. Residential Rural and Coastal Settlement Zone

H2. Residential Rural and Coastal Settlement Zone H2. Residential Rural and Coastal Settlement Zone H2.1. Zone description The Residential Rural and Coastal Settlement Zone applies to rural and coastal settlements in a variety of environments including

More information

Aircraft Manufacturing Organisations Certification

Aircraft Manufacturing Organisations Certification Civil Aviation Rules Part 148, Amendment 4 Docket 8/CAR/1 Contents Rule objective... 3 Extent of consultation... 3 Summary of submissions... 3 Examination of submissions... 4 Insertion of Amendments...

More information

European Treaty Series - No. 121 CONVENTION FOR THE PROTECTION OF THE ARCHITECTURAL HERITAGE OF EUROPE

European Treaty Series - No. 121 CONVENTION FOR THE PROTECTION OF THE ARCHITECTURAL HERITAGE OF EUROPE European Treaty Series - No. 121 CONVENTION FOR THE PROTECTION OF THE ARCHITECTURAL HERITAGE OF EUROPE Granada, 3.X.1985 2 ETS 121 Protection of the architectural heritage, 3.X.1985 The member States of

More information

Heritage sites, features and areas contribute to our identity and to amenity.

Heritage sites, features and areas contribute to our identity and to amenity. 17 Historic Heritage 17.1 Introduction / Resource Description 17.1.1 17.1.2 Heritage is defined in the Resource Management Act 1991, and essentially includes items or places that have significance to the

More information

Works, services and infrastructure code

Works, services and infrastructure code 9.4.11 Works, services infrastructure code 9.4.11.1 Application (1) This code applies to assessable development identified as requiring assessment against the Works, services infrastructure code by the

More information

Gisborne District Council

Gisborne District Council 11.0 NOISE AND VIBRATION... 1 11.1 STRUCTURE OF THIS CHAPTER... 1 11.2 INTRODUCTION... 1 11.3 ISSUES... 2 11.4 OBJECTIVES (NOISE INCLUDING VIBRATION)... 2 11.5 POLICIES (NOISE INCLUDING VIBRATION)... 2

More information

HAUC England Advice Note No. 2014/02. Code of Practice for Inspections: Defects Not Causing Danger Inspections ENGLAND

HAUC England Advice Note No. 2014/02. Code of Practice for Inspections: Defects Not Causing Danger Inspections ENGLAND HAUC England Advice Note No. 2014/02 Code of Practice for Inspections: Defects Not Causing Danger Inspections ENGLAND Version: VI Control Document No.: 1 Document Owner: Roger Culpin and Mark Ostheimer

More information

Content Copy Of Original

Content Copy Of Original Content Copy Of Original Ministry of the Environment Ministère de l Environnement ENVIRONMENTAL COMPLIANCE APPROVAL NUMBER 4495-9FUQDY Issue Date: February 5, 2014 Holcim (Canada) Inc. 2300 Steeles Ave

More information

Commonwealth of Massachusetts Executive Office of Energy and Environmental Affairs and Department of Environmental Protection

Commonwealth of Massachusetts Executive Office of Energy and Environmental Affairs and Department of Environmental Protection Commonwealth of Massachusetts Executive Office of Energy and Environmental Affairs and Department of Environmental Protection Technical Support Document on Proposed Regulatory Amendments to: 310 CMR 7.75

More information

ARTICLE 29 DATA PROTECTION WORKING PARTY

ARTICLE 29 DATA PROTECTION WORKING PARTY ARTICLE 29 DATA PROTECTION WORKING PARTY 17/EN WP 256 Working Document setting up a table with the elements and principles to be found in Binding Corporate Rules (updated) Adopted on 29 November 2017 INTRODUCTION

More information

State Significant Development and State Significant Infrastructure

State Significant Development and State Significant Infrastructure Planning, Development & Heritage State Significant Development and State Significant Infrastructure Last updated: July 2015 These Fact Sheets are a guide only and are no substitute for legal advice. To

More information

Earthquake-prone, Dangerous and Insanitary Buildings Policy 2011

Earthquake-prone, Dangerous and Insanitary Buildings Policy 2011 Earthquake-prone, Dangerous and Insanitary Buildings Policy 2011 1.0 Introduction 1.1 Objective To ensure that the policy on earthquake-prone, dangerous and insanitary buildings meets the requirements

More information

9.3.9 Industry uses code

9.3.9 Industry uses code 9.3.9 Industry uses code 9.3.9.1 Application (1) This code applies to accepted development and assessable development identified as requiring assessment against the Industry uses code by the tables of

More information

The Proposed Auckland Unitary Plan (notified 30 September 2013)

The Proposed Auckland Unitary Plan (notified 30 September 2013) ART 3 REGIONAL AND DISTRICT RULES»Chapter H: Auckland wide rules»4 Natural resources» 4.14 Stormwater management Introduction The roposed Auckland Unitary lan (notified 30 September 2013) This section

More information

For Council Use. Building Category R1 R2 R3. Approving Officer. Note: PIM (Appln vetted and lodged) Water Services Add Inspect *

For Council Use. Building Category R1 R2 R3. Approving Officer. Note: PIM (Appln vetted and lodged) Water Services Add Inspect * Building consent applic ation document check -sheet Consent To get application form go to: Consent Number: PO Box 903 Tel: 0800 732 732 15 Forth Street Fax: 0800 732 329 Invercargill 9840 Email: sdc@southlanddc.govt.nz

More information

Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until Non Technical Summary

Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until Non Technical Summary Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until 2035 Non Technical Summary SLR Consulting Limited Project Ref: 403.00079.00474

More information

Chapter 17 Cumulative Impacts

Chapter 17 Cumulative Impacts Chapter 17 Cumulative Impacts CONTENTS 17. Cumulative Effects... 2 17.1 Introduction... 2 17.2 Summary of Relevant Legislation, Planning Policy and Guidance... 2 17.3 Methods... 5 17.4 Consultation...

More information

Urban Development Institute of Australia Western Australian Division Incorporated

Urban Development Institute of Australia Western Australian Division Incorporated Our Ref: 27.1.1 26 November 2004 Dr Judy Edwards MLA MINISTER FOR THE ENVIRONMENT Level 29 Allendale Square 77 St Georges Terrace Perth, WA 6000 Dear Minister Re: Revised Draft Environmental Protection

More information

South Australia Continuing to Make Room for Wind Farms: Tru Energy Renewable Developments Pty Ltd V Regional Council of Goyder & Ors [2014] SAERDC 48

South Australia Continuing to Make Room for Wind Farms: Tru Energy Renewable Developments Pty Ltd V Regional Council of Goyder & Ors [2014] SAERDC 48 South Australia Continuing to Make Room for Wind Farms: Tru Energy Renewable Developments Pty Ltd V Regional Council of Goyder & Ors [2014] SAERDC 48 Claudia Mollina 1 The Environment, Resources and Development

More information

EARTHQUAKE- PRONE BUILDINGS POLICY

EARTHQUAKE- PRONE BUILDINGS POLICY EARTHQUAKE- PRONE BUILDINGS POLICY 2009 1. Introduction CONTENTS 2. Policy Objectives and Principles 3. Key Policy Components - Assessing earthquake-prone buildings - Standard of strengthening required

More information

REPORT FORM. TERMINATION OF EMPLOYMENT CONVENTION, 1982 (No. 158)

REPORT FORM. TERMINATION OF EMPLOYMENT CONVENTION, 1982 (No. 158) Appl. 22.158 158. Termination of Employment, 1982 INTERNATIONAL LABOUR OFFICE GENEVA REPORT FORM FOR THE TERMINATION OF EMPLOYMENT CONVENTION, 1982 (No. 158) The present report form is for the use of countries

More information

H3. Residential Single House Zone

H3. Residential Single House Zone H3. Residential Single House Zone H3.1. Zone description The purpose of the Residential Single House Zone is to maintain and enhance the amenity values of established residential neighbourhoods in number

More information

Expression of Interest (EOI) For. Empanelment of lawyers

Expression of Interest (EOI) For. Empanelment of lawyers Expression of Interest (EOI) For Empanelment of lawyers For handling matters under Insolvency & Bankruptcy Code, 2016 before National Company Law Tribunal EOI NO- Date: Issued By: Deputy General Manager

More information

TOWARDS SUSTAINABLE DEVELOPMENT

TOWARDS SUSTAINABLE DEVELOPMENT TOWARDS SUSTAINABLE DEVELOPMENT The Role of the Resource Management Act 1991 PCE Environmental Management Review No.1 Office of the PARLIAMENTARY COMMISSIONER FOR THE ENVIRONMENT Te Kaitiaki Taiao a Te

More information

Annexure B Section 22

Annexure B Section 22 Annexure B Section 22 Accreditation of Audit Firms, Reporting Accountants, Reporting Accountant Specialists and IFRS Advisers to provide accounting and/or advisory services to applicant issuers Scope of

More information

Environmental and Social Management Plan

Environmental and Social Management Plan Environmental and Social Management Plan Capital Works State Highway 205 / Schist Street Intersection Upgrade 21 September 2015 NZTA142200 Page ii Record of amendment Amendment number Description of change

More information

Sustainability Roadmap for Myanmar (Environment Perspective) Dr. San Oo Director Environmental Conservation Department 20 January 2015

Sustainability Roadmap for Myanmar (Environment Perspective) Dr. San Oo Director Environmental Conservation Department 20 January 2015 Sustainability Roadmap for Myanmar (Environment Perspective) Dr. San Oo Director Environmental Conservation Department 20 January 2015 1 Ministry of Environmental Conservation and Forestry (MOECAF) Environmental

More information

Electricity Supply Agreement

Electricity Supply Agreement Electricity Supply Agreement 1. General 1.1 Mazoon Electricity Company SAOC (the Supplier) shall on or from the Start Date, subject to the satisfactory completion of a Supply Application Form, provide

More information

DISCRIMINATION, BULLYING AND HARASSMENT PREVENTION PROCEDURES

DISCRIMINATION, BULLYING AND HARASSMENT PREVENTION PROCEDURES PROCEDURES EFFECTIVE DATE 01-06-2015 LAST AMENDMENT 05-24-2007 DISCRIMINATION, BULLYING AND HARASSMENT PREVENTION PROCEDURES Responsible Department Human Resources Responsible Executive Associate Vice

More information

OPENCAST COAL PLANNING SERIES

OPENCAST COAL PLANNING SERIES SCOTTISH PLANNING POLICY 16 pp OPENCAST COAL PLANNING SERIES Scottish Planning Policy SPP 16 Opencast Coal Revised July 2005 Crown copyright 2005 ISSN 1741 1203 spp PLANNING SERIES: Scottish Planning Policies

More information

Section 22. Scope of section. Accreditation. Eligibility Criteria

Section 22. Scope of section. Accreditation. Eligibility Criteria Section 22 Accreditation of Audit Firms, Reporting Accountants, Reporting Accountant Specialists and IFRS Advisers to provide accounting and/or advisory services to applicant issuers Scope of section The

More information

Initial Modification Report No.39. Transfer of Exit Capacity between Northern Ireland Exit Points to permit Secondary Trading of Exit Capacity

Initial Modification Report No.39. Transfer of Exit Capacity between Northern Ireland Exit Points to permit Secondary Trading of Exit Capacity Initial Modification Report No.39 Transfer of Exit Capacity between Northern Ireland Exit Points to permit Secondary Trading of Exit Capacity 30 th September 2016 Please find below Initial Modification

More information

STATEMENT OF EVIDENCE OF ANGELA MADELINE STEWART

STATEMENT OF EVIDENCE OF ANGELA MADELINE STEWART IN THE MATTER OF the Resource Management Act 1991 AND IN THE MATTER OF a further submission on the Christchurch Replacement District Plan BY Tegel Foods Limited Submission number: 2774 STATEMENT OF EVIDENCE

More information

Hydropower Guidance Note: HGN 7 Competing Schemes

Hydropower Guidance Note: HGN 7 Competing Schemes Guidance Note Hydropower Guidance Note: HGN 7 Competing Schemes This guidance is not intended as a statement of law and should be read in combination with and in the context of the relevant enactments

More information

Operating Requirements Manual 11 October 2015 Version 1

Operating Requirements Manual 11 October 2015 Version 1 Operating Requirements Manual 11 October 2015 Version 1 Contents 1 Introduction 1 2 Interface Risk Management 2 2.1 Interface Risk Assessment 2 2.2 Interface Risk Management Plan 4 2.3 Provision of Assistance

More information

Employment of Fixed-Term Staff Policy. University-wide. Staff Only Students Only Staff and Students. Vice Chancellor

Employment of Fixed-Term Staff Policy. University-wide. Staff Only Students Only Staff and Students. Vice Chancellor Name of Policy Description of Policy Employment of Fixed-Term Staff Policy This policy covers the arrangements for the employment for fixedterm contract staff members at the University. University-wide

More information

The Building Control Act 1990 places a statutory obligation on owners, designers and builders to design and build in accordance with the building

The Building Control Act 1990 places a statutory obligation on owners, designers and builders to design and build in accordance with the building 7FSTJPO +VMZ The Building Control Act 1990 places a statutory obligation on owners, designers and builders to design and build in accordance with the building regulations; establishes Building Control

More information

RMA Analysis Report. Fibre to the Home (FTTH) Aerial Network for a Hypothetical New Entrant

RMA Analysis Report. Fibre to the Home (FTTH) Aerial Network for a Hypothetical New Entrant RMA Analysis Report Fibre to the Home (FTTH) Aerial Network for a Hypothetical New Entrant 31 July 2014 Quality Control Title Client Version Final Date 31 July 2014 File Reference A57016.00 Prepared by

More information

The Environmental Management and Protection (Saskatchewan Environmental Code Adoption) Regulations

The Environmental Management and Protection (Saskatchewan Environmental Code Adoption) Regulations ENVIRONMENTAL MANAGEMENT 1 ENVIRONMENTAL CODE ADOPTION) E-10.22 REG 2 The Environmental Management and Protection (Saskatchewan Environmental Code Adoption) Regulations being Chapter E-10.22 Reg 2 (effective

More information

Central NSW Regional Contaminated Land Policy Template

Central NSW Regional Contaminated Land Policy Template Central NSW Regional Contaminated Land Policy Template Contamination Central: Supporting safe, stable and sustainable redevelopment of land in Central West NSW. Funded by the New South P a g e 1 {Instruction

More information

Chapter 4 Planning and statutory requirements. Chapter 4 Planning and statutory requirements

Chapter 4 Planning and statutory requirements. Chapter 4 Planning and statutory requirements Chapter 4 Planning and statutory requirements Chapter 4 Planning and statutory requirements Contents Page number 4. Planning and statutory requirements 4-1 4.1 Approval under the EPBC Act 4-1 4.1.1 Controlled

More information

Tree Management Plan

Tree Management Plan Tree Management Plan Project: Parnell Prepared For: By: Newmarket Level Crossing Cowie Street, Opus International Consultants Matthew Paul Date: 4/09/17 1 Contents 1.0 Scope of Tree Management Plan 2 2.0

More information

Safety barrier to a deck located adjacent to a retaining wall at Oraka Beach Road, Mahia

Safety barrier to a deck located adjacent to a retaining wall at Oraka Beach Road, Mahia Determination 2008/81 Safety barrier to a deck located adjacent to a retaining wall at Oraka Beach Road, Mahia Figure 1: Section showing deck and top of the bank 1 The matters to be determined 1.1 This

More information

New Zealand Transport Agency: Christchurch Southern Motorway Proposal. Notices of requirement and resource consent applications

New Zealand Transport Agency: Christchurch Southern Motorway Proposal. Notices of requirement and resource consent applications Public notice New Zealand Transport Agency: Christchurch Southern Motorway Proposal Notices of requirement and resource consent applications The New Zealand Transport Agency has lodged an application with

More information

Online Store Application Form

Online Store Application Form Online Store Application Form You need to be a Lincoln Sentry Account holder to place orders using the online store website. Please provide your existing Lincoln Sentry account number. Submit the completed

More information

ECB-PUBLIC OPINION OF THE EUROPEAN CENTRAL BANK. of 4 October 2017

ECB-PUBLIC OPINION OF THE EUROPEAN CENTRAL BANK. of 4 October 2017 EN ECB-PUBLIC OPINION OF THE EUROPEAN CENTRAL BANK of 4 October 2017 on a proposal for a regulation of the European Parliament and of the Council amending Regulation (EU) No 1095/2010 and Regulation (EU)

More information

Tender specifications for open procedure for framework agreement on road transport of round wood

Tender specifications for open procedure for framework agreement on road transport of round wood for open procedure for framework agreement on road transport of round wood Procurement Notice No. /S -"[tal]" "[tal]" "[tal]" "[tal]" Page 1/18 Table of contents 1. THE CONTRACTING AUTHORITY... 3 2. LEGAL

More information

Shanks Family Trust (Trevor Shanks)

Shanks Family Trust (Trevor Shanks) RMA Section 42A Report GO DISTRICT COUNCIL 26 Oxford Street. Gore Reference: LU 2016/257 Location: 26 Oxford Street/ Gore Legal Description: Lot 1 Deposited Plan 14335 Applicant: Shanks Family Trust (Trevor

More information

For information on water pollution, see our Fact Sheet on Pollution.

For information on water pollution, see our Fact Sheet on Pollution. 1 Water Management Water Management Last updated: 2010 These Fact Sheets are a guide only and are no substitute for legal advice. To request free initial legal advice on an environmental or planning law

More information

NSW Heritage Law. Planning, Development & Heritage. Overview. Last updated: August 2012

NSW Heritage Law. Planning, Development & Heritage. Overview. Last updated: August 2012 Planning, Development & Heritage NSW Heritage Law Last updated: August 2012 These Fact Sheets are a guide only and are no substitute for legal advice. To request free initial legal advice on an environmental

More information

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments This rule as amended was approved by the Alberta Utilities Commission on June

More information

LEGISLATIVE CONSENT MEMORANDUM EUROPEAN UNION (WITHDRAWAL) BILL

LEGISLATIVE CONSENT MEMORANDUM EUROPEAN UNION (WITHDRAWAL) BILL LEGISLATIVE CONSENT MEMORANDUM EUROPEAN UNION (WITHDRAWAL) BILL Introduction 1. The Scottish Government remains of the view that the best option for the UK as a whole, and for Scotland, would be the one

More information

UNITED NATIONS COMMISSION ON INTERNATIONAL TRADE LAW (UNCITRAL)

UNITED NATIONS COMMISSION ON INTERNATIONAL TRADE LAW (UNCITRAL) UNITED NATIONS COMMISSION ON INTERNATIONAL TRADE LAW (UNCITRAL) UNCITRAL Model Law on Procurement of Goods, Construction and Services with Guide to Enactment CONTENTS PREAMBLE CHAPTER I. GENERAL PROVISIONS

More information

HYDRO AND ELECTRIC ENERGY REGULATION

HYDRO AND ELECTRIC ENERGY REGULATION Province of Alberta HYDRO AND ELECTRIC ENERGY ACT HYDRO AND ELECTRIC ENERGY REGULATION Alberta Regulation 409/1983 With amendments up to and including Alberta Regulation 136/2015 Office Consolidation Published

More information

HSE statement on radiation protection advisers

HSE statement on radiation protection advisers HSE statement on radiation protection advisers The requirements of this Statement came into effect on 31 March 2007 Purpose Introduction Criteria of core competence Assessing bodies Suitable RPA's Annex

More information

July State Planning Policy. Department of Infrastructure, Local Government and Planning

July State Planning Policy. Department of Infrastructure, Local Government and Planning July 2017 State Planning Policy Department of Infrastructure, Local Government and Planning The State of Queensland, July 2017. Published by the Department of Infrastructure, Local Government and Planning,

More information

3 Objectives 3 Ob jec tives

3 Objectives 3 Ob jec tives 3 Objectives 3 Objectives 3 Objectives 3 Objectives contents Objective number Page 3.1 Ki uta ki tai: mountains to the sea O1-O5 37 3.2 Beneficial use and development O6-O13 38 3.3 Māori relationships

More information