WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY

Size: px
Start display at page:

Download "WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY"

Transcription

1 WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS J O G Tande and K Uhlen SINTEF Energy Research, Norway SUMMARY Cost efficient utilisation of the wind energy resource requires wind farms to be located at areas with good wind resources. Such areas are often in proximity to a relatively weak grid that may represent technical constraints for exploiting the wind resources. Hence, aiming for cost efficient utilisation of wind energy resources it is a challenge to find ways to overcome the technical constraints, i.e. basically issues related to thermal capacity, voltage quality and stability Figure 1: Example network with small wind farm. We consider a small wind farm on a medium voltage feeder as shown in Figure 1 to illustrate issues of voltage quality. We demonstrate that the development of IEC [1] provides firm basis for assessment of the impact of wind turbines on voltage quality. This make previously used simplified rules unnecessary, and opens for increased utilisation of wind energy in weak grids. Further, we demonstrate that possible voltage quality problems due to a small wind farm may be overcome simply by selecting an appropriate wind turbine type, and/or by adjusting wind turbine control parameters. The assessment includes determination of voltage profiles (Figure 2), emission of flicker, voltage dips and harmonics. Voltage (pu) min load/max wind max load/0 wind Node number Figure 2: Result of example load-flow analysis. We consider the case of a large wind farm in a regional 132 kv grid distant from the main 300 kv transmission grid to illustrate issues related to thermal capacity and voltage stability. First we assume the regional grid to be connected to the main transmission via two separate feeders. In this case, depending on the amount of injected wind power, an outage of one of the feeders may cause a voltage collapse as shown in Figure 3. Hence, this could be a constraint for the wind power development in the regional grid Bus Wind farm Wind power injected (MW) Figure 3: Voltage dependency of injected wind power. Voltage (kv) This problem can be solved however by installation of a inexpensive system protection scheme that send a signal to automatically reduce the wind power generation when a line outage is detected. Sometimes regional networks are connected to the main transmission via one feeder only. If this was the case, we show that application of an SVC unit or a similar device for continuous voltage control allows increased wind power penetration. We have not made any detailed assessment of the costsavings associated with the suggested solutions compared to the alternative of conventional grid reinforcement by installation of new lines. This is because such numbers will be very case specific. We suspect however that for a majority of projects, the solutions considered will be more economic than installation of new lines. [1] IEC (2001) Measurements and assessment of power quality characteristics of grid connected wind turbines. FDIS.

2 WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS J O G Tande and K Uhlen SINTEF Energy Research, Norway ABSTRACT The development of IEC provides firm basis for assessment of the impact of wind turbines on voltage quality. This makes previously used simplified rules unnecessary, and opens for increased utilisation of wind energy in weak grids. Assessment of thermal capacity and voltage stability constraints call for additional analyses and innovative solutions. These are pinpointed by examples enabling cost-effective means to allow increased penetration of wind power in weak grids. SYMBOLS ψ k N T U LV U T c(ψ k,v a ) cos(ϕ) d E Plt E Pst k f (ψ k ) k u (ψ k ) N 10 N 120 P lt P mc P n P st S k U LV U MV U n v a network impedance phase angle LV transformer deviation from nominal ratio voltage drop from LV transformer to consumer voltage drop due to transformer losses flicker coefficient for wind turbine power factor of wind turbine sudden voltage reduction long-term flicker emission limit short-term flicker emission limit flicker step factor for wind turbine voltage change factor for wind turbine number of wind turbine starts within 10 min. number of wind turbine starts within 2 hours number of wind turbines long-term flicker emission maximum permitted power from wind turbine rated power of wind turbine short-term flicker emission network short-circuit power voltage at low voltage consumer voltage at medium voltage node nominal voltage annual average wind speed at wind turbine hub 1 INTRODUCTION The total operating wind power capacity in the world has increased from approximately 2000 MW in 1990 to well over MW by end of The development has created a booming wind power industry. Continuous rapid growth is expected indicating MW of operating wind power capacity by year Driving forces for this development are environmental concerns, Kyoto targets and the improved cost efficiency of new wind farms. Cost efficient utilisation of the wind energy resource requires wind farms to be located at areas with good wind resources. Such areas are often in proximity to a relatively weak grid that may represent technical constraints for exploiting the wind resources. Hence, aiming for cost efficient utilisation of wind energy resources it is a challenge to find ways to overcome the technical constraints. Technical constraints in relation to wind power in weak grids may be associated with limited thermal capacity in parts of the grid and the effect that wind power has on voltage quality and stability. Indeed, if the weak grid is a small island grid, frequency control could also be a constraint. In this paper however, the weak grid is assumed to be part of a large interconnected power system where wind power will not have a significant effect on the frequency control. Hence, the focus of this paper is on issues related to thermal capacity, voltage quality and stability. The main points we are making are: - The development of IEC [1] provides basis for detailed assessment of the impact of wind turbines on voltage quality. This make previously used rule of thumbs unnecessary, and opens for increased utilisation of wind energy in weak grids. - Possible voltage quality problems due to a small wind farm may be overcome simply by selecting an appropriate wind turbine type, and/or by adjusting wind turbine control parameters. - Thermal capacity and voltage stability constraints related to a large wind farm call for innovative solutions involving e.g. dedicated system protection and dynamic compensation of reactive power. - The solutions considered may be more economic than installation of new lines. Voltage quality issues are addressed in section 2, whereas issues related to thermal capacity and voltage stability are addressed in section 3. In both sections we include examples illustrating both possible constraints and solutions. Conclusions are drawn in section 4. 2 VOLTAGE QUALITY Throughout this section we will refer to the EN [2] to characterise the voltage quality that any customer can expect under normal operating conditions. We consider slow voltage variations, i.e. voltage variations measured as 10-minute-mean RMS values, flicker, voltage dips and harmonic voltage, and describe how

3 wind power may influence these characteristics. Assessment is made according to [1] were applicable. For illustration, we use the example network and wind turbine specifications given in Figure 1. The wind turbines are of a conventional design, operating at fixed speed and using stall control for power limitation at high wind speeds. Each wind turbine is equipped with power electronics that limits the in-rush current to the induction generator during start, and capacitors that are switched to maintain cos(ϕ) = 1,0 during operation. Wind turbine: P n = 750 kw cos(ϕ) = 1,0 U n = 0,69 kv v a = 8,2 m/s c(55,8,2)=10,9 N 10 = 1 N 120 = kv +/-1,5 % P mc = 1,2 P n k f (55)=1,2 k u (55)=1, Sum max load: 7,4 MW; 1,5 Mvar Sum min load: 2,2 MW; 0,5 Mvar Wind farm PCC: U n = 22 kv S k = 37,6 MVA ψ k = 55 deg E Pst = 0,7 E Plt = 0,5 Figure 1: Example network with small wind farm. 2.1 Slow Voltage Variations Load-flow analyses may be conducted to assess the slow voltage variations. Figure 2 shows results for two load situations that for the example specifications give the maximum and minimum voltage levels on the medium voltage (MV) line. Node 1 denotes the MV node at the high voltage (HV) transformer that for simplicity in this example is set to be constant = 1,0 pu. The five 750 kw wind turbines constituting a wind farm are connected at nodes 54-58, whereas all other nodes connect consumers via low voltage (LV) transformers and LV lines. Voltage (pu) min load/max wind max load/0 wind Node number Figure 2: Result of example load-flow analysis. The voltage at a LV consumer is given by: U LV = U N U U (1) MV T T LV For this example system at maximum load, U T = 2 % and U LV = 5 %, whereas the voltage drop is negligible at minimum load. This indicates that the tap changer for the transformer at node 53 must be set to -5 % for achieving a minimum voltage at LV > 0,90 pu. Assuming the tap-changer to be fixed to -5 %, the maximum voltage at LV would then be 1,09 pu. If the wind farm were expanded with more wind turbines of the same type, the maximum voltage would further increase. According to [2] the slow voltage variations shall be within ± 10 % of U n during 95 % of a week. In addition, for low voltage only, the slow voltage variations shall always be within -15/+10 % of U n. Hence, for the example system, slow voltage variations may be a constraint for further expansion of the wind farm. This constraint may however easily be overcome e.g. by adjusting the cos(ϕ) of the wind turbines. A modest reduction of the cos(ϕ) from unity to 0,98 (inductive) reduces the maximum voltage by 1,5 %, and makes room for more wind power. Actually, the wind farm may expand to a total of eight 750 kw wind turbines operated at cos(ϕ) = 0,98 before slow voltage variations again become a constraint for further expansion. We have made a simplification disregarding the deadband of the voltage regulation at the HV-transformer. If we had taken this into account, the obtained minimum and maximum voltages would be slightly different. Further, possible uncertainties in estimates of minimum and maximum load levels could impose safety margins. None of this does however change the general analysis result, suggesting that a possible slow voltage variation constraint may be counteracted on by adjusting the cos(ϕ) of the wind turbines. One argument against is that a reduced cos(ϕ) causes increased network losses. This implies that cos(ϕ) regulation should be used with care, and that alternative options should be assessed. Examples of alternative options are grid reinforcement by installation of new lines and voltage dependent reduction of wind power production, see e.g. Tande [3]. 2.2 Flicker According to [2] the long-term flicker severity shall be 1 during 95 % of a week. To ensure this, each source of flicker connected to the network can only be allowed a limited contribution, e.g. as for the example network E Pst = 0,7 and E Plt = 0,5 at the point of common coupling (PCC) of the wind farm. At other networks, different values may be found using IEC [4] as a guide. Following the recommendations given in [1], the flicker emission from a single wind turbine or wind farm may be assessed. Procedures are given both for assessing flicker emission due to starts and due to continuous operation. The procedure for assessing flicker emission due to starts

4 assumes that each wind turbine is characterised by a flicker step factor, k f (ψ k ), being a normalised measure of the flicker emission due to a single worst-case start. Further, the procedure assumes that for each wind turbine information is also given on the maximum number of starts, N 10 and N 120, that can be expected within a 10 minute and 2 hour period respectively. Based on these characteristics, the maximum expected flicker emission due to starts from a single wind turbine or wind farm can be calculated: 18 Pst = N S k i= 1 8 Plt = N S k i= 1 3, ( k ( ψ S ) 10,i f,i k ) n,i 3, ( k ( ψ S ) 120,i f,i k ) n,i 0, , 31 2 (2) (3) For deduction of the above equations, reference is given to [1]. For the example specifications we get P st = 0,71 and P lt = 0,68, and exceeding the assumed example limits. Hence, the flicker emission due to starts may be a constraint for operation of the example wind farm. This constraint may however be overcome quite easily by using another type of wind turbine with a smaller k f, basically a pitch regulated or a (semi-)variable speed type. Another alternative is to ensure that only a reduced number of wind turbines are allowed to start within the same 10- minute and 2-hour period. The latter involves altering the control system settings of the wind turbine to a smaller value for N 120, and introducing a wind farm control system that allows only a reduced number of wind turbines to start within the same 10-minute period, in effect altering in (2). The procedure for assessing flicker emission due to continuous operation assumes that each wind turbine is characterised by a flicker coefficient, c(ψ k, v a ) being a normalised measure of the maximum expected flicker emission during continuous operation of the wind turbine. To find the flicker emission from a single wind turbine, the flicker coefficient with the relevant ψ k and v a is simply multiplied by S n /S k, whereas the emission from a wind farm can be found by: P st 1 = Plt = S k i= 1 ( c ( ψ,v ) S ) i k a 0, 5 2 n,i P st = P lt in (4) because it is probable that conditions during the short-term period persist over the long-term period. Further (4) assumes that the maximum power levels between wind turbines are uncorrelated. At special condition however, wind turbines in a wind farm may synchronise causing power fluctuations to coincide. (4) would then underestimate the flicker emission. This is assessed in Tande et al [5], concluding that for common (4) conditions however, (4) will provide a good estimate. For the example specifications we get P st = P lt = 0,49, which is just within the assumed example limit E Plt = 0,5. If the wind farm were expanded with more wind turbines of the same type, the flicker emission would further increase above the acceptable limit. Hence, for the example system, flicker emission due to continuous operation may be a constraint for further expansion of the wind farm. To overcome this constraint, the straightforward approach is to select a different wind turbine type that has a smaller c value. First of all, c = 10,9 is rather high for a fixed speed, stall regulated wind turbine, so this value should not be taken as typical for this types of wind turbines. Certainly, a (semi-)variable speed wind turbine would yield a much lower c value, whereas a fixed speed, pitch regulated type could actually yield a higher value of c. 2.3 Voltage Dips According to [2], a voltage dip is a sudden reduction of the voltage to a value 0,01 and 0,90 pu followed by a voltage recovery after a short period of time, conventionally 1 ms to 1 minute. The expected number of voltage dips during a year may vary from a few tens to one thousand. Start-up of a wind turbine may cause a sudden reduction of the voltage followed by a voltage recovery after a few seconds. Assuming that each wind turbine is characterised by a voltage change factor k u (ψ k ), the sudden voltage reduction may be assessed according to [1]. S n 100 ku ( ψ k (5) S k d = ) As more wind turbines in a wind farm are unlikely to start-up at the exact same time, (5) is not a function of the number of wind turbines as (2), (3) and (4). For the example wind turbines, we find that d = 3,0 %. This sudden voltage reduction is in most cases acceptable, especially considering that this would imply a voltage less than 0,90 pu, i.e. a voltage dip, only for starts coinciding with high load at the network. Further, as (5) is not a function of the number of wind turbines in the farm, we can conclude that for the example system, voltage dips are not a constraint for further expansion of the wind farm. 2.4 Harmonic Voltage [2] states limits for individual harmonic voltages up to the order of 25, and that the total harmonic distortion of the voltage, calculated up to the order of 40, shall be 8 %. To ensure this, only a limited emission of harmonic currents can be allowed. The limits depend on network specifications, and can be found using IEC [6] as a guide.

5 A wind turbine with an induction generator directly connected to the grid without an intervening power electronic converter is not expected to distort the voltage waveform. Power electronics applied for soft-start may give a short-duration burst of higher order harmonic currents, though the duration and magnitude of these are in general expected to be so small that they can be accepted without any further assessment. So, for the example system with fixed speed wind turbines, emission limits for harmonics is not a constraint. If however we had considered variable speed wind turbines using power electronic converters, these should be assessed. Thyristor-based converters are expected to emit harmonic currents that may influence the harmonic voltages for which limits are given in [2]. Such converters are however rarely used in new wind turbines. Rather, the converters are transistor-based, and operated at switching frequencies above 3 khz. As a consequence, the impact of such new wind turbines on the voltage waveform is commonly negligible, and not a constraint for wind power development. 3 THERMAL CAPACITY AND STABILITY This section discusses challenges and opportunities arising when a large wind farm is connected in an area distant from the main transmission grid. Consider the following case. A large wind farm is to be connected at the remote end of a wide regional network that also connects nearby consumers (distribution grids) and some other local generation. The regional grid is connected to the main transmission grid via one or two long tie-lines. The example network is illustrated in Figure 3. Long distances and limited transmission capacity in the regional network may lead to thermal overload Main transmission grid (300 kv) Bus 2 Bus 1 66 kv Distribution grid Local load (L1) ~ Local generation (G1) Bus 3 Regional distribution grid 132 kv 22 kv ~ 690 V Figure 3: Example network with large wind farm. SVC Wind farm MW and voltage stability problems during critical operating conditions. Two examples are used to describe the relevant problems, and to illustrate possible solutions that enable secure operation of large wind farms in the remote areas. 3.1 Example 1 This case relates to the example network shown in Figure 3. Normal considerations with respect to power system security require two separate feeders to the local distribution grid. Thus, in normal operation when both lines (bus1-bus2 and bus1-bus3) are in service, the grid is strong. With modest wind power penetration, the system can handle any single contingency, i.e. outage of any line, transformer or local generation, without loss of supply to any consumer load. Consider an outage of one of the two feeding 132 kv lines as the contingency case, and an operating situation with rather low local load and low local generation. In this case high wind power penetration may cause thermal overload on the remaining feeder (bus1-bus2) and also a risk of voltage collapse because of the increased need for reactive support on the weakened transmission. Figure 4 illustrates how the problem results in a serious voltage drop when the wind power generation exceeds 100 MW Bus Wind farm Wind power injected (MW) Figure 4: Voltage dependency of injected wind power. Voltage (kv) This problem, which would result in a total voltage collapse if the wind power generation exceeded 140 MW, can be solved by installation of a dedicated system protection scheme. A robust and inexpensive scheme could be designed based on monitoring of line currents, voltage drops and breaker operations. When current limits are exceeded or a line outage is detected, a signal is sent to automatically reduce the wind power generation or to disconnect a necessary number of wind turbines. 3.2 Example 2 Regional networks are not always operated according to the (N-1) security criterion. Consider the same case except that the second feeder (bus1-bus3) is not present. Again, with modest wind power penetration an acceptable level of security is maintained because the

6 local generation (G1 + Wind) is able to supply the main parts of the local load in case of a critical contingency. In this case there are two main challenges. High wind power penetration will in normal operation lead to voltage stability problems and thermal overload because of the limited transmission capacity. This is basically the same problem as the contingency case in section 3.1. Since this is now a problem in normal operation, a different solution is required to be able to utilise the full wind power capacity. As illustrated in Figure 3, a possible solution is to install dynamic reactive compensators (e.g. an SVC unit) for continuous voltage control. Figure 5 shows that by applying SVC units of various ratings, it is possible to increase the wind power installation up to above 160 MW before the voltage stability limits are reached. The second problem is when a critical contingency occurs, and the regional network is isolated from the main interconnection. In such a case the isolated network may have a large but varying surplus of power due to the wind generation. Application of energy storage and automatic frequency control of the wind turbines may be necessary in order to maintain a continuous supply of power in this situation. Phase voltage (kv) Operating point at rated Wind power production SN = 80 Mvar SN = 90 Mvar SN = 100 Mvar SN = 120 Mvar SN = 140 Mvar Wind power generation (MW) Figure 5: Voltage stability limits. 4 CONCLUSION Until the development of [1], there was no standard procedure for characterising the power quality of a wind turbine. Basically, the manufacturer provided rated data only, giving little basis for detailed assessment of the impact of wind turbines on voltage quality. Therefore, simplified rules were often applied, e.g. requiring the voltage increment due to a wind turbine installation to be less than 1 %. Application of this 1 % rule of thumb on our example network in Figure 1 would in fact allow only one 750 kw wind turbine. As demonstrated in section 2 however, [1] gives basis for detailed assessment allowing substantially more wind power to be connected. Further, section 2 demonstrates that possible voltage quality problems due to a small wind farm may be overcome simply by selecting an appropriate wind turbine type, and/or by adjusting wind turbine control parameters. Section 3 shows that assessment of thermal capacity and voltage stability constraints related to a large wind farm calls for additional analyses and innovative solutions. These are pinpointed by examples enabling increased penetration of wind power in weak grids. We have not made any detailed assessment of the costsavings associated with the suggested solutions compared to the alternative of conventional grid reinforcement by installation of new lines. This is because such numbers will be very case specific. We suspect however that for a majority of projects, the solutions considered will be more economic than installation of new lines. ACKNOWLEDGEMENTS This paper is to a large degree based on work carried out in conjunction with the projects Wind power in distribution grids and Large scale integration of wind power financed by the Norwegian Research Council and other Norwegian entities. Figure 4 and Figure 5 are courtesy of our good colleagues Trond Toftevaag and Magni Tor Palsson. REFERENCES [1] IEC (2001) Measurements and assessment of power quality characteristics of grid connected wind turbines. FDIS. [2] EN (1995) Voltage characteristics of electricity supplied by public distribution systems. [3] Tande JOG (2000) Exploitation of wind-energy resources in proximity to weak electric grids. Applied Energy 65 pp [4] IEC (1996) EMC - Part 3: Limits Section 7: Assessment of emission limits for fluctuating loads in MV and HV power systems - Basic EMC publication. (Technical report) [5] Tande JOG, Relakis G, Alejandro OAM (2000) Synchronisation of wind turbines. Proc. of Wind Power for the 21st Century, Sept. 2000, Kassel, Germany. [6] IEC (1996) EMC - Part 3: Limits - Section 6: Assessment of emission limits for distorting loads in MV and HV power systems - Basic EMC publication. (Technical report)

Large-scale Wind Power Integration and Voltage Stability Limits in Regional Networks

Large-scale Wind Power Integration and Voltage Stability Limits in Regional Networks Large-scale Wind Power Integration and Voltage Stability Limits in Regional Networks Magni Þ. Pálsson, Trond Toftevaag, Member IEEE, Kjetil Uhlen, Member IEEE, John Olav Giæver Tande SINTEF Energy Research

More information

ELECTRIC ARC FURNACE WITH STATIC VAR COMPENSATOR PLANNING AND OPERATIONAL EXPERIENCE

ELECTRIC ARC FURNACE WITH STATIC VAR COMPENSATOR PLANNING AND OPERATIONAL EXPERIENCE GERHARD HACKL 1 HERWIG RENNER 2 MANFRED KRASNITZER 3 CHRISTIAN HOFBAUER 1 ELECTRIC ARC FURNACE WITH STATIC VAR COMPENSATOR PLANNING AND OPERATIONAL EXPERIENCE Abstract The paper describes the process of

More information

Power Flow Control Scheme for Wind Energy Conversion System

Power Flow Control Scheme for Wind Energy Conversion System Vol.2, Issue.3, May-June 2012 pp-644-648 ISSN: 2249-6645 Power Flow Control Scheme for Wind Energy Conversion System using FACTS Controller R. Vibin 1, K. Malarvizhi 2 1 PG Scholar, Department of EEE,

More information

WIND ENERGY INTEGRATION IMPACT ON POWER QUALITY IN ESTONIA

WIND ENERGY INTEGRATION IMPACT ON POWER QUALITY IN ESTONIA WIND ENERGY INTEGRATION IMPACT ON POWER QUALITY IN ESTONIA Hannes Agabus 1, Ivo Palu 2 1 Estonian National Gird (Estonian TSO), grid analyst, doctoral student, M.Sc, Address: Kadaka tee 42, Tallinn 12915,

More information

Network Interconnection Studies of Distributed Generation

Network Interconnection Studies of Distributed Generation Network Interconnection Studies of Distributed Generation Anna Kulmala, Kari Mäki, Sami Repo and Pertti Järventausta Tampere University of Technology, Department of Electrical Energy Engineering, P.O.

More information

UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES

UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES Guideline 1 (11) Contents 1 INTRODUCTION... 2 2 PRINCIPLES OF THE SUPPLY OF REACTIVE POWER... 2 2.1 Supply point

More information

IMPACT OF SMALL PRODUCERS ON POWER QUALITY IN DISTRIBUTION GRIDS BASED ON ELEKTRILEVI OÜ GRID

IMPACT OF SMALL PRODUCERS ON POWER QUALITY IN DISTRIBUTION GRIDS BASED ON ELEKTRILEVI OÜ GRID IMPACT OF SMALL PRODUCERS ON POWER QUALITY IN DISTRIBUTION GRIDS BASED ON ELEKTRILEVI OÜ GRID Rasmus ARMAS Elektrilevi OÜ - Estonia Rasmus.Armas@elektrilevi.ee ABSTRACT The amount of distributed generation

More information

Electrical Networks and Integration of Wind Energy

Electrical Networks and Integration of Wind Energy Electrical Networks and Content: 1. Wind energy in Germany Dr. Boris Valov Institut für Solare Energieversorgungstechnik - ISET Division Engineering and Power Electronics 2. Change in operation of electrical

More information

Distribution Code Definitions

Distribution Code Definitions Distribution Code Definitions Version 5 Approved September 2007 Comments to this document can be forwarded to: RSA Grid Code Secretariat Attention: Mr. Bernard Magoro Eskom, Transmission System Operator

More information

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System Primary Interest Groups Balancing Authorities (BAs) Transmission Operators (TOPs) Generator Operators

More information

POTOMAC ELECTRIC POWER COMPANY

POTOMAC ELECTRIC POWER COMPANY POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission

More information

WIND TURBINE PLANT CAPABILITIES REPORT

WIND TURBINE PLANT CAPABILITIES REPORT WIND TURBINE PLANT CAPABILITIES REPORT 2013 Wind Integration Studies Published by AEMO Australian Energy Market Operator ABN 94 072 010 327 Copyright 2013 AEMO AEMO 2013 WIND TURBINE PLANT CAPABILITIES

More information

Mitigation of Voltage Fluctuations in Power System Using STATCOM

Mitigation of Voltage Fluctuations in Power System Using STATCOM RESEARCH ARTICLE OPEN ACCESS Mitigation of Voltage Fluctuations in Power System Using STATCOM M. Venkatesh & Ramakrishna Raghutu Assistant Professors, Dept. of Electrical & Electronics Engineering, GMRIT,

More information

Distribution System Design General Requirements

Distribution System Design General Requirements Electricity Policy Document 279 Issue 7 September 2017 Distribution System Design General Requirements Contents 1 Introduction 2 Scope 3 Definitions 4 General Requirements 5 Documents Referenced 6 Keywords

More information

Connection of generation plant to distribution networks. Guidance on completing the application form

Connection of generation plant to distribution networks. Guidance on completing the application form Connection of generation plant to distribution networks It is possible to connect almost any generation plant to the distribution network and in order for the connection to meet the requirements of a new

More information

International ejournals

International ejournals ISSN 2249 5460 Available online at www.internationalejournals.com International ejournals International Journal of Mathematical Sciences, Technology and Humanities 21 (2011) 205 212 ENERGY CONTROL CENTER

More information

Technical Requirements for Distributed Generation Connection

Technical Requirements for Distributed Generation Connection Technical Requirements for Distributed Generation Connection Distributed Generation Connection Requirements SECTION 1: INTRODUCTION 1.1 General Purpose This document defines the requirements for connecting

More information

Power quality improvement by using STATCOM control scheme in wind energy generation interface to grid

Power quality improvement by using STATCOM control scheme in wind energy generation interface to grid IOP Conference Series: Earth and Environmental Science PAPER OPEN ACCESS Power quality improvement by using STATCOM control scheme in wind energy generation interface to grid To cite this article: Sheeraz

More information

AORC Technical meeting 2014

AORC Technical meeting 2014 http : //www.cigre.org C5-1036 AORC Technical meeting 2014 Solar PV Rooftop System Connection to MEA s Distribution Network: Technic and Economic Aspects Tosak Thasananutariya Metropolitan Electricity

More information

Contribution of PV Power Plants to Flicker Severity in Power Distribution Grids

Contribution of PV Power Plants to Flicker Severity in Power Distribution Grids Contribution of PV Power Plants to Flicker Severity in Power Distribution Grids Denisa G. Rusinaru, Leonardo G. Manescu, Adelaida, M. Duinea and Cristian C. Bratu Abstract This paper presents some results

More information

Wind farm models and control strategies

Wind farm models and control strategies Risø-R-1464(EN) Wind farm models and control strategies Poul Sørensen, Anca D. Hansen, Florin Iov, Frede Blaabjerg and Martin H. Donovan Risø National Laboratory Roskilde Denmark August 2005 Author: Poul

More information

Impacts of the Decentralized Wind Energy Resources on the Grid

Impacts of the Decentralized Wind Energy Resources on the Grid 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2013 Grid of the Future Symposium Impacts of the Decentralized Wind Energy Resources on the Grid Babak Enayati, PhD, Senior

More information

Power Quality Measurement and Evaluation of a Wind Farm Connected to Distribution Grid

Power Quality Measurement and Evaluation of a Wind Farm Connected to Distribution Grid Available online at www.sciencedirect.com ScienceDirect Procedia - Social and Behavioral Sciences 195 ( 2015 ) 2370 2375 World Conference on Technology, Innovation and Entrepreneurship Power Quality Measurement

More information

Grid Connection and Power Quality Optimization of Wind Power Plants

Grid Connection and Power Quality Optimization of Wind Power Plants Grid Connection and Power Quality Optimization of Wind Power Plants Fikri Baris UZUNLAR 1, Onder GULER 2, Ozcan KALENDERLI 3 1, 2 Istanbul Technical University, Energy Institute, Istanbul, Turkey barisuzunlar@hotmail.com,

More information

A*STAR Funded IEDS Project - Microgrid Energy Management System. by H B GOOI

A*STAR Funded IEDS Project - Microgrid Energy Management System. by H B GOOI A*STAR Funded IEDS Project - Microgrid Energy Management System by H B GOOI 4 Aug 2009 Outline Introduction - Distributed Generators and Microgrids Proposed Microgrid Energy Management System (MEMS) MEMS

More information

Power Quality Assessment of Large Motor Starting and Loading for the Integrated Steel-Making Cogeneration Facility

Power Quality Assessment of Large Motor Starting and Loading for the Integrated Steel-Making Cogeneration Facility Power Quality ssessment of Large Motor Starting and Loading for the Integrated Steel-Making Cogeneration Facility Cheng-Ting Hsu, Member, IEEE Department of Electrical Engineering Southern Taiwan University

More information

The Impact of Wind Generation on System Services in Ireland

The Impact of Wind Generation on System Services in Ireland The Impact of Wind Generation on System Services in Ireland Renewable Energies, an Opportunity and Challenge for Electricity Systems October 8th 2009 Dr Ivan Dudurych, EirGrid 4000 600 3600 480 Load, MW

More information

Standard TPL Transmission System Planning Performance Requirements

Standard TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

Facility Interconnection Requirements

Facility Interconnection Requirements Facility Interconnection Effective 1/1/2016 1. Purpose Facility Interconnection Facility Interconnection (FAC-001-2) To avoid adverse impacts on the reliability of the Bulk Electric System (BES), RPU documents

More information

The Power Quality of Wind Turbines

The Power Quality of Wind Turbines THESIS FOR THE DEGREE OF DOCTOR OF PHILOSOPHY The Power Quality of Wind Turbines ÅKE LARSSON Department of Electric Power Engineering CHALMERS UNIVERSITY OF TECHNOLOGY Göteborg, Sweden 2000 The Power Quality

More information

Value-based Transmission Investment and Operations. Marija Ilic Invited Panel, IEEE PES 2014 Washington DC

Value-based Transmission Investment and Operations. Marija Ilic Invited Panel, IEEE PES 2014 Washington DC Value-based Transmission Investment and Operations Marija Ilic milic@ece.cmu.edu Invited Panel, IEEE PES 2014 Washington DC 2 Outline The evolving role of on-line T&D management Basic definition of an

More information

CSIRO CLUSTER PROJECT #3

CSIRO CLUSTER PROJECT #3 CSIRO CLUSTER PROJECT #3 Milestone 5 Optimal Sitting and Dispatch of Distributed generation A software development and simulation of generation and cost optimised controller By Dilan Jayaweera, Syed Islam,

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM

ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM January 2017 PRESENTED BY JENNY RIESZ SLIDE 1 AGENDA 1. Introduction to the NEM 2. Future Power System Security Program 3. Identifying

More information

POWER SYSTEM STABILITY GUIDELINES

POWER SYSTEM STABILITY GUIDELINES PREPARED BY: DOCUMENT REF: Planning PSSG-02 VERSION: 1.0 DATE: 25 May 2012 FINAL Final Matt Zema CEO Date 25/ 5 /2012 Version Release History VERSION DATE AUTHOR PEER REVIEW APPROVED COMMENTS 1.0 25/5/12

More information

CERTS Microgrids. Tom Jahns Professor, University of Wisconsin-Madison. LPPC Rates Roundtable May 21, 2013

CERTS Microgrids. Tom Jahns Professor, University of Wisconsin-Madison. LPPC Rates Roundtable May 21, 2013 CERTS Microgrids Tom Jahns Professor, University of Wisconsin-Madison LPPC Rates Roundtable May 21, 2013 Wisconsin Energy Institute WEI WEI provides linkage among all organizations associated with energy

More information

Wind Energy Conversion Using Shunt Active Power Filter

Wind Energy Conversion Using Shunt Active Power Filter Quatrième onférence Internationale sur le Génie Electrique IGE 1, 34 Novembre 21, Université de echar, lgérie Wind Energy onversion Using Shunt ctive Power Filter Samira Dib, rahim Ferdi, hellali enachaiba

More information

The Effect of the Volt/Var Control of Photovoltaic Systems on the Time-Series Steady-State Analysis of a Distribution Network

The Effect of the Volt/Var Control of Photovoltaic Systems on the Time-Series Steady-State Analysis of a Distribution Network The Effect of the Volt/Var Control of Photovoltaic Systems on the Time-Series Steady-State Analysis of a Distribution Network Insu Kim, Ronald G. Harley, and Raeey Regassa Georgia Institute of Technology,

More information

TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY

TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY 1 1. Summary When one part of the grid is facing security of supply risk where local generation in one region of the grid is not enough for

More information

Power Control for Wind Turbines in Weak Grids: Project summary

Power Control for Wind Turbines in Weak Grids: Project summary Risø-R-1117(EN) Power Control for Wind Turbines in Weak Grids: Project summary Henrik Bindner (Ed.) Risø National Laboratory, Roskilde March 1999 Abstract In many parts of the world and certainly in Europe

More information

Grid Connection and Remote Control for the Horns Rev 150 MW Offshore Wind Farm in Denmark

Grid Connection and Remote Control for the Horns Rev 150 MW Offshore Wind Farm in Denmark 1 Grid Connection and Remote Control for the Horns Rev 150 MW Offshore Wind Farm in Denmark Peter Christiansen, Senior Eng., B.Sc., Elec.Eng. 1), Knud K. Jørgensen, Senior Eng., M.Sc., Elec.Eng. 1) and

More information

Planification du réseau, exploitation et gestion : nouvelles approches dans la recherche

Planification du réseau, exploitation et gestion : nouvelles approches dans la recherche Planification du réseau, exploitation et gestion : nouvelles approches dans la recherche Prof. Mario Paolone Distributed Electrical Systems Laboratory L e s d é fis de la m ise e n œ uvre de la s t r a

More information

Joint DSO TSO reactive power management for an HV system considering MV systems support

Joint DSO TSO reactive power management for an HV system considering MV systems support 24th International Conference & Exhibition on Electricity Distribution (CIRED) 12-15 June 2017 Session 3: Operation, control and protection Joint DSO TSO reactive power management for an HV system considering

More information

SMART GRID SCENARIO. Marina Egea,

SMART GRID SCENARIO. Marina Egea, SMART GRID SCENARIO Marina Egea, What is Smart Grid is an electricity network that can integrate in a costefficient manner the behaviour and actions of all users connected to it - generators, consumers

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...

More information

Modeling of the Dynamic Behavior of the Island Power System of Cyprus

Modeling of the Dynamic Behavior of the Island Power System of Cyprus Transmission System Operator CYPRUS Modeling of the Dynamic Behavior of the Island Power System of Cyprus Andreas G. Petoussis Stavros Stavrinos Session 6: Modeling and Power Quality Friday, 24 September

More information

Comparison of Variable Speed Wind Turbine Control Strategies

Comparison of Variable Speed Wind Turbine Control Strategies Comparison of Variable Speed Wind Turbine Control Strategies S. Arnaltes Department of Electrical Engineering Escuela Politécnica Superior, Universidad Carlos III de Madrid Avda. Universidad 30, 8911 Leganés

More information

Gas Natural Fenosa s Experiences on Renewable Energy Integration

Gas Natural Fenosa s Experiences on Renewable Energy Integration Gas Natural Fenosa s Experiences on Renewable Energy Integration Julio Gonzalo García Asset Management 17 th October 2013 Outline 1.About us 2.Spanish Regulation 3.R+D projects 4.Conclusions 2 About us

More information

Impact study of PV integration in Bornholm power system

Impact study of PV integration in Bornholm power system Downloaded from orbit.dtu.dk on: Jan 31, 2018 Impact study of PV integration in Bornholm power system Korompili, Asimenia; Zimmermann, Jakob Kjær; Wu, Qiuwei Publication date: 2014 Document Version Publisher's

More information

COST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED TRANSMISSION SERVICES

COST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED TRANSMISSION SERVICES COST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED PREPARED BY: Network Development VERSION: 2.0 RELEASE DATE: 30 May 2012 Version Release History Version Date By Changes 1.0 6 Oct 11 Transmission

More information

Lebanese National Renewable Energy Grid Code

Lebanese National Renewable Energy Grid Code Technical Study and Development of Renewable Energy Grid Interconnection Guidelines for Lebanon Lebanese National Renewable Energy Grid Code ZAKARIA RAMMAL National Energy Consultant September 23 rd 2016

More information

DISTRIBUTION GRID PLANNING CONSIDERING SMART GRID TECHNOLOGIES

DISTRIBUTION GRID PLANNING CONSIDERING SMART GRID TECHNOLOGIES DISRIBUION GRID PLANNING CONSIDERING SMAR GRID ECHNOLOGIES Baktash NASIRI, Christian WAGNER, Ulf HÄGER and Christian REHANZ Institute of Energy Systems, Energy Efficiency and Energy Economics (ie³) U Dortmund

More information

7. Electrical Facility Ratings

7. Electrical Facility Ratings 7. Electrical Facility Ratings 7.1 Accredited Net Generating Capacity This Section shall be used to determine the annual and seasonal accredited net generating capacity of generators in calculating the

More information

Master Thesis Department of Electrical Engineering. The Effect of a Short- Circuit Current in a High Voltage Installation With a Synchronous Machine.

Master Thesis Department of Electrical Engineering. The Effect of a Short- Circuit Current in a High Voltage Installation With a Synchronous Machine. 44 The Effect of a Short- Circuit Current in a High Voltage Installation With a Synchronous Machine. Background Short circuit in a power plant leads to large short-circuit currents and causes large mechanical

More information

Medium Voltage UPS Solutions - When and Why? Frank Herbener, Piller Group GmbH, Germany

Medium Voltage UPS Solutions - When and Why? Frank Herbener, Piller Group GmbH, Germany Medium Voltage UPS Solutions - When and Why? Frank Herbener, Piller Group GmbH, Frank.Herbener@Piller.com, Germany 1 Contents 1 Scope 3 2 Power Demand and Distribution in today s Mission Critical Applications

More information

La regulación del incierto futuro de los sistemas eléctricos

La regulación del incierto futuro de los sistemas eléctricos La regulación del incierto futuro de los sistemas eléctricos Foro XM-2017 El futuro de la energía eléctrica en Colombia 25 de mayo, Cartagena, Colombia Carlos Batlle https://energy.mit.edu/profile/carlos-batlle

More information

Outcomes and recommendations GREDOR

Outcomes and recommendations GREDOR Outcomes and recommendations GREDOR The increase of the capacity of renewable generation, the evolution of consumption modes such as electrical vehicles, and the changes in the electricity markets sector

More information

GRID CODE FOR ISOLATED SYSTEMS

GRID CODE FOR ISOLATED SYSTEMS 1 GRID CODE FOR ISOLATED SYSTEMS Susana Ludovino REDE ELÉCTRICA NACIONAL, S.A., 1749-061 Lisboa, PORTUGAL (e-mail: susana.ludovino@ren) Abstract The aim of this study is to verify the application of an

More information

Hierarchical Frequency Control Scheme for Islanded Multi-Microgrids Operation

Hierarchical Frequency Control Scheme for Islanded Multi-Microgrids Operation Hierarchical Frequency Control Scheme for Islanded Multi-Microgrids Operation Nuno José Gil, and J. A. Peças Lopes, Senior Member, IEEE Abstract This paper presents a new hierarchical approach to deal

More information

Consultation on Connecting Further Generation in Northern Ireland. Call for Evidence

Consultation on Connecting Further Generation in Northern Ireland. Call for Evidence Consultation on Connecting Further Generation in Northern Ireland Call for Evidence 12 Table of Contents 1 Executive Summary... 3 2 Introduction... 6 2.1 Purpose of this Paper... 6 3 Alternative Connection

More information

EVALUATING INVESTMENT DEFERRAL BY INCORPORATING DISTRIBUTED GENERATION IN DISTRIBUTION NETWORK PLANNING

EVALUATING INVESTMENT DEFERRAL BY INCORPORATING DISTRIBUTED GENERATION IN DISTRIBUTION NETWORK PLANNING EVALUATING INVESTMENT DEFERRAL BY INCORPORATING DISTRIBUTED GENERATION IN DISTRIBUTION NETWORK PLANNING D. T-C. Wang d.wang@ed.ac.uk L. F. Ochoa luis_ochoa@ieee.org G. P. Harrison gareth.harrison@ed.ac.uk

More information

Dispatching Variable Generation Resources

Dispatching Variable Generation Resources Dispatching Variable Generation Resources A Discussion Paper for Stakeholder Engagement 91 (Renewable Integration) Table of Contents Introduction... 3 IESO Dispatch Processes... 5 Registration... 5 Dispatch

More information

EDF and Integration of Distributed Energy Resources

EDF and Integration of Distributed Energy Resources IEEE Power Engineering Society Tuesday, June 20, 2006. Montreal EDF and Integration of Distributed Energy Resources Bruno Meyer (presenter) Director Power Systems Technology and Economics Yves Bamberger,

More information

TUV Rheinland of N.A.

TUV Rheinland of N.A. TUV Rheinland of N.A. Renewables Energy Division Topic: Green Power Compliance Speaker: Robert Holt, SFr Regional Sales Manager Renewable Energies Division Smart Grid Background Situation: Utility demand

More information

ANALYSIS OF THE BEHAVIOR FOR REACTIVE POWER COMPENSATION USING SVC CONTROLLED HYBRID SOLAR/WIND POWER GENERATING SYSTEMS

ANALYSIS OF THE BEHAVIOR FOR REACTIVE POWER COMPENSATION USING SVC CONTROLLED HYBRID SOLAR/WIND POWER GENERATING SYSTEMS ANALYSIS OF THE BEHAVIOR FOR REACTIVE POWER COMPENSATION USING SVC CONTROLLED HYBRID SOLAR/WIND POWER GENERATING SYSTEMS Shadab Shakeel 1, Ameenuddin Ahmed 2 1 Student, M.Tech, 2 Asst. Prof., Department

More information

A Probabilistic Security Criterion for Determination of Power Transfer Limits in a Deregulated Environment

A Probabilistic Security Criterion for Determination of Power Transfer Limits in a Deregulated Environment A Probabilistic Security riterion for Determination of Power Transfer Limits in a Deregulated Environment Kjetil Uhlen and Gerd H. Kjølle, SINTEF Energy Research Gunnar G. Løvås and Øyvind Breidablik,

More information

Economic assessment of distribution network planning: a practical approach

Economic assessment of distribution network planning: a practical approach Economic assessment of distribution network planning: a practical approach Seminar@University of Liège Yannick PHULPIN EDF R&D - EFESE February 8, 2013 1 EDF R&D 08/02/2013 Outline of the talk! Context

More information

Power-Flow Analysis of Large Wind Power Plant Collector Systems With Remote Voltage Control Capability

Power-Flow Analysis of Large Wind Power Plant Collector Systems With Remote Voltage Control Capability 1 Power-Flow Analysis of Large Wind Power Plant Collector Systems With Remote Voltage Control Capability Mohamed Zakaria Kamh and Reza Iravani Abstract This paper presents and develops a new powerflow

More information

Rule 21 Sheet 1 GENERATING FACILITY INTERCONNECTIONS

Rule 21 Sheet 1 GENERATING FACILITY INTERCONNECTIONS Southern California Edison Revised Cal. PUC Sheet No. 31574-E Rosemead, California Cancelling Revised Cal. PUC Sheet No. 30685-E Rule 21 Sheet 1 A. Applicability 1. This Rule describes the Interconnection,

More information

Long Term Planning Method Comparison Considering DG Interconnection

Long Term Planning Method Comparison Considering DG Interconnection Long Term Planning Method Comparison Considering DG Interconnection Marie-Cécile Alvarez Co-authors : G2Elab: Raphaël Caire, Bertrand Raison, Nouredine Hadjsaid EDF R&D: Bogdan Enacheanu, Olivier Devaux

More information

PowrSym4. A Presentation by. Operation Simulation Associates, Inc. February, 2012

PowrSym4. A Presentation by. Operation Simulation Associates, Inc. February, 2012 PowrSym4 A Presentation by Operation Simulation Associates, Inc. February, 2012 1 Presentation Contents History of PowrSym Introduction to OSA The PowrSym3 Model PowrSym4 Enhancements 2 PowrSym Background

More information

POWER CONTROL FOR WIND TURBINES IN WEAK GRIDS

POWER CONTROL FOR WIND TURBINES IN WEAK GRIDS POWER CONTROL FOR WIND TURBINES IN WEAK GRIDS H. Bindner (Ed.) RISØ NATIONAL LABORATORY THE TEST STATION FOR WIND TURBINES Contract JOR-3-CT95-0067 PUBLISHABLE FINAL REPORT January 1996 to December 1998

More information

Integration of Wind Power Plants in The Electric Power System: A Case Study in Piauí Brazil

Integration of Wind Power Plants in The Electric Power System: A Case Study in Piauí Brazil International OPEN ACCESS Journal Of Modern Engineering Research (IJMER) Integration of Wind Power Plants in The Electric Power System: A Case Study in Piauí Brazil Bartolomeu Ferreira Dos Santos Junior

More information

Power control of a photovoltaic system connected to a distribution frid in Vietnam

Power control of a photovoltaic system connected to a distribution frid in Vietnam Power control of a photovoltaic system connected to a distribution frid in Vietnam Xuan Truong Nguyen, Dinh Quang Nguyen, Tung Tran To cite this version: Xuan Truong Nguyen, Dinh Quang Nguyen, Tung Tran.

More information

Generator Assessment & Roles During A Restoration

Generator Assessment & Roles During A Restoration Generator Assessment & Roles During A Restoration PJM State & Member Training Dept. PJM 2015 Objectives Students will be able to: Identify the process and requirements for operating during system restoration

More information

Slide 1. ABB August 23, 2016

Slide 1. ABB August 23, 2016 Claudio Facchin, President Power Grids division, ABB Cigré Keynote Address, Paris, August 21, 2016 Big shift in power Shaping power systems of the future Slide 1 Big shift in power Global challenges Population

More information

Cost and Benefits of Embedded Generation in Ireland

Cost and Benefits of Embedded Generation in Ireland Cost and Benefits of Embedded Generation in Ireland September 2004 Report prepared for Sustainable Energy Ireland by: PB Power CONTENTS 1. Executive Summary 1 1.1 Representative Networks 2 1.2 Costs and

More information

THE GRID CODE FOR THE NIGERIA ELECTRICITY TRANSMISSION SYSTEM

THE GRID CODE FOR THE NIGERIA ELECTRICITY TRANSMISSION SYSTEM THE GRID CODE FOR THE NIGERIA ELECTRICITY TRANSMISSION SYSTEM The Grid Code -Version 01 1 of 131 GRID CODE INDEX PART 1: GENERAL CONDITIONS (GC) 7 1. SECTION: BACKGROUND 7 1.1. Title 7 1.2. New Arrangement

More information

Active Distribution Networks

Active Distribution Networks Active Distribution Networks Nikos Hatziargyriou nh@power.ece.ntua.gr NTUA, Greece Distributed Generation Technologies Examples Advanced Turbines Reciprocating Engines Fuel Cells Photovoltaics Wind Thermally

More information

and gas network infrastructure, whose analysis is the focus of this work, as expanded upon later.

and gas network infrastructure, whose analysis is the focus of this work, as expanded upon later. 3 4 5 6 7 8 9 3 4 5 6 7 8 9 3 4 5 6 Modelling, assessment and Sankey diagrams of integrated electricity-heat-gas networks in multi-vector district energy systems Xuezhi Liu and Pierluigi Mancarella School

More information

Microgrid EPFL Méthodes innovantes issues de la recherche

Microgrid EPFL Méthodes innovantes issues de la recherche Microgrid EPFL Méthodes innovantes issues de la recherche Prof. Mario Paolone Distributed Electrical Systems Laboratory S m a r t Grids S o lutions intelligentes p o ur les s ites e t les v illes Mardi

More information

FAST POWER FACTOR REGULATOR. Computer-14df - xx - 144a INSTRUCTION MANUAL ( M / 00A ) (c) CIRCUTOR S.A.

FAST POWER FACTOR REGULATOR. Computer-14df - xx - 144a INSTRUCTION MANUAL ( M / 00A ) (c) CIRCUTOR S.A. FAST POWER FACTOR REGULATOR Computer-14df - xx - 144a INSTRUCTION MANUAL ( M 981 611 / 00A ) (c) CIRCUTOR S.A. -------- POWER FACTOR REGULATOR COMPUTER- 14f --------- Page 2 POWER FACTOR REGULATOR COMPUTER-

More information

Operating Procedure PURPOSE... 2

Operating Procedure PURPOSE... 2 No. 3100 Table of Contents PURPOSE... 2 1. RESPONSIBILITIES... 2 2. SCOPE/APPLICABILITY... 3 2.1. Background... 3 2.2. Scope/ Applicability... 3 3. PROCEDURE DETAIL... 4 3.1. Acceptable System Performance

More information

Advice on Power Factor and Accuracy of Temperature Dependant Outputs

Advice on Power Factor and Accuracy of Temperature Dependant Outputs Advice on Power Factor and Accuracy of Temperature Dependant Outputs REPORT WP03749-EE-RP-0001 Rev. 1 3 September 2009 Advice on Power Factor and Accuracy of Temperature Dependant Outputs REPORT WP03749-EE-RP-0001

More information

Distribution Network Planning for Mumbai

Distribution Network Planning for Mumbai Newsletter Issue 98 January 2006 Distribution Network Planning for Mumbai Carsten Böse Project Manager Siemens AG, PTD SE PT carsten.boese@siemens.com Introduction The Indian utility Reliance Energy Ltd.

More information

IMP/001/914 Code of Practice for the Economic Development of the 132kV System

IMP/001/914 Code of Practice for the Economic Development of the 132kV System Version:- 3.0 Date of Issue:- September 2015 Page 1 of 36 IMP/001/914 Code of Practice for the Economic Development of the 132kV System 1 Purpose The purpose of this document is to state Northern Powergrid

More information

Multi-objective reactive power support from wind farms for network performance enhancement

Multi-objective reactive power support from wind farms for network performance enhancement University of Wollongong Research Online Faculty of Engineering and Information Sciences - Papers: Part A Faculty of Engineering and Information Sciences 2013 Multi-objective reactive power support from

More information

GRID CODE COMPLIANCE TESTING OF RENEWABLES NEW REQUIREMENTS AND TESTING EXPERIENCES

GRID CODE COMPLIANCE TESTING OF RENEWABLES NEW REQUIREMENTS AND TESTING EXPERIENCES GRID CODE COMPLIANCE TESTING OF RENEWABLES NEW REQUIREMENTS AND TESTING EXPERIENCES Nils Schäfer, Dr. Gunter Arnold, Wolfram Heckmann Fraunhofer Institute for Wind Energy and Energy System Technology Kassel,

More information

Validation of dynamic models of wind farms (Erao-3)

Validation of dynamic models of wind farms (Erao-3) ECN-E 07-006 Validation of dynamic models of wind farms (Erao-3) Executive summary, benchmark results and model improvements J.T.G. Pierik (ECN) J. Morren (TUD) 1 January 2007 Validation of dynamic models

More information

Variable Renewable Energy Sources in Distribution Networks Martin Braun Fraunhofer IWES & Universität Kassel

Variable Renewable Energy Sources in Distribution Networks Martin Braun Fraunhofer IWES & Universität Kassel Variable Renewable Energy Sources in Distribution Networks Fraunhofer IWES & Universität Kassel 1st International Conference on Large-Scale Grid Integration of Renewable Energy in India New Delhi, India

More information

DISTRIBUTION LOSS ADJUSTMENT FACTORS ESB SUBMISSION THE COMMISSION FOR ELECTRICITY REGULATION

DISTRIBUTION LOSS ADJUSTMENT FACTORS ESB SUBMISSION THE COMMISSION FOR ELECTRICITY REGULATION DISTRIBUTION LOSS ADJUSTMENT FACTORS ESB SUBMISSION TO THE COMMISSION FOR ELECTRICITY REGULATION Document No: DOC-140105-AIL 7/02/2000 Introduction: The Commission for Electricity Regulation (CER) have

More information

1.818J/2.65J/3.564J/10.391J/11.371J/22.811J/ESD166J SUSTAINABLE ENERGY. Prof. Michael W. Golay Nuclear Engineering Dept.

1.818J/2.65J/3.564J/10.391J/11.371J/22.811J/ESD166J SUSTAINABLE ENERGY. Prof. Michael W. Golay Nuclear Engineering Dept. 1.818J/2.65J/3.564J/10.391J/11.371J/22.811J/ESD166J SUSTAINABLE ENERGY Prof. Michael W. Golay Nuclear Engineering Dept. Energy Supply, Demand, and Storage Planning The Example of Electricity 1 PRESENTATION

More information

Special Purpose Transformers. Johann Griebichler, Marketing & Sales Distribution Transformers, Factory Weiz - Austria

Special Purpose Transformers. Johann Griebichler, Marketing & Sales Distribution Transformers, Factory Weiz - Austria Special Purpose Transformers Johann Griebichler, Marketing & Sales Distribution Transformers, Factory Weiz - Austria siemens.at/future-of-energy Agenda Location Siemens AG Österreich, Factory Weiz Renewable

More information

System Service Provision

System Service Provision System Service Provision An independent view on the likely costs incurred by potential System Service Providers in delivering additional and enhanced System Services. 16010928 London, 5 By order of EirGrid

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014 No. Comment Submitted ISO Response Date Q&A Posted 1 Can the CAISO provide a line rating methodology (similar to a NERC FAC-008 standard) or include a requirement of using any The ISO does not provide

More information

Renewable Integration at ERCOT

Renewable Integration at ERCOT Renewable Integration at ERCOT Dan Woodfin Director of System Operations ERCOT CIGRE Chile September 12, 2016 The ERCOT Region The interconnected electrical system serving most of Texas, with limited external

More information

Click to edit Master title style. Click to edit Master title style Active Network Management Workshop

Click to edit Master title style. Click to edit Master title style Active Network Management Workshop Click to edit Master title style Click to edit Master title style Active Network Management Workshop David van Kesteren System Planning Topics Click to to edit Master title style What is ANM Why do we

More information

Shunt and series reactors for medium- and high-voltage grids siemens.com/transformers

Shunt and series reactors for medium- and high-voltage grids siemens.com/transformers Economical and stable grid operation Shunt and series reactors for medium- and high-voltage grids siemens.com/transformers Reactors enhance grid stability and economic efficiency Shunt reactor from Siemens

More information

R2 TESTING GUIDELINE. PREPARED BY: Network Models Systems Capability VERSION: Final RELEASE DATE: 28 June 2013

R2 TESTING GUIDELINE. PREPARED BY: Network Models Systems Capability VERSION: Final RELEASE DATE: 28 June 2013 PREPARED BY: Network Models Systems Capability VERSION: Final RELEASE DATE: 28 June 2013 Version Release History Version Date By Approved By Changes 0.1 June 2013 BB MS This document has been created by

More information

DECISION 1 SCOPE AND CONSIDERATIONS... 2

DECISION 1 SCOPE AND CONSIDERATIONS... 2 MEMORANDUM TO Windfarm developers FROM TenneT TSO SUBJECT Overplanting - version: Hollandse Kust (zuid) DECISION FOR INFORMATION ONLY QUALITY CONTROL Prepared: Daniël Vree Reviewed: Frank de Vries 19.09.2017

More information