1 EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION White Clay Mining project is located at village Palaskhedi Tahsil Bhainsdehi; District - Betul (MP). The lease area is being hold by Smt. Shikha Upadhyay, having office at D- 141, New Minal Residency, J. K. Road, Tehsil- Huzur, Dist. Bhopal (MP) and the lessee is private individual. The fresh lease was granted for period of 20 years from to As per P-II form, land of lease area is Govt. land. The Expert Appraisal committee of MoEF suggested Terms of References (ToR) for the preparation of the Environmental Impact Assessment (EIA) and Environmental Management Plan (EMP) Report through its letter No. J-11015/123/2011-IA.II (M) New Delhi dated , which is incorporated in the EIA/EMP report at their respective places. 1.2 DETAILS OF THE PROJECT Table - 1 S. No. Particulars Details 1. Locations A. Village Palaskhedi B. Tehsil Bhainsdehi C. District Betul D. State Madhya Pradesh Toposheet No. 55G/11 2. Coordinate o N E o N E o N E o N E 3. General ground level 435 above MSL 4. Elevation range Highest-555 m RL lowest- 435m RL 5. Temperature Min: C and Max: C 6. Relative Humidity Max. Min. 100% 20% 7. Mean Annual Rainfall 1000 mm 8. Nearest National Highway Betul-Paratwada 1 km - SE CH-EX.1

2 9. Nearest Railway Station Betul 82km 10. Nearest Airport Nagpur - 240km 11. Nearest Tourist Place within 10km radius Muktagiri Jain Temple 3.5km - NW 12. Archaeological Important Place None within 10km radius 13. Ecological Sensitive Areas (Wild Life Sanctuaries) None within 10km radius 14. Reserved / Protected Forest within Hattighat RF km- NW 10km radius (Boundary to boundary Patoli RF - 6.0km- NNW distance) Sawalmendra RF km- NE 15. Nearest major city with Nil population within 10km radius 16. Nearest Town / City within 10km radius Nil Paratwada-11km 17. Surrounding village within 1 km area of the project. Palaskhedi/Kharali- 0.2km - S 18. Nearest River Nag Nadi km- W Megha Nadi km- NE Arna Nadi km - EEN Bahram Nadi - 4.5km- SSE 19. Nearest Lake/ Ponds/Nalla Ambara Nalla km -W Bahram Talav km -E Chaursi Nalla - 6.0km - N Stop dam - 1.5km - SSW 20. Nearest Hill Ranges None within 10km radius 21. Source of Water Mine pit, dug well Source: Field Survey CH-EX.2

3 1.3 MINING LEASE STATUS Subject lease area of White Clay mineral is located at village Palaskhedi, Tahsil Bhainsdehi; District - Betul (MP). The fresh lease was granted for period of 20 years from to As per P-II form, land of lease area is Govt. land Mining Details Table 2 S. No. Particulars Details 1 Type of Mine Open Cast 2 Mining Lease Area Hect 3. Mineable Area 3.06hect 4. Existing Pits & Quarries hect 5. Existing Dumps Nil 6. Infrastructure and road 0.09hect 7. Mineral Storage Nil 8. Plantation Nil 9. Barren Land hect 10. Geological Reserve tonnes q Recoverable Reserve tonnes 12. Method of mining Manually 13. Ultimate Depth of Mining 6m 14. Ultimate Pit Slope 45 o 15. Proposed capacity of mines 5330tonnes per annum 16. Expected Life of Mines 29years 17. Lease Period 20 year upto Thickness of top soil/ob Minimum 0.0 m Maximum 2.0 m Average 1.0 m 19 Existing mode to transportation of Road mineral 20 Area to be covered under dumps 0.32hect 21 Area covered under pit 2.205Hect 22 Area to be reclaimed by lease period Nil end 23 Area to be converted as water reservoir 0.5hect 24 Area to be covered under plantation by 1.0hect lease period end 25 Average mrl AMSL 26 Ground water table CH-EX.3

4 Monsoon period Dry month Source: Approved Mining Plan by IBM Mineable Reserves and Life of Mine 20m bgl (415mRL) 25m bgl (410mRL) Mineable reserves are those reserves, which are left after deducting mineral blocked in benches and barrier zone. Table-3 Category UNFC code Reserves in T A - Mineral reserve Proved 111 Nil Probable (122) B Remaining mineral resources Feasibility 211 Pre-feasibility 221 & (221) Measured (331) Indicated Inferred Reconnaissance Life of the mine Updated balance reserve of white Clay reserve at Palaskhedi White Clay mine stands at T. Therefore /5330=29.19year says 29year Method of Mining White clay is present 0.0m to 2.0m below the surface level. It exists on the surface along the lateritic soil. Since it is not difficult to reach from the surface, the opencast mining method has been adopted for the mining. Hence opencast mining method for the excavation of minerals has been chosen. The mining operations will be carried out by manual means. Presently no mining activity has been carried out by present lessee. Presently hect area has been developed by previous lessee. Proposed mining operation will be carried out by manual method of mining using hand tools such as spades, hammer, crowbar, chisel etc. Loading of mineral in to truck/ dumper will be done manually by head load using can basket and tasla etc. Proposed CH-EX.4

5 mining will be carried out in already partially developed quarry-3 in south western direction it is having less slope and mineral exposed below 1.5m soil cover. Systematic benches will be developed in this quarry. The gradient of the haul road will be maintained 1:16. Providing site-services in southwestern 7.5m barrier zone of the lease area will develop infrastructure. There is 1.5m soil cover is proposed working block. It will be removed by manually. The dumping of soil is proposed in south western part along barrier zone of the lease area. During the first five year three benches will be developed one in soil and two in white clay. During the ensuing the five year period about 4800m 2 areas will be developed with RL of 465.5m. Ground water seepage will not encounter because the ground water table is 20m below the ground surface level (i.e. 415mRL) and working will be done upto 465.5m RL. Table-4 Year wise development/ production for the two years period Year Soil in cubic Waste in cum White clay production meter (intercalated) in tones 1 st nd rd th th Nil Total REQUIREMENTS FOR THE PROJECT Land Requirement Total mining lease area is Ha. The status of the land is given below: Table - 5 Dist. Tehsil Village Khasra No. Area in ha Ownership Betul Bhainsdehi Palaskhedi 21/ Govt. Land Source: Approved Mining Plan by IBM & P-II form Water Requirement The total water requirement is 11 m 3 /day Manpower Requirement CH-EX.5

6 Taking ultimate life of mine to be maximum 29 years, the employees enrolled with the mine will be retiring. Therefore majority of employees shall get through normal retirement. Some employees coming mid way of mine life, due to other circumstances may need adjustments. Estimated requirement of manpower for this project will be about Table-6 Man power requirements S. Management and Supervisory Qualification Nos. No. Personnel required 1. Part time mining engineer 1 2. Mine manager having Managers 1 certificate of Competency 3. Mining Mate Mining Mate s certificate 1 of Competency 4. Skilled labour 3 5 Semi skilled labour 15 6 Working days Annual production 5330T Power Requirement It is proposed to have connection from M.P. State Electricity Board for required power. However no power will be required for mining process Extent of Mechanization Proposed mining operation will be carried out by manual method of mining using hand tools such as spades, hammer, crowbar, chisel etc. Loading of mineral to truck/ dumper will be done manually by head load using can basket and tasla etc 2.0 DESCRIPTION OF THE ENVIRONMENT 2.1 CLIMATIC CONDITION The micro-meteorological conditions regulate the transport and diffusion of air pollutants released into atmosphere. While the principal meteorological variables affecting horizontal convective transport are average wind speed and direction, the vertical convective transport is a function of atmospheric stability. The transport of CH-EX.6

7 pollutants is also governed by topography of the region. The data on various meteorological parameters at project site was collected during study period with the help of mechanical weather station. Meteorological data consisting of wind speed, wind direction, humidity and temperature were recorded simultaneously. The brief discussion over the meteorological condition of the area is as below: Temperature: During study period, the maximum temperature in the observed to be 32 o C to 39 o C whereas the minimum temperature was observed to be 4 to 10 o C. Relative Humidity: The air is generally humid in this region during the monsoon when the average relative humidity. During the study period maximum relative humidity was observed is 99% and minimum RH was observed is 6%. Rainfall: Monsoon in the area comes from south westerly winds. The average annual rainfall based on the last 10-year IMD data, was observed to be 1000 mm. During the study period, 11mm rainfall has been observed. Cloud: During the study period maximum cloud cover was observed 6 oktas. Wind Patterns during study period: The predominant directions of wind were observed is S, SWS, SE, WSW & W followed by W. 2.2 OTHER BASELINE DETAILS During the study period, ambient air quality and noise level monitoring was done at 4 locations whereas, surface & ground water sampling was carried out at 3 & 4 locations respectively and soil sampling was done at 3 locations. Results for the same are summarized below: Table 7 Baseline Data: November, 11 to January, 12 Particulars Details Specification Ambient air quality NAAQS PM 10 Max. 88 & Min µg/m 3 PM 2.5 Max & Min µg/m 3 SO 2 Max & Min. 80 µg/m NO 2 Max & Min µg/m 3 Noise level CPCB Standard Day time (6:00 am to Max & Min. 75 Leq. db (A) CH-EX.7

8 10:00 pm) Night time (10:00 Max & Min. 70 Leq. db (A) pm to 06:00 am) Water quality IS 10500:1991 (Desirable limits) Surface water ph Max & Min TDS Max. 255 & Min mg/l Total Hardness Max. 121 & Min mg/l Ground water ph Max & Min TDS Max. 395 & Min mg/l Total Hardness Max. 195 & Min mg/l Soil quality ph Max & Min <4.5 extremely acidic very strong acidic strongly acidic moderately acidic slightly acidic Neutral slightly alkaline moderately alkaline strongly alkaline >9.0 Very strongly alkaline BIOLOGICAL ENVIRONMENT The major area of the core zone is barren land or waste land, hence, no major adverse impact is anticipated. The core zone covered by sparse vegetation of grass only; hence, no loss of flora is expected. No fauna comes under schedule-i as well as in buffer Zone is present in the ML area; therefore, no adverse impact on fauna is anticipated. Core zone is not having forest and mining will be manual type and with blasting. Further no endangered species has been found in the buffer zone. Hence no impact in anticipated. Afforestation on 1.0ha area with 1410 numbers of trees is proposed. Further no movement of wild animals has also been noticed in the area. CH-EX.8

9 3.0 ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES Impact on Air Environment Drilling and blasting operations are source of fugitive dust emission. Drilling and blasting will not be proposed for the subject mine. The major part of the dust generated during such operations usually gets settle down near vicinity and thus the effect of such operation will be localized phenomenon. The results of the background PM 10 concentration at all receptors over the area are insignificant and are very low as compared to the standards prescribed by the CPCB for ambient air quality. Thus, it can be safely stated that due to the proposed mining activity, there will be no adverse impact on the existing ambient air quality. Following air pollution control measures shall be taken to minimize negative impact due to mining activity: Dust suppression over the roads by carrying out water sprinkling. It is observed that the approach road from lease area (working pit - South west) to PWD road (about 2km) is Pucca Road (RCC Road). However habitation (palaskhedi village) has been observed along the said pucca road. Water spraying will be suggested on same road before movement of mineral loaded truck. Proper stabilization of soil/ob dumps through grasses and shrubs. Green belt development along the roads, over the overburden dumps and in the mining area as whole Impact on Water Environment Impact on Ground Water :- Mining in the area will be done well above the existing water table therefore impact on water regime will not be done. The ground water table is at m bgl. The ground water chemistry indicates that the ground water in the area is potable and doesn t contain any toxic elements. Impact on Surface Water:- No impact on existing surface water resources is expected on the mining activity is confined to limited area occupying. In fact, the accumulated rain water in the quarry pits CH-EX.9

10 will recharge the ground water. Mine discharge has been taken to settling tanks (pit No.1) in south west direction through garland drain. However siltation will not been around the lease area. Mitigation measures for Water Pollution No toxic substance will be generated during the mining operation which may affect the quality of surface water. No waste water will be discharged outside the lease area which may affect the quality of surface water bodies. However, protective measures are proposed to be taken by making garland drain all around the working pits & dump in order to control sedimentation and siltation etc. of the water bodies and water courses. Thus the impacts are negligible on either ground water resources or surface water resources. No surface water or ground water pollution is expected as the mine working does not intersect the ground water table. Impact on Noise Major noise generating sources of the mining activity is excavation, loading and truck movement used for transportation of minerals. i. Compulsory use of personnel protective equipment (PPE) such as ear plugs for the workers ii. Use of physical barriers and green belt development around the mine to restrict the noise from going outside the proposed mine boundary during operation Impact on Land & Soil Environment Open cast mining disturbs the land environment of the area to significant unless it is not supported by proper reclamation measures. Proposed lease area is hilly terrain having two numbers of prominent mounds with lowest counter level observed in 435m falling in SE part of the lease area and highest counter level is 555m falling in northern part of the lease area. No major drain flow from within or near vicinity of area. The gradient and drainage of area is towards south east and east. The mining is proposed in partially developed pit in South west direction. Since the ultimate depth is proposed up to 6mbgl, the land use pattern will be changed during course of mining. It is proposed to leave the CH-EX.10

11 excavated pit as water reservoir structure, which may give positive impact. Proposal of backfilling given may be at end of lease period after completion of further exploration and find out the further depth of mineral. During the lease period 2.205ha area will be excavated upto 6mbgl. The present land use in buffer zone is agricultural land and stony waste land. This mining lease area does not possess threat to any forest growth as existing land use of the site is barren land. So that there is no chance of loss of forest due to mining activity. Thus there is no adverse impact over land environment due to the mining activity, as all the activities will be limited to the core zone only. 4.0 POST PROJECT ENVIRONMENTAL MONITORING PROGRAMME S. No. Environmental Attributes Table 8 POST PROJECT MONITORING PROGRAMME 1 Ambient Air quality Mine Site Village Palaskhedi, Nimobra Locations Parameters Period and PM 10, SO 2, NOx, CO and as directed by MPPCB Frequency 24 hr. average samples month mining phase every during 2 Ground water Mine well Drinking Water Pre Monsoon and parameters as Post Monsoon per IS Surface water Mine pit and stop ph, conductivity, Pre Monsoon and dam Alkalinity, TS, Post Monsoon TDS, TSS, Total hardness, Cl, SO 4, Ca, Mg, K, Na, Zn, Al, Fe, Total 4 Ambient Noise mine site (near the db (A) levels Hourly day and working pit during night time Leq CH-EX.11

12 S. No. Environmental Attributes 5 Mines Water Discharge into drains Locations Parameters Period and excavation and around the lease periphery) total 04 point Mining Area 6 Soil Quality In and around the site ph, conductivity, Alkalinity, TS, TDS, TSS, Total hardness, Cl, SO 4, Ca, Mg, K, Na, Al, Fe, Zn, Total Coliform Organic matter, C, H, N, alkalinity, Acidity, metal heavy Frequency levels every quarter Pre and Post Monsoon Annual 5.0 ADDITIONAL STUDIES The Additional Studies conducted as per the Terms of Reference (ToR) issued by MoEF vide letter No. J-11015/123/2011-IA.II (M) New Delhi dated , are Biological Study & Subsidence Prediction modelling has been carried out. 6.0 PROJECT BENEFITS Better education facilities, proper health care, road infrastructure and drinking water facilities are basic social amenities for better living standard of any human being. Smt. Shikha Upadhaya will increase these facilities either by providing or by improving the existing facilities in the area, which will help in uplifting the living standards of local communities. CH-EX.12

13 Table 9 Proposed Exp towards the Socio Economic activity Activity Provision of carpus fund for social /developmental activities like provision of infrastructure facility at school, medical camps etc as proposed by Village Panchayat Exp. Incurred 5% of Royalty per year 7.0 ENVIRONMENT MANAGEMENT PLAN 7.1 MANAGEMENT OF LAND USE PATTERN The activity will affect the present landscape of the ML area. The original topography of the ML area will be affected mainly due to the mining operation. Table 10 Environmental Management Items Existing At the end of lease period Total lease area hect Ultimate depth 5.5m 6m bgl Ultimate pit slope Area under dumps Nil 0.32hect Area under pits hect 2.205hect Area to be reclaimed Nil Nil Infrastructure & Road 0.09hect 0.1ha Mineral storage Nil Nil Plantation Nil 1.0hect Water reservoir 0.1hect 0.5hect 7.2 AIR QUALITY MANAGEMENT Present Air Quality At present no mining activity is going in the lease area. Therefore the impact on the air quality of proposed area is negligible Air Pollution Control All suitable pollution control measures will be adopted to minimize the air pollution and noise pollution viz. CH-EX.13

14 Mitigative measures suggested towards air pollution are based on the data obtaining for ambient air quality monitoring data. Dust control measures Dust would be generated during mining, handling and transportation of the material. The controls measures are proposed to control the fugitive dust released during the mineral production are given below: a) Haulage road & Dumps Following measures should be taken to mitigate the effect of mining operation over ambient air environment: 1. Water sprinkling on haul road has already been carried out at frequent intervals during the playing of dumpers. 2. Plantation along the mining lease boundary and haul roads will be carried out to reduce the spread of dust. 3. Existing over burden dumps will be stabilized with legumes and grass to prevent the erosion of soil and arrest the dust emission during windy days. b) In lease area 1. Water has been sprayed over the muck pile to reduced the dust generation; 2. Dust mask has already been provided to all workers working in dusty atmosphere. 3. Plantation will be done at the periphery of mining lease 4. Regular maintenance of vehicles has been carried out in order to control emissions; 5. A good housekeeping and proper maintenance has been practiced which has been help in controlling pollution. c) Village road The approach road from lease area (working pit - South west) to PWD road (about 2km) is Pucca Road (RCC Road). However habitation (palaskhedi village) has been observed along the said pucca road. Water spraying will be suggested on same road before movement of mineral loaded truck. CH-EX.14

15 7.3 WATER QUALITY MANAGEMENT The Surface water bodies in the study area mainly Nag Nadi, Megha Nadi, Arna Nadi, Bahram Nadi, Ambra Nalla, Baharm talav, Chaursi Nalla & Stop Dam located W, NE, ENE, SES, W, E, N & SWS direction at about 3.5km, 4.20km, 3.80km, 4.5km, 7.0km, 0.75km, 6.0km & 1.5 km respectably from mine. Therefore the nearest surface water body is Baharm Talav, which is located at E direction at 750 mt. One hillock observed between lease area and Baharam Talav. The general slope of area is towards south east and east; hence water drainage pattern should also be towards the southern east direction. Following measures will be taken to avoid contamination and siltation problem: 1. Garland drain will be provided around dump requires maintenance. Drain will also be provided around the pit. All garland drain will be connected to Settling tank and water of settling tank will be used for dust suppression and agricultural purpose 2. Pit No. 1 (50x 20 x 5.5m), which is located south west side of the lease area is converted as settling tank. The pumped out water will be used for agricultural purpose. 3. During lease period 0.50 ha area will be converted as a water reservoir. 4. Silt trapping system will be provided for the garland drains. Maintenance and cleaning of drains will be taken care at regular interval 5. Quality of water of settling tank will be checked at pre-monsoon and post- monsoon Rain water harvesting Following methods shall carry out the rainwater harvesting: 1. After excavation of mineral, excavated pit will be converting as a water reservoir structure. 2. The discharged mine water can be gainfully utilized by the local people for irrigation and domestic use. Thereby the mine water is a resource for many of the local villagers. 7.4 SOLID WASTE MANAGEMENT Mineralized part of the lease area is covered by 1.5 to 2.0m soil cover. The waste produced during mining operations consists of hard insoluble quartzite and soil. During CH-EX.15

16 the first five year 7200 m 3 soil will be generated and this will be dumped in southwestern part of the lease & during lease period, total m 3 soil will be generated. During the first five year 958 m 3 mine waste will be generated and during the lease period total 4500 m 3 mine waste generated. About 50% mine waste & soil will be used for the constructing and maintenance the approach road, plantation, retaining wall and garland wall etc and rest of 50% mine waste and soil will be dumped in the south west and south eastern barrier zone which will cover hect area and constructing the retaining wall around the dump will be provided their stability. There is no program of backfilling during lease period. All waste dumps will be stabilized with grasses and trees for prevent the waste material to the nearby area. The length of garland drain will be approx 1200m. The present land use in buffer zone has been presented in Chapter-3. No adverse impact is anticipated in land use of buffer zone due to the mining operations, as all the activities will be limited to core zone only. The land use in the buffer zone may have a positive impact due to the possible conversion of un-irrigated land to irrigated land. Following measures should be taken to avoid/minimise the adverse effects of proposed mining activity. : 1. Vegetation should be removed only from the specific site on which extraction of mineral to be take place, if any. 2. Proper stabilization of overburden dumps 3. Before dumping, soil should be removed from the dump place. 4. The topsoil should be separated stacked and slope should be maintained. 5. The water reservoir of 0.5 ha shall be provided fencing and proper steps. 6. Plantation along dumps, lease periphery and water reservoir shall be carried out. 7.5 NOISE MANAGEMENT Since the mining is manual and opencast type without blasting, the source of noise generation will be excavation and vehicle movement. The noise generation from above CH-EX.16

17 mining activities will be temporary. There are one villages observed within 500m radius; noise level will be insignificant as the operations are of intermittent nature. The prevailing day and night noise levels around the village reported are between dba and respectively. The ambient noise level monitoring carried out around the proposed mine shows that ambient noise levels are well within the stipulated limits of CPCB. In order to further control the noise levels in the work zone following measures are adopted: Mitigation Measures to Reduce Ambient Noise Levels 1. Three type green belt will be provided in phased manner around the periphery of the mine to screen the noise; 2. Trees will be planted on both sides of roads used for transportation; 3. Proper maintenance will be done of noise generating machinery including the vehicles; and Measures to Protect Workers from High Noise Levels 1. Provision of protective devices like ear muffs/ear plugs; 2. Reducing the exposure time of workers to the higher noise levels 7.6 SOCIO-ECONOMIC ENVIRONMENT The impacts on the different components viz employment, housing, educational, and medical and transport facilities, fuel availability, economics, status, health agriculture is not significant because size of project is very small. However, it would definitely increase the employment opportunity (primary as well as secondary) in the project area. Some of these impacts would be beneficial. It is not out of place to mention that another two mines, which are adjacent to the subject mine, may likely to come in operation in near future. The Project Management will identify the needs of the surrounding villages and will develop a social management plan to benefit the surrounding areas. Thus the surrounding villages will get benefits from the proposed mining activity. CH-EX.17

18 The expectation of the people of the area is concerned towards employment, education, and health facilities. The literacy rate may be increased with the economic benefits may arises from the mining activities. Further the villagers and workers may also get benefitted by medical camps and primary medical facilities, which will be provided by the management. In addition, the employment potential will ameliorate economic conditions of families of workers directly and provide employment to many other families indirectly who are involved in business and service oriented activities. This in-turn will improve the socio-economic conditions of the area. Activity Provision of carpus fund for social /developmental activities like provision of infrastructure facility at school, medical camps etc as proposed by Village Panchayat Exp. Incurred 5% of Royalty per year 7.7 GREENBELT DEVELOPMENT AND PLANTATION PROGRAMME Since there are no notified endangered species in the area, which will be effected due to the mining activities, therefore the biological environment will not have significant impact due to proposed environment. The impact on the biological environment due to amount of dust generation is minimised by well-developed green belt in and around mining lease area. The green belt development not only functions as foreground and background landscape features resulting in harmonizing and amalgamating the physical structures of the mines with surrounding environment, but also acts as pollution sink as indicated above. Thus, implementation of afforestation program is of paramount importance. In addition to augmenting present vegetation, it will also check soil erosion, make the ecosystem more complex and functionally, stable and make the climate more conducive. CH-EX.18

19 The plantation matrix should be adopted for the green belt development includes pits of 0.3m x 0.3m x 0.3 m size with the spacing of 2.0 m x 2.0m. Selection Criteria of plant species for Green Development Plant The selection of plant species for the development depends on various factors such as climate, elevation and soil. Area falls under the tropical region and thus the local species should be selected. Following criteria may be taken for selection of species The species should be fast growing. The species should form a dense canopy. As far as possible, the species should be indigenous and locally available Species tolerance to air pollutants like PM 10, SO 2, and NOx should be preferred. Tree with high foliage density, leaves with larger leaf area and hairy on both the surface. Soil improving plants (Nitrogen fixing, rapidly decomposable leaf litter). Sustainable green cover with minimal maintenance. Plant Species for Mine Area and its Boundary Acacia nilotica Albizzia species Acacia auriculiformis Azadirachta indicata Annona squamosa Bauhinia variegata Butea monosperma Cassia festula Dalbergia sisoo Erythrina indica Ficus bengalensis Ficus religiosa Grewia species Leuceana leucocephala Morus indica/alba Prosopis species Syzygium cuminii Tamarindus indica Terminelia arjuna Zizyphus species Carissa species Feronia species Phylanthus species Madhuca species Magnifera species Leuceana leucocephala Plantation Schedule A stage-wise comprehensive afforestation program is prepared and shall be implemented. The locations of the proposed greenbelt along with area of the green cover are given in the conceptual plan. CH-EX.19

20 Afforestation plan Environment impact & management : Ecology: Stage Wise Cumulative Plantation Requirements of plants for Afforestation/Reclamation Year Un-worked area Outside dumps Inside Dumps Top soil dumps Total (reclaim) Area (Ha) Trees Area (Ha) Trees Area (Ha) Trees Area Trees Area (Ha) Trees (Ha) Present Nil Nil Nil Nil 1 st to 5 th th to year Total CONCLUSION As discussed, it is safe to say that the project is not likely to cause any significant impact on the ecology of the area, as adequate preventive measures will be adopted to contain the various pollutants within permissible limits. Green belt development around the area would also be taken up as an effective pollution mitigative technique, as well as to control the pollutants released due to mining. CH-EX.20

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION Jaypee Group is a leading Business House of the country with its presence in Core industries and Service Sectors like Cement, Infrastructure development,

More information

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA 1.0 INTRODUCTION M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA dry type of coal washery at Village: Hindadih, Tehsil: Masturi, District: Bilaspur (C.G.) for which

More information

Executive Summary for Dang Sarkar Metal Stone Quarry (42.63 Ha) EXECUTIVE SUMMARY

Executive Summary for Dang Sarkar Metal Stone Quarry (42.63 Ha) EXECUTIVE SUMMARY EXECUTIVE SUMMARY 1. PREAMBLE Minerals are the chief source of present phase of industrialization, and play an important role in the present phase of the national economy and overall development of the

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. (Change in Technology) at Hindadih Village, Masturi Tehsil Bilaspur District, Chhattisgarh Submitted to

More information

PROJECT BRIEF. Noise environment: No Entrant noise generation sources exist in and around project area.

PROJECT BRIEF. Noise environment: No Entrant noise generation sources exist in and around project area. PROJECT BRIEF PROJECT LOCATION: - Pahar Kua Marble Range Mining Project Q L No 235 is located near village Pahar Kua, Tehsil Makrana., District Nagaur Rajasthan. Project is approachable from national highway.

More information

THE RAMCO CEMENTS LIMITED

THE RAMCO CEMENTS LIMITED 1 P a g e 2 P a g e THE RAMCO CEMENTS LIMITED (Formerly Madras Cements Ltd.) COMPLIANCE REPORT FOR ENVIRONMENTAL CLEARANCE JAYANTHIPURAM NORTH BAND MINING LEASE 2.0 MILLION TPA CAPACITY EC Lr. No. : J-11015/377/2006-IA.II

More information

HINGULA OPEN CAST PROJECT HINGULA AREA MAHANADI COALFIELDS LIMITED

HINGULA OPEN CAST PROJECT HINGULA AREA MAHANADI COALFIELDS LIMITED HALF YEARLY PROGRESS REPORT ON IMPLEMENTATION OF ENVIRONMENTAL CLEARANCE CONDITION BY MoEF (PERIOD FROM OCTOBER 13 TO MARCH 14) HINGULA OPEN CAST PROJECT HINGULA AREA MAHANADI COALFIELDS LIMITED SIX MONTHLY

More information

EXECUTIVE SUMMARY. Executive Summary for 12.77ha Gosalpur Manganese, Iron, Blue dust & ETC Minerals

EXECUTIVE SUMMARY. Executive Summary for 12.77ha Gosalpur Manganese, Iron, Blue dust & ETC Minerals EXECUTIVE SUMMARY 1. PREAMBLE Minerals are the chief source of present phase of industrialization, and play an important role in the present phase of the national economy and overall development of the

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. 0.96 MTPA Wet type Coal Washery at Birgahani Village, Baloda Tehsil Janjgir-Champa District, Chhattisgarh

More information

FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) PART A

FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) PART A (I) FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR 2013-14 M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) Name & Address of the Owner / Occupier of the Industry Operation or Process

More information

ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT

ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT EXECUTIVE SUMMARY NAGERCOIL MUNICIPALITY, KANYAKUMARI DISTRICT TWAD BOARD,SEWERAGE DIVISION,NAGERCOIL

More information

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are: 4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 4.1 POTENTIAL ENVIRONMENTAL IMPACTS 4.1.1 Impacts during Construction Phase Negative or adverse impacts during the construction phase are: Land environment:

More information

PROPOSED TERM OF REFERENCE

PROPOSED TERM OF REFERENCE PROPOSED TERM OF REFERENCE FOR ESTABLISHMENT OF PROPOSED MOLASSES/GRAIN BASED DISTILLERY HAVING CAPACITY: 160.0 KLD (MOLASSES BASED) OR 120.0 KLD (MOLASSES BASED) + 40.0 KLD (GRAIN BASED) ALONGWITH 7.0

More information

TERMS OF REFERENCE. Identification of the sources of pollution and assessing the impacts on the environment due to proposed project if any;

TERMS OF REFERENCE. Identification of the sources of pollution and assessing the impacts on the environment due to proposed project if any; TERMS OF REFERENCE 1.0 PROPOSED SCOPE OF WORK FOR EIA STUDY The components of the EIA study include: Determination of baseline data using primary data generation and secondary data available from various

More information

EXECUTIVE SUMMARY INTRODUCTION : Jayaswal Neco Industries Limited

EXECUTIVE SUMMARY INTRODUCTION : Jayaswal Neco Industries Limited EXECUTIVE SUMMARY A. INTRODUCTION : M/s Jayaswal Neco Industries Limited (JNIL) belongs to the wellknown industrial group of Central India viz. NECO GROUP having annual turnover exceeding Rs. 3500 Crores.

More information

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra Draft Terms of References (ToR) (Based on the model TOR given in Environmental Impact Assessment Guidance Manual for building construction projects by MoEF & CC) For PROPOSED IT PARK By M/s.Balewadi Tech

More information

Sr.No Condition Status A. SPECIFIC CONDITIONS:

Sr.No Condition Status A. SPECIFIC CONDITIONS: J.K. CEMENT WORKS, MANGROL (RAJ.) Compliance report of Mangrol Lime stone mine (For the period from April 2011 to September 2011) Sub:- Conditions of Environment Clearance from MOEF, New Delhi Letter No.

More information

MCDR INSPECTION REPORT

MCDR INSPECTION REPORT 1 MCDR INSPECTION REPORT General SN Particulars Details Date of Inspection 18.10.2016 1 Name of the Mine Dhobitola Titaniferous Iron Ore Mine 2 Total Lease Area (Ha) 2.61 Ha (Entire Forest Land) with breakup

More information

ToR Letter No. SEIAA/AP/ANT/ Dated Monitoring Period : October 2016 to December Applicant

ToR Letter No. SEIAA/AP/ANT/ Dated Monitoring Period : October 2016 to December Applicant EXECUTIVE SUMMARY of Proposed Quartz Mine (30.667 Ha.) with a Production of 91,125 TPA at Sy. No. 410, D.Cherlopalli Village, Bathalapalli Mandal, Anantapur District, Andhra Pradesh. ToR Letter No. SEIAA/AP/ANT/2015-3568

More information

The mine is opened on The reasons for delay for starting mining operations are:

The mine is opened on The reasons for delay for starting mining operations are: 1 P a g e 2 P a g e THE RAMCO CEMENTS LIMITED (Formerly known as Madras Cements Ltd.) COMPLIANCE REPORT FOR ENVIRONMENTAL CLEARANCE BUDAWADA LIMESTONE MINE - 1.10 MILLION TPA CAPACITY EC Lr. No : J-11015/150/2008-IA.II

More information

N.H. 6 is 50 km away from the proposed plant boundary; in N direction;

N.H. 6 is 50 km away from the proposed plant boundary; in N direction; 1.1 INTRODUCTION Godawari Power & Ispat Limited (GPIL) has an existing Iron Ore Crushing plant of 12,00,000 MTPA capacity at Gidhali, Village Kusumkasa, Tehsil - Balod, District - Durg (Chhattisgarh) and

More information

CMPDI. 4.6 Mine Closure Plan

CMPDI. 4.6 Mine Closure Plan 4.6 Mine Closure Plan Post-mining Land Use Planning The mine closure planning with regard to for Lekhapani OCP will broadly involve the following aspects: 1. Technical Aspects 2 Environmental Aspects 2.

More information

HINAUTI LIMESTONE MINE Mine Lease area ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P)

HINAUTI LIMESTONE MINE Mine Lease area ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P) HINAUTI LIMESTONE MINE Mine Lease area 378.261 ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P) 2012-2013 SUBMITTED TO M.P.POLLUTION CONTROL BOARD BHOPAL (M.P.) Jaypee Sidhi Cement

More information

No. J-l1015/313/2010-IA.II (M) Government of India Ministry of Environment & Forests

No. J-l1015/313/2010-IA.II (M) Government of India Ministry of Environment & Forests No. J-l1015/313/2010-IA.II (M) Government of India Ministry of Environment & Forests Paryavaran Bhavan, C.G.O. Complex, Lodi Road, New Delhi-110 003. Dated the 28th June, 2013 To, M/ s Arbind Kumar Singh

More information

Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited

Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited Introduction: Jaypee Group is the 3 rd largest cement producer in the country. The Groups cement facilities are located in

More information

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK PROVINCE OF NEW BRUNSWICK DEPARTMENT OF ENERGY AND RESOURCE DEVELOPMENT Minerals and Petroleum Development Branch GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK Guide to the

More information

EXECUTIVE SUMMARY. FOR CHORMARI - DEGARHAT LIMESTONE DEPOSIT AT VILLAGES CHORMARI AND DEGARHAT DISTRICT SATNA, MADHYA PRADESH (EXTENT: 102.

EXECUTIVE SUMMARY. FOR CHORMARI - DEGARHAT LIMESTONE DEPOSIT AT VILLAGES CHORMARI AND DEGARHAT DISTRICT SATNA, MADHYA PRADESH (EXTENT: 102. JAIPRAKASH ASSOCIATES LTD. (CEMENT DIVISION) EXECUTIVE SUMMARY FOR CHORMARI - DEGARHAT LIMESTONE DEPOSIT AT VILLAGES CHORMARI AND DEGARHAT DISTRICT SATNA, MADHYA PRADESH (EXTENT: 102.983 Ha) APRIL, 2008

More information

APPENDIX VIII. Form 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE

APPENDIX VIII. Form 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE APPENDIX VIII Form 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE (I) Basic Information S.No. Particulates Details 1. Name of the Mining Lease site

More information

PRE-FEASIBILITY REPORT. 5.0 Hectare sand mine under bhu-jal

PRE-FEASIBILITY REPORT. 5.0 Hectare sand mine under bhu-jal 1.0 SUMMARY OF THE PROJECT PRE-FEASIBILITY REPORT Project Name of Company / Mine Location Village Taluka District State Sand mine Gram Panchayat Tarrighat, Sand mine Tarrighat Tarrighat Patan Durg Chhattisgarh

More information

Clearance Letter no. : MoEF Vide Letter no. J-11011/79/2003-IA-II (I) dated April 21, 2004

Clearance Letter no. : MoEF Vide Letter no. J-11011/79/2003-IA-II (I) dated April 21, 2004 Name of the Project: Jaypee Rewa Plant, Unit of M/s Jaiprakash Associates Limited for expansion Of cement production from 2.5 MTPA to 3.5 MTPA at Jaypee Nagar, District Rewa, Madhya Pradesh Project Code:

More information

Jaypee Lime Stone Mine Jaypee Bela Plant (A Unit of Jaiprakash Associates Limited)

Jaypee Lime Stone Mine Jaypee Bela Plant (A Unit of Jaiprakash Associates Limited) Jaypee Lime Stone Mine Jaypee Bela Plant (A Unit of Jaiprakash Associates Limited) Introduction: Jaypee Group is the 3 rd largest cement producer in the country. The groups cement facilities are located

More information

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS Beaver Bank Bypass Highway 101 to the Beaver Bank Road Halifax County, NS NOVA SCOTIA DEPARTMENT OF THE ENVIRONMENT

More information

PRE FEASIBILITY REPORT (PFR)

PRE FEASIBILITY REPORT (PFR) APPLICANT : M/s PLANTERS AGGREGATES 27 PRE FEASIBILITY REPORT (PFR) APPLICANT : M/s PLANTERS AGGREGATES 28 INDEX S. No. Contents Page No. 1.0 EXECUTIVE SUMMARY 30 2.0 INTRODUCTION OF THE PROJECT / BACKGROUND

More information

Environmental Impact Assessment

Environmental Impact Assessment Environmental Impact Assessment A brief discussion Presented by: Apekshit Solanki Kirti Neetu Yadav Sameera Vishakha Shankar Introduction EIA is a formal process to predict the environmental consequences

More information

PRE FEASIBILITY REPORT FOR. Mining of Riverbed Sand. From Darakeswar River. Area : 8.09 Ha ( 20 Acres )

PRE FEASIBILITY REPORT FOR. Mining of Riverbed Sand. From Darakeswar River. Area : 8.09 Ha ( 20 Acres ) PRE FEASIBILITY REPORT FOR Mining of Riverbed Sand From Darakeswar River Area : 8.09 Ha ( 20 Acres ) AT Mouza: Kunjapur, Plot No: 2227 (P), 2269 (P), 2603 (P),JL: 112, Village: Kunjapur, Block : Indus,,

More information

PROJECT FEASIBILITY REPORT

PROJECT FEASIBILITY REPORT PROJECT FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE For PROPOSED CHEMICAL MANUFACTURING UNIT From M/s. MORADIA BROTHERS CHEM PVT LTD LOCATED AT: Block No.: 45, JalBhumi Industrial Estate,

More information

SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH

SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH SRI K. RAVI SHANKAR SURVEY.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH FORM I (OPENCAST QUARTZ MINE 40.313 ha) SUBMITTED BY Sri K. Ravi Shankar Door No. 39/49/39, Krishnadevaraya

More information

Portbury Dock Renewable Energy Plant. Cumulative Impact Assessment Non-Technical Summary September 2009

Portbury Dock Renewable Energy Plant. Cumulative Impact Assessment Non-Technical Summary September 2009 Portbury Dock Renewable Energy Plant Cumulative Impact Assessment Non-Technical Summary September 2009 INTRODUCTION On 28 th August 2009 E.ON Climate & Renewables UK Developments Limited (EC&R) submitted

More information

EXCUTIVE SUMMARY OF ENVIRONMENTAL IMPACT ASSESSMENT For. Pardawan Silica Sand Mine Along With Crusher and Washing Plant.

EXCUTIVE SUMMARY OF ENVIRONMENTAL IMPACT ASSESSMENT For. Pardawan Silica Sand Mine Along With Crusher and Washing Plant. EXCUTIVE SUMMARY OF ENVIRONMENTAL IMPACT ASSESSMENT For Pardawan Silica Sand Mine Along With Crusher and Washing Plant Village Pardhwan, District Chitrakoot, (U.P.) Area -93.15 ha Proposed capacity: 2,50,000

More information

Page# The Top soil generation is very less and it is being simultaneously utilized.

Page# The Top soil generation is very less and it is being simultaneously utilized. Page# 1 Name of Project : Belkapahar Mine of Wolkem Industries Ltd. Project Code: 226/336/-2005 Clearance Letter No. : J-11015/23/2004-IA.II (M) dated 31.03.2005 Period of Compliance Report : October,

More information

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 Group Housing Complex My woods AT Plot no. GH-04, Sector -16 C, Noida Extension, Greater Noida, U.P. Being developed by M/s Mahagun India Pvt. Ltd. A-19, Sector-63,

More information

1.0 EXECUTIVE SUMMARY

1.0 EXECUTIVE SUMMARY 1.0 EXECUTIVE SUMMARY S.No Particulars Details 1 Name of Project 2 Project Proponent 3 Village Proposed Granite Building Stone Quarry of Mr. Saji Sebastian Mr. Saji Sebastian Madeckal House, Kizhakkambalam

More information

Base Metal and Iron Ore Mining

Base Metal and Iron Ore Mining Multilateral Investment Guarantee Agency Environmental Guidelines for Base Metal and Iron Ore Mining Industry Description and Practices This document addresses the mining of base metal ores (copper, lead

More information

V.S LIGNITE POWER Pvt. Ltd AT VILLAGE-GURHA, KOLAYAT, BIKANER, RAJASTHAN

V.S LIGNITE POWER Pvt. Ltd AT VILLAGE-GURHA, KOLAYAT, BIKANER, RAJASTHAN V.S LIGNITE POWER Pvt. Ltd AT VILLAGE-GURHA, KOLAYAT, BIKANER, RAJASTHAN HALF YEARLY REPORT FOR THE PERIOD OCTOBER, 2011 to MARCH 2012 V. S. Lignite Power Pvt. Ltd. Name of the Project : 1x 135 MW Lignite

More information

MAJHIGAWAN LIMESTONE MINE Mine Lease area ha. ( A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.

MAJHIGAWAN LIMESTONE MINE Mine Lease area ha. ( A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M. MAJHIGAWAN LIMESTONE MINE Mine Lease area 362.68 ha. ( A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P) 2012-2013 SUBMITTED TO M.P.POLLUTION CONTROL BOARD BHOPAL (M.P.) Jaypee Sidhi Cement

More information

Sub: Submission of compliance report. Ref: Letter 1.No.21-4(67)/NCR/CGWA/ dated 16 Mar No.4-6/NCR/TS-637 dated

Sub: Submission of compliance report. Ref: Letter 1.No.21-4(67)/NCR/CGWA/ dated 16 Mar No.4-6/NCR/TS-637 dated Arvind Goenka ' RESIDENT The Regional Director, Central Ground Water Board North Central Region 1 st Block, 4 th Floor, Paryawas Bhawan Jail Road, Bhopal (M.P) 462011 Dr. Ajay Goenka SECRETARY Sub: Submission

More information

M/S Overseas Min-Tech Consultants, Jaipur. Pre-Feasibility Report Index INDEX 1 EXECUTIVE SUMMARY... 1

M/S Overseas Min-Tech Consultants, Jaipur. Pre-Feasibility Report Index INDEX 1 EXECUTIVE SUMMARY... 1 White Clay/China Clay Mining Project (3,250 TPA), M.L. No.3/01, ML Area 4.80 ha, Index INDEX 1 EXECUTIVE SUMMARY... 1 2 INTRODUCTION OF THE OBJECT/ BACKGROUND INFORMATION... 4 2.1 IDENTIFICATION OF PROJECT

More information

PRE - FEASIBILITY REPORT

PRE - FEASIBILITY REPORT PRE - FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE For EXISTING MINING ACTIVITY CATEGARY B2 UNDER THE EIA NOTIFICATION 2006 AMENDED ON 31/05/2012 TO PIRABHAI VALABHAI NANDASANIYA LOCATED

More information

CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA.

CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA. CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA. A. CONSENT TO ESTABLISH UNDER THE PROVISIONS OF WATER (PREVENTION & CONTROL OF

More information

FACTSHEET INTRODUCTION. help rebalance the water cycle, mitigate the effects of climate change and improve human health and livelihoods.

FACTSHEET INTRODUCTION. help rebalance the water cycle, mitigate the effects of climate change and improve human health and livelihoods. 1 FACTSHEET INTRODUCTION World Water Day, on 22 March every year, is about focusing attention on the importance of water. This year s theme, Nature for Water, explores nature-based solutions (NBS) to the

More information

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton Viridor Waste Management Proposed Development of an In-Vessel Composting Facility Land at Exide Batteries, Salford Road, Bolton Non-Technical Summary January 2009 Introduction Viridor Waste Management

More information

JAYPEE NIGRIE SUPER THERMAL POWER PROJECT

JAYPEE NIGRIE SUPER THERMAL POWER PROJECT JAYPEE NIGRIE SUPER THERMAL POWER PROJECT (A Unit of M/s Jaiprakash Power Ventures Limited) Villages: Nigrie, Tehsil :Sarai District: Singrauli 2014 2015 SUBMITTED M.P. POLLUTION CONTROL BOARD BHOPAL (M.P.)

More information

Mine at Village: Kubri,Tahsil: Maihar, Dist: Satna(M.P)

Mine at Village: Kubri,Tahsil: Maihar, Dist: Satna(M.P) i i ii CENTRAL INSTITUTE OF MINING RESEARCH, DHANBAD (Council of Scientific & Industrial Research) PROJECT REPORT ON EIA/EMP OF Lime Stone, Bauxite and Clay Mine at Village: Kubri,Tahsil: Maihar, Dist:

More information

MINING REGULATIONS IN FOREST AND ECO-FRAGILE AREAS A PRESENTATION BY RAJEEVA, IFS, ADDITIONAL PRINCIPAL CHIEF CONSERVATOR OF FORESTS.

MINING REGULATIONS IN FOREST AND ECO-FRAGILE AREAS A PRESENTATION BY RAJEEVA, IFS, ADDITIONAL PRINCIPAL CHIEF CONSERVATOR OF FORESTS. MINING REGULATIONS IN FOREST AND ECO-FRAGILE AREAS A PRESENTATION BY RAJEEVA, IFS, ADDITIONAL PRINCIPAL CHIEF CONSERVATOR OF FORESTS. MINERAL RESOURCES IN INDIA The mineral resources in India consist of

More information

.in Dated 9th August, Sharma ;

.in Dated 9th August, Sharma  ; F. No. J-11011/151/2010-IA II (I) Government of India Ministry of Environment and Forests (I.A. Division) Paryavaran Bhawan CGO Complex, Lodhi Road New Delhi -110 003.. To, Ankleshwar E-mail: pb.rastoai@nic.in

More information

Chapter MINERAL EXTRACTION AND MINING OPERATIONS

Chapter MINERAL EXTRACTION AND MINING OPERATIONS Chapter 17.31 MINERAL EXTRACTION AND MINING OPERATIONS Sections: 17.31.010 Purpose 17.31.020 Procedure for Extraction and Rehabilitation Requests 17.31.030 Operation and Rehabilitation Standards for all

More information

CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP) ENVIRONMENTAL MANAGEMENT PLAN (EMP)

CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP) ENVIRONMENTAL MANAGEMENT PLAN (EMP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP)

More information

STANDARD TEMPLATE & FORM-1 FOR KODIDRA LIMESTONE MINE AREA= 4.70 HECT. PROPOSED PRODUCTION: - 28,000 TPA OF LIMESTONE PROJECT COST: - 17.

STANDARD TEMPLATE & FORM-1 FOR KODIDRA LIMESTONE MINE AREA= 4.70 HECT. PROPOSED PRODUCTION: - 28,000 TPA OF LIMESTONE PROJECT COST: - 17. STANDARD TEMPLATE & FORM-1 FOR KODIDRA LIMESTONE MINE AREA= 4.70 HECT. SURVEY NO.81/2, NEAR VILLAGE - KODIDRA, TALUKA- VERVAL, DISTRICT GIRSOMANATH, (GUJARAT) PROPOSED PRODUCTION: - 28,000 TPA OF LIMESTONE

More information

10.0 AIR QUALITY AND CLIMATIC FACTORS

10.0 AIR QUALITY AND CLIMATIC FACTORS .0 AIR QUALITY AND CLIMATIC FACTORS.1 ASSESSMENT METHODOLOGY.1.1 General Section 39 (2) (b) (ii) of the Transport (Railway Infrastructure) Act 2001, requires that proposed developments are examined in

More information

No. 138 /PS-MS/MPPCB/SEAC/TOR (75)/2011 Bhopal, dt. 03 /06/2011. Env. Consultant: Créative Enviro Service, Bhopal. (SN-29)

No. 138 /PS-MS/MPPCB/SEAC/TOR (75)/2011 Bhopal, dt. 03 /06/2011. Env. Consultant: Créative Enviro Service, Bhopal. (SN-29) 1 By: Speed-Post State Level Expert Appraisal Committee (Formed as per S.O. no. 1533 dated 14 th Sept 2006 of Government of India, Ministry of Environment & Forests) PARYAWARAN PARISAR, E-5, ARERA COLONY,

More information

TABLE OF CONTENTS LIST OF FIGURES. Mt Arthur Coal Open Cut Modification Environmental Assessment

TABLE OF CONTENTS LIST OF FIGURES. Mt Arthur Coal Open Cut Modification Environmental Assessment Executive Summary TABLE OF CONTENTS ES1 BACKGROUND ES-1 ES2 EXISTING OPERATIONS ES-1 ES3 MODIFICATION OVERVIEW ES-1 ES4 CONSULTATION ES-1 ES5 COMMUNITY INITIATIVES AND INVOLVEMENT ES-3 ES6 ENVIRONMENTAL

More information

Trenches combined with living hedges or grass lines Rwanda - Imiringoti

Trenches combined with living hedges or grass lines Rwanda - Imiringoti Trenches combined with living hedges or grass lines Rwanda - Imiringoti Trenches combined with living hedges or grass lines are slow-forming terraces to control soil erosion by changing the length of the

More information

Application for Gas Exploration and Production

Application for Gas Exploration and Production 1800 Washington Blvd. Suite 655 Baltimore Maryland 21230 Application for Gas Exploration and Production This application is to be used to obtain a permit to Drill and Operate a well, within the State for

More information

06/01851/MIN CONSTRUCTION OF A NOISE ATTENUATION BUND AT Hermitage Farm, Newport Road, Moulsoe FOR NGW and EF Richards

06/01851/MIN CONSTRUCTION OF A NOISE ATTENUATION BUND AT Hermitage Farm, Newport Road, Moulsoe FOR NGW and EF Richards 06/01851/MIN CONSTRUCTION OF A NOISE ATTENUATION BUND AT Hermitage Farm, Newport Road, Moulsoe FOR NGW and EF Richards THE APPLICATION Planning permission is sought for the construction of a noise attenuation

More information

Max. building height (m)

Max. building height (m) Environmental Management Plan (EMP) for Himalaya Falaknuma by Himalaya Developers Ahmedabad No. Particulars Details 1. Proposal for New Project 2. Type of Project and Commercial Building Construction Project

More information

ENVIRONMENTAL MONITORING PROGRAMME

ENVIRONMENTAL MONITORING PROGRAMME Stage-I (2x800 MW) Page 1 5 CHAPTER - VI ENVIRONMENTAL MONITORING PROGRAMME 6.0 OBJECTIVES Regular monitoring program the environmental parameters is essential to take into account the changes in the environment.

More information

General Permit No.: OHR Page 53 of 146

General Permit No.: OHR Page 53 of 146 Page 53 of 146 Part 8 Sector-Specific Requirements for Industrial Activity Subpart J Sector J Non-Metallic Mineral Mining and Dressing. You shall comply with Part 8 sector-specific requirements associated

More information

Summary of Preparatory Study

Summary of Preparatory Study Summary of Preparatory Study 1. Title of the Cooperation Project, Relevant Project Report Preparatory Survey on the Project for the Establishment of Rural Water Supply System in Kambia Town in the Republic

More information

Madanpur South Coal Block Hasdo-Arand Coal Field Dist: Korba, State : Chhatisgarh

Madanpur South Coal Block Hasdo-Arand Coal Field Dist: Korba, State : Chhatisgarh EXECUTIVE SUMMARY OF RAPID ENVIRONMENTAL IMPACT ASSESSMENT AND ENVIRONMENTAL MANAGEMENT PLAN FOR Madanpur South Coal Block Hasdo-Arand Coal Field Dist: Korba, State : Chhatisgarh OF Madanpur South Coal

More information

CHAPTER-1 INTRODUCTION

CHAPTER-1 INTRODUCTION - 1 - CHAPTER-1 INTRODUCTION Profile & Background of the Proponent: The Project proponent Smt. Raziya Khanum Proprietor of M/s. Raj Minerals has been in the trade of Mining & Marketing for more than 25

More information

Dust generation/ Air pollution. Noise and vibration. Water pollution. Drainage and sedimentation

Dust generation/ Air pollution. Noise and vibration. Water pollution. Drainage and sedimentation Energy Resilience for Climate Adaptation Project (ERCAP) Environmental Code of Practice (ECOP) for COMPONENT 2: Demonstration Measures to Enhance Resilience of Energy Sector (Pilot for Strengthening Transmission

More information

Executive Summary Page 1 EXECUTIVE SUMMARY

Executive Summary Page 1 EXECUTIVE SUMMARY Executive Summary Page 1 1.1 Introduction EXECUTIVE SUMMARY Madhya Pradesh Road Development Corporation Ltd. (MPRDC), decided to take up the upgradation, rehabilitation and widening of various state highway

More information

Annex F Scoping Checklist

Annex F Scoping Checklist Scoping Checklist Table F1: Scoping Checklist Table. Questions to be considered in Scoping /? Which Characteristics of the Project 1. Will construction, operation or decommissioning of the Project involve

More information

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department 2017 [Type a quote from the document or the summary of an interesting point. You can position the text box anywhere in the document. Use the Drawing Tools tab to change the formatting of the pull quote

More information

SHREE CEMENT LIMITED; RAS (PALI) RAJASTHAN COMPLIANCE STATUS OF ENVIRONMENT CLEARANCE LETTER NO.: J-11011/981/2008-IA-II (I) dated: February 27, 2010

SHREE CEMENT LIMITED; RAS (PALI) RAJASTHAN COMPLIANCE STATUS OF ENVIRONMENT CLEARANCE LETTER NO.: J-11011/981/2008-IA-II (I) dated: February 27, 2010 SHREE CEMENT LIMITED; RAS (PALI) RAJASTHAN COMPLIANCE STATUS OF ENVIRONMENT CLEARANCE LETTER NO.: J-11011/981/2008-IA-II (I) dated: February 27, 2010 A Specific Conditions Compliances status (i) (ii) (iii)

More information

REPORT OF SAND STONE MINING PROJECT (KHATADARI Q.L. No. 178 FOR

REPORT OF SAND STONE MINING PROJECT (KHATADARI Q.L. No. 178 FOR REPORT OF SAND STONE MINING PROJECT (KHATADARI Q.L. No. 178 FOR Near Village Tehsil District State Capacity Lease Area Category of Project Project Cost KANTBARA BIJOLIYA Bhilwara Rajasthan 36561 TPA of

More information

MIDC, Nagpur Expansion of Existing Butibori Industrial Area (BIA Phase II) - Form-1

MIDC, Nagpur Expansion of Existing Butibori Industrial Area (BIA Phase II) - Form-1 ANNEXURE I SITE LOCATION MAP Building Environment (India) Pvt. Ltd 1 ANNEXURE II LAYOUT PLAN Building Environment (India) Pvt. Ltd 2 ANNEXURE III LAND DETAILS Sr. No. LAND DETAILS (In Ha.) 1. LARGE SIZE

More information

APPENDIX H AIR DISPERSION MODELLING REPORT BY PROJECT MANAGEMENT LTD. (REF. CHAPTER 11 AIR QUALITY AND CLIMATIC FACTORS)

APPENDIX H AIR DISPERSION MODELLING REPORT BY PROJECT MANAGEMENT LTD. (REF. CHAPTER 11 AIR QUALITY AND CLIMATIC FACTORS) 101050.22.RP.0001 A Environmental Impact Statement 15 th April 2005 APPENDIX H AIR DISPERSION MODELLING REPORT BY PROJECT MANAGEMENT LTD. (REF. CHAPTER 11 AIR QUALITY AND CLIMATIC FACTORS) S:\Projects\190900\101050

More information

SP Old Florida Investment Resources, LLC SMR Aggregates SR 64 Borrow Pit (DTS # )

SP Old Florida Investment Resources, LLC SMR Aggregates SR 64 Borrow Pit (DTS # ) H.O. 03/24/14 SP-14-01 Old Florida Investment Resources, LLC SMR Aggregates SR 64 Borrow Pit (DTS #201400001) Request: Approval of a Special Permit for major earthmoving in the A (General Agriculture)

More information

North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA)

North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA) SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA) Proposed at: Bonda Industrial

More information

TES Industrial Development SW ¼ SEC Lacombe County Outline Plan

TES Industrial Development SW ¼ SEC Lacombe County Outline Plan TES Industrial Development Lacombe County Outline Plan 112849297 June 2012 am v:\1128\active\112849297\07_reports_studies\rpt_tes_20120508.doc i Table of Contents 1.0 INTRODUCTION... 1 1.1 PURPOSE... 1

More information

Strategic mine planning of surface mining projects incorporating sustainability concepts

Strategic mine planning of surface mining projects incorporating sustainability concepts 6th International Conference on Sustainable Development in the 645 Strategic mine planning of surface mining projects incorporating sustainability concepts C. Roumpos and E. Papacosta Public Power Corporation

More information

SCHEDULE. FORM A (Rule 3(1)) THE CERTIFICATE OF ENVIRONMENTAL CLEARANCE RULES 2001 APPLICATION FOR A CERTIFICATE OF ENVIRONMENTAL CLEARANCE

SCHEDULE. FORM A (Rule 3(1)) THE CERTIFICATE OF ENVIRONMENTAL CLEARANCE RULES 2001 APPLICATION FOR A CERTIFICATE OF ENVIRONMENTAL CLEARANCE SCHEDULE FORM A (Rule 3(1)) THE CERTIFICATE OF ENVIRONMENTAL CLEARANCE RULES 2001 APPLICATION FOR A CERTIFICATE OF ENVIRONMENTAL CLEARANCE This form must be completed in triplicate for any proposed activity

More information

Project Proponent: Shri Kuldeep Pratap Singh Bhati Page - 11

Project Proponent: Shri Kuldeep Pratap Singh Bhati Page - 11 1.0 EXECUTIVE SUMMARY This is a new mining lease of Ball Clay Silica Sand, M.L. No.- 48/2011, located near Village- Indo Ka Bala, Tehsil-Kolayati, District Bikaner (Rajasthan) over an area of 4.2464 hectares.

More information

COAL STOCKPILES IN INDIAN POWER PLANTS. H Ramakrishna TCE Consulting Engineers Limited 73/1, St Marks Road, Bangalore , Karnataka, India

COAL STOCKPILES IN INDIAN POWER PLANTS. H Ramakrishna TCE Consulting Engineers Limited 73/1, St Marks Road, Bangalore , Karnataka, India SUMMARY: Coal will be transported to the power plant by belt conveyors in case of pit head power plants. In case of power plants located far away from the mines, coal will be transported by rail. In some

More information

12 Oct Virama Karya presentation on South Coast Highway. Therefore require a new route expressway

12 Oct Virama Karya presentation on South Coast Highway. Therefore require a new route expressway in association with Design 151.66 Km (Existing Road Apr. 180 km) 2 OBJECTIVE: The Government of Timor Lestewishes to Engage Consultant to carry out the Preliminary, Detailed Engineering Design and Environment

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project of MANUFACTURING OF SYNTHETIC ORGANIC DYES (5 f B IND II) By SHREEJI BAPA DYE CHEM PLOT NO 1319 & 1320, PHASE-III, GIDC, VATVA, AHEMADABAD-382445, GUJARAT,

More information

EIA Notification of LESSEE TANT

EIA Notification of LESSEE TANT (other than fully mechanized) APPLICATION FOR EVIRONMENT CLEARANCE EIA tification 2006 and tification Dt.15.01.2016 (B2 Category) of Pranmati Soap Stonee Deposit (Khasra no. 60, 61, 63 and others) For

More information

Revised FORM - I & PRE-FEASIBILITY REPORT

Revised FORM - I & PRE-FEASIBILITY REPORT Hind Energy & Coal Beneficiaton (India) Ltd. [Change in Technology from Dry to Wet Type of Coal Washery in EC issued by MoEF letter vide no. J-11015/364/2009-IA-II(M) dated 21st May 2014] at Hindadih Village,

More information

Environmental Management Plan (EMP)

Environmental Management Plan (EMP) SE DELI GS DRIFT MI E ORA GE RIVER MI ES MI I G ACTIVITIES A D PROPOSED EW I PIT SLIMES DISPOSAL Environmental Management Plan (EMP) Compiled for: Namdeb Diamond Corporation (Pty) Ltd Compiled by: Unit

More information

hard reflecting surfaces close by (such as tall buildings) increasing noise levels by up to 3dB(A)

hard reflecting surfaces close by (such as tall buildings) increasing noise levels by up to 3dB(A) Noise Definition Noise is generally defined as unwanted sound. The noise from a fleet of heavy plant working twelve hours a day within 50m of some houses and always within 500m of a residential property

More information

Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until Non Technical Summary

Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until Non Technical Summary Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until 2035 Non Technical Summary SLR Consulting Limited Project Ref: 403.00079.00474

More information

Annesley Andalusite Mine: Section 24G Rectification Process. Consultation with community members 15 June 2017

Annesley Andalusite Mine: Section 24G Rectification Process. Consultation with community members 15 June 2017 Annesley Andalusite Mine: Section 24G Rectification Process Consultation with community members 15 June 2017 AGENDA Welcome and introduction Meeting protocol Purpose of the meeting Project background Project

More information

GOVERNMENT OF INDIA MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE. LOK SABHA STARRED QUESTION No. 334 TO BE ANSWERED ON

GOVERNMENT OF INDIA MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE. LOK SABHA STARRED QUESTION No. 334 TO BE ANSWERED ON GOVERNMENT OF INDIA MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE LOK SABHA STARRED QUESTION No. 334 TO BE ANSWERED ON 09.08.2016 Ecological Impact of Mining *334. SHRI JANARDAN SINGH SIGRIWAL state:

More information

Section XXV Preconstruction Assessments and Damage Mitigation Procedures

Section XXV Preconstruction Assessments and Damage Mitigation Procedures Section XXV Preconstruction Assessments and Damage Mitigation Procedures A. Introduction - In recent years, HRSD has received an increasing number of complaints from residents and locality staff regarding

More information

Environmental Information Worksheet

Environmental Information Worksheet Environmental Information Worksheet Water System Owner (Attach additional sheets if necessary) Needs and Alternatives Provide a brief narrative that describes: Current drinking water system needs. Project

More information

Infrastructure Development and Environment

Infrastructure Development and Environment Infrastructure Development and Environment Few Stories Lift irrigation from Chambal River No Development Zone around Numaligarh Refinery NH - 31 C passing through Jaldapara, Mahananda and Buxa Nh-72 cutting

More information

E. STORMWATER MANAGEMENT

E. STORMWATER MANAGEMENT E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson

More information

Rajasthan State Pollution Control Board

Rajasthan State Pollution Control Board M/s Raj West Power Private Limited Village- Bhadresh, Tehsil:Barmer District:Barmer Sub: Ref: Sir, Consent to Operate under section 25/26 of the Water (Prevention & Control of Pollution) Act, 1974 and

More information

Section 2 Proposal Description

Section 2 Proposal Description Section 2 Proposal Description 2. PROPOSAL DESCRIPTION 2.1 Overview The Proposal comprises the construction, operation and closure of mining at the J5 and Bungalbin East iron ore deposits and associated

More information