SOME COST IMPLICATIONS OF ELECTRIC POWER FACTOR CORRECTION AND LOAD MANAGEMENT
|
|
- Hugo Kelly
- 6 years ago
- Views:
Transcription
1 SOME COST IMPLICATIONS OF ELECTRIC POWER FACTOR CORRECTION AND LOAD MANAGEMENT BY HERCULES VISSER Dissertation submitted in partial fulfilment of the requirements for the degree Magister Philosphiae in Engineering Management In the Faculty of Engineering at the Rand Afrikaans University Supervisor: Prof. J.H. Pretorius Co. Supervisor: Prof. L. Pretorius May 2001
2 ACKNOWLEDGEMENTS I would like to thank my Creator for the ability and guidance He gave me during this study. Without His support, this work would not have been possible. What shall I render to the Lord For all His benefits toward me? Ps. 116:12 Then I would like to thank various people for their direct and indirect contributions to this research study: My wife, Ria, for her encouragement and support. Prof J.H. Pretorius and Prof L. Pretorious for the privilege to study under them and for their patience and wise guidance. "Everything should be made as simple as possible, but not simpler." Albert Einstein
3 SUMMARY Presently, ESKOM is rated as the fifth largest utility in the world that generates and distributes electricity power to their consumers at the lowest price per kilowatt-hour (kw.h). As a utility, ESKOM is the largest supplier of electrical energy in South Africa and is currently generating and distributing on demand to approximately 3000 consumers. This represents 92% of the South African market. ESKOM was selected as the utility supplying electrical energy for the purpose of this study. ESKOM's objective is to provide the means and systems by which the consumer can be satisfied with electricity at the most cost-effective manner. In order to integrate the consumers into these objectives, ESKOM took a decision in 1994 to change the supply tariff from active power (kw) to apparent power (kva) for a number of reasons: To establish a structure whereby the utility and the consumer can control the utilisation of electrical power supply to the consumer. To utilise demand and control through power factor correction and implementation of load management systems. To identify some cost implications of electrical power factor correction and load management. Consumers with kw maximum demand tariff options had little or no financial incentives to improve their low power factor (PF) by reducing their reactive current supply. Switching to (kva) maximum demand will involve steps to be taken to ensure that the reactive component is kept to a minimum with maximum power factor.
4 ESKOM has structured various tariff rates and charges with unique features that would accommodate the consumers in their demand side management and load cost requirements, which, when applied, will result in an efficient and cost effective load profile. These tariffs are designed to guide consumers automatically into an efficient way of using electrical power, as it is designed to recover both the capital investment and the operating cost within two to three years after installation of power factor correction equipment. ESKOM's concept of Time-of-use (TOU) periods for peak, standard and off-peak times during week, Saturday and Sunday periods is discussed as load management. Interruptible loads can be scheduled or shed to suit lower tariff rates and to avoid maximum demand charge. The concept of load management will change the operation pattern of the consumer's electricity demand whereby the consumer will have immediate technical and financial benefits. In the last chapter of this dissertation, a hypothetical case study addresses and concludes on some of the technical and cost implications of electrical power factor correction and load management as a successful and profitable solution to optimize electrical power supply to the consumer. By implementing the above, ESKOM ensures that the consumer utilizes the electrical power supply to its optimum level at the lowest cost per kilowatthour (kw.h) generated.
5 OPSOMMING ESKOM is tans die vyfde grootste verskaffer in die wereld wat elektriese drywing genereer en versprei na kliente teen die laagste eenheidsprys per kilowatt-uur (kw-uur). ESKOM is die grootste verskaffer van elektriese energie in Suid-Afrika en ontwikkel en versprei elektriesie energie op aanvraag na ongeveer 3000 kliente wat ± 92% van die Suid-Afrikaanse mark verteenwoordig. Vir die doel van hierdie studie word ESKOM gekies as die verskaffer van elektriese energie. ESKOM se doelwit is om middele en stelsels te voorsien wat tevredenheid sal besorg aan kliente sodat hulle die beste en mees effektiewe koste-voordeel van elektriese verbruik kan geniet. Om te verseker dat die klient 'n deelname in hierdie doelwitte het, het ESKOM 'n besluit gedurende 1994 geneem om die voorsieningstariewe van aktiewe drywing (kw) na skynbare drywing (kva) te verander vir 'n aantal redes: Om 'n struktuur daar te stel waarby die voorsiener en die klient die bestuur en benutting van elektriese drywingstoevoer optimaal kan beheer. Aanvraag en ladingsbeheer kan benut word deur arbeids-faktor regstelling en die implementering van lading bestuurstelsels. Om sekere koste-implikasies van elektriese en arbeids-faktor regstelling en ladingsbestuur te identifi seer. Kliente met (kw) maksimum aanvraag tarief-opsies het min of geen finansiele voordeel om sodoende die lae arbeidsfaktor (PF) te verbeter deur die reaktiewe stroom lewering te
6 verminder. Die oorskakeling na kva maksimum aanvraag sal tot gevolg he dat versekerde stappe geneem sal word om die reaktiewe komponente tot a minimum te beperk met 'n maksimum arbeidsfaktor. ESKOM het verskeie strukture met tariewe en unieke kenmerke wat die klient sal skik in sy terrein van bestuurs-aanvraag en ladingskoste vereistes. Wanneer dit wel geimplimenteer word, het dit doeltreffende en koste-effektiewe ladingsprofiele. Hierdie tariewe is ontwerp om die klient outomaties na 'n meer doeltreffende metode van die gebruik van elektriese ladingsbestuur te lei, omdat dit ontwerp is vir beide kapitaal belegging en bedryfskoste herwinning binne twee tot drie jaar na die installering van arbeidsfaktor regstellingstoerusting. ESKOM se konsep vir ladingsbestuur word bespreek en dit behels die gebruik van periodes van tye van drywingsverbruik (TOU) waaronder spits-, standaard- en laagtyd verduidelik word, betreffende weekstye, Saterdae en Sondagperiodes. Onderbroke ladings kan geskeduleer of gekanselleer word sodat die lae verbruikstariewe in aanmerking kan kom en maksimum aanvraag kostes vermy kan word. Hierdie konsep van ladingsbestuur sal die bedryfspatroon van die klient se elektriese aanvraag verander en daardeur sal die klient onmiddellike tegniese en finansiele voordeel geniet. `n Hipotetiese gevallestudie word aangespreek wat van die tegniese en koste implikasies van arbeidsfaktor-regstelling en ladingsbestuur as 'n suksesvolle en winsgewende oplossing uitwys en sodoende die kragvoorsiening na die klient optimaliseer. Deur die
7 bogenoemde to implimenteer, verseker ESKOM dat die klient elektriese kragvoorsiening optimaal sal aanwend teen die laagste koste per kilowatt-uur (kw-uur).
8 TABLE OF CONTENTS ACKNOWLEDGEMENTS SUMMARY CHAPTER 1 ELECTRICITY SUPPLY IN SOUTH AFRICA PAGE Introduction Historical background Presently Problem statement The structure of the study Objectives of power factor correction Conclusion 9 CHAPTER 2 POWER FACTOR CORRECTION 2.1 Introduction What is power factor correction (PFC) Constant kw correction The importance of power factor correction Some technical disadvantages of a poor power factor Some methods of obtaining a good power factor The need for power factor correction Technical reasons Economic reasons 20 TOC 1
9 2.7 The impact of poor power factor on the utility Factors affecting power factor levels Power factor measurement Capacitor Rating Conclusion 25 CHAPTER 3 TARIFF STRUCTURES OF THE UTILITY 3.1 Introduction The approach Tariffs Tariff options Time-of-use (TOU) tariffs Tariffs on power factor Cost implications for time-of-use Implication of tariffs Two-part tariffs Capital investment costs Running costs Conclusion 38 CHAPTER 4 LOAD MANAGEMENT 4.1 Introduction Load management planning 41 TOC 2
10 Planning Load Measurement categories Load factor Interruptible loads Interruptible electric service Appliance control Demand limitations Strategic conservation Energy management Time-of-use load scheduling ESKOM's Megaflex / Miniflex / Ruraflex ESKOM's night-save Time-of-use maximum demand The need for load shedding Primary load shedding Frequency load shedding Manual load shedding Maximum peak power demand shedding Demand control Conclusion 57 CHAPTER 5 CASE STUDY 5.1 Introduction 59 TOC 3
11 5.2 Problem statement Case study Approach to the case study Power supply and improvements Summary of the case study Conclusion 64 CHAPTER 6 CONCLUSIONS AND RECOMMENDATIONS 6.1 Final conclusion Recommendations 67 ANNEXURE TO THE CASE STUDY 7 Power supply and improvements Power load distribution 69 8 ESKOM's tariffs and charges for Annual energy cost before power factor correction Annual cost saving after power factor correction Annual energy cost saving after power factor correction Capital cost to improve power factor correction to Pay-back time on capital investment 72 9 Load management (LM) 73 TOC 4
12 9.1 Annual energy cost before load management Annual cost saving after power factor correction and load management Total annual cost saving after load management and power factor correction Compound amount of capital Equal payment series with compound amount after power factor correction Equal payment series with compound amount after load management Grand total compound amount on capital saving 75 LIST OF FIGURES LIST OF TABLES BIBLIOGRAPHY TOC 5
13 LIST OF FIGURES AND TABLES FIG. NO. DESCRIPTION CHAPTER PAGE 2.1 Power vector for constant kw Vector of active, apparent and reactive currents Vector angle between kw and kva with lagging power factor Wave-forms of leading power factor Daily demand versus power factor Comparison of Standard-rate Vector for free charge loads Increase of capacitance required as unity power factor is reached Average cost as a function of load factor Demand periods for weekdays Demand periods for night-save Typical demand profile without demand control Typical demand profile with demand control Power load distribution Annexure 69
14 8 ESKOM's tariffs and charges for 2001 Annexure Factory plant working (TOU) schedules Annexure Proposed change of (TOU) schedules for plant Annexure 70 TABLE NO. DESCRIPTION CHAPTER PAGE 4.1 Average time-of-use cost ESKOM tariffs and charges for Megaflex Annexure 70
15 CHAPTER 1 PROBLEM STATEMENT AND OBJECTIVES INTRODUCTION 1.1 HISTORICAL BACKGROUND On 5 June 1873, the British Minister of U.K. decided to change the farm Vooruitzicht in South Africa to Kimberley, the place that some time ago delivered the greatest diamond of all time, the Star of Africa. Kimberley had a population of and developed in a short period to the full status of a city. Steam trolley-bus services existed in 1881, which were replaced with electrical trolley-busses in South Africa has always been well advanced in the use of electricity. Kimberley had electric street lighting in 1882 before the City of London and only three years after Edison started supplying electricity from the Pearl Street Power Station in New York. The first electric reticulation system was commissioned in Kimberley in 1890, and Johannesburg Municipality began to supply electricity in 1891 [26]. Electricity supplies were provided in Pretoria, Cape Town, Durban, East London, Port Elizabeth, Bloemfontein and Pietermaritzburg by 1906 [43, 44]. "The need was recognized for a national electricity authority early in the 1920s and in terms of the Electricity Act of 1922 the Electricity Supply Commission (ESCOM, later changed to ESKOM) was formed by a notice in the Government Gazette of 6 March 1923" [26, 40]. Page 1
16 A cheap and abundant supply of electricity was provided by ESKOM throughout South Africa [42, 5]. In less than thirty (30) years, ESKOM owned and operated six electricity undertakings. Each undertaking generated and supplied power to the major load centres throughout the country via a transmission network system. For ESKOM to meet the rapid increase in power demand, they had to build seven new power stations between [41, 43]. "South Africa's first nuclear station using sets of about 1000 MW rating was commissioned near Cape Town in 1982" [26]. Up to 1970, virtually all generation was done in coal-fired stations. The world's largest dry-cooling coal power station, Matimba, was finally commissioned in 1995 near Ellisras in South Africa. ESKOM is rated as the world's fifth largest utility in the supply of electrical power and the lowest cost producers of electricity in the world. (ESKOM's Annual Report 1999) [41]. 1.2 PRESENTLY South Africa has, until recently, been in a position where the utility supplying electrical energy to the different consumer sectors, had adequate capacity to supply its consumers. This situation is rapidly changing due to various factors. ESKOM has introduced a pilot project aimed at the development and introduction of a real-time pricing tariff to its consumers. There are a number of factors that affect the electricity cost to consumers, each of which can be managed by the consumer in order to reduce a consumer's electricity bill. Page 2
17 1.3 PROBLEM STATEMENT For many years, the gold mines and large power users enjoyed a special dispensation with respect to electricity in the previous ESKOM-era structure via kilowatt-hour (kw.h) tariff rate [25, 40]. The mines and other large consumers enjoyed kw maximum demand tariff as opposed to the kva maximum demand tariff for the rest of the country. A one-hour block demand integrating period was allowed to calculate the kw maximum demand in contrast to the half-hour block demand integrating period for the kva maximum demand tariff. ESKOM specified that consumers use the kw maximum demand tariff to maintain an average power factor for each one-hour integrating period to be greater than 0,85 (i.e. the kvar.h units consumed to be less than 62% of the kilowatt-hour units consumed, for each integrating period). This was seldom enforced on the consumers with no effect of any financial penalty [25, 40]. Many consumers on the kw maximum demand tariff option had power factors below the contractual limits as there was little or no financial incentive due to the special dispensation for improvement. Consumers on the half-hour kva demand tariff paid significantly more than consumers on the one-hour kw demand tariff for electricity. However, notification was given to all kw demand tariff users that their privileged position would be terminated. Financial opportunities were made available to change to a half-hour kva demand tariff and the simultaneous installation of power factor correction equipment [25]. Page 3
18 It was announced in an advertisement in the Business Day (11 January 1998) that "ESKOM proposed an amendment to standard prices and the promulgation of a charge for excess demand on Standard-rate and Night-save tariffs" [25]. With effect from 1 April 1998, ESKOM introduced charges for excess demand on kw demand consumers whose power factor was below 0,85, based on the kva and kw demand readings in the one-hour block interval during which the kw maximum demand was registered, as follows: "Excess demand = (kva demand x 0,85) (kw demand)". (1.1) It was then decided that active power (kw) demand consumers with a power factor at maximum demand of less than 0,85, would be financially penalised [25]. For the following four years, the Standard-rate and Night-save active power (kw) demand charges were progressively increased by 1,42% per annum above the average annual increase applicable to the apparent power (kva) demand tariff. The implementation of the above actions turned out that the apparent power (kva) demand tariff was more attractive to the consumers. This resulted that after a few years, kw demand consumers with a power factor greater than 0,85, benefit more by changing to kva demand tariff, with effectively no cost penalty, and with the opportunity of very significant cost savings in their electricity bill by installing power factor correction equipment" [25]. Page 4
19 Distribution power economy, a company in load management, offered a comprehensive tariff analysis and tariff impact study service. This included design, engineering, supply, installation and management of effective power factor correction and demand side management projects. In most cases, these projects can be fully financed by the savings in the electricity bill effected by the installation of the power factor correction equipment. This capital outlay on the power factor equipment was usually paid back within one to two years, which was indeed a good investment opportunity [25]. 1.4 THE STRUCTURE OF THE STUDY In the light of the above mentioned historical background and problem statement, this study will cover some cost implications of power factor correction and load management that are considered to be necessary to improve the utilisation of electrical power supply to the consumer. The following factors will be covered in Chapter 2, i.e. what is power factor correction, the relationship between active power (kw), apparent power (kva) and reactive power (kvar), the importance of power factor correction, technical and economical reasons affecting the power factor (PF) levels. The tariff structure in Chapter 3 will address the impact of the various tariff options for the consumer that are applicable to power factor conditions, time-of-use tariffs and two-part tariffs. Load management is the second factor in this study Chapter 4 will cover load management planning, categories of load management, time-of-use (TOU), load scheduling, maximum demand control are all factors when implemented and managed correctly. This should reduce the load demand to the Page 5
20 consumer and ultimately turn into financial savings. A hypothetical case study in Chapter 5 addresses and concludes the above mentioned methods and implications with cost analysis, conclusions and final recommendations. 1.5 OBJECTIVES OF POWER FACTOR CORRECTION Financial benefits in the installation of certain specialised equipment can be achieved in an industrial or mining installation in the following three areas: "Savings on electrical tariff charges. Enabling additional installed capacity without additional cost. Increased operational efficiency of electrical equipment, including reduction of maintenance costs" [24]. Any sizable electrical system is usually charged with a tow-part tariff by nature: "A unit charge based on the number of units consumed per month. A charge based on the highest half hour (or one hour) maximum demand over a monthly period" [24]. Currently, there are two methods in operation to measure maximum demand: kva (kilo-volt Amp), and kw (kilowatt). ESKOM prefers to measure maximum demand in apparent power (kva), and it is now mandatory for all new installations to be installed and charged on this basis. The active power (kw) method is in the process of being phased out, and certain financial incentives for existing installations to switch from active power (kw) to apparent Page 6
21 power (kva) basis have been offered by ESKOM. The apparent power (kva) of a load comprises two components: The kw or active component (which can be converted directly into useful work), and The kvar or reactive component (which cannot be converted directly into useful work) [24, 25]. The reactive component of electrical load indicates the measure of the power factor of an installation. The utilisation of items of equipment that has inductance and requires magnetic fields to operate (i.e. electric motors and transformers) tends to have higher reactive components. To improve the efficiency of the plant, system or electrical distribution network, the reactive component is to be kept to a minimum throughout the system. The power factor in a system ranges theoretically from zero to one. When a plant or system has a power factor of one, the operation has maximum efficiency. As the system current drops, it provides a clear evidence that the system's efficiency has improved when plant losses decrease and output increases, i.e. less motor burn-outs and the starting of motors improves. ESKOM' s new charge for maximum demand on installations (apparent power) is directly related to the power factor, as is shown in the following equation: [24] Power factor = active power (kw) (1.2) apparent power (kva) S 2 p2 ± Q2 Where S = apparent power P = active power Q = reactive power Page 7
22 When the reactive component decreases, the apparent power component will decrease, the power factor will increase and the maximum demand charge will decrease, which will result in a tangible cost saving. However, the maximum demand charge is not affected by the power factor for those installations still operating on active power (kw) maximum demand basis. Depending on the nature of the electricity usage by the operation, a strategy could be devised to reduce the maximum demand charge. Switching to apparent power (kva) maximum demand will involve steps to be taken to ensure the measurement basis of the strategy is and that the reactive component is kept at a minimum, with maximum power factor [8, 24, 25, 40]. Various methods are available to ensure that a high power factor of 0,98 to 0,99 is maintained during plant operation. This will require the correct design and installation of specialised equipment for the purposes of power factor correction. The operational efficiencies of the installation will also enhance the importance and attractiveness of such power factor equipment [24]. Page 8
23 1.6 CONCLUSION Power factor correction with its attendant cost savings both in the short and long term are an issue, which should be investigated thoroughly by all managers who are serious about improving their financial performance. The system to perform a complete service analysis in the area of power factor correction is available from preliminary investigation through to design, supply and implementation. To reveal the possible cost savings and pay-back period, preliminary sophisticated measuring and reporting facilities could be used and followed by a more tailored design, manufacture, installation and maintenance plan. Page 9
24 CHAPTER 2 POWER FACTOR CORRECTION 2.1 INTRODUCTION ESKOM changed the power supply tariffs from active power (kw) to apparent power (kva) in 1994 and introduced a maximum demand tariff that aims at forcing the consumer to improve the power factor to Eric Granger [5] states that power factor correction is a method of using alternating current in the most economic fashion. It can reduce current, reduce losses and, as a possible consequence, reduce electricity charges. It is a method ensuring that the voltage and current remain substantially in phase with each other, producing the optimum power [5]. This chapter will cover the following aspects of power factor correction: What is power factor correction [4]? Constant active power (kw) correction. The importance of power factor correction [5]. Some technical disadvantages of a poor power factor [3]. Some methods of obtaining a good power factor [3]. The need for power factor correction [1]. The impact of poor power factor on the utility [1, 5]. Factors affecting power factor levels. Page 10
25 Power factor measurements. 2.2 WHAT IS POWER FACTOR CORRECTION? All electrical operational plants comprise two kinds of current, namely active current and the reactive component. These components effect the power factor Cos 4). The definition of power factor as stated by Theodore Wildi is "the power factor of an alternating current circuit is the ratio of the active power P to the apparent power S, given by the equation; Power factor = P / S = Cos 4) (2.1) Where P = active power (W) S = apparent power (VA)" [6] The active current (or working) is the current that the equipment requires for useful work, while the reactive current is the wattless current that is produced by different types of loads. W.G. Hutcheon defines that the power factor may be expressed as the ratio of working current in a circuit to the total current in that circuit, and its value is exactly equal to the ratio of active power (kw) or the working power to the total apparent power (kva) [4]. Power factor = Iw = active power (kw) = Cos (2.2) It apparent power (kva) Where Iw = working current = active current It = total current = apparent current Page 11
26 2.2.1 Constant active power (kw) correction If static capacitors are used to correct a power factor from Cos 4)1 to Cos 4)2, the apparent power (kva) diagram is as in Figure 2.1. P kw Q kvar Figure 2.1 Power vector diagram for constant active power (kw POP Cos 4 = active power (kw) apparent power (kva) OA = kva of load before correction. OD = kw of load. DA = kvar lagging before correction (This indicates an inductive load). OB = kva of load after correction. DB = kvar lagging after correction. AB = the required leading kvar. = DA DB = OD (Tan (I) 1 Tan 4) 2)- [4, 8, 10]. Page 12
27 The total current required by a plant comprises two kinds of currents, namely working current (in phase with the voltage) and reactive current (90 lagging the voltage). The former is the current that is converted by the equipment into useful work (active current), and the latter is the current that is required to produce the magnetic flux necessary for the operation of induction equipment, and is named the magnetising current (reactive current) or wattless current. The working current flows in phase with the voltage and the inductive reactive current lags the voltage by exactly 90. The total current and the reactive currents are vectorially represented in Figure 2.2 and Figure 2.3. Active current l w Voltage Reactive current I t Apparent current I t Figure 2.2 Vectors of active, apparent and reactive currents 1101 The vector diagram, as indicated in Figure 2.3 represents the working current (Iw) and the reactive current Ir. The total current is defined as follows: It = ir 2 (2.3) The power components in terms of voltage and current components are: Apparent power (kva) = V(kV) x It (total current in It) Active power (kw) = V(kV) x Iw (working current in Iw) Reactive power (kvar) = V(kV) x Ir (reactive current in Ir) Page 13
28 NOTE: Voltage and current values are root mean square (RMS) values. From the vector diagram, the power factor may also be expressed as the ratio of working current in a circuit to the total current in the circuit [5, 45, 49]. Figure 2.3 Vector angle between active power (kw) and apparent power (kva) with lagging power Factor 110] 2.3 THE IMPORTANCE OF POWER FACTOR CORRECTION Without adequate power factor correction, any industrial load can draw as much as twice the current that is required. This means that a large element of apparent current is drawn from the supply, causing losses in the distribution cables and equipment, etc. These losses have a great impact on the sizes of cables and system equipment that will influence the capital lay-out of the plant [5, 20]. By improving the power factor, the reactive current component will be reduced, which should have a cost saving for the consumer [46]. In 1998, ESKOM undertook to lead the way in energy conservation by replacing the biggest commercial office lighting development in South Africa at Megawatt Park. ESKOM modernised, standardised and upgraded the efficiency of the office lighting, resulting in improving the system's power factor, thereby maximizing the economic benefit of the power usage [2]. Page 14
29 The purpose was to reduce the reactive power costs of Megawatt Park enough to compensate for the additional capital outlay [2. 4, 5]. "The improvement had the following advantages: Reduce energy consumption figures kilowatt-hour (kw.h). Lower contribution of the lighting installation to the total building maximum demand apparent power (kva). Correction of the lighting's power factor to Flicker free fluorescent lighting. Lighting levels continuously within the range specified. Longer lamp life. Lower lamp lumen depreciation over lamp life time. Reduced maintenance cost. Better colour rendition. Reduced noise levels associated with the lighting installation. Reduced heat load to building air conditioning. Improved productivity of building users" [2]. The cost to upgrade the lighting at Megawatt Park was in the region of R3.7 million. The energy cost saving per year was approximately R , with additional maintenance savings of R The power kilowatt-hour (kw.h) annual saving resulted in approximately R5,5 million capital, which was paid back over four years [I, 2, 52]. From this example, it is clear that power factor correction offers an obvious and immediate cost benefit to consumers who are charged on apparent power (kva) demand with improved power factor system [2, 5]. Page 15
30 In South Africa, electricity power tariff charges vary across the country due to area and point of supply, i.e. domestic loads will be less costly to supply than an industrial township or agricultural land. Industrial sites are measured and charged with a maximum tariff charge because the amount of inductive equipment working from the power supply is more exposed to power factor correction system due to the apparent current factor (kva). Most of the fluorescent light fittings are equipped with power factor correction capacitors, whereas induction motors and transformers, which are uncorrected, contribute towards poor power factor values [4, 5, 52]. Fluorescent lights in use represent a steady load, because they are fitted with capacitors in the factory and often this installation tends to be forgotten. 2.4 SOME TECHNICAL DISADVANTAGES OF POOR POWER FACTOR The most obvious drawback for a load of low power factor is that the current necessary is greater than for the ideal case of unity power factor. A low power factor will result in low voltage regulation on a transmission line and expensive appliances, i.e. step-up transformers might be needed to ensure that the end-voltage regulation meets the sending end voltage. As induction motor torque is proportional to the square of the applied voltage, a large sudden fall in the voltage could cause the motor to come to a halt [3, 49]. The amount of active power (kw) is not affected by the power factor, but it will be less than the apparent power (kva) capacity of the central station that is affected by the value of the power factor. Although power generators may be Page 16
31 fully loaded from an output point of view, the load may still be in demand for more current as the generators will not be delivering their full load of true power [3, 49]. 2.5 SOME METHODS OF OBTAINING A GOOD POWER FACTOR "The obvious method is to use, wherever possible, apparatus which has good power factor" [3]. The installation of a capacitor has the effect of decreasing the current taken from the supply but does not decrease the excitation current actively circulating round the capacitor-motor circuit. The current flowing through the capacitor will lead the voltage by 90. The best position for a capacitor is, theoretically, as close as possible to the motor, directly across the motor terminals. This will allow the use of a smaller size of feeder owing to the reduced current taken from the supply. The capacitor should be individually connected to a motor and controlled by the same switch as the motor so that it is brought into service when required. Group and block connection of capacitors requires some method of control as capacitance must be taken out of service when not required. Automatic control is the best type of control. Most of the reactive power can be produced by capacitors installed in parallel with the motor, either as the motor terminals or as starter terminals. When dimensioning the cable to the capacitor, fuses or backup circuit breakers protect the supply cable and the motor. Therefore, the capacitor cable must be rated such that it is protected by a short-circuit device. When setting any over-current relays, the effect of the capacitor is to reduce the current and this must be taken into account. Page 17
32 It is sometimes possible to correct power factor by means of a common capacitor, such as discharge lamps controlled by a three-phase contactor. Therefore, it does not warrant the installation of many small capacitors due to the higher cost per reactive power (kvar), and the cost of installation and possible cable with glands. A good option would then be that of a centralised power factor correction system, connected to the main distribution board. The reactive power regulator controls the switching of the capacitor steps according to the varying reactive power requirements in an automatic capacitor bank. Inductive and capacitive operating limits for the regulator are set and the amount of reactive power in the system is maintained within these limits, which would diminish problems of over-compensation [48]. Care must be taken in rating cables and feeder circuit breakers connecting power factor correction equipment to the distribution board because capacitors draw a constant current at constant voltage with no diversity factor or load variation, as is the case with other loads, such as motors driving compressors. Capacitor reactive power (kvar) is proportional to the square of the applied voltage and changes in voltage significantly increase the current drawn by the capacitors. Three-phase induction motors are normally supplied uncorrected, which will contribute towards poor power factor figures. Items representing a varying working load, e.g. induction motors, may need a degree of power factor correction. This will vary with their work load, and automatic switching of capacitors is available for this purpose in order to serve complete factories or equipment complexes. Correcting the power factor of individual motors is another factor to be considered. Large motors are generally fitted with their own phase advancer. Small motors can be looked after by installing batteries of static capacitors across the supply terminals. Page 18
33 The efficiency of the modern capacitors is very high as the dielectric losses are less than 0,5% of the apparent power (kva) capacity of the capacitor. Very little error is therefore made by assuming that they take a current that leads the applied voltage by exactly 90 [3]. 2.6 THE NEED FOR POWER FACTOR CORRECTION "Apart from the technical benefits to the utility (i.e. to mitigate the problems enumerated above), there are also significant advantages for consumers to improve their power factors" [1]. Power factor correction capacitor generally pay for themselves within two or three years, after which any further savings accumulated, will be to the benefit of the client [1, 5, 24]. In the case study in Chapter 5, the power factor was improved from 0.7 to 0.96, and the capital invested was paid back within 2.88 years. Energy losses in the consumer's own networks are very much a hidden factor, and lost energy at full tariff purchased, could also be a great saving investment [4, 5]. Both the consumer and the utility network capacity are affected if the power factor is low or improved [1, 49, 52]. A low plant operating power factor may result in overloaded distribution supply and transformers, and increased copper losses in equipment, which result in a reduced voltage level. Improvement in the power factor can reduce the power losses, raise the voltage, reduce system losses and reduce power cost. Poor power factor has an increasing maintenance burden on any power plant and switch-gear, but with an improved power factor system it should require less maintenance and be less costly to operate [1]. Page 19
34 2.6.1 Technical Reasons If the power factor was improved to 0,96, the plant would have used much less current and would therefore have extra active (kw) power in reserve. The voltage drop is proportional to the current and will therefore decrease with the current. It therefore follows that the closer the power factor correction equipment is situated to the source of low power factor (load), the greater will be the benefits and results accrued from the correction equipment. It is clear from the above that the apparent power reduces as the power factor improves [6, 8]. The result will be that the apparent current (kva) after the correction is less than before the correction, which means that the live currents have also reduced in the same ratio as the total power. Therefore, the plant connected to the correction equipment will not be as heavily loaded as before the correction Economic Reasons From a technical point of view, the kilowatt-hour (kw.h) savings might be small due to the losses in the cables, but without power factor improvement the cable might have to be much larger in cross sectional area in order to carry the apparent power. This includes other plant equipment, which will result in an additional capital lay-out [8, 59]. The main reason for power factor correction is the saving of electrical charges. The distribution and transmission network of the utilities has to accommodate various supply and load conditions on their systems, as consumers individually have different demands in loading, peak currents, maximum demand and power factor levels [8, 14, Page 20
35 21]. Therefore, the utilities apply a two- or even a three-part tariff. The two-part tariff consists of energy kilowatt-hour (kw.h) charge that indicates the total usage of energy supplied to the consumer during the month. "In certain cases where the utility wishes to reduce the peak during a certain period of the day, it introduces a second demand charge for the period of the day. This charge compensates users who reduce their own demand during the utility's peak demand period" [8, 15]. Consumers that are charged on apparent power (kva) demand tariff can only benefit with an improved power factor system. Figure 2.1 indicates that active power (kw) demand is not affected by power factor correction. The tariffs across the country vary largely due to distance, demand and consumer needs [8, 14]. 2.7 THE IMPACT OF POOR POWER FACTOR ON THE UTILITY Poor power factor impacts negatively on the costs of the system in three main areas: Poor power factor will cause the network capacity not to be fully utilized, i.e. 0,5 power factor will only supply 50% active power. This will result in a premature (unnecessary) upgrade of the system instead of only improving the power factor [1, 5, 52]. Excessive energy losses are due to high current and low voltage from motors and transformers in their magnetic fields [6, 49]. The cost of compensating equipment such as static VAR compensators (SVCs) as well as the cost of generating reactive power, remains an expensive investment by running generators sets in synchronous condenser mode [1]. Static compensation delivers or draws reactive power in order to stabilize the voltage [1, 6]. Page 21
36 2.8 FACTORS AFFECTING POWER FACTOR LEVELS Power factor has different levels due to the various loads on plant systems that vary with load supply. The maximum demand has an important influence on the power factor rating. The consumer's previous twelve-months electricity account coupled with a good overall knowledge of plant operation and load measurement would be a useful evaluation for the power factor correction specification [8, 20, 40]. 2.9 POWER FACTOR MEASUREMENT Load measurement exposes extensive savings as load management and reactive power compensation go hand in hand. Load management should start with measurement and planning. The following two options are raised in this regard [14, 39, 40]: Power factor usually varies with load [14]. Measurement of the power factor is not only Cos (I) as harmonics can influence current wave-forms from zero crossing as shown in Figure 2.4, and a more rigorous way of measuring power factor must be utilised. Spot measurements could be misleading as the power factor normally varies with the load [33]. Page 22
37 E ct I f I Time (ms) Figure 2.4 Wave -forms of lagging power factor [39J Before power factor correction or load management can be implemented, it would be sensible to carry out a power survey. The survey could be done with a commercial power analysis. KVA 200 Demand and Power Factor PF Powe ea 0 I Daily demon /19 06:00 Figure 2.5 Daily demands versus power factor [ /19 22:00:00 06/20 14:00:00 Test Time /21 06:00:00 Page 23
38 Figure 2.5 is a graphic representation of the correlation between the power factor and daily demand which indicates that the power factor varies with the load. Controlling the demand must be undertaken with a detailed knowledge of the nature of the load, the consumption pattern, the power factor variation and an understanding of the likely impact of changes in the plant or environment [14, 39]. "Consider the following example: 80% of the total load consists of four large motors. It would possibly be more economical to install capacitors directly onto the motor terminals, as this would eliminate the need for costly control switch-gear for the capacitors" [8]. The following points are to be noted: Do not fit the motor with a capacitor that is too large, as this could cause the motor to become self-excited when the supply is temporarily disconnected. The motor could generate an over-voltage, which might cause connected lamps to burn out and the failure of the motor insulation due to over-voltages. As the motor current decreases, one will have to reset the motor protection. If the load is constant the load factor should almost be at unity. A fixed capacitance could be fitted to the load into the busbars of the distribution switchboard [8]. However, if the load drops, the power factor of the system will become leading and the system could become unstable [6, 8, 55]. It is essential to monitor the amount of kilovars on the distribution system, and to switch capacitors in and out depending on the load demand. These could be managed by using power factor relays. These relays sense the power factor of the distribution system and switch the capacitors of Page 24
39 the system on demand. The settings on the power factor relay determine the time delay between the switching of various steps CAPACITOR RATING There are many factors that must be taken into consideration when designing a power factor correction system [4, 8]. Increases in system voltage, the presence of harmonics and the actual tolerance of the capacitors will overload the capacitor rating. "One manufacturer derates his capacitor's so that it can take a 20% over-voltage, a 50% over-current and a 45% increase in power. The international electro-technical standard specification no.70 calls for a 10% over-voltage and a 30% over-current derating. These ratings are determined at an ambient temperature of 40 C. The recommended derating in power is 5% at 45 C, 15% at 50 C and 30% at 55 C" [8] CONCLUSION This chapter indicates the steps to be taken to improve the power factor and to what level of expense the consumer is exposed with a low power factor. As indicated in Figure 2.1, the power factor is the ratio between the 'active power P' and the `apparent power S', which is expressed as a percentage of the cosine angle between the active and apparent powers. It also indicates that the active power cannot exceed the apparent power. However, as the angle between `1 3' and 'S' increases, so does the reactive power 'Q', which indicates that the power factor is lagging as the load requires kilovars (kvar) from the power source. ESKOM has proven at Megawatt-Park office centre that by implementing power factor correction, both reactive power and the apparent cost were reduced, and the Page 25
40 life-cycle of the equipment was also improved due to the wattless current component. There are many methods and apparatus that can be applied to power factor correction. However, only capacitors will be covered in this dissertation. The need to improve power factor components has technical and financial advantages that outrate any form of low power factor components. The power factor of a system is determined mainly by the nature of the load itself, and a low power factor of 0.7 can be improved to 0.96 by installing capacitors. From the utility point of view, it reduces the real system load capacity due to the excessive energy losses and high currents that are far more valued than the cost involvement to implement power factor correction system to any plant operation. Before implementing any power factor correction system, it is advisable to perform a detailed plant analysis on both the technical and financial issues as referred to in order to assess the value and impact of the required power factor correction system. Page 26
41 CHAPTER 3 TARIFF STRUCTURES OF THE UTILITY 3.1 INTRODUCTION "Electricity tariffs are designed to recover both the costs associated with the actual generation of electrical energy and the considerable capital investment associated with the infrastructure to transmit and distribute this energy. The costs associated with generation are recovered by charging for the actual energy consumed, while the cost of transmitting the electrical energy is recovered by a maximum demand charge"[20, 21, 22]. The aim of an electric utility is to ensure that the energy generated and the distribution and transmission network are controlled, optimized and maintained to supply electricity on demand. Good management could be achieved if marginal cost pricing were used as an effective tool on the demand side [14, 18]. Fabrycky stated that "The term marginal cost pricing refers- specifically to an increase of output whose cost is barely covered by the monetary return derived from it" [62]. From the ESKOM 1999 Annual Report, it is clear that the above definition suits its purpose as it generates electricity power at a non-profit return, and as already stated, the lowest in the world. It is thus imperative that ESKOM also designs tariffs and charges to such a degree that they will fit the above definition with the scope that they will cover all the costs associated with the supply and demand of electrical power. "ESKOM announced that Page 27
42 by selling more kilowatt-hour (kw.h) during off-peak periods, the total peak demand could be reduced, which enables generating equipment to operate more effectively over longer periods of time. This would mean that there will be more electric power available without increasing of capital cost" [14]. 3.2 THE APPROACH "The constant adaptation between electricity supply and demand can be achieved in two ways: on the supply side, through the construction of additional facilities and on the demand side, by implementing tariffs, load management schemes and a commercial policy" [18]. When the demand changes, the supply system will also change as both the consumer and utility have installed capacity and have operating conditions of the system. These conditions have to be taken into account. In order to reach an overall optimum for the community as a whole, ESKOM decided to control the total load demand system. Implementation of appropriated tariffs and load management schemes to compare costs resulted in benefits for both the utility and consumer to be reflected by marginal generation and distribution costs. ESKOM, as the largest supplier of electricity, has certain pricing rules to follow: meeting the demand, minimising its production costs and selling at marginal costs. The consumer's electricity consumption pattern has a cost factor in the supply system which has been affected by the consumption via the tariff charge [16, 18, 40]. B.Lescoeur stated: "By selecting the alternative to minimise the cost, the consumer will choose the least cost alternative for the whole community" [18]. Page 28
43 All the differences in cost cannot be reflected, nor can all the costs verify the various kinds of supply. It is therefore necessary to equalise and limit the tariffs and metering as well as the installation costs to avoid excessive complexity of the tariffs. By selecting the correct tariff, consumers are often able to reduce their electricity bills without any further intervention. By selecting the right tariff and exploiting the tariff characteristics, consumers can make a positive impact on this important input cost. The utility must evaluate the larger energy user requirements and investigate possible electrical solutions to accommodate their needs of loads [15, 18]. Electrical solutions with competitive large development potential should accurately reflect the costs, and a tariff charge must be drawn up to suit the overall cost of the community. The electricity tariffs for large consumers are based on the consumption of energy and maximum demand, which measure both active power (kw) and apparent power (kva). The highest single demand recorded will be used to establish the consumer's annual charge to recover the capital and service-related costs of the energy supply [61]. 3.3 TARIFFS Each tariff has its own unique features. These features are a function of the tariff design objectives and a compromise between cost reflectiveness, demand side management pricing signals, simplicity, consumer requirements, etc. In order to be efficient and cost effective, it would be prudent for the consumer to execute a load profile analysis and then select the best tariff to suit the system's load profile. The analysis will also indicate the cost saving on the electricity bill and add operational time to the plant without any further intervention [11, 18, 53]. Page 29
South African Journal of Industrial Engineering November 2017 Vol 28(3) Special Edition, pp AUTOMATED ELECTRICITY BILL ANALYSIS IN SOUTH AFRICA
South African Journal of Industrial Engineering November 2017 Vol 28(3) Special Edition, pp 66-77 AUTOMATED ELECTRICITY BILL ANALYSIS IN SOUTH AFRICA P. Goosen 1 *, M.J. Mathews 1 & J.C. Vosloo 1 ARTICLE
More informationTariffs January 1, 2017
Tariffs January 1, 2017 Nova Scotia Power Inc. Tariffs & Regulations Approved by the Nova Scotia Utility and Review Board pursuant to The Public Utilities Act, R.S.N.S., 189,c.380 as amended Tariffs For
More informationMedium Voltage UPS Solutions - When and Why? Frank Herbener, Piller Group GmbH, Germany
Medium Voltage UPS Solutions - When and Why? Frank Herbener, Piller Group GmbH, Frank.Herbener@Piller.com, Germany 1 Contents 1 Scope 3 2 Power Demand and Distribution in today s Mission Critical Applications
More informationPower Factor Fundamentals
Power Factor Fundamentals What we will learn: Most Industrial loads require both Real power and Reactive power to produce useful work You pay for BOTH types of power Capacitors can supply the REACTIVE
More informationMeasurement and verification of a municipal water pumping project
Measurement and verification of a municipal water pumping project I E Bosman North-West University, Potchefstroom L J Grobler North-West University, Potchefstroom Abstract The processes that were followed
More informationNEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems
NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems SUBCHAPTER 9 NET METERING AND INTERCONNECTION STANDARDS FOR CLASS I
More informationFacility Interconnection Requirements
Facility Interconnection Effective 1/1/2016 1. Purpose Facility Interconnection Facility Interconnection (FAC-001-2) To avoid adverse impacts on the reliability of the Bulk Electric System (BES), RPU documents
More informationIMPORTANCE OF ENERGY EFFICIENCY: FROM THE PERSPECTIVE OF ELECTRICAL EQUIPMENTS
1B International Conference on Science & Technology: Applications in Industry & Education (2008) IMPORTANCE OF ENERGY EFFICIENCY: FROM THE PERSPECTIVE OF ELECTRICAL EQUIPMENTS Anwar Al-Mofleh, Soib Taib,
More informationInternational ejournals
ISSN 2249 5460 Available online at www.internationalejournals.com International ejournals International Journal of Mathematical Sciences, Technology and Humanities 21 (2011) 205 212 ENERGY CONTROL CENTER
More informationEE 741. Load Characteristics
EE 741 Load Characteristics Overview Some definitions Relation between load and loss factors Load models Load management Rate structure Metering Load forecasting Definitions Demand curve, maximum demand,
More informationEnergy Cost Reduction through Load Balancing & Load Shedding
white paper Energy Cost Reduction through Load Balancing & Load Shedding SCR controllers firing in phase angle degrade the power factor while increasing harmonics and electrical noise. A poor power factor
More informationAt Load Power Factor Correction Final Report August 2010
At Load Power Factor Correction Final Report August 2010 The New York State Energy Research and Development Authority (NYSERDA) is a public benefit corporation created in 1975 by the New York State Legislature.
More informationFAST POWER FACTOR REGULATOR. Computer-14df - xx - 144a INSTRUCTION MANUAL ( M / 00A ) (c) CIRCUTOR S.A.
FAST POWER FACTOR REGULATOR Computer-14df - xx - 144a INSTRUCTION MANUAL ( M 981 611 / 00A ) (c) CIRCUTOR S.A. -------- POWER FACTOR REGULATOR COMPUTER- 14f --------- Page 2 POWER FACTOR REGULATOR COMPUTER-
More informationImpacts of the Decentralized Wind Energy Resources on the Grid
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2013 Grid of the Future Symposium Impacts of the Decentralized Wind Energy Resources on the Grid Babak Enayati, PhD, Senior
More informationPV AND OTHER RENEWABLES THE FINANCIAL ADVANTAGE
PV AND OTHER RENEWABLES THE FINANCIAL ADVANTAGE Different Types of Renewables Most popular types: Solar, Wind & Biogas. Solar - uses the sun to generate electricity. Advantages: Sun is free. Passive source
More informationFixed Demand (Block Demand) The utility company sends a signal to synchronize the start of the Maximum Demand period.
Maximum demand control systems M 6 M.6.02 GB Maximum Demand Control There are three terms that appear on the majority of electric company bills: Active energy consumption (kw h) Reactive energy consumption
More informationStandard TPL Transmission System Planning Performance Requirements
A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon
More informationRate Design and Resource Planning
Rate Design and Resource Planning Rate Considerations and Resource Planning Decisions El Paso Electric Company New Mexico Public Advisory Group Meeting December 11, 2014 Rates and Resource Planning The
More informationThe ESP Handbook. Chapter 15 Obtaining Consumer Usage and Metering Information. Version 7.0 February 1, 2017
The ESP Handbook Chapter 15 Obtaining Consumer Usage and Metering Information Version 7.0 February 1, 2017 SCE is committed to providing timely and accurate information to its customers or their authorized
More informationUPS Electrical Design and. Installation. critica POWER SUPPLIES
UPS Electrical Design and critica POWER SUPPLIES Installation Important considerations for the electrical design and installation of UPS systems in mission critical applications Where Critical Power applications
More informationPolicy for determining capital contributions on Vector s electricity distribution networks. From 1 December 2017
Policy for determining capital contributions on Vector s electricity distribution networks From 1 December 2017 Pursuant to: Electricity Distribution Information Disclosure Determination 2012 1 Table of
More informationAGREEMENT FOR CONNECTION TO [EASTERN /LONDON / SOUTH EASTERN] POWER NETWORKS PLC S DISTRIBUTION SYSTEM
AGREEMENT FOR CONNECTION TO [EASTERN /LONDON / SOUTH EASTERN] POWER NETWORKS PLC S DISTRIBUTION SYSTEM BETWEEN AND (1) [Eastern / London / South Eastern] Power Networks plc Company Number [02366906 / 03929195
More informationTariff Circular & Tariff Schedules. (Effective from 01 st April 2015)
Tariff Circular & Tariff Schedules (Effective from 01 st April 2015) Madhya Gujarat Vij Company Limited Corporate Office, S.P. Vidyut Bhavan, Race Course, Vadodara-390 007 1465/2014 ANNEXURE: TARIFF SCHEDULE
More informationENERGY AND COST MODELLING OF WATER RETICULATION SYSTEMS IN DEEP-LEVEL GOLD MINES
ENERGY AND COST MODELLING OF WATER RETICULATION SYSTEMS IN DEEP-LEVEL GOLD MINES by Gregory Keith Murray Submitted in partial fulfilment of the requirements for the degree Master of Engineering (Electrical
More informationGeorge Ferreira Ex-ED, Electricity and Energy Nelson Mandela Bay Municipality Port Elizabeth, South Africa
George Ferreira Ex-ED, Electricity and Energy Nelson Mandela Bay Municipality Port Elizabeth, South Africa Overview The history of the NMBM - Pilot projects outcome - NMBM Financial trends What is a smart
More informationNational Water Demand Management Policy
National Water Demand Management Policy Introduction In 1997, the Ministry of Water and Irrigation developed Jordan s Water Strategy and the following four policies, which include: Water Utility Policy;
More informationElectricity generation, electricity consumption, system integration, production and consumption balance
Prof. Dr. Andrej Gubina University of Ljubljana, Faculty of Electrical Engineering Electricity generation, electricity consumption, system integration, production and consumption balance Maribor, Slovenia,
More informationAdvice on Power Factor and Accuracy of Temperature Dependant Outputs
Advice on Power Factor and Accuracy of Temperature Dependant Outputs REPORT WP03749-EE-RP-0001 Rev. 1 3 September 2009 Advice on Power Factor and Accuracy of Temperature Dependant Outputs REPORT WP03749-EE-RP-0001
More informationPreliminary Energy Analysis conducted at PEEKAY STEEL
Preliminary Energy Analysis conducted at PEEKAY STEEL In Foundry Section As part of the course EE6401 Energy Audit and Management, Instructed by Dr.Ashok. S, NIT Calicut during monsoon semester 2015 Submitted
More informationESP ENERGY SYSTEM PLANNING (PTY) LTD COMPANY EXPERIENCE (PROJECTS) Cons ulting Group
ENERGY SYSTEM PLANNING (PTY) LTD COMPANY EXPERIENCE (PROJECTS) Suite 2B, 08 Arnold Road, Rosebank, 2196, Johannesburg, South Africa Tel: +27 11 447 9852; Website: http://www.espcg.com Transaction advisory
More informationCHOPTANK ELECTRIC COOPERATIVE, INC. P.S.C. Md. No. 3 Fifth Revised Page No. 59 COGENERATION AND SMALL POWER PRODUCTION RATE SCHEDULE X
Fifth Revised Page No. 59 908 COGENERATION AND SMALL POWER PRODUCTION RATE SCHEDULE X A. AVAILABILITY Available to members of the Cooperative for purchases of electricity by the Cooperative from qualified
More informationPQ04. Understanding Power Monitoring
PQ04 Understanding Power Monitoring Understanding Power Monitoring Randy Keranen Drives, Motors, and Power Monitors Product Manager April 9, 2015 Related Classes at the Expo PQ05 Energy Intelligence: EnergyMetrix
More informationAURORA ENERGY LTD. Use-of-System Pricing Methodology
AURORA ENERGY LTD Methodology Applicable from 1 April 2009 Prices Applicable from 1 April 2009 1 INTRODUCTION 2 PRICING OBJECTIVES 3 COST STRUCTURE 4 REVENUE STRUCTURE 5 PRICING COMPONENTS 5.1 Distribution
More informationREQUEST FOR INNOVATIVE ELECTRICAL CONSERVATION PROGRAMS. Gainesville City Commission Energy Conservation Workshop April 19, 2004
REQUEST FOR INNOVATIVE ELECTRICAL CONSERVATION PROGRAMS Gainesville City Commission Energy Conservation Workshop April 19, 2004 1 RFP Goals Enlist Private Sector s creativity & harness their industry knowledge
More informationSMALL GENERATOR INTERCONNECTION REQUEST (Application Form)
SMALL GENERATOR INTERCONNECTION REQUEST (Application Form) Attachment 2 Transmission Provider: Bluestem Electric Cooperative, Inc. Designated Contact Person: Kevin Heptig Address: P.O. Box 5, Wamego, Kansas
More informationRajasthan Distribution Sector
Rajasthan Distribution Sector Feeder Renovation Program Jul, 2012 Jaipur, Ajmer & Jodhpur Vidyut Vitran Nigam Limited A1: INTRODUCTION 1.1 The distribution system of Rajasthan had was suffering from very
More informationTHE POTOMAC EDISON COMPANY Electric P. S. C. Md. No. 53 Fifth Revision of Original Page No. 28 Canceling Fourth Revision of Original Page No.
Fifth Revision of Original Page No. 28 Fourth Revision of Original Page No. 28 NET ENERGY METERING RIDER AVAILABILITY This Rider is available to all Customers who own and operate a biomass, solar, fuel
More informationGalileo Research. Distributed Generation
Galileo Research Distributed Generation 2001-2013 Distributed, or small generation units, typically less than 30MWs, strategically located near consumers and load centers can provide benefits to customers
More informationExperts speak on UPS output Watt, VA, and Power Factor ratings.
Experts speak on UPS output Watt, VA, and Power Factor ratings. White Paper #13 Executive Summary Experts speak on the subject of UPS output ratings, and how the use of UPS with an output power factor
More informationRestructuring Electricity Tariff in Jordan and Introducing Time of Use (TOU) Tariff: Electricity Regulatory Commission (ERC)
Restructuring Electricity Tariff in Jordan and Introducing Time of Use (TOU) Tariff: Electricity Regulatory Commission (ERC) Economic and Studies Research Dept. Presented By: Meqdad Qadous Economic and
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).
More informationPower Trend User Guide
Power Trend User Guide GETTING STARTED 1. Click on the following link to the PowerTrend home page or Copy/Paste it into your browser Address Locator. https://www5.snopud.com/powertrend/login.aspx. 2. Log
More informationPricing guidelines for electricity distributors. A handbook for pricing practitioners
Pricing guidelines for electricity distributors A handbook for pricing practitioners November 2016 Contents Foreword 5 1 Introduction 6 2 Connection Groups 9 3 Residential Group 12 3.1 Low Fixed Charge
More informationAORC Technical meeting 2014
http : //www.cigre.org C5-1036 AORC Technical meeting 2014 Solar PV Rooftop System Connection to MEA s Distribution Network: Technic and Economic Aspects Tosak Thasananutariya Metropolitan Electricity
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...
More informationMaximizing Consumer Value Through Dynamic Pricing: A Suggested Approach for Regulators
Maximizing Consumer Value Through Dynamic Summary Regulators and electricity providers have developed and now offer numerous pricing structures to optimize their provision of electricity to consumers.
More informationELECTRIC ARC FURNACE WITH STATIC VAR COMPENSATOR PLANNING AND OPERATIONAL EXPERIENCE
GERHARD HACKL 1 HERWIG RENNER 2 MANFRED KRASNITZER 3 CHRISTIAN HOFBAUER 1 ELECTRIC ARC FURNACE WITH STATIC VAR COMPENSATOR PLANNING AND OPERATIONAL EXPERIENCE Abstract The paper describes the process of
More informationPower Flow Control Scheme for Wind Energy Conversion System
Vol.2, Issue.3, May-June 2012 pp-644-648 ISSN: 2249-6645 Power Flow Control Scheme for Wind Energy Conversion System using FACTS Controller R. Vibin 1, K. Malarvizhi 2 1 PG Scholar, Department of EEE,
More informationWhere is moving the electricity sector and how are Electric. Industry Investment Decisions Influenced by Potential
Where is moving the electricity sector and how are Electric Industry Investment Decisions Influenced by Potential Instability in the Regulatory Environment by : G. Dodero I.P.G. Industrial Project Group
More informationTechnical University of Moldova EMM Departament. plus. Author: Rachier Vasile. Scientific coordinator: prof. dr. ing. Sobor Ion
EMM Departament Author: Scientific coordinator: Rachier Vasile prof. dr. ing. Sobor Ion sre.utm@gmail.com, rachier.vasile@yahoo.com, http://www.energy.utm.md Chişinău 2012 The aim of the project: Integration
More informationElectrical Networks Principles and Performance
Engineering Standard Electrical Networks Electrical Networks Principles and Performance Version: 1 Issued: January 2015 Owner: Chief Engineer Approved By: Paul O Halloran Chief Engineer PRINTOUT MAY NOT
More informationPFC in the Plastics Industry
P o w e r Q u a l i t y S o l u t i o n s www.epcos.com/pfc The collection of PQS is a library with in-depth information on PFC applications, case studies and reference projects. It also serves as a helpdesk
More informationNon-BM Balancing Services Volumes and Expenditure
Non-BM Balancing Services Volumes and Expenditure Table of Contents Background... 1 Summary of Total Non-BM Service Provision... 2 Total Ancillary Services Expenditure... 2 Frequency Response... 3 Dynamic
More informationFood & Beverage Portfolio
Line card Food & Beverage Portfolio Products for the Primary Processes Process Automation DCS A flexible, scalable and innovative control system that ensures the productivity, availability and safety of
More informationVirtual Power Plant Simulation
AEP/EPRI Smart Grid Demo Virtual Power Plant Simulation Project Overview Smart Grid Advisory Meeting June 23, 2009 Tom Jones / Tom Walker Virtual Power Plant Simulation Project Virtual Power Plant (VPP)
More informationONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES
ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES 2016 Commercial and Residential Solar Programs Kickoff Meeting November 11-12, 2015 Ken Brunkenhoefer Oncor Asset Planning OVERVIEW
More informationELECTRICAL SYSTEMS. TEST YOURSELF QUESTIONS: Answer Key. CHAPTER 1: Sustainability in Electrical Systems
ELECTRICAL SYSTEMS TEST YOURSELF QUESTIONS: Answer Key CHAPTER 1: Sustainability in Electrical Systems 1. What are the benefits of sustainability in green building design? The benefits of sustainability
More informationA student investigated the efficiency of a motor using the equipment in Figure 1. Figure 1
A student investigated the efficiency of a motor using the equipment in Figure. Figure He used the motor to lift a weight of.5 N a height of.0 m. He measured the speed at which the weight was lifted and
More informationQuick Start Guide (for PacifiCorp Customers) January, 2011
Quick Start Guide (for PacifiCorp Customers) January, 2011 Contents Chapter 1 Signing On to Energy Profiler Online 2 Chapter 2 Overview of Analysis Capabilities.. 3 Chapter 3 Selecting Accounts/Groups.....
More informationThe Idaho Power Company
Preventing Electrical Pollution Working with Customers to Control Electrical Pollution Idaho Power s Approach By Jon D Roholt For the IEEE PES T&D Conference & Exposition Chicago IL, April 23, 2008 The
More informationNon-BM Balancing Services Volumes and Expenditure
Non-BM Balancing Services Volumes and Expenditure Table of Contents Background... 1 Summary of Total Non-BM Service Provision... 2 Total Ancillary Services Expenditure... 2 Frequency Response... 3 Dynamic
More informationThe ESP Handbook. Chapter 9 Billing under CCA. Version 2.0 May 1, 2015
The ESP Handbook Chapter 9 Billing under CCA Version 2.0 May 1, 2015 9.1 Introduction This chapter provides an overview of billing policies and procedures under Community Choice Aggregation (CCA). The
More informationTechnical Requirements for Distributed Generation Connection
Technical Requirements for Distributed Generation Connection Distributed Generation Connection Requirements SECTION 1: INTRODUCTION 1.1 General Purpose This document defines the requirements for connecting
More informationEDF EVALUATES SMART METERING IN MARTINIQUE: EXPECTATIONS & LOCAL REVIEW
EDF EVALUATES SMART METERING IN MARTINIQUE: EXPECTATIONS & LOCAL REVIEW Joseph MAIRE Laure CHOSSEGROS Gilles RONDY EDF SEI France EDF SEI - France EDF Martinique - France Joseph.maire@edf.fr Laure.chossegros@edf.fr
More informationBloemwater Conduit Hydropower Plant launched
Bloemwater Conduit Hydropower Plant launched Marco van Dijk Department of Civil Engineering University of Pretoria marco.vandijk@up.ac.za On 31 March 2015 the Minister of Water and Sanitation, Nomvula
More informationEnergex. Tariff Structure Statement. 1 July 2017 to 30 June Energex s Tariff Structure Statement
Energex Tariff Structure Statement 1 July 2017 to 30 June 2020-1- Energex s 2017-20 Tariff Structure Statement Version control Version Date Description V.1 27 November 2015 TSS proposal submitted to the
More informationEnergia Online. User Guide
Energia Online User Guide Contents Registration and Login: Page 1 Energia Plus: Page 4 Energia Premium: Page 14 Glossary: Page 31 Contents Registration It is possible to register for access to Energia
More informationSCHEDULE 12 Transmission Enhancement Charges. Establishment of Transmission Enhancement Charges.
SCHEDULE 12 Transmission Enhancement Charges (a) Establishment of Transmission Enhancement Charges. (i) Establishment of Transmission Enhancement Charges by Transmission Owners and Entities That Will Become
More informationRefinement of Hydel power by implementing FACTS at Narangwal hydroelectric power plant
International Journal of Electronics Engineering Research. ISSN 0975-6450 Volume 9, Number 8 (2017) pp. 1323-1328 Research India Publications http://www.ripublication.com Refinement of Hydel power by implementing
More informationSouth African Distribution Code
South African Distribution Code Tariff Code Version 6.0 July 2014 This document is approved by the National Energy Regulator of South Africa (NERSA) Issued by: RSA Grid Code Secretariat Contact: Mr. Bernard
More informationENABLING EMBEDDED GENERATION
APRIL 2014 ENABLING EMBEDDED GENERATION Turning Australian electricity on its head WHAT IS EMBEDDED GENERATION? Energy supply systems around the world are being transformed by embedded (or distributed)
More informationUncontrolled Document when printed. Refer to internet for latest version. Disclaimer refer
Issue June 2013 Page 83 of 91 SA Power Networks 2013 Network Tariff & Negotiated Services Manual No. 18 Issue June 2013 Page 84 of 91 SA Power Networks 2013 Network Tariff & Negotiated Services Manual
More informationPermanent Load Shifting Program
1. Program Description Permanent Load Shifting (PLS) can help reduce system peak load by storing energy produced during off-peak period and shifting electricity use from on-peak to off-peak periods on
More informationCustom Application 2018 Retrofit Program
The Retrofit Program is designed for Commercial and Industrial (C&I) customers to help replace aging and inefficient equipment and systems with more energy efficient technologies. Tailored to a customer's
More informationDISTRIBUTION CODE OF SRI LANKA. Public Utilities Commission of Sri Lanka
DISTRIBUTION CODE OF SRI LANKA Public Utilities Commission of Sri Lanka July 2012 TABLE OF CONTENTS THE DISTRIBUTION CODE OF SRI LANKA... 1 1 GENERAL CODE... 3 1.1 INTRODUCTION... 3 1.2 APPLICABILITY...
More information16.3 Electric generators and transformers
ElEctromagnEts and InductIon Chapter 16 16.3 Electric generators and transformers Motors transform electrical energy into mechanical energy. Electric generators do the opposite. They transform mechanical
More informationSIMARIS Software Tools
SIMARIS Software Tools Easy, fast and safe planning of electric power distribution Answers for infrastructure. s Planning power distribution more efficiently with SIMARIS The innovative software family
More informationCONTENTS 2. PROJECT DESCRIPTION NEED FOR THE PROJECT ABOUT THE PROPONENT SITE SELECTION OVERVIEW OF THE PROJECT 2 5
CONTENTS 2. PROJECT DESCRIPTION 2-2 2.1 NEED FOR THE PROJECT 2 2 2.2 ABOUT THE PROPONENT 2 4 2.3 SITE SELECTION 2 4 2.4 OVERVIEW OF THE PROJECT 2 5 Figure 2.1: Provisional wind profile for the Jeffrey
More informationUsing Software and Submeters to Manage Energy
Dan Ellis Product Manager Power Management Products Eaton s Cutler-Hammer business Introduction To be economically competitive in today s global marketplace, it is necessary to reduce the cost of production
More informationDecoupling vs. Lost Revenues. Regulatory Considerations
Decoupling vs. Lost Revenues Regulatory Considerations David Moskovitz Cheryl Harrington Tom Austin May 1992 Regulatory Assistance Project 177 Water Street Gardiner, Maine 04345 207-582-1135 DECOUPLING
More informationUNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES
UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES Guideline 1 (11) Contents 1 INTRODUCTION... 2 2 PRINCIPLES OF THE SUPPLY OF REACTIVE POWER... 2 2.1 Supply point
More informationB. Provide liquid-filled secondary substation transformers as indicated on drawings.
SECTION 26 12 13 PART 1 - GENERAL 1.01 WORK INCLUDED A. Comply with the provisions of Sections 26 05 00. B. Provide liquid-filled secondary substation transformers as indicated on drawings. 1.02 RELATED
More informationUNMIK REGULATION NO. 2004/22 ON THE PROMULGATION OF A LAW ADOPTED BY THE ASSEMBLY OF KOSOVO ON ELECTRICITY
UNITED NATIONS United Nations Interim Administration Mission in Kosovo UNMIK NATIONS UNIES Mission d Administration Intérimaire des Nations Unies au Kosovo UNMIK/REG/2004/22 30 June 2004 REGULATION NO.
More informationDOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES
Guidelines effective March 5, 2007 NES is committed to providing safe, reliable electric service at a reasonable price for all of our customers. These guidelines offer direction for activities relating
More informationMETHODOLOGY FOR ENERGY AUDITS IN POWER PLANTS REGARDING ANALYSIS OF ELECTRICAL ENERGY CONSUMPTION
METHODOLOGY FOR ENERGY AUDITS IN POWER PLANTS REGARDING ANALYSIS OF ELECTRICAL ENERGY CONSUMPTION Aleksandar NIKOLIĆ 1, El.eng. Institute Nikola Tesla, University of Belgrade, Serbia INTRODUCTION Electricity
More informationChapter Six{ TC "Chapter Six" \l 1 } System Simulation
Chapter Six{ TC "Chapter Six" \l 1 } System Simulation In the previous chapters models of the components of the cooling cycle and of the power plant were introduced. The TRNSYS model of the power plant
More informationConnection of generation plant to distribution networks. Guidance on completing the application form
Connection of generation plant to distribution networks It is possible to connect almost any generation plant to the distribution network and in order for the connection to meet the requirements of a new
More informationDANVEST POWER UNIT. with special Low Load Unit for wind-diesel power stations
DANVEST POWER UNIT with special Low Load Unit for wind-diesel power stations Controls weak or isolated grids - and gives top power quality extremely low fuel consumption and maximum exploitation of renewable
More informationELECTRIC COST OF SERVICE AND RATE DESIGN STUDY
DRAFT Report ELECTRIC COST OF SERVICE AND RATE DESIGN STUDY Navajo Tribal Utility Authority August 2007 DRAFT NAVAJO TRIBAL UTILITY AUTHORITY ELECTRIC COST OF SERVICE AND RATE DESIGN STUDY Table of Contents
More informationBILLING FORMULA FOR CUSTOMERS THAT SELL ELECTRICITY TO BC HYDRO PURSUANT TO AN ELECTRICITY PURCHASE AGREEMENT WITH A CONTRACTED GBL
Original of Page 1 BILLING FORMULA FOR CUSTOMERS THAT SELL ELECTRICITY TO BC HYDRO PURSUANT TO AN ELECTRICITY PURCHASE AGREEMENT WITH A CONTRACTED GBL 1.0 OVERVIEW AND APPLICABILITY This tariff supplement
More informationCombined heat and power units up to 401 kw el. and 549 kw th
Combined heat and power units up to 401 kw el and 549 kw th 2/3 CHP units for heat and power Tailor-made energy concepts for the provision of heat and power. Combined heat and power modules (CHP modules
More informationEPS 7000 and EPS 8000
EPS 7000 and EPS 8000 Single and Parallel Operation 09/2015 www.schneider-electric.com Legal Information The Schneider Electric brand and any registered trademarks of Schneider Electric Industries SAS
More informationAPC by Schneider Electric APC SYMMETRA MW 400 kw to 1600 kw Multi-Module Uninterruptible Power Supply
APC by Schneider Electric APC SYMMETRA MW 400 kw to 1600 kw Multi-Module Uninterruptible Power Supply THIS GUIDE SPECIFICATION IS WRITTEN IN ACCORDANCE WITH THE CONSTRUCTION SPECIFICATIONS INSTITUTE (CSI)
More informationCONDITION ASSESSMENT AND LIFE EXTENSION. R.A. Chaplin Department of Chemical Engineering, University of New Brunswick, Canada
CONDITION ASSESSMENT AND LIFE EXTENSION R.A. Chaplin Department of Chemical Engineering, University of New Brunswick, Canada Keywords: Materials, Inspection, Testing, Assessment, Life Extension Contents
More informationON THERMAL ENERGY. Based on Article 65 (1) of the Constitution of the Republic of Kosovo, LAW ON THERMAL ENERGY CHAPTER I GENERAL PROVISIONS
LAW No. No. 05/L 05/L -058-052 ON ON INDUSTRIAL THERMAL ENERGY DESIGN LAW No. 05/L -052 ON THERMAL ENERGY Assembly of the Republic of Kosovo, Based on Article 65 (1) of the Constitution of the Republic
More informationFixed Price Energy A Guaranteed Deal
Fixed Price Energy A Guaranteed Deal Fixed Price Energy November 2014 Prices effective from 27th July 2012 Fixed Price Energy November 2014 Product Offer Fixed Price u Prices are guaranteed to remain the
More informationRule 21 Sheet 1 GENERATING FACILITY INTERCONNECTIONS
Southern California Edison Revised Cal. PUC Sheet No. 31574-E Rosemead, California Cancelling Revised Cal. PUC Sheet No. 30685-E Rule 21 Sheet 1 A. Applicability 1. This Rule describes the Interconnection,
More informationACHIEVING ENERGY CONSERVATION GOALS WITHOUT THE BROAD APPLICATION OF SMART METERS ONTARIO FEDERATION OF AGRICULTURE
ACHIEVING ENERGY CONSERVATION GOALS WITHOUT THE BROAD APPLICATION OF SMART METERS Background ONTARIO FEDERATION OF AGRICULTURE The Ontario Federation of Agriculture is a voluntary membership organization.
More informationPresentation to CTA: Electricity Pricing Assessment for Mozambique
Presentation to CTA: Electricity Pricing Assessment for Mozambique Donald Hertzmark Nathan Associates June 2008 Maputo, Mozambique Electricity Pricing Analysis Objectives Assess cost and quality of electricity
More information