2 NECESSITY OF THE PROPOSED PROJECT

Size: px
Start display at page:

Download "2 NECESSITY OF THE PROPOSED PROJECT"

Transcription

1 Executive Summary 1 INTRODUCTION M/s. Prosperous Energy Private Limited (PEPL), a wholly owned subsidiary of Videocon Industries Limited has proposed the 2X660MW Coal based supercritical Thermal Power Plant near Ghuman (V), Jawa (T), Rewa (Dt), Madhya Pradesh. The proposed developmental activity is Greenfield project falls under the category A of Project Activity 1(D) under the schedule as per EIA notification issued on 14th September, 2006 and hence the project requires Environmental Clearance from MoEF, Govt of India. In order to assess the likely impacts from current project on the surrounding environment and evaluating the means of alleviating the likely negative impacts, if any, from the proposed project, PEPL has retained Ramky Enviro Engineers Ltd. as their environmental consultant. The report has been prepared as per the recommendation in the Terms of References (TOR) from the Expert Appraisal Committee (EAC) at Central Level vide their letter no. J-13012/47/2011-1A.II(T) Dated NECESSITY OF THE PROPOSED PROJECT The actual growth in industrial, agricultural and domestic demand will establish that there is an appreciable shortfall in the installed capacity, demand and energy availability as on date. This shortfall will continue even after the commissioning of the proposed power plants in various parts of the State. As M.P state is the most preferred state for industrialization, the industrial demand for power will be ever increasing. Added to the industrial demand the agriculture need as well as domestic consumption coupled with the improved standard of living of the population will be on the rise. Lack of availability of sufficient electric power has always been one of the greatest deterrent to the economic growth of the state. The Potential from Hydel plants is already exploited to the maximum. Further, the hydel generation which is being restricted only to the monsoon period and peaking requirement cannot cater to the overall power requirement of the region and hence the capacity addition in thermal power sector has become necessary. Taking all these into consideration, establishment of the proposed power plant of 2X660 MW Super-Critical Coal based Thermal Power Plant near Ghuman Village, at Rewa District is justified in all aspects, since this will meet a part of the projected power demand and supply. Salient Features of the proposed Project Site are given in Table 2.1 and Technical Details of the proposed 2X660 MW Coal Based Super Critical Thermal Power Plant are given in Table 2.2 Photograph of site is given in Figure 2.1. Page ES.1

2 Table 2.1 Site Environs of the Study Area (10km radius w.r.t site) S. No Particulars Details Ghuman Village, Jawa Tehsil, Rewa District, 1 Location Madhya Pradesh State. 2 Geographical Positions '55" to '55" North Latitude and '08" to '39" East Longitude 3 Elevation above MSL ~ m above Mean Sea Level 4 Land required for the Activity 800 Acres 5 Present Land use Barren land and some Single Crop agricultural use 6 Nature of Soil Light to Medium black soil 7 Nature of Terrain Flat with undulating 8 Predominant Wind direction SE 9 Nearest Highway NH-76 (~10 Km) North East 10 Nearest Railway station Dabhaura (~7.5 Km) West 11 Nearest Airport Allahabad Airport (Arial) ~81 Km North East 12 Nearest Sea Port Paradip (~750km) South East 13 Nearest Village Dabhaura ~7.5Km, West 14 Nearest Town/City Allahabad ~85 Km, North East 15 Topography Flat terrain 16 Monuments None in 15Km radius 17 Archaeologically important places None in 15Km radius 18 National Parks None in 25Km radius. Panna National Park 97 Km, South West. 19 Reserve Forests Dhurkuch East RF 0.5km South from site boundary. Akauria RF ~5km North West 20 Seismicity Zone-III 21 Streams/Rivers Mandha Nala ~2.5km East, Mohana Nala ~7km East & Ukmeh Nadi ~11 Km South west Table 2.2 Technical Details of the Proposed 2X660 MW Coal Based Super Critical Thermal Power Plant 1.0 Project Information & Location 1.1 Project : Prosperous Energy Private Limited 1.2 Plant Capacity : 2X660 MW (1320 MW) 2.0 Land 2.1 Total Land Required : 800 Acres 3.0 Fuel Source and Consumption 3.1 Source of Fuel : Indian Coal from South Eastern Coalfields Limited/ Mahanadi Coalfields Limited through railway siding or Blending with Imported Coal in the ratio of 50: Fuel Gross Calorific Value : 100% Indian Coal 3700 Kcal/Kg Page ES.2

3 Indian:50%, Imported:50% 3.3 Fuel Consumption at 85% PLF 100% Indian Coal Indian:50%, Imported:50% : 3850 Kcal/Kg 7.44 MTPA (999 TPH or TPD) 7.06 MTPA (949 TPH or TPD) 3.4 Support Fuel & Source : Heavy Fuel Oil from Nearest Refinery 3.5 Support Fuel Requirement : KL/Annum 4.0 Water Source and Quantity 4.1 Source of Water : The Makeup Water Requirement shall be met from Tonnes River through pipe lines at distance of 35km from the project site. 4.2 Raw Water Requirement : 5300 m 3 /hr ( m 3 /day) 4.3 Wastewater Generation : 777 m 3 /hr (18648 m 3 /day) 4.4 Treatment Scheme : Separate ETP & STP s will be provided. Treated water will be reused within the plant premises 5.0 Plant & Equipment 5.1 Boiler & Auxiliaries Boiler 5.2 Type Steam Parameters per Boiler : Pulverised Coal Firing Boiler (PC) : Once through sliding pressure supercritical boiler, Vertical wall evaporator with rifle tubing, Conventional Two-pass, radiant reheat, Balanced draft and drumless type unit designed for firing Indian/Imported/Blended coal as prime fuel : Flow 2600 TPH : Pressure 246 to 266 kg/cm 2 : Temperature 565/593 0 C Boiler Efficiency : 85% Turbine & Auxiliaries : Horizontally split, multi cylinder (One HP, One IP & Two LP) 3000 RPM multistage, tandem compound, single reheat, condensing type unit. Turbine Heat Rate : 1850 Kcal/KWh Plant Heat Rate 5.3 Ash Generation & Handling System : 2315 Kcal/KWh : Conventional Wet type removal system Total Ash generation (100% Indian Coal) (Blended 50:50) Fly ash : 328 TPH 274 TPH Bottom ash : 82 TPH 68 TPH Total ash : 410 TPH (9840 TPD) 342 TPH (8199 TPD) Cooling Tower Cooling System No of Cooling Tower Capacity Chimney No. of Chimney : Natural Draft Cooling System : 2 (One for each unit) : m3/hr for each unit : 1 (Twin Flue stack) Page ES.3

4 Height of Chimney 6.0 Project Schedule Unit-1 Unit Manpower requirement During Construction phase During O & M : 275 m high Twin flue gas path for 2X660 MW : 39 Months : 42 Months : 1750 Personnel s : 700 Personnel s Figure 2.1 Photograph of Proposed Site 3 BASELINE ENVIRONMENTAL STATUS Meteorology (Climate) Weather data was collected for a period of December 2011 to February 2012 and analyzed. The predominant wind direction during the study period was blowing from SE to NW. The average temperature varies seasonally from 5.2 O C to 41 O C. Humidity is very high and rises to about 61 percent during the south-west monsoon. Ambient Air Quality The ambient air quality was monitored at 10 locations within 10Km radius of the project site as per MoEF guidelines. The study area represents mostly rural environment. Air pollutants like Suspended Particulate Matter (SPM), Particulate Matter (PM<2.5µ, PM<10µ), Sulfur dioxide (SO 2 ), Oxides of Nitrogen (NO X ), Ozone (O 3 ), and Mercury (Hg) were identified for representing the baseline status of the ambient air quality within the study area. The observed air pollutants were within the standard limits as suggested by the respective organizations. Page ES.4

5 Water Quality Status Surface water (5 no) and ground water samples (7 no) were collected from different sources within the study area and some important physical and chemical parameters including heavy metals were considered for depicting the baseline status of the study area. The samples collected from the study area were found to be fit for human consumption; however the hardness and dissolved solids in some of the ground water samples seem to be beyond desirable limit but within the permissible limits. Noise Quality Noise levels are monitored at 5 Locations in the study area. The main sources of noise in the study area are domestic activities, and vehicular traffic. The main occupation of the villagers in the study area is agricultural business. The noise levels observed in some of the rural areas are primarily owing to vehicular traffic. The day equivalents during the study period are ranging between 42.8 db (A) to 51.6 db (A) whereas, the night equivalents were in the range of 40.0 db (A) to 40.4 db (A). From the results, it can be seen that the Day equivalents and the Night equivalents were within the Ambient Noise standards of residential area standards. The day and night equivalent levels during the study period are ranging between 46.7 db (A) to 51.3 db (A). Soil Quality Soil Samples were collected from 8 locations from the study area. The ph of the soil is an important property; plants cannot grow in low and high ph value soils. The ph values in the study area are varying from 6.0 to 8.5. The organic carbon in the study area is varying from 0.03 to 0.25%. The available Nitrogen as N in the study area is varying from 107 to 175 kg/ha. The available Phosphorus is varying from 8.5 to 27 kg/ha. The available potassium in the study area is varying between 90 to 511 kg/ha. Flora & Fauna There are no endangered or endemic species of flora and fauna in core and buffer zone of the proposed project. 4 ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES The proposed power plant may cause impact on the environment in two phases. During Construction phase During Operation phase a) Impacts during construction phase: The possible construction activities that contribute to the environmental impacts are: Dust Generation during leveling of earth Dust generation due to the movement of vehicles on unpaved roads Emission of pollutants from vehicular exhaust Unloading of raw materials and removal of unwanted waste material from site Accumulation of excavated earth material Page ES.5

6 The impact of the above activities would be temporary and will be confined within the project boundary b) Impacts during Operation Phase Impact on Air Quality The proposed project is a coal based thermal power plant and the major source of pollution would be the emissions from the stack. The ash content in the raw coal is considered 36% in Blended coal and 41% in Indian coal for prediction of air emissions. The important air pollutants generated from the thermal power plant are particulate matter (PM), sulfur di-oxide (SO 2 ), and oxides of nitrogen (NO X ). The major air pollutants generated from the proposed thermal power plant are given below: 1. Dust particulates in flue gas from chimney 2. SO 2 and NO X in flue gas 3. Coal dust particles due to handling of coal 4. Fly ash dust particles from ash silos and ash disposal area 5. Coal dust generated at the conveyor transfer points 6. Fly ash vented out during the unloading of fly ash from ESP hoppers to silos Table 4.1 Stack and Emission Details Proposed Plant Details Units Unit-1 Unit-2 Plant Capacity MW Type of Fuel - Coal Coal Height of the Stack m Internal Dia. of Stack M 7 7 Temperature of Flue Gas C Ambient Temperature (mean) C Velocity of Flue Gas m/s Flow Nm 3 /s Blended Indian coal Blended Indian coal Fuel Consumption TPH Ash Content (in coal used) % Sulfur Content % PM Emissions g/s SO 2 Emissions g/s NO X Emissions g/s Page ES.6

7 Particulars Table 4.2 Post Project Scenario-Units: µ/m 3 Particulate Matter (PM 10 ) Sulfur Dioxide (SO2) Oxides of Nitrogen (NO X ) Baseline Scenario (Max) Blended coal Predicted GLC (Max) Overall Scenario (Worst Case) Indian coal Predicted GLC (Max) Overall Scenario (Worst Case) NAAQ Standards * Source: * MoEF, Notification, New Delhi 16 th November 2009, Schedule VII The proposed mitigation measures Dust suppression/extraction facilities will be provided to mitigate the dust generated at coal transfer points and coal stockyard. Dust collection system will be provided in coal bunkers to evacuate dust and hazardous gases like methane from the coal bunkers. To reduce the dust nuisance while loading the ash into the open trucks from fly ash silos, the fly ash would be conditioned with water spray It is proposed to cover the ash in the open trucks with tarpaulin to prevent flying of fine ash during transportation To control the particulate matter in the flue gas, an efficient electrostatic precipitator with an efficiency of 99.9% is proposed. Impact on Water Quality The water required for the proposed project shall be met from the Tonnes River through pipeline of about 35km away from the proposed site. The possible sources of wastewater within the project site are: i) Wastewater from Workshop: ii) Sewage from Domestic Use: iii) Effluent from water treatment plant iv) Blow downs from Cooling Tower v) Ash Disposal vi) Filter Backwash and Service Water The proposed mitigation measures Oily water will be treated separately to remove oil/grease before being discharged into effluent pond. Clarification is used to settle out large suspended particles and also to make the smaller colloidal particles settle Filtration will be made to a porous barrier across flowing liquid to remove suspended materials Page ES.7

8 Effluents from DM plant shall be treated in neutralization pit. The wastewater from plant units will be collected and treated in conventional effluent treatment plant. Treated effluent will be reused at maximum extent within the plant and excess treated water will be discharged to nearby natural streams according to stipulated on-land discharge standards. Impact on Noise Levels Any industrial activity, in general, consists of several sources of noise pollution. The different sources of noise pollution are mentioned below: Crusher unit Induced draft & Forced draft fans Boiler feed pumps Turbines Generators Cooling Towers Frequent vehicular movement The proposed mitigation measures are Properly designed plant and machinery (i.e. by providing inbuilt mechanisms like silencers, mufflers, and enclosures for noise generating parts) and shock absorbing pads at the foundation of vibrating equipment will be provided. In the high noise intensity working areas/zones ear muffs or ear plugs or any other suitable personal protective equipment would be provided to the workmen. Development of greenbelt around the plant boundary will diffuse the noise pollution. Provision of isolation for major noise generating equipments. Distribution of working hours among more personals working with major noise generating equipments. Regular noise level monitoring would be carried out for taking corrective action, wherever required. Vehicular movement will be restricted during peak hours and the drivers will be informed to blow horns only when required 5 ENVIRONMENTAL MONITORING PROGRAM Environmental Monitoring Program has been designed for assessing the efficiency of implementation of Environment Management Plan and to take corrective measures in case of any degradation in the surrounding environment. Different activities involved in the proposed project and their impact on various environmental attributes have been taken into account while designing a detailed environmental monitoring program. Implementation of EMP and periodic monitoring is proposed to be carried out at plant level and area level for the proposed thermal power plant and allied activities like coal handling facilities, Page ES.8

9 workshop, colony, etc. A comprehensive monitoring mechanism has been devised for monitoring of impacts due to proposed project. Plant level environmental protection measures like dust suppression, treatment and recycling of wastewater, plantation and noise control in the plant premises, housekeeping, implementation of EMP and Environmental Clearance conditions will be monitored by the plant authorities. 6 Social Impact Assessment (SIA) Study The detailed Social Assessment was carried out to examine the potential adverse and beneficial consequences of the proposed development project on the affected people. All acquired land is barren; only a little portion of land is fertile which is not being irrigated. The Research Team analyzed the needs identified during stakeholder consultations in the process of SIA and found the suitable activities to fulfill the prioritized needs of the study area, which are mentioned below where PEL have scope to initiate CSR Activities. Drinking water schemes Infrastructure especially in Aanganwadis and schools till SSC and insufficient number of education centres Awareness for Government Development schemes Local youth training for creating employment opportunities, etc. 7 PROJECT BENEFITS Agriculture is the primary way of employment for the local people within the study area. The contribution of the power plant on local social infrastructure is expected to be significant. The proposed power plant will stimulate the growth of industrial and commercial activities in and around the study area and district, by improving the availability of the power. This Project will provide a significant amount of direct and indirect employment opportunities to the local people with different skills and trades. The physical infrastructure and socio-economic status of the surrounding areas will be benefited as follows: Road transport facilities which improve accessibility Improvement in education, housing, and banking facilities Improvement in postal & communication services Recreation facilities Improvement in power supply, water supply and sanitation Improvement in economic conditions Proper training to the local people will be given to improve the employment potential within the plant Increase in revenue to the state in the form of taxes and duties from the development of local businesses Local markets with food and non-food commodities will be improved due to the increase inflow of human residents within the district Page ES.9

10 An amount of Rs. 10 Crores will be earmarked towards CSR Activities initially and later on need based allotment of funds will be done for taking up CSR activities by keeping a separate fund using minimum of 2% of profit share. 8 ENVIRONMENTAL MANAGEMENT PLAN The EMP will be integrated in all the major activities of the project, with clearly defined policies, to ensure that the ecological balance of the area is maintained and the adverse effects are minimized. It has been evaluated that the environmental impacts, due to the proposed project, are anticipated both during constructional and operational phase. Hence, the mitigative measures are planned for both the phases and the overall management plan helps to improve the surrounding environment by reducing the pollution loads from proposed activities. The EMP aims to control pollution at the source level to the possible extent with the available and affordable technology followed by the standard treatments before getting discharged. The recommended mitigation measures will synchronize the economic development of the study area with the environmental protection of the region. Environmental protection measures like monitoring & management, dust suppression, treatment and re-use of wastewater, plantation, and noise control within the project area will be looked after by the project level management. 9 CONCLUSIONS The EIA study has made an overall assessment of the potential environmental impacts likely to arise from the proposed power plant. The impact predictions indicate that the maximum GLC levels of PM, SO 2 and NO x superimposed on the baseline levels the expected impacts are minimized within a 1km from the release of pollutant from the stacks and were well within the prescribed limits of CPCB standards if blended coal is used. The wastewater from plant units will be collected in a Central Monitoring Basin and it will be treated in effluent treatment plant. Treated water quality shall be maintained as per stipulated standards. Treated effluent will be reused at maximum extent within the plant premises. Mitigation measures are proposed to minimise the adverse impacts if any due to the activity of power generation in the form of EMP. The demand for electricity has been steadily increasing in the state of Madhya Pradesh. Setting up of Power Plant in this area will benefit the society by providing better infrastructural, educational and medical facilities in the area also improvement in indirect employment and economic growth of the area. Page ES.10

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION Jaypee Group is a leading Business House of the country with its presence in Core industries and Service Sectors like Cement, Infrastructure development,

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. 0.96 MTPA Wet type Coal Washery at Birgahani Village, Baloda Tehsil Janjgir-Champa District, Chhattisgarh

More information

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA 1.0 INTRODUCTION M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA dry type of coal washery at Village: Hindadih, Tehsil: Masturi, District: Bilaspur (C.G.) for which

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. (Change in Technology) at Hindadih Village, Masturi Tehsil Bilaspur District, Chhattisgarh Submitted to

More information

Clearance Letter no. : MoEF Vide Letter no. J-11011/79/2003-IA-II (I) dated April 21, 2004

Clearance Letter no. : MoEF Vide Letter no. J-11011/79/2003-IA-II (I) dated April 21, 2004 Name of the Project: Jaypee Rewa Plant, Unit of M/s Jaiprakash Associates Limited for expansion Of cement production from 2.5 MTPA to 3.5 MTPA at Jaypee Nagar, District Rewa, Madhya Pradesh Project Code:

More information

JAYPEE NIGRIE SUPER THERMAL POWER PROJECT

JAYPEE NIGRIE SUPER THERMAL POWER PROJECT JAYPEE NIGRIE SUPER THERMAL POWER PROJECT (A Unit of M/s Jaiprakash Power Ventures Limited) Villages: Nigrie, Tehsil :Sarai District: Singrauli 2014 2015 SUBMITTED M.P. POLLUTION CONTROL BOARD BHOPAL (M.P.)

More information

Particulate Emission Monitoring HN Pathak Supdtg Engr Madhya Pradesh Power Generation Co. Ltd

Particulate Emission Monitoring HN Pathak Supdtg Engr Madhya Pradesh Power Generation Co. Ltd Particulate Emission Monitoring HN Pathak Supdtg Engr Madhya Pradesh Power Generation Co. Ltd MADHYA PRADESH POWER GENERATING Co. Ltd. INTRODUCTION Satpura Thermal Power Station is an oldest running plant

More information

Rajasthan State Pollution Control Board

Rajasthan State Pollution Control Board M/s Raj West Power Private Limited Village- Bhadresh, Tehsil:Barmer District:Barmer Sub: Ref: Sir, Consent to Operate under section 25/26 of the Water (Prevention & Control of Pollution) Act, 1974 and

More information

PROPOSED TERM OF REFERENCE

PROPOSED TERM OF REFERENCE PROPOSED TERM OF REFERENCE FOR ESTABLISHMENT OF PROPOSED MOLASSES/GRAIN BASED DISTILLERY HAVING CAPACITY: 160.0 KLD (MOLASSES BASED) OR 120.0 KLD (MOLASSES BASED) + 40.0 KLD (GRAIN BASED) ALONGWITH 7.0

More information

Pre-Feasibility Report For Khargone STPP Stage-I (2X660 MW) District- Khargone, Madhya Pradesh

Pre-Feasibility Report For Khargone STPP Stage-I (2X660 MW) District- Khargone, Madhya Pradesh 1.0 Executive Summary Name of Project: Name of Project Proponent: Location of the Project: Capacity & Unit Configurations: Land Requirement, Current Land Use and Availability: Water Requirement and Availability:

More information

Environmental Impact Assessment

Environmental Impact Assessment Environmental Impact Assessment A brief discussion Presented by: Apekshit Solanki Kirti Neetu Yadav Sameera Vishakha Shankar Introduction EIA is a formal process to predict the environmental consequences

More information

HINGULA OPEN CAST PROJECT HINGULA AREA MAHANADI COALFIELDS LIMITED

HINGULA OPEN CAST PROJECT HINGULA AREA MAHANADI COALFIELDS LIMITED HALF YEARLY PROGRESS REPORT ON IMPLEMENTATION OF ENVIRONMENTAL CLEARANCE CONDITION BY MoEF (PERIOD FROM OCTOBER 13 TO MARCH 14) HINGULA OPEN CAST PROJECT HINGULA AREA MAHANADI COALFIELDS LIMITED SIX MONTHLY

More information

V.S LIGNITE POWER Pvt. Ltd AT VILLAGE-GURHA, KOLAYAT, BIKANER, RAJASTHAN

V.S LIGNITE POWER Pvt. Ltd AT VILLAGE-GURHA, KOLAYAT, BIKANER, RAJASTHAN V.S LIGNITE POWER Pvt. Ltd AT VILLAGE-GURHA, KOLAYAT, BIKANER, RAJASTHAN HALF YEARLY REPORT FOR THE PERIOD OCTOBER, 2011 to MARCH 2012 V. S. Lignite Power Pvt. Ltd. Name of the Project : 1x 135 MW Lignite

More information

OPTIMISATION OF WATER USAGES IN THERMAL POWER PLANTS AND A STUDY ON DRY COOLING SYSTEM

OPTIMISATION OF WATER USAGES IN THERMAL POWER PLANTS AND A STUDY ON DRY COOLING SYSTEM CONFERENCE ON WATER OPTIMISATION IN THERMAL POWER PLANTS OPTIMISATION OF WATER USAGES IN THERMAL POWER PLANTS AND A STUDY ON DRY COOLING SYSTEM S. K. Thakur, Dr. L. D. Papney, Chief Engineer (I/C), TE&TD

More information

CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA.

CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA. CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA. A. CONSENT TO ESTABLISH UNDER THE PROVISIONS OF WATER (PREVENTION & CONTROL OF

More information

North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA)

North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA) SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA) Proposed at: Bonda Industrial

More information

ENVIRONMENTAL IMPACT ASSESSMENT AND YOU

ENVIRONMENTAL IMPACT ASSESSMENT AND YOU ENVIRONMENTAL IMPACT ASSESSMENT AND YOU PARTICIPATING IN PUBLIC CONSULTATIONS FOR: COAL FUELED THERMAL POWER PLANTS C A G Citizen consumer and civic Action Group 1. What are Thermal Power Plants? Electricity

More information

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra Draft Terms of References (ToR) (Based on the model TOR given in Environmental Impact Assessment Guidance Manual for building construction projects by MoEF & CC) For PROPOSED IT PARK By M/s.Balewadi Tech

More information

ENVIRONMENTAL MONITORING PROGRAMME

ENVIRONMENTAL MONITORING PROGRAMME Stage-I (2x800 MW) Page 1 5 CHAPTER - VI ENVIRONMENTAL MONITORING PROGRAMME 6.0 OBJECTIVES Regular monitoring program the environmental parameters is essential to take into account the changes in the environment.

More information

Executive summary. EIA STUDY for 1320MW Coal Based Super-critical Thermal Power Plant at Deosar, District Singrauli, Madhya Pradesh 13-13

Executive summary. EIA STUDY for 1320MW Coal Based Super-critical Thermal Power Plant at Deosar, District Singrauli, Madhya Pradesh 13-13 EXECUTIVE SUMMARY PROJECT BACKGROUND DB power (Madhya Pradesh) Limited a fully-owned subsidiary of Bhaskar Group proposes to develop a coal based super critical 2x660 MW Thermal Power Plant at Tehsil-

More information

TERMS OF REFERENCE. Identification of the sources of pollution and assessing the impacts on the environment due to proposed project if any;

TERMS OF REFERENCE. Identification of the sources of pollution and assessing the impacts on the environment due to proposed project if any; TERMS OF REFERENCE 1.0 PROPOSED SCOPE OF WORK FOR EIA STUDY The components of the EIA study include: Determination of baseline data using primary data generation and secondary data available from various

More information

2 No. Continuous Ambient Air Quality Monitoring System (CAAQMS) installed in downwind & upwind direction and are connected to APPCB server.

2 No. Continuous Ambient Air Quality Monitoring System (CAAQMS) installed in downwind & upwind direction and are connected to APPCB server. Environmental Clearance Point Wise Half Yearly Compliance Report (October 2014 to March 2015) Cement Plant - EC No: F.No. J-11011/450/2007-IA II(I) Dated: 24 th March 2008 A. SPECIFIC CONDITIONS : S.NO.

More information

LANCO ANPARA POWER PVT. LTD

LANCO ANPARA POWER PVT. LTD LANCO ANPARA POWER PVT. LTD PLOT No. 229, PHASE-I, UDYOG VIHAR, GURGAON-122016, HARYANA Ph: 0124 4691000-04, 2341625, Fax: 0124 2341627, 4691005 SUMMARY OF RAPID ENVIRONMENTAL IMPACT ASSESSMENT AND ENVIRONMENTAL

More information

ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT

ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT EXECUTIVE SUMMARY NAGERCOIL MUNICIPALITY, KANYAKUMARI DISTRICT TWAD BOARD,SEWERAGE DIVISION,NAGERCOIL

More information

SOME ENERGY-EFFICIENT TECHNOLOGIES IN JAPAN

SOME ENERGY-EFFICIENT TECHNOLOGIES IN JAPAN SOME ENERGY-EFFICIENT TECHNOLOGIES IN JAPAN (EXECUTIVE SESSION) November, 2007 JAPAN EXTERNAL TRADE ORGANIZATION JAPAN CONSULTING INSTITUTE SOME ENERGY-EFFICIENT TECHNOLOGIES IN JAPAN 1. Power Generation

More information

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 Group Housing Complex My woods AT Plot no. GH-04, Sector -16 C, Noida Extension, Greater Noida, U.P. Being developed by M/s Mahagun India Pvt. Ltd. A-19, Sector-63,

More information

Excerpt of Thermal Power Guidelines for New Plants

Excerpt of Thermal Power Guidelines for New Plants Excerpt of Thermal Power Guidelines for New Plants The following is an excerpt of the Thermal Power guidelines for New Plants, a complete version of which is found in the Pollution Prevention and Abatement

More information

Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited

Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited Introduction: Jaypee Group is the 3 rd largest cement producer in the country. The Groups cement facilities are located in

More information

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department 2017 [Type a quote from the document or the summary of an interesting point. You can position the text box anywhere in the document. Use the Drawing Tools tab to change the formatting of the pull quote

More information

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are: 4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 4.1 POTENTIAL ENVIRONMENTAL IMPACTS 4.1.1 Impacts during Construction Phase Negative or adverse impacts during the construction phase are: Land environment:

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project of MANUFACTURING OF SYNTHETIC ORGANIC DYES (5 f B IND II) By SHREEJI BAPA DYE CHEM PLOT NO 1319 & 1320, PHASE-III, GIDC, VATVA, AHEMADABAD-382445, GUJARAT,

More information

M/s. SAL STEEL LTD Survey no.245/p, Village:-Bharapar, Taluka:- Gandhidham, District:-Kutch, Gujarat.

M/s. SAL STEEL LTD Survey no.245/p, Village:-Bharapar, Taluka:- Gandhidham, District:-Kutch, Gujarat. Pre-Feasibility Study Report For Proposed Fly Ash Co-processing clinker grinding cement Unit of 40,000 MT/month Production capacity within our Existing Premises for M/s. SAL STEEL LTD Survey no.245/p,

More information

Post Combustion CO 2 Capture Scale Up Study

Post Combustion CO 2 Capture Scale Up Study Post Combustion CO 2 Capture Scale Up Study Prachi Singh and Mike Haines International Greenhouse Gas R&D programme 6 th International Conference on Clean Coal Technologies (CCT 2013) 12-16 th May 2013

More information

Questionnaire (Wood Processing)

Questionnaire (Wood Processing) Questionnaire (Wood Processing) QUESTIONNAIRE FOR WOOD PROCESSING (SECTOR-RELATED QUESTIONS) The completion of this questionnaire is voluntary. However, replying to the relevant questions as completely

More information

APPENDIX H AIR DISPERSION MODELLING REPORT BY PROJECT MANAGEMENT LTD. (REF. CHAPTER 11 AIR QUALITY AND CLIMATIC FACTORS)

APPENDIX H AIR DISPERSION MODELLING REPORT BY PROJECT MANAGEMENT LTD. (REF. CHAPTER 11 AIR QUALITY AND CLIMATIC FACTORS) 101050.22.RP.0001 A Environmental Impact Statement 15 th April 2005 APPENDIX H AIR DISPERSION MODELLING REPORT BY PROJECT MANAGEMENT LTD. (REF. CHAPTER 11 AIR QUALITY AND CLIMATIC FACTORS) S:\Projects\190900\101050

More information

Welcome to. Kendal Power Station

Welcome to. Kendal Power Station Welcome to Kendal Power Station Technical Overview of the power station Scope General Overview Coal Handling Milling Plant Boiler Plant Turbine Train Steam Flow Path Ash Handling Generator HV Yard Cooling

More information

THE RAMCO CEMENTS LIMITED

THE RAMCO CEMENTS LIMITED 1 P a g e 2 P a g e THE RAMCO CEMENTS LIMITED (Formerly Madras Cements Ltd.) COMPLIANCE REPORT FOR ENVIRONMENTAL CLEARANCE JAYANTHIPURAM NORTH BAND MINING LEASE 2.0 MILLION TPA CAPACITY EC Lr. No. : J-11015/377/2006-IA.II

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT TATA CONSULTING ENGINEERS LIMITED PRE FEASIBILITY REPORT FOR 4000 MW COAL BASED ULTRA MEGA POWER PLANT AT HUSAINABAD, DEOGHAR DISTRICT, JHARKHAND, INDIA Project Proponent: Deoghar Mega Power Limited A

More information

No. 138 /PS-MS/MPPCB/SEAC/TOR (75)/2011 Bhopal, dt. 03 /06/2011. Env. Consultant: Créative Enviro Service, Bhopal. (SN-29)

No. 138 /PS-MS/MPPCB/SEAC/TOR (75)/2011 Bhopal, dt. 03 /06/2011. Env. Consultant: Créative Enviro Service, Bhopal. (SN-29) 1 By: Speed-Post State Level Expert Appraisal Committee (Formed as per S.O. no. 1533 dated 14 th Sept 2006 of Government of India, Ministry of Environment & Forests) PARYAWARAN PARISAR, E-5, ARERA COLONY,

More information

COAL STOCKPILES IN INDIAN POWER PLANTS. H Ramakrishna TCE Consulting Engineers Limited 73/1, St Marks Road, Bangalore , Karnataka, India

COAL STOCKPILES IN INDIAN POWER PLANTS. H Ramakrishna TCE Consulting Engineers Limited 73/1, St Marks Road, Bangalore , Karnataka, India SUMMARY: Coal will be transported to the power plant by belt conveyors in case of pit head power plants. In case of power plants located far away from the mines, coal will be transported by rail. In some

More information

HALF YEARLY COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE CONDITIONS

HALF YEARLY COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE CONDITIONS HALF YEARLY COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE CONDITIONS 1. Name of the Project: M/s MCC PTA India Corp. Private Limited Haldia ( WB) Note: Company Name was change from MCC PTA India Corp.Private

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT VENSUB LABORATORIES PRIVATE LIMITED SY. NO. 29, TUPAKULAGUDEM VILLAGE, TALLAPUDI MANDAL, WEST GODAVARI DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT VENSUB LABORATORIES PRIVATE LIMITED Duplex No. 12,

More information

COGENERATION PLANT FAQ. What is biomass cogeneration? Cogeneration is the simultaneous production of electricity and heat using a single primary fuel.

COGENERATION PLANT FAQ. What is biomass cogeneration? Cogeneration is the simultaneous production of electricity and heat using a single primary fuel. COGENERATION PLANT FAQ What is biomass cogeneration? Cogeneration is the simultaneous production of electricity and heat using a single primary fuel. Biomass cogeneration uses waste wood and horticultural

More information

HINAUTI LIMESTONE MINE Mine Lease area ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P)

HINAUTI LIMESTONE MINE Mine Lease area ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P) HINAUTI LIMESTONE MINE Mine Lease area 378.261 ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P) 2012-2013 SUBMITTED TO M.P.POLLUTION CONTROL BOARD BHOPAL (M.P.) Jaypee Sidhi Cement

More information

.in Dated 9th August, Sharma ;

.in Dated 9th August, Sharma  ; F. No. J-11011/151/2010-IA II (I) Government of India Ministry of Environment and Forests (I.A. Division) Paryavaran Bhawan CGO Complex, Lodhi Road New Delhi -110 003.. To, Ankleshwar E-mail: pb.rastoai@nic.in

More information

PRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD

PRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD PRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD PLOT No. F-1,2,3,8,9,10, ADDL. MIDC, PHASE II, AND GUT NO. 46 & 63, VILLAGE DAREGAON, TEHSIL: JALNA DIST: JALNA, MAHARASHTRA 2014-15 1. Executive

More information

4. The ambient air quality monitoring stations We are monitoring the ambient air quality

4. The ambient air quality monitoring stations We are monitoring the ambient air quality GLOBAL CALCIUM PRIVATE LTD., 125&126, SIPCOT COMPLEX, HOSUR 635 126 Ref : No. J-11011/411/2006-IA-II(I) dated 1 st August 2007. Compliance Report for the Period ending 31.3.2015 Sl. Specific Conditions

More information

N.H. 6 is 50 km away from the proposed plant boundary; in N direction;

N.H. 6 is 50 km away from the proposed plant boundary; in N direction; 1.1 INTRODUCTION Godawari Power & Ispat Limited (GPIL) has an existing Iron Ore Crushing plant of 12,00,000 MTPA capacity at Gidhali, Village Kusumkasa, Tehsil - Balod, District - Durg (Chhattisgarh) and

More information

Biomass Boiler Emission Abatement Technologies. Simon Wakefield

Biomass Boiler Emission Abatement Technologies. Simon Wakefield Biomass Boiler Emission Abatement Technologies Simon Wakefield simon.wakefield@hwenergy.co.uk About Us Established in 2003 Specialise only in biomass heating Team of 50 staff Design & engineering led company

More information

RAPID ENVIRONMENTAL IMPACT ASSESSMENT

RAPID ENVIRONMENTAL IMPACT ASSESSMENT RAPID ENVIRONMENTAL IMPACT ASSESSMENT FOR THE PROPOSED AUGMENTATION & EXPANSION OF EXISTING THERMAL POWER PLANT BY M/s. ARS Metals Pvt. Ltd. Chennai, Tamil Nadu AT Sithurnatham, Sirupuzhalpettai & Eguvarapalayam

More information

Portbury Dock Renewable Energy Plant. Cumulative Impact Assessment Non-Technical Summary September 2009

Portbury Dock Renewable Energy Plant. Cumulative Impact Assessment Non-Technical Summary September 2009 Portbury Dock Renewable Energy Plant Cumulative Impact Assessment Non-Technical Summary September 2009 INTRODUCTION On 28 th August 2009 E.ON Climate & Renewables UK Developments Limited (EC&R) submitted

More information

PROJECT BRIEF. Noise environment: No Entrant noise generation sources exist in and around project area.

PROJECT BRIEF. Noise environment: No Entrant noise generation sources exist in and around project area. PROJECT BRIEF PROJECT LOCATION: - Pahar Kua Marble Range Mining Project Q L No 235 is located near village Pahar Kua, Tehsil Makrana., District Nagaur Rajasthan. Project is approachable from national highway.

More information

NTPC O&M Conference Performance and Optimization of Water Utilisation Increase of Existing Power Plants. Speaker Name; Tufani Ram 13-14/02/2013

NTPC O&M Conference Performance and Optimization of Water Utilisation Increase of Existing Power Plants. Speaker Name; Tufani Ram 13-14/02/2013 NTPC O&M Conference 2013 Performance and Optimization of Water Utilisation Increase of Existing Power Plants Speaker Name; Tufani Ram 13-14/02/2013 Introduction Water is a vital Resource Irrigation Potable

More information

Revised FORM - I & PRE-FEASIBILITY REPORT

Revised FORM - I & PRE-FEASIBILITY REPORT Hind Energy & Coal Beneficiaton (India) Ltd. [Change in Technology from Dry to Wet Type of Coal Washery in EC issued by MoEF letter vide no. J-11015/364/2009-IA-II(M) dated 21st May 2014] at Hindadih Village,

More information

RECLAMATION OF COAL MINE VOID

RECLAMATION OF COAL MINE VOID RECLAMATION OF COAL MINE VOID Reclamation of Coal Mine Void with Fly Ash Filling of mine voids with fly ash in an environmental sound process is the most viable option of bulk utilisation. This not only

More information

Annex F Scoping Checklist

Annex F Scoping Checklist Scoping Checklist Table F1: Scoping Checklist Table. Questions to be considered in Scoping /? Which Characteristics of the Project 1. Will construction, operation or decommissioning of the Project involve

More information

WEF Residuals and Biosolids Conference 2017

WEF Residuals and Biosolids Conference 2017 Triple Bottom Line Analysis of Energy Recovery from Thermal Oxidation of Wastewater Solids Compared to Coal Anna J. Munson 1*, Webster F. Hoener 1, Robert P. Dominak 2, James E. Welp 1 1 Black & Veatch.

More information

PROJECT FEASIBILITY REPORT

PROJECT FEASIBILITY REPORT PROJECT FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE For PROPOSED CHEMICAL MANUFACTURING UNIT From M/s. MORADIA BROTHERS CHEM PVT LTD LOCATED AT: Block No.: 45, JalBhumi Industrial Estate,

More information

Welcome To Our Exhibition

Welcome To Our Exhibition Welcome To Our Exhibition Welcome to the exhibition of our proposals for a Waste Recycling and Renewable Energy Facility Distributed Renewable Energy Networks Ltd (DRENL) propose to develop a 10MW Waste

More information

Worldwide Pollution Control Association. August 3-4, 2010

Worldwide Pollution Control Association. August 3-4, 2010 Worldwide Pollution Control Association IL Regional Technical Seminar August 3-4, 2010 Visit our website at www.wpca.infowpca An Unbiased Comparison of FGD Technologies: Wet, Spray Dry and CDS WPCA Conference

More information

SINGHAL ENTERPRISES PRIVATE LIMITED

SINGHAL ENTERPRISES PRIVATE LIMITED SINGHAL ENTERPRISES PRIVATE LIMITED (INTEGRATED MINI STEEL & POWER PLANTS) Taraimal Village, Gharghoda Mandal, Raigarh District, Chattisgarh State. 1.0 INTRODUCTION SINGHAL ENTERPRISES PRIVATE LIMITED

More information

Chapter 2.6: FBC Boilers

Chapter 2.6: FBC Boilers Part-I: Objective type questions and answers Chapter 2.6: FBC Boilers 1. In FBC boilers fluidization depends largely on --------- a) Particle size b) Air velocity c) Both (a) and (b) d) Neither (a) nor

More information

Environmental Information Worksheet

Environmental Information Worksheet Environmental Information Worksheet Water System Owner (Attach additional sheets if necessary) Needs and Alternatives Provide a brief narrative that describes: Current drinking water system needs. Project

More information

Prefeasibility Report. 30,000 KLPY Anhydrous (Absolute) Alcohol Manufacturing Plant at Patalganga MIDC

Prefeasibility Report. 30,000 KLPY Anhydrous (Absolute) Alcohol Manufacturing Plant at Patalganga MIDC Prefeasibility Report For 30,000 KLPY Anhydrous (Absolute) Alcohol Manufacturing Plant at Patalganga MIDC of Alkyl Amines Chemicals Limited 401-407 Nirman Vyapar Kendra, Plot No. 10, Sector 17, Vashi,

More information

KADALADI TALUK, RAMANATHAPURAM DISTRICT, TAMIL NADU

KADALADI TALUK, RAMANATHAPURAM DISTRICT, TAMIL NADU KADALADI TALUK, RAMANATHAPURAM DISTRICT, TAMIL NADU MAY, 2016 CONSULTING ENGINEERS 191, ANNA SALAI, CHENNAI - 600006 FEASIBILITY REPORT FOR 5 X 800 MW KADALADI SUPER CRITICAL THERMAL POWER PROJECT AT KADALADI

More information

The unit obtained NOC (CFE) of A.P. Pollution control Board in the year 1988 and started operations.

The unit obtained NOC (CFE) of A.P. Pollution control Board in the year 1988 and started operations. 1. Introduction M/s. Sri Krishna Pharmaceuticals Limited, Unit-III (Formerly Sri Krishna Drugs Limited) was established in the year 1988. It is located at Sy. No. 57, Golkonda kalan, Raikunta (V), shamshabad

More information

A proposed new gas-fired power station on the Wilton International site

A proposed new gas-fired power station on the Wilton International site TEES CCPP PROJECT A proposed new gas-fired power station on the Wilton International site Welcome This event is intended to provide you with information about the proposed Tees Combined Cycle Power Plant

More information

Law enforcement on proactive protection of noise and vibration pollution for

Law enforcement on proactive protection of noise and vibration pollution for Law enforcement on proactive protection of noise and vibration pollution for residential in Thailand Thalearngsak Petchsuwan Director of Air Quality and Noise Management Bureau Pollution Control Department

More information

Steam Electric Power Generating Effluent Guidelines Protecting Surface Water from Power Plant Discharges

Steam Electric Power Generating Effluent Guidelines Protecting Surface Water from Power Plant Discharges Steam Electric Power Generating Effluent Guidelines Protecting Surface Water from Power Plant Discharges EPA Call with the Institute of Clean Air Companies June 22, 2016 Effluent Guidelines Definition

More information

New 790-Megawatt Unit. Council Bluffs Energy Center

New 790-Megawatt Unit. Council Bluffs Energy Center New 790-Megawatt Unit Council Bluffs Energy Center JUST THE FACTS Council Bluffs Energy Center s New 790-Megawatt Unit Background To ensure a long-term positive impact on Iowa's economy and a secure supply

More information

PRESENTATION ON DEVELOPMENT OF NEW POWER PROJECTS APPROACH & WAY FORWARD

PRESENTATION ON DEVELOPMENT OF NEW POWER PROJECTS APPROACH & WAY FORWARD PRESENTATION ON DEVELOPMENT OF NEW POWER PROJECTS APPROACH & WAY FORWARD Presentation By N.K.Srivastava General Manager (Engg. Services & R&M) 20.04.2012 PROJECT DEVELOPMENT AT NTPC PROJECT IS DEVELOPED

More information

Steam Power Station (Thermal Station)

Steam Power Station (Thermal Station) Steam Power Station (Thermal Station) A generating station which converts heat energy into electrical energy through turning water into heated steam is known as a steam power station. A steam power station

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For PRIOR ENVIRONMENTAL CLEARANCE STORAGE CAPACITY ENHANCEMENT OF HPCL, LPG BOTTLING PLANT Capacity: 3 X 500 MT At Plot No.499 Kota-Jhalawar Road (NH-12) Village- Mandana, Tehsil-

More information

Coke Manufacturing. Environmental Guidelines for. Multilateral Investment Guarantee Agency. Industry Description and Practices. Waste Characteristics

Coke Manufacturing. Environmental Guidelines for. Multilateral Investment Guarantee Agency. Industry Description and Practices. Waste Characteristics Multilateral Investment Guarantee Agency Environmental Guidelines for Coke Manufacturing Industry Description and Practices Coke and coke by-products (including coke oven gas) are produced by the pyrolysis

More information

Performance Analysis of Cement manufacturing Industry

Performance Analysis of Cement manufacturing Industry www.ijecs.in International Journal Of Engineering And Computer Science ISSN:2319-7242 Volume 4 Issue 3 March 2015, Page No. 10937-10941 Performance Analysis of Cement manufacturing Industry Neeraj Pandagre

More information

Kazushige KUROSAWA*, Zhibao ZHANG**, and Zhengbing WANG** [Delivered Products & Systems] 1. Introduction. 2. Overview of Nanjing

Kazushige KUROSAWA*, Zhibao ZHANG**, and Zhengbing WANG** [Delivered Products & Systems] 1. Introduction. 2. Overview of Nanjing [Delivered Products & Systems] Report on Delivery and Operational Condition of Grate-type (Stoker-type) Incinerator with Advanced Flue Gas Treatment System in China -Nanjing City, Jiangsu Province- Kazushige

More information

Presentation on Excellence in Energy Management-2017

Presentation on Excellence in Energy Management-2017 Presentation on Excellence in Energy Management-2017 Company Profile Kuantum Papers is in the business of production and marketing of writing & printing paper, while conserving precious resources & protecting

More information

Checklist in respect of selection of Design Consultancy for EER&M of Parli TPS (U-3)

Checklist in respect of selection of Design Consultancy for EER&M of Parli TPS (U-3) Checklist in respect of selection of Design Consultancy for EER&M of Parli TPS (U-3) (a) Names of all consultants who submitted proposals; 1. M/s Tractable Engineers Pvt.Ltd New Delhi 2. M/s Evonik Energy

More information

COAL, OIL SHALE, NATURAL BITUMEN, HEAVY OIL AND PEAT Vol. II -Environmental Impacts of Oil Shale and Pollution Control Technologies - J. Q.

COAL, OIL SHALE, NATURAL BITUMEN, HEAVY OIL AND PEAT Vol. II -Environmental Impacts of Oil Shale and Pollution Control Technologies - J. Q. ENVIRONMENTAL IMPACTS OF OIL SHALE AND POLLUTION CONTROL TECHNOLOGIES J. Q. Wan School of Chemical Engineering, University of Petroleum, Beijing, China Keywords : Environmental impacts, Pollution control,

More information

ZZH/CLAB-KSPCB/04/ Environmental Officer,

ZZH/CLAB-KSPCB/04/ Environmental Officer, ZZH/CLAB-KSPCB/04/ 21273 08-12-2014 Environmental Officer, Regional Office, Karnataka State Pollution Control Board Parisara Bhavan, LIG II, B 217 B-1, Main Road, A-16 th Cross Near Hari Om Trust, Habbuwada

More information

Activity Aspects Impacts/ Nuisances Construction phase - Site preparation. - Generation of excavated soil, debris and construction wastes

Activity Aspects Impacts/ Nuisances Construction phase - Site preparation. - Generation of excavated soil, debris and construction wastes MINISTRY OF ENVIRONMENT AND NDU ENVIRONMENTAL GUIDELINE No. 31 Asphalt Plant Set Up Temporarily For The Purposes Of A Project By A Public Department 1.0 Purpose of guideline This environmental guideline

More information

Carrington Power Station

Carrington Power Station Carrington Power Station INTRODUCTION 01 Welcome to Carrington Power Station Carrington Power Station is a 884.2MW plant that generates enough electricity to power more than one million homes and businesses.

More information

Gold Standard Passport CONTENTS

Gold Standard Passport CONTENTS Gold Standard Passport CONTENTS A. Project title B. Project description C. Proof of project eligibility D. Unique Project Identification E. Outcome stakeholder consultation process F. Outcome sustainability

More information

Lake County Success. support through synergistic local partnerships that not only mitigate, but also produce

Lake County Success. support through synergistic local partnerships that not only mitigate, but also produce Lake County Success Generating Environmental Gains With Geothermal Power By Mark Dellinger, Administrator, Lake County (CA) Sanitation District, and Eliot Allen, Principal, Criterion/Planners Engineers

More information

Appendix VIII: Determination of chimney heights

Appendix VIII: Determination of chimney heights Appendix VIII: Determination of chimney heights 181 Regional Air Quality Plan for Taranaki 182 Regional Air Quality Plan for Taranaki Appendix VIII: Determination of stack heights and boiler operation

More information

FACILITY PROFILE. New Brunswick Power Corporation for the Belledune Thermal Generating Station

FACILITY PROFILE. New Brunswick Power Corporation for the Belledune Thermal Generating Station FACILITY PROFILE New Brunswick Power Corporation for the Belledune Thermal Generating Station Prepared by: Industrial Processes Section, Impact Management Branch Department of Environment and Local Government

More information

WHITE PLUME REMOVAL USING FUEL ADDITIVES IN THERMAL POWER PLANTS

WHITE PLUME REMOVAL USING FUEL ADDITIVES IN THERMAL POWER PLANTS WHITE PLUME REMOVAL USING FUEL ADDITIVES IN THERMAL POWER PLANTS Byeong-Kyu Lee 1), Seung-Won Cho 2) and Sang-Ki Chun 3) 1) Department of Civil and Environmental Engineering, University of Ulsan, Ulsan

More information

CMPDI. 4.6 Mine Closure Plan

CMPDI. 4.6 Mine Closure Plan 4.6 Mine Closure Plan Post-mining Land Use Planning The mine closure planning with regard to for Lekhapani OCP will broadly involve the following aspects: 1. Technical Aspects 2 Environmental Aspects 2.

More information

MIT Carbon Sequestration Forum VII Pathways to Lower Capture Costs

MIT Carbon Sequestration Forum VII Pathways to Lower Capture Costs MIT Carbon Sequestration Forum VII Pathways to Lower Capture Costs 1 October 1 November 2006 Royal Sonesta Hotel, Cambridge, MA Oxyfuel Pathways Rodney Allam Consultant Air Products PLC, UK Oxyfuel Technology

More information

Sr.No Condition Status A. SPECIFIC CONDITIONS:

Sr.No Condition Status A. SPECIFIC CONDITIONS: J.K. CEMENT WORKS, MANGROL (RAJ.) Compliance report of Mangrol Lime stone mine (For the period from April 2011 to September 2011) Sub:- Conditions of Environment Clearance from MOEF, New Delhi Letter No.

More information

APPENDIX VIII. Form 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE

APPENDIX VIII. Form 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE APPENDIX VIII Form 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE (I) Basic Information S.No. Particulates Details 1. Name of the Mining Lease site

More information

ENGINEERED SOLUTIONS ENERGY ENVIRONMENTAL

ENGINEERED SOLUTIONS ENERGY ENVIRONMENTAL ENGINEERED SOLUTIONS ENERGY ENVIRONMENTAL As a technology innovator, Babcock & Wilcox (B&W) provides a comprehensive package of engineered solutions for a wide range of applications. Established in 1867,

More information

POST COMBUSTION CO 2 CAPTURE SCALE UP STUDY

POST COMBUSTION CO 2 CAPTURE SCALE UP STUDY 19 September 2013 POST COMBUSTION CO 2 CAPTURE SCALE UP STUDY TOM GUENTHER PROJECT MANAGER POWER GENERATION SERVICES PURPOSE OF STUDY Retained by IEA Environmental Projects Ltd. In order for CCS to impact

More information

FORM - I-A CHECK LIST OF ENVIRONMENTAL IMPACTS

FORM - I-A CHECK LIST OF ENVIRONMENTAL IMPACTS FORM - I-A CHECK LIST OF ENVIRONMENTAL IMPACTS 1. LAND ENVIRONMENT QUERY 1.1 Will the existing land use get significantly altered from the project that is not consistent with the surroundings? Attach Maps

More information

Environmental Management System Integrated Pollution Control. Origination Date 1 st February Area: The Group

Environmental Management System Integrated Pollution Control. Origination Date 1 st February Area: The Group Environmental Management System Integrated Pollution Control Document No. 5.2.1 Version no. 1 Origination Date 1 st February 2017 Area: The Group Approval: Group Services & Facilities Last Revision Date

More information

TABLE OF CONTENTS. Title page Table of contents List of tables List of figures Non- technical summary

TABLE OF CONTENTS. Title page Table of contents List of tables List of figures Non- technical summary TABLE OF CONTENTS Title page Table of contents List of tables List of figures Non- technical summary Page i ii vii viii ix CHAPTER 1: INTRODUCTION 1 1.1 Project Background 1 1.2 Aims and Objectives 3 1.3

More information

COAL WATER SLURRY FUEL Alternate Fuel for Thailand

COAL WATER SLURRY FUEL Alternate Fuel for Thailand COAL WATER SLURRY FUEL Alternate Fuel for Thailand Power-Gen Asia 2014 Royal Daniel Managing Director RDaniel@roe.com Contents Introduction of POWER Burns and Roe Coal Water Slurry (WS) Fuel in General

More information

Downsizing a Claus Sulfur Recovery Unit

Downsizing a Claus Sulfur Recovery Unit INFRASTRUCTURE MINING & METALS NUCLEAR, SECURITY & ENVIRONMENTAL Downsizing a Claus Sulfur Recovery Unit OIL, GAS & CHEMICALS By Charles L. Kimtantas and Martin A. Taylor ckimtant@bechtel.com & mataylo1@bechtel.com

More information

Compliance of Environmental Clearance SEIAA/GUJ/EC/8(a)/251/2012 Dated (Period April 2016 to September 2016)

Compliance of Environmental Clearance SEIAA/GUJ/EC/8(a)/251/2012 Dated (Period April 2016 to September 2016) Compliance of Environmental Clearance SEIAA/GUJ/EC/8(a)/251/2012 Dated 06.09.2012 (Period April 2016 to September 2016) Sr. No. Conditions Compliance status A. Specific Conditions A.1 Water 1. The fresh

More information

Energy Audit of 250 MW Thermal Power Stations PTPS, Panipat

Energy Audit of 250 MW Thermal Power Stations PTPS, Panipat Energy Audit of 250 MW Thermal Power Stations PTPS, Panipat Vikrant Bhardwaj 1, Rohit Garg 2, Mandeep Chahal 3, Baljeet Singh 4 1 Asstt. Professor in Deptt. Of Mechanical Engineering, IIET, (Kinana) Jind

More information